Project Management Report MGT 60403 | Taylor's University Lakeside Campus

Page 1

LEGACY ART CENTER, MUAR Project Management Report | MGT60403

YEE MAE YUEN 0328561 TUTOR: AR. ALIA AHAMAD


contents

1.0 project information

1. Project Information 1.1 Project Introduction 1.2 Project Brief 1.3 Site Introduction

1.1 PROJECT INFORMATION

2. Stakeholders 2.1 Key stakeholder 2.2 External Stakeholders 2.3 Internal Stakeholders

The Muar Kun Seng Keng Lion Dance Association has over 80 national titles and 70 international titles. Despite their extraordinary achievement, the locals of Muar do not relate personally to the Lion Dance scene. The Lion Dance: Art and Cultural center will serve as Muar City’s cultural landmark and public activity center. The cultural center aims to provide a sense of appreciation to the town’s culture through innovation, where the locals experience the culture of the lion dance through thematic spaces.

1.2 PROJECT BRIEF

4. Design Analysis 4.1 Design Suitability 4.2 Design Visualisation 4.3 Project Viability

• • • • • • •

5. Project Procurement & Resource Planning

1.3 SITE INTRODUCTION

6. Risk Analysis & Maintenance Strategy 6.1 Maintenance Strategy: Program Maintenance 6.2 Maintenance Strategy: Building & Site Maintenance 6.3 Risk analysis (with Mitigation Plan)

The site is located in Bandar Maharani, the royal town of Muar. The town is strategically located along the Muar River, which contributes to the rich history of the site. Located along Jalan Maharani, the site faces the main road which is busy throughout the day. The significance of its surrounding context consists of a bus terminal, chinese shophouses with traditional trades such as dried seafood, traditional Chinese medicine etc, Astaka shopping center, a primary chinese school and Sungai Bentayan.

3. Site Analysis 3.1 SWOT Analysis 3.2 PESTLE Analysis

7. Project Success Criteria 8. Work Breakdown Structure (WBS) 9. Gantt Chart

Gross floor area of 2000 sqm (21527.82 sqft) excluding basement with minimum 40% of spaces dedicated for the lion dance programmes A total of 4 levels including walkable roof top garden The scheme includes a proper drop off zone, performing spaces, costume making workshop and training space at empty lots. The Adami shophouses shell is to be maintained. Renovation to be made at the roof to support the platforms housing the Garden of Spices Lanscaping with planter boxes (minimum height 600mm excluding plant) to be placed along the edges of the platforms At least 20 car parking lots with 2 handicap car parking and 2 service car parking must be included. Minimum 75% of the required parking slots must be underground (basement) Must be compliant to Muar’s local city planning or local guidelines and requirements


1

3

Sungai Bentay

an

3

2

3

3

4

Figure 1: Site plan, 1:750

Legend 1. Muar bus terminal 2. Chinese shophouses 3. Chinese temple 4. SJK (C) Chung Hwa


2.0 stakeholders 2.1 KEY STAKEHOLDER

EXTERNAL STAKEHOLDER (PUBLIC) The users of the site are considered external stakeholders with low impact to the project. However, the project should be relevant and designed accordingly to them as they are the end user of the building. The external stakeholders (public) are identified are bus transit passengers, aged locals and orimary school students.

2.3 INTERNAL STAKEHOLDERS

Figure 2: Muar Kun Seng Keng Lion Dance troupe logo Muar Kun Seng Keng Lion Dance is a registered cultural organisation with branches in different states across Malaysia such as Kedah, Kuala Lumpur, Perak, Sarawak and Negeri Sembilan. Objectives: • To develop the spirit of the art of the Dragon and Lion Dance • To encourage fellowship within the Dragon and Lion Dance community • To promote the culture of Dragon and Lion Dance to a global stage • To promote the principle of the International Alliance of Muar Kun Seng Keng

2.2 EXTERNAL STAKEHOLDER (LOCAL AUTHORITIES)

Figure 3: Majlis Perbandaran Muar (MPM) logo Majlis Perbandaran Muar (MPM) was established in 1952 as Bandar Maharani Town Council (within Local Authorities Ordinance 1973). Once known as the Muar Selatan District Council (within the Local Government Act, temporary provisions 1973), which encompasses 17 sub-districts which until now is occupied by approximately 230, 000 residents of all ethnicity. MPM aims to achieve progress, peace and prosperity for Muar town through public programmes and law enforcement.

The internal stakeholders of this project are the team members of the project team themselves which consists of both consultants and contractors. Internal stakeholders in this project are groups or parties within the project who will be directly affected by the project. They hold a high liability in the case any discrepancies occur.


3.0 site analysis 3.1 SWOT ANALYSIS STRENGTHS

WEAKNESSES

• High vehicular circulation around the site • High pedestrian density at the bus terminal • Pedestrian bridge links directly to the site

• Pedestrian bridge visually disrupts the view of the building • Users from site context engage minimally with site • Heavy vehicular flow along Jalan Maharani produces a barrier between the bus terminal and the site

OPPORTUNITIES

THREATS

• Pedestrian bridge acts as magnet to pull bus • Commercialisation of the site context transit passengers to the site threatens the unique characteristic of the site • Primary school students as one of target user (engaging with the youth of Muar) • Heavy vehicular circulation on Jalan Maharani and Jalan Abdullah provides double frontages for the site

3.2 PESTLE ANALYSIS POLITICS

ECONOMY

SOCIAL

TECHNOLOGY

LEGAL

ENVIRONMENT

The Sultan of Johor constantly works with the local authorities to organise festivals and events which encourages public engagement. These events do occur within the site context.

The old Chinese shophouses consists of traditional trades which are threatened due to commercialisation and tourism.

The site consists of user groups from different generations. The age gap and lack of intersecting nodes reduces chances of engagement with each other.

Building Information Modelling (BIM) is used to reduce construction time. With reference to the Green Building Index (GBI), passive design strategies are implemented during Schematic Design stage.

The site should adhere to the local building requirements. At site, the setback is about 8 meters from the site boundary and existing shophouses. The building height is limited to a maximum of 5 levels.

Sungai Bentayan is currently canalised to control flooding around the site. However, the canalisation of the river reduces its significance as a natural water source and habitat to certain living beings.


4.0 design analysis

1. Massing produced according to site setbacks. Existing side 2. Void placed adjacent to Sg. Bentayan to emphasise a public 3. The massing is elevated to a generous height of 6 metres to alley and back alley is maintained. For emphasis on sungai ben- realm adjacent to the river. Greenery and a pocket garden is create a celebrated public space along ground floor while intayan while maintaining walkability of site located here creasing permeability through the building

4. Spaces are created according to hierarchy (size) and function. 5. Platforms are placed to create connections through each space. 6. Bridge redesigned and extended to the school. Create enThe width of spaces follow the existing grid lines of the site The platforms act as a circulation route and outdoor space trance at first floor for pedestrians.


Design Strategies

Public to private

Visual attraction

Freeing up ground floor

Connecting the youth

Humanistic facade

Axis of emphasis

Celebrating public realm

Positive outdoor space

Corner facades

Multiple entry points

Five foot walkway

Modular grids of site

Adaptive reuse

Cascading frontage

Moving like the lion


4.0 design analysis Spatial Planning

Ground floor plan NTS

First floor plan NTS

Second floor plan NTS

Third floor plan NTS


4.2 DESIGN VISUALISATION

Figure 4: Visual renders of the cultural center


4.3 PROJECT VIABILITY

Third floor Second floor

PROJECT OBJECTIVES Full completion of the project within the acquired budget while ensuring optimum satisfaction from the client. A satisfactory response from the end users regarding its functional performance is also targeted. Throughout the project, risks and complications met are to be resolved in the best way possible with minimum effect to the quality of the project. PROJECT GOALS Short term goals Forming and maintaining an efficient and fully operational project team to execute the tasks of the project. The team should communicate well among each other and the project should be executed within allocated budget of approximately RM 24 million. Long term goals To keep the essence of the lion dance culture in Muar by reflecting it in its spaces and built form. The cultural center should serve to educate the future generation and the tourists of the lion dance culture in Muar. Basement

First floor Space

GFA (sqft)

Carpark

13409.10

Ground floor

Space

GFA (sqft)

Communal kitchen

1417.09

Tumpang cafe

2186.89

Staff quarters

797.89

Communal bathroom

356.62

4768.85

Public bathroom

358.38

199.13

Management office

646.49

Pop-up stores

1060.25

961.29

Children’s art studio

846.94

Lion Dance costume making space Projection room

95.88

Clay making space

199.13

Open public plaza

6170.64

Outdoor cinema

922.43

TOTAL

13,244.94

Outdoor seating area

495.81

M & E room

148.70

Circulation spaces

4,885.98

Platforms TOTAL

Space

GFA (sqft)

Shophouses Security office

Space

GFA (sqft)

Leisure space

279.86

TOTAL

279.86

Space

GFA (sqft)

Lion Dance costume making work studio

406.06

Storage room

102.48

Lion Dance training space

1249.23

Space

GFA (sqft)

Platforms

7,927.83

Roof Garden

1,615.04

TOTAL

9,685.60

TOTAL

1,615.04

Gross building cost Basement 13,409.10 sqft x RM 250 Ground Floor 13,244.94 x RM 200 First Floor 15,571.45 x RM 200 Second Floor 9,685.60 x RM 200 Third Floor 279.86 x RM 200 Fourth Floor 1,615.04 x RM 200 Total building cost Other construction cost Landscaping Flat roof system Rainwater harvesting system Total construction cost Direct expenses cost Construction supervision fee Consultant Fees (15% Building Cost) Labour cost (150 workers, RM2500/mth, 24 mths) Total direct expenses cost

Fourth Floor

= RM 3,352,275 = RM 2,648,988 = RM 3,114,290 = RM 1,937,120 = RM 55,972 = RM 323,008 = RM 11,431,653 = RM 100,000 = RM 50,000 = RM 10,000 = RM 160,000 = RM 80,000 = RM 1,714,747.95 = RM 9,000,000 = RM 10,794,747.95

2298.00

Other expenses cost Travel expenses Stationary and printing fees Insurance Field measurement Transportation of materials Total other expenses cost

= RM 10,000 = RM 5,000 = RM 50,000 = RM 20,000 = RM 50,000 = RM 1,350,000

15,571.45

GRAND ESTIMATED COST

= RM 23,736,400.95


5.0 project procurement and resource planning As the project is relatively small with a simple and direct project brief, a conventional project procurement is implemented. The PAM Standard Form of Contract 2006 will be used in this project because it is most commonly used in Malaysia. Hence, the team members will be familiar with the contract and their responsibilities.

Client Muar KSK Lion Dance troup

CHARACTERISTICS OF TRADITIONAL PROCUREMENT • The design process and construction process is separated, where consultants are incharge of design and cost control while the contractors are responsible for construction works. • The architect is appointed to prepare the design brief, schematic design, working drawings, inviting tenders, overlooking the project, site inspection and preparing certificates of payment • The architect is the contract administrator between the client and contractor ADVANTAGES OF CONVENTIONAL PROCUREMENT

Architect YMY Architects Sdn Bhd

Main Contractor Gold Li Development Sdn Bhd

Civil & Structural Engineer CSM Consultant Sdn Bhd

Sub contractors

Mechanical & Electrical Engineer REVIDEO PRECISION Engineering Sdn Bhd

Specialist

Quantity Surveyor Moh Seng Consultants Sdn Bhd

Supplier

Interior Architect Full House Interior Designer Sdn Bhd

Landscape Architect TKC Natural Living Sdn Bhd

Figure 4: Organizational structure of the project

1. Worth for value in selection of contractor The open tender allows various contractors to bid according to their lowest cost without risking the quality of product to be delivered 2. More control on design and outcome of project In contrast with Design & Build procurement, the client will have more power regarding the design and final outlook of the project before tendering documents are prepared 3. Fixed cost of project The overall price is already established upfront, hence the cost of the project will not vary as much once it is completed. Preparation of tender documents before tendering also limits future claims by contractors which reduces cost fluctuation


PROGRAMME MAINTENANCE

BUILDING & SITE MAINTENANCE

To maintain the quality of the spaces, programme maintenance is needed as a guideline for the Passive design strategies have been implemented in the cultural center to maximise ventilation management to upkeep the cultural center. The cultural center consists of mostly public spaces which and reduce heat gain into the building. Besides maintaining its built form, the softscapes placed encourages interaction and multiple activities, so a regular upkeep of the spaces is necessary. adjacent to the river and along the platforms of the cultural center require regular maintenance.

Component

Frequency

Method

1

Training space

Daily

Ensure minimum level of cleanliness after usage

2

Outdoor cinema

Daily

Ensure cleanliness of space while maintaining video-screening equipment

3

Projection room

Daily

Ensure workability and functionality of the equipment in the room

4

Performing space

Weekly

Ensure proper usage and cleanliness

5

Event space

Weekly

6

Pop-up stores

Method

Pedestrian walkway

Annually

Ensuring tiles and stone pavements are in good condition for usage

2

Landscape along river

Quarterly

Landscapes to be well maintained and overhanging branches from trees to be trimmed quarterly

3

Vegetation on platforms

Daily

Plants to be watered daily and trimmed monthly

Ensure proper usage and cleanliness

4

Services area

Monthly

Ensure clear circulation to spaces and proper functioning equipment

Daily

Ensure minimum level of cleanliness after usage

5

Electrical appliances

Annually

Ensure proper usage and well maintenance

Weekly

Ensure basement parking is clear of any obstructions in vehicular circulation

6

Rainwater & Drainage system

Quarterly

Ensure constant water supply to the vegetation in the building. Drainage system to be clear of blockages

7

Air conditioning

Monthly

Technician to carry out regular maintenance to increase energy efficiency and thermal comfort

8

Piping utilities

Annually

Leakages and damages to be inspected and repaired when necessary

9

Lifts

Annually

Specialist to carry out maintenance for uninterrupted function and usage

10

Basement

Quarterly

Regular inspection to ensure service rooms are functioning

11

Pedestrian bridge

Annually

Painting works to be done with the cultural center to upkeep the image of the site

12

Fire fighting appliances

Annually

Ensure all fire fighting appliances are fully functioning

Basement parking

8

Lion Dance costume making workshop

Daily

Ensure minimum level of cleanliness after usage

9

Children’s art studio

Daily

Ensure minimum level of cleanliness after usage

Playscape

Frequency

1

7

10

Component

Weekly

Ensure cleanliness and maintenance of playscape for the safety of children

11

Rooftop garden

Daily

Plants to be watered everyday, with other maintenance on a regular basis

12

Garden of spices

Daily

Plants to be watered everyday while ensuring cleanliness of space


6.0 risk analysis and maintenance strategy DESIGN PHASE RISK

POSSIBILITY

SEVERITY

EFFECT

MITIGATION STRATEGY

CONTIGENCY

Misinterpretation of project goals and objectives among design team

3/5

2/5

Deliverables by each member is A meeting including all members of the project not up to expectations and does (both design team and construction team) to be not meet client’s requirement. This held to brief and realign the project goals and causes a further delay in the project. objectives

Regular meetings should be conducted (weekly/ fortnightly) to realign the team regarding their expected outcomes while checking on everyone’s progress

Building Plans (BP) not approved by local authorities

3/5

3/5

The project will be delayed until Resend the amended BP for approval from local BP should be checked thoroughly through a few the amended BP drawings are authorities stages before submitting for approval approved by local authorities

Miscommunication between specialist and consultant in finalising detailed drawings

5/5

4/5

During regular meetings, discussions between In the event of a misunderstanding or Project’s progress will be delayed specialist and consultant should be mediated miscommunication, a mediator (eg: project as detailed drawings are needed by the project architect to conclude to a mutual manager, architect) should take over to for tender agreement reevaluate and solve the problem

Over budget after calculating cost according to updated working drawings from all consultants

3/5

4/5

The client might not be able to Discuss and justify the updated costs with the The material and structural concept of the financially support the project client design should be taken into account for cost

RISK

POSSIBILITY

SEVERITY

Construction site flanked by two main roads with high traffic flow and high pedestrian flow. This might delay the construction of the project.

3/5

3/5

Disruption of construction process Materials needed to be transported to site should Traffic conditions of the site should be taken will delay other tasks as planned be ordered in advance to take into account of into account before preparing the Gantt Chart. according to the Gantt Chart. traffic delays.

3/5

Might exhaust resources and A temporary storage should be built to protect overwork labours. Heavy rainfall Temporary works should be carefully planned the materials from weather. The project manager and varying moisture levels will to prepare for unforeseen circumstances. should manage his labourers wisely. affect curing of concrete which is the main material of the building.

CONSTRUCTION PHASE

Work delayed due to inclement weather

5/5

EFFECT

MITIGATION STRATEGY

CONTIGENCY


RISK Construction site is located right beside existing shophouses. The noise from construction works might disrupt the neighbours. Improper and inefficient waste management might pollute the clean streets of Jalan Maharani

POSSIBILITY

SEVERITY

3/5

5/5

EFFECT

MITIGATION STRATEGY

CONTIGENCY

2/5

Neighbours will complain about the The neighbours will usually go home after work. A working permit at night should be obtained noise to the local authorities and Hence, construction works should be done at in advance. construction works might be put on night instead. hold until the noise issue is resolved.

3/5

Might exhaust resources and A temporary storage should be built to protect overwork labours. Heavy rainfall Temporary works should be carefully planned the materials from weather. The project manager and varying moisture levels will to prepare for unforeseen circumstances. should manage his labourers wisely. affect curing of concrete which is the main material of the building.

BUILDING OPERATION & MAINTENANCE PHASE RISK Ineffective and inefficient management in maintaining built and natural assets High consumption of water to maintain landscaping and other building services

POSSIBILITY

5/5

5/5

SEVERITY

EFFECT

MITIGATION STRATEGY

CONTIGENCY

3/5

The quality of spaces will deteriorate Develop a maintenance guideline for the Appoint a facilities manager to maintain the and end users might not be able management to follow to ensure the quality of built and natural assets to benefit entirely from the cultural these assets center

3/5

High costs will incur as water is A rainwater harvesting system should be essential for Garden of Spices and A rainwater harvesting system should be installed considered during the design phase to avoid other landscaping surrounding the additional cost in current phase cultural center


7.0 success criteria In this project, there are three cores that become key factors in determining the success of the project; time, scope and cost. These three elements interrelate with each other and form The Triple Constraint, which means a change in one element will affect the other. Hence, all three constraints should be satisfied to classify this project as a success.

Success Criteria

Time

Project Components

Measurable goals

Estimated construction duration: 24 months

• Tasks are completed on time with refernce to Gantt Chart • Consistent progress and smooth workflow • Transportation of labour and materials with no time delay

Tasks assigned to each team member is executed according to client’s expectations

• Completed building to be similar to initial design approved by client • Minimal construction defects during and after construction is completed • Supervision work to be done periodically by each supervisor with any discrepancies reported to the project architect

Estimated project budget: RM 24 million

• Careful selection of materials based on availability and economical value, which could reduce maintenance costs in the long term • Minimise production of waste on site • Budget is kept on track through out the project

Time

Scope

Cost

Scope Cost Figure 5: Diagram of the Triple Constraint


8.0 work breakdown structure Legacy Art Center, Muar

PRELIMINARIES

CONSTRUCTION PHASE

FINAL COMPLETION

1.1 PROJECT BRIEF 1.1.1 Analyse brief 1.1.2 Preliminary cost estimation

2.1 Preliminary 2.6 ARCHITECTURAL FINISHES 2.1.1 Mobilisation and Site establishment 2.6.1 Tiling works 2.1.2 Dilapidation Survey (Adjoining existing 2.6.2 Wall finishes trees & property) 2.6.3 Ceiling works 2.1.3 Setting out 2.6.4 Floor finishing 2.1.4 Site cleaning & levelling 2.6.5 Staircase finishing and hand railing 2.1.5 Underground mapping 2.1.6 Set up hoarding and signboard 2.7 M&E SERVICES 2.7.1 Earthing system 2.2 SUBSTRUCTURE 2.7.2 Building control system 2.2.1 Soil excavation 2.7.3 Electrical fittings 2.2.2 Piling works for foundation 2.7.4 Lift system 2.2.3 Inserting RC footing 2.7.5 Fire safety, detection & protection 2.2.4 Basement slab 2.7.6 Heating, ventilation and air conditioning 2.2.5 Basement wall system 2.7.7 Information and communication technology 2.3 SUPERSTRUCTURE 2.7.8 Plumbing & Sanitary 2.3.1 RC Transfer Slab (Ground floor) 2.7.9 Security & Alarm system 2.3.2 RC Round column (basement to fourth 2.7.10 CCTV installation floor) 2.3.3 Internal concrete walls and partition 2.8 EXTERNAL/LANDSCAPE walls 2.8.1 Surface water drainage 2.3.4 RC Slab for platforms 2.8.2 External M&E work 2.3.5 Lifts & fire staircase 2.8.3 Installation of softscape and hardscape 2.3.6 Ramp 2.8.4 Installation of signage

3.1 HANDING OVER 3.1.1 Final cleaning & inspection 3.1.2 Issuance of Certificate of Completion & Compliance (CCC) 3.1.3 Preparation of Final Accounts for contract

1.2 SITE ANALYSIS 1.2.1 Site investigation 1.2.2 Soil investigation 1.2.3 Site Accessibility 1.2.4 SWOT & PESTLE analysis 1.3 DESIGN DEVELOPMENT 1.3.1 Detail Design Drawings 1.3.2 Building Plan (BP) submission 1.4 CONTRACT DOCUMENTATION 1.4.1 Tender documentation 1.4.2 Project Planning & Schedule 1.4.3 Stakeholder notification

2.4 ROOFING 2.4.1 RC flat roof system 2.4.2 Scupper drainage and gutter drainage system 2.5 DOOR & WINDOW 2.5.1 Door frame & panel 2.5.2 Window frame & panel 2.5.3 Window/ Glass works


9.0 gantt chart


Task Description

Duration (Days)

Examine Site Information Schematic Design

4

1

2

3 4

1 2

Apr

3 4 1 2 3

May 4 1

Jun

2 3 4

1 2 3

July 4 1

2

Aug

3 4

1 2 3

Sept 4

Oct

1 2 3 4 1 2

5

Contract Documentation

25

Tender Coordination & Integration Construction

55 Milestone

PRELIMINARY (4 weeks) 15

Dilapidation Survey

5

Setting out

5

Site cleaning & leveling

5

Underground mapping

10 3 Milestone

FOUNDATION (6 weeks) Soil investigation

5

Excavation of soil

15

Piling of foundation

15 Milestone

STRUCTURE (8 weeks) RC Slab, Ramp and landing (Basement to Roof)

15

RC beam, column and flooring (ground floor to roof)

15

RC lift core

15 Milestone

ROOF (2 weeks) Gutter and drainage system

10

WALL & OPENINGS (9 weeks)

10

Ground floor wall

15

First floor wall

10

Second floor wall

7

Third floor wall

7

Milestone

Milestone

PLATFORMS Casting conrete platforms surrounding building

2 3

Mac

5

15

Setting up Hoarding & signboard

1

Feb

120

Design Development

Mobilisation and Site establishment

Jan Milestone

PRE-CONSTRUCTION (24 weeks) Design Brief

2019

10

FITTING & FINISHES (9 weeks) Plastering & painting

20

Floor finishes

20

Doors & windows

25

Staircase & handrail

10

No


2020

ov

Dec

Jan 4

Milestone

1

2

3

Feb 4 1 2

3

Mac 4

1

2

3

Apr 2

3 4

May 1

2 3

Jun 4

2

July 4

1

2

3

Aug 4 1 2 3

Sept 4 1

2

3 4

Oct 1 2

3

Nov 4 1

2

3

Dec 4

1

2

3

4


Task Description

Duration (Days)

M&E SERVICES (22 weeks) Lift car installation

10

Electrical and light fittings

15

Plumbing & sanitary

10

Mechanical ventilation

15

Fire protection system

10

Telephone & data system

5

Rainwater harvesting system

15

Recycle waste system installation

15

EXTERNAL WORK (17 weeks) Road & pavement

15

Surface water drainage

20

Sewerage & pipe

15

Landscaping

10

Signage

5

Miscellaneous

7

PHASE OUT (1 WEEK) Comissioning

3

Site cleaning

2

Inspection & handover

2

2019 Jan 1

2 3

Feb 4

1

2

3 4

Mac 1 2

Apr

3 4 1 2 3

May 4 1

2 3 4

Jun 1 2 3

July 4 1

2

3 4

Aug 1 2 3

Sept 4

Oct

1 2 3 4 1 2

No


ov

2020 Dec

Jan 4

1

2

3

Feb 4 1 2

3

Mac 4

1

2

3 4

Apr 2

3 4

May 1

2 3

Jun 4

2

July 4

1

2

Aug

3

4 1 2 3

Sept 4 1

2

3 4

Oct 1 2

3

Nov 4 1

2

3

Dec 4

1

2

3

Milestone

Milestone

Milestone

4