ONE LONDON ROAD BLOCK 5 BUILD UPDATE APRIL 2022
ONE London Road Block 5 Build Update April 2022 • Kitchens fitted to first and second floors • Kitchens being fitted to the third floor rooms • Plastering will be completed to First, Second and Third floors by Friday 8th April • Main stairwell to be plastered and completed next week • Electrical and Mechanical on second fix to second floor and on schedule • Progress will then shift to the Third floor for MnE • Flooring to be put down to all bathrooms to the first floor • Second floor bathrooms to be started next week • Decorators have started working on the first floor rooms and communals • Internal doors to be delivered in the last 2 weeks in April for the first, second and thrid floors • Cladding around 4 weeks away