4 minute read

The Features of Controlled Demolition vs. Fire-Induced Failure

Next Article
Endnotes

Endnotes

■ Joelma Building in Sao Paulo, Brazil (height: 25 stories; fire duration: one hour and 40 minutes)

■ Andraus Building in Sao Paolo, Brazil (height: 31 stories; fire duration: unknown)

Advertisement

The NIST survey also noted two major fire test programs conducted at the Building Research Establishment (BRE) Laboratories in Cardington, United Kingdom. The first series of tests, conducted on a representative eight-story composite steel-framed office building, resulted in significant fire damage but did not result in collapse, even with unprotected steel floors. The second series of tests conducted on a seven-story concrete building also did not result in collapse.

Given the high frequency of fires in steel-framed high-rise buildings and the low frequency of fire-induced collapses, the probability when a fire occurs in a steel-framed high-rise building that it will result in a partial collapse is extremely low. The probability that it will result in a total collapse appears to be even lower.

Let us take WTC 7 as an example. According to the official explanation, its collapse was due solely to normal office fires and not from structural damage caused by debris. The probability when WTC 7 caught fire that it would totally collapse as a result of those normal office fires was exceedingly low.

The Features of Controlled Demolition vs. Fire-Induced Failure

Let us now move from examining the occurrence of collapse to the manner of collapse produced by controlled demolition and fire-induced failure, respectively. Table 1 on the following page lists several common features that generally distinguish controlled demolitions and fire-induced failures.

As Table 1 illustrates, the corresponding features of controlled demolition and fire-induced failure are virtually the opposite of each other. Not every controlled demolition exhibits all of the features of controlled demolition listed in Table 1, nor does every fire-induced failure exhibit all of the features of fire-induced failure listed in Table 1. However, there is very little crossover: When a building’s cause of collapse is controlled demolition, the building exhibits virtually none of the features of fire-induced failure. Similarly, when a building suffers a fire-induced failure, it exhibits virtually none of the key features of controlled demolition (with the exception

Fire damage in WTC 5 (2002 NIST survey of fires that resulted in total or partial collapse).

Partial connection and floor failures in WTC 5 (2002 NIST survey of fires that resulted in total or partial collapse).

CONTROLLED DEMOLITION

The collapse is total, leaving virtually no parts of the building standing.

The onset of collapse is always sudden. FIRE-INDUCED FAILURE

The collapse is usually partial (always partial in the case of steel-framed buildings), leaving much of the building standing.

The onset of collapse is gradual, with visible building deformations appearing prior to the actual collapse.

The collapse lasts a matter of seconds. The collapse takes place over many minutes or hours.

The collapse typically starts at the base of the building, though it can be engineered as top-down also.

The building descends symmetrically through what was the path of greatest resistance, though asymmetrical collapses are sometimes engineered on purpose.

The building typically descends to the ground at near free-fall acceleration. The collapse occurs randomly anywhere in the building.

Collapse is always asymmetrical.

The descent of falling portions of the building is slowed or stopped by the lower sections of the building.

“Demolition squibs” (isolated explosive ejections) are visible outside the main zone of destruction. Explosions only occur at the location of fires, if at all.

Concrete and other materials are sometimes pulverized, resulting in fine dust clouds.

The building’s steel structure is totally or mostly dismembered. Concrete and other materials are not pulverized. Most of the building’s remaining structure is left intact or in large sections.

The building’s steel structure is left mostly intact, even if heavily damaged.

of the four smaller non-steel-framed buildings that NIST’s 2002/2008 survey identified as having suffered total collapse from fire).

If we look closely at the five buildings in NIST’s survey that were over 20 stories or steel-framed or both, and that suffered partial fire-induced collapse, we find that none of them exhibited the features of controlled demolition in Table 1 above.

■ One New York Plaza experienced local connection failures resulting in filler beams dropping onto their supporting girders on two floors.

■ Alexis Nihon Plaza experienced a partial collapse of its 11th floor, which was arrested by the floor below it.

■ WTC 5 experienced partial collapses of four floors and two bays. ■ The Jackson Street Apartments experienced the partial collapse of a floor/ceiling assembly.

■ CESP 2 experienced a substantial partial collapse of its central core. The degree of deformation prior to collapse is unknown.

Other than possibly experiencing little deformation prior to collapse, CESP 2 exhibited no other feature of controlled demolition.

In comparison, as we will discuss in the chapters ahead, the destruction of WTC 7 exhibited all of the features of controlled demolition listed in Table 1, while WTC 1 and WTC 2 exhibited eight out of the nine features listed in the table (the collapse WTC 1 and WTC 2 did not start at their bases).

This article is from: