Water / Sewer Line Project

The City closed on the $3,000,000 Texas Water Development Board (TWBD) debt issuance to fund Phase #1 of the water and sewer line rehabilitation project on Friday, October 9th. Based on current projections the design portion of the project will be completed in December 2020. Bidding for the project will occur after the design is complete. The City hopes to enter the construction phase of the project in February 2021 and anticipates construction will last approximately a year. For more information on the sections of pipe that are designated for rehabilitation during Phase #1 of this project, please visit our website at www.nassaubay.com/WaterRehab.