Foreword from Minister of State ..........................................................................2 Foreword from Chairman ....................................................................................4 Strategic Review 2001..........................................................................................7 Operations Review 2001 ....................................................................................11 OPW Achievements............................................................................................49 Financial Review 2001 ........................................................................................53 Staff and Senior Personnel..................................................................................65
Foreword from Minster of State OPW Annual Report 2001
Foreword from Minister of State The year 2001 has again seen the Office of Public Works (OPW) providing the highest quality services to Government in terms of Property, Construction and Procurement. The Office undertook a vast range of projects during 2001, indicating how it can break new ground in terms of project managing a broad scope of work.
But 2001 also brought a number of challenges,
Last year, for the first time since heritage
both expected and unexpected. Early in the year
functions were transferred from the OPW to the
the foot-and-mouth crisis brought many of our
Department of Arts, Heritage, Gaeltacht and the
activities to an abrupt halt and I commend all
Islands, the Board of the Office of Public Works
those involved in the efforts to eradicate the
was restored to its full complement. In March,
disease. I have no doubt that this Office’s quick
David Byers was appointed to the position of
response throughout the country greatly assisted
Commissioner and joined the Chairman, Brian
the fight against foot-and-mouth disease. The
(Barry) Murphy and Commissioner Seán Benton
Euro Changeover brought challenges throughout
as a Board member. Taking responsibility for the
the organisation. I do not think, however, that it
management and development of the Office’s
could have been executed more smoothly and
property portfolio and the maintenance of all
again I would like to acknowledge the efforts of
OPW properties, Commissioner Byers has
all concerned.
brought a new vision, not to mention a wealth
Finally, I would like to thank all the staff of the
of experience, to the role.
Office of Public Works for everything they have
As I have acknowledged in previous years, the
achieved over the past twelve months and wish
OPW continues to carry out a full range of
you all a successful 2002.
wonderful projects. One of the highlights for me during 2001 was the restoration of Farmleigh. Since its opening on 28 July, Farmleigh has played host to a number of foreign delegations and more than 35,000 visitors have enjoyed
Martin Cullen, TD
guided tours of the house. Not surprisingly,
Minister of State at the Department of
Farmleigh was awarded the Construction
Finance with special responsibility for the
Excellence Award in the Restoration and
Office of Public Works
Conservation category.
2
Foreword from Minster of State OPW Annual Report 2001
Réamhrá ón Aire Stáit
Ach tháinig dúshláin chun cinn freisin i 2001, cinn a rabhthas ag súil leo agus cinn eile a tháinig gan choinne. Cuireadh stop tobann le go leor dár ngníomhaíochtaí i dtús na bliana de
Arís sa bhliain 2001 chuir Oifig na nOibreacha
bharr an Ghalair Crúb agus Béil agus molaim
Poiblí (OOP) seirbhísí ardchaighdeáin ar fáil
gach duine a bhí páirteach sna hiarrachtaí deireadh a chur leis an ngalar. Níl amhras ar bith
don Rialtas, seirbhísí a bhaineann le Maoin,
orm ach gur chuidigh an freagra luath ón Oifig
Foirgníocht agus Soláthar. Thug an Oifig faoi
seo ar fud na tíre leis an gcomhrac in aghaidh an
raon leathan tionscadal le linn 2001, rud a
Ghalair Crúb is Béil. Thug an tAthrú go dtí an
léirigh arís an chaoi ar féidir léi talamh nua a
Euro dúshláin chun cinn ar fud na heagraíochta.
threabhadh ó thaobh bhainistíocht tionscadal a
Is iontach chomh réidh agus a cuireadh an
dhéanamh ar raon leathan oibre.
tAthrú igcrích. Arís ba mhaith liom aitheantas a
Don chéad uair ó aistríodh na feidhmeanna
thabhairt don obair a rinne gach duine a raibh
oidhreachta ón OOP chuig an Roinn Ealaíon
baint acu leis an iarracht seo.
Oidhreachta, Gaeltachta agus Oileán, bhí líon
Ar deireadh, ba mhaith liom buíochas a
iomlán comhaltaí ar Bhord an OPW arís i 2001.
ghlacadh le foireann Oifig na nOibreacha Poiblí
I mí Márta ceapadh David Byers i bpost
as gach rud atá bainte amach acu sa dá mhí
Coimisinéara agus ghlac seisean áit ar Bhord
dhéag atá imithe agus guím gach rath oraibh i
Oifig na nOibreacha Poiblí i dteannta an
2002.
Chathaoirligh Brian (Barry) Murphy agus an Choimisinéara Seán Benton. Agus é ag glacadh freagrachta as bainistíocht agus as forbairt phunann maoine na hOifige agus as chothabháil mhaoin iomlán an OPW thug an Coimisinéir Martin Cullen, T.D.
Byers fís nua chuig an ról gan trácht ar an
Aire Stáit ag an Roinn Airgeadais le
saibhreas taithí oibre a thug sé leis.
freagracht speisialta i leith Oifig na nOibreacha Poiblí
Mar a thug mé le fios sna blianta roimhe seo, tá an OOP ag leanúint de bheith ag plé le réimse leathan tionscadal iontach. Ceann de na buaicphointí, dar liomsa, in 2001 ba ea an obair athchóirithe a rinneadh ar Farmleigh. Ó osclaíodh é ar an 28 Iúil, tá roinnt toscaireachtaí eachtrannacha tagtha chuig Farmleigh agus bhain os cionn 35,000 turasóir tairbhe as turais threoraithe an tí. Ní hionadh ar bith é gur bronnadh Gradam Scothobair Thógála, sa chatagóir Athchóiriú agus Caomhnú, ar Farmleigh.
3
Foreword from Chairman OPW Annual Report 2001
Foreword from Chairman I am happy to present the Annual Report of the Office of Public Works for the year 2001. The primary function of this Report is to present and summarise the activities of the Office of Public Works over the past year. It also outlines the considerable diversity of the work undertaken by this organisation, and displays its
I am confident, having reviewed the progress
readiness to respond successfully to a great
that we have made, and looking at the service
variety of requirements. Innovative practices are
excellence demonstrated in this Annual Report,
seen here to be applied in work processes, and
that we will continue to deliver fully on our
best management practice affirmed.
mandate.
The report thus demonstrates that the considerable changes already wrought in the organisation of the Office of Public Works, Brian (Barry) Murphy
together with those which continue to be
Chairman
effected, have resulted in the Office delivering a
The Office of Public Works
manifestly better service. The Office is capable of further development along this path towards commercially minded responses to tasks and goals set by Government and by the agencies carrying out Government policies who choose the OPW to act for them. The ultimate aim is to give better service to the public. We now have the ability and the experience, born of our work over the past several years, to adapt to the changing circumstances that will inevitably face us in the years ahead.
4
Foreword from Chairman OPW Annual Report 2001
Réamhrá ón gCathaoirleach
thabhairt don phobal. Tá an taithí againn anois agus tá sé ar ár gcumas, de bharr na hoibre atá déanta againn le roinnt blianta, dul in oiriúint do na cúinsí athraitheacha atá romhainn go cinnte sna blianta atá le teacht.
Tá an-áthas orm Tuarascáil Bhliantúil Oifig na nOibreacha Poiblí don bhliain 2001 a chur i
Tá mé cinnte, tar éis athbhreithniú a dhéanamh
láthair.
ar an dul chun cinn atá déanta againn agus ag
Is é príomhfheidhm na tuarascála seo
breathnú ar an tseirbhís den scoth atá léirithe sa
gníomhaíochtaí na hOifige le bliain anuas a chur
Tuarascáil Bhliantúil seo, go leanfaimid de bheith
i láthair agus achoimre a dhéanamh orthu.
ag comhlíonadh ár gcúraimí.
Léiríonn an Tuarascáil seo freisin éagsúlacht réimse oibre na hOifige seo agus chomh toilteanach agus atá an Oifig tabhairt faoi líon Brian (Barry) Murphy
mór riachtanais éagsúla a chomhlíonadh go
Cathaoirleach
sásúil. Is léir go bhfuil cleachtais nuálacha á gcur
Oifig na nOibreacha Poiblí
i bhfeidhm i bpróisis oibre agus go bhfuil sárchleachtais bhainistíochta á ndeimhniú. Mar sin, léiríonn an Tuarascáil seo go bhfuil an Oifig ag seachadadh seirbhís den scoth de thoradh na n-athruithe suntasacha atá curtha i bhfeidhm nó fós á gcur i bhfeidhm san eagraíocht. Tá ar chumas na hOifige leanúint ag forbairt sa treo seo chun freagairt níos mó ar bhonn tráchtála do thascanna agus do spriocanna a leagann an Rialtas síos agus na gníomhaireachtaí a roghnaíonn an Oifig le gníomhú thar a gceann chun polasaithe Rialtais a chur i bhfeidhm. Is í an aidhm sa deireadh thiar ná seirbhís níos fearr a
5
OPW Annual Report 2001
6
Strategic Review 2001
Strategic Review OPW Annual Report 2001
Strategic Review Statement of Strategy The OPW published its Statement of Strategy in June 1998 in fulfilment of its statutory obligations under the Public Service Management Act, 1997. In accordance with Section 4 (i) (b) of the Public Service Management Act, this section of the Annual Report assesses the progress made against strategic targets during 2001. This assessment will address these issues under the six broad headings identified in the Strategy.
Front row L to R: Tony Smyth – Director of Engineering Services, Brian (Barry) Murphy – Chairman, Commissioner David Byers. Back row L to R: Vincent Campbell – Director of Corporate Services, Commissioner Sean Benton, Michael O'Doherty – Director of Architectural Services.
8
Strategic Review OPW Annual Report 2001
1. Quality Customer Service
c) The development of Service Level Agreements with Customer Departments and Offices
The elements under this heading which were identified under the Strategy are:
Work is ongoing in this area.
a) The production of Customer Service Action
d) Customer Service Training Programme
Plans
Delivery of Customer Service Training proceeded
b) The achievement of ISO 9002 Accreditation
throughout the year, with training being
by the business units
undertaken by 45 staff from the following
c) The development of Service Level
Business Units:
Agreements with Customer Departments and Offices d) The implementation of Customer Service
•
Property Management Services
•
Corporate Services (Personnel and Development Services, Training Unit and
Training programmes for all business units
Library)
a) Customer Service Action Plans Work is ongoing on the development of up-to-
2. Performance Measurement
date Action Plans in a number of areas. It is
The main themes identified in the Strategy
intended that these Plans will be organic in
Statement relating to this area are:
nature and that they will change continuously to
•
Preparation of accounts
•
Benchmarking of performance against other
reflect the evolving needs of the customer base and the developing work practices and systems
similar organisations
which will emerge from the application of ISO
a) Preparation of Accounts
9002.
Work continued throughout 2001 on the To date, Action Plans have been produced by the
refinement of the principles enunciated in the
Government Supplies Agency, Project
Accounting Protocols published in 1999. This will
Management Services and the Property
result in annual accounts which reflect a fuller
Maintenance Service.
and more accurate picture of the performance of
b) ISO 9002 Accreditation
the various Business Units and, ultimately, of the
Work continued throughout the year in various
Office as a whole.
Business Units on the measures necessary to
b) Benchmarking
achieve ISO 9002 Accreditation.
Work has continued throughout 2001 to identify
The following areas achieved ISO 9002
suitable benchmarking partners and strategies.
Accreditation in 2001:
Actual benchmarking exercises are being put in
•
Architectural Services
place following completion of these preparatory
•
Hydrometric Section, Engineering Services
•
Structures Section, Engineering Services
measures.
9
Strategic Review OPW Annual Report 2001
3. Organisation and Support Services
4. Staff Training and Development
In the Annual Report for the year 2000, the
Action on a number of initiatives relevant to this
initiatives required to provide for a sustained
theme progressed throughout the year,
renewal and replenishment of organisational
including:
supports for the Office were set out. In
a) Performance Management and Development
particular, that Report outlined the measures to
System.
be put in place by management on foot of a
Carr Communications were contracted to
number of issues, including matters which
provide support for the development of
reflected the conclusions of the Farrell Grant
PMDS. b) Staff Development Programmes.
Sparks Review. These measures, which were
The development of modern promotional
designed to reflect the strategic aims set out
systems, designed to streamline career
earlier, formed the basis for a number of key
development of staff, continued throughout
initiatives by management throughout 2001 and
the year in respect of certain administrative
were cascaded throughout the Business Units.
grades.
The following progress in respect of these
5. Information and Communications Technology (ICT)
measures was achieved during the year: •
The second Commissioner post to strengthen the delivery of the Property Management
A key organisational development during the
service was filled. •
year was the establishment of an IT User Group
The Corporate Services function, headed by a
which comprises representatives of the Business
Director, centralised all of the key support
Units and is chaired by a Commissioner. This
functions into one area. •
group will facilitate a more strategic approach to
The use of corporate structures to deliver on
the development and delivery of ICT systems
specific projects was pioneered by the
within the Office and it will also ensure that ICT
acquisition by the OPW of two companies,
developments are driven by business objectives.
Colmstock and Deepriver. •
6. Information Society Initiatives
Preliminary steps were undertaken to explore the use of corporatised entities in the
In the past year an e-strategy has been
Accommodation Programme. •
developed which sets out how the OPW will
Specific proposals for a Public Private
migrate to electronic service delivery.
Partnership to be undertaken by the Office were investigated. •
Facilities Management Unit, Legal Services Section and a Policy Unit were established.
•
Progress was achieved in some areas in the use of atypical employment arrangements for the delivery of particular initiatives and projects.
10
Operations Review 2001
Operations Review Property Services
Property Management Services Breakdown of Rents by Government Department - 2001 â‚Ź
DEPARTMENT
0%
Revenue Commissioners
14,821,949.00
20.93
Justice, Equality and Law Reform
13,260,281.00
18.73
Social, Community and Family Affairs
8,324,414.00
11.76
Finance
7,445,830.00
10.51
Office of Public Works
4,500,887.00
6.36
Enterprise, Trade and Employment
3,674,628.00
5.19
Public Enterprise
3,496,045.00
4.94
Foreign Affairs
2,658,122.00
3.75
Agriculture and Food
2,054,649.00
2.90
Education and Science
2,016,868.00
2.85
Arts, Heritage, Gaeltacht and the Islands
2,000,989.00
2.83
Health and Children
1,707,514.00
2.41
Taoiseach
1,520,190.00
2.15
Environment
1,045,772.00
1.48
Ombudsman
1,043,072.00
1.47
Marine and Natural Resources
406,137.00
0.57
Oireachtas
347,599.00
0.49
Defence
292,762.00
0.41
Tourism, Sport and Recreation
196,602.00
0.28
70,814,310.00
100
Total:
BREAKDOWN OF RENTS Social, Community and Family Affairs (11.8%)
Others (48.6%)
Justice, Equality and Law Reform (18.7%)
Revenue Commissioners (20.9%)
12
Operations Review Property Services
Transactions Involving Leased Accommodation in 2001 Dublin Acquisitions 1 January – 31 December 2001 Location
Date
Square Metres
Car Parking Spaces
Department
Smithfield Chambers Fl 4&5
01/01/01
687.74
-
Probation and Welfare Service
€272,485.79
Dundrum Gort Muire Whitefriars
29/01/01
261.99
-
Central Statistics Office
€53,433.12
Fitzwilliam Street Lower, Clifton Mews
19/02/01
204.46
1
Justice Equality & Law Reform
€104,753.39
Custom House Dublin Port
01/03/01
Site
-
Revenue
Parnell Square 2-3
15/03/01
2,126.12
9
Social Community & Family Affairs
€698,355.94
Monastery Rd Clondalkin 01/04/01
2,432
88
Justice Equality & Law Reform
€559,646.59
Merrion Square 24, The Mews
01/05/01
137.71
5
Education & Science
€68,210.33
Tallaght Plaza Hotel Carpark
07/05/01
-
60
Revenue
€65,823.22
Capel Street 89/94
15/06/01
1,972
16
Justice Equality & Law Reform
Gloucester St Sth Car Park
03/07/01
-
20
Arts, Heritage, Gaeltacht & the Islands
Park West Business Park
01/09/01
915.43
30
Public Enterprise
Chapter House Abbey St 07/09/01
7,281
45
Civil Service & Local Appointments Commission Director of Public Prosecutions
Manor Street 10/09/01 Business Park, Units 6&7
338.48
-
Health
Pembroke Street Upper 22/23
Serviced Offices
-
Foreign Affairs
Bishops Square, 01/11/01 Redmond’s Hill, Dublin 2
8,624.31
36
Social Community & €3,321,484.22 Family Affairs. Foreign Affairs. Justice Equality & Law Reform.
Total:
24981.24
310
28/09/01
13
Rent Per Annum
€43,678.99
€689,321.76 €19,046.07 €219,696.43 €3,074,391.00
€73,175.01 €182,842.28
€9,446,344.14
Operations Review Property Services
Dublin Disposals 1 January – 31 December 2001 Location
Date
Square Metres
Car Department Parking Spaces
Warehouse, Airport Business Park, Cloghran
08/06/01
1811.99
-
1811.99
-
Total:
Justice, Equality & Law Reform
Rent Per Annum €191,859.65 €191,859.65
Provincial Acquisitions 1st January – 31 December 2001 Location
Date
Square Metres
Car Department Parking Spaces
Wicklow Town, The Murrough
01/01/01
972
18
Various
Athlone Connaught St 62
01/01/01
80.86
-
Arts, Heritage, Gaeltacht & the Islands
€11,046.72
Terryglass Garda
01/01/01
83.65
-
Justice, Equality & Law Reform
€9,142.11
Sligo John ST 51A Census
01/01/01
120.82
-
Central Statistics Office
€12,697.38
Dunmanway Census
01/01/01
65
-
Central Statistics Office
€9,903.96
Dundalk Francis Street Census
01/01/01
82.62
-
Central Statistics Office
€10,102.04
Wexford. Paul Quay Car Park 1
15/01/01
-
45
Various
€45,600.00
Cork George’s Quay Census
18/01/01
176.58
-
Central Statistics Office
€33,013.19
Tralee Market House Census
19/01/01
83.65
-
Central Statistics Office
€11,427.64
Naas Corbans Lane Census
25/01/01
29.74
-
Central Statistics Office
€17,776.33
Boyle Elphin Street
01/02/01
59.30
-
Social Community & Family Affairs
€7,923.17
Castlerea, The Square
01/02/01
29.00
-
Arts, Heritage, Gaeltacht & the Islands
€6,602.64
Cavan Farnham St 7
01/02/01
37.18
-
Education & Science
€9,903.96
Tralee, The Monastery
18/02/01
527.70
12
Education & Science
€57,138.22
Cork Ballincollig
21/02/01
27.89
1
Arts, Heritage, Gaeltacht & the Islands
€6,551.85
Castleisland Church St Gda Co. Kerry
01/03/01
77.05
-
Justice, Equality & Law Reform
€6,602.64
Galway Ross House Ground Floor
01/04/01
52.79
-
Education & Science
14
Rent Per Annum €123,926.00
€13,205.28
Operations Review Property Services
Provincial Acquisitions 1st January – 31 December 2001 (continued from previous page) Location
Date
Square Metres
Car Parking Spaces
Department
Killybegs, Donegal Road
07/05/01
226.96
-
Social, Community & Family Affairs
Rent Per Annum
€68,733.46 €3,885.40
Cahir The Mill Church St.
11/06/01
21.84
-
Marine & Natural Resources
Galway Victoria Place
15/06/01
422.87
-
Education & Science €155,520.06
Sligo Bridge Street,
01/08/01
799.26
-
Social, Community & Family Affairs €146,019.88
Waterford Marina Hotel CPK
01/08/01
-
51
Revenue, Education & Science
€50,138.22
Galway Upr Abbeygate St
01/09/01
181.23
-
Probation & Welfare Service
€61,342.32
Waterford Parnell Street
03/09/01
111.53
-
Health & Safety Authority
€25,394.76
Waterford Thomas St Car Park
01/10/01
-
15
Agriculture & Food
€20,569.76
Killarney, Main St
08/10/01
22.97
-
Education & Science
€6,602.64
Bantry Bridge St Temp GS
01/11/01
178.00
-
Justice, Equality & Law Reform
€27934.24
Cork Carrolls Quay Car Park
20/11/01
-
61
Revenue
€60,414.14
4470.49
203
Total:
€1,019,118.01
Provincial Disposals 1st January 2001 – 31st December 2001 Location
Date
Square Metres
Car Parking Spaces
Department
Wicklow The Arches, Main St,
31/01/01
28
-
Arts, Heritage, Gaeltacht & the Islands
€3,656.85
Wicklow The Mall
16/05/01
42.75
-
Revenue
€5,612.24
Wicklow Govt. Offices, Marlton Rd
01/06/01
39.04
-
Social Community & Family Affairs
Kilrush Vandeleur Centre
31/08/01
19.24
-
Arts, Heritage, Gaeltacht & the Islands
€4,951.85
Wicklow Abbey St.
17/10/01
57.25
-
Agriculture & Food
€5,942.37
186.28
-
Total:
15
Rent Per Annum
€13,840.15
€34,003.46
Operations Review Property Services
OPW Policy on Property Purchases
•
In recent years the OPW has pursued a policy of
•
covenants High rental properties whose rents are likely to increase substantially in future reviews
availing of suitable opportunities that arise, (a) to purchase strategic properties and (b) to acquire
•
Buildings on whose refurbishment the OPW has spent, or plans to spend, substantially
the freehold in properties held under long or onerous leases. Specific target properties are being identified on an ongoing basis.
•
Buildings required for long term use
•
Properties of strategic value to the OPW, because of their development potential, or
The following criteria are used in targeting
the possibility of their later marriage to other
buildings for acquisition: •
Those held under leases with onerous
buildings
Those held under long leases
Site and Office Purchases 2001 Cost €
Location
Description
Dublin 8 Thomas Street
Site Assembly for Digital Hub
73,334,992
Dublin 2 Burgh Quay 13/14
Office Block
34,473,389
Dublin 8 Bride Street 41/47
Site for Office Development
Co. Galway Clifden Garda Station
Site
736,448
Co. Wexford New Ross Garda Station
Site
603,125
Co. Cork Bantry Garda Station
Site
555,510
Co. Clare Corofin
Site for Office Development
424,463
Co. Donegal Ballyshannon Garda station
Site
292,039
Co. Limerick Abbeyfeale Garda Station
Site
2,349,015
203,158
Co. Galway New Inn Garda Station
Site
152,368
Co. Kildare Carbury Garda Station
Site
109,197
Dublin 1 Upper O’Connell St 11/13
Office Block (Landlord’s Interest)
79,993
Co. Waterford Kilmacthomas Garda Station
Site
38,092
16
Operations Review Property Services
Market Analysis There was a general slowdown in the Irish property market in 2001, particularly in office accommodation. The sellers’ and landlords’ market of the last few years was increasingly displaced by a buyers’ and tenants’ one. The weakening demand for property became more noticeable after September 11 and coincided with significant increasing availability in suburban office parks. Accordingly the OPW positioned itself strategically through the year to take best advantage of the changing circumstances and to respond to a consistent level of demand from Government departments and new services.
Bishops Square
This is reflected in the value for money achieved The rental market came under pressure during
in the purchasing, leasing and rent review
2001. Prime Dublin rents shifted downward from
outcomes and in the proactive and efficient
€545 per sq. m. to €520 per sq. m. Nearly
management of the OPW’s portfolio.
160,000 sq. m. was signed in 2001, down over
Rental Market
4% on 2000.
The OPW’s overall takeup represented just under
Market involvement by the OPW included:
a quarter of the overall Dublin market activity in 2001 and over two-thirds of the entire public sector involvement in that market last year.
Property
Sq. m.
Rent (per sq.m.)
SIAC Building
3,084
€211.83
City Square
2,718
€327.98
Bishops Square
8,624
€375.88
Phoenix House
6,968
€375.88
Capel St
1,972
€375.88
Abbey St
7,281
€410.00
The OPW capitalised on its market strength in the market to secure very favourable leasing terms.
Rent Reviews It is the policy of the OPW to seek to conclude rent reviews by way of a negotiated process, based on comparative rental data. The prevailing market rents being paid on properties similar in nature and location to those under rent review
17
Bishops Square
Operations Review Property Services
are studied and analysed by OPW valuers. This
advice, valuation, negotiation and conveyancing.
comparative analysis generates a benchmark
By the end of 2001 over 60 acquisition cases
rental range. A similar analysis is carried out
had been referred to the OPW. Those
independently by the landlord’s agents for the
acquisitions at contract stage represent a
same purpose. In the light of the results on the
potential outlay of c.€7.5m.
analyses, negotiations then take place between
Accommodation for Asylum Seekers
the OPW and the landlord and, normally, these lead to a new, revised rent being agreed.
The OPW is providing a range of services in In the event of a failure to agree a revised rent
support of the Government’s accommodation
by negotiation, it is OPW policy to refer the case
programme for asylum seekers which is
to third party adjudication.
managed by the Reception and Integration Agency of the Department of Justice, Equality
The outcome of reviews in 2001 was in line with
and Law Reform. These services include technical
market evidence through the year and averaged
advice and support and procurement services for
a rate of €297 per sq. m. for second generation
the Agency. In practical terms this means that
space in Dublin City. The main rent review
the OPW purchases buildings, renovates rented
outcomes in 2001 were: Property
buildings and also constructs new buildings. The
New Rent per sq. m.
day-to-day operation of these facilities is carried
St. John’s House
€177.61
Townsend St 157/164
€210.22
Sackville House
€259.74
Trinity St 10/11
€271.47
Earl Court
€294.82
accommodation for erection at sites listed below.
Mount St 85/93
€297.30
The centres referred to are the first of their kind
Clare St 22/25
€345.52
in Ireland and demonstrate the OPW’s flexibility
Molesworth Buildings
€403.00
and expertise in imaginative use of the latest
out by management companies who are contracted by the Agency. During 2001 the OPW continued to source modular de-mountable system-built
building technology.
School Site Acquisitions
Two centres were developed through 2001 using
Since January 2000, the Property Management
system-building:
Service of the OPW has been undertaking the
Centre
acquisition of sites for primary and post-primary
Knockalisheen, Co Clare
400
€8.5m
schools all over the country on behalf of the
Cork Airport Hotel
450
€7.6m
Department of Education and Science. A complete service to the Department is provided, covering site selection, technical
19
Capacity
Cost
Operations Review Property Services
Council of State Room, Áras an Uachtaráin
Collins Barracks
New Business Relationship with Chief State Solicitor’s Office (CSSO) Recently, in line with the OPW’s commerciallyminded approach to service delivery and the wish of the Chief State Solicitor to develop modern legal services in the CSSO, Property Management Services and the CSSO have established a more structured business relationship which focuses on the setting of objectives, prioritisation of cases and the monitoring of progress in completing property transactions.
20
Financial Review 2001
Operations Review Property Services
Facilities Management Facilities Management provides a range of services in a number of properties. While the nature of the service may vary depending on the character of the property, it typically includes energy management, grounds and buildings maintenance, security, waste management and management of events within the buildings and in the grounds.
Dublin Castle Guided tours of the State Apartments are provided daily all year round. During 2001, 154,972 people visited the State Apartments, participating in 7,500 individual guided tours. Dublin Castle also hosted 504 events during the year at which there was a total in excess of 500,000 attendees.
Farmleigh
The Royal Hospital Kilmainham (RHK)
A guided tour service is provided at Farmleigh
on Saturdays from the Phoenix Park Visitor
for organised tours of the House. From the date
Centre. During the year approximately 10,000
of opening some 100 groups have been
visitors visited Áras an Uachtaráin on the
facilitated. Public events included the Official
Saturday tour. Another 12,000 people have
Opening with a concert by the National
visited the Áras by invitation or attended one of
Symphony Orchestra and two weekends of
the many receptions held throughout the year
performances by the National Concert Orchestra.
December 2001, guided tours were provided of
The Royal Hospital, Kilmainham (RHK)
the House, which had been decorated in
Facilities Management expanded its operations
Victorian Christmas style. A total of 35000
during the year to provide event management
visitors visited Farmleigh between 28 July and 31
services on an agency basis at the Royal Hospital,
December 2001.
Kilmainham. Arrangements were put in place in
On the Christmas Open Days, 1, 2, 15, and 16
late November and five events have been
Áras an Uachtaráin
hosted. The RHK houses the Irish Museum of
A guided tour of Áras an Uachtaráin, the
Modern Art which attracted 261,214 visitors
Residence of the President of Ireland, is provided
during the year.
21
Operations Review Property Services
Exhibitions in the Atrium, 51 St. Stephen’s Green
Department of Finance A facilities management company was contracted to provide under the direction of
January
Sacred Places: 2000 Years of Irish Church Architecture.
the OPW all aspects of building services, from cleaning contracts to ongoing maintenance work
August
Mies van der Rohe Award, 2001.
and minor capital projects, at the Department
September
Lundbeck Art Exhibition.
of Finance, Merrion Square. This is a trial
October
contract and will be reviewed to ascertain the effectiveness and costs of this type of service.
Mid-October Night of Theatre. November
The National Museum of Ireland, Kildare Street
North Thomond Church Silver Exhibition.
Institute of Designers in Ireland.
The National Museum of Ireland, Kildare Street (detail)
22
Operations Review Property Services
Property Maintenance Services €
Summary Report of Expenditure by OPW 1 Property Maintenance Services Maintenance
10, 262,000
Capital Expenditure
22,296,283
General Maintenance Client Accounts
18,111,437
Agency work done by OPW for Departments
5,564,105
School Works
26,785,862 83,019,687
1
This table shows expenditure on contract work managed by Property Maintenance Services, excluding Health & Safety works
Reorganisation of the Property Maintenance Service
•
Maintenance Service (BMS) which is a key factor in the new arrangements to provide a
Arrangements were put in place in 2001 to
dedicated workforce in the Dublin area to
facilitate the following: •
The reorganisation of the Building
deal with the State’s substantial stock of
The introduction of measured term contracts
heritage properties. BMS will operate from its
which are seen as a key goal in the
new headquarters at Rialto, Dublin and will,
development of a structured maintenance
in effect, manage these properties insofar as
service for the State property portfolio. This
ongoing maintenance and minor capital
system of handling work enables client
works are concerned.
Departments to order work through a
•
centralised help desk and is handled on site
Greater autonomy in OPW Regional Offices in running minor capital projects and
through contracted labour. It is intended to
ongoing maintenance works within their
have these contracts ready for rollout by mid-
region. The scope of the work in the offices
2002.
will be expanded to cater for a more broadly based service.
23
Operations Review Property Services
Health and Safety Unit
areas of thermal insulation and the complete refurbishment of school ceilings or roofs.
The main activity of the OPW's Health and Safety Unit during 2001 concerned the national
The Unit also provides an in-house service on
asbestos management programme. The Unit is
matters relating to general health and safety and
carrying out a systematic survey of all public
general guidelines and assistance on other
buildings in the State, including major facilities
health and safety works in State buildings.
such as Farmleigh, Government offices, Garda A number of Court cases arising from asbestos
stations, heritage buildings, schools and military
were processed during the year. All new cases
establishments.
are now being handled by the State Claims During 2001 approximately 800 buildings were
Agency.
surveyed to determine the location, type, form In the year 2001 the revision of the Safety
and condition of any asbestos present. This
Statements required under health and safety
brings the total since the Unit was established in
legislation for each OPW-occupied building was
1998 to about 2,500 or nearly 50% of State
concluded for a number of locations and the
buildings. During the year some 250 individual
new Statements should be ready for circulation
works contracts were undertaken. The works
early in 2002.
involved a wide range of individual items from the replacement of small boiler flues to extensive
24
Chapter Name OPW Annual Report 2001
Project Management Services
requirements in order to assist in delivering
Project Management Services, with the
Engineering standards, in compliance with
assistance of the OPW’s Architectural and
Government and EU Procurement procedures.
on time and within budget the clients/customers requirements to the highest Architectural and
Engineering Services and such private sector
Delivery of the clients/customers requirements
Professional disciplines as may be required,
involves managing the development of tender
manages the delivery of new construction,
documentation, assembly and appointment of
refurbishment, conservation and major
the Design Team, securing necessary planning
maintenance projects on behalf of the OPW and
permission, selecting contractors, overseeing
its clients/customers.
progress on site and managing the costs of the projects.
Project Management Services articulates, in detail, the clients/customers brief of
Major Programmes Agriculture Programme: The ongoing Programme of works to various offices anticipates a total expenditure of €5m of which €3,896,826 was spent in 2001. Office Refurbishment/Fit Out: Total cost of the Programme is approximately €15m of which €3,354,648 was spent in 2001. Office Rationalisation Programme (incl. Major Projects): The Programme for the major fit-out of entire buildings envisaged a total spend of some €105,734,104; the outturn for 2001 was €38,238,162 Dúchas Programme/Cultural Institutions: The estimated cost of projects comprehended by this Programme is €443,331,000 of which €19,374,933 was expended in 2001.
Completed
In Progress
In Planning
Refurbishment of Farmleigh House
Refurbishment of Waterford Government Offices, The Glen
Collins Barracks, Block 14, for the NMI
Legal Aid Board new HQ offices in Caherciveen, Co. Kerry.
Grange EU Food and Veterinary Office, Co. Meath
Restoration of the Palm House, Botanic Gardens, Glasnevin
Refurbishment of the former National College of Art and Design building for use by the National Library of Ireland (NLI)
Refurbishment of 4 Kildare St. for the NLI the refurbishment of the East Wing and Central Block of the NLI
Central Block/East Wing, NMI
Cleaning of the stonework on the Kildare Street side of the NLI
Works on fire safety and accommodation rationalisation at the NCH
New Waterways Regional Headquarters, Scarriff, Co. Clare
Turlough Park House, The National Museum of Country Life, Castlebar, Co. Mayo,
Improvements to the stage lighting at the NCH
25
Operations Review Project Management Services
Left: La Pieta Right: National Concert Hall, Auditorium
Other Major Developments (continued from previous page) Completed
In Progress
In Planning
Visitor Facility Maynooth Castle, Co. Kildare
Restoration of St. Stephens Green perimeter paths
Works to the Terrace Restaurant at the National Concert Hall
National Gallery of Ireland – Millennium Wing nearing completion
Installation of emergency lighting at Marsh’s Library Resurfacing, drainage of the courtyard at the Irish Museum of Modern Art (IMMA), Royal Hospital Kilmainham (RHK) For the NMI at Collins Barracks Works on the North/East and North/West links - Block 15 - Coins and Medals Exhibition and at Kildare Street – Medieval Exhibition
Left: Collins Barracks Right: National Gallery of Ireland, Millennium Wing
26
Operations Review Project Management Services
Left & Right: Blanchardstown Social Welfare Local Office
Department of Social, Community and Family Affairs Programme Expenditure in 2001 was €4,752,630 and the overall cost of the programme is €61,380,408
Completed
In Progress
In Planning
Blanchardstown, Dublin. Office fit-out
Arklow, Co. Wicklow. Refurbishment and extension
Goldsmith House, Dublin
Finglas, Dublin. Office fit-out
Northside Civic Centre at Coolock, Dublin, to provide accommodation for a number of State, voluntary and community organisations
Con Colbert House, Dublin
Listowel, Co. Kerry. Office fit-out
Dungloe, Co. Donegal Office fit-out
Sligo offices. Extension
Bishop’s Square, Dublin Office fit-out
Navan, Co. Meath
Longford office. Refurbishment
27
Operations Review Project Management Services
Department of Justice, Equality and Law Reform Prisons Programme The elements of the year 2000 Programme in hand is €205m of which €8,160,662 was spent in 2001.
Completed
In Progress
In Planning
Cork Prison Phase I (Wall) Construction of a new wall
Castlerea Prison, Co. Roscommon courthouse outside the prison grounds grove project within the prison
Cork Prison Phase II Juvenile detention centre pre-release centre, medical, catering, educational and training, services, recreation, visitor and administration facilities part of walled car-park
Limerick Prison Replacement of C Wing and conversion of E Wing for use as women’s accommodation
Limerick Prison Construction of new women’s unit half-way house pre-release unit
Mountjoy Prison Construction of (1) a new gatelock and (2) a new shower and laundry unit Portlaoise Prison Provision of new Gatelock
Ballyfermot Garda Station
Bray Garda Station
28
Operations Review Project Management Services
Templemore Garda College
Department of Justice, Equality and Law Reform Garda Building Programme The value of work on hand annually is â‚Ź25m of which â‚Ź16,236,140 was spent in 2001.
Completed
In Progress
In Planning
Accommodation in Talbot Premises, Santry, Dublin
Clifden Garda District HQ
Ballinrobe Garda Area HQ
Extensions/refurbishment at Templemore Garda College
Cobh Garda District HQ
Ballymore Garda Station
Bray Garda District HQ
Kilmacthomas Garda District HQ
Blanchardstown Drugs Unit
Ballyfermot Garda District HQ
Kilrush Garda District HQ
Templemore Garda District HQ
Castlecomer Garda Area HQ
Thomastown Garda District HQ
Bantry Garda District HQ
Dunshaughlin District HQ
Tourmakeady Garda Station
Ballyshannon Garda District HQ and Courthouse
Tullamore District HQ
Tralee Garda Divisional HQ
Waterville District HQ
Tallaght Garda Divisional HQ
Clondalkin District HQ
29
Operations Review Project Management Services
Court Service Programme Expenditure in 2001 was €7,073,711(£5,571,000) and the overall cost of the programme is €72,905,597
Completed
In Progress
In Planning
Kilrush Courthouse, Co. Clare
Phoenix House, Dublin Ground Floor Fit-out for use as court accommodation
Youghal, Co. Cork
Phoenix House, Dublin
Áras Ui Dhalaigh, Dublin (Part of the Four Courts complex)
Westport Courthouse, Co. Mayo Phase 2
Newcastlewest, Co. Limerick Swinford, Co. Mayo Westport, Co. Mayo East Wing (Four Courts) Navan, Co. Meath Tullamore, Co. Offaly Nenagh, Co. Tipperary Thurles, Co. Tipperary
Leinster House Programme of Works The current Programme of works totals €25m of which €10,207,424 was spent in 2001.
Completed
In Progress
In Planning
New LH2000 building fully completed including new Committee Rooms, Coffee Dock, New Press Reception Area
Electronic Voting in Dail Chamber
Underground Car Park and Landscaping Project
30
Operations Review Project Management Services
SPECIAL PROJECTS PROGRAMME This Programme if implemented in full would incur expenditure in excess of €644,000,000 of which €6,502,329 was spent in 2001. *This excludes the cost of the Sports Campus Ireland project €550,000,000 and the Aquatic and Leisure Centre €48,900,000.
In Planning Architectural Competition for Waterford North Quays Provision of Accommodation for the Department of Finance at 7/9 Merrion Row, Dublin Transfer of State Laboratory and the Dept. of Agriculture, Food and Rural Development Laboratories from Abbotstown, Dublin 15, to Backweston, Co. Kildare Assessment of Development Potential of sites at John’s Road/Military Road (part joint ownership with eircom), Relocation of Marine Institute from Abbotstown to Galway Provision of Food Safety Centre for Dept. of Agriculture, Food and Rural Development at Backweston, Co. Kildare Provision of Animal Compounds etc., on Farm at Longtown, Clane, Co. Kildare for Dept. of Agriculture, Food and Rural Development
International Programme Expenditure in 2001 was €6,983,560 and the overall cost of the programme is €28,657,419.00
In Progress
In Planning
Restoration and completion of the Island of Ireland Peace Park at Messines, Belgium
Refurbishment of the Irish College at Leuven, Belgium
Refurbishment of the Irish College, Paris
Refurbishment of St. Isidore’s College, Rome
Refurbishment of the Pontifical Irish College, Rome
Funding was provided to the Pontifical Irish College in Rome in support of a continuing programme of refurbishment and maintenance
(left) St. Isidore's College, Rome (right) Irish College, Paris
31
Dublin ZOO Entrance Building
Dublin ZOO Entrance Building
Dublin Zoo Programme In 2001 the Taoiseach approved a further five-year capital development programme for Dublin Zoo at a cost of €12,697,381. Expenditure in 2001 was €2,538,206.
32
Operations Review Project Management Services
The OPW Access Programme The Access Programme has included many buildings with a high public profile, such as Apollo House, Gardiner Street and Kilbarrack Social Welfare local offices, Dolphin House (Family Courts) and Iveagh House (Department of Foreign Affairs).
Blanchardstown Social Welfare Local Office
The 2001 works programme has been the most successful to date with a total spend of nearly €1.4m which breaks down among the various
Flood Relief Programme
Departments as follows:
The programme of Flood Relief Schemes is
Sports Council
€4,072
Dublin Castle
€5,240
managed by the OPW under the Arterial Drainage Amendment Act (1995). It consists
Government Buildings
€13,266
mainly of urban flood relief schemes which are
Finance
€21,922
carried out on behalf of local authorities. The
Foreign Affairs
€22,943
programme has grown substantially in the past
Revenue Commissioners
€28,116
few years in response to demands from local
Ordnance Survey
€78,265
authorities and increased incidences of flooding.
Environment
€178,618
The value of projects in the programme at year
Áras an Uachtaráin
€273,436
Health
€319,450
end was approx €300 million.
Social, Community & Family Affairs €417,205 Total
Progress in 2001
€1,362,533
Schemes Completed •
Bandon River, Dunmanway, for Cork Co. Council
The buildings in the 2001 programme included the Social Welfare offices at Ballyfermot and Ballymun, the ENFO office at Andrew Street,
•
Maam Valley, for Galway Co. Council
•
Hazelhatch, for Kildare Co. Council
Dublin, the computer building and public shop
Schemes in progress
at the Ordnance Survey Offices, Phoenix Park,
•
Carrick-on-Suir, for Tipperary Co. Council
and Joyce House, Dublin. This latter building has
•
Kilkenny City, for Kilkenny Corporation and Co. Council
a high public profile as it houses the General Register Office for births, deaths and marriages.
Schemes in planning
During 2001 the OPW undertook an access
Potential schemes in Carlow town and in
survey of all buildings within its portfolio
Clonmel were placed on public exhibition during
nationwide. In all over 4,000 properties were
the year. Preparatory work in preparation for
surveyed. The results of the survey are currently
public exhibition was advanced for schemes in
being analysed and will form the basis for a
Waterford City (Johns River) and Cregaclare, Co.
programme of priority works.
Galway.
33
Operations Review Project Management Services
Support to local authorities
Quantity Surveying
In addition to the above schemes which OPW
Cost Norms
manages under the 1995 Act, a great deal of
In 1992 basic cost norms were set for the
work is carried out in providing support and
various building types commonly procured by the
advice to local authorities in their response to
OPW. Simultaneously, a procedure was
flooding events. This can take the form of
introduced that would provide a standard
technical advice, co-funding of technical studies,
approach to and presentation of estimates
Environmental Impact Statement’s, or co-funding
(‘yellow form’). The norms and procedures are
of works carried out by the local authority itself.
an aid to forecasting and controlling cost.
Examples which were progressed during the Because of the wide variation in unit cost
year are: •
between buildings of the same type, importance
Development of a brief and funding of major
is attached to (i) for Orders of Cost (initial
study of Tolka River for Dublin Corporation,
estimates), identifying and allowing for
Fingal Co. Council, Meath Co. Council •
•
abnormals (e.g. a difficult site) and (ii) basing the
EU competition for appointment of consultants to study flood relief measures at
Contract Budget (at completion of sketch
Mallow and Fermoy, Co. Cork
design) on a thorough estimate and following normal cost control procedures thereafter.
Funding of report by the UDC on flooding in Ennis
The basic norms and ancillary allowances are
In addition to the above, support and/or funding
reviewed from time to time, currently quarterly.
was provided to local authorities in relation to
Reviews take into account not only past and
other locations in counties Carlow, Cork, Clare,
anticipated movement in tender levels but also
Kildare, Galway, Leitrim, Limerick, Mayo, Meath,
changes in standards (e.g. higher insulation),
Tipperary, Waterford, Wexford, Wicklow and
legislation (e.g. health and safety) and on-going
South Dublin.
cost research. The cost norm movement in the illustration is the average for the more typical buildings.
Tender Price Movement OPW Cost Norm Movement
34
Operations Review Architectural Services
programme of graduate training continues.
Architectural Services
Practical experience gained under this scheme
Architectural service for OPW projects are
affords the graduates an early opportunity of
provided from within the OPW’s Architectural
taking the RIAI / UCD. Professional Practice
Services and augmented by outsourcing partial
examinations. Eight graduates have completed
services or by employing consultant architects.
the course fifteen are presently on the course.
Conservation The Conservation Unit, in addition to executing major building conservation projects, continued with a number of conservation research initiatives, including: •
Developing a building stone database in conjunction with the State Laboratory
•
Conservation research
•
Continuing investigation into the provenance of stone; mortars and renders; paints, under joint agreement with the State Laboratory.
•
Participating with British Research Establishment (BRE) in research into older reinforced concrete structures.
•
Developing a research programme of specific practice-related subjects viz: fire safety (historic buildings) and accessibility; timber as structure; stone cantilevers; sculpted and carved elements; historic gardens/landscapes, and establishing collaborators to share in the undertakings.
Formal Professional Development
Sustainability
A formal professional development work group
Conforming with Government policy on
was established in 2001 and a full programme
Sustainable Development, the design of new
of courses and seminars was drawn up to start
buildings and upgrading of old are now subject
in January 2002. The programme is planned to
to examination in line with a Green Auditing
maintain core and specialised professional
system introduced into the practice in 2001.
competencies at the highest level.
Energy conservation through efficient energy sources, effective insulation and minimal fresh
Graduate Training Programme
water consumption, are some of the more
The OPW is committed to supporting the
obvious targets to be met.
Government’s architectural policies, and a
35
Operations Review Architectural Services
Right: Interior of Michael Davitt Museum, Co Mayo.
Top Left: Michael Davitt Museum, Co Mayo. Bottom Left: Food and Veterinary Office, Grange, Co. Meath.
Consultants’ Selection Handbook The revised version of the Handbook was issued in September 2001 and its requirements are being implemented in Architectural Services. It outlines the protocols within the OPW for seeking the appointment of consultants, and the procedures for maintaining lists of, and appointing consultants on a competitive basis.
36
Marsh's Library
Operations Review Engineering Services
Engineering Services Features of this business unit’s activities during 2001 included:
Foot-and-Mouth Disease Engineering Services contributed to the national effort to prevent the spread of foot-and-mouth disease by: •
providing personnel and equipment to assist in the disposal of animal carcasses in the Cooley peninsula
•
supplying and equipping temporary office accommodation in Ardee for use in the
Shinkeen Stream (Hazelhatch) Drainage Scheme
operation of checkpoints in the Louth area •
supplying mats and disinfectant at State
Drainage Maintenance
buildings and facilities in many areas The 2001 programme was seriously disrupted •
making OPW personnel available to regional
because of the outbreak of foot-and-mouth
veterinary offices •
disease. Despite the suspension of operations
devising and implementing a specific
between March and mid-May, the favourable
protocol to supplement that issued by the
weather at the end of the year allowed a
Department of Agriculture, Food and Rural
substantial part of lost production to be
Development.
recovered. The number of applications processed for developments affecting drainage reflects increasing awareness of the potential impact on flood risk. Output is summarised below.
East Region
West Region
South-West Region
Total
2000
2001
2000
2001
2000
2001
2000
2001
Channels maintained (km)
819
743
645
528
533
456
1,997
1,727
Bridges repaired/replaced
74
48
55
51
40
59
169
158
-
-
1
1
18
18
19
19
Numbers employed at 1st Jan
114
119
92
99
70
71
276
289
Maintenance expenditure (€m)
4.2
4.3
3.3
4.0
2.7
3.7
10.2
12.0
Development applications processed
100
177
30
72
35
145
165
396
Embankments maintained (km)
38
Operations Review Engineering Services
Plant Fleet Upgrading
flooding along the Shannon corridor in January 2000 were issued to local authorities and
The Service continued its ongoing plant
digitisation of the OPW’s, existing damaged land
replacement programme, spending €1.2m on
maps began.
new plant and equipment.
Hydrology and Hydrometric Section
Central Engineering Services The Workshops continued to service drainage
This section received 375 requests for data, 96%
maintenance operations and other clients. They
of which were responded to within 7 days of
also undertook prestige projects such as railings
receipt.
at Dublin Zoo, St. Stephen’s Green and Altamont House.
Structural Section
Flood Hazard Mapping Programme
This section continued to provide an advisory, design and monitoring service. Prestige projects completed included Custom House, Galway,
A programme to produce maps of areas of the
and Burren Display Centre, Kilfenora, Co. Clare.
country at risk from flooding was commenced.
The throughput of cases is shown below.
During 2001 maps detailing the extent of
Project/Activity
No. on hand at 1/1/2001
New projects in 2001
Total
No. completed in 2001
Building
27
10
37
7
Civil/Structural
7
2
9
5
Reports
33
40
73
44
Valuation Section
Mechanical and Electrical Section
This section had 107 cases of claims for
This section is currently re-focussing its activities
compensation from landowners and also
towards providing project advisory, design and
provided valuation and title research services in
monitoring services. Its activities in 2001 are
relation to four OPW Flood Relief schemes. The
summarised below.
Section also provided advice to Duchás, the Work Area
Heritage Service, and Waterways Ireland.
39
M & E works value
Maintenance
€3.8m
Minor works
€11.4m
New Works
€13.9m
Monitoring
€40m
Operations Review Engineering Services
Energy Conservation
comparable data has been available. One detailed examination of the data showed a saving of 16%
In many large buildings in the OPW portfolio,
in what had been a well-run building even before
energy usage is monitored on a continuous
the new technology was applied.
basis. This includes practically all the buildings for which the OPW has a direct responsibility for
The advantage of this system is that, as it
the energy consumption.
constantly monitors usage, the savings recur each year. This is more efficient than intervening
Though the system uses the most up-to date
improvements followed by regression.
technology, the principles applied are essentially very simple. Systems in the buildings used to
The same service is available to many of the
provide comfortable conditions are set locally to
buildings managed by other departments.
avoid waste. Actual energy consumption data is
Practical advice is available from the Energy
monitored in a special computer-based system
Conservation unit within Mechanical and
where the analysed data is used to advise the
Electrical services in the OPW.
building managers on possible savings. The normal saving expected with this approach is 10-20%. In the case of the OPW buildings, these savings have been recorded in cases where useful
40
Operations Review Government Supplies Agency
Government Supplies Agency A total of 85 organisations, including Government departments and offices, State agencies and other public sector bodies, utilise contracts of the Government Supplies Agency.
Turnover The total turnover during 2001 on contracts placed by the Government Supplies Agency was €60,431,000. This comprised €32,414,000 on drawdown contracts, and €28,017,000 on individual contracts. The following table gives a breakdown of the turnover by product/service type. Conference Suite commissioned by Furniture Branch
Contract Description
Turnover €000
Printing & Binding Services
15,011
Vehicles & Transport Equipment
14,865
Liquid Fuels
5,673
Advertising Services
4,756
Stationery & Office Supplies
4,284
Uniforms & Clothing
3,978
Euro Converters
3,873
Natural Gas
3,342
Personal Protective Equipment
1,403
Footwear
1,279
Public Order Equipment
1,091
Janitorial Supplies
Benchmarking The Government Supplies Agency has researched practices in a number of enterprises, both public and private, in order to establish standards for benchmarking its procurement service. Two approaches have been identified. One measures actual performance against operational guidelines developed to reflect best practice. The other is based on assessment of the cost of the procurement service as a proportion of the total procurement spend.
876
For 2001, the cost of the GSA’s procurement Total
60,431,000
service has been 1.74% of total spend.
41
Operations Review Corporate Services
Corporate Services
The management of legal services was
Personnel, Development and Organisational Services
covered included commercial and other property
A review of the Personnel function and
planning, health and safety, EU/national
responsibilities took place, resulting in a
procurement, employment and litigation.
contracted out to a firm of solicitors. Areas
transactions, commercial/construction contracts,
streamlining and redefining of the personnel
Freedom of Information Unit
operation. A new combined staff and The OPW conducts its business in an open and
organisation chart was published on the intranet
transparent manner. It therefore attempts to
and is now updated on an ongoing basis.
make information available outside the formal
Financial Services Division
procedures of the Freedom of Information Act,
Financial Services successfully managed OPW’s
1997, subject to the general scope of
preparations for and changeover to the Euro.
exemptions in the Act, if this is the preferred
Corepay, the new computerised system for the
option of the person seeking the information.
payment of salaries and wages, was introduced
On 23 July 2001, the Chairman appointed an
successfully in 2001.
additional thirteen Decision Makers and five Internal Reviewers, all of whom attended in
Internal Audit
2001 the appropriate training course organised Internal Audit maintained a proactive policy of
by the Centre for Management and Organisation
independent audits throughout the Office,
Development (CMOD).
ensuring a high level of compliance with In addition, the OPW developed a new
standards and procedures.
automated tracking system covering all requests
Training Unit
for information under the Act. This system will
The Training Unit over the past year has
facilitate more efficient and proactive
continued to implement the training programme
management of requests within the Office.
developed following the Training Needs Analysis The following table gives details of the practical
carried out in 1997.
and proactive approach the Office has adopted
Legal Services Section
to the administration of requests received under
In 2001, the Legal Services Section continued the
Freedom of Information activity under this
process begun the previous year of managing
heading during the year:
the provision of legal services in the Office.
42
Requests Withdrawn or Handled outside FOI
2
65
73
25
3
58
Total rec'd in 2001
75
1
74
0
20
26
8
1
21
Total Total
76
Appeals to Information Commrs.
Requests Transferred
217
Internal Reviews (received)
Requests Refused
7
Live Cases
Requests Part Granted
Mixed
226
No of requests dealt with
Requests Granted
Non-personal
21/04/98 to 31/12/01
Applications Received Personal
Operations Review Corporate Services
2
26
15
2
10
4
Journalists
Business
Members of Oireachtas
Staff
Others
226
86
48
3
9
80
75
37
18
0
1
19
FOI Statistics for year 2001 – summary: Live cases at beginning of year 2001 = 3 Requests received during 2001 = 75 Live cases at end of 2001 = 2 No. of requests dealt with during 2001 = 76
43
Operations Review Corporate Services
Farmleigh Library
The OPW LIbrary
A librarian is now based in Farmleigh and scholars may request permission to consult
The Library was recently extended to house the
material in their particular area of interest.
OPW architectural plans and drawings collection and considerable progress in cataloguing them
The facilities of the OPW Library were highly
was made in the course of 2001.
commended by ISO auditors at the time of recommending the Architectural Services Practice
Another major new area of responsibility was
for ISO 9001 Accreditation.
the Library at Farmleigh. This houses two collections, a selection of 1300 books of Irish
Art Management
interest which were purchased and placed on
The furnishing of Farmleigh with works of art
open shelves for the enjoyment of guests staying
was an important task early in the year.
in Farmleigh, and the very fine Guinness
A suitable collection of paintings, drawings,
collection which is on loan to the State and is
prints and sculpture - contemporary and historic
kept under conditions of the strictest security.
44
Operations Review Corporate Services
Colonel Thomas Eyre
Anne Eyre
- was assembled by the Art Management Group.
Two important portrait commissions were placed
Two exceptional eighteenth-century paintings
in 2001: James Hanley, RHA, was commissioned
were loaned by the National Gallery of Ireland
to paint the portrait of An Taoiseach, Bertie
to Farmleigh: an idyllic classical landscape by
Ahern, and Joe Dunne completed the portrait of
George Barret, RA (c. 1728 - 1784) and a
President Mary McAleese.
shipwreck scene attributed to Claude Joseph
Apart from purchasing art under the per cent
Vernet (1714 - 1789). These paintings had been
for art scheme, the Art Management Group
donated to the State in 2001 under the Relief
undertakes to acquire works of special historical
for Donations of Heritage Items Scheme.
significance or works with a particular
A large scale equestrian painting of Arkle by
connection to public-owned buildings.
Nicola Russell was also donated to Farmleigh
The portraits of the first Surveyor-General of
while a sculpture by internationally renowned
Ireland, Colonel Thomas Eyre, and his wife Anne,
sculptor, Tony Cragg, was located in the gardens.
dated 1750, were purchased at auction.
The Group continued to manage the Episodes
Eyre was responsible for the completion of the
from the Passion series of paintings by Hughie
North Range at Dublin Castle.
O'Donoghue. Study for a figure was loaned to the Irish Institute at Florence.
45
Operations Review Corporate Services
Art of the State Exhibition The exhibition featured works of art from the collections managed by the Department of Finance and Personnel, Northern Ireland and the OPW. From Past to Present, Art of the State 2002, Touring Exhibition 5 - 22 September Dráiocht, Centre for the Arts, Blanchardstown Centre 27 September - 20 October The Old Market House Arts Centre, Dungarvan, Co. Waterford 27 October - 4 November Wexford Vocational College, Westgate, Wexford 8 November - 4 December Enniskillen Castle Museum, Co. Fermanagh 6 December - 6 January 2002 Coleraine Town Hall, Co. Londonderry 11 January - 29 January 2002 Atrium, OPW Head Office, 51, St. Stephen's Green, Dublin 2 Templemore Garda College, Hugh Lorigan
Commissioned Art works installed in 2001 Location
Artist
Medium
Agriculture House, Kildare Street
Martina Galvin
Mixed media
Ardfert Cathedral
Fergus Johnston
Music
Link 51/52 St. Stephen’s Green
Marie Foley Paula Meehan
Sculpture Poem
Templemore Garda Station
Bridget Flannery Hugh Lorigan Brian Duggan
Painting Sculpture Sculpture
Tullamore Garda Station
Cathy Carmen
Sculpture
Bray Garda Station
Orla de Brí Linda Brunker
Sculpture Sculpture
Iveagh Court
Benedict Byrne
Sculpture
Asylum Seekers Residence, Knockalisheen, Clare
Fiona Woods
Artist-in-Residence
Clondalkin Garda Station
Colm Brennan
Sculpture
46
Operations Review Corporate Services
Templemore Garda College, Brian Duggan
Art works commissioned in 2001 LOCATION
ARTIST
MEDIUM
Galway Custom House
Anna McLeod
Sculpture
Portlaoise Prison Training Centre
John O’Connor
Mixed media
Dept of Education, Marlborough Square
Linda Brunker
Sculpture
Tralee Ship Canal
Alex Pentax
Sculpture
Ballyfermot Garda Station
John Campion
Mixed media
Commissions
Department, representatives from the Arts
The Art Management Group continued its
Council and an artists representative body, such
commitment to commissioning works of art
as the Artists Association of Ireland. Advice was
under the per cent for art scheme. Commissions
also given to other Government Departments on
for art works costing over €20,000 are managed
the management of their own commissions, for
by selection panels that comprise the Design
example, to Dúchas, the Heritage Service, for
Team Leader, the Project Architect, the Client
Limerick Navigation Scheme.
47
Operations Review Corporate Services
Expenditure
Art Management Handbook
Total expenditure in 2001 was in the order of
The Art Management Group worked on
â‚Ź400,000.
updating the Art Management Handbook which outlines its practice and policies in relation to the
Art Graduates
art works purchased and commissioned under
This year, the Art Management Office employed
the per cent for art scheme. It will be published
six graduates from the Department of the
early in 2002.
History of Art at University College Dublin, Trinity College Dublin and the National College of Art and Design to assist in cataloguing the collection of works of art owned by the State that are managed by the OPW. There are now almost 6,000 works on the art database. The Art Management Office is undertaking to digitally photograph the collection to make it available on the internet in 2002.
48
OPW Achievements
OPW Achievements ISO 9001:2000 Accreditation
ISO 9001:2000 Accreditation
DATE RECEIVED Architectural Services
October 2001
The OPW Architectural Services implemented a new management system in January 2001 and the Practice Manual was updated in this regard. This Manual is constantly updated and used as a method of improving and developing the system, by sharing professional information.
Engineering Services 1. Hydrology and Hydrometric Section
September 2001
This section is committed to providing a top class service to all clients by: •
carrying out its function to accepted professional and technical standards
•
ensuring that all employees are equipped for, and committed to, delivering a professional and quality service
•
continuously improving upon the standard of service provided.
This Section developed a Quality Management System and became the first professional/technical body in the Civil Service to receive accreditation. 2. Structural Section
January 2002
A Quality Management System was developed in line with the same commitment to excellence as outlined above.
50
OPW Achievements Awards 2001
OPW Awards – 2001 The following projects were managed by OPW Project Management Services and designed or commissioned by OPW Architectural Services:
Project
Award
Client
Michael Davitt Museum, Co. Mayo
RIAI Regional Award
The Michael Davitt Museum
Skibbereen Visitor Centre, Co. Kerry
RIAI Regional Award - Exhibition Status
Office of Public Works on behalf of the Department of Arts, Heritage, Gaeltacht and the Islands, Cork Co. Council and Skibbereen UDC
Botanic Gardens Visitor Centre, Dublin
RIAI Regional Award - Exhibition Status
Office of Public Works on behalf of the Department of Arts, Heritage, Gaeltacht and the Islands
Irish Folklife Museum, Turlough Park, Co. Mayo
RIAI Regional Award Office of Public Works; Mayo Co. and Gulbenkian Museum Council; Department of Arts, Heritage, of the Year Award Gaeltacht and the Islands and the National Museum of Ireland
Irish Pavilion EXPO 2000, 1 Hanover, Germany
RIAI Regional Award (overseas category)
Office of Public Works on behalf of the Department of Enterprise, Trade and Employment
Muckross House Walled Garden Complex, Co. Kerry
RIAI Regional Award - Exhibition Status
Office of Public Works on behalf of the Department of Arts, Heritage, Gaeltacht and the Islands, and the Trustees of Muckross House
Welcoming Pavilions, 2 Leinster House, Dublin
RIAI Regional Award
Office of Public Works on behalf of the Department of An Taoiseach
RIAI Regional Award
Office of Public Works on behalf of the Houses of the Oireachtas
Local Enquiry Offices Revenue 4 Commissioners, Mount Street, Dublin
RIAI Regional Award - Exhibition Status
Office of Public Works on behalf of the Revenue Commissioners
Curvilinear Range, Botanic Gardens, Dublin
RIAI Restoration Medal 1993-1995
Farmleigh House, Dublin
Construction Excellence Award - Public Building Category
Leinster House 2000, Dublin
1
2
3
4
3
Murray O’Laoire Architects, commissioned by the Office of Public Works Bucholz McEvoy, commissioned by the Office of Public Works OPW Architectural Services supported by Dolan & Donnelly Architects and Paul Arnold Newenham & Mulligan, commissioned by Office of Public Works
51
OPW Annual Report 2001
52
Financial Review 2001
Financial Review OPW Annual Report 2001
Expenditure Programme The table below shows, on a Business Unit basis, all expenditure managed by OPW in 2001 or incurred in 2001 on contracts placed by OPW (2000 figures are shown for comparison). This involves funds granted directly to OPW via Vote 10 and Vote 44; expenditure on works and services managed by OPW and paid for by other Government Departments or Agencies; expenditure by other Departments and Agencies on drawdown contracts placed by OPW; and the Local Loans Fund which is administered by OPW on behalf of the Department of Finance.
Provisional Outturn €000 2000
2001
124,217
44,325
1.
Property Management Services
1.1
Purchase of Sites & Buildings
1.2
Rent, Rates, etc.
56,270
70,814
1.3
Construction of Accommodation for Asylum Seekers
15,490
17,980
195,977
133,119
Property Management Services Total
2.
Property Maintenance Services
2.1
Minor New Works
41,378
51,480
2.2
Maintenance material and supplies
37,173
53,367
2.3
Fuel, electricity, water, cleaning materials
10,597
13,147
2.4
Facilities Management (President’s Household only) Property Maintenance Services Total
549
575
89,697
118,569
3.
Project Management Services
3.1
Building Programme
174,873
203,921
3.2
Flood Relief (including Humanitarian Aid)
7,183
13,113
3.3
Zoological Society of Ireland
9,515
2,539
3.4
Irish College, Paris
0
6,349
3.5
Irish College, Rome
0
254
3.6
Louvain Institute for Ireland
0
381
191,571
226,557
536
1,117
10,192
12,074
126
20
Project Management Services Total
4.
Engineering Services
4.1
Drainage Surveys
4.2
Maintenance Works – Maintenance costs of completed drainage schemes
4.3
Services to the Department of the Marine & Natural Resources
4.4
Purchase of Engineering plant & machinery
1,143
1,249
4.5
Maintenance of Engineering plant & machinery
1,684
1,792
2,090
237
15,771
16,489
4.6
Engineering Works for the Department of Arts, Heritage, Gaeltacht & the Islands Engineering Services Total
5.
Government Supplies Agency
5.1
Printing & publications
22,074
26,324
General procurement services
34,870
29,937
Government Supplies Agency Total
56,944
56,261
5.2
54
Financial Review OPW Annual Report 2001
6.
Corporate Services
6.1
Salaries, wages and allowances
6.2
Travel and subsistence
6.3
Incidental expenses
6.4
Postal and telecommunications services
6.5
Office equipment and other office supplies
6.6
Office premises expenses
1,241
1,264
6.7
Consultancies
273
320
25,350
28,123
Corporate Services Total
7. 7.1
18,645
20,727
1,418
1,386
745
932
966
1,032
2,062
2,462
Funds administered by OPW on behalf of the Department of Finance Local Loans Fund
61,709
38,412
637,019
617,531
Vote 10
415,043
399,928
Vote 44
1,778
2,245
Works funded by Government Departments
93,239
110,277
Expenditure by Government Departments on OPW drawdown contracts
65,250
66,669
Total This amount is funded as follows:
Funds administered by the OPW on behalf of the Department of Finance Total
55
61,709
38,412
637,019
617,531
Financial Review OPW Annual Report 2001
Funding of Programmes â‚Ź000
Note
1.
2000
2001
415,043
399,928
OPW funded: Vote 10 (Gross) Vote 44 (Flood Relief) Total
2.
1,778
2,245
416,281
402,173
19,046
26,786
1,339
6,427
Work funded from the Votes of other Departments: Construction Works & Services Department of Education Prison Projects Sundry Works
61,316
59,227
1
11,412
17,817
2
126
20
Stationery
18,876
20,868
Vehicles & Transport Equipment
20,330
14,865
5,253
5,879
8,166
7,770
2,666
4,757
Energy
8,864
11,654
General Cleaning Materials, etc.
1,095
876
158,489
176,946
61,709
38,412
61,709
38,412
Maintenance Works Services to the Department of the Marine & Natural Resources Supplies for Government Departments
Furniture Clothing
3
Advertising
Total 3.
Funds administered by the OPW on behalf of the Department of Finance: Local Loans Fund
4
Total
1.
These involve minor maintenance works on State occupied accommodation.
2.
This included work in Castletownbere, Dunmore East, Innisbofin and Killybegs
3.
Two Departments share most of the expenditure on clothing, the Departments of Defence and of Justice, Equality & Law Reform.
4.
These funds are managed on behalf of the Department of Finance. They involve the recoupment of loan payments from certain local authorities and harbours twice yearly, and the early redemption loans.
Note: It is the policy of OPW to process invoices without delay. Since 2 January 1998 the Office is operating in accordance with the Prompt Payment of Accounts Act, 1997.
56
Financial Review OPW Annual Report 2001
Funding of Programmes
57
Financial Review OPW Annual Report 2001
OPW Operating Costs OPW – Salaries & Wages 2001 Business Unit
€000
Architectural Services
3,960
Engineering Services
12,769
Government Supplies Agency
1,533
Project Management
1,649
Property Maintenance
16,807
Property Management
1,421
Corporate Services
3,813
Total
41,952
Other Current Costs Business Unit
€000
Architectural Services
503
Engineering Services
931
Government Supplies Agency
997
Project Management
120
Property Maintenance
485
Property Management
340
Corporate Services
688
General Office Expenses
3,508
Total
7,572
58
Financial Review OPW Annual Report 2001
Architectural Service Income and Expenditure Account for the year ended 31 December 2001 2000 Note Notional Fee Income
2001
€000
€000
1
€000
10,258
€000 12,747
Expenditure Employment Costs
2
4,395
5,110
Services
3
1,013
1,277
Rent
4
502
509
Insurance
5
307
381
187
197
88
85
Core Support
Depreciation Development Costs IT Running Costs
52
58
Communications
48
80
Heat and Light
33
Notional Surplus
34
6
6,625
7,731
3,633
5,016
Notes to the Income and Expenditure Account 1. Notional fee income Notional fee income has been calculated using commercial fee scales discounted by 7.5% to reflect current market conditions. No adjustment has been made to either: (a)
reflect any additional discounts which may be allowed to customers to whom long term services over a number of projects are provided; or
(b)
reflect any premium which may arise on the provision of specialist services.
2. Employment Costs Actual pension and social welfare costs incurred have been increased where appropriate to reflect rates payable by private sector organisations. No adjustment has been made to base salary levels to reflect current market pay scales or bonus and other performance related remuneration. 3. Core Support Services Support costs have been allocated on the basis of staff numbers as a percentage of total established staff. Pension and social welfare costs incurred have been increased in line with note 2 above. 4. Rent Actual
€000 14
Notional
495
Total
509
Actual rent is allocated based on area occupied as a percentage of total space being rented. Notional rent is calculated at an average of €25.40 per square foot as an approximation of current market rates on similar properties. The notional charge is also allocated based on area occupied.
59
Financial Review OPW Annual Report 2001
5. Insurance Insurance is a notional charge to reflect professional indemnity insurance costs that would be incurred by a private sector practice and is calculated based on a percentage (3%) of notional fee income. 6. Notional Surplus The notional surplus does not reflect a number of additional costs that may be incurred by an equivalent private sector practice but which cannot be estimated with a sufficient degree of accuracy to permit their inclusion in this income and expenditure account. These costs include, but are not limited to, legal fees, marketing costs, entertainment and working capital management. Note: All income and expenditure figures are shown net of VAT
60
Financial Review OPW Annual Report 2001
Dublin Castle Financial Information year ended 31 December 2001 Income & Expendenditure Report: Commercial activities
2001 Gift Shop/
Guided
Conference
State
Restaurant
Tours
Centre &
Apartment
Room Hire
€
€
€
€
€
€
8,540
408,753
940,090
742,665
293,310
2,393,358
-
275,870
122,376
248,280
-
598,069
8,540
132,883
817,714
494,385
293,310
1,795,289
-
113,636
593,728
205,612
16,946
929,922
8,540
19,247
223,986
288,773
276,364
865,367
Other Halls TOTAL Income Direct Costs Contribution Indirect Costs Surplus/ (Deficit) Fixed Costs
571,714
Notional Profit
293,653
61
Financial Review OPW Annual Report 2001
Barretstown Castle Trust Income and Expenditure account year ending 31 March 2001 Note
2000
2001
€
€
Interest receivable
4,515
6,482
Total Income
4,515
6,482
Legal and accounting fees
2,357
1,844
Gang Camp "Fantasia" Gala
2,539
0
Camper Scholarship Scheme
3,809
3,809
Total Expenses
8,705
5,653
(4,190)
829
2000
2001
-
-
-
-
Income
1
Expenses
2
Surplus (Deficit) for year
Balance Sheet as at 31 March 2001 Current Assets Debtors
3
Office of Public Works – current account
4
ACC deposit account
5
0
714
972
1,478
206,174
206,414
207,146
207,892
84
0
Current Liabilities Office of Public Works – current account
4
Accruals
6
4,383
4,383
4,467
4,383
Net Current Assets
202,679
203,509
Represented by Capital Account
203,509
164,659
Notes to the financial statements year ended 31 March 2001 1. Income The only income in the financial year ended 31 March 2001 was interest income earned on the ACC deposit account. 2. Expenses Under the current lease terms with the Gang Camp, all outgoings including maintenance and repairs of the castle are the responsibility of the Gang Camp. The accounting and legal fees relate to services provided by Ernst & Young, together with Arthur Cox in relation to services provided in 2000 and 2001. The cost of €2,539 in the year ended 31 March 2000 relates to tickets for the Gang Camp "Fantasia" Gala, the trust no longer purchases tickets for the Gala.The Camper Scholarship Scheme expense in 2000 and 2001 of €3,809 relates to an undertaking by the trust to sponsor a child at the camp for five years from 1999, at a total cost of €19,046.
62
Financial Review OPW Annual Report 2001
3. Debtors Amounts falling due within one year Accrued deposit interest ESB refund due
2000
2001
€
€
297
0
676
764
973
764
4. Office of Public Works – Current Account The amount of €714 owing from the Office of Public Works reflects the current or "suspense" account maintained by the Office of Public Works. 5. ACC Deposit Account The balance on the ACC bank deposit account agrees with the bank statement as at 31 March 2001. 6. Creditors
2000
Amounts falling due within one year Ernst & Young Relocation of family of former employee
2001
€
€
1,844
1,844
2,539
2,539
4,383
4,383
The Ernst & Young accrual is in respect of fees for the year ended 31 March 2001. The amount of €2,539 is in respect of costs associated with the relocation of the family of former employee.
63
OPW Annual Report 2001
64
Staff and Senior Personnel
Senior Personnel OPW Annual Report 2001
Senior Personnel
Staff and Senior Personnel
Brian (Barry) Murphy, Chairman of the Office of Public Works
Property Services OPW staff as at 31 December 2001 Min of State and Admin
Commissioner David Byers
Property Management Services
309.5
Tom Costello Architectural
142.5
Engineering
62
Other
44
OPW Grades
Principal Officer Paul Molloy Principal Officer
Property Maintenance Services
755
Des Thorpe Total
1,313
Head of Maintenance
Health and Safety Unit Pierce Kenny Principal Officer
Facilities Management Mary Heffernan General Manager, Farmleigh Tommy O’Shaughnessy General Manager, Dublin Castle
66
Contacts OPW Annual Report 2001
Project Management Services
Engineering Services
Commissioner Sean Benton
Tony Smyth
Jim Blighe
Director of Engineering Services
Principal Officer
Larry McGettrick
Clare McGrath
Chief Mechanical & Electrical Engineer
Principal Officer
Tom Sherlock
Una Redmond
Principal Officer
Principal Officer
Corporate Services
Special Projects Unit
Vincent Campbell
Kevin Connolly
Director of Corporate Services
Director
June Thompson
Architectural Services
Principal Officer
Michael O’Doherty
Lynda Hendley
Director of Architectural Services
Press Officer
Liam Egan
Finola Parnell
Assistant Principal Architect
Freedom of Information Officer
Michael Haugh
Financial Services and Government
Assistant Principal Architect
Supplies Agency
Ciaran O’Connor
Joseph Farrell
Assistant Principal Architect
Principal Officer
Klaus Unger Assistant Principal Architect Finbar Wall Assistant Principal Architect
67
Contacts OPW Annual Report 2001
Office of Public Works Head Office Office of the Minister of State, Office of the Chairman, Corporate Services, Property Management Services, Project Management Services, Property Maintenance Services, Architectural Services, Engineering Services, 51 St Stephen’s Green, Dublin 2. Tel: (01) 647 6000 LoCall: 1890 213 414 Main Fax No: (01) 661 0747 Website: www.opw.ie E-mail: info@opw.ie
Quantity Surveying Section, Professional Accountants 4 - 5 Harcourt Road, Dublin 2
(01) 647 6000
Arterial Drainage – Design Section, Hydrology & Hydrometric Section, Structural Engineering Section 17-19 Lower Hatch Street, Dublin 2
(01) 647 6000
Accounts Government Offices, Hebron Road, Kilkenny
(056) 72600
LoCall
1890 213 424
Government Supplies Agency 51 St Stephen’s Green, Dublin 2
(01) 647 6000
LoCall
1890 213 434
Government Publications Sale Office, Sun Alliance House, Molesworth Street, Dublin 2
(01) 679 3515
Furniture Branch Mountshannon Road, Rialto, Dublin 8
(01) 453 1588
Building Maintenance Service Pembroke Row, Baggot Street, Dublin 2
(01) 676 4633
Dublin Castle Conference Centre Dublin 2
(01) 679 3713
Farmleigh White’s Road, Castleknock, Dublin 15
(01) 815 5900
Central Engineering Workshop Jamestown Road, Inchicore, Dublin 8
(01) 453 4204
68
Contacts OPW Annual Report 2001
Arterial Drainage Maintenance Newtown, Trim, Co Meath
(046) 31352
Fair Green, Ardee, Co Louth
(041) 685 3256
Robinstown, Mullingar, Co Westmeath
(044) 48332
Ballycraine, Castlebridge, Co Wexford
(053) 24181
Drumbear, Cootehill Road, Monaghan
(047) 83201
Main Street, Headford, Co Galway
(093) 35456
Foxford Road, Ballina, Co Mayo
(096) 22065
Gallows Brae, Lifford, Co Donegal
(074) 41273
Corrib Sluice Barrage, Sluice House, Galway
(091) 563097
Templemungret House, Mungret, Limerick
(061) 227139
Inch Bridge, Listowel, Co Kerry
(068) 21166
Connaught Harbour, Portumna, Co Galway
(0509) 41086
Government Buildings, Spa Road, Tralee
(066) 24479
Hydrology & Hydrometric Services Barrack Street, Athlone, Co Westmeath
(0902) 92918
Hebron Road, Kilkenny
(056) 72641
Fair Green, Ardee, Co Louth
(041) 685 7992
Templemungret House, Mungret, Co Limerick
(061) 227139
Foxford Road, Ballina, Co Mayo
(096) 22065
Regional Architectural Offices Steward’s House, White’s Road, Castleknock, Dublin 15
(01) 812 8122
Dublin Castle, Dublin 2
(01) 475 5175
Demesne Buildings, Dundalk, Co Louth
(042) 933 4221
2 Chapel Street, Sligo
(071) 42202
Government Offices, High Road, Letterkenny,
(074) 21365
Barrack Street, Athlone, Co Westmeath
(0902) 92087
13 Catherine Street, Waterford
(051) 874134
Government Buildings, Portlaoise
(0502) 21133
Government Buildings, Arklow, Co Wicklow
(0402) 32761
Government Buildings, Anne Street, Wexford
(053) 22470
14 Old Blackrock Road, Cork
(021) 4966 200
The Demesne, Killarney, Co Kerry
(064) 31028
2 Mallow Street, Limerick
(061) 313500
Government Offices, Thurles, Co Tipperary
(0504) 21532
16 Eyre Square, Galway
(091) 563016
Pavilion Road, Castlebar, Co Mayo
(094) 21331
69
Offices OPW Annual Report 2001
Map showing distribution of OPW offices throughout Ireland
70
National Museum of Country Life and Turlough Park House