Mexico Energy Review 2019

Page 269

INSIGHT |

RECONCILING SOCIAL AND ENVIRONMENTAL PROTECTION WITH BUSINESS DEVELOPMENT LUIS VERA Former Partner at V&A

A first reading of the energy industry’s regulatory framework

includes two additional development phases that will add

suggests that environmental impact assessments should be

another 150MW of installed capacity. “Each development

prioritized, followed by indigenous consultations and finally,

stage required a different assessment, including social and

the social impact assessment. But Luis Vera, Former Partner

environmental impact assessments,” says Vera. Based on the

at socio-environmental law firm V&A, says this is not always

firm’s extensive work dealing with social and environmental

the case. “The logic behind this established timeline is at

issues, Vera believes it is essential for developers to be

odds with the actual fieldwork,” he says. “Environmental

aware of the importance of these steps. “Investors must

impact assessments have looser time frames and we use

become increasingly aware that nontechnical issues have a

this time to simultaneously cover the social aspects that

prominent social component,” he says. “Anthropologists and

overlap with environmental issues.” This means the firm

sociologists must be involved to build lasting relationships

can get a sneak peek at social insights such as indigenous

with local communities.”

presence or sensitive environmental areas prior to carrying out the consultation process.

When presenting its social and environmental impact assessments, V&A adds a chapter that takes into account

Compliance with the social and environmental requirements

the project location’s needs and regional development

when developing a large-scale energy project can prove

goals. “By doing so, our clients obtain increased certainty

challenging, especially considering the regulatory

on where to focus their investment, not only to grow

framework remains largely in the draft stage. Duplication

the company’s own business but also to contribute to

of responsibilities within government agencies does

the long-term regional development of the project’s

little to solve the problem, says Vera. “SEMARNAT and

location,” Vera says. The firm is also actively involved in

ASEA developed two different standards of the same

the public side of the social and environmental equation.

regulatory framework due to their respective mandates,”

“One of our partners is developing an algorithm together

he says. “Meanwhile, the Ministry of Energy’s social impact

with the Ministry of Energy so it can be more selective

guidelines are still on the drafting table, meaning social

in the projects it reviews, shifting from anecdotal to

impact assessments lack an established reference.”

standardized procedures.”

In 2017, the firm obtained 43 authorized social impact

In the near term, Vera worries litigation services will be

assessments, with 24 more in the pipeline for 2018. Using

more in demand due to the way the first procurements

this experience, V&A established a series of precedents

and allotments were carried out after the reform passed,

related to energy law interpretation and how environmental

both in the oil and gas licensing rounds and the long-

legislation applies to both regulated and nonregulated

term electricity auctions. “ASEA’s and SEMARNAT’s early

users. “V&A showcased consistency in all its assessments

heavy workload and understaffed agencies mean some

and legal interpretation to help decision-makers streamline

shortcuts were taken, such as hastily granted authorizations

their authorization and permitting processes,” he says. “Our

and procedures, casting doubt over the legality of a few

work also generates certainty in evaluation by financial

projects,” Vera explains.

entities.” From its outset, V&A established itself as a strategy firm Oak Creek’s Tres Mesas wind farm in Tamaulipas is among

rather than a litigation firm, given effective strategies

the large-scale energy projects V&A was involved in. It

eliminate the potential for later litigation, but that is

started as a pilot project that soon extended to a first and

changing. “We prioritized creativity over legal defense. But

second development phase totaling 148MW of installed

considering the coming scenario, we are also developing a

capacity, operating since May 2017. The project now

specialized litigation department,” says Vera.

265


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.