ONE London Road Block 5 Build Update Nov 2021

Page 1

ONE London Road Block 5

Nov 2021 Build Update


ONE London Road Block 5 Build Update • • • • • • •

15th November 2021 - Building being sealed Screeners working on levels 2 & 3 Building will be weathered in by first week in December Internal works can progress at this point Window installation is up to the second floor with glass being delivered and fitted M&E is well underway to the first and second floors Once sealed the internals will be dried out ready for the internal fittings to commence during the latter part of December 2021