
1 minute read
SKINNER SPORTS COMPLEX
TARGET COMPLETION various dates 2023
BUDGET $1.0 million
Advertisement
PROJECT MANAGER Bryan Lyness/James Fish
FUNDING SOURCE MPFDC/GF Bonds
DESIGN FIRM MPARD Staff CONTRACTOR Various
SUMMARY Project will include fencing improvements and realignment, entryway updates, drop off and pickup improvements, a new entry plaza with new surfacing, an expanded restroom facility and more storage for baseball concessions.
CURRENT UPDATE Staff anticipates this to be a project that potentially runs into 2024 depending on budget allocations The improvements are being planned to be completed during MYBA's off season as much as possible to provide as little disruption to their seasons as possible. Fencing and painting contractors were scheduled to begin on February 1, but winter weather delayed the work until the week of February 13 for the painting contractor The painting contractor is scheduled to have the work completed by the middle of April pending weather.
The fencing contractor has been delayed until summer due to MYBA scheduling tournaments and the weather Staff has contracted with TRC Architects to design the restroom expansion, interior remodeling and improvements for shade structures with initial design concepts received and in review. Staff has started the design work internally