Buildings and Estates Working Together to Safeguard the Campus
Annual Report
2020
Buildings and Estates Annual Report 2020 | 1
Acknowledgements Editor Ian O’Donoghue Design One Little Studio Imagery Sean Curtain, Alan Place, Brian Arthur, Ian O’Donoghue, John O’Sullivan, Bidvest Noonan Contributors Tony Considine, Eric Crowe, Cliona Donnellan, Pat McMahon, Kieran Tuite, John O’Sullivan, Eilis Gaffney, Brian Considine, James McDonnell, Eoin Meagher, Chris Fogarty, Kelly O’Connor, Ger Manning, Marian Hartigan, Robert Reidy, Jim O’Callaghan, Gerald Hallinan. 2 | Building and Estates Annual Report 2020
Table of Contents 01.
Director’s Welcome....................................................................................... 04
02.
2020: A Year in Numbers........................................................................... 05
03.
Overview ............................................................................................................ 06
04.
Mission and Vision ....................................................................................... 07
05.
Strategic Plan: Progress Report ........................................................... 08
06.
COVID-19 ......................................................................................................... 13
07.
Department Activities.................................................................................. 21
08.
Projects................................................................................................................ 47
09.
Health and Safety ......................................................................................... 61
10.
Green Campus.................................................................................................. 62
11.
Quality................................................................................................................. 64
12.
Recurrent Expenditure............................................................................... 70
13.
Buildings and Estates Organogram ..................................................... 72
14.
Our Team........................................................................................................... 74
Director’s Welcome
The academic year 2019/2020 was an extraordinary one in the history of the University of Limerick. For the Buildings and Estates Department, the year started full of promise with exciting construction projects for the Student Centre, the Climbing Wall, the Foundation Lift and other smaller projects, which were all making steady progress. Furthermore, the University had acquired the Dunnes building in the city centre, and early ideas for its development were being explored. The University had also finalised a Draft Framework for Physical Development for the main campus, which was due to be considered by the Governing Authority around March 2020. Also in March, Buildings and Estates was undergoing its external peer quality review. However, there were murmurings in the news about a coronavirus outbreak in China, which the World Health Organization was very worried about. The outbreak was declared a pandemic on 11 March 2020. And then it came – the Taoiseach’s announcement on 12 March 2020 that Ireland was entering a lockdown. Buildings and Estates was tasked with shutting down and securing the campus. Increased national restrictions introduced during March were maintained until May, after which there was a gradual phased easing until late August. Restrictions were then gradually re-introduced due to an upsurge in COVID-19 cases. It became apparent to UL authorities that teaching in AY2020/21 needed to be conducted online with only very limited access being permitted to essential laboratory activities. Apart from a brief removal of many restrictions in December, a Level 5 lockdown was re-introduced and remained in force well into 2021. Throughout the period March to October 2020, the Buildings and Estates Department was tasked by the Executive Crisis Management Committee and later
4 | Buildings and Estates Annual Report 2020
by the expanded Space Management Committee to develop detailed physical and operational responses to the evolving situation and to help devise and implement the various protocols (health declarations, return to work, etc.) developed by Government departments. The University was requested to accommodate and construct an intermediate care facility at the Arena. This major installation, with capacity for over 100 patients and subsequently 64 beds, including all the necessary facilities, was to provide step-down care and rehabilitation to patients from hospitals in the area. The facility was designed, procured, installed and made operational in less than 10 weeks. Around the same time, an existing lab in the Tierney Building was reconfigured, including enhanced airhandling/filtration systems, to facilitate COVID-19 research. Throughout this period, mechanical/electrical and other essential systems throughout the campus had to be either brought back on stream or maintained in operation. This work was undertaken by Buildings and Estates staff, grounds staff, core maintenance staff, cleaners and security in the midst of the worst global pandemic in 100 years. There is great credit due to all these workers. I would like to acknowledge and thank each of them for their continued hard work and dedication. We look forward with hope that the vaccination programme for the population will allow a return to normality for AY2021/22.
Robert Reidy Director
2020: A Year in Numbers
128,000
PPE items ordered
17th
42,000
COVID signage items ordered
in the World UI Green Metric Rankings
110
classrooms and lecture theatres set up by the Portering team to comply with social distancing guidelines
85
departmental returnto-work business plans received
15,000
2,000
570
customer emails to B&E Help Desk
items of homeworking equipment issued
of space managed across 47 buildings
3,090
litres of sanitising gel ordered
office chairs ordered for staff remote working
261,850m2
Two-in-a-row winner of Best Student Campus Award (Education Awards 2020)
729
teaching events (labs/ tutorials) audited by the Portering team in Semester 1
18
At 18 metres, Ireland’s highest indoor climbing wall opened in October 2020
Buildings and Estates Annual Report 2020 | 5
Overview Buildings and Estates (B&E) is a customer-driven department that aspires to providing an excellent service to the UL campus and wider community. The B&E mission is to support the University to achieve its goals; its vision is to provide outstanding physical facilities for the pursuit of academic, cultural and recreational activities; its ethos is to sustain and seek to continually improve the quality of the services it provides to the campus community. The department is led by the B&E Director, who reports to the University’s Chief Operations Officer.
B&E’s brief includes the following functions: ■
New building and works projects
■
Goods inwards and distribution
■
Maintenance of the campus building fabric and associated building plant
■
Space planning and management
■
Maintenance of all campus grounds, sports fields, roads, pavings, water features, lighting and services
■
Insurance
■
Energy management
■
Land acquisition, including legal issues
■
Security
■
Signage
■
Traffic and parking management
■
Key management
■
Cleaning
■
Furniture – procurement and maintenance
■
Waste management
■
■
Portering service
Liaison with Higher Education Authority (HEA) and Department of Education and Skills in relation to buildings and physical development matters
B&E comprises 46 full-time UL direct staff, 46 full-time contract maintenance staff, 57 full- and part-time security staff and 63 full- and part-time cleaning staff. In addition to the full-time contract staff, B&E hires specialist contractors to maintain items such as safety systems and other mechanical and electrical systems. B&E’s current organisational structure is depicted on the organogram on pages 72 and 73.
6 | Buildings and Estates Annual Report 2020
The University of Limerick’s mission is to build on the expertise of its scholars in creating, harnessing and imparting knowledge for the benefit of its students and the enrichment of its community. This mission shapes that of Buildings and Estates, which is to support the University to achieve its goals.
Vision
Mission
Mission and Vision
The Buildings and Estates Department delivers services to ensure the provision of outstanding physical facilities for the pursuit of academic, cultural and recreational activities. The Buildings and Estates Department provides the framework for the infrastructure that realises this vision through the campus/ physical development plan.
Buildings and Estates Annual Report 2020 | 7
Progress Report Buildings and Estates Strategic Plan 2017-2021
8 | Buildings and Estates Annual Report 2020
In 2017, Buildings and Estates published a five-year strategic plan to provide a medium-term development and management plan both for the department itself and the UL estate. The plan was written to align with and support Broadening Horizons, UL’s strategic plan 20152019. Whilst the activities of B&E have always supported the strategic direction of the University, this was the first strategic plan devised by B&E. To support the UL plan, B&E identified the following five pillars around which to formulate its own plan.
2.2
Infrastructure improvement plan
2.3
Space strategy
2.4
Vehicular access strategy
2.5
Sustainability strategy
2.6
Excellence
On 1 November 2019, UL launched a new strategic plan, UL@50, to cover the period 2019–2024. In November 2020, the President established a Consultation Review Group to develop a process whereby all UL staff would be given the opportunity to provide feedback and contribute to an examination of what we do well, what we could do better and how that could be achieved in relation to the UL@50 goals. The ultimate aim of the consultations is to ensure that staff have a voice in determining the University’s strategic initiatives. The final report is projected for early summer 2021. It is envisaged that this report will cover both the recalibration of the UL@50 strategic plan and a sustainable structure for consultation into the future. Once the report is published, B&E will review the University’s strategic initiatives and will issue, as necessary, an addendum/amendment to its own strategic plan to bring it in line with the new institutional strategy. An overview of the status in December 2020 of each of the aforementioned pillars is presented on the next three pages.
Buildings and Estates Annual Report 2020 | 9
2.2
2.2.1 Capital development plan
Work complete on the Climbing Wall and CONFIRM. Construction ceased on the Student Centre and the contract was terminated. A completion contract is being procured for a restart in Q2 2021. An Architectural competition will be held during 2021 for a design for the future City Centre Campus. An interim use by Fablab and part of the School of Architecture is currently under discussion along with talks with UL Community Engagement and LCCC for a Citizens Observatory and Community Hub. A briefing document on Framework for Capital Development 2020-2030 is complete together with a 3D model of the proposed plan. The plan is due for presentation to the Governing Authority.
2.2.2 Refurbishment plan 2017–2019
The Framework for Capital Development envisages a significant recurring budget to tackle backlog and recurring maintenance. Resurfacing of the Main Avenue complete. B&E were successful in securing €1.1m under the HEA Devolved Grant 2020/21
2.2.3 Campus and landscape development plans
See Note under 2.2.1 above. The Campus Landscaping Masterplan will follow.
2.2.4 Parking for special campus and sports events
Consultant engaged to develop tender drawings to complete road connection into Kilmurry Village and thereby creating a third exit on to Plassey Park Road for UL traffic. A Link road from Kilmurry Village to the University Road (at Troy Studios) will be completed and the full resurfacing of University road will commence in Q2 2021.
2.2.5 Student accommodation
The Framework for Capital Development envisages an additional student village being built on campus. The brief for the City Centre Campus includes provision of further student accommodation.
2.3
2.3.1 Management of existing spaces
Briefing document on framework for capital development 2020-2030 is complete. A 3D model of the proposed plan has been created. Plan is due for presentation to the Governing Authority.
Space strategy
2.3.2 Space planning
Terms of reference for Space Management Committee have been agreed and adopted. Membership of Committee has been finalised. UL Space Policy has been approved. Since the first lockdown in March 2020 the Committee has been meeting weekly. Its terms of reference have expanded to deal with COVID-19 response and membership of the committee has been expanded to deal with COVID-19 challenges.
Infrastructure improvement plan
10 | Buildings and Estates Annual Report 2020
2.4
2.4.1 10-minute city-to-UL link
The draft Limerick Shannon Metropolitan Area Transport Strategy (LSMATS) was published in September 2020 by the National Transport Authority (NTA) in collaboration with Limerick City and County Council, Clare County Council and Transport Infrastructure Ireland. Public consultation on the draft strategy continued until 30 October 2020. The UL strategy for dealing with traffic transport and Smarter Travel was presented to GA and was approved.
2.4.2 Limerick Northern Distribution Road*
UL works on the North Exit are complete. The exit is now closed pending discussions with the local authority.
2.4.3 University Road exit at National Technology Park*
Road works on Plassey Park Road by LCC are not scheduled to start until Q2 2021 at which point work on the third exit on the southern boundary can commence (also see 2.2.4)
2.5.1 ISO 50001
Condition survey tempate has been developed for the CS Building but rollout for additional buildings on hold due to COVID-19.
2.5.2 Energy behaviour change
Physical infrastructure to enable commissioning of the OPW’s EM&T now in place. OPW has completed an energy review of buildings.
2.5.3 Waste management
As of mid-Jan 2020, the dual waste bin system was installed in all buildings operated by the University.
2.5.4 Biodiversity action plan
UL has signed up to the All Ireland Pollinator Plan
2.5.5 Ground water
Filtering system in the Arena, PESS and Schrodinger to be upgraded.
Vehicular access strategy
2.5 Sustainability strategy
*Subheading updated to reflect current status
Buildings and Estates Annual Report 2020 | 11
2.6 Excellence
12 | Buildings and Estates Annual Report 2020
2.6.1 B&E staff plan
3 new porters were recruited in late 2020 and will commence work in Q1 2021. In March 2020 the External Quality Review Group recognised that B&E are under-resourced staff wise and made a number of recommendations for some additional roles. A recruitment plan for these roles is currently under way.
2.6.2 Quality management system
B&E’s External review took place 02-05 March 2020. Overall the feedback from the reviewers was very positive. The Buildings & Estates QRG report was approved by the Quality Committee on 28/05/2020 for publication.
2.6.3 Customer engagement
A survey via Office 365 Forms was circulated to 456 customers who used B&E’s services for Qtr 1 i.e. for Minor Works, Mechanical, Electrical and Buildings Maintenance. 24% response rate. 87% rated service ’Good’. Due to COVID-19 additional surveys have been deferred until customers are back on campus.
2.6.4 Stakeholder engagement
Stakeholder engagement ongoing through various meetings with B&E staff. COVID-19 brought a whole suite of new challenges to the department in 2020 with the department supporting over 100 Return to Work applications. There was immense effort and coordination from the Facility Managers and Technical Services teams to get UL back to research and teaching in a safe and compliant way in 2020.
2.6.5 Benchmarking
UL rose to 17th place in the world in the UI Green metric rankings. The Times Higher Education World Rankings 2020 rank UL 501-600.
2.6.6 Technical improvements
A report on CAFM was prepared but progress was impacted by COVID-19. However, enabling modules for data repositories for a CAFM system have been identified and ordered, with implementation due to commence in Q1 2021. B&E took delivery of a new fleet of grass-cutting machinery and transport vehicles that will be operated by the Grounds staff. Included in the package were four ride-on mowers and one walk-behind mower as well as three runaround buggies, two of which are battery operated and have zero emissions and are extremely quiet around the campus grounds.
COVID-19
Overview On 12 March 2020, then Taoiseach Leo Varadkar announced the closure of all schools, colleges and childcare facilities until 29 March. The announcement came one day after the World Health Organization formally declared that the outbreak was a pandemic. The COVID-19 pandemic has created unprecedented societal challenges. Like all Irish universities, UL has maintained ‘business as usual’ to the greatest extent possible by rapidly transitioning in March 2020 to remote learning and working. B&E played a key role in the efforts to reopen the campus for the 2020/21 academic year and contributed to the national emergency response by fitting out the UL Sport Arena as an intermediate care facility for the Health Service Executive (HSE).
Buildings and Estates Annual Report 2020 | 13
Timeline of COVID-19 Events at UL March 12 UL Campus closes at 6pm to all staff and students
March 22 Request received by B&E to assist with setting up a field hospital in the UL Sport Arena
May 15 Space Management Committee tasked with preparing a UL specific plan on how to make the campus safe for the return of staff & students, creating a plan that meets all the requirements outlined in the government roadmap and UL’s own specific needs.
June 1 Work commences on getting buildings ready for reopening, sourcing PPE and signage
August 27 Ecostatic equipment and chemicals arrive
September 10 Treatment of water systems for legionella now 100% complete
June 8 HSE Intermediate Care Facility opens in the UL Sport Arena
August 20 University sector-wide Cleaning Regime ‘Taskforce’ established
September 13 Return to Work Project Manager and Space Manager meet with MARCOMMS to help plan information video which is part of communications plan for students
December 8 In advance of students returning home for Christmas, mass COVID-19 testing of students is facilitated on campus.
14 | Buildings and Estates Annual Report 2020
November 27 HSE hands back the UL Sport Arena. Decommissioning works by B&E commence.
March 24 Taoiseach announces universities will remain closed until 19th April
March 24 B&E as a department develops its own protocol, induction and self-declaration forms to reduce the spread risk of COVID-19 in the workplace.
May 8 March 29 Government Return to UL closes to public access. Barriers put in Work Safely Protocol is place across entrances. Access to campus published. Work from restricted to UL personnel carrying out home continues. essential business and campus village residents
June 8 Bernal Institute pilot return to work starts
July 2 COVID-19 Signage tenders returned
March 28 Non-essential construction ceases
June 10 June 19 Goods Inwards reopens to Physical Distancing survey support the deliveries to completed for teaching spaces at 2 research labs metres and 1 metre.
June 26 Multiple departmental COVID-19 Business Response Plans & requests for assistance in developing plans received by B&E. A process is put in place to record, circulate to relevant personnel and coordinate the completion of items within.
September 17 A fulfilment company appointed to distribute face coverings to 17,063 students
November 20 Government publishes Work Safely Protocol
September 25 HR issues ‘Homeworking Equipment’ information
September 28 Semester 1 commences. Return to Work Safely Protocol and sector-specific guidance rolled out across all academic spaces in time for the return of students.
November 9 Student Attendance tool within Sulis goes live and replaces sign-in sheets.
15 | Building and Estates Annual Report 2020
October 15 B&E commences dispensing homeworking equipment from Park Point.
Buildings and Estates Annual Report 2020 | 15
Return to Work Safely Protocol Following the publication of the Government’s Return to Work Safely Protocol in May 2020, the UL Space Management Committee, chaired by the Chief Operations Officer, appointed a project manager to coordinate the implementation of the protocol. The B&E Director nominated a member of (B&E) staff to undertake this role (Return to Work Project Manager), which was approved by the Space Management Committee. Since the publication of the Return to Work Safely Protocol, the Space Management Committee has met on a weekly basis to monitor its implementation and the implementation of emerging sector-specific guidance, such as the latest public health advice. An initial review of the Return to Work Safely Protocol identified 93 individual tasks that needed to be carried out to fully implement the protocol. Having examined the individual tasks in further detail, it became evident that the tasks could not be completed in isolation and needed to be grouped into discrete work packages. The resulting implementation plan for UL segregated the delivery of the protocol into two major strands: (i) the implementation of campus-wide measures by a select number of support departments; and (ii) the development of COVID-19 business response plans at the level of research areas, departments and units.
COVID-19 Business Response Plan Template B&E developed a COVID-19 Business Response Plan template to enable research areas/departments/units, etc. to comply with the requirements of the Return to Work Safely Protocol. B&E set up a process to record, track, approve and action submitted COVID-19 business response plans and presented these to the Space Management Committee on a weekly basis for initial approval and prioritisation. This enabled B&E to manage the expectations of those wishing to return to work on campus and helped us to plan our activities.
Campus-wide Measures B&E led the implementation of campus-wide measures, such as physical measures, revised facilities management procedures and procurement of personal protective equipment (PPE). To this end, B&E procured COVID-19 signage, ordered all of its PPE requirements for the Autumn semester, identified and kitted out isolation rooms in all buildings, defined the additional cleaning requirement (which led to an increase in the complement of cleaners on site by 20%), ordered ecostatic cleaning equipment and accompanying chemicals, commenced a process to ensure buildings were Legionella-free prior to reoccupation, programmed its ventilation equipment to minimise the risk of COVID-19 spreading and erected multiple hand sanitising stations. B&E also applied agreed physical distancing rules to determine revised capacities for each classroom, lecture theatre and shared space. This enabled us to set up furniture and deploy signage as appropriate. The project plan was rolled out across all academic spaces before students returned to campus. This was a mammoth task. By way of example, a nonexhaustive list of measures implemented in the Kemmy Business School (KBS) and Schuman buildings is presented opposite.
16 | Buildings and Estates Annual Report 2020
Mechanical and electrical checks completed ■ Water
hygiene services (Legionnaires’ disease mitigation) ■ Water
storage tank clean
■ Sterilisation
of services pipework
■ Daily
flushing regime due to reduced usage
Sanitising gel stations
■ Heating
unit
■ Ventilation
Stations were strategically installed in locations at all building entrances, points of frequent footfall and outside computer labs. Units were checked daily by the porter and cleaning staff.
■ Fire
Movement systems
■ Electrical
A keep-left system was put in place in the wide corridor spaces on the ground floors of the two buildings while a one-way system operated on staircases and upper levels where corridors are narrow. Signs were used to indicate routes.
17 | Building and Estates Annual Report 2020
system
systems: sprinklers, smoke fans, fire extinguishers and hose reels, and fire hydrants
■ Emergency
■ Building
lighting
distribution board
management system control
■ Fire
alarm
■ Gas
supply (test)
■ Lift
Buildings and Estates Annual Report 2020 | 17
Cleaning and sanitisation ■ Building cleaning plan in place, e.g. standard office cleans (of rooms identified as being in use), corridor vacuuming, removal of waste from bins
■ Classrooms:
■ Sanitisation
■ Lecture
students at 1-metre spacings; lecturer located 2m away from students
■ Computer
labs: 1m spacings; lecturer located 2m away from students
plan in place:
theatre: while students can be spaced at 1m, all lecture theatre seating is measured at 2m spacings as we have the space to do so in line with the national guideline of a maximum of 50 people in an indoor space.
■ Twice-daily
sanitation of all common touch points, e.g. door handles/push plates, corridors, lifts, stairs, bin lids
■ Wipes
available for self-service in classrooms, lecture theatres and computer labs
■ Ecostatic sanitising of
the classrooms carried out in the evenings once per week (remains effective for up to a month)
■ Deep
cleans completed (ongoing periodically throughout summer)
Restrooms ■ Restrooms deep-cleaned and re-opened for use ■ Legionnaires’
disease mitigation measures completed, including replacing all toilet seats
■ Max
capacity signs on the door; capacity based on 2-metre distancing at wash-hand basins
■ Installation
of paper towel dispensers
■ Installation
of liquid soap dispensers
■ Installation
of pedal assist bins
■ Removal/decommissioning
units and hand towel units
of hand dryer
Multi-occupancy room capacities ■ Audits of classrooms, lecture theatres, computer labs and multi-occupancy offices completed ■ Max
capacity signs on all room doors
■ Furniture
adjusted to facilitate seating at the required distance, with sticker signage indicating which seats not to use
18 | Buildings and Estates Annual Report 2020
Staff kitchenette After reviewing the kitchenette in the KBS, it was decided that it was safer to keep it closed to avoid the risk of contaminated items being shared.
Isolation rooms ■ One isolation room provided per building – one in KBS, one in Schuman ■ Provision
of PPE in dedicated pedestal
■ Seating ■ COVID
waste bin for contaminated waste
• Breakout spaces ■ Seating adjusted to ensure 2m spacings only ■ Excess
furniture removed and cordoned off to prevent misuse
Signage The following page shows samples of signage located across KBS/Schuman.
buildingsmaintenance@ul.ie
NO STAIRS: ACCESS UP ONLY Reserved For Persons With Disabilities And Service Staff Only
Face coverings must be worn are here. Face StayCoverings safe. Mandatory in the Protect each other. Glucksman Library
STAIRS:
Coronavirus COVID-19 Public Health Advice
ENTRY ONLY
EXIT ONLY
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE FOLLOW SOCIAL DISTANCING
Max Occupancy
Wearing a face covering helps prevent the spread of COVID-19
Masks must be worn for TWO WAY CORRIDOR: #holdfirm the duration of your visit.
> It should fit snugly and cover your nose/chin > Avoid touching it while wearing > Continue to wash your hands and social distance > Not suitable for under 13s or those who have difficulty wearing them
DOWN ONLY
Stay safe. Protect each other.
KEEP LEFT
Place Art Work Here
PLEASE EMAIL:
PLEASE CLOSE LID BEFORE FLUSHING
PLEASE WIPE DOWN YOUR WORK SPACE REGULARLY
IF THIS ROOM IS USED FOR A COVID RELATED OCCURANCE
Coronavirus COVID-19
Ireland’s public health advice is guided by WHO and ECDC advice
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE FOLLOW SOCIAL DISTANCING
Max 1 Person
Max 2 People
Max 3 People
Max 4 People
Max 1
Max 2
Max 3
Max 4
Maximum quantity of people permitted at any one time
Protect yourself and others from getting sick Wash your hands • after coughing or sneezing • when caring for the sick • before and after you prepare food • before eating • after toilet use • when hands are visibly dirty • after touching cuts, blisters or any open sores • you can use alcohol hand rub, if hands are not visibly dirty
Place Art Work Here
Maximum 1 person permitted in the toilets at any one time
Maximum 2 people permitted in the toilets at any one time
Maximum 3 people permitted in the toilets at any one time
Maximum 4 people permitted in the toilets at any one time
PLEASE WIPE DOWN YOUR WORK SPACE REGULARLY
ndhygiene
www.hse.ie/ha
Coronavirus COVID-19
THIS WAY
PLEASE FOLLOW SOCIAL DISTANCING
THIS WAY
NO ENTRY
Coronavirus COVID-19 Public Health Advice
Stay safe. Protect each other. Continue to:
Wash
your hands well and often to avoid contamination.
Cover
your mouth and nose with a tissue or sleeve when coughing or sneezing and discard used tissue safely
Distance
yourself at least 2 metres (6 feet) away from other people, especially those who might be unwell
COVID-19 symptoms include
PLEASE FOLLOW SOCIAL DISTANCING
Avoid
crowds and crowded places
> high temperature > cough > breathing difficulty > sudden loss of sense of smell or taste > flu-like symptoms
Know
the symptoms. If you have them self isolate and contact your GP immediately
If you have any symptoms, self-isolate to protect others and call your GP for a COVID-19 test.
#holdfirm
Coronavirus COVID-19
Coronavirus COVID-19 Public Health Advice
Stay safe. Protect each other.
THIS WAY
PLEASE FOLLOW SOCIAL DISTANCING
Continue to:
For more information
www.gov.ie/health-covid-19 www.hse.ie
Ireland’s public health advice is guided by WHO and ECDC advice
Wash
Cover
Avoid
Know
your hands well and often to avoid contamination.
Coronavirus COVID-19
Distance
yourself at least 2 metres (6 feet) away from other people, especially those who might be unwell
Coronavirus COVID-19 Public Health Advice
To protect yourself and others you need to wash your hands with soap and water Wet your hands with water and apply soap Rub your hands together until the soap forms a lather Rub the top of your hands, between your fingers and under your fingernails 20
your mouth and nose with a tissue or sleeve when coughing or sneezing and discard used tissue safely
crowds and crowded places
ONE WAY SYSTEM IN OPERATION
COVID-19 symptoms include > high temperature > cough > breathing difficulty > sudden loss of sense of smell or taste > flu-like symptoms
#holdfirm For more information
www.gov.ie/health-covid-19 www.hse.ie
Do this for about 20 seconds Rinse your hands under running water Dry your hands with a clean towel or paper towel
the symptoms. If you have them self isolate and contact your GP immediately
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE DON’T MOVE THE FURNITURE
Ireland’s public health advice is guided by WHO and ECDC advice
Kill the virus. Save lives.
Ireland is operating a delay strategy in line with WHO and ECDC advice
NO ACCESS
TWO WAY CORRIDOR:
PLEASE FOLLOW SOCIAL DISTANCING
PLEASE FOLLOW SOCIAL DISTANCING
19 | Building and Estates Annual Report 2020
19 | Building and Estates Annual Report 2020
KEEP LEFT
HAND SANITISER
SANITISING WIPES
IF FOUND EMPTY PLEASE EMAIL THE FOLLOWING LOCATION CODE:
IF FOUND EMPTY PLEASE EMAIL THE FOLLOWING LOCATION CODE:
TO
TO
buildingsmaintenance@ul.ie
buildingsmaintenance@ul.ie
ISOLATION ROOM PLEASE FOLLOW SOCIAL DISTANCING
Building and Estates Annual Report 2020 | 19
Buildings and Estates Annual Report 2020 | 19
Updated Guidance During the roll-out of the Return to Work Safely Protocol, additional guidance documents were published, including Implementation Guidelines for Public Health Measures in Higher Education Institutions (HEIs) and Practical Guidance for Further and Higher Education for Returning to Onsite Activity in 2020, which were integrated into the overall project plan.
Recording Information for the Purposes of Contact Tracing Updated guidance placed an onus on higher education institutions (including UL) to record attendance at all ‘events’ on campus. B&E prepared a briefing note for discussion at the Space Management Committee to outline potential approaches that could be adopted. These included technology-based solutions, paperbased solutions and the use of existing records held by Academic Registry (e.g. timetables). It was agreed to use a paper-based system initially with a view to switching, if possible, to a technology-based alternative. The paperbased system required daily deployment and collection of sign-in sheets by Security to and from all teaching spaces in use (157 of the total 425 teaching spaces available). Spaces not in use were kept locked. To facilitate the cross-referencing of information collected for the purposes of contact tracing against the expected number of sign-in sheets, B&E’s Portering team undertook utilisation surveys of centrally scheduled teaching spaces over a 10-week period (making 2,147 observations in the process). The information helped inform the decision to switch to UL’s learning platform (Sulis) to record information for the purposes of contact tracing. Weekly utilisation rates ranged from a low of 18% in Week 11 (Year 4 only on campus) to a high of 74% in Week 4/ Week 7 (Year 1 and Year 3/Year 1 and Year 4 on campus). The weighted average weekly utilisation rate was 64%. Overall, 94% of all centrally scheduled classes were labs.
Accessing UL Buildings In keeping with the latest public health and government advice, B&E maintained and implemented an up-todate process for permitting access to UL buildings. The process complements UL’s health & safety process to manage visitors to campus. Both processes ensure that workers travelling to and working on campus are doing so for essential purposes.
Homeworking Equipment
In keeping with the latest public health and government advice, B&E maintained and implemented an upto-date process for permitting access to UL buildings.
20 | Buildings and Estates Annual Report 2020
In early October, B&E began dispensing homeworking equipment from Park Point. Details of the numbers are given in the Administration section of this report.
Mass Testing In advance of the Christmas break, the HSE contacted UL to request that a COVID-19 test centre be set up to facilitate the mass testing of UL students. To minimise the potential for spreading the virus (especially by those travelling home for Christmas), free COVID-19 tests were offered to all students. B&E worked with the HSE to identify a suitable testing space and to set up the space in accordance with HSE specifications. Preparations included installing floor tape and signage, arranging/removing furniture, opening windows and providing waste collection facilities. Over 1,000 students signed up to avail of a test, 917 of whom attended for testing. After testing was complete, B&E reinstated the facility to its original setup and deep-cleaned the space.
Department Activities Buildings and Estates Annual Report 2020 | 21
Technical Services Elimination
Most Effective
Substitution
Engineering Controls Administrative Controls
Personal Protective Equipment
Community Protective Equipment
The world changed on 12 March 2020 with the first COVID-19 lockdown. This was keenly felt by everyone, none more so than the B&E Technical Services (TS) team. The lockdown and subsequent restrictions brought many challenges, as described below.
Return to Work/Return to Teaching Process B&E processed over 85 return-to-work applications by various departments, research groups and units. The TS team played a major role in developing and mapping out these processes, which involved modifying building infrastructure and systems to comply with COVID guidelines. The TS team took the processes and developed specific procedures and instructions for TS staff, such as ventilation and anti-Legionella precautions. An overview of some of these items is presented in the checklist on page 24. The return to partial occupation of buildings following the initial lockdown of 12 March presented a major challenge for the TS team. Many systems required checking or recommissioning, as outlined in the checklist. This was carried out on a building-by-building basis as the return-to-work process progressed.
Least Effective
Ventilation According to the US Centers for Disease Control and Prevention (CDC), there are multiple categories of measures, each with differing levels of effectiveness, that can be put in place to prevent hazards (CDC, 2021). The figure above shows the US CDC’s hierarchy of controls adapted to the COVID-19 context (source: Cornell University, 2021). The Government’s Work Safely Protocol1 recognises the usefulness of, amongst other things, engineering and administrative controls (e.g. increased ventilation) in mitigating against the spread of COVID-19. The protocol sets out two methods of increasing ventilation: mechanical ventilation (i.e. forced ventilation) and natural ventilation. The protocol also points to specific guidance on ventilation from the Health Protection Surveillance Centre (HSPC); European Centre for Disease Prevention and Control (ECDC); Chartered Institution of Building Services Engineers (CIBSE); and Federation of European Heating, Ventilation and Air Conditioning Associations (REHVA).
1 Published in November 2020, this protocol is a revision of the May 2020 Return to Work Safely Protocol.
22 | Buildings and Estates Annual Report 2020
Ventilation Switch off
Mechanical Ventilation (Forced Ventilation) B&E reviewed all relevant guidance on mechanical ventilation and modified the campus building management system control strategies to maximise this type of ventilation. The general thrust of the guidance on mechanical ventilation is to: ■ Supply
as much outside air as possible [in place]
■ Use
the most efficient filter possible for the system where recirculation is used (in UL’s case, this is an ePM1 85%) [in place]
■ Switch
on mechanical ventilation in ‘occupied mode’ for two hours before occupancy commences and two hours after occupancy ends [in place]
■ Continue
to operate ventilation outside of ‘occupied mode’ to achieve the minimum outdoor airflow rate as set out in EN16798-1:2019 [in place]
In the hierarchy of controls shown on the previous page, mechanical ventilation is an engineering control and, accordingly, plays a central role in preventing the spread of COVID-19. The figures above and below show the impact of mechanical ventilation on the amount of virus-laden particles within the breathing zone (above figure ventilation off, below figure ventilation on) (source: REHVA, 2020).
Ventilation Switch on
23 | Buildings and Estates Annual Report 2020
Buildings and Estates Annual Report 2020 | 23
Returning to Work - Building Services Systems Checklist To be completed prior to building reoccupation.
BUILDING NAME
System
Component
Task
Natural Gas Supply
Gas installation
Carry out soundness test. Reinstate gas supply to building.
Compressed Air
Re-commissioning checks
(Note: The re-commissioning process should be coordinated with the specialist provider)
Run systems to working pressure. Check all safety devices. Check system for any air leaks. Check running current.
Water Hygiene Services
Water storage tanks
Clean water storage tanks.
Water services
Sterilise/disinfect water services pipework. Flushing regime to be agreed.
Incoming mains water supply
Take a meter reading. Check mains water filters and replace if required.
Water softeners
Check salt level and top up. The water softener should then be put through a manual regeneration so that it is ready for use.
Heating
Ventilation
Drinking fountains
Run five (5) litres of water through outlet
Sanitary ware
Check operation of Cisternmiser Units
Hot water storage vessels
Inspect and replace anodes where required.
Waster water traps
Inspect sample of traps to determine whether there is a requirement to clean the traps prior to opening the building.
Cold water main
Check the cold water supply to the heating system is on.
Pressurisation unit
Check unit status for faults.
Fresh air requirements
The ventilation systems have been accessed and all units are switched to 100% fresh air.
CO2 control
Where applicable, adjustments to CO2 control not to exceed 400PPM.
24 | Buildings and Estates Annual Report 2020
System
Component
Task
Chilled Water
Cold water main
Check the cold water supply to the cooling system is on.
Pressurisation unit
Check unit status for faults.
Chilled water system
Start the system.
(Note: The re-commissioning process should be coordinated with the specialist provider)
Circulate the system water. Schedule the recommencement of routine service visits, system analysis and dosing of the system with inhibitor.
Laboratory Gas Supply
Gas installation
Carry out soundness test. Remove lock-off tag-off. Reinstate power supply to gas manifold.
Fire Protection
Sprinkler
Periodic inspection checks are up to date.
Smoke fans
Check operation of fans.
Smoke curtains
Check operation of curtains.
Fire extinguishers and hose reels
Periodic inspection checks are up to date.
Fire hydrants
Periodic inspection checks are up to date.
-
Periodic inspection checks are up to date.
Addressible
Check system for fault list.
Central battery
Check system voltage and charge rate.
Cooling
Fan coils and cassette units
Where units have been switched off, ensure that any condensate drainage is free-flowing and the tray/reservoir is emptied.
Electrical Distribution
Distribution boards
Visually inspect.
BMS / Controls
Controlled devices
Controlled devices
Fire Alarm
-
Periodic inspection checks are up to date.
Gas Detection
-
Periodic inspection checks are up to date. All devices are functioning.
Emergency Lighting
Lifts
-
Check functionality of passenger lifts; report issues to specialist provider.
Automatic Opening Vents
Air compressors
Check operation of compressor.
Chain driven
Check control panel for faults. Manually open vents.
25 | Buildings and Estates Annual Report 2020
Buildings and Estates Annual Report 2020 | 25
Legionnaires’ Disease Threat Large water distribution systems require an appropriate sterilisation regime to prevent the risk of Legionella Pneumophilia bacteria growing. Growth of the bacterium in question is dependent on a number of variables, one of which is the degree of water use, i.e. drawing the water through the system and maintaining a fresh supply. Under-utilisation of a system runs the risk of promoting Legionella. Following the March 2020 lockdown, UL buildings generally had very little occupancy, which obviously meant very little water use. The TS team was faced with the dilemma that while the buildings were sparsely occupied, they were not empty. Furthermore, shutting down and draining water distribution systems is not a solution to the Legionella threat because small pockets of stagnant water will be present in the system and thus will exacerbate the risk. After consulting with various published guidelines and with water treatment specialists, the TS team adopted the solution of bringing forward B&E’s normal annual water supply sterilisation process and designing and implementing a flushing regime. Seventy-nine individual water systems were included in the process. The flushing regime involved B&E staff running water through the systems (running taps, flushing toilets, etc.) in a controlled and systematic manner to simulate normal building water use. This flushing regime is still ongoing at the time of writing and will continue, in accordance with guidelines, until building occupancy rises to above 40% of normal design occupancy.
Energy Savings Initial guidelines advised that mechanical ventilation plant and systems be modified to provide as much fresh air as possible – even at the expense of comfort and energy consumption. Subsequent versions of the guidelines stepped back from this because it was acknowledged that: 1. Maximising fresh air throughput in cold conditions was likely to overwhelm the capacity of ventilation plant and possibly cause damage 2. Running ventilation systems around the clock does not add any benefit over running the systems for two hours before and after occupancy Resolving these changes to the guidelines in an effort to reduce excessive energy consumption involved making further major modifications to building management system control strategies.
Toilet Seats REHVA guidance draws attention to the potential for SARS-CoV-2 aerosols to be generated by flushing toilets with open lids. A survey conducted by the TS team showed that 254 toilet WCs on campus were not fitted with a lid. The team replaced these seats with seats that incorporated a closable lid and erected signage in restrooms advising that the lid should be closed before the toilet is flushed.
26 | Buildings and Estates Annual Report 2020
Operations
Space Management The Buildings & Estates Department currently manages 261,850m² (2,818,530ft²) of space across 47 UL buildings. The table on the next page sets out how this space is broken down into different room types and indicates the broad spectrum of the space portfolio that is handled by the department.
Buildings and Estates Annual Report 2020 | 27
Type of space
Area m²
% of total space
Office and related
32,408
12.38%
Laboratory and support
33,265
12.70%
Teaching
11,775
4.50%
Catering/bar/commercial
8,405
3.21%
Library
9,758
3.73%
Sports facilities
15,130
5.78%
Student residences
76,142
29.08%
Non-assignable
52,240
19.95%
Other
22,728
8.68%
261,850
100%
Total
B&E continues to work to consolidate and rationalise the space occupied by the various faculties, divisions, departments and research centres within UL. Although most of us worked off campus for the greater part of 2020, significant expansion plans for many areas throughout the campus were developed during the year and a number of new initiatives, which have added greatly to the challenge of managing space in general, were introduced. The past year saw a reduction in the number of office moves when compared to more recent years. However, a total of 81 office moves still took place in 2020, which led to further consolidation of many divisions and departments across the University. All moves are agreed in advance with ITD to ensure that staff’s computers, printers and phone extensions are moved and operational on the day of the move. The chart opposite shows the number of office moves that were planned and implemented by B&E over the last number of years.
Office Moves February 2020 saw the first meeting of the newly reconstituted Space Management Committee. Comprising several members of UL senior management, the committee makes key decisions in relation to future space planning and considers proposals on how vacant and decanted spaces should be reallocated to best serve the University’s strategic plan. Due to the COVID-19 outbreak, much of the work of the committee since April focused on the safe operation and re-opening of the University.
28 | Buildings and Estates Annual Report 2020
Office Moves 315
300
No. of Office Moves
250
218
200
195
162
150
155 144
142
142 131 112
110
101
100
81
78
2008
2010
2012
2014
2016
2018
2020
Year
In September 2020, the HEA requested all higher education institutions to complete a major space survey. The survey asked responding institutions to provide in excess of 4,000 separate pieces of information. The range of information sought included but was not limited to: ■ A
breakdown by building of all space on campus. For each building, space was to be split into 22 different pre-defined categories.
■ For
each building, the primary and secondary discipline occupier and the percentage of that space as well as the percentage of the building devoted to research
■ Latitude
and longitude co-ordinates and Eircode for each building
■ Area
of playing fields, number of car parking and bicycle spaces
■ Area
and folio numbers for all land holding as well as available development land
■ Insurance
valuation for each building
■ Detailed
condition breakdown of each building by defined categories and an estimate of costs to bring each building back to a good level. This is defined as operationally safe with only minor defects.
■ Functional
suitability of each building to accommodate the activity housed in the
building
■ Breakdown
of staff and student numbers
■ Form
of construction and materials used in each building, including floors, walls, roofs, etc.
■ Annual
energy usage and emissions, BER ratings and details of mechanical plant and lighting types, etc.
■ Annual
waste mass
■ Environmental ■ Operating
management system in place
costs
29 | Buildings and Estates Annual Report 2020
Buildings and Estates Annual Report 2020 | 29
As a result of the COVID-19 global pandemic, to support the operation of the University and to ensure the safety and wellbeing of its staff and students, B&E conduced the spacerelated surveys opposite.
30 | Buildings and Estates Annual Report 2020
Space-related surveys ■
■
■
Separate 2m and 1m social distancing capacity surveys in over 140 separate classrooms and lecture theatres, in over 300 undergraduate and postgraduate labs and in over 50 computer labs A 2m social distancing survey to establish the capacity of almost 300 multi-occupancy offices To assist Student Life, a 2m social distancing survey of all rooms in the existing student centre
In addition, B&E carried out a number of other space-related initiatives: ■
■
■
■
■
■
To ensure that postgraduate research students returning to the Foundation Building would be properly distanced from each other, B&E met with representatives from each faculty and agreed a schedule for when each of the 300+ desks could be used and the name of the person who would use it. B&E engaged with many different departments to agree the temporary re-purposing of rooms as isolation rooms. In total, 26 isolation rooms across 19 different buildings were provided. B&E ensured that all the rooms were fully stocked with required PPE, waste disposal receptacles, cleaning schedules, etc. Due to social distancing capacity guidelines, B&E reviewed campus spaces that would potentially be suitable for converting to classrooms on a short-term basis. Twelve separate spaces were identified, costs were estimated and, finally, in conjunction with ITD and Academic Registry, four additional teaching spaces were provided as part of the central pool of rooms. Before students returned to campus in September, B&E identified areas that would be suitable as social/communal/study spaces for students to use between attendance at labs and tutorials. The spaces comprised communal and catering areas that were to remain closed otherwise. In all, 12 spaces were identified. B&E carried out 2m social distancing capacity surveys in all areas and removed seats or tapedoff areas where students would not be permitted to sit. From Week 3 to Week 12 of the Autumn semester, B&E carried out an hourly audit of every centrally scheduled teaching event to physically check whether or not the event took place. This information was then used by ITD/HR to monitor attendance tracking and by the Provost & Deputy President to monitor the uptake of teaching events that were deemed to have to take place on campus. From Week 6 to Week 12 of the Autumn semester, B&E worked with colleagues in the Library to monitor the Library’s daily and peak occupancy figures. In the event that the capacity of the Library would be exceeded, B&E put a contingency plan in place to provide additional study spaces in the Main Building. This additional space was not required ultimately.
The year 2021 is shaping up to be another very challenging year in terms of space planning and allocation, and a number of significant requests for additional space are already in the planning stage.
Buildings and Estates Annual Report 2020 | 31
Cleaning
B&E is responsible for cleaning UL’s academic buildings. The work is carried out by Bidvest Noonan. The contract for the provision of UL cleaning services was tendered in 2019 in consultation with the Office of Government Procurement (OGP). The contract was awarded in August 2019, the duration of which is in accordance with the OGP guidelines. Generally, the cleaning of buildings is carried out between 6pm and 2am, Monday to Friday. All general areas and teaching spaces are cleaned daily. Offices are cleaned twice a week on an agreed cleaning schedule, which is available on the cleaning section of the B&E website. Daytime janitorial staff provide a restroom service from 9am to 5pm, Monday to Friday, and attend to any emergency cleaning situations that might arise during these hours.
COVID Cleaning Due to COVID-19, B&E adapted the cleaning services in accordance with the requirements of the Return to Work Safely Protocol and the aforementioned guidelines for public health measures in higher education institutions. The cleaning scope was expanded to include an additional daily clean of all restrooms; provision of pedal bins in restrooms; use of disinfectant chemicals; twice-daily sanitisation of common touch points (push plates, door handles, bin lids, lift buttons, hand rails) in buildings; ecostatic spraying; additional waste removal, including the use of specific storage areas for PPE waste; and an automated audit of sanitised areas.
32 | Buildings and Estates Annual Report 2020
Ecostatic Spraying With the help of Bidvest Noonan, B&E researched additional sanitisation methods that could be used in conjunction with general cleaning to ensure that the high-usage areas would receive extra sanitisation. Ecostatic sanitisation systems were deemed to be the most suitable. Ecostatic cleaning agents are safe to use, non-corrosive, non-irritating, non-toxic, food-safe and cost-effective and have a prolonged antimicrobial effect that degrades/decomposes into safe by-products after use. The process is implemented using a backpack spray system by specifically trained cleaning staff. An ecostatic sanitisation schedule was developed for classrooms, lecture theatres, the Library, public spaces and the seating areas of catering spaces on a five-day rolling cycling. B&E would like to take this opportunity to recognise the outstanding work provided by our cleaning staff throughout what was a very challenging year.
Window Cleaning The contract for the provision of window cleaning services for UL was tendered in 2017 in consultation with the OGP. The contract was awarded in August 2017 to Bidvest Noonan for a period of time in accordance with the OGP guidelines. All external glazing and internal windows are cleaned between July and September annually, when the campus is at its quietist. The contractor uses a reach and wash system that is environmentally friendly as no chemicals are used. This system also eliminates the need for ladders or high-access equipment, which reduces health and safety risks.
Taken in 2019
Portering The Portering team has a wide-ranging mix of duties and responsibilities. The following are examples of the activities carried out by the Portering team:
■ Being
■ Setting
■ Providing
up and regularly spot-checking teaching spaces, communal areas, seminar spaces and a significant number of nonscheduled labs, computer labs and PBL (problem-based learning) rooms
■ Setting
up and regularly checking exam centres for central and locally held departmental exams
■ Setting
up and supporting special events, such as VIP visits, ceremonies, open days, teaching and career fairs, as well as numerous local departmental events and functions
■ Stewarding
and marshalling UL events such as ceremonies, open days, Science Week, Party in the Plaza and the Christmas tree lighting ceremony
■ Transporting
and delivering goods inwards materials and sorting and delivering SDS postal items and general postal packages
■ Moving
equipment, furniture and other large items around the campus
■ Actively
participating in UL emergency response procedures and being first responder for emergency calls
■ Moving
Print Room material, including A4 paper and printed matter
■ Reporting
faults to the Buildings office
■ Being
responsible for housekeeping in communal areas and teaching spaces
■ Being
responsible for the security of campus buildings and car parks
33 | Buildings and Estates Annual Report 2020
responsible for the security of internal spaces, including individual offices and restricted areas such as labs and roof access frontline support for AV equipment in a number of outlying buildings, lecturing spaces and seminar rooms
■ Providing
frontline interaction, information and support for students, including students with a disability
■ Generally
supporting members of the public by dealing with their enquiries and providing visitors with information on events and seminars
The onset of restrictions in March 2020 due to the global pandemic brought with it challenges to how we all conduct ourselves in the workplace. Our team of porters remained on campus and continued to offer support to UL students and staff. The team set up 110 classrooms and lecture theatres to comply with COVID-19 social distancing guidelines and later audited 729 teaching events (labs/tutorials) in Semester 1. October marked the end of an era within the Portering team. Tony O’Donnell (pictured above, fourth from right) brought the curtain down on a career spanning almost 30 years with B&E. Starting his time in the Main Building, Tony went on to offer support to our colleagues in the Students’ Union and, finally, the Foundation Building. While COVID-19 robbed us of the opportunity to say a proper goodbye, all his friends in green and the wider B&E family wish Tony all the best for the future and a long and happy retirement.
Buildings and Estates Annual Report 2020 | 33
Taken in 2019
Goods and Materials All goods purchased on behalf of UL are channelled in through Goods Inwards. The relevant paperwork is processed and the goods are despatched via the portering service and a delivery van to outlying campus buildings. Goods Inwards handles an average of 1,000 goods a week (counting pallets as one, even though each pallet may contain multiple items). Adhering to UL’s Return to Work Safely Protocol, the Goods Inwards team returned to campus on 10 June, alternating between them the weeks working from home or in the office. While the volume of deliveries to research labs increased and to administrative offices and teaching labs dropped, the overall volume was nearly back to normal levels by the end of the year.
34 | Buildings and Estates Annual Report 2020
The biggest change during 2020 related to the number of despatches from Goods Inwards – large numbers of laptops (after encryption) were shipped out by departments to staff working at home. Goods Inwards also arranged collections from home addresses back to UL or between home addresses, and even between countries. UL uses its Agresso financial system – known as the ‘Procure-to-Pay’ process – to manage the ordering, receipt, delivery and payment of goods. Goods Inwards is an integral part of this process: the goods are logged (received electronically) on the system, which, in turn, clears the way for payment to be authorised.
Building Architectural Maintenance B&E is responsible for the building fabric of UL’s academic buildings. This work is carried out by an external building maintenance contractor procured through the OGP tendering process. The appointed contractor maintains the building fabric (excluding mechanical and electrical installations) with an on-campus building trade team and manages third-party contractors specialised in the maintenance of the building fabric. The on-campus building maintenance team comprises one building maintenance supervisor, eight carpenters and four general operatives. Work carried out by the building maintenance team includes repairing and maintaining the building fabric, carrying out planned preventative maintenance (PPM), delivering furniture between campus buildings and carrying out minor works requested by UL departments. Between October 2019 and October 2020, in addition to general maintenance (GM) and repairs, B&E completed eight minor works to a value of €117,000 and carried out substantial COVID-related works in preparation for students returning for the Autumn semester in September. This latter work involved:
Forklift
Minor Works / Projects
■
■
■
■
Installing over 330 hand sanitiser units with related signage Erecting 260 paper towel dispensers to replace cotton towel dispensers Setting up 30 COVID pop-up banners at entrances to various buildings Setting up of 26 COVID isolation rooms in buildings around campus Erecting over 9,000 COVID-related signs around campus (e.g. room occupancy, hand-washing, directional, toilet flush, etc.)
The table and graph show the breakdown of works carried out during the period October 2019 to October 2020. Works
No. completed
% of total
GM (customer generated)
3,788
59.12%
GM (PPM generated)
857
13.38%
Minor works/projects
116
1.81%
PPM
146
2.28%
Forklift
316
4.93%
Van
1,184
18.48%
Total no. of jobs completed
6,407
100%
316
GM (Customer
3,788
Generated)
Completed Jobs
116
Van
■
1,184
857
146
GM (PPM Generated)
PPM
Buildings and Estates Annual Report 2020 | 35
Grounds Standing on 149 hectares (368 acres) in total, UL’s south bank comprises 47 hectares (116 acres) while the north bank covers 102 hectares (252 acres). The growth of the University at strategic times is guided by physical development plans, an integral part of which is an assessment of the landscape. The priority given to the landscape has resulted in a high-quality, attractive and pleasant environment, which has become a major asset to the campus. B&E is responsible for the development and upkeep of the campus landscape. The University’s in-house grounds staff and external contractors carry out these works. In addition to the landscape, the grounds staff are responsible for providing and maintaining outdoor sports facilities. These include the athletics track, tennis courts, over 12
36 | Buildings and Estates Annual Report 2020
hectares of high-quality sports fields and the newly developed McGuires sports complex. Together with the UL Sport Arena, these areas enable UL to provide excellent sport and recreational facilities to the campus community and to host high-profile sports events. As essential work continued all through the pandemic, our grounds staff were busy mowing grass, edging paths and attending to the sports pitches. They weeded and mulched shrubs and trees, trimmed hedges, planted trees and shrubs, and cleared leaves, frost and ice from paths and trails to make the campus a peaceful sanctuary where resident students and members of the local community could exercise within 5km of their home during this difficult time.
Notable Trees on Campus One of the most outstanding trees on campus is the copper beech, which is located close to the main reception on the plaza. Copper beech, also known as purple beech, is a cultivated form of common beech (although copper-coloured beech trees are also sometimes found in nature). It grows to a height of more than 40m. The bark is smooth, thin and grey, often with slight horizontal etchings. Twigs are slender and grey but not straight – their shape resembles a zigzag. Torpedo-shaped leaf buds are coppery and up to 2cm in length, with a distinctive criss-cross pattern. Some quick facts: ■ Common
name: Copper beech
■ Scientific
name: Fagus sylvatica f. purpurea
■ Family: Fagaceae ■ Flowers:
Monoecious, meaning both male and female flowers grow on the same tree. In April and May, the copper beech’s tassel-like male catkins hang from long stalks at the end of twigs, while female flowers grow in pairs, surrounded by a cup.
■ Leaves:
Deep purple in the spring, turning to a coppery hue in the autumn, oval and fringed with silky brown hairs
■ Fruits:
Once wind-pollinated, this cup becomes woody and encloses one or two reddish brown beech nuts (known as beechmast).
Ongoing Native Tree and Shrub Planting As part of our ongoing improvements to the campus landscape, we carried out a tree-planting management scheme in winter 2020. Notable work included planting: ■ Large
hornbeams (Carpinus betulus) outside the Arena building
■ Oaks (Quercus
robur) opposite the Concert Hall
■ Holm
oaks (Quercus ilex) – landscape planting on the plaza outside the climbing wall
■ Hollies
(Ilex) near Plassey House
■ Pollinator-friendly
shrub layers outside the Library
Buildings and Estates Annual Report 2020 | 37
Campus Security B&E is responsible for securing the UL campus and buildings, managing the campus car parks and directing the campus traffic at peak times. B&E aims to provide a safe and secure environment for the campus community. The campus security team comprises two senior managers, eight supervisors, and 15 full-time and 33 part-time officers. Building porter staff assist Campus Security during normal working hours by monitoring internally the academic buildings. Campus Security monitors activity externally using mobile security vehicles, a security motorbike and the campus’s CCTV system, which includes 380 CCTV cameras located throughout the campus. Outside of normal working hours, Campus Security takes overall responsibility for the security of the entire campus. Campus Security also monitors the newly installed emergency-beacon system that is strategically located around campus. The campus security control centre is located on the south bank and operates 24/7, 365 days of the year. During the outbreak of COVID-19 and the introduction of the Government’s Level 5 restrictions in March 2020, Campus Security
assisted the University to ensure compliance by restricting access onto the campus to approved essential UL staff and HSE key workers who were supporting the temporary on-campus field hospital in the UL Arena. The security operations were modified to prevent access to amenities on both the north and south banks (i.e. pitches). As COVID-19 restriction levels were reduced, Campus Security adapted to support UL policies based on government guidelines and advice. In October 2020, with the start of the new semester and the return of students to campus, Campus Security helped collect ‘proof of attendance’ from students at lectures for the purpose of contact tracing should the need for tracing arise. Campus Security also helped issue equipment to staff who were working from home due to the pandemic. As the nationwide lockdowns evolve, Campus Security continues to be flexible and adaptable to meet the security needs of the University. Below is a snapshot of security activities during the pandemic.
Essential Workers & Key Staff Accessing Campus During Lockdown. Period March -June 2020
Permission for access to University Buildings Period June - Sept (Restricted) June
March
July 789
April
142 4,252
1,695
June 5,922
6,213 4,215
5,703
August
May External 1,767 2,636 Internal
Campus Security patrols 2020
38 | Buildings and Estates Annual Report 2020
September
Administration
Emails Monthly Summary Received
Sent
4,000
3,500
Emails received
3,000
2,500
2,000
1,500
1,000
500
0 March
April
May
June
July
August
September
October
November
December
Month
Overview The year 2020 started like any other in the B&E administration office: maintenance requests were cleared and new ones opened, Relevant Contract Tax (RCT) renewals for the departments’ various contractors were processed, purchase requisitions were raised, invoices were approved for payment, uploads were made to Agresso and meetings for the year ahead were scheduled. In general, the office was getting ready to greet B&E’s first customers of 2020 face to face. However, this normal working environment was not to last, and by March 13, the Administration team had moved to working from home full time. Forty-one weeks later, the team continues to work from home. This new method of working brought its challenges, some of which we have never had to consider before.
Between 13 March and 23 December 2020, the team received 15,447 emails of enquiry. The number peaked at 247 on one day in August.
Buildings and Estates Annual Report 2020 | 39
Insurance Policies
Renewal Rates
The following insurance policies are administered by B&E on behalf of UL and specified associated bodies: Property Damage & Business Interruption, Public & Products Liability, Employers’ Liability, Professional Indemnity, Motor, Computer, Directors and Officers Liability, Personal Accident, Travel (staff and Erasmus students only), Marine Hull, Crime, Engineering, Fine Arts, Environmental Impairment Liability and Cyber Liability. In addition, a single Medical Malpractice insurance policy is held for a particular contract and a single Clinical Trials policy is held for a particular research project.
When the insurance policies were renewed in September 2019 for 2019/20, market indicators influenced the renewal rates of particular policies held by UL. The most significant changes were:
IIMG UL is a member of the IIMG (Intervarsity Insurance Management Group). The purpose of the group is to ensure that all opportunities for collaborative working are identified and evaluated in the short, medium and long term and to assist in ensuring that an effective insurance programme is in place across the six universities. The members are UL, UCC, NUI Maynooth, NUI Galway, TCD and DCU. IIMG collectively purchases Property Damage & Business Interruption, Employers’ Liability, Public & Products Liability, Professional Indemnity and Motor insurance. The OGP ran the tender competition for insurance brokers in 2019 and appointed the successful broker on behalf of IIMG in early 2020. The OGP also tendered insurance underwriting services on behalf of the IIMG in 2018, and this awarded contract will remain in place until 2022. The annual bursary from the property insurance underwriters to each IIMG member institution to spend on preventative works to protect property, as agreed with the underwriter, was available again in 2020. UL used the 2019 bursary in 2020 to upgrade a number of the older generation fire alarm panels to a version capable of operating on the ID2net protocol and installed a number of fibre optic cables between various fire alarm panels. Phase 1 of this work was supported by this bursary.
40 | Buildings and Estates Annual Report 2020
1. Property risk underwriting: Due to a ‘hard’ insurance market and insurers’ detailed approach to underwriting, property insurers automatically applied rate increases, even on premises with no claims experience, with individual rates applying to institutions with significant claims and/or unfavourable underwriting characteristics. 2. Liability claims environment: 2020 saw movement in quantity and quantum for liability claims, which is now very evident in the claims numbers and resulting insurance company actions. The performance of the general liability and motor insurance accounts has been significantly loss making. Factors shaping this deterioration include: a. 75% of Injuries Board awards relate to motor personal injury claims. b. An increasing number of employers’ liability and public liability cases are rejected and then proceed to the circuit and high courts, which increases costs. c. The number of employers’ liability claims in the lower wage occupations increased. d. Under-pricing of premiums in the past, under-reserving and the implementation of Solvency II (capital allocation per product line) are affecting insurers’ profitability. e. The cost of claims in Ireland is too high – the size of the average personal injuries award in the high and circuit courts continues to rise as we live in an increasingly litigious society.
COVID-19 COVID-19 brought unique challenges in relation to managing the UL insurance programme. For example, with buildings unoccupied, security, heating, ventilation and waste water still had to be managed and the UL Sport Arena was handed over to the HSE for use as a temporary hospital ‘step-down’ facility for patients recovering from COVID-19 who were well enough to leave hospital but still needed some nursing and therapy care. The pandemic also gave rise to the additional cost of computing equipment not just for staff working from home but for the University as a whole to support remote workers to log into the UL servers. In addition, revenue from accommodation and commercial facilities was lost, which remains an ongoing challenge for UL with its insurance underwriters.
Future Insurance Goals B&E operates in an ever-changing environment. This was never more obvious than in 2020 as we endeavoured to stay abreast of new developments within the insurance space at a time when UL strived to grow its share of regulated and unregulated clinical trials and address the increasing concern around cyber security. IIMG insurance brokers will continue to assist with arranging forums on topics of growing interest to the group.
Buildings and Estates Annual Report 2020 | 41
Challenges Finance New procedures were documented for purchase requisitions, purchase orders and online invoice approvals (typically signed by the manager in wet ink), to name just a few. Communication with Colleagues The initial difficulty was to find the best method of communicating with each other. It soon became clear that multiple emails would not work because all members of the team were receiving excessive amounts of messages and it was becoming increasingly difficult to stay on top of the influx. Like the rest of the UL community, the staff soon moved to Microsoft Teams, which proved to be the best solution for the department. The Administration team, in particular, quickly adapted to and embraced this online system of communication. Access to Buildings While the campus was shut down, many essential personnel were required to remain on campus. These included maintenance contractors, security staff and researchers who had deadlines to meet with materials that could spoil if not used within a certain timeframe. B&E administrators became the first point of contact for a new procedure to access the campus – all requests for access were processed through the buildingsmaintenance@ ul.ie email account. Each email had to be replied to and processed, with daily approval reports issued to Security. June to August became the busiest period, which, traditionally, would be when most staff take annual leave but were instead preparing for online teaching. Some days the buildings maintenance inbox volume tripled in size. Between 13 March and 23 December 2020, the Administration team received 15,447 emails of enquiry. The number peaked at 247 on one day in August.
42 | Buildings and Estates Annual Report 2020
Monthly Summary by Category 800 700 600
Requests
500 400 300 200 100 0
March
April
May
June
July
August
September
October
November
December
Month Security incl. access
RTW requests
Chair requests
Builders
Electrical
Mechanical
Reply Statistics 80
Percentage
60
40
20
0
15
30
45
60
60 - 70
120 +
Time in Minutes You respond
People respond to you
Weekly Statistics
1,000 800 600 400
Received
Dec 13
Dec 20
Nov 29
Dec 06
Nov 15
Nov 22
Nov 08
Oct 25
Nov 01
Oct 11
Oct 18
Sep 27
Oct 04
Sep 13
Sep 20
Sep 06
Aug 30
Aug 16
Aug 23
Week
Aug 09
Jul 26
Aug 02
Jul 12
Jul 19
Jul 05
Jun 21
Jun 28
Jun 14
Jun 07
May 31
May 17
May 24
May 10
Apr 26
May 03
Apr 12
Apr 19
Apr 05
Mar 29
Mar 15
0
Mar 22
200 Mar 08
Number of Messages
1,200
Sent
Buildings and Estates Annual Report 2020 | 43
Return to Work Following the establishment of the Space Management Committee, a return-towork implementation plan was developed for those for whom it was essential to return to the campus, e.g. researchers and chief technical officers charged with preparing labs for face-to-face teaching in September 2020. As noted earlier in this report, the implementation plan was adapted from the Government’s Return to Work Safely Protocol and project managed by a B&E member of staff. The plan was administered through the buildings maintenance log by the Administration team, which assisted the facility managers with the approval procedures. With 85 academic and support units making return-to-work applications, this new task represented a sharp learning curve for everybody involved.
COVID-19 Declaration and Training To enter the campus following the submission and approval of returnto-work business plans, all B&E staff underwent UL Return to Work training so that they could return to a safe working environment, no matter how short the visit. The Administration team commenced a rota of weekly visits to the campus to issue items such as keys and parking permits to B&E’s customers.
Lead Worker Representatives B&E appointed COVID-19 lead worker representatives for each discipline. Those designated staff members along with B&E staff then underwent COVID-19 training.
Provision of PPE B&E was tasked with ordering and distributing PPE equipment to those researchers and essential staff returning to work on campus. All the requests for PPE came through the Administration team.
44 | Buildings and Estates Annual Report 2020
COVID-19 Expenditure Tracking B&E was assigned the duty of tracking COVID-19-related expenditure around PPE, cleaning, ventilation and security with the goal of facilitating researchers and essential staff to return to work safely. Government guidance documents were constantly changing, and the team had to react in a prompt but considered way.
Remote Working When it became clear that UL staff would not be returning to campus anytime soon, the University introduced a remote working scheme and published a homeworking equipment policy to facilitate staff to work from home. Under the scheme, staff could apply to be issued with a monitor, keyboard and mouse, docking station and chair. The initiative was embraced by staff; the initial requests were managed by the Human Resources Division (HR) and the equipment was ordered by ITD and B&E. In conjunction with its security contractor, B&E managed the distribution of the equipment. The Administration team provided weekly updates on requests to the Space Management Committee through the Return to Work Project Manager. In excess of 2,000 items of homeworking equipment were distributed to UL staff. Remote working presented staff with the new challenge of being able to shut down the PC at 5pm; some staff reported logging on late at night to respond to the non-stop flow of emails. UL has since promoted a policy of not sending emails outside of 9am to 5pm, or at least not expecting a response outside of office hours unless one is working flexible hours to facilitate home schooling, caring responsibilities, illness or managing family life with multiple members of the household working from home.
588
Keyboards & Mice
525
Monitors
570
Chairs
475
Docking Stations
Buildings and Estates Annual Report 2020 | 45
Positive Change and Opportunities For those members of staff who normally travel well over an hour to and from the campus every day, the end of commuting for those working from home was surely the most significant positive change during 2020. Many pandemic-related remote workers discovered that working from home gave them time in their day to take a walk before work and to exercise good mental health practices, such as mindfulness. HR continues to provide many supports for a positive homeworking environment, such as weekly skills workshops. A HR survey during 2020 found that 70% of staff rated remote working positively. While the pandemic provided parents with the opportunity to home-school their children and spend more time playing with the smaller children, this also brought challenges, not least of which was the rising demand for highspeed broadband. However, during the 2km and 5km travel restrictions, the pandemic presented people with opportunities to reconnect with their local natural environment and enjoy the amenities they may otherwise take for granted. As previously stated, the UL campus provided the wider local community with a beautiful landscape to enjoy as a welcome distraction from the worries of COVID-19.
46 | Buildings and Estates Annual Report 2020
Projects Buildings and Estates Annual Report 2020 | 47
Small Capital Projects Essential building upgrade projects are carried out annually by B&E and are classified as small capital projects, i.e. under the EU procurement value threshold. The types of project carried out can be categorised as health and safety, energy and money saving, building reorganisation and refurbishment or customer project requests. The tables and photographs to follow show some sample projects completed and underway in 2020.
Sample small projects completed in 2020 Building
Project title
Description of works
Grounds
Main plaza paving
Construction of a universal access path across sections of the plaza
Grounds
Main avenue resurfacing
Resurfacing of the main avenue from flag poles to roundabout
Main Building
Registry
Reconfiguration of the layout of Registry area in Block E
Languages
Language
Refurbishment of the Language Centre offices and teaching rooms
KBS/Schuman
KBS/Schuman
Reconfiguration of office spaces to house additional staff
Arena
Track changing room upgrades
Refurbishment of the changing rooms
Health Sciences
HSG032
Reconfiguration of space into administration office
Lonsdale
Compressors
Replacement of compressors
Crèche
New gate/path
Creation of new path and gate at side of building
Small projects underway in 2020 Building
Project title
Description of works
Various
Fire assessment works
Remedial works to specific buildings following fire risk assessments
Student Centre
Stables archway
Repairs to roof
Grounds
Watermain
Replacement of a section of old asbestos watermain along the main avenue
Grounds
Basketball hoops
Installation of a number of hoops in student villages
Boathouse
Pontoon
Replacement of damaged pontoon
City Campus
Fab Lab
Relocation of the Fab Lab from Ruthland Street to City Campus
48 | Buildings and Estates Annual Report 2020
Buildings and Estates Annual Report 2020 | 49
Large Capital Projects Completed
Details on recently completed capital projects are given below.
Climbing Wall Size – 250m2 Completion – October 2020 Architects – Hugh Kelly Architects
50 | Buildings and Estates Annual Report 2020
Confirm (Park Point Unit 2) Size – 1,327m2 Completion – March 2020 Architects – KOBW
Buildings and Estates Annual Report 2020 | 51
External Lift – Foundation Building Completion – November 2020 Architects – KOBW
52 | Buildings and Estates Annual Report 2020
Capital Project Underway
New Student Life Building Size – 3,528m2 Completion – Summer 2022 Architects – Carr Cotter & Naessens
Buildings and Estates Annual Report 2020 | 53
Future Capital Project
City Campus (former Dunnes Stores)
54 | Buildings and Estates Annual Report 2020
HSE Intermediate Care Facility
HSE Intermediate Care Facility at UL Sport Arena In early March 2020, then UL President Dr Des Fitzgerald reached out to the UL Hospitals Group to offer the use of the UL Sport Arena as a field hospital. The B&E Director offered the services of B&E’s core contractor teams to realise this goal. Following on-site meetings on 31 March and 1 April with representatives of HSE Estates West Team and UHL staff, specifications, drawings and an Order of Magnitude were quickly produced, and work commenced immediately on getting the facility up and running in a short period of time.
Buildings and Estates Annual Report 2020 | 55
Credit must be given to the members of the B&E team for their incredible work in getting this initiative over the line. Thanks to the following groups for their support in the works: ■ KOBW Architects – ■ Maurice
room layouts and details
Johnson & Partners – fire consultants
■ Sensori FM
– mechanical and building services
■ Kirby
Group – electrical services
■ ASM
Group – health & safety (construction)
■ Drombanna Engineering ■ Bidvest
– external ground works
Noonan – cleaning and security
■ JW
Flooring – temporary flooring
■ UL
Sport Arena maintenance team – on-site support
56 | Buildings and Estates Annual Report 2020
Some of the key works required to get the facility up and running included: ■ Dividers
installed in showers
■ Construction of
25m pools
■ Squad
temporary walls to separate the changing rooms from the 50m and
changing room fitted out as a staff canteen
■ Deep
clean of high-level structural steelwork and services (e.g. air-handling ducts) in Sports Hall
■ New
floor covering laid over existing sports hall floor
■ Construction
of temporary walls with sinks along sections of the sports hall
■ Construction
of temporary external wall and double doors to the outside instead of roller
shutter door
■ Creation ■ Oxygen
of temporary external bin storage area
tank concrete base laid and fenced
■ Store
areas in the sports hall subdivided into clean utility, dirty utility, clean linen, dirty linen and pantry rooms; new partitions, ceilings and alto sheeting on walls added
■ New
dirty utility room built in one corner of the hall
■ Existing
classroom subdivided into a pharmacy; window openings closed up for security
■ Existing
first aid room converted into a dirty utility
■ Offices and ■ External
reception areas to be used by HSE staff cleared out
generator hired to provide backup in the event of power failure
■ Extensive
additional power sockets, water and waste connections and extraction systems installed to service the new rooms
■ Entire
facility deep-cleaned to a high standard
■ External
fenced-off seating area created for patients
Work progressed quickly, and the facility was handed over to the HSE on 15 May for it to be fitted out with partitions, beds and equipment. The facility was officially opened on 8 June and started to receive its first patients straight away. The Intermediate Care Facility wound down operations at the start of November 2020 and was handed back to UL by the HSE at the end of November. The B&E team then commenced work on returning the facility to its original state.
Buildings and Estates Annual Report 2020 | 57
Tierney Building – Research Lab At the end of April 2020, the Office of the Vice President Research requested B&E to produce costings and a plan for reconfiguring a laboratory in the Tierney Building to a high-specification research laboratory. The lab was required to be operational by 25 May 2020. Following the production of initial costings, approval was given on 1 May for the work to proceed. The internal work within the lab was completed on Friday 15 May, which enabled work on setting up the area to be carried out from Monday 18 May. In accordance with the schedule, the external structures were completed and weatherproofed by Friday 22 May. The works involved in the project included: ■ Whiterock fitted
to walls
■ Modifications
to ductwork within the room
■ Replacement
of filters to AHUs (air-handling units) and fume cupboards
■ Bio
safety cabinet relocated and fitted
■ External ■ All
changing area with enclosed link to lab erected
existing equipment recommissioned
58 | Buildings and Estates Annual Report 2020
HEA Devolved Grant 2020 In August 2020, the HEA announced a devolved capital grant allocation of €25 million to the higher education sector. The grant is intended to help institutions address their most urgent infrastructural requirements for the academic year 2020/21, including maintenance and refurbishment of facilities; replacement and upgrade of equipment, including ICT equipment; and small-scale building works in the context of the delivery of strategic goals. UL was awarded an allocation of €2,165,000 from the grant. B&E received €1.144 million of this. Some of the works being carried out under the devolved grant include: ■
Fall prevention/edge protection improvements
■
Hockey pitch lighting distribution boards
■
Lift installation improvements
■
Roof leak repairs
■
Emergency lighting and fire alarm upgrades
■
Building security upgrades
■
Main electrical protective earthing upgrades
■
Improved disability access
Buildings and Estates Annual Report 2020 | 59
60 | Buildings and Estates Annual Report 2020
Health and Safety
The onset of COVID-19 in early 2020 gave rise to new challenges and ways of working for all of us. The whole area of safety, health and welfare at work came into sharper focus in March 2020 than at any other time in the past. After the initial lockdown, we saw a gradual transition to a ‘new normal’ with the introduction of COVID-19 inductions, health declarations, lead worker representatives and response plans. B&E worked closely with its direct staff and service providers to ensure the requirements of the Government’s Return to Work Safely Protocol were implemented as we continued to maintain the campus throughout the pandemic. Below are some of the headline health and safety statistics for 2020.
Area
Total
Lost time accidents arising as a result of work activities (+3 days lost)
0
Workdays lost as a result of accident/incident or near miss
1
No. of different service providers (contractors) used by B&E to undertake works on campus
120
No. of B&E service provider inductions completed
555
Buildings and Estates Annual Report 2020 | 61
Green Campus
UI GreenMetric Ranking 2020 UL came 17th out of 912 entrant institutions across 84 countries in the 2020 UI GreenMetric World University Ranking. The table below shows UL’s performance in the scheme from 2012 to 2020 compared to six of the other seven Irish universities (NUIG did not partake in the scheme).
DCU
2012
2013
2014
2015
2016
2017
2018
2019
2020
80
46
53
58
27
15
12
12
15
93
190
128
130
97
154
NUIM TCD
94
107
TUD*
198
157
193
274
229
59
UCC
3
2
2
4
12
9
9
9
9
22
24
20
20
17
UCD UL
111 58
29
11
16
Note: A blank cell means the university in question did not partake in the scheme that year. *Technological University Dublin – was Dublin Institute of Technology until January 2019 UL’s ranking from 2012 to 2020 in the context of the total number of entrants globally is given below.
2012
2013
2014
2015
2016
2017
2018
2019
2020
UL
58
29
11
16
22
24
20
20
17
Total no. of entrants
215
301
360
407
516
619
719
780
912
UL in top percentile
27%
10%
3%
4%
4%
4%
3%
3%
2%
UL’s ranking in the suburban category from 2014 to 2020 in the context of the total number of global entrants is given below. 2014
2015
2016
2017
2018
2019
2020
UL’s suburban ranking
3
2
7
6
6
6
5
Total no. of entrants
95
105
126
151
181
183
222
62 | Buildings and Estates Annual Report 2020
Environmental Update 1. Green Campus reaccreditation for 2020 confirmed 2. Report prepared for Governing Authority Subcommittee on Traffic, Transport and Smarter Travel, which centred on sustainable transport options to and from UL and traffic alleviation measures 3. Two submissions made for grant funding to the Higher Education Energy Efficiency and Decarbonisation Pathfinder Programme 4. HEA higher education institution decarbonisation study on selected UL buildings completed 5. Department of Communications, Climate Action and Environment survey completed on all UL buildings to inform the upgrade of public sector buildings to B BER by 2030 6. Commissioning of OPW’s energy monitoring and targeting system completed 7. B&E now reporting to the Campus and Infrastructure Committee (chaired by the President) on the activities of the Green Campus Committee, Environmental Committee and Environmental Society 8. Technical Services team working on water stewardship accreditation 9. Continued attendance at Environmental Association for Universities and Colleges (EAUC) and Irish Universities Association (IUA) Sustainability Working Group meetings
Buildings and Estates Annual Report 2020 | 63
Quality
The Buildings and Estates Department is a customer-driven organisation that strives to provide excellence in the services it delivers. We believe that the campus community is entitled to a high standard of quality from us. The department’s quality ethos is
“To sustain and seek to continually improve the quality of all services that we provide to the campus community”
64 | Buildings and Estates Annual Report 2020
Key Business Processes The figure below sets out the key B&E service procedures (on the right) that are used to provide and maintain outstanding physical facilities. The associated quality management system (QMS) procedures are shown on the left. The supporting procedures that underpin these key procedures are reviewed, discussed and challenged in accordance with the schedule set out in the department’s quality calendar.
Quarterly Business Review
Quality Manual
Quality Policy
QMS PROCEDURES
KEY SERVICE PROCEDURES
Documentation Management
Management of Capital Projects
Department Objectives and Measures
Maintenance and Minor Works
Departmental / Management Communication
Measurement and Continual Improvement
Space Management Cleaning Management
Employee Satisfaction
Waste Management
Training and Continuing Professional Development
Portering Operations
Continual Improvement and Customer Satisfaction
Customer Interaction and Feedback
Goods Inwards and Distribution Furniture Provision Insurance
Customer Feedback and Customer Focus Group
Security
Self-Assessment
Key Control
Process Structure and Interaction
Parking Grounds Maintenance Energy and Water Customer Satisfaction
Signage
Buildings and Estates Annual Report 2020 | 65
Memberships B&E (and hence UL) is a member of the following associations/organisations/groups: ■ Association
of University Directors of Estates (AUDE) (B&E was its first member outside of
■ Association
of University Chief Security Officers (AUCSO)
the UK)
■ Irish
Association of University Directors of Estates
■ Irish
Universities Association Sustainability Working Group
■ University
Sector Energy Environment Economy Group (E9)
■ Environmental ■ Insurance
Intervarsity Management Group
■ Chartered ■ Golf
Institute of Engineers
Course Superintendents Association of Ireland
■ Project
Management Institute
■ Mid-West ■ EPA
Association of Universities and Colleges Office Bearers Group
Project Management Networking Group
(Environmental Protection Agency) Large Water Users Community of Practice
■ OGP
(Office of Government Procurement) Category Councils
■ Corporate
Enabling of Clinical Research
66 | Buildings and Estates Annual Report 2020
Quality Team Although B&E has a quality leader, the department does not have a dedicated quality team as such. All core members of staff are considered members of the quality team, and quality features as a permanent agenda item at multiple departmental meetings (e.g. Quality Business Review, Coordination). While a representative subgroup of B&E’s quality team was tasked with compiling the department’s selfassessment report (SAR) for its 2020 external quality review, all members of staff were involved in the selfassessment exercise to some extent. In addition, the wider quality team members were encouraged to provide feedback on a draft version of the SAR prior to delivering the final report to the Quality Support Unit for circulation to the external quality review group.
Quality Improvement Plan B&E maintains a quality improvement plan (QIP). Contained within the QIP are action items arising from multiple sources, including customer focus groups, staff and student surveys, Quarterly Business Review meetings and self-assessments. The action items span a wide range of issues, including environmental improvements, facilities improvements, outdoor events, maintenance and minor works and improvements to the QMS itself. Specific action items are overseen by the relevant forum, such as the Operations, M&E Team and Minor Works meetings. The overall implementation of the QIP is monitored at the Quarterly Business Review, and the efficacy of specific quality improvement action items is measured using existing feedback channels.
2020 External Quality Review The Universities Act (1997) obliges universities in Ireland to formally establish quality assurance procedures aimed at improving the quality of education and related services. Furthermore, the Act stipulates that each university’s quality assurance procedures must be evaluated at regular intervals (but not less frequently than once every 10 years). In support of the requirements of the Act, UL published a standard framework for support departments on the implementation of a QMS.
In preparation for the March quality review, B&E appointed a new quality team leader, established a core quality team, undertook focus groups (among both staff and students), introduced new and more effective mechanisms for collecting and acting upon feedback, reviewed its quality manual and associated procedures in their entirety, updated its QIP and completed a SAR for the quality review group (QRG). In its post-review report to B&E, the QRG made this comment in relation to the SAR: “We wish to record our appreciation of the excellence of the SAR and of the effort that clearly went into preparing it.” The QRG found the SAR “to be a very comprehensive and professional document, showing evidence of commitment to the UL quality process over a long period and a keen awareness of the need to monitor and account for the division’s performance.” The report later stated that “B&E provides an excellent operational service within its resources”. The QRG other things: ■
■
■
commended
B&E
for,
amongst
The delivery of the B&E strategic plan, Building a Sustainable Future, 2017-2021, and the subsequent annual reports demonstrating progress against this plan. The division’s commitment to and delivery of the environmental sustainability agenda and Green Campus and its active collaboration with the UL Environmental Society. The clear recognition by B&E of risks posed by specific resource gaps for the division’s capability and capacity to support the University’s strategic plan.
B&E received 23 recommendations from the QRG – 10 at Level 1 and 13 at Level 2. Of the 23 recommendations, B&E accepted 22 in full or in part; one recommendation was rejected. The QRG’s recommendations can be largely broken down into three thematic areas: (i) the strategy for developing and managing the estate; (ii) additional human resources; and (iii) communication. The Buildings & Estates QRG report was approved by the Quality Committee on 28 May 2020 for publication.
B&E was an early adopter of a QMS, and for this reason, the department’s most recent external quality review (March 2020) was the third of its kind. The review took place just after the worst of the flooding and before the onset of the COVID-19 pandemic in Ireland. The earlier reviews focused primarily on ensuring that the department had adopted a fit-forpurpose QMS. While the March 2020 review also evaluated the B&E QMS, the review placed a greater emphasis on strategic alignment, organisational structure, management and governance.
Buildings and Estates Annual Report 2020 | 67
Our Customer Charter Maintenance
Us
Maintenance
You
> Promptly acknowledge receipt of your request > Respond to your urgent requests immediately > Advise you immediately when your request has been completed and within five working days when your request has not been completed
> Send an email to Buildingsmaintenance@ul.ie, including location room number > Read emails from BENotices > Give at least 24 hours notice for collection/ delivery requests
Cleaning
Cleaning
> Clean buildings as per Service Level Agreement with cleaning company > Collect recycling paper from offices weekly > Provide janitorial service during normal working hours for toilets and emergency clean-up of spillages > Carry out deep clean of new buildings & vacant offices > Clean building glazing once a year > Provide feminine hygiene service in female toilets
> Report any floor spillages that could result in an accident > Segregate paper and general waste > Dispose of general waste in corridor waste bins > Report toilets that require servicing (including blockages) to Buildingsmaintenance@ul.ie
Security
Security
> Provide a safe and secure environment on campus > Monitor vehicle parking to ensure compliance with UL parking policy > Be responsible for traffic management > Be responsible for security of campus building stock > Respond to incidents/accidents and contact emergency services when required
> Park in official car park spaces > Follow instructions issued by security officers > Report any suspicious behaviour by individuals or vehicle occupants > Inform campus security of any proposed events taking place on campus
Space Management & Office Moves
Space Management & Office Moves
> Promptly acknowledge receipt of your request > Respond to the changing requirements of UL’s teaching and research priorities > Allocate space in the best interests of UL according to space allocation protocol > Provide you with a suitable single/shared office or workstation > Endeavour to provide everyone with sufficient space to enable them to carry out their function > Discuss with you your space requirements or any issue about your office move
> Outline your space requirements to your faculty manager or head of department > Make your request as clear as possible > Ensure your department’s existing space is fully utilised before seeking additional space > Adhere to UL’s space allocation protocol and understand that space is a valuable and finite resource > Relinquish any unused or under-utilised space
Landscaping & Grounds
Landscaping & Grounds
> Manage the maintenance and development of the campus landscape to provide an attractive and pleasing environment for the campus and wider community in support of UL’s mission > Manage and maintain the field sports facilities > Keep the campus clean
> Enjoy and respect the parkland facilities and riverside setting > Report any safety or hazard issues to Buildingsmaintenance@ul.ie
68 | Buildings and Estates Annual Report 2020
Minor Works
Us
The same as maintenance, above, with the addition of the following: > If your request is on hold because we’re awaiting information from you, we’ll send you a reminder after 10 working days > If you don’t receive a quotation within five working days, we’ll advise you of the status of the request
Minor Works
You
> Complete a Minor Works form > Provide a detailed description of the works
Porter Service
Porter Service
> Promptly acknowledge receipt of your request > Set up and support special events > Take responsibility for housekeeping in communal areas and teaching spaces > Provide security in campus buildings and car parks (in conjunction with Campus Security) > Provide frontline support for AV equipment in a number of outlying buildings, lecturing spaces and seminar rooms > Participate in UL emergency response procedures, including fire alarms, major incidences and medical emergency calls > Provide information about events and seminars to visitors > Deliver goods inwards material, sort and deliver SDS postal items and sort and deliver general postal packages
> Email requests to Buildingsmaintenance@ul.ie > Give adequate notice of events that you host > Report suspicious activity to Buildings and Estates or directly to Campus Security > Give advance notice of the need to relocate material within buildings > Leave teaching spaces in the correct setup for the next class (leave them as you would like to find them) > Include your room number on orders that are being delivered to UL
Insurance
Insurance
> > > > > >
> > > > > >
Promptly acknowledge receipt of your request Provide evidence of UL insurance cover Advise on existing UL policies Liaise with UL insurance brokers on your behalf Update Asset Register with new plant/equipment Lodge settlement cheques to your dept. cost code > Seek additional cover on your behalf (additional charge may apply) > Submit claims on your behalf > Assist with incident investigations
> > > > >
Send an email to cliona.donnellan@ul.ie Make your request as clear as possible Advise of incidents/accidents immediately Submit claim forms promptly Pay additional bespoke premiums promptly Provide requested additional details promptly Advise Buildings and Estates of new plant/ equipment in your department Complete questionnaire/claim forms comprehensively and provide supporting docs Provide dept. cost code for settlement Advise insurance administrator of planned sabbaticals at least one month in advance of travel Ensure your contractors/visiting groups have current public and employers’ liability insurances to levels of €6.5m and €13m respectively
Buildings and Estates Annual Report 2020 | 69
Recurrent Expenditure The Buildings and Estates recurrent maintenance and operations expenditure for the financial year 2019/2020 was €15,441,942. A breakdown of this expenditure is shown in the various graphs. Much of the annual recurrent budget goes on energy costs and labour costs for maintenance, cleaning and security contractors. The department continues its drive for continual improvement and adopts better work practices, where possible, to ensure all its resources are managed prudently. This is very evident in the financial data for the last 10 years, where the spend per square metre (sqm) of building footprint has remained static while over the same period, the total building footprint has grown by 34%.
Financial year
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
2017/18
2018/2019
2019/20
Recurrent spend (.000)
€12,213
€12,280
€12,621
€12,649
€12,900
€13,570
€14,053
€14,734
€15,908
€15,442
Total gross floor area sqm
121,488
123,305
127,600
127,600
127,600
141,815
141,815
149,135
154,297
154,297
Recurrent spend per sqm
€101
€100
€99
€99
€101
€96
€99
€99
€103
€100
Grounds Maintenance
Water 2%
3%
Other
6%
M&E maintenance
Gas & Electricity
11%
14%
Security
70 | Buildings and Estates Annual Report 2020
16%
Salaries
18%
Building Maintenance
14%
Cleaning
10%
Waste Disposal 4%
Insurance
1%
Recurrent Spend per Year and per Sqm
160,000
120 115
150,000
110 105
130,000
100 95
120,000
Euro Per SQM
SQM
140,000
90 110,000
85
100,000
80 2010/11
2011/12
2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 Year
Total GFA Sqm
B&E Recurrent Spend per sqm
Total Spend and Recurrent Spend per Sqm 120
15,000
115 110 10,000
100 95 5,000
Euro / SQM
Euro ,000
105
90 85
0
80 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 Year
Total Spend
B&E Recurrent Spend per sqm
Buildings and Estates Annual Report 2020 | 71
Organogram Director Buildings & Estates Robert Reidy
Energy Manager Chris Fogarty Engineering Services Technical Services Manager Tony Considine
Goods Inwards Technician Jim O’Callaghan
Personal Assistant Marian Hartigan
Space Manager Brian Considine Buildings Officer Pat McMahon
Grounds Manager John O’Sullivan
Facilities Managers (3) Gerald Hallinan Sean Collins Eilis Gaffney
72 | Buildings and Estates Annual Report 2020
Projects ProjectsManager Officer Ger Manning
Projects Manager Ian O’Donoghue
Administration & Insurance Manager Cliona Donnellan
Senior Administrator Procurement / Compliance Jane Murphy
Mechanical & Electrical Maninenance Contractors
Technical Services Engineer Eric Crowe
Goods Inwards Operative Mike Clifford
Grounds Foreman (2) Denis Walsh Noel Copse
Grounds Staff (5)
Grounds Maintenance Contractors
Services Supervisor (Acting) James McDonnell
Senior Porter (1) Tony O’Sullivan
Porters (12)
Security Contractors
Buildings Maintenance Contractors
Cleaning Contractors
Administration Kelly O’Connor
Safety Co-ordinator Eoin Meagher (PT)
Administration Karen Fraher Carmel Kirwan Amanda Lee
Buildings and Estates Annual Report 2020 | 73
Our Team The 46 members of B&E staff listed below are employed directly by UL. Director
R. Reidy
Technical Services Manager
T. Considine
Buildings Officer
P. McMahon
Projects Officer
G. Manning
Projects Manager
I. O’Donoghue
Facilities Managers
G. Hallinan, E. Gaffney, S. Collins
Energy Manager
C. Fogarty
Technical Services Engineer
E. Crowe
Administration Manager
C. Donnellan
Space Manager
B. Considine
Senior Administrator – Procurement and Compliance
J. Murphy
Administrators/PA Support
K. Fraher, K. O’Connor, C. Kirwan, A. Lee, M. Hartigan
Goods Inward Technician
J. O’Callaghan
Safety Co-ordinator
E. Meagher (part-time)
Goods Inward Operative
M. Clifford
Resident Engineer
O. Downes
General Services Supervisor
D. Corrigan, J. McDonnell (acting)
Senior Porter Attendants
T. O’Sullivan
Porters
T. O’Donnell, D. Madden, A. Beville, D. Hogan, J. Mulligan, N. McCarthy, M. Collins, S. Kett, R. Cosgrave, J. Kett, B. McInerney
Grounds Manager
J. O’Sullivan
Grounds Forepersons
D. Walsh, N. Copse
Grounds Staff
M. Morrissey, P. McGrath, E. Barry, N. Noonan, M. O’Kelly, V. Fraher, D. Meehan
Student Co-op Placement (Smarter Travel)
74 | Buildings and Estates Annual Report 2020
E. Hogan
Buildings and Estates Annual Report 2020 | 75
Buildings and Estates
061-202001/2006 buildingsmaintenance@ul.ie AM-065, Main Building, University of Limerick