ONE London Road September Build Report 2021 Block 5
3rd Floor beams going down in the next week Metal works ground and 1st floor complete Plumbing and Electrical works on all floors started Groundworks ongoing Brickwork on all floors completing by 3rd week in October Windows have been delivered to site
View towards Block 1 (noted as Block 2 in the final scheme) High Level Car Park
Any Other Information No further information listed by developer September 2021