BUILD UPDATE
ONE London Road Block 5
August 2021
ONE London Road - Block 5 • Ground floor & first floor laid down, and beams in for second floor • Roof covering scheduled for October • Orders placed for M&E contractors (lift) • Window orders placed • Metal stud orders placed and starting in next few weeks • Groundworks ongoing • Tree felling and car parking in next few weeks • Drainage ongoing