PROJECT CRASHING

Page 1

Project Crashing Department of Industrial Engineering Faculty of Engineering Chiang Mai University


Project Crashing

Crashing is reducing project time by expending additional resources Crash time is an amount of time an activity is reduced Crash cost is the cost of reducing the activity time Goal is to reduce project duration at minimum cost

Project Crashing

N Chareonchai, T Anantana

2


Step of Crashing Project

Determine Allowable Crash Time and Crash Cost Start crashing with the lowest crash cost in the critical path Recheck the critical path - only 1 critical path - more than 1 critical path

Project Crashing

N Chareonchai, T Anantana

3


Housebuilding Network Activity times in weeks

3

1

12

0

8

2

4

4 4

6

12

4

7

4

5

Project Crashing

N Chareonchai, T Anantana

4


Normal Activity And Crash Data Activity

Normal Time (wks)

1-2* 2-3* 2-4 3-4 4-5 4-6* 5-6 6-7*

Project Crashing

12 8 4 0 4 12 4 4

Crash Time (wks) 7 5 3 0 1 9 1 3

Normal Cost $3,000 2,000 4,000 0 500 50,000 500 15,000 $75,000

Crash Cost $5,000 3,500 7,000 0 1,100 71,000 1,100 22,000 $110,700

N Chareonchai, T Anantana

Total Allowable Crash Time (wks) 5 3 1 0 3 3 3 1

Crash Cost per Week $400 500 3,000 0 200 7,000 200 7,000

5


Normal And Crash Relationships $ 7,000 6,000

Crash cost

5,000 4,000

Normal cost

Crashed activity Slope = crash cost per week Normal activity

3,000 2,000

Crash time

1,000 0

Project Crashing

2

4

6

Normal time 8

10 12 14

N Chareonchai, T Anantana

Weeks

6


Network With Crashing Costs Activity 1-2 can be crashed a total of 5 weeks for $2000 Crash cost per week = Total crash cost/Total crash time = $2,000/5 = $400 per week Project duration = 36 wks

3 8

1

12 $400

2

$500 4 $3,000

0

4 $200

12 $7,000 4 4

6

4 $7,000

7

$200

5

Project Crashing

N Chareonchai, T Anantana

7


Crashing Solution Activity 1-2 2-3 2-4 3-4 4-5 4-6 5-6 6-7

Project Crashing

Normal Time (wks) 12 8 4 0 4 12 4 4

Crash Time (wks) 7 5 3 0 1 9 1 3

Crash Time Used

Crash Cost per Week

Crashing Cost Incurred

5 3 0 0 0 3 0 1 12

$400 500 3,000 0 200 7,000 200 7,000

$2,000 1,500 0 0 0 21,000 0 7,000 $31,500

N Chareonchai, T Anantana

8


Crashed Project 8

Project duration = 24 wks

3

5

0 12

1

2

Original time

Project Crashing

12

7

6

4

4

4

9

4

Crashed times

N Chareonchai, T Anantana

3

7

4

5

9


Time-Cost Relationship

Crashing costs increase as project duration decreases Indirect costs decrease as project duration decrease Reduce project length as long as crashing costs are less than indirect costs (optimum cost)

Project Crashing

N Chareonchai, T Anantana

10


Time-Cost Tradeoff Minimum cost = optimal project time

Total cost

Cost ($)

Indirect cost

Direct cost (Crashing cost) Crashing

Time

Project Duration Project Crashing

N Chareonchai, T Anantana

11