Design Project Management
SDM | 2014
Brief of the project
•
To install an artifact/installation in the SDM studio explaining what SDM is…
•
Duration of the Project is 3 DAYS.. Final Presentation on 19-12-2014 at 12:00 pm
•
No. Of People – 5 Aditya, Arvind, Daniya, Manu, Poorva
Objective
•
To Understand and deliver the brief given in the particular time.
•
Carefully Document entire Project Management.
•
Make Optimum use of resources available.
Duration of the Project
INVESTIGATE
IDEATE
BRAINSTORMING ON PLANNING OF THE PROJECT Understanding Brief | Analyzing Resources | Secondary Research
IDEATION & CONCEPT GENERATION Brainstorming | Understanding Stakeholders | Distribution of Task
IMPLEMENT
EXECUTE
ANALYSING & IMPLEMENTATION Resources Available | Limitations and Threats | Mock-Ups and Evaluation
EXECUTION Collaborative Effort | Feedback | Compilation
Deadline 16th Dec 2014
17th Dec 2014
17th Dec 2014
18th Dec 2014
Time is Money
Milestones 17th Dec 2014 IDEATION & CONCEPT GENERATION Brainstorming | Understanding Stakeholders | Distribution of Task 1st Team Meeting
• • • • •
HCP Field Visit
Day 1. Evening
Day 3. Evening IMPLEMENTATION
16th Dec 2014 BRAINSTORMING ON PLANNING OF THE PROJECT Understanding Brief | Analyzing Resources | Secondary Research Planning the entire project. Interpreting the Brief. Brainstorming the Concept. Secondary research through key words. Analyzing the resources. Conceptualizing one idea.
19th Dec 2014 Final touchups and Display
Day 3. Morning
Day 2. Evening TEAM DISCUSSION/ ASSIGNING THE TASK
• • • • • •
Collaborative Effort | Feedback | Compilation • Execution • Budgeting • Feedback • Compilation
Day2. Morning Day 1. Morning
Implementation
Concept Generation. ( PLAN A / PLAN B ) Ideation. Site Finalizing. Assigning the Task. Material Procurement.
First Client Meeting CLASS DISCUSSION
16th Dec 2014
18th Dec 2014
Day 3. Night EXECUTION
18th Dec 2014 ANALYSING & IMPLEMENTATION Resources Available | Limitations and Threats | Mock-Ups and Evaluation • Learning how Proper Project Management is documented. • Making the wireframe. • Creating the guidelines.
Tasks Tasks Site Analysis
Aditya
Arvind
Daniya
Manu
Poorva
Time Duration 1 hr
No delay
Permission
Half day
No delay
Photo Documentation
3 days
No delay
Finalizing the concept on paper
2 days
12 hrs delay
Half day
No delay
Material Sourcing
3 hrs
No delay
Making Wireframe/Prototype
2 hrs
No delay
Execution
12 hrs
2 hrs delay
Documentation
3 days No delay
Team Planning and assigning tasks & Discussion on Material
WHERE IS SDM ?
WHAT IS SDM ?
IDEA
SDM Multidimensional
u
x pe r c e p t i o n a l e r i e ni t e d we s t i a l
t a n d i v i d e d w e f a l l
Anamorphic Installation
ACTUAL
PROPOSED
E
XECUTION
FROM 4PM TO 4AM
It took 5 hrs to Finish ‘S’ Task Assigned Aditya Poorva Manu
Putting the Tape to make guidelines
Daniya : View finder
After 1 hr Break It took 3 hrs to Finish ‘D’ Task Assigned Putting the Tape to Daniya make Manu guidelines Aditya : Material Sourcing ( for Plan B.. Replacement Uday Vir Singh )
Poorva : View finder
After 1 hr Break It took 1 hrs to Finish ‘M’ Task Assigned Aditya Uday Manu
Putting the Tape to make guidelines
Poorva : View finder Daniya : Compilation.
T
HIS
IS HOW ITS ACTUALLY DONE !
SDMERS AT WORK
SDMERS AT WORK
SDMERS AT WORK
SDMERS AT WORK (special credit to Uday Vir Singh )
THAT’S ALL FOLKS !!!!
THANK YOU