Utility February 2022

Page 90

SWIT CHGE AR

ENERGYCONNECT: MEETING THE CHALLENGES OF A REMOTE ENVIRONMENT

Project EnergyConnect, once approved and constructed, will directly link the energy networks of South Australia and New South Wales for the first time.

T

he largest electricity interconnector project to date in Australia, EnergyConnect is a cornerstone of the Australian Energy Market Operator’s (AEMO) 2020 Integrated System Plan (ISP). The ISP is a roadmap to ensure Australia has a resilient and secure grid to accommodate future renewable energy, and promote a decarbonised future. The project has passed a cost-benefit analysis, overseen by the Australian Energy Regulator (AER) and is progressing through the final phase of a rigorous approval process. The challenges of delivering EnergyConnect are being assessed, including the transmission route, the construction of transmission lines and substation requirements. EnergyConnect will enable the renewable wind and solar energy generated in South Australia to flow into the New South Wales grid, helping stabilise prices in the National Energy Market (NEM).

ENERGYCONNECT TIMELINE Phase

Status

Timing

Preliminary investigations and project scoping

Completed

Regulatory Approval received in July 2021

Community and landowner consultation

In progress

From 2018

Project approvals

In progress

From early 2020 – mid 2022

Detailed Design and Site Early Works

In progress

Early 2021 – mid 2022

Construction

Proposed

From 2022 (NSW Western section)

Project commissioning

Proposed

By 2024

THE CHALLENGES OF DISTANCE Transgrid will build the New South Wales section of EnergyConnect, ElectraNet will deliver the South Australian component and Secure Energy has been appointed as the primary contractor.

88

UTILITY • FEBRUARY 2022

Transgrid will construct a 674km transmission line from the South Australian – New South Wales border to Wagga Wagga, linking two existing substations and one new substation. This isolation, combined with the project’s required 50-year life span, requires that infrastructure choices assure iron-clad network reliability and security. Yousseph Ters, Transgrid Project Integration Manager, said, “The stability of the network is vital, with outages requiring quick remediation, which will be a challenge given the remoteness of the transmission and substation infrastructure.”

INNOVATION VS TRIED AND TESTED TECHNOLOGY Transgrid’s delivery of EnergyConnect includes an estimated 1,900 new transmission towers, linking the three substations to South Australia. “We need to demonstrate the value that EnergyConnect will provide, balancing the concerns of landholders and affected communities with environmental, heritage and economic constraints,” Mr Ters said. “Our Network Planning team works closely with team EnergyConnect to choose technical solutions that blend innovative transmission tower technology, with tried and tested substation installations familiar to transmission infrastructure across Australia.” TRANSMISSION TOWERS TO SUIT THE TERRAIN EnergyConnect is using innovative guyed tower technology, consisting of a single mast with guyed wires that spread out diagonally, providing the support required for the tower. Guyed towers are used extensively in the US, South America, Africa and Europe in locations where the topography is flat. Australia’s grid is often in hilly and rocky areas, so this will be the first use of double circuit guyed towers in

WWW.UTILITYMAGAZINE.COM.AU


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Customers at the centre of the energy sector

5min
pages 98-101

Using ACB retrofit solutions to ensure stable power supply

2min
pages 94-95

Temporary solution for a wastewater plant

2min
pages 86-87

The importance of sewer rehabilitation

7min
pages 82-85

EnergyConnect: meeting the challenges of a remote environment

6min
pages 90-91

Weld-free repair offerings making waves in the industry

2min
pages 88-89

and cable works

2min
pages 92-93

Managing utilities with aerial imagery

2min
pages 80-81

Satellites providing unparalleled accuracy in dam surveillance

4min
pages 76-77

Cadastre modernisation energises GIS

2min
pages 78-79

Implementing Victoria’s embedded networks ban

6min
pages 66-67

Maximising Distributed Energy Resources using State Estimation

5min
pages 68-69

Journey to net zero well underway in regional WA

4min
pages 70-71

Mapping the future of distributed energy resources

7min
pages 72-75

Managing pressure in water networks using polymer valves

2min
pages 64-65

The role of desalination in Australia’s changing climate

6min
pages 62-63

Fully automated iron measurements for cost-effective water analysis

2min
pages 60-61

Highlights from Sydney Water’s Innovation Festival

6min
pages 58-59

Charting a path for utility digital transformation

1min
pages 40-41

How amendments to the Security of Critical Infrastructure Act will impact your utility

5min
pages 44-45

Identifying critical differences between Smart Water Metering and Smart Water

2min
pages 42-43

Flexible energy resources key to a low carbon energy future

5min
pages 46-49

The world’s only CAT III 1500 V current clamp

2min
pages 50-51

Big data supporting the new energy paradigm

5min
pages 34-35

Creating the future of water for councils and communities

2min
pages 56-57

Combating network leaks with digital technology

4min
pages 36-37
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.