Turitea wind farm Community Liaison Group
1 August 2019
AGENDA 1. Introductions; health and safety 2. Project update
3. Follow ups to previous meeting
2 WHAT WE’LL DISCUSS TONIGHT
PROJECT UPDATE > Transmission line design finalised, with a reduction in the number of structures ▪ Reduces the number of access tracks ▪ Reduces traffic volumes
▪ Reduces materials required ▪ Reduces vegetation clearing requirements > Wind farm – successful Safety in Design and Preliminary Design Review completed > Mercury’s Palmerston North office is in operation > Ongoing engagement with Rangitaane o Manawatu and Rangitaane o Tamaki Nui a Rua
3 WHAT’S HAPPENING IN THE NEXT EIGHT WEEKS
HIGH LEVEL SCHEDULING Wind Farm > Site village being established adjacent to South Range Road > Formation of the new South Range Rd entrance commencing
> Site mobilisation
Transmission Line > Transmission line set out > Geotechnical investigations > Upgrade of Greens Road
Linton Substation > Fabrication of Electrical fittings > Issue of substation tender package
4 WHAT’S HAPPENING IN THE NEXT EIGHT WEEKS
CONSTRUCTION NOISE MANAGEMENT PLANS Construction Noise Limits
5
Modelled Worst Case Construction Noise Clearance and Vegetation Removal
6
CLICK TO ADD FOOTER
17 and 18 are closest helicoptered structures to dwellings
7
CLICK TO ADD FOOTER
Poles 17 and 18 modelled 70dBA contour (helicopter)
8
CLICK TO ADD FOOTER
Erosion and Sediment Control Plans
9
CLICK TO ADD FOOTER
CONTRACTORS’ UPDATES – WIND FARM AND ROADING Completed Activities > Geotechnical investigation at most Wind Turbine sites completed > Facilitated Safety in Design workshop completed > Preliminary Design Review completed
Planned Activities > Site offices establishment > Formation of the new South Range Rd entrance > Site mobilisation > Establish site environmental controls
10 WIND FARM
PROJECT UPDATE • A new site entry will be constructed on the straight heading east prior to the right hand turn at the top of Pahiatua Track highway. • This entry is designed to allow construction vehicles and personnel safe access by a designated turning bay into the Construction Site and ensure Community and Public have safe travel through. • Traffic Management will be in place during construction to ensure safety for Construction Personnel, Community and Public while this activity is being undertaken. • A secondary Construction access point will be constructed on the east side of Pahiatua track road at the bottom of the range. This access point is primarily for the delivery of blades to the project. 55metres in length and transport/construction vehicles travelling in a East to West direction. (Napier to Palmerston North) This will be gated/locked construction access road to prevent unauthorised vehicles entering and exiting. 11 VESTAS UPDATE
12
13
CLICK TO ADD FOOTER
PROJECT UPDATE South Range Road Upgrade: • The South Range Road is defined as the spine of the project as all access to wind turbines are predominantly from this road.
• The road will be straightened, widened with new culverts and base materials to allow for transport of major equipment to project from new access road/s to approximately 1km past the gate into the Turitea reserve. • The road is an integral part also for operations and maintenance of the wind farm and will also be a safer public road access road for community at completion of construction.
14 SOUTH RANGE ROAD
15
16
Wind Farm Preliminary Design Layout
17
CLICK TO ADD FOOTER
CONTRACTORS UPDATE - TRANSMISSION LINE Completed Activities > Transmission line design and route completed > Pole and Hardware designs completed > Access track plans completed
Planned Activities > Transmission line set out – Survey pegs placed > Geotechnical investigations > Foundation design
> Formation of access tracks & laydown areas > Upgrade of Greens Road
18 TRANSMISSION LINE
WORKS ON GREENS ROAD Greens Road is used to access poles 9 onward, the Browns Flat staging area and most of the Towers. Consent conditions requires specified upgrades to this road. The upgrades require engineering design, a report to council, then the upgrade works can occur. Local companies GHD and Stringfellows will be completing the design and build work and will be engaged to ensure the road is kept swept and any ongoing maintenance is identified. – Road condition survey - complete – Engineering design - underway – Traffic management plan – underway – inputs please – Boundary survey - August – Kahuterawa Rd (line of sight improvements) - August/September – Tree removal (Greens Rd) - September – Earthworks - September – Sealing and culverts - September weather permitting
19
Construction Process > Preparation Works
20
CLICK TO ADD FOOTER
Construction Process > Foundations
21
CLICK TO ADD FOOTER
Construction Process > Getting everything straight and true
22
TRANSMISSION LINE
Construction Process > Flying in concrete
23
TRANSMISSION LINE
Construction Process > Poles installed in only a few lifts
24
CLICK TO ADD FOOTER
HELICOPTER WORK We will be using helicopter during the project for: lifting heavy equipment concrete pole erection (9,10,17,18) tower erection (26-30 and 33-35) stringing
Potentially using a Blackhawk helicopter for some work
25
CONTRACTORS UPDATE – LINTON SUBSTATION Completed Activities > Site geotechnical investigations > Protection systems design > Control room layout of additional equipment > Multiparty facilitated safety workshop
Planned Activities > Fabrication of Electrical fittings > Issue of substation tender package
> Awarding civil works > Begin Mobilising to site
26 LINTON SUBSTATION
PUBLIC FEEDBACK ON TRAFFIC MANAGEMENT PLAN > Drivers should be aware that Turitea road is part of the Te Araroa Trail and is heavily used by walkers, runners and cyclists. > The first 2kms includes a short steep narrow set of sharp bends where there is no footpath, pavement, hard shoulder, soft shoulder or space of any kind, plus a one-way bridge.
> Request to include some building work to provide new cycle and walking path so drivers are not sharing that bit of narrow road with those on foot or bike. > A couple of mirrors on the tight bends on Turitea Road would provide improved visibility.
Feedback passed on to PNCC's Traffic Management Consultant for consideration as part of Plan review and certification.
27
CLICK TO ADD FOOTER
FOLLOW UPS TO PREVIOUS MEETING 1. Summary of previous meeting sent out by email (with links to website) 2. Feedback received via website/email and actioned
3. Dates for next meetings
28 ACTIONS TAKEN AFTER LAST MEETING
FOR FURTHER INFORMATION > TURITEAWINDFARM@MERCURY.CO.NZ