Who Should Apply? An experienced project manager who meets the following requirements: • Perform their duties under general supervision and are responsible for all aspects of the project for the life of the project • Lead and direct cross-functional teams to deliver projects within the constraints of schedule, budget and resources • Demonstrate sufficient knowledge and experience to appropriately apply a methodology to projects that have reasonably well-defined project requirements and deliverables.
Price: Member: US$405.00 Non-member: US$555.00 Prerequisites: Secondary degree (high school diploma, associate’s degree or the global equivalent) 7,500 hours leading and directing projects 35 hours of project management education
Question: 1
Identify Risks is part of which Process Group? A. Planning B. Executing C. Closing D. Initiating Correct Answer: A
https://www.realexamcollection.com/pmi/pmp-dumps.html
Question: 2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses? A. Risk and uncertainty increase; the cost of changes increases. B. Risk and uncertainty increase; the cost of changes decreases. C. Risk and uncertainty decrease; the cost of changes increases. D. Risk and uncertainty decrease; the cost of changes decreases. Correct Answer: C
https://www.realexamcollection.com/pmi/pmp-dumps.html
Question: 3
Which tool or technique is used in the Plan Scope Management process? A. Document analysis B. Observations C. Product analysis D. Expert judgment Correct Answer: D
https://www.realexamcollection.com/pmi/pmp-dumps.html
Question: 4 Which tool or technique is an examination of industry and specific vendor capabilities? A. Independent estimates B. Market research C. Analytical techniques D. Bidder conferences Correct Answer: B
https://www.realexamcollection.com/pmi/pmp-dumps.html
Question: 5 An input used in developing the communications management plan is: A. Communication models. B. Enterprise environmental factors. C. Organizational communications. D. Organizational cultures and styles. Correct Answer: B