2013
BALANCED CANTILEVER BRIDGE DESIGN FOR
R Prabu, Md. Riaz & Ranjil P Ramath
8/31/2013
BALANCED CANTILEVER BRIDGE DESIGN 1)
By R. Prabu, Design Engineer, 2) Mohammed Riaz, Design Engineer, 3) Ranjil P Ramath, PM/Team Leader
ABSTRACT: This paper describes about the analysis and design of two balanced cantilever bridges designed to carry metro rail over it and crossing a railway line underneath (Rail over Bridge – RoB). Since the bridge is crossing the main and live railway line, only option for constructing the bridge it is in pre-cast and that too balanced cantilever construction. To accommodate the roadway underneath one of the internal support became a monolithic portal with superstructure. The balance cantilever thus had to rest on portal beam at one support and on free bearing at other pier support. As the bridge is on curve, it demanded bridge builder method of construction, which resulted in the stabilising frame concept for the transfer of unbalanced moments during construction. The maximum toe reaction (point load) from bridge builder was around 2200kN during lifting and empty weight was around 350kN. This extreme bandwidth of load posted a colossal challenge of proportioning the prestress design for no tension at any part. The box section has been designed to carry these loads. Substructure and foundation has been designed for all load cases as per DBR and importantly for the stability during construction and secondary effects due to prestressing at the monolithic portal. Bearing loads are estimated meticulously to ascertain no-tension condition, at any service stage to avoid tension bearings.
1.0 STRUCTURAL ARRANGEMENT: The span arrangement of the two bridges has been listed below in the table and the schematic views developed in-house of the two bridges is as shown below,
S. No. 1.
Location Bridge 1
Span Configuration 36.0 + 52.0 + 31.5m
Alignment In Transition
Superstructure Type Prestressed Box Girder
2.
Bridge 2
30.0 + 50.0 + 40.0m
In 128m Radius of Curvature
Prestressed Box Girder
Perspective View of Balanced Cantilever Bridges
1
2.0 STAGES OF ANALYSIS & DESIGN: Various stages of design has been shown below,
Balanced Cantilever Design Load data as per DBR Construction Load Input
Using Staad Pro & In-house program Section Design Construction Stage Analysis Service Stage Analysis
Cycle of design process
Superstructure Transverse Analysis
Prestress Design Using MIDAS Civil 2012 & STAAD Pro Bearing Load Calculation Substructure Design Stability and Design of Supporting Frame Foundation Design
3.0 SOFTWARE USED: The following software is used for analysis & designs of the two balanced cantilever bridges. 1) 2) 3) 4) 5) 6)
MIDAS-Civil 2012 – For Stage Analysis, Prestress design and Camber detailing. STAAD Pro V8i – For Stage analysis Checks, Transverse Analysis, Portal frame analysis. Auto CAD 2D/3D - For Concept views, Cable profiling, Detailed drawings. In-House excel program developed for transverse & longitudinal superstructure design. In-House excel program developed for substructure & foundation design. In-House excel program developed for movement of live load on curved path in STAAD-Pro V8i.
2
4.0 CONSTRUCTION METHODOLOGY / CONSTRUCTION LOADS: This balanced cantilever bridge has been planned to be constructed by erecting the precast segment with varying sizes of weight ranging from 200kN to 450kN, with the help of bridge builder system to lift and transfer the segment while prestressing is done in sequence as dictated by the design.
Lifting is permitted only along the axis of the bridge to avoid torsional stresses. This stage wise process will be continued until all the precast segment has been erected either side of the two pier head. After this the key segment will be brought in and will be stitched to form the cantilevers into a single continuous structure, for further loadings. During construction stage analysis the following construction loads has been considered as per the Design Basis Report and as per the loading details shared by the contractor for the construction stages, and they are a) b) c) d) e)
Bridge Builder weight – Loaded & Empty at each stages Construction impact effect – 10% of segment weight. Segment shifting trolley weight Accidental load at tip - 100kN Point load Construction live load on deck surface - 1.0kN/m2.
Conceptual 3-Dimensional views of the bridges have been prepared in Auto CAD 3D to appreciate the bridge architecture, investigate mandatory clearances, any construction issues. One of such created conceptual views is as shown below,
3
Perspective View of Balanced Cantilever Bridge 2 – During Construction in Progress 5.0 ANALYSIS OF SUPERSTRUCTURE: The structure has been modelled and analysed using MIDASCivil_2012, for various stages of construction and service. A detailed construction scheme has been prepared, with clear demarcation of the loading and unloading schedules along with the prestressing requirements. The span to depth ratio for both the superstructure has been chosen as shown below, S. No.
Location
Main Span
Span to Depth Ratio At Support At Mid span
1.
Bridge 1
52.0m
17
25
2.
Bridge 2
50.0m
16
24
The substructure consists of Fixed pier (Monolithic with superstructure), Free pier (L Type), Cantilever pier caps and the foundation is of open foundation at Bridge 1 location with a safe bearing capacity 750.0kN/m2, and pile of 1.0m diameter at Bridge 2 location with maximum vertical load capacity of 5000kN/pile & lateral load capacity of 400kN/pile. The structure can be subjected to two boundary case loading during its construction stages,
4
1) Structure with loaded bridge builder with all construction loads, 2) Structure with empty bridge builder with no construction loads. Hence the analysis needs to simulate these governing construction boundary cases. Hence two separate models have been generated with each case to investigate the stress distribution. For service case, the completed construction stage model is used and for the following load the structure is designed, 1) Super imposed Loads 2) Vertical Train Load with CDA as per Indian Railway Standard (IRS) Bridge Rules, 3) Centrifugal force, 4) Braking & Traction, 5) Derailment loads, 6) Overall temperature, 7) Differential temperature, 8) Long welded rail (LWR), 9) Nosing force, 10) Wind load, 11) Seismic force Z-II, 12) Differential Settlement, 13) Vehicle collision load Live load analysis has been done for 6Car, 3Car, 2Car train loading with an axle load of 170kN.
Live Load Details Since the span in the structure is varying from 30.0 to 52.0m, to get the governing forces, the above combination of cars have been generated in model and analysed. Envelope function of MIDAS-Civil 2012 has been used to identify the maximum at each section, during the incremental of live load movements.
5.1 TRANSVERSE ANALYSIS & DESIGN: The Bridge has been analysed & designed as per the DBR for all applicable loads mentioned above. Effects of derailment, construction loads, lifting loads, stacking loads are also checked. Since the bridge builder transfer a heavy point load and it is directly supported over the box girder deck slab, the same has been checked for flexure, shear and punching additionally. A 3D FEM Model using plates is created in STAAD-Pro V8i and the stresses are checked and the RCC section is designed for the stresses.
5
Stress Distribution – With Bridge Builder Loads
5.2 CONSTRUCTION STAGE LONGITUDINAL ANALYSIS: Since the construction of the superstructure is done by stages and a detailed construction stage analysis is done using the MIDAS-Civil 2012. Each construction stages have been briefly explained as shown below, RP2 and RP3 denotes the respective piers.
6
Stage – 1: Pier Head completed + Segment 1 Erection at RP2 & RP3 RP1
RP2
RP3
CL of pier/Bearing (Fixed)
CL of pier/EJ 36000*
RP4
CL of pier/Bearing (Free) 31500*
52000*
CL of pier/EJ
Bridge builder (Typ)
7500
7500
7500
S1
7500
S1
Pier head-cast-in-situ portion (Typ)
S1
RB
RB
Temporary support (Typ)
Piercap (Typ)
Railway portion
Span-1
Open foundation(Typ)
Span-1
S1
0 - 30 days
Pier (Typ)
Span-2
Span-2
STAGE-1 Pier head completion+segment 1 erection RP2 and RP3
Stage – 2: Seg-1 Erected+Seg-2 Erection RP2 & RP3 RP1
RP2
RP3
36000*
52000*
10500
10500
10500
S2 S1
S1 S2
Railway portion
Span-1
Span-1
10500
S1
RB
RB
Stabilizing frame
Open foundation(Typ)
CL of pier/EJ
S2
S1
S2
RP4
CL of pier/Bearing (Free) 31500*
CL of pier/Bearing (Fixed)
CL of pier/EJ
31 - 34 days
Span-2
Span-2
STAGE-2 Segment 2 erection RP2 and RP3
Stage – 3: Seg-2 Erected+Seg-3 Erection RP2 & RP3 RP1
RP3
RP2
CL of pier/EJ
CL of pier/Bearing (Fixed) 52000*
36000*
13500
13500
13500
S3 S1
S3
S2
S3
Stabilizing frame
Open foundation(Typ)
Span-1
Span-1
S2 S1
S1 S2
Railway portion
35 - 38 days
S3
Span-2
STAGE-3 Segment 3 erection RP2 and RP3
7
13500
RB
RB
S2 S1
RP4
CL of pier/Bearing (Free) 31500*
Span-2
CL of pier/EJ
Stage – 4: Seg-3 Erected+Seg-4 Erection RP2 & RP3 RP1
RP2
CL of pier/EJ
RP3
CL of pier/Bearing (Fixed) 36000*
52000*
16500
S4
16500
S4
S2 S3 RB
S1
S4
CL of pier/EJ
16500
S3 S2 S1
S1 S2 S3
RB
16500
S3 S2 S1
RP4
CL of pier/Bearing (Free) 31500*
S4
Railway portion Stabilizing frame
Span-1
Open foundation(Typ)
39 - 42 days
Span-1
Span-2
Span-2
STAGE-4 Segment 4 erection RP2 and RP3
Stage – 5: Seg-4 Erected+Seg-5 Erection RP2 & RP3 RP2
RP1 CL of pier/EJ
RP4
RP3
CL of pier/Bearing (Fixed) 52000*
36000*
CL of pier/EJ
CL of pier/Bearing (Free) 31500*
Bridge builder (Typ) 19500
S4
19500
S3 S2 S1
S1
S5
S5
19500
S2 S3 S4
S1 S2 S3
S4
RB
RB
S5
19500
S4 S3 S2 S1 Railway portion
S5
Stabilizing frame
Open foundation(Typ)
Span-1
Span-1
43 - 46days
Span-2
Span-2
STAGE-5 Segment 5 erection RP2 and RP3
Stage – 6: Seg-5 Erected+Seg-6 Erection RP2 only RP1
RP2
CL of pier/EJ
RP3
36000*
52000*
22500
22500
22500
S6 S4
S3 S2 S1
S1
S5
RB
S6
S2 S3 S4 S5
S4 S3 S2 S1
22500 S1 S2 S3
RB
S5
RP4
CL of pier/Bearing (Free) 31500*
CL of pier/Bearing (Fixed)
Railway portion Stabilizing frame
Open foundation(Typ)
Span-1
Span-1
47 - 50 days
STAGE-6 Segment 6 erection on RP2
8
Span-2
Span-2
S4 S5
CL of pier/EJ
Stage – 7: Seg-6 Erected and stressed at RP2 only RP2
RP1 CL of pier/EJ
25500
25500
S3 S2 S1
S1
22500
S2 S3 S4 S5
S6
S5
Span-1
Span-1
22500
S4 S3 S2 S1
S4 S5
S1 S2 S3
Railway portion
Stabilizing frame
Open foundation(Typ)
CL of pier/EJ
RB
RB
S4
CL of pier/Bearing (Free) 31500*
52000*
36000*
S6 S5
RP4
RP3
CL of pier/Bearing (Fixed)
51 - 54 days
Span-2
Span-2
STAGE-7 Segment 6 erected and stressed on RP2
Stage – 8: Seg-6 Erected on RP3 RP1
RP2
CL of pier/EJ
RP3
36000*
52000*
25500
25500
S3 S2 S1
S1
22500
S2 S3 S4 S5
S6
S6 S5
CL of pier/EJ
22500
S4 S3 S2 S1
S1 S2 S3
S4 S5 S6
RB
S4
RB
S6 S5
RP4
CL of pier/Bearing (Free) 31500*
CL of pier/Bearing (Fixed)
Railway portion Stabilizing frame
55 - 58 days
Span-1
Span-1
Open foundation(Typ)
STAGE-8 Segment 6 erection on RP3
Span-2
Span-2
Stage – 9: Key Segment Erection from RP3 RP1
RP2
CL of pier/EJ
RP3
CL of pier/Bearing (Fixed) 36000*
RP4
CL of pier/Bearing (Free) 31500*
52000*
Bridge builder (Typ) 25500
S3 S2 S1
S1
S2 S3 S4 S5
S6
24500
S6 S5
S4 S3 S2 S1
24500
S1 S2 S3
RB
S4
RB
S6 S5
KS
25500
Railway portion Stabilizing frame
Open foundation(Typ)
Span-1
Span-1
59th day
Span-2
ACTIVITY-1 : Key segment erection from RP3 STAGE-9
9
Span-2
S4 S5 S6
CL of pier/EJ
Stage – 10: Stressing of Continuity Cables RP1
RP2
CL of pier/EJ
RP3
CL of pier/Bearing (Fixed) 36000*
RP4
CL of pier/Bearing (Free) 31500*
52000*
CL of pier/EJ
1816 25500
S6 S5
S4
25500
S3 S2 S1
S1
24500
S2 S3 S4 S5
24500
S6 KS S6 S5
S1 S2 S3
S4 S5 S6
RB
RB
EQ EQ
S4 S3 S2 S1 Stitch concrete - 1 Stitch concrete - 2
Railway portion Span-1
Open foundation(Typ)
63 - 66 days
Span-1
STAGE-10 Stressing continuity cables
Span-2
Span-2
Stage – 11: Cast of RP1 & RP2 cast-in-situ portion by Full Staging Method (FSM) RP1
RP2
CL of pier/EJ
RP3
36000*
RP4
CL of pier/Bearing (Free) 31500*
CL of pier/Bearing (Fixed) 52000*
CL of pier/EJ
FSM - Left 10486
FSM - Right 6985
S6 S5
S4
S3 S2 S1
S1
S2 S3 S4 S5
S6 KS S6 S5
S4 S3 S2 S1
S1 S2 S3
S4 S5 S6
RB
RB
Railway portion
Open foundation(Typ)
Span-1
Span-1
67 - 100 days
Span-2
Span-2
STAGE-11 Cast FSM at RP1 and RP4
Stage – 12: Complete Structure – Checked for its design life considering 120 years RP1
RP2
CL of pier/EJ
RP3
CL of pier/Bearing (Fixed) 36000*
S6 S5
S4
52000*
S3 S2 S1
S1
S2 S3 S4 S5
S6 KS S6 S5
RP4
CL of pier/Bearing (Free) 31500*
S4 S3 S2 S1
S1 S2 S3
Open foundation(Typ)
Span-1
Span-1
RB
RB
Railway portion
100th day
STAGE-12 Completed structure
10
Span-2
Span-2
S4 S5 S6
CL of pier/EJ
5.3 PRESTRESS DESIGN: 5.3.1 PERMANENT PRESTRESSING DESIGN: Since construction is in stages, during each construction stage of construction of cantilever, the top cable at each segment is Prestressed to take care of the hogging moment coming at each stage. After construction of the cantilever arm, the key segment has been attached and the continuity cable has been Prestressed to take care of both the sagging and hogging moment coming over the section. At last after completion of RP1 & RP4 piers the soffit cable has been stressed to take care of the sagging moment coming over the segment. Layout of the above listed cable profile has been shown below. 3D view of the bridge with all cables is developed and the clash checks have been done.
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
RP2
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable dead end
Cable stressing end
52000
36000
RP1
RP3
CL of Pier/Bearing
S6
S5
S4
S3 S2
S1 S1
S2
Cable stressing end
Cable stressing end
S3
S4
S5
S6
Cable stressing end
Cable stressing end
Cable dead end
RP2 Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
Cable stressing end
of box girder
CL of Pier/Bearing
S6
S5
S4
S2
S3
S1
S1
S2
S3
S5
S4
S6
Top Prestressing Cable RP2
RP1 36000
52000
RP3
CL of Pier/Bearing
CL of Pier CL of Bearing Cable dead end
Cable stressing end
Cable stressing end
Cable dead end
Y S6 S5
S4
S3
S2
S1
S1
CL of Pier CL of Bearing
S2
S3
CL of Pier/Bearing
Cable dead end
Cable stressing end
Cable stressing end
S1
S2
S6
S5
S4
S3
S2
S1
PLAN SCALE 1:75
Continuity Cable between – RP1 & RP2
11
S3
of box girder
Cable dead end
RP2
RP3
36000
RP1
52000
Cable stressing end
S3
CL of Pier/Bearing
RP3
Cable stressing end
Cable stressing end
S1
S1
S2
31500
CL of Pier/Bearing
Cable stressing end
S2
S3
S4
S5
S6
KS
S6
S5
S3
S4
S1
S2
S1
S3
S2
Cable stressing end
CL of Pier/Bearing
of box girder
Cable stressing end
S3
S2
CL of Pier/Bearing
S1
S2
S1
S3
S4
S5
S6
KS
S6
S5
S4
S3
S2
Cable stressing end
S1
S1
Cable stressing end
S2
S3
Z=-1821
Continuity Cable Between – RP2 & RP3 RP2
RP3
36000
31500
52000 Cable stressing end
CL of Pier/Bearing
Cable stressing end
Cable stressing end
Cable stressing end
S1
Cable stressing end
CL of Pier/Bearing
Cable stressing end
S2 S3
S4
S5
S6
KS
S6
S5
S4
S3
S1 S2
CL of Pier/Bearing
of box girder
RP1
Cable stressing end
Cable stressing end
S1
Cable stressing end
S2
Cable stressing end
S3
S4
S5
S6
KS
S6
S5
S4
S3
S2
PLAN SCALE 1:75
Soffit Cable Between – RP2 & RP3 CL of box girder
CROSS SECTION OF PRESTRESS CABLES
12
Cable stressing end
S1
Cable stressing end
CL of Pier/Bearing
RP3
3D-View of Cable Profile for clash checks
Schematic View of Cable Profile at Support location (Blister not shown) – At RP2 & RP3 5.3.2 TEMPORARY PRESTRESSING DESIGN: As mentioned earlier, as the permanent top prestress has been proportioned in advance for the upper boundary of the construction loads, the lower boundary loads when placed along with this prestressing was creating tensile stresses at soffit of the structure. To avoid this tensile stress temporary sequential prestressing using, high strength restrained bars are used. These bars are placed at top and bottom of the box section and stressed to provide an axial stress equal to 0.8MPa (average). These bars are untied and reused in a forwarding sequence, in batches. To control the bottom tension over supports, external short cables (19T15) are used. The arrangement of the temporary stressing bar has been as shown below,
13
CL of pier/Bearing (Fixed) 3000
3000
15000 In situ portion Jacking end
Dead end
Jacking end
Dead end
350
S1
S1
Stitch concrete
Stitch concrete
CL of box girder
Dead end
Jacking end
S2
S1
Temporary Prestressing Details
5.4 PRESTRESS DESIGN RESULTS FROM MIDAS-CIVIL: The stress diagram of the superstructure during complete construction of the structure has been shown below. In which the maximum compressive stress attained in the section shows as -12.76MPa < the allowable stress 20.00MPa. And there is no tension in the section.
14
Stress diagram showing stresses â&#x20AC;&#x201C; (During Construction Stage â&#x20AC;&#x201C; 12) Similarly during service stage, the stresses have been checked for all possible load combination and all the stresses are within the limit. The governing load case stresses has been shown below,
Stress diagram showing stresses â&#x20AC;&#x201C; (During Governing Service Stage) The stresses have been checked for both case of loaded and empty bridge builder. As explained earlier due to the upper and lower boundaries of loads, each cases show substantial variation in the in the design forces. To satisfy both the cases using same prestress, a number of design trials have been performed using the permanent and temporary prestress, and an optimum solution has been worked out. Bending Moment Diagram (BMD) in the construction stages (CS9 for example) is shown below,
15
Bending Moment Diagram â&#x20AC;&#x201C; During Construction Stage With Loaded Bridge Builder
Bending Moment Diagram â&#x20AC;&#x201C; During Construction Stage with Empty Bridge Builder The section has been checked for ultimate load for the governing ultimate load case and it has been done through in-house excel program. 6.0 ANALYSIS & DESIGN OF SUBSTRUCTURE AND FOUNDATION: 6.1 STABILIZING FRAME FOR UNBALANCED MOMENT: As explained above, since the superstructure is supported over bearing, to make the structure a stable during construction the stabilizing frame is used to make the cantilever arm a stable one as shown below. The bridge builder is of steel structure designed to erect a segment weight of 450kN. It is not practically possible to erect both the segments simultaneously, and thus will have unbalanced moments, which will vary from stage to stage and will also transfer tension and compression (alternate) in the bridge builder legs.
16
Bridge Builder Arrangement
Stabilizing Frame Arrangements As shown above is the case where the segment is erected from only one (left)side of cantilever. Due to this unsymmetrical loading left side leg of stabilizing frame will have full compression and the right side leg of stabilizing frame will have full tension. But to avoid this tension, a permanent compression is applied by anchoring a temporary restrained bar from superstructure to the stabilizing frame. In this case the restrained bar should be always in compression, during all stage of construction, and thus for varying range of loads subjected to. Allowance shall be given for the fatigue and elastic recoveries. As per the calculation by considering all stages, the structure stability and stresses are checked for unbalanced moments. Places at portal location, these frames are fixed to the ground using rock anchors. 6.2 DESIGN OF FOUNDATION & SUBSTRUCTURE: The foundation & Substructure has been designed as an RCC section fully adhering the DBR, and detailed drawings have been prepared. In the design of L pier,
17
the foundation has been kept eccentrically to reduce the permanent transverse moment generated in the pier. In pile design, possible reversal load cases have been checked for both favourable and unfavourable cases due to permanent longitudinal and transverse moments using in house program. Since the ROB GADs has been finalised by the contractor and got approved from the Railways prior to the initiation of the detail designs, there existed restrictions in the foundation sizes and hence it required many trials to maintain the sizes near that or acceptable to railways. In the bridge at Bridge 2 location where one of its substructure is portal and the superstructure alignment was very close to the right leg of the portal, due to which the maximum vertical forces has been attracted by the right leg of portal, hence the left leg of portal foundation was governed by the minimum load and corresponding moment case. This has induced complication to adhere to the foundation size as per approved GAD. But to avoid tension at left leg of the portal, the stiffness of the pier has been reduced in transverse direction, due to which the transverse moment attracted by the foundation due to gravity loads got reduced and the same foundation size has been followed. Substructure has been designed for the 37 load cases with all possible reversible. 7.0 CONCLUSION: The bridge is a special type and first in India where the bridge is integrated to a portal beam, and constructed as balanced cantilever. The entire definitive design of the two bridges has been delivered to the client with in a period of 3 months’ time frame. Many conceptual views have been developed and have been well appreciated by client. This has showcased team’s capacity to deliver projects with customer satisfaction. Simulation of cable profiling in 3D-views helped to check the cable clashes and check for minimum cover to the concrete, and thus reaffirmed the workability of sleeker sections. The bridge has been proportionated to have an optimal design with an average thickness of 0.62m and prestress to superstructure concrete quantity equal to 55 kg/m3, which is challenging achievement for this sort of complex structure, and within this short time frame of designs. By doing this special and complex type of structural design, team has also been exposed to the international experiences of senior technical advisor, and has equipped the team to do similar and more challenging type of structure in future. This project involves three levels of independent checking’s and internal peer review, which the design team has successfully undergone and delivered the designs. This is also the first time that Indian team has delivered this sort of complex bridge project (balanced cantilever technique), by its local resource’s skill sets. Finally we shall confidently conclude that, with this sort of service, we are rightly sailing towards our vision of becoming the consultant of choice in the global market, and we could find the positive reflections in clients approach too.
18