JUNIOR/DINGHY FACILITY REDEVELOPMENT
JUNIOR/DINGHY
REDEVELOPMENT IN PROGRESS
Advertisement
below: architectural plan of New Facility insert: artist’s rendition of New Clubhouse
The Junior/Dinghy Facility redevelopment commenced on 2 February 2021 with the demolition of the Dinghy shed.
JUNIOR/DINGHY
facility
oats and equipment previously stored in the shed were relocated to a tempo-B rary location. It was exciting to see the pouring of the concrete slab in
Week 6. Following this milestone in the project, a ‘Slab Celebration’ was held on 14 March for supporters of the redevelopment. We are so thrilled to see this project underway and look forward to watching the redevelopment come to fruition over the next 12 months.
Please follow us on this journey.
Stage 1
Demolish existing Dinghy Shed and construct a new Clubhouse. Stage 1a
To take place concurrently with Stage 1 and to be returned to Club as soon as practicably possible after earthwork is complete for returfing and irrigation. Stage 2
Existing Clubhouse and ablutions block to remain operational throughout. Stage 1
Demolition, earthworks, landscaping and civil works to be commenced after the new Clubhouse is operational. images overleaf
WEEK 1
WEEK 2
WEEK 5 WEEK 1
WEEK 3
WEEK 6
opposite left: Old Shed opposite right: outside of Old Shed opposite below: new Training Equipment location
left and below: weekly update in pictures