The Villas Build Update April 2022

Page 1

THE VILLAS BUILD UPDATE APRIL 2022


The Villas Build Update April 2022 • The demolition of the single storey was completd 8th March 2022 • Reduced level to form piling mats, came across pre-existing buildings from before the Police station which have had to been removed • Piling commencement 11th April 2022 • Piling should take approx 3 weeks • Steel work to then commence Mid-Late April • Archeology have completed exploratory works, discovered position of previous bottle ovens from the pottery era marked and updated maps for historic purposes - recorded and added to library • Pictures and information pack on the bottle ovens and local history will be added later before completion