Executive Summary

Next Article
Report methodology

Report methodology

Introduction

The East Coast Digital Programme (ECDP) will introduce in-cab radio based signalling - known as digital signalling - on the East Coast Main Line, one of the UK’s major railway lines linking London to Edinburgh. Working in partnership with operators, the Government and the supply chain, the programme will upgrade the train control systems to create a greener, more reliable and flexible railway. It will also increase capacity on the line.

Advertisement

The ECDP is due to be the first intercity digital railway in the UK, fitting trains with the latest signalling technology and removing the old lineside signals. It will mean that the signalling system will be able to communicate with trains continuously rather than only at fixed points, instructing and responding in real time and reducing delays - thereby improving capability and performance. Funding for the programme was confirmed by Government in early 2020 after the project was initiated by Network Rail in 2018.

The programme will migrate around 3000 drivers to ETCS operations across tens of duty

Benefits that ECDP is delivering

◦ Increased system availability ◦ Improved punctuality ◦ Improved track staff safety ◦ Improved passenger safety ◦ Reduced energy consumption and carbon costs

holders, and deploy ETCS on hundreds of vehicles.

Network Rail launched a procurement process to find private sector partners to help deliver the programme in September 2018. It was an entirely new way of working, to team up with partners from the supply chain from programme conception to design, develop and deploy the CCS upgrade, including ECTS and Traffic Management System (TMS) technology. The key element of the scope of these relationships was that they were to be outcome based and to support and maintain the systems throughout the assets’ life. The procurement concluded with Siemens confirmed as the programme’s Train Control Partner (TCP) and Traffic Management Partner (TMP), and Atkins as Railway Systems Integration Partner (RSIP) – with support from Ramboll and PWC. The programme was established and continues to be overseen by Network Rail, in partnership with operators with cross industry governance.

Programme status

At the time of publication, the Programme had delivered:

1.The full business case has been completed.

It is founded on an industry-developed baseline plan, from blueprint to detail delivery partner and supplier cost plans. It is the first to be developed this way. 2. Northern City Line (NCL) was rapidly developed in the partnership model with operator, route and supplier. It is in delivery with commissioning of the upgraded system planned for 2022. This will be the first migration to a no signals

ETCS since the Cambrian project in 2010, and the first for a higher capacity railway in the UK.

3. Business change projects have been mobilised from across duty holder organisations to deliver the shift to ETCS operations. 4. The train migration project has started work with operators to drive the technology deployment, .

5. The first migration on ECML between

Welwyn and Hitchin is in design development and started delivering infrastructure upgrades in Christmas 2021.

Train fitment and readiness projects are being progressed across the fleets and vehicles used on the line.

Currently, over 70% of the cost plan on ECDP is for items that go beyond upgrading the East Coast South section - preparing for roll-out on the wider network beyond ECML. In October 2021, ECDP received a ‘green’ status from the Infrastructure and Projects Authority (IPA) review - one of only a few railway projects to do so. This has recognised that the industry partnership and operating model has been successful in exposing the risks of this enterprise and responding to them. It also recognised how the user centric approach meant that the plan is as resilient as possible given the inherent complexity and the range of organisations brought together. In November 2021, the Government’s Integrated Rail Plan confirmed further funding to upgrade the East Coast Main Line, including delivering full digital signalling.

Work on the Northern City Line, ECDP

Report methodology

During September to November 2021, the Railway Industry Association (RIA) held a series of interviews with key figures involved on the East Coast Digital Programme to hear their views on how the programme has been developed and its progress so far. The interviews included representation from:

• Network Rail

• Siemens - Train Control Partner (TCP) and Traffic Management Partner (TMP) • Atkins - Railway Systems Integration Partner (RSIP) Lead • London North Eastern Railway (LNER) - as the lead train operator on the route • PWC - Part of the RSIP consortium

• RSSB - Developing the new supporting standards Each group was asked a series of questions, including around the set-up of the programme, how it differs from others, the benefits, any potential drawbacks and wider lessons for the industry. From these interviews, RIA has identified several common themes, which are set out in greater detail below.

Grand Central Class 180 at Biggleswade on ECML, Milda Manomaityte

How is the ECDP different?

First and foremost, it is clear that ECDP is indeed different from other railway programmes. Interviewees were unanimous that it differs significantly from previous projects or programmes they have been involved in. Primarily, this is in the structure, which was established as a partnership model.

The model means that traditional supply chain companies including OEMs are acting as partners, with operators also heavily involved. The Railway Systems Integration Partner (RSIP) – led by Atkins, with support from Ramboll and PWC is responsible for the integration of the system onto the railway and the associated business change.

The Train Control Partner (TCP) – Siemens is responsible for the development, delivery and integration of the CCS technology and system architecture.

The Traffic Management Partner (TMP) – Siemens is also responsible for the development and delivery of the traffic management software. These companies, or partners, also act as the main technical leads and have stepped up to take on more responsibility to manage the technical integration of the system with the operational railway as well as engage collaboratively with each other, Network Rail and the railway operators. Some of these responsibilities would traditionally fall on Network Rail.

The partners also take on risk on achieving the outcomes. Whereas with normal infrastructure or signalling programmes in the UK, where the responsibility to deliver successfully is on Network Rail, on ECDP the partners – including Siemens and Atkins – have far more responsibility for delivering outcomes. Partners are also given much more flexibility in specifying how these are met than is traditionally the case. So, from start to finish of the process, it is markedly different. One interviewee from the RSIP, Atkins, said: “The partners have stepped up to take on more responsibility to realise outcomes - [this is] traditionally something that Network Rail would take on alone.”

Moreover, each operator which uses the East Coast Main Line is embedded in the programme. This includes duty holder organisations including passenger train, freight, open access or heritage railway operators who will need to operate in ETCS. - e.g. LNER, GTR, Grand Central, Hull Trains, Lumo, amongst others. In addition, a senior representative from LNER acts as the lead coordinator for industry business change on behalf of the operators.

“The partners have stepped up to take on more responsibility to realise outcomes - [this is] traditionally something that Network Rail would take on alone.”

Interviewee from the Railway Systems Integration Partner, Atkins