FEASIBILITY STUDY main street dam feasibility study
2 0 1 2
MAIN STREET DAM REMOVAL
ACKNOWLEDGEMENTS COLUMBUS DOWNTOWN DEVELOPMENT CORPORATION Guy Worley, CEO Amy Taylor, COO Milt Lewis, Director of Construction Services
CITY OF COLUMBUS Dax Blake, PE, Administrator, Division of Sewerage and Drainage Mike GrifďŹ th, PE, Division of Sewerage and Drainage Erin Miller, Environmental Steward
STANTEC Bryon Ringley, PE, Principal Scott Peyton, PE, Senior Associate Travis White, PE, SI, Senior Project Engineer Brad Rodgers, PE, CHMM, Senior Associate Cody Fleece, Senior Ecologist Rich Williams, PhD, PE, Senior Geotechnical Engineer Jenny Rytel, PG, Geologist Mary Murphy, Administrative Assistant
MSI DESIGN Keith Myers, FASLA, Principal Darren Meyer, RLA, Associate Principal Andrew Overbeck, AICP, Urban and Regional Planner Aron Fraizer, ASLA, Associate Charles Benick, Project Designer
RESOURCE INTERNATIONAL Michelle Eckels, CPG, Director of Environmental Services Mark Ward, PS, Survey Manager
ASC GROUP Shaune Skinner, President Al Tonetti, Cultural Resource Specialist
COLDWATER CONSULTING Kristen Risch, Senior Restoration Specialist
02
SHELLEY, METZ, BAUMANN, HAWK Jon Beier, PE, LEED AP BD+C
02
acknowledgements and table of contents
04
executive summary
06
planning context
08
recent investment
10
river evolution
12
feasibility study
14
natural channel design
16
concept plan
26
implementation
main street dam removal feasibility study
table of contents & acknowledgments
TABLE OF CONTENTS
03
EXECUTIVE SUMMARY RIVERFRONT RENAISSANCE
riverfront and connect the neighborhoods and districts along the
Columbus is in the midst of a riverfront renaissance. Beginning
river corridor.
with North Bank Park in 2004, and continuing with the opening of the Scioto Mile and the Scioto Audubon Metro Park, Downtown’s
STRONGER CONNECTIONS
riverfront has been transformed. The 2010 Downtown Columbus
In addition to strengthening the connection between Downtown
Strategic Plan built on this momentum by proposing the removal
and the Scioto Peninsula, the removal of the Main Street
of the Main Street Dam and the creation of a greenway along the
Dam will better link The Ohio State University to Downtown
Scioto River as the beginning of a new green corridor through the
Columbus. With the removal of the 5th Avenue Dam at OSU on
heart of the city. The Scioto Greenways Feasibility Study , funded
the Olentangy River well underway, there will be a free-flowing,
by the Columbus Downtown Development Corporation and the
navigable river from the campus area through Downtown
City of Columbus, explores the environmental, engineering, and
Columbus. These two projects set the stage for the exploration
land planning challenges associated with removal of the dam. The
of removing or modifying other dams upstream on the Olentangy
study provides a technical solution that meets these challenges
River, with the complete realization creating a naturalized river
and shows how a naturalized river corridor and parkland will enable
corridor from Highbanks Metro Park to the Scioto Audubon
Downtown to truly embrace the Scioto River.
Metro Park through OSU and Downtown. This 16.5-mile green link would be unmatched in any major U.S. city today.
A NEW URBAN RIVERFRONT The downtown portion of the Scioto River is currently an overly-
UNLIMITED TRANSFORMATIVE POTENTIAL
wide, slow-moving pool of sediment-laden water, due to the Main
Improving the health of the river increases its value to the
Street Dam. Removing the dam would allow the water course to be
community, contributing to a more prosperous, competitive
narrowed and green space to be added along its edges. Building
metropolis for the 21st century. The removal of the Main Street
on the public and private investment in The Scioto Mile, the urban
Dam is an important first step in carrying out the vision of
riverfront would be expanded with 33 acres of new green space
a restored river corridor through Downtown Columbus and
that connects Downtown to the river and the Scioto Peninsula. The
beyond.
Master Plan Concept includes plaza and event spaces that enhance the Scioto Mile. Phase one improvements focus on new greenways on both sides of the Scioto River that would tie into the existing Downtown and regional bikeway system and allow for new access at the river level. The greenway transitions to a naturalized river edge
PROJECT GOALS
condition designed to restore river habitat and withstand flood events.
A RESTORED RIVER
•
Build on recent park investments
In addition to enhancing the public realm, removing the Main Street
•
Reduce river width
Dam allows for the implementation of a natural channel design that
•
Clean and restore river habitat
restores river habitat. Today, the downtown portion of the Scioto
•
Enhance greenway connections
River is designated as a Modified Warm Water Habitat by the Ohio
•
Improve access to river
EPA due to the lower expectations for aquatic habitat and biological
•
Create economic value and spur redevelopment
success in this area. The Scioto River can attain a higher aquatic
•
Improve linkages between downtown and Scioto Peninsula
•
Work within existing 100 year floodplain
habitat use if the physical impairments are removed and the natural
04
form and function of the river is restored. A healthier river, along with new pathways and recreational access, will bring people to the
BEFORE
AFTER - MASTER PLAN CONCEPT
executive summary
main street dam removal feasibility study
“Building on the Scioto Mile, this new urban riverfront downtown could be expanded with 33 acres of new green space.”
05
RIVER EVOLUTION EARLY HISTORY Throughout Columbus’ history, the Scioto River has been
REMAINS OF THE FEEDER CANAL
evolving. In place by the mid-1800s, the original timber dam was built to provide water for the feeder canal that connected the Scioto River to the Ohio and Erie Canal. Over this period, the river channel has been constantly changing, along with the city. Smaller river channels were filled in, islands were removed and the river course was altered to accommodate bridges, railroads, industry and other development.
RESHAPING THE RIVER The most significant changes to the river corridor occurred
INDUSTRY ALONG THE SCIOTO RIVER
after the flood of 1913. The flood destroyed the original timber dam and the river width narrowed closer to its natural watercourse. The resulting mud-flats that were exposed created an unsightly appearance in Downtown. The Main Street Dam was built in 1921 in order to create a more aesthetically pleasing riverfront, and resulted in a wider river. This river pool was built in concert with other Civic Center riverfront improvements, including City Hall. The Main Street Dam was altered in 1929 to add another foot and half in height to the dam that created the river width of the Scioto River
DAMAGE FROM THE 1913 FLOOD
today.
THE RIVER TODAY Over time, the Main Street Dam has prevented the passage of sediment and limited the navigability of the Scioto River. In the late 1980s, efforts were made to dredge the river to deepen the channel and allow for water craft use, but the river soon deposited more sediment and further efforts were not undertaken. Additionally, by this time the original 1920s improvements had begun to age with the concrete revetments and balustrade along the river edge crumbling into the river. As part of the improvements to North Bank Park and the Scioto Mile, this revetment condition has been removed and the river edge has been naturalized. The balustrade along Civic Center Drive has also been restored and renovated.
06
THE MAIN STREET DAM TODAY
1845
1868 ET HIGH STRE
ET HIGH STRE
REET
REET
Feeder Canal and Sluice
•
1899
Timber Dam
1920
ET
ET
HIGH STRE
HIGH STRE
REET
REET
BROAD ST
•
BROAD ST
Scioto Peninsula Filled In Remaining Islands
1941
• •
Post - 1913 Flood Condition Timber Dam Destroyed
1939
ET
ET
HIGH STRE
HIGH STRE
REET
REET
BROAD ST
•
Wider Main Street Dam built to replace timber dam
BROAD ST
• •
Taller Main Street Dam Current River Width
main street dam removal feasibility study
BROAD ST
BROAD ST
•
river evolution
“Since the founding of Columbus the Scioto River has been evolving and changing.”
07
COMMUNITY CONNECTIONS LINKING DOWNTOWN AND NEIGHBORHOODS From Worthington to Downtown Columbus, seven low head dams
HIGHBANKS METRO PARK
interrupt the natural flow of the Olentangy River. These dams impair aquatic habitat, degrade water quality, limit recreational opportunities, and create a safety hazard. The 2010 Downtown Columbus Strategic Plan advanced a strategic vision for removing these dams to create a 16.5 mile greenway corridor that connects Scioto Audubon Metro Park and Downtown to numerous neighborhoods and High Banks Metro Park to the north. Cleaning the rivers and removing low head dams would restore the natural river course, reintroduce river habitat as a tranquil amenity, and create more green space and recreational opportunities. This
THE OHIO STATE UNIVERSITY
catalytic idea builds on the recent investment and current plans to restore river health. With North Bank Park, the Scioto Mile, and the Scioto Audubon Metro Park, nearly all of the downtown riverfront park system has been remade into a world-class park destination. However, this investment is incomplete until the river health is restored. The City of Columbus has taken the first step toward a healthy river with its efforts to implement a $2.5 billion wet weather management program to reduce the occurrence of combined sewer overflows. The 5th Avenue Dam removal represents the first step in restoring the natural river course and enhancing habitat along this
DOWNTOWN COLUMBUS
corridor. With the removal of the Main Street Dam, the initial link in this river greenway system will be created between The Ohio State University and Downtown Columbus. In time, this model can extend north along the river corridor, connecting neighborhoods to the river and to Downtown Columbus.
COMMUNITY BENEFITS
08
•
Connected – links neighborhoods, communities, and recreational opportunities
•
Healthy – promotes physical activity and bike commuting in a beautiful and engaging environment
•
Smart – provides educational opportunities for the entire community to learn about the importance of protecting our river systems
•
Sustainable – restores the river habitat and increases biodiversity
•
Prosperous – raises property values adjacent to the greenway corridor and encourages reinvestment
SCIOTO AUDUBON METRO PARK
Highbanks Metro Park
planning context
“The Scioto-Olentangy Greenway Corridor would create a 16.5 mile green link through the heart of the city.�
R i ver
entang y O l
o ot S ci
Clintonville
R e iv r Ohio State University 5th Avenue Dam
STUDY AREA Downtown Columbus Main Street Dam Scioto Audubon Metro Park
main street dam removal feasibility study
Worthington
main st. dam
main st. dam removal feasibility study area
09
RECENT AND FUTURE INVESTMENT RECENT IMPROVEMENTS The RiverSouth area and Downtown Columbus riverfront have
NORTH BANK PARK
seen hundreds of millions of dollars of public and private investment over the past decade. In addition to North Bank Park and the Scioto Mile, surrounding street infrastructure has been improved to allow for two-way traffic, and there are two new bridges across the Scioto River. New residential development at the Annex at River South has also come online to complement the existing residential properties Downtown by providing affordable rental options. The renovated Lazarus Building offers 700,000 square feet of office space and prime street-level retail in a LEED Gold certified building.
THE SCIOTO MILE
DEVELOPMENT OPPORTUNITIES The Main Street Dam removal project will capitalize on these investments and be the catalyst for further redevelopment. Across the country, dam removal and river restoration projects have been shown to enhance the economic value of property, businesses and communities. This new 33-acre greenway in the heart of Downtown will draw people to the waterfront and encourage interaction at the river level. Building on the recent completion of two new bridges across the Scioto River that
MAIN STREET BRIDGE
provide better access to COSI and other attractions, this new riverfront greenway will further help the west bank of the river to embrace the riverfront and Downtown, acting as a catalyst for redevelopment of vacant and underutilized property on the Scioto Peninsula and East Franklinton.
ECONOMIC IMPACT SCIOTO AUDUBON METRO PARK
10
•
The 33 acre greenway will increase private development and attract hundreds of thousands of visitors annually
•
Surrounding this revitalized river and greenway is nearly 100 acres of vacant and underutilized land that is primed for redevelopment, especially on the Scioto Peninsula and East Franklinton.
•
The Main Street Dam removal project will support as many as 350 new jobs in the region
NORTHBANK PARK
LAZARUS BUILDING
RICH STREET BRIDGE
COLUMBUS COMMONS
SCIOTO MILE
MAIN STREET BRIDGE
main street dam removal feasibility study
recent investment
“The Main Street Dam Removal project seeks to build on the investment and momentum along the Downtown Columbus riverfront”
SCIOTO AUDUBON METRO PARK
RECENT INVESTMENT POTENTIAL FUTURE REDEVELOPEMNT
11
FEASIBILITY STUDY OBJECTIVES
a permeable gravel aquifer and the Scioto River that
The Main Street Dam Removal Feasibility Study had four
both discharges and receives water from the river.
primary objectives: •
•
•
Sediments: Sediment samples contained some con-
Develop a thorough understanding of the river and the
taminants above residential levels. Ohio EPA indicates
land and structures within and around it.
preliminarily that these contaminants may not need to
Determine the potential environmental and engineering
be removed but could be reused under certain condi-
issues involved in removing the dam, particularly the
tions.
impact on the 100 year floodplain •
•
Develop a concept plan for the river channel that restores
DEVELOPING THE CONCEPT PLAN
the natural river course and improves water quality
With this baseline information determined, a Concept Plan
Expand the concept plan to show how the reclaimed
for the dam removal and addition of parkland was created
public land on either side of the river could be reused as
to demonstrate what could be done with the narrowed river
urban park space
channel in terms of new open space and restored river habitat in Downtown. This plan adds 33 acres of additional green
ADDRESSING THE CHALLENGES
space to Downtown and offers a new pedestrian linkage be-
Throughout this project numerous issues were addressed:
tween Downtown and COSI in addition to enhanced river rec-
•
Historic Preservation: Study outlined changes made to
reation opportunities and extensive new pathways and river
the Scioto River over time and determined that the Main
viewpoints. The proposed dam removal, restoration design,
Street Dam is not in the Civic Center Historic District,
and park improvements were then modeled and compared to
although the project is subject to Section 106 of the
existing conditions along the river. No rises in one-percent an-
National Historic Preservation Act of 1966.
nual chance flood elevations will occur. The Standard Project
Ecology: Determined that the dam is inhibiting the river
Flood will remain contained within the floodwall. Average an-
from reaching its potential use attainment designation
nual river elevations will decrease by approximately seven feet
of Warm Water Habitat, and that dam removal and river
immediately upstream of the former dam location. Likewise,
restoration will improve habitat for native fish and mussel
the structures and bridges within the river corridor were also
species that should reside in the Scioto River.
assessed and changes recommended in order to mitigate
Hydrogeology: Found that there is a relationship between
impacts of the river lowering.
•
•
RESPONSES
CONCERNS 1.
Utility Crossings will be exposed by lower water
1.
Proposed river bed will maintain cover above
2.
Existing lines will be extended to ensure that the
3.
Bridge piers will either be on the banks of the new
existing utility crossings.
levels and impacted by increased scour. 2.
Combined Sewer Overflow odor will increase due
submerged condition remains, containing odor.
to lower water levels. 3.
Piers of existing bridges will be exposed by drop-
river, or will have extended caps on piers to ad-
ping the water level.
dress concerns. 4.
5.
12
Foundations near river for OSIS, floodwall, and
4.
Groundwater in the area feeds the river and is
adjacent buildings could be damaged by the
currently cut-off by the floodwall. The groundwater
lowering of the river.
conditions today will not be altered.
Flood levels could be adversely impacted by removing the dam.
5.
The 100 year floodplain extents are not altered as part of this project, allowing the river and park system to handle flood events.
BEFORE
AFTER
main street dam removal feasibility study
feasibility study
“With the removal of the Main Street Dam the Scioto River will be narrowed by nearly half and Downtown Columbus will gain 33 acres of new riverfront park land.�
13
RIVER CHANNEL NARROWING NATURAL DESIGN MODELING OF THE CONCEPT As part of the Feasibility Study, the impact of the dam removal
FLOODPLAIN WIDTH
and the implementation of a natural channel design for the Scioto EE HIGH STR
River were assessed. Modeling of the proposed conditions resulted in no rises in the 1% annual chance of flood elevations
T
and found that the Standard Project Flood will remain contained within the floodwall. In general, the 100 year floodplain extents are not altered as part of this project. In certain areas, especially in front of COSI, it actually improves slightly (see diagram at right).
BROAD
STREET
IMPACT ON THE RIVER LEVEL While the impact of the dam removal is greatest immediately upstream of the former dam location, resulting in a seven foot decrease in the water surface elevation based on average annual flow conditions, the entire river corridor will see a decrease in channel width. The sections at right illustrate this change in channel width and the added greenway (based on average annual flow conditions).
Existing 100 year floodplain Proposed 100 year floodplain reduction
HABITAT RESTORATION Removing the dam and implementing a natural channel design will result in an increase in ambient dissolved oxygen, a reduction in low flow water temperatures, and an improvement of habitat
CHANNEL WIDTH
diversity and aquatic habitat. The natural channel design will also HIGH STR
provide the necessary substrates and flow regimes needed for the recolonization of fish and mussel species that were once found ON
EET
in this segment of the Scioto River. The dam removal will also
1
TI
C SE
allow these species to migrate upstream, increasing the diversity of those aquatic communities. Due to these improvements, an increase in the Qualitative Habitat Evaluation Index from the Ohio
BROAD
STREET SECTION
2
EPA is expected for this segment of the Scioto River. SE
CT
ENVIRONMENTAL BENEFITS
14
•
Recreates and restores a more natural channel for the Scioto River
•
Has a positive impact on water quality, river health and aquatic habitat
•
Provides for the recolonization of native fish and mussel species
•
Allows for upstream migration, increasing the diversity of these aquatic communities.
IO
N
3
Existing Channel Proposed Channel
VETERANS MEMORIAL
Existing crossing =
495 feet
•
Proposed crossing =
250 feet
•
Width reduction =
245 feet
EXISTING
495’ E
xisting
Crossin
g
SC I RI OTO VE R
•
SC I RI OTO VE R
SECTION 1
natural channel design
FEDERAL COURTHOUSE
PROPOSED
BICENTENNIAL PARK
SECTION 2 •
Existing crossing =
495 feet
•
Proposed crossing =
245 feet
•
Width reduction =
250 feet
SC I RI OTO VE R
HEALTH DEPARTMENT SITE EXISTING
495’ E
Cross
ing
SC I RI OTO VE R
xisting
PROPOSED
245’ 495’ E
Propo
xisting
sed C
rossin
Cross
g
ing
SCIOTO MILE PROMENADE
SECTION 3 Existing crossing =
570 feet
•
Proposed crossing =
270 feet
•
Width reduction =
300 feet
EXISTING
570’ E
xisting
Cross
ing
SC I RI OTO VE R
•
SC I RI OTO VE R
COSI
main street dam removal feasibility study
250’ P ropose d Cros 495’ E sing xisting Crossin g
PROPOSED
270’ P ropose d Cros 570’ E sing xisting Cross ing
15
MASTER PLAN CONCEPT INTRODUCTION
PROJECT PHASING
With the engineering parameters of the Main Street Dam Remov-
To enable the efficient implementation of this project, the pro-
al defined, the project team created a Master Plan Concept for
posed Master Plan Concept improvements have been divided
the narrowed river, restored river edge and adjacent greenway.
into two phases. The Master Plan diagram at right highlights
The implementation of a natural channel design allows for the
major plan components under each phase.
creation of approximately 33 acres of ground that can be used to meet floodplain requirements, restore river habitat and create
Phase One components focus on dam removal, river channel
greenway connections.
formation, river restoration and associated greenway and bike path components. Phase Two components include event and
New pathways on both sides of the Scioto River tie into the
plaza spaces, additional hardscape and landscape features and
existing downtown and regional bikeway system and allow for
fountains, and a pedestrian bridge across the Scioto River con-
interaction and access at the river level. The park pathway and
necting the Scioto Peninsula to the Scioto Mile Promenade. Ren-
plaza areas transition to naturalized river edge condition that is
derings of all Phase One components are shown on subsequent
designed to withstand flood events. The greenway will link into
pages of this report. An Implementation section follows that
the existing bikeway system with bike paths and landscaped
outlines the preliminary estimate of probable cost for Phase One.
park areas. This greenway corridor will connect The Ohio State University to Downtown Columbus and provide recreational opportunities such as cycling, canoeing and kayaking. Taken together, these improvements will create an opportunity for the public to experience and interact with the river in a more natural state.
The Master Plan Concept seeks to build on recent park investment along the downtown riverfront from North Bank Park to
PHASE ONE IMPROVEMENTS
the Scioto Audubon Metro Park. Elements of the Scioto Mile will be enhanced with new plaza and event spaces, especially at the Town Street Prow that will have a two-level overlook. On the west side of the river, an extension of the plaza and lawn in front of COSI will create an expanded event space. Building on
•
Removal of concrete low head dam south of the Main Street Bridge
•
Removal of accumulated sediment behind dam
•
Restoration of a more naturalized and narrower river course and channel topography with the creation of pools, riffles, and glides that improve river flow and habitat.
•
Creation of a stabilized riveredge and naturalized river bank using bioengineering methods – no riprap or concrete walls with the exception of limited, target areas for public access to the river edge.
•
Construction of a greenway system with bike paths, park space, and connections to existing public parks and amenities.
the theme of connections, a proposed pedestrian bridge will directly connect COSI and the Scioto Peninsula to the Scioto Mile Promenade and Downtown Columbus helping to visually and physically link these two nodes of activity.
With these improvements, Downtown will no longer turn its back on the Scioto River. Instead, it will be able to use the river for recreation, admire it for its natural beauty and celebrate it as the “central park” of Downtown Columbus.
16
concept plan
“Downtown Columbus will no longer turn its back on the Scioto River. Instead, people will be able to use it for recreation, admire it for its natural beauty and celebrate it as the ‘central park’ of Downtown Columbus.”
1
2
2
1 7 3 3
8 5
4 6
MASTER PLAN CONCEPT PHASE ONE COMPONENTS
PHASE TWO COMPONENTS
1.
5.
Restored River Channel: Reconfigured river channel
Town Street Prow: Two-level plaza space that preserves
sculpted with pools, riffles and glides to create a more
the existing Town Street Prow and creates a lower-level
natural and healthy river environment, supporting a diverse
overlook to the river and West Bank. The two levels are
aquatic habitat.
connected by a grand stair along the south edge of the existing Prow.
2.
Restored River Edge: Bio-engineered, stabilized and vegetated river edge with native plant material and riparian
3.
4.
6.
East Landing: Urban plaza and event space that provides a
habitat. The river edge transitions from native plantings to
connection between Downtown Columbus, the Scioto Mile
manicured parkland upslope of the leisure trail.
Promenade and the pedestrian bridge.
Leisure Trail: Continuous 12-foot-wide leisure trail on both
7.
Event Plaza and Lawn: Extension of the plaza and lawn
the east and west banks that is integrated with the Scioto-
space in front of COSI to create a venue for expanded
Olentangy Bikeway and larger regional bike trail system.
festivals, events and exhibits.
Scioto Quay: Lower level walkway along river’s edge. The
8.
main street dam removal feasibility study
2
2
3
Pedestrian Bridge: Signature bridge for pedestrians con-
quay brings people to the river and provides a link in the
necting COSI and the Scioto Peninsula to the Scioto Mile
trail system.
Promenade and Downtown Columbus.
17
BEFORE
18
AFTER - PHASE ONE
concept plan
main street dam removal feasibility study
“This project has such tremendous potential to transform the image of our city.� - public comment
19
BEFORE
20
AFTER - PHASE ONE
concept plan
main street dam removal feasibility study
“Removing the dams will help clean up the river and improve the experiences throughout the neighborhoods along the river corridor into Downtown Columbus and the Scioto Audubon Metro Park.� - public comment
21
BEFORE
22
AFTER - PHASE ONE
concept plan
main street dam removal feasibility study
“This idea is groundbreaking. It returns the river to its natural flow and uses a sustainable model for flood management.” - public comment
23
BEFORE
24
AFTER - PHASE ONE
concept plan
main street dam removal feasibility study
“Ohio means ‘beautiful river.’ As the state capital, Columbus could be the showcase of what a natural, beautiful river looks like. I would dedicate my life to making this idea a reality.” - public comment
25
IMPLEMENTATION WHAT WILL IT COST
•
Based on the concept developed as part of the Feasibility Study,
Greenways (Transportation): includes all pathways and bikepaths and associated hardcape improvements.
a preliminary estimate of probable cost was prepared. Below is the estimate for Phase One improvements, which is divided into
•
several project categories:
Greenways (Park Space): includes all park space improvements adjacent to pathways and bikeways.
• •
Existing Conditions / Site Preparation and Dam Removal:
MOVING FORWARD
Involves project mobilization and the demolition of the Main
The Main Street Dam Removal will require a coordinated effort
Street Dam.
among multiple regulatory agencies and the private and public sectors to achieve implementation. This new 33-acre green
•
River Restoration: includes all necessary earthwork as part
space will improve the health of the river and increase its value
of removing sediment and adding necessary fill to create
to the community. Building on recent park investment and
the adjacent parkland, the creation of the new river channel,
planned improvements, this new “central park” will be a green
and the restoration of the naturalized river edge itself.
link that both creates a more cohesive Downtown and connects it to the wider city. Taken together, these improvements to the
•
Utility Work: includes required extensions and protection of
river corridor will help the city become a more prosperous and
existing utilities that are exposed as part of the lowering of
competitive metropolis for the 21st century.
the river level.
Dam Removal $325,415 River Restoration
1%
$20,194,304 57%
Existing Conditions / Site Preparation $3,003,212 8%
Greenways (Park Space) $4,109,125 12%
Greenways (Transportation)
Utility Work
$3,878,757
$3,995,493
11%
11%
Existing Conditions / Site Preparation Dam Removal River Restoration Utility Work
26
Greenways (Transportation) Greenways (Park Space)
AFTER - PHASE ONE
main street dam removal feasibility study
BEFORE
27
implementation