This is the 1st Affidavit of Harry Sheldon Swain in this case and was made on 31/Jan/2018 No. 18 0247 Victoria Registry
In the Supreme Court of British Columbia BETWEEN: WEST MOBERLY FIRST NATIONS, and ROLAND WILLSON ON HIS OWN BEHALF AND ON BEHALF OF ALL OTHER WEST MOBERLY FIRST NATIONS BENEFICIARIES OF TREATY NO. 8 PLAINTIFFS AND: HER MAJESTY THE QUEEN IN RIGHT OF THE PROVINCE OF BRITISH COLUMBIA, THE ATTORNEY GENERAL OF CANADA, and BRITISH COLUMBIA HYDRO AND POWER AUTHORITY
DEFENDANTS
AFFIDAVIT #1 OF HARRY SHELDON SWAIN I, Harry Sheldon Swain, of 838 Pemberton Road, in the City of Victoria in the Province of British Columbia, Associate Fellow at the Centre for Global Studies, University of Victoria, make oath and say as follows: 1.
I was the chair of the Joint Review Panel ("JRP" or "Panel") on the British Columbia
Hydro and Power Authority's proposed Site C Clean Energy Project (the "Project"). I have personal knowledge of the facts and matters in this Affidavit, except where stated to be on information and belief, in which case I verily believe them to be true. Part A: Expert Report 2.
I was retained by Sage Legal, counsel for the Plaintiffs in this Action, to prepare
an expert report setting out my opinion regarding: (a) the need for the Project, and alternatives to the Project;
-2-
(b)
the limitations placed by the provincial and federal governments on the Panel's terms of reference, and how any such limitations may have affected
the Panel's ability to reach conclusions regarding the effects of the Project on the need for the project or potential alternatives;
(c)
the reasons why the Panel recommended subjecting the project to scrutiny by the BC Utilities Commission (the "BCUC");
(d)
the decision by the provincial government in December 2014 to proceed with the Project without any BCUC review;
(e)
the decision of the provincial government in 2017 to commence a BCUC inquiry,
and
my view regarding the appropriateness of the terms of
reference issued in respect of the inquiry; and
(f)
whether the process followed and conclusions reached by the BCUC were reasonable in light of the inquiry's terms of reference.
3.
Attached to my affidavit as Exhibit "A" is my expert report in response to these
instructions (the "Expert Report"). I hold the opinions expressed in my Expert Report and adopt the Expert Report as my evidence in this proceeding. A copy of my curriculum vitae is included in my Expert Report as Schedule "B". 4.
I certify that I am aware of my duty as an expert witness to assist the court and not
to be an advocate for any party.
I further certify that I have made my Expert Report in
conformity with this duty and will, if called on to give oral or written testimon y, give that testimony in conformity with this duty.
5.
My Expert Report is based on my experience and expertise in the energy sector
and specific experience and expertise with respect to electrical power generation, distribution and markets.
- 3 -
Joint Review Panel Report 6.
My Expert Report is also based, in part, on my personal experiences as the chair
of the JRP. The Panel was established by the federal Minister of the Environm ent and the British Columbia Minister of Environment. Attached to this Affidavit as Exhibit "B" is a
copy of the Site C Clean Energy Project Environmental Impact Stateme nt Guidelines , issued by the Minister of Environment of Canada and the Executive Director of the Environmental Assessment Office of British Columbia on September 5, 2012. 7.
Attached as Exhibit "C" to this affidavit is a copy of the Report of the Joint Review
Panel, Site C Clean Energy Project, of May 1, 2014.
I was one of the authors of this
report (the "Report"). The final Report was published on May 1 , 2014 with no dissenting statements.
The entire text was a consensus of the three panelists.
The Panel then
ceased work and was kept in reserve until the publication of the governm ents' decisions
in late 2014 in case either government needed to ask for clarification on any matter in the
Report. No clarifications were requested. The BCUC Inquiry 8.
My Expert Report also addresses the BCUC's Inquiry Respecting Site C.
9.
In 2017, the new provincial government referred the Project to the BCUC for review
by way of Order of the Lieutenant Governor in Council No. 244, dated August 02, 2017. A copy of this order, including the terms of reference for the British Columbia Utilities Commission Inquiry Respecting Site C, is attached as Exhibit "D" to this Affidavit. 10.
I
participated
in
the
review
process
by
providing
two
submissions
to
the
Commission.
11.
On November 1, 2017, the BCUC released its final report regarding its review of
the Project, the British Columbia Utilities Commission Inquiry Respecting Site C's Final
Report to the Government of British Columbia. A copy of this report is attached as Exhibit "E" to this Affidavit.
-4 -
Documents Relied on in Formulating My Expert Report 12.
The documents I reviewed and relied on in producing my Expert Report include
those identified in the footnotes of my Expert Report. I also relied on my experience with, and knowledge of, the record before the JRP, which is maintained online and made publicly
available
by
the
Canadian
Environmental
Assessment
Agency
at
http://www.ceaa.gc.ca/050/documents-eng.cfm?evaluation=63919, as well as my review of documents made publicly available during my participation in the BCUC Inquiry Respecting
Site
C,
which
remain
available
online
through
the
BCUC
website,
http://www.sitecinquiry.com. I have also reviewed:
(a)
A letter from the Deputy Minister, Ministry of Energy, Mines and Petroleu m Resources, and the Deputy Minister, Ministry of Finance to Mr. David
Morton, Chair of the BCUC, dated November 15, 2017, a copy of which is attached as Exhibit "F" to this Affidavit; and
(b)
A letter from Mr. David Morton, Chair of the BCUC to the Deputy Minister, Ministry of Energy,
Mines and Petroleum Resources, and the Deputy
Minister, Ministry of Finance, dated November 23, 201 7, a copy of which is attached as Exhibit "G" to this Affidavit. 13.
Except where otherwise stated or implied, I assume that the facts and opinions
provided in the documents that I have relied on in my Expert Report accurately reflect the facts and opinions stated therein as those authors understand them.
14.
I swear this Affidavit in respect of the Plaintiffs' application for an injunctio n in this
proceeding.
4
w\
SWORN f0R-ARF4RMEB)~BEFORE ME at Vancouver, British Columbia, on 31/Jan/2018.
2
A eoinmissidner for Affidavits for British'Columbia
SONYA A. MORGAN Barrister and Solicitor
) ) ) ) ) ) )
Harry Sheldon Swain
This is Exhibit
" /"7 " referred to In the
affidavit
St/dcyn
sworn before me at V>c?hy\ Q
this^M
day of AaroafU
-
, 20 1^2
'"2^^J
A ComnTissionerYor t^ktf^rfffdavits Within British Columbia
SONYA A. MORGAN Barrister and Solicitor
EXPERT REPORT
Harry Swain January 31, 2018
-2Part One: Qualifications 1.
In 1977-79, I worked in the federal Department of Energy , Mines and Resources
as Canada's first Senior Advisor for Renewable Energy and then as Director General for Electricity,
Coal,
Uranium
and Nuclear Energy. While there
I co-authored the first
assessment of Canada's renewable energy prospects,1 and assiste d in chartering the Lower Churchill Development Corporation, a company whose purpose was to develop
hydroelectric projects in Labrador. 2.
In 1980 I served as British Columbia's Assistant Deputy Minister for Energy
Policy, assisting in preparing the original legislation establis hing the British Columbia Utilities Commission. As Deputy Minister of the federal Depart ment of Indian Affairs and Northern Development in
1987-92, I had general responsibility for the provision of
electricity on Indian Reserves, and for settling the grievan ces of Manitoba First Nations regarding the flooding of their reserves by Manitoba Hydro. These and other matters are referenced in my curriculum vitae, a copy of which is attache d to as Schedule "A" to this Expert Report.
3.
I was one of the authors of the Joint Review Panel on the Site C Clean Energy
Project (the "Panel" or "JRP")'s Report of the Joint Review Panel, Site C Clean Energy
Project, of May 1, 2014 (the "Report").2 Save for direct quotes from the Report, the views in this Expert Report are my own, not those of the Panel. The direct quotes are not necessarily the views of the sponsoring governments, or the British Columbia Hydro and Power Authority ("BC Hydro" or the "Proponent"). Part Two: Joint Review Panel Report 4.
The Terms of Reference of the Panel were contained in an Amended Agreement
to Conduct a Cooperative Environmental Assessment, includin g the Establishment of a
Joint Review Panel, of the Site C Clean Energy Project between the Minister of the
Environment, Canada, and the Minister of the Environment, British Columbia of August 3, 2012, published at pages 326-41 of the Report.
1 H. Swain, R. Overend and T, Ledwell, "Canada's renewable energy prospects," Solar Energy.
23(1979)459-70
"
2 A copy of the Report is available online at http://www.ceaa.qc.ca/050 /documents/p6391 9/991 73E.pdf.
- 3A. Limitations on the ability of the JRP to reach conclusions or recommendations relevant to West Moberly First Nations Overview
5.
There
were
both
practical
and
policy
obstacles
to
reaching
unequivocal
conclusions relevant to West Moberly First Nations. The framing of BC's public policy, within which all analyses had to be conducted, meant that a number of electricity supply alternatives less damaging to the Peace River First Nations could not be considered. The
Environmental
Impact
Statement
("EIS")
Guidelines
were
deficient
in
some
important ways, meaning that the EIS contained little relevant analysis on certain topics,
notably cumulative, or province-wide economic, effects. As to practical matters, there was no assessment of electricity demand beyond that prepared by BC Hydro, nor any searching third-party investigation of the reliability of BC Hydro's load forecasts . The time and resources available to the JRP, together with the capacity of BC Hydro to produce
paper
(18,000
pages
in
the
Amended
EIS
alone)
and
the
process
requirements, meant that the Report was produced under considerable time pressure. Policy and Practical Limitations 6.
The production and analysis of the EIS was constrained by established public
policy. Government policy statements and especially policy embodied in statute and regulation guided both the Proponent and the Panel. Practically, this meant that BC government restrictions in the Clean Energy Act, SBC 2010, c 22 ("C/ean Energy Act') ruled out a number of sources of supply which would have lessened or avoided the impacts on the interests of the West Moberly First Nations. Prohibited sources included:
(a)
The
Columbia
River
Entitlement,
a
resource
paid
for years
ago and
available to BC under treaty with the United States, was and is equal to
half the incremental power generated in the US Columbia River system by reason of the Canadian storage made available under the Treaty and amounting to approximately the production of Site C in a typical year
(discussed below). The reason this source could not be counted as part of
-4-
BC's base supply was that it was foreign,3 an odd stance in a province that lives by trade.
(b)
Nuclear energy, the sole available resource that has fewer greenhouse
gas
emissions
than
hydroelectricity,
a
source
not
associated
with
methylmercury in fish, and one which if built would not likely be on the
lower Peace River.4
(c)
Wind, solar, geothermal, run-of-river or tidal energy developed by, rather than
purchased
by,
BC
Hydro,
these
sources
being
reserved
for
Independent Power Producers (IPPs).
(d)
Burrard Thermal, an existing 900 MW gas-fired power plant (s. 13) which could have produced energy, especially at peak periods, more cheaply
than other sources.5
(e)
Despite s. 17 of the Clean Energy Act, the use of "smart meters" and a
"smart grid" for the management of available supply. Later ministerial directives prohibited time-of-use pricing for residential and commercial
customers, despite the known positive effects this could have on demand and despite the billion-dollar expenditure on smart meters by BC Hydro. 7.
In addition, certain procedural limitations were imposed on the Panel. The Panel
consisted of three members, and were assisted by about half a dozen researchers seconded from the two governments. Over eight months, the Panel examined about 18,000 pages of studies done or commissioned by BC Hydro, several thousand pages of intervenor submissions, held hearings in northeast BC and wrote and delivered its Report. The Panel had been promised expert assistance but when it said it wanted to hire a consultant in utility finance and economics, the Panel was told by CEAA that it would be required to develop a statement of qualifications, a statement of work to be done, to advertise this on MERX, and to select the cheapest compliant bidder following a formal evaluation of bids and interviews with candidates. As this would have taken
3 Clean Energy Act, ss. 2(a) and 6(2) 4 Ibid., s. 2(o). 5 Ibid. , s. 13
-5several months, the Panel was forced to perform its economic analysis with internal resources.
Amongst the Panel members and research assistants, I was the only one
with relevant economic training.
8.
The effect of these restrictions, together with the generous load forecasts of BC
Hydro, meant that pressure mounted from all sides to build Site C. Disallow ing the Columbia River Entitlement as part of BC's core supply, reserving all new non-Site C alternatives to the
IPP sector while making
BC
Hydro the judge of whether their
proposals were economic, prohibiting demand management through the use of alreadyinstalled "Smart Meters", and prohibiting the use of the existing Burrard Thermal plant even for peak days all conduced to narrow the choice to Site C, with its heavy load of consequences for the West Moberly First Nations.
9.
These
alternatives
would
have
required
disregarding
two
of the
legislated
objectives.6 The objective of cheaper rates would have been ensured by building less expensive supply alternatives, or by using demand management measure s, on an as-
needed basis rather than decades ahead of need. The objective of switching customers from
carbonaceous
to
hydroelectric energy
sources
contradicted
the
objective
of
cheaper rates by choosing electricity alternatives that were much more expensive than natural gas. I conclude that the effect of BC energy policy was to bias choices toward a
Project whose effects were disproportionately concentrated on the West Moberly First Nations.
tf. JHP findings with respect to the need for the Project "The Panel rejects, as a governing purpose, the maximization of the hydraulic potential
of the Peace River. "7 10.
BC Hydro justified the need for the Project in terms of three purposes: "(1) to
cost-effectively meet BC Hydro's forecast need for energy and capacity, (2) to meet forecast need in alignment with the provincial policy objectives of the Clean Energy Act and relevant B.C. Government policy statements, and (3) to cost-effe ctively maximize
the development of the hydroelectric potential of the Site C Flood Reserve which was
6 See ss. 2 and 6 of the Clean Energy Act. JRP Report, p. 272
-6-
established in 1957."8 The Panel rejected the last of these on the grounds that there was no legislative statement of this 1950's 'Two Rivers Policy' and that if accepted it would so tilt the scales in favour of Site C as an alternative to meeting the valid first two objectives as to render the entire JRP approach unnecessary. The Two Rivers Policy was simply an attempt to bias the analysis in favour of BC Hydro's preferred conclusion. "The Panel concludes that the Project must rest on its main claims— that it would supply electricity that B.C. customers would need and would pay for at a lower combination of cash and external costs than any alternative— and not on regiona l economic benefits ,"9 11.
BC Hydro argued that the Project would provide a suite of benefits to labour,
businesses,
First
Nations
municipalities
and
even,
surprisingly,
the
regional
environment. The view of the Panel was that these were for the most part simply geographical
displacements,
and
not
net
benefits.
A
different
suite
but
not
inconsequential suite of effects would have been felt if $7.9 billion was spent elsewhere, or not taken from ratepayers and spent at all. The 'local benefits ' argument is frequently
used by governments and project developers who want to create local enthusiasm and political support for a development regardless of the fact that those benefits will have to be paid for by others, with little net effect.
"The Panel cannot conclude on the likely accuracy of Project cost estimates because it
does not have the information, time, or resources. This affects all further calculations of unit costs, revenue requirements and rates. 12.
"10
In the view of the Panel, the real assessment of economic costs and benefits lay
with BC Hydro's first two statements of purpose noted above. A project passing these tests would have sufficient economic advantages over all alternat ives that it would pay its own costs and provide enough left over to compensate environmental and First Nations cost bearers for their losses. But there was no indepen dent analysis of the
claimed costs, only an attestation by KPMG, BC Hydro's auditors , that best practices had been used. This led to the Panel's recommendation that key economic aspects be
referred to the
BCUC for detailed investigation
3 JRP Report, p. 271 9 JRP Report, p. 279 10 JRP Report, p. 280
by the sole public body with the
-7mandate, experience and expertise to do so. We were somew hat suspicious at the time that BC Hydro's experience with building large dams dated from the 1980s, and that there were few employees who had relevant experience, but this qualitative worry
manifested itself only in the conclusion above.11 In the event, our fears have been realized. The current estimate of the cost of the completed project is 35 percent more than the $7.9 billion promise of 2013, and there is more than six years to go to completion. The point is important, as the Panel's qualified conclusions about the relative attractiveness of the Project rested on cost estimates that have not been met. As with load forecasts, better work by BC Hydro would not have led to a decision to build SiteC.
"The
Panel
concludes
that
BC
Hydro's
forecasting
techniques
are
sound,
but
uncertainties necessarily proliferate in long-term forecasts ,"12 13.
This conclusion was based on assurances that BC Hydro's load forecasting
methods were consistent with industry standards, and had been approved by BCUC in
2008. It was also based on the description of these method s in the EIS. My current opinion, based on another four years of experience and time for analysis, is that this statement was too generous, and that the Panel's concern about the effect of price on demand - see below - should have carried greater weight. My presentation to the
BCUC Inquiry on October 14, 2017 summarizes this concern and gives illustrative calculations of why this should be so. 13
14.
BC Hydro's demand forecasts are persistently and systematically wrong.14 The
Panel did not have the expertise, time, or testimony to challen ge BC Hydro's methods. I
11 B.C., Manitoba, Quebec and Newfoundland are currently all engaged in large hydroelectric developments. Only Quebec has had continuous experience over decades of building such projects. Hydro Quebec is the only company performing within time and on budget. 12 JRP Report, p. 285
13 Harry Swain, "Testimony to BC Utilities Commission on Site C," 14 Oct. 2017. Commission document F-36-2, http://www.sitecinquirv.com/wp-content/uploads/2017/10/0Q62 1 F362 SwainH SiteC Submissions.pdf
14 BC Utilities Commission, "Site C - Alternative Resource Options and Load Forecast Assessment," 8 September 2017. Commission document A9. http://www.sitecinquiry.com /wpcontent/uploads/201 7/1 0/00700 A-9 Site-C-lnquiry Deloitte-LLP-lnde pendent-Report-No2.pdf . R. Hendriks, P. Raphals and K. Bakker, "Reassessing the need for Site C," Program for Water Governance, University of BC, April 17; online as BCUC Commission documen t F-106-1 at http://www.sitecinquirv.com/wp-content/uploads/2017/08/DQC 900127 F106-1 Proqram-on-WaterGovernance
University-of-British-ColumbiaUBC Site-C-Submission Redacte d.pdf Figs. 1-9, pp. 16-25.
-8wish we had had the benefit of the later work of Deloitte or the UBC Program on Water
Governance in 2013-14. BC Hydro's flawed load forecasting was more central to the Site C decision than I appreciated at the time. There is no reason now to believe that much new power, if any, will be required in the next 20 to 30 years.
"The Panel concludes that it is unlikely that the transmission and liquefaction energy
requirements of the new liquefied natural gas industry will be satisfied by any source except natural gas itself, and thus that BC Hydro's Integrated Resource Plan sensitivity
scenario of 'Low Liquefied Natural Gas' forecast is most likely correct Z'15 15.
The Panel regarded the forecast allowances for LNG skeptic ally. No other LNG
plants in the world used grid electricity for compression and liquefaction, and no BC
projects were near final investment decisions.16 Successful LNG plays around the world were based for the most part on associated gas without local uses, not on greenfield
operations, as was being proposed for northeastern BC. Neverth eless, the exploration, tracking, water use and landscape fragmentation caused by the development of the Montney Formation and its condensate-rich gas was acceler ated by LNG feasibility work, with concomitant effects on West Moberly interests.
"The Panel concludes that basing a $7.9 billion Project on a 20-year demand forecast without an explicit scenario of prices is not good practice. Electricity prices will strongly
affect demand, including Liquefied Natural Gas facility demand . 16.
Âť 17
Demand is driven by prices, and thus load forecasts should be as well. We
calculated an implicit price elasticity from BC Hydro load forecas ts, but it was combined with the impact of DSM (demand-side management) measur es in a way that made it difficult to untangle the separate effects. In any case, calcula ting long-term elasticity of
demand (and cross-elasticity with respect to natural gas, which has proven plentiful and cheap) requires a forecast of rates, which BC Hydro did not provide but which a competent utility and board must require. An elasticity-base d load forecast requires
modelling and computational capacity which was beyond the capacity of the Panel.
15 JRP Report, p. 286 16 JRP Report, p. 286 17 JRP Report, p. 287
-9"The Panel concludes that the demand-side management yield ought to at least keep up with the growth in gross demand, and therefore the potentia l savings from 2026 to
2033 may be understated.
Using BC Hydro's price elasticity of demand of -0.57,
accepting BC Hydro's forecast of gross demand, and positing a real price increase of 50
percent from 2014 to 2033, the Panel concludes that net demand in 2033 is likely to be about 65 terawatt hours. The Panel concludes that demand manage ment does not appear to command the same degree of analytic effort as does new supply. 17.
Âť 18
BC Hydro tends to believe that only DSM - specific expenditures by the company
to induce or require lower energy consumption - are effective. They underrate the effect of price on consumer behaviour, usually allowing market price signals and responses to their expenditures to overlap, with the latter being much the more important. But price elasticity is highly important, and with the increases in rates which can be foreseen from their present debt and deferral accounts and a continuing capital expenditure budget,
substantial real rate increases are inevitable. This can be expecte d to depress the demand for power to the point where the only market for margina l supply additions is
the US spot market.19 Site C will be a mostly stranded asset for many years. If BC Hydro's load forecasting had taken account of normal market respons es, especially for its residential and commercial demand, the case for the need for the Project could not have been made.
"The Panel concludes that the Proponent has not fully demons trated the need for the Project on the timetable set forth.
18.
•• 20
In the face of load forecasts that were not of investment grade and plausible
demand scenarios requiring much less power, the Panel's conclus ion was inescapable. BC Hydro did not, and still has not, made a case for building any new power for many
years. The date for new power requirements keeps receding, and as noted below, there are numerous less expensive alternatives. The fact that constru ction began in 2015 meant that no time was allowed to go beyond consultation with First Nations to a deeper exploration of treaty rights. 18 JRP Report, p. 291 19 Alberta is not a market. Site C power would be roughly twice the price of Alberta's gas-fired systems
even without the cost of the necessary new transmission lines.
20 JRP Report, p. 306
- 10C. JRP findings on alternatives to the Project 19.
BC
Hydro
defined
their portfolios of alternatives
as
resource
development
opportunities capable of producing 1,100 MW of capacity and 5,100 GWh of energy the same as the output from Site C. But these numbers were unrelated to the demand side of their load forecast. Nevertheless all alternatives were required to produce this output. A more logical way of addressing the problem would have been to array supply and DSM alternatives in terms of what each could contribute at a given price. A rational way of meeting some posited - or experienced - demand would be to commission the
cheapest sources first, up to the desired level of production. Since all alternatives were quantitatively smaller than Site C, there would have been an opportu nity to use cheaper
sources to follow the market and thus avoid the planned large losses of Site C in its early years.
"The Panel concludes that B.C. will need new energy and capacit y at some point. Site C would be the least expensive of the alternatives ,
and its cost advantages would
increase with the passing decades as inflation makes alternat ives more costly.
20.
"21
This statement was based on a $7.9 billion dollar cost for Site C, a cost which
has increased by 35 per cent in the first 2.5 (of a scheduled eight) years of construction. As well, the cost of alternatives has declined dramatically in the last four years. It is no longer true that Site C would be the least expensive alternative. The conclusion that its cost advantages would increase over time was based on the Panel's assumption that the Project would be financed over a period of time normal in the utility business - say,
30 years. We did not contemplate a 70-year term or an all-debt structure. I do not believe that BC Hydro can forecast the continuation of present low rates four to six decades into the future. These changed circumstances have not stopped BC Hydro
from repeatedly quoting the conclusion above.22 "The Panel concludes that methodological problems in the weighin g and comparison of
alternatives
render unitized
energy
costs
only
generally reliable
as
a
guide
to
21 JRP Report, p. 305 22 BC Hydro, "BC Hydro responds to Dan Levin of The New York Times," News , 13 December 2016 ; Dave Conway (Community Relations Manager, Site C Clean Energy Project, BC Hydro), "Site C presents better long-term value of British Columbians," Business in Vancouv er, 15-21 November 2016, p. 33
-11 investment. The Panel is more confident about the ranking of BC Hydro's projects, or
independent
power
producers'
projects ,
or
demand
side
management
projects
considered as separate lists. Uncosted attributes such as the ability to follow ioad, oeopraphical diversity , or the ability to assist with the integration of intermittent sources need
more
analytical
attention.
The
Panel concludes
that
a
number of supply
alternatives are competitive with Site C on a standard financial analysis , although in the
long term. Site C would produce less expensive power than any alternat ive." 23 21.
Today, I would stress that "long term" means the period beyond the Project's
amortization. I would further say that the work not done, to the detriment of First Nations' interests, included an assessment of the costs of various new technologies and their probable trajectories over the next several years. The speed of technological change has taken many large institutions by surprise. Had the Panel been able to engage its own experts, both new evidence and a challenge to BC Hydro assumptions
would have been possible. The absence of a practical capability to engage such people meant that practical alternatives that would have had much less, even zero, impact on the rights and interests of West Moberly and Prophet River First Nations did not get a fair hearing.
"The Panel concludes that a failure to pursue research over the last 30 years into B.C.'s geothermal resources has left BC Hydro without information about a resource that BC Hydro
thinks may offer up
to
700 megawatts of firm
economic power with low
environmental costs. " 24 22.
Sometimes alternatives had been taken off the table by BC Hydro derelictions. In
1983, when faced by BCUC with the same conclusion the JRP reached ("not on the
timetable set forth"),25
BC
Hydro was
advised to
investigate the
possibilities of
geothermal energy. A modest amount of work was done in the Coast Range Mountains but shortly
abandoned.
In
recent years,
BC
Hydro
has eschewed
research
and
23 JRP Report, p. 298 24 JRP Report, p. 299 25 "The evidence does not demonstrate that construction must or should start immediately or that Site C is the only or best feasible source of supply..." B.C. Utilities Commission, Site C Report, Report and Recommendations to the Lieutenant Governor-in-Council, May 1983; available at
https://www.sitecproiect.com/sites/default/files/1983050Q%20Report%20and%20Reco
o%20the%20Lieutenant%20Governor%20in%2QCouncil%20-%20BCH.pdf.
mmendations%20t
This excellent report is an
example of the quality of work that can be done by an alert and diligent regulator.
- 12-
development entirely, as being, in its view, inappropriate for its role. The consequence was that BC Hydro's EIS stated that there was perhaps 700 MW of firm power available at prices
at or below
characterized
it could
Site C,
but since the
resource
had
not
considered
available
possibility.
be
an
not been
adequately
The
Canadian
Geothermal Association vigorously disputed this conclusion, and more recently has
come forward with concrete proposals,26 but the effect of Site C will be to put off for many years any new call for IPP power.
"The
Panel
concludes
that
analytic
efforts
to
quantify
the
potential
benefits
of
geographic diversity and climate-induced changes to hydrolo gy could allow a better characterization of important resources.
23.
" 27
BC Hydro presented detailed estimates of the costs of allowab le alternatives, but
their work on Site C was much more thorough than their work on DSM or on the renewable options that were reserved by policy to IPPs. In any event, the Panel had no
capacity to challenge any of this work and all parties had to rely on it. 24.
The principal alternatives for increasing supply or moderating demand can be
grouped as follows:
(a)
Conservation, substitution, demand-side management (DSM). These were all approved under the Clean Energy Act. For a generation-ori ented utility, these were unfashionable alternatives, and appeared not to garner the same level of analysis as supply alternatives.
(b)
Thermal (gas-fired, oil-fired, coal or nuclear,
all of which were either
prohibited or disfavoured by public policy in BC). The outrigh t prohibition of nuclear alternatives, and the strong discouragement of carbonaceous sources in the Clean Energy Act removed options that might have reduced pressures on First Nations interests. Putting nuclear aside on grounds of public acceptability, small amounts of gas used for peaking power could have put off the date for large new generation capacity for years. But the
Clean Energy Act prohibited the operation of Burrard Therma l, a large 26 CanGEA, BCUC documents F-66-3 and F-66-4, Oct. 14 and 18, 2017 27 JRP Report, p. 300
- 13existing plant near load centre. It discouraged new uses for gas, despite the governmental
enthusiasm for liquefying that gas
and
shipping
it
abroad for burning.
(c)
Hydroelectricity
(including
big
dams,
the
Columbia
smaller run-of-river operations, micro hydro).
River
Entitlement,
Here, the major problem
was that the prohibition against counting BC's share of the downstream
benefits of the Columbia River Treaty meant that a large source - about
1,300 MW and 4,100 GWh, 28 versus Site C's 1,100 MW and 5,100 GWh which
BC
had
acquired
at the cost of flooded valleys on the upper
Columbia System, was assumed to be unreliable. In fact, it is available under a treaty with the United States, normally a reliable partner. The treaty may be denounced by either side with ten years' notice: a highly unlikely event, in my opinion, because of the great benefits this historic
investment confers on both countries, but in any case the ten-yea r clause was inserted so that there would be plenty of time to construct alternatives if need be. As it stands, the BC government instantly sells its entitlement back to the US at spot market prices, which are generally less than a third
of the cost of Site C power.
(d)
Tidal: A convincing case was made that this resource is not econom ic, or technologically mature enough, to be considered.
(e)
Geothermal: As noted, this may be a highly attractive source in economic, environmental,
and
First
Nations'
concerns,
but
it
was
left
out
of
consideration because neither BC Hydro nor its owner took the advice of the BC Utilities Commission in 1983.
(f)
Wind:
BC
Hydro saw opportunities for wind power and included it in
portfolios of alternative means to generate 5,100 GWh a year. Their costs
28 Cathy Eichenberger, BC Ministry of Energy, Mines and Mineral Developm ent, personal communication.
The downstream benefits vary with precipitation and are currently under negotiation, with the US side claiming they are worth a lot less money after 2024.
- 14-
estimates were high at the time and are even more so now.29 It would now appear
that
wind
alone
could
accommodate
all
of
BC's
marginal
requirements for decades at prices much less than Site C. BC Hydro was concerned about integrating an intermittent resource, but admitted that the
very large existing storage capacity in its reservoirs was underu tilized.
(g)
Solar photovoltaic:
Cost
and
the
same
concern
about integration
of
intermittent sources led BC Hydro to add rather arbitrary additio ns to their assumed price for solar. In addition they attributed a higher cost of capital to the solar, wind, and run-of-river IPPs, and ignored the fact that IPPs would
pay taxes.
Here,
perhaps more obviously than elsewhere,
BC
Hydro's assessment methodology produced results biased in favour of Site C.
25.
All supply alternatives save Site C and DSM were prohibi ted by policy from
exploitation by BC Hydro. They were reserved for IPPs on grounds of their assumed
greater efficiency. BC Hydro became their sole, and not always enthusiastic, consumer. What in my opinion is a cultural or institutional preference for large-scale hydro in BC Hydro was reinforced by the policy of the British Columbia government. 26.
In brief, BC Hydro did not favour run-of-river IPP projects, whose modest scale
would have made them suitable for First Nations' develop ment, on grounds of cost and seasonal intermittency; nor wind on grounds of unrelia bility; nor solar on grounds of
diurnal intermittency and seasonal variation. Storage, other than that represented by the large quantities of water behind dams on the Columb ia and Peace systems, was thought
hopelessly
straightforward
expensive,
although
integration of much
that
existing
storage
more renewable energy,
would
allow
the
so that the relatively
inexpensive wind and solar options could be added to assure d supply. 27.
The JRP missed one point which should have been obviou s to BC Hydro, namely
that IPP contract renewals could be expected to be less expensive than the initial contracts. Most such projects can be expected to substa ntially amortize their capital
29 The median of 42 wind bids in Xcel's Colorado solicitation was US$1 8. 1 0/MWh for industrial (42,000 MW) quantities of electricity, which raised eyebrows througho ut the industry.
- 15costs in an initial contract, but the equipment will typically have a longer operation al life.
Lowering the presently very high costs of IPP power30 would moderate somewhat the pressure on rates while still seeing a flow of taxes to all levels of government.
Part 2: The BCUC Inquiry of 201 7 28.
Before the JRP was created, the BC government decided not to refer the Project
to the BCUC by exempting it from the BCUC's review through s. 7 of the Clean Energy Act , s. 7(1 )(d).
29.
The
arguments.
Panel decided to pay special attention to the economic and financial It was
frustrated,
as
noted
above,
by the
inability
to
hire
specialist
assistance.
30.
At the conclusion of its work, the Panel felt more strongly than ever that the
Project should be referred to the BCUC, at least for certain parts of the analysis that the panel was unable to perform. In the JRP Report, the Panel recommended that if the
Project should proceed, "a first step should be the referral of Project costs and hence unit energy costs and revenue requirements to the BC Utilities Commission for detailed
examination."31 In addition, the Panel recommended that, "if Ministers are inclined to proceed, they may wish to consider referring the load forecast and demand side
management plan details to the BC Utilities Commission."32 These recommendations
were rejected.33 31.
In 2015 and 2017, new governments were elected in Ottawa and BC. The new
federal government did
not propose to
reopen
issues concluded
by the
previous
government. In BC, the new government similarly declined to rescind the 2014 decision approving the
Project,
opting
instead for a three-month study of a subset of the
economic issues it raised while not slowing construction.
On August 2, 2017, the
provincial government by Order-in-Council 244, tasked the BC Utilities Commiss ion with
a review to be delivered by November 1 , 2017.
30 $88.90/MWh for the most recent fiscal year. BC Hydro, Annual Service Plan Report 2016/17, p. 24 31 JRP Report, p. 280 32 JRP Report, p. 306 33 B.C Environmental Assessment Office, "EAO Executive Director's Response to the Joint Review Panel Report for BC Hydro's Site C Clean Energy Project," n.d. [Dec. 2014], pp 14, 15
- 1632.
The Terms of Reference of the review were highly restricti ve. The Commission
had to accept as the basis for its analysis the load forecas t of BC Hydro. Since that forecast seemed to require new generation, the Commission was required to assess alternatives to Site C. Those alternatives had to be within the scope of the Clean Energy Act. And since the most sensitive point for the provincial govern ment was the effect on rates
the
Commission
was
supposed to make an
assessment of the effects of
alternatives on what ratepayers would face in their monthly bills, both before and after the next election. It had to provide a preliminary report in six weeks, hold truncated public hearings, and deliver a final report in 12 weeks. The BCUC was asked, in other words, to focus on a subset of financial questions, leaving aside First Nations' and environmental concerns, as well as the overall justification of the Project in terms of its economic costs and benefits.
33.
This was a poisoned chalice. If the future held less demand than posited by BC
Hydro's discredited forecasts, then the question of alternatives was moot. But the Terms of Reference made it clear that BCUC had to devote a substan tial part of its available staff time to the analysis of alternatives that might not be required at all, or for a very long time.
34.
The Terms of Reference did not allow for a rigorous analysi s of the financial and
economic issues posed by Site C. They focused the Commi ssion on costs, not needs. They did not allow the Commission to examine BC Hydro's suspect load forecast. 35.
I
urged
the
Commission
to take
an
expansive
view of its
mandate.
In
a
submission on August 28, 2017, I argued that the Commission should not solely rely on
BC Hydro's forecast of peak capacity demand and energy demand .34 In the event, the Commission limited its analysis to the low bound of BC Hydro's forecast range which was already too high. Their report and reasoning made it clear that, unfettered, they would have adopted a lower forecast.
34 Swain, H. BCUC F-36-1 , 28 August 2017
- 1736.
A remarkable 28 pages of its final report conce rns environmental, social, and
First Nations issues it was instructed to ignore.35 37.
Subsequent to the delivery of the BCUC Repor t on Nov. 1, 2017, two provincial
deputy ministers signed
a
letter raising questions about the
BCUC
analysis
and
results,36 to which the BCUC responded.37 In my view, the deputies' letter exhibited prejudice and a bias towards completion of Site C. 38.
In the event, and directly as a result of its limited terms of reference, the BCUC
inquiry produced an equivocal result that allowe d the provincial government to conclude that, even though the Project was economicall y loss-making, the assumed but incorrect requirement to pay off the sunk costs immediatel y would be an unbearable burden for ratepayers, and so the Project should continue.
Date:
31/Jan/2018
Harry Sheldon Swain
35 BC Utilities Commission, Inquiry Respecting Site C: Final Report to the Government of British Columbia, November 1, 2017, pp. 10-37
36 D. Nikolejsin and L. Wanamaker, letter to D. Morton , 15 November 2017; 37 D. Morton, letter and enclosure to D. Nikolejsin and L. Wanamaker, 23 November 2017
- 18-
Schedule "A" January 2018
Harry Sheldon SWAIN Address:
838 Pemberton Road, Victoria, B.C. V8S 3R4, Canada
Phone: 250-370-0001
E-mail: swainh@telus.nct Born:
26 July 1942, Prince Rupert, B.C. Canadian citizen
Experience:
President, Trimbelle Limited, July 1998; continued as Trimbelle Investmen ts Limited, 2008; Partner, Sussex Circle, September 1998-2002 Current:
President, Trimbelle Investments Limited Associate Fellow, Centre for Global Studies, University of Victoria Board member and Vice-President, Foundation for the Victoria Symphony Past:
Board member, Treasurer and President, Victoria Symphony Society, 2008-15 Chair, Joint Review Panel, Site C, 2013-14 Advisory Board, Toronto Addiction Rehabilitation Centre
Advisory Board, School of Public Administration, University of Victoria Director, Pacific Climate Impacts Consortium Advisory Board, Pacific Marine Analysis and Research Association Audit, and Evaluation and Performance Measurement Committees, Departmen t of Indian Affairs and Northern Development Subcommittee on Public Inquiries, Committee on Judicial Independence, Canadian Judicial Council Partner, Sussex Circle Inc. Chair, Research Advisory Panel, Walkerton Inquiry, Ontario, 2000-02 Chair, Expert Panel on water and wastewater infrastructure, Ontario,
2005 Chair, Expert Panel on safe drinking water for First Nations, Canada, 2006 Fellow and Governor, Royal Canadian Geographical Society Management Board member, Canadian Geographic Enterprises Board member, Canadian Bank Note Limited Board member, Nikron Technologies Inc. Board member and Audit Committee Chair, OSIFA Board member, OMEIFA Board member, Ontario Infrastructure Projects Corp. Chair, Canadian Biosciences Commercialization Institute Member, Founders Network Editorial Board, Isuma Senior Managing Director, Corporate and Investment Banking, SG Canada, March 1998 Director, Hambros Bank Ltd., Sept. 1996, CEO, Hambros Canada Inc., and Representative of Hambros Bank Limited in Canada, April 1997 Directorships: Hambros Bank Limited (U.K.), Hambros Canada Inc., Strategic Value Corp., Bonham & Co HFM (UK) Ltd., 1996-98; Hambros Tower Hill Holdings Ltd. 1996-98 Special Advisor to the Minister of Finance, Ottawa, October 1995; on secondment to the Bank of Montreal, Toronto, January 1996
- 19 -
Deputy Minister, Department of Industry, Ottawa, September 1992
Directorships: Business Development Bank of Canada, Public Policy Forum, Canadian Tourism Commission, Communications Research Centre Deputy Minister, Department of Indian Affairs and Northern Developme nt, Ottawa, October 1987
Assistant Secretary to the Cabinet for Economic and Regional Development Policy, Privy Council Office, May 1985 Assistant Deputy Minister (Plans), Department of Regional Industrial Expansion, Ottawa, August 1984
Director, Industry, Trade and Technology, January 1981; Deputy Secretary (Projects), May 1982; Deputy Secretary (Operations), November 1982, Ministry of State for Economic (and Regional) Development, Ottawa, January 1981
President, H.S. Swain and Co. Ltd., Sidney, B.C., September 1980 Assistant Deputy Minister (Energy), B.C. Ministry of Energy, Mines and Petroleum Resources, Victoria, January 1980 Senior Advisor, Renewable Energy Resources; Director General, Electrical Coal Uranium and Nuclear Energy; Energy Mines and Resources Canada, Ottawa, January 1977
Executive, Temporary Assignment Pool, Treasury Board Secretariat; on loan to Department of Regional Economic Expansion as Co-Chairman, Intergovernmental Waterfront Committee, Halifax; and in Policy and Coordination Branch, Ottawa, January 1976 Project Leader and Research Scholar, Urban and Regional Systems Project, International Institute
for Applied Systems Analysis, Laxenburg, Austria, January 1974 Director, External Research, Ministry of State for Urban Affairs, Ottawa, May 1971 Assistant Professor, Department of Geography, University of British Columbia, Vancouver, September 1970
Lecturer, Department of Geography, and Lecturer in Geography at Scarborough College,
University ofToronto, September 1968 Education:
Partners Directors and Officers Examination, Canadian Securities Institute, 1997
University of Victoria, 1997: LL.D Cambridge University, 1969-70: postdoctoral fellow, St. Catharine's College
University of Minnesota, 1964-68: graduate student in urban geography; collateral study in economics, statistics and sociology; M.A. 1967, PhD 1970 University of British Columbia, 1960-64: honours in geography; collateral study in economics and architecture; B.A. (Hons.) 1964
-20Publications Books, monographs, etc.:
With Cotton Mather, St. Croix border country, Pierce County Geographical Society, Prescott, Wisconsin, 1968 Reviewed by W.F. ZeLinsky, Annals AAG, Dec. 1970 802-3; by Pierce F. Lewis, Geogr. Rev, 1970, 159-61; and by Earl Chapin, St. Paul Pioneer Press Central place networks, doctoral dissertation, University of Minnesota, 1970, 379pp. (Ed.), National settlement strategies east and west, ILASA CP 75-3, 1975 (Ed., with Ross D. MacKinnon), Issues in the management of urban systems, IL\SA CP 75-4, 1975
(Ed.), The IIASA project on urban and regional systems, IIASA SR 75-1, 1975 (Ed., with Martyn Cordey-Hayes and Ross D. MacKinnon), special issue of Environment and Planning A, 7:7, papers from December 1974 conference on national systems and strategies, ILASA, October 1975 With J.K. Stager, Canada North: journey to the High Arctic, Rutgers University Press, 1992 With Fred Lazar and Jim Pine, Watertight: the case for change in Ontario's water and wastewater sector, report of the water strategy expert panel, Queen's Printer, Toronto, July 2005
With Stan Louttit and Steve E. Hrudey, Report of the expert panel on safe drinking water for First Nations, Canada, Indian Affairs and Northern Developm ent, Ottawa, November 2006 Oka: a political crisis and its legacy, Vancouver: Douglas & Mclntyre, 2010. ISBN 978-1-55365429-2.
Excerpted in The Citizen, Ottawa, 19 September 2010, A8 Donner Prize runner-up for 2010.
With James Mattison and Jocelyne Beaudet, Report of the Joint Review Panel on the Site C Clean Energy Project, Canadian Environmental Assessment Agency, Ottawa, and BC Environmental Assessment Office, Victoria, May 2014 Articles:
with Peter P. Waller, "Changing patterns of oil transportation and refining in West Germany," Economic Geography 43:2 (1967) 143-56 With J. Parlour and M. Ulrich, "System, secretariat, and spatial scale," Ministry of State for Urban Affairs DP 1, 28 May 1971, Ottawa With J. V. Minghi and D. Rumley, "The Vancouver civic election of 1970: a preliminary report," 97 114 m R. Leigh, ed., Contemporary geography: western viewpoints, vol. 12 of B.C. Geographical Series, Vancouver, 1972
"Information requirements for urban research and policy," Canadia n Surveyor, 26:5 (1972) 484-7 "Research for the urban future," 22"d International Geograp hical Congress, Montreal, 15 August 1972
With Allan O'Brien, "Some avenues for urban systems analysis," in M. Rousselot, ed., Proc. IIASA planning conference on urban and regional systems, IIASA38, Laxenburg, 1973, 23-5 and 163-8
38 International Institute for Applied Systems Analysis, Laxenbur g, Austria
-21 -
"Models of national settlement systems: comments on two papers by Cordey-Hayes," IIASA WP 74-
31, August 1974
"IIASA holdings of materials on national settlement systems and policies," IIASA WP 74-47, September 1974
"Solar option: the cost of land," IIASA WP 75-15, Feb. 1975 "Revised 1975 program: management of urban and regional systems," IIASA URB-1, February 1975
"Evaluating growth proposals," IIASA WP 75-33, April 1975 With John Casti, "Catastrophe theory and urban processes," IIASA RM 75-14, April 1975 Reprinted in J. Cea, ed., "Optimization techniques: Proc. 7th IFIP Conf., Nice, Sept., 1975," Lecture notes in computet science, 40 (1976) 388-406, SpringerVerlag, Berlin
With Claire de Narbonne, "French urban research institutions," IIASA RM 75-19, May 1975; rev. as "Urban research institutions in France,' October 1975
With Peter Hall and Niles Hansen, "Urban systems: a comparat ive analysis of structure, change and public policy," IIASA RM 75-35, July 1975 With Peter Hall and Niles Hansen, "Status and future directions of the Comparative Urban Regions study: a summary of workshop conclusions, IIASA RM 75-59, November 1975
With William C. Clark, "Hypotheticality, resilience and option foreclosure," IIASA WP 75-
80, July
1975
With Malcolm I. Logan, "Urban systems: a policy perspective," Environment and Planning A, 7:7 (1975) 743-55 Translated and reprinted in Mitteilungen des Oesterreichisches Institut fuer Raumplanung, Vienna With R. Overend and T.A. Ledwell, 'Canadian renewable energy prospects," Solar Energy 23 (1979) 459-70
"The Halifax-Dartmouth Waterfront project," in W.T. Perks and I.M. Robinson, eds., Urban and regional planning in a federal state: the Canadian experien ce, McGraw-Hill, New York, 1979, 271-81 "Temptation of corruption," Ethics in civil service, 128-37, National School of Public Administration, Warsaw, 1996 With Tim Garrard, "Resourcing the federal effort in investme nt promotion: Investment Partnerships Canada in light of international practices," Sussex Circle, Ottawa, June 2000 "Privatization in Canada and lessons for Russia," chapter 3 in A. Radygin, R. Entov, G. Malginov, Y. Gritsun, V. Bondarev, O. Prerdeina, H. Swain and T. Goodfello w, Transformation of ownership relationship: comparative analysis of the Russian regions and the general problems of the emergence of the new system of ownership rights in Russia, Institute for Economy in Transition, Moscow, 2001; also published in Russian With D. R. O'Connor, chapters 3, 5-8 and 15 of Report of the Walkerton Inquiry Part 2, Queen's
Printer, Toronto, May 2002
-22With J. Carruthers, K. Minden and C. Urban, "Corporate governanc e and accountability in Canada,"
section 5, pp. 137-74 in A. Radygin et a!, The problems of corporate governance in Russia and its regions, Institute for Economy in Transition, Moscow, 2002; also published in Russian
With Harvey Schipper and Gale Murray, "Moving forward, looking forward: a new path for Canada's health care system," The Change Foundation, Toronto, October 2003
"A strategy for safe drinking water," in S.E. Hrudey, ed., Drinking water safety: a total quality management approach, Institute for Risk Research, Universit y of Waterloo, 2003, 83; also www.ittneram.ca
"Canadian corporate bankruptcy: law and public policy," Ch. 7 in A.D. Radygin, A.E. Gontmakher, M.G. Kuzyk, I.V. Mezheraups, H. Swain, Yu. V. Simachov, N.A. Shmeleva and R.M. Entov, The institution of bankruptcy: development, problems, areas of reforming, CEPRA, Institute for Economy in Transition, Moscow, 2005. In Russian as HHCTHTYT EAHKPOTCTBA
With Ian D. Clark, "Distinguishing the real from the surreal in management reform: suggestions for beleaguered admuiistrators in the government of Canada," Canadian Public Administration, 48:4, pp. 453-476, winter 2005 In Russian in 3KOHOMtiuecKaH nontiTHKa, November 2006 "Mixed ownership companies in Canada," Institute for the Economy in Transition, Moscow, 2007
With Emma Sharkey, "Climate change and water users in B.C.," Pacific Climate Impacts Consortium, Centre for Global Studies, University of Victoria, August 2007 "Setting die scene: the challenge of climate change," Working Paper, Local Government Institute, School of Public Administration, University of Victoria, October 2007 With C.L. Abbott, K.E. Bennett, K. Campbell and T.Q. Murdock, "Forest pest and climate change symposium," Dunsmuir Lodge, Pacific Climate Impacts Consortiu m, Victoria, 14-15 October 2007 "Drinking water and wastewater: a primer," Policy Options, July-August 2009, 26-30
"Negotiating Treaty Land Entitlement in Saskatchewan," in Tasha Hubbard and Marilyn Poitras, The Land is Everything, Office of the Treaty Commiss ioner of Saskatchewan, 2014, 68-84
With Ian D. Clark, "Program Evaluation and Aboriginal Affairs: a history and a thought experiment," pp. 51-69 in E. Parson, ed., A Fine Balance, McGill-Queens University Press, 2015 With James Baillie, "Tsilhqot'in Nation v. British Columbia: aboriginal title and section 35," Canadian Business Law Journal, 56 (March 2015) 264-79 "Paths to reconciliation in a post-Tsilhqot'in world," Canadia n Business Law Journal, 58:3 Pec. 2016) 313-24 With Menaka Pai and Plarvey Schipper, "Putting people first: critical reforms for Canada's health care system," Health Care in Canada, 37:2, 3(2016): 13-31 "Site C: Complete, mothball or abandon?" Submission F44-1, BC Utilities Commission Inquiry
into Site C, 28 August 2017 "Testimony to the BC Utilities Commission," Vancouver, 14 October 2017
SITE C CLEAN ENERGY PROJECT ENVIRONMENTAL IMPACT STATEMENT GUIDELINES SEPTEMBER 5, 2012
Pursuant to the British Columbia Environmental Assessment Act and the Canadian Environmental Assessment Act
This is Exhibit "
' rsfarred to in the
nn SiQfr-ih
affidavit of
sworn before me at V \ GiCTH Q. , ^ this
day of CYq/ULCm'U , 20
A Commissioner for taKigg^Arfidavits Within British Columbia
SONYA A. MORGAN Barrister and Solicitor
is*a
British Columbia
Canada
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
TABLE OF CONTENTS TABLE OF CONTENTS
PREFACE TO THE ENVIRONMENTAL IMPACT STATEMENT GUIDELINES ACKNOWLEDGEMENTS
AUTHORSHIP
EXECUTIVE SUMMARY
ABBREVIATIONS AND ACRONYMS DEFINITIONS
Introduction
1.1 Guiding Principles 1.2 Purpose of the Environmental Impact Statement 1.3 Presentation and Organization of the EIS
3
XV XVI
1 1 1
1 3
Proponent Description
5
Project Overview 3.1
5
Project Governance Process
3.1.1
6
Scheduling
6
3.2
Project Location
6
3.3
Project Components and Activities Dam and Generating Station
3.3.1
3.3.1.1 3.3.1.2
Spillways
3.3.3
Reservoir
3.3.4
Transmission Line to Peace Canyon Access Roads and Rail
3.3.5 3.3.7
3.3.8 3.3.9 3.3.10 3.3.11 3.4
7 8
Earthfill Dam Generating Station
3.3.2
3.3.6
4
XIV
XVII
VOLUME 1 - INTRODUCTION, PROJECT PLANNING, AND DESCRIPTION
2
XII XIII
TABLE OF CONCORDANCE
1
X
Highway 29 Realignment Quarried and Excavated Construction Materials Worker Accommodation Construction Phase Activities Operations Phase Activities Decommissioning Activities References
8 9
9 9 10 10 10 10
10 11 14 14 14
Need for, Purpose of, Alternatives to, and Alternative Means of Carrying Out the
Project
4.1
15
Need for and Purpose of the Project
15
4.1.1
Need for the Project
15
4.1.2
Purpose of the Project
15
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
4.2
Alternatives to the Project Alternative Means of Carrying Out the Project References
4.3 4.4
5
Project Benefits.. 5.1
6
7
References
Assessment Process
15 16 16 16 18 18
6.1 6.2
Provincial Agencies, Departments and Organizations The Federal Authorities
18
6.3
18
6.4
Co-operative Review Process Permitting
6.5
References
19
18
19
Information Distribution and Consultation Public Information Distribution and Consultation
19
7.1 .1
20
7.1
7.1.2 7.2
7.2.1 7.2.2 7.3
7.3.1 7.3.2 7.4
Pre-panel Review Stage Construction Communication
19 20
Aboriginal Group Information Distribution and Consultation Pre-Panel Review Stage Construction Communication
20
Government Agency Information Distribution and Consultation Pre-Panel Review Stage
21
Construction Communication References
22
21 21 22 22
VOLUME 2 - ASSESSMENT METHODOLOGY AND ENVIRONMENTAL EFFECTS ASSESSMENT
23
8
23
Effects Assessment Methodology 8.1
Overview
23
8.2
Technical Studies and Planning
24
8.3
Selection of Valued Components
25
Identification of Candidate Valued Components - Step 1 Project Interaction Identification - Step 2 Selection of Valued Components - Step 3 Assessment Boundaries
25
8.3.1 8.3.2
8.3.3 8.4
26 28 28
8.4.1
Spatial Boundaries
28
8.4.2
Temporal Boundaries
29
8.5
8.5.1
Effects Assessment Methods Baseline Conditions
8.5.2
Analysis of Effects
8.5.2.1 8.5.2.2 8.5.2.3 8.5.2.4
8.5.3
Description of Potential Adverse Effects on Valued Components Identification of Mitigation Measures Characterizing Residual Effects Significance of Residual Effects Cumulative Effects Assessment
29 30 30 31
31 32 33 34
8.5.3.1
Spatial and Temporal Boundaries
34
8.5.3.2
The Project Inclusion List
35
ii
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
8.5.3.3 8.6 9
Analysis of Cumulative Effects
References
Environmental Background .. Previous Developments
9.1
9.2
Land
9.2.1 9.2.2 9.3
9.3.1 9.3.2 9.3.3 9.3.4 9.3.5 9.3.6 9.4
Geology, Terrain and Soils Land Status, Tenure, and Project Requirements. Water Surface Water Regime Water Quality Groundwater Regime Thermal and Ice Regime Fluvial Geomorphology and Sediment Transport Methylmercury Air
9.4.1
Micro-Climate
9.4.2
Air Quality
9.4.3 9.5 9.6 10 10.1
Fish and Fish Habitat Effects Assessment Valued Component Scoping and Rationale
10.2
Fish and Fish Habitat
10.2.1 10.2.2 10.2.3 10.2.4 10.2.5 10.3 11 1 1.1
Noise and Vibration Electric and Magnetic Fields References
Fish and Fish Habitat Spatial Boundaries Fish and Fish Habitat Temporal Boundaries Fish and Fish Habitat Baseline Potential Effects of the Project and Proposed Mitigation Summary of Residual Effects on Fish and Fish Habitat . References
Vegetation and Ecological Communities Effects Assessment Valued Component Scoping and Rationale
11.2
Vegetation and Ecological Communities 1 1 .2.1 Vegetation and Ecological Communities Spatial Boundaries .... 1 1 .2.2 Vegetation and Ecological Communities Temporal Boundaries 1 1 .2.3 Vegetation and Ecological Communities Baseline 11.2.3.1 Rare and Sensitive Ecological Communities 11.2.3.2 Rare Plants
36 36 37 37 37 37 40 40
40 42 43 43 45 46 46 46 47 48 49 49
49 50 50 50 51 51 52
53 53 53
53 54 54
54 55 55
56 Potential Effects of the Project and Proposed Mitigation 56 1 1 .2.5 Summary of Residual Effects on Vegetation and Ecological Communities... 57 1 1 .3 References 57
11.2.4
12
12.1
Wildlife Resources Effects Assessment Valued Component Scoping and Rationale
12.2 12.2.1
Wildlife Resources Wildlife Resources Spatial Boundaries...
57 58 59
59
iii
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
12.2.2 12.2.3
Wildlife Resources Temporal Boundaries Wildlife Resources Baseline
59
12.2.3.1 12.2.3.2
Butterflies and Dragonflies Amphibians and Reptiles
59
12.2.3.3
60
12.2.3.5
Migratory Birds Non-Migratory Game Birds Raptors
12.2.3.6
Bats
61
12.2.3.7
Furbearers
61
12.2.3.8
Ungulates
12.2.3.4
12.2.3.9
Large Carnivores 12.2.4 Potential Effects of the Project and Proposed Mitigation 12.2.5 Summary of Residual Effects on Wildlife Resources 12.3 References
13
59
59
60 61
61 62 62 62
62
Greenhouse Gases Effects Assessment Valued Component Scoping and Rationale Greenhouse Gases 13.2.1 Greenhouse Gases Spatial Boundaries 13.2.2 Greenhouse Gases Temporal Boundaries
63
13.2.3 13.2.4
64
13.1 13.2
Greenhouse Gases Baseline Potential Effects of the Project and Proposed Mitigation 13.2.5 Summary of Residual Effects for Greenhouse Gas 13.3 References
63
63 63 64 64
65 65
VOLUME 3 - ECONOMIC AND LAND AND RESOURCE USE EFFECTS ASSESSMENT 66 14
Economic Effects Assessment
14.1 14.2 14.2.1 14.2.2
14.2.3 14.2.4 14.2.5
Valued Component Scoping and Rationale Local Government Revenue
67
Potential Effects of the Project and Proposed Mitigation Summary of Residual Effects on Local Government Revenue
67
Labour Market 14.3.1 Labour Market Spatial Boundaries 14.3.2 Labour Market Temporal Boundaries 14.3.3 Labour Market Baseline 14.3.4 Potential Effects of the Project and Proposed Mitigation 14.3.5 Summary of Residual Effects on Labour Market 14.4 Regional Economic Development 14.4.2 14.4.3 14.4.4
14.4.5 14.5
67
Local Government Revenue Spatial Boundaries Local Government Revenue Temporal Boundaries Local Government Revenue Baseline
14.3
14.4.1
66
66
Regional Economic Development Spatial Boundaries Regional Economic Development Temporal Boundaries Regional Economic Development Baseline Potential Effects of the Project and Proposed Mitigation
Summary of Residual Effects on Regional Economic Development References
67 67 68 68 68
68 68 69 69 70 70 70 70 70 71 71
iv
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
15
15.1 15.2
Traditional Lands and Resource Use Effects Assessment Valued Component Scoping and Rationale
71 72
Current Use of Lands and Resources for Traditional Purposes 15.2.1 Current Use of Lands and Resources for Traditional Purposes Spatial
72
Boundaries
72
15.2.2
Current Use of Lands and Resources for Traditional Purposes Temporal
Boundaries
73
15.2.3 15.2.4 1 5.2.5
73
Current Use of Lands and Resources for Traditional Purposes Baseline Potential Effects of the Project and Proposed Mitigation Summary of Residual Effects for Current Use of Lands and Resources for
Traditional Purposes
15.3 16
16.1
References
Land and Resource Use Effects Assessment Valued Component Scoping and Rationale
16.2
16.2.1 16.2.2 16.2.3 16.2.4 16.2.5 16.3
Agriculture
Agriculture Spatial Boundaries Agriculture Temporal Boundaries Agriculture Baseline Potential Effects of the Project and Proposed Mitigation Summary of Residual Effects on Agriculture Forestry
16.3.1 16.3.2
Forestry Spatial Boundaries Forestry Temporal Boundaries 16.3.3 Forestry Baseline 16.3.4 Potential Effects of the Project and Proposed Mitigation 16.3.5 Summary of Residual Effects on Forestry 16.4 Oil, Gas and Energy 16.4.1 Oil, Gas and Energy Spatial Boundaries
74 74 74 74
75 77 77
77 77 78 79
79 79 79
79 80
80 80 80
16.4.2
80
16.4.3 16.4.4
80
Oil, Gas and Energy Temporal Boundaries Oil, Gas and Energy Baseline Potential Effects of the Project and Proposed Mitigation 16.4.5 Summary of Residual Effects on Oil and Gas 16.5 Minerals and Aggregates 16.5.1 Minerals and Aggregates Spatial Boundaries 16.5.2 Minerals and Aggregates Temporal Boundaries 16.5.3
Minerals and Aggregates Baseline 16.5.4 Potential Effects of the Project and Proposed Mitigation 16.5.5 Summary of Residual Effects on Minerals and Aggregates 16.6 Harvest of Fish and Wildlife Resources 16.6.1 Harvest of Fish and Wildlife Resources Spatial Boundaries
16.6.2 16.6.3 16.6.4 16.6.5 16.7
16.7.1 16.7.2
Harvest of Fish and Wildlife Resources Temporal Boundaries Harvest of Fish and Wildlife Resources Baseline Potential Effects of the Project and Proposed Mitigation Summary of Residual Effects on Harvest of Fish and Wildlife Resources .... Outdoor Recreation and Tourism
Outdoor Recreation and Tourism Spatial Boundaries .... Outdoor Recreation and Tourism Temporal Boundaries
81 81 81 81 82 82 82 83 83 83 83
83 84
85 85
85 85
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
16.7.3
Outdoor Recreation and Tourism Baseline Potential Effects of the Project and Proposed Mitigation 16.7.5 Summary of Residual Effects on Outdoor Recreation and Tourism 16.8 Navigation 16.7.4
86 86
16.8.1
Navigation Spatial Boundaries
86
16.8.2
Navigation Temporal Boundaries
87
16.8.3 16.8.4
Navigation Baseline Potential Effects of the Project and Proposed Mitigation 16.8.5 Summary of Residual Effects on Navigation 16.9 Visual Resources 16.9.1 Visual Resources Spatial Boundaries 16.9.2 16.9.3
Visual Resources Temporal Boundaries Visual Resources Baseline
16.9.4 Potential Effects of the Project and Proposed Mitigation 16.9.5 Summary of Residual Effects on Visual Resources 16.10 References VOLUME 4 - SOCIAL, HERITAGE, AND HEALTH EFFECTS ASSESSMENT.. 17
85 86
Social Effects Assessment Valued Component Scoping and Rationale 17.2 Population and Demographics 17.2.1 Population and Demographics Spatial Boundaries 17.2.2 Population and Demographics Temporal Boundaries 17.2.3 Population and Demographics Baseline 17.2.4 Potential Effects of the Project and Proposed Mitigation 17.2.5 Summary of Residual Effects on Population and Demographics 17.3 Housing
17.1
17.3.1 17.3.2
Housing Spatial Boundaries Housing Temporal Boundaries
17.3.3
Housing Baseline 17.3.4 Potential Effects of the Project and Proposed Mitigation 1 7.3.5 Summary of Residual Effects on Housing 1 7.4 Community Infrastructure and Services 17.4.1 17.4.2 17.4.3 17.4.4
1 7.4.5 17.5
Community Infrastructure and Services Spatial Boundaries Community Infrastructure and Services Temporal Boundaries .. Community Infrastructure and Services Baseline Potential Effects of the Project and Proposed Mitigation
Transportation Spatial Boundaries Transportation Temporal Boundaries 17.5.3 Transportation Baseline 17.5.4 Potential Effects of the Project and Proposed Mitigation 1 7.5.5 Summary of Residual Effects on T ransportation 17.6 References
18.1
87 88 88 88 88
88 89 90 90 91 91
91 92 92
93 93 93 94 94 94
94 94 94 95
95 95 95 95
96
Summary of Residual Effects on Community Infrastructure and Services .... 96 Transportation
17.5.1 17.5.2
18
87
Heritage Resources Effects Assessment Valued Component Scoping and Rationale
96 96 97 97 97 98 98 98
98
vi
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
18.2
Heritage Resources
18.2.1
18.2.2
Heritage Resources Spatial Boundaries Heritage Resources Temporal Boundaries
18.2.3
99 99 99
Heritage Resources Baseline 18.2.4 Potential Effects of the Project and Proposed Mitigation 18.2.5 Summary of Residual Effects on Heritage Resources.... 18.3 References
100
Health Effects Assessment Valued Component Scoping and Rationale 19.2 Human Health 19.2.1 Human Health Spatial Boundaries
101
19
19.1
19.2.2 19.2.3
Human Health Temporal Boundaries Human Health Baseline
19.2.4
Potential Effects of the Project and Proposed Mitigation 19.2.5 Summary Residual Effects on Human Health 19.3 References
99 100 101 101 102 102 102 102
102 103 103
VOLUME 5 - ASSERTED OR ESTABLISHED ABORIGINAL RIGHTS AND TREATY RIGHTS, ABORIGINAL INTERESTS AND INFORMATION, ENVIRONMENTAL MANAGEMENT PLANS, AND FEDERAL INFORMATION REQUIREMENTS
104
20
Asserted or Established Aboriginal Rights and Treaty Rights, Aboriginal Interests and Information Requirements 20.1 Aboriginal Groups 20.2 Aboriginal Groups Background Information
104 104
105
20.3 20.4
Asserted or Established Aboriginal Rights and Treaty Rights Aboriginal Accommodation
106
20.5
Outstanding Aboriginal Issues Other Interests of Aboriginal Groups
106 107
20.8
Aboriginal Consultation and Engagement Aboriginal Summary
20.9
References
107
20.6 20.7
21 21.1 22 22.1 23
23.1 23.2
106 107 107
Summary of Proposed Environmental Management Plans References
108
Compliance Reporting
110
References Requirements for the Federal Environmental Assessment Effect of the Environment on the Project
110
110 111
112
Potential Accidents and Malfunctions Cumulative Environmental Effects
113 114
23.5
Capacity of Renewable Resources Requirements of any Follow-up Program
23.6
References
115
23.3 23.4
24
Summary of Potential Residual Effects of the Project
114 114
115
vii
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
25
Complete Lists of Mitigation and Follow-up Measures
116
26
Conclusion
116
27
EIS Guidelines References
116
28
Appendices
122
List of Tables The tables listed below are found in these EIS Guidelines. Table 8.1
Example of an interactions matrix used to screen project interactions
27
Table 8.2
Spatial boundary descriptors
29
Table 8.3
Residual effects characterization
32
Table 8.4
Summary of assessment of potential significant residual adverse effects
Table 9.1
33
The Proponent proposes to use the following hydraulic models to predict potential changes in surface water hydrology
41
Table 10.1
Fish and fish habitat valued component rationale
50
Table 10.2
Fish and fish habitat assessment areas
50
Table 11.1
Vegetation and ecological communities valued component rationale
54
Table 11.2
Vegetation and ecological communities assessment areas
54
Table 12.1
Wildlife resources valued component rationale
58
Table 12.2
Wildlife resource assessment areas
59
Table 13.1
Greenhouse gases valued component rationale
63
Table 13.2
Greenhouse gases assessment areas
64
Table 14.1
Economic conditions valued components rationale
66
Table 14.2
Local government revenue assessment areas
67
Table 14.3
Labour market assessment areas
68
Table 14.4
Regional economic development assessment areas
70
Table 15.1
Current use of lands and resources for traditional purposes valued component rationale
Table 15.2
72
Current use of lands and resources for traditional purposes assessment areas
72
Table 16.1
Land and resource use valued components rationale
75
Table 16.2
Agriculture assessment areas
77
Table 16.3
Forestry assessment areas
79
viii
Site C Clean Energy Project Environmental Impact Statement Guidelines Table of Contents
Table 16.4
Oil, gas and energy assessment areas
80
Table 16.5
Mineral and aggregates assessment areas
81
Table 16.6
Harvest of fish and wildlife resources assessment areas
83
Table 16.7
Outdoor recreation and tourism assessment areas
85
Table 16.8
Navigation assessment areas
87
Table 16.9
Visual resources assessment areas
88
Table 16.10
Proposed visual resources receptor sites
89
Table 17.1
Social valued components rationale
91
Table 17.2
Population and demographics assessment areas
93
Table 17.3
Housing assessment areas
94
Table 17.4
Community infrastructure and services assessment areas
95
Table 17.5
Transportation assessment areas
96
Table 18.1
Heritage resources valued component rationale
99
Table 18.2
Heritage resources assessment areas
99
Table 19.1
Human health valued component rationale
101
Table 19.2
Human health assessment areas
102
Table 23.1
Federal requirements effects assessment concordance table
111
Table 24.1
Summary of assessment of potential environmental effects ..
115
List of Figures The figures listed below are found in these EIS Guidelines. Figure 3.1
Site C project location
Figure 8.1
Conceptual representation of the environmental assessment process
24
Figure 8.2
Decision process for the selection of valued components
26
7
ix
This is Exhibit "
" referred to in the
So CUo
affidavit tif Wasrj sworn before me at \J \cAor\ a , this _3_L_ day of "Taautl/-
20 _Li
A Corffmission^r for takm§^ifMivifs Within British Columbia
SONYAA MORGAN Barrister ®nd Solicitor
REPORT OF THE JOINT REVIEW PANEL SITE C CLEAN ENERGY PROJECT BC HYDRO MAY 1,2014
k""
u
Tl k*
^1 W_
••
*&•'''
"1 -
•? •
vi
• ••
Sffl
-jMikg
lgSllS§9
in
REVIEW PANEL ESTABLISHED BY THE FEDERAL MINISTER OF THE ENVIRONMENT AND THE BRITISH COLUMBIA MINISTER OF ENVIRONMENT
V '
! i - 1 t - j
REPORT OF THE JOINT REVIEW PANEL
SITE C CLEAN ENERGY PROJECT B.C. HYDRO AND POWER AUTHORITY
BRITISH COLUMBIA
MAY, 2014
Report of the Joint Review Panel - Site C Clean Energy Project
Published under the authority of the federal Minister of the Environment, Government of Canada and the B.C. Minister of Environment, Government of British Columbia
May 2014
PDF:
Cat. No.: En106-127/2014E-PDF
ISBN:
978-1-100-23631-5
ยง Her Majesty the Queen in Right of Canada
This report was written and transmitted in English. This report has been translated into French.
Copies are available on request from:
Canadian Environmental Assessment Agency
British Columbia Environmental Assessment Office
22nd floor, 160 Elgin Street, Ottawa ON K1A 0H3 Canada
836 Yates Street, 2nd Floor, Victoria BC V8W 9V1 Canada
Email: info@ceaa-acee.gc.ca
Email: eaoinfo@gov.bc.ca
Telephone: 1-866-582-1884
Electronic version is available at: www.eao.gov.bc.ca
Electronic version is available at www.ceaa-acee.gc.ca
Site C Clean Energy Project
Joint Review Panel Report
The Panel would like to acknowledge the technical and logistic support of its joint federal-provincial
Secretariat: Courtney Trevis and Brian Murphy (Panel co-Managers); Catherine Bailey-Jourdain, Philip Seeto, Christine Levicki, Daniel Martineau and Sean Moore (Project Analysts); Lucille Jamault (Project Communications); Joanne Smith (Registry Support); Brian J. Wallace, QC (Legal Counsel); and Judith Brand (Editor).
The Panel is solely responsible for the content of this Report.
iii
Site C Clean Energy Project
Joint Review Panel Report
SUMMARY In August 2013, the federal and provincial governments named a Joint Review Panel to examine and to hold a public hearing on BC Hydro's proposed Site C Clean Energy Project, a third hydroelectric facility to be built on the Peace River, near Fort St. John. This is the report of the Panel's assessment of the Project, which the governments are required to publish. The
Panel was mandated to inquire into the environmental, economic, social, health, and heritage effects of the Project and their significance, to examine proposals for the mitigation of adverse effects, and to record assertions of Project effects on the Aboriginal rights and treaty rights of the affected First Nations and Metis peoples. Any large industrial project carries with it some costs that are not captured in a narrowly economic analysis. The question is whether the benefits from the project outweigh those costs. It is in the nature of a public hearing process that the advocates for each side speak as forcefully as they can, and that there would appear to be no middle ground. The Panel's
mandate required it to weigh both sides, and to present a balance sheet, accounting for its associated recommendations, to allow elected provincial and federal governments to determine if the benefits justify the costs. The decision on whether the Project proceeds is made by elected officials, not by the Panel. The benefits are clear. Despite high initial costs, and some uncertainty about when the power would be needed, the Project would provide a large and long-term increment of firm energy and
capacity at a price that would benefit future generations. It would do this in a way that would produce a vastly smaller burden of greenhouse gases than any alternative save nuclear power, which B.C. has prohibited. The Project would improve the foundation for the integration of other renewable, low-carbon energy sources as the need arises. The Project would also entail a number of local and regional economic benefits, though many of these would be transfers from other parts of the province or country. Among them would be opportunities for jobs and small businesses of all kinds, including those accruing to Aboriginal people.
There are other economic considerations. The scale of the Project means that, if built on BC Hydro's timetable, substantial financial losses would accrue for several years, accentuating the intergenerational pay-now, benefit-later effect. Energy conservation and end-user efficiencies have not been pressed as hard as possible in BC Hydro's analyses. There are alternative sources of power available at similar or somewhat higher costs, notably geothermal power. These sources, being individually smaller than Site C, would allow supply to better follow demand, obviating most of the early-year losses of Site C. Beyond that, the policy constraints that the B.C. government has imposed on BC Hydro have made some other alternatives unavailable. There are other costs, however, and questions of where they fall. Replacing a portion of the Peace River with an 83-kilometre reservoir would cause significant adverse effects on fish and fish habitat, and a number of birds and bats, smaller vertebrate and invertebrate species, rare plants, and sensitive ecosystems. The Project would significantly affect the current use of land and resources for traditional purposes by Aboriginal peoples, and the effect of that on Aboriginal rights and treaty rights generally will have to be weighed by governments. It would not, however, significantly affect the harvest of fish and wildlife by non-Aboriginal people. It would end agriculture on the Peace Valley bottom lands, and while that would not be significant in the context of B.C. or western Canadian agricultural production, it would highly impact the farmers who would bear the loss. The Project would inundate a number of valuable paleontological, archaeological, and historic sites. It would have modest effects on health, which could be mitigated, although the health effects of methylmercury on people who eat the reservoir fish
iv
Site C Clean Energy Project
Joint Review Panel Report
require more analysis to be sure. For most users, outdoor recreation and tourism, transportation, and navigation would also experience effects but not significant effects. Because of the significant adverse effects identified on some renewable resource valued components in
the long-term, there would be diminished biodiversity and reduced capacity of renewable resources, should the Project proceed. The Project would not have any measureable effect on the Peace-Athabasca Delta. Risks and associated environmental effects due to potential accidents and malfunctions have been appropriately mitigated by BC Hydro through project design and planned project management.
There would be the usual health and social risks common to boom towns. The low local unemployment rate would mean that most of the Project workers would come from other parts of the province and Canada. However, increased local demand would mean that a broader range of goods and services would become available to all residents of Fort St. John. The local economic upside would largely provide the resources to deal with possible problems, including those related to health, education, and housing, especially if the arrangements BC Hydro is willing to make with local authorities can be concluded. The Peace River region has been and is currently undergoing enormous stress from resource development. In this context, the Panel has determined that the Project, combined with past, present and reasonably foreseeable future projects would result in significant cumulative effects on fish, vegetation and ecological communities, wildlife, current use of lands and resources for traditional purposes, and heritage. In some cases, these effects are already significant, even without the Project.
BC Hydro proposed a suite of mitigation measures which the Panel accepts. The Panel arrived at its own conclusions about the impact of the proposed Project and made recommendations in consequence. The Panel evaluated all proposals by participants and believes that the ones carried forward here represent a complete and practical list. For ease of reference, the Panel's specific conclusions are in shaded text boxes in each of the chapters, followed by any necessary recommendations. A complete list of the Panel's conclusions and recommendations to be taken into account under section 5 of the Canadian Environmental Assessment Act, 2012 is in Appendix 1.
Harry Swain Jocelyne Beaudet James Mattison
Site C Clean Energy Project
Joint Review Panel Report
CONTENTS Introduction
1
2
3
4
5
vi
The Environmental Assessment Process
1
2
1. 1
The Legislative Framework for the Review
2
1.2
Stages of the Review Process
3
1.3
BC Hydro's Environmental Assessment Methods.
3
1.4
The Joint Review Panel Stage
5
1.5
Panel Report and Government Decision Process
6
Project Description
8
2. 7
Project Background..
8
2. 2
Project Components.
9
2.3
Project Phases
Aquatic Environment
16
18
3. 7
Hydrology
18
3.2
Thermal and Ice Regime
22
3.3
Fluvial Geomorphology and Sediment Transport
24
3.4
Groundwater Regime
27
3. 5
Water Quality
29
3. 6
Mobilization and Fate of Mercury
31
3. 7
Peace Athabasca Delta
35
Fish and Fish Habitat
43
4. 1
Proponent's Methodology
43
4. 2
Assessment of Fish and Fish Habitat
45
4.3
Mitigation Measures
53
4.4
Cumulative Effects Assessment.
55
Vegetation and Ecological Communities
57
5. 7
Proponent's Methodology
57
5.2
At-Risk and Sensitive Ecological Communities
59
5. 3
Rare Plants.
65
5.4
Plants of Interest to Aboriginal Groups
67
5.5
Cumulative Effects Assessment
69
Site C Clean Energy Project
6
Wildlife Resources
Joint Review Panel Report
72
6. 1
Proponent's Methodology
72
6.2
Species at Risk
75
6.3
Migratory Birds
81
6.4
Ungulates
85
6.5
Cumulative Effects Assessment.
88
7
Current Use of Lands and Resources for Traditional Purposes
92
7. 1
Proponent's Methodology
92
7.2
Changes in Fishing Opportunities and Practices
96
7.3
Changes in Hunting and Non-Tenured and Subsistence Trapping Opportunities and Practices ... 103
8
7.4
Changes in Other Traditional Uses of the Land.
109
7.5
Cumulative Effects Assessment
113
Asserted or Established Aboriginal Rights and Treaty Rights 8. 1
9
10
11
Affected Aboriginal Groups
Land and Resource Use
123
123
128
9. 1
Other Harvest of Fish and Wildlife Resources
128
9. 2
Agriculture.
145
9. 3
Effects on Other Resource Industries
150
9.4
Transportation
153
9.5
Air Navigation
159
9. 6
Water Navigation
160
9.7
Outdoor Recreation and Tourism.
172
Community Life
182
10. 1
Population and Demographics
182
10.2
Housing
185
10.3
Community Infrastructure and Services
188
10.4
Employment, Labour Markets and Local Residents.
193
10.5
Local Government Revenue
196
10.6
Regional Economic Development.
198
Human Health
11.1
Ambient Air Quality.
202
202
vii
Site C Clean Energy Project
Joint Review Panel Report
11.2
Potable and Recreational Water Quality.
208
11.3
Noise and Vibration
211
11.4
Electric and Magnetic Fields
217
11.5
Methylmercury in Fish
219
11.6
Other Participant Views Related to Human Health
224
11.7
Panel's Overall Analysis on Human Health
225
12
Heritage Resources ..
227
12.1
Physical Heritage .
227
12.2
Cultural Heritage..
234
12.3
Visual Resources.
238
13
Environmental Protection and Management
241
13.1
GHG Emissions
.241
13.2
Effects of the Environment on the Project
243
13.3
Accidents and Malfunctions
249
13.4
Cumulative Effects Assessment.
.254
13.5
Capacity of Renewable Resources
262
13.6
Environmental Management Plans, Follow-up and Monitoring
266
14
15
16
Project Purpose, Cost, and Benefits
271
14.1
Purpose of the Proposal
271
14.2
Project Benefits
272
14.3
Project Costs
279
Need for and Alternatives to the Project
282
15.1
Demand
282
15.2
Demand Moderation.
287
15.3
Supply: Energy
291
15.4
Supply: Capacity
296
15.5
Policy Constraints on Supply
300
15.6
Panel's Overall Analysis on Need for the Project
305
Panel's Reflections
307
Appendix 1
List of Panel's Conclusions and Recommendations
310
Appendix 2
Agreement and Panel Terms of Reference
326
viii
PROVINCE OF BRITISH COLUMBIA
ORDER OF THE LIEUTENANT GOVERNOR IN COUNCIL Order in Council No.
244
, Approved and Ordered
August 02,2017
Lieutenant Governor Executive Council Chambers, Victoria
On the recommendation of the undersigned, the Lieutenant Governor, by and with the advice and consent of the Executive Council, orders that the attached order, British Columbia Utilities Commission Inquiry Respecting Site C, is made.
This is Exhibit "
^
" referred to in the
affidavit of VWrU 7WgVlcA A sworn before me aiPVifWW, & this 3>l^day of JfxAua T"?
,20lfL
*V-i- .—,
A Commissionerfor takingAfMaws Within British Columbia
/
SONYA A. MORGAN Barrister and Solicitor
/
7 Attorn
General
Presiding Member of the Executive Council
(This pari isfor administrative purposes only and Is notpart ofthe Order,)
Authority under which Order is made:
Act and section:
Utilities Commission Act, R.S.B.C, 1996, c. 473, s. 5
Other: 040148786
page 1 of 3
British Columbia Utilities Commission Inquiry Respecting Site c
Definitions
1
In this order:
"Act" means the Utilities Commission Act; "Site C project" means the authority's project to construct a third dam and hydroelectric generating station, including related transmission facilities, on the Peace River to add 1 100 megawatts of firm capacity and 5 100 gigawatt hours of annual energy to the authority's system. Referral to commission
2
By this order, the Lieutenant Governor in Council, under section 5 (1) of the Act, requests that the commission advise the Lieutenant Governor in Council respecting the Site C project in accordance with the terms of reference set out in section 3 of this order.
Terms of reference
3
The terms of reference in accordance with which the commission must inquire into the matter referred to it by section 2 are as follows: (a) the commission must advise on the implications of (i) completing the Site C project by 2024, as currently planned,
(ii) suspending the Site C project, while maintaining the option to resume construction until 2024, and
(iii) terminating construction and remediating the site; (b) more specifically, the commission must provide responses to the following questions: (i) After the commission has made an assessment of the authority's expenditures on the Site C project to date, is the commission of the view that the authority is, respecting the project, currently on time
and within the proposed budget of $8,335 billion (which excludes million project reserve established and held by the
the $440
province)?
(ii) What are the costs to ratepayers of suspending the Site C project, while maintaining the option to resume construction until 2024, and what are the potential mechanisms to recover those costs?
(iii) What are the costs to ratepayers of terminating the Site C project, and what are the potential mechanisms to recover those costs? (iv) Given the energy objectives set out in the Clean Energy Act, what, if any, other portfolio of commercially feasible generating projects
and
demand-side management initiatives could provide similar benefits (including firming; shaping; storage; grid reliability; and
maintenance or reduction of 2016/17 page 2 of 3
greenhouse gas emission
levels) to ratepayers at similar or lower unit energy cost as the Site
C project? (c) in making applicable determinations respecting the matters referred to in paragraphs (a) and (b), the commission must use the forecast of peak capacity demand and energy demand submitted in July 2016 as part of the
authority's Revenue Requirements Application, and must require the authority to report on
(i) developments since that forecast was prepared that will impact demand in the short, medium and longer terms, and (ii) other factors that could reasonably be expected to influence demand from the expected case toward the high load or the low load case;
(d) the commission must consult interested parties respecting the matters referred to in paragraphs (a) and (b); (e) in carrying out its inquiry, the commission must be guided by the understanding that the inquiry is not a reconsideration of decisions made in the environmental assessment process or by statutory decision makers or the courts;
(0 the commission may obtain expert advice on any subject related to the inquiry and may exercise any of its powers under the Act in order to carry out the inquiry in accordance with these terms of reference; (g) the
commission must submit to the minister administration of the Hydro and Power Authority Act
charged
with
the
(i) a preliminary report outlining progress to date and preliminary findings by September 20, 2017, and
(ii) a
final report, including the results consultations, by November 1, 2017.
page 3 of 3
of
the
commission's
»#•#©» • Patrick Wruck
Suite 410, 900 Howe Street
bcuc
Commission Secretary
Vancouver, BC Canada V6Z 2N3
British Columbia
Commission.Secretary@bcuc.com
TF:
1.800.663.1385
Utilities Commission
bcuc.com
F:
604.660.1102
9@®#@
• • • • • *
» # # © • •••• «• ©##•
P:
604.660.4700
November 1, 2017 BCUC Inquiry Respecting Site C
A-24
Sent via eFile
The Honourable Michelle Mungall, M.L.A. Minister of Energy, Mines and Petroleum Resources Parliament Buildings PO Box 9060 Stn Gov't Victoria, BC V8W 9E2
EMPR.Minister@gov.bc.ca
Re:
British Columbia Hydro and Power Authority - British Columbia Utilities Commission Inquiry Respecting Site C - Project No. 1598922 - Final Report
Dear Minister:
In accordance with Order in Council No. 244 dated August 2, 2017, the British Columbia Utilities Commission hereby submits its Final Report with respect to the Site C Inquiry.
Sincerely,
Original signed by:
Patrick Wruck Commission Secretary
This is Exhibit ' E Y
affidavit of
" referred to in the '.itlnA C\
sworn before me at \1 I CH/Ofi 0<
this 3A^Tday of ~j>vAu.a<-ci 20 j2. ,,
A •Commissioner fo"r fatfmg^Affidavits Within British Columbia!
SOMYA A. MORGAN Rammer and Solicitor
55604 | Site C Inquiry - Final Report
1 of 1
•][•
• I-
21
us
s
p :v?
~ - .
m
'. -*
\ mmm mm
.
m
&
eStegS
_ K l\
— . -
lH*#s
-
IBSl
•-, -'• - -
&ggu
\
:,
m
mm .
..
\
.
pa
"
„
\ v\
\
I V-
?• ,.Vvf-
M
m
\\
mm
i MK
v
•s.
\
V
I
V
J . *
\X
A/
\Y
\/u r
i S
§m f i-aaH
x
t
.1 fx
••V '••' I «
*.
•
rr
a;SX«l
Ji
i
n
|
f
\ »
W
~
\ v.
I
-
_
. v
'
, •
'
•
;
'
M
mm
I"
\
K • '
! - § j ,
jl
•y.
It
if
f
i m
I?
sSISa
Va
H u
About the BCUC Who we are
The British Columbia Utilities Commission (BCUC) is an independent
regulatory agency of the Government of British Columbia that operates
under and administers the Utilities Commission Act. The BCUC is
quasi-judicial and makes legally binding rulings.
What we do
The BCUC's primary responsibility is
the regulation of BC's energy utilities. In addition to setting rates, the BCUC regulates all franchises, privileges, and concession agreements granted to public utilities. It is our mission to ensure that ratepayers receive safe, reliable and non-discriminatory energy services
at fair rates from the utilities we regulate, while also providing utilities the opportunity to earn a fair return on their capital investments.
«•«••• • • «••••* • MM • •
MM • ••© • e©e© ©• • •©•
bcuc British Columbia Utilities Commission
This report was prepared in response to Order-in-Council No. 244 for the Honourable Michelle Mungall, Minister of Energy, Mines and Petroleum Resources.
British Columbia Utilities Commission Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 Before:
Phone: 604.660.4700 BC Toll-free: 1.800.663.1385 Fax: 604.660.1102
David M. Morton, Panel Chair and Commissioner
Dennis A. Cote, Commissioner Karen A. Keilty, Commissioner
Richard I. Mason, Commissioner
Email: commission.secretary@bcuc.com
bcuc.com
ERRATA
Report errata
1.1
Math Error regarding Mid C price forecasts used in the Site C Calculator
Issue
The Mid C price forecasts used in the Site C unit energy cost UEC Calculator are in real terms and should have been inflated to nominal terms.
Commission comments The Panel confirms that the graph upon which the Mid C price forecasts were derived are in real F$2018 and therefore should be inflated to nominal. In the alternative portfolio spreadsheets, these same price forecasts were inflated to nominal. By correcting the Mid C price forecasts to nominal in the Site C UEC calculator, we find that the rate impact
(NPV) from Site C under the low load case is $336 million lower, at $2,852 million instead of $3,188. Under the mid load case, the rate impact from Site C is $68 million, at $3,901 million instead of $3,969 million. There is no impact on the high load case as there is no surplus energy in that scenario.
Formulas issues regarding the Commission Illustrative Alternative Portfolio
1.2
Issues
1.
In the "Energy & capacity gap" sheet, the text box pointing to cell R42 says "Assumes ramp up at 800 GWh/yr" but the ramp up did not occur in the cells to the right of R42. This should be corrected to include the 800 GWh/yr ramp up for the years F2037 to F2041.
2.
In the "Low LF - portfolio" sheet, the cells titled "(capacity) gap to fill" beginning at Y28 and ending at CB28 contain equal values of 1145 MW but the corresponding values in row 33 of the "Energy &
capacity gap" sheet are 985 MW (i.e., Site C gross capacity less 14% planning reserve). This should be corrected so that the values in both sheets are the same and the correct value is 985 MW. 3.
Pursuant to the change made according to #2 above, a further change is required to cells AJ31 to CB31 of the "Low LF - portfolio" sheet, all of which have the hard number of -629.96 MW rather the cell difference formula which appears in the adjacent AI31 cell and would yield a result of -470 MW.
4.
Pursuant to the changes according to #1 to 3, there is no need for capacity from industrial curtailment in F2039 and F2040 and the in-service date for the first wind project (PC 18) can be delayed by one year from F2039 to F2040.
Commission comments The Panel confirms that the issues outlined above need to be corrected. By correcting them, we find that the
rate impact (NPV) from the Illustrative Alternative Portfolio under the low load case is $87 million lower, at $3,147 million instead of $3,234. There is no impact on the mid and high load cases as the issues affected only the low load case.
Site C Inquiry | Final Report
lof 11
ERRATA
The tables and figure in the Executive Summary would read correctly as follows:
Corrected Table on p. 7 of the Executive Summary: Rate Impact ($ million) Scenario
A. Illustrative
B. Site C
Alternative
Unit Energy Cost ($/MWh)
Difference
Illustrative
(A-B)
Alternative
Portfolio
Portfolio
$3,147
Commission
Site C
$2,852
$295
$31
$44
Assumptions
Finding: The Panel confirms there is no change to its finding that "[a]s can be seen in the table below, the cost to ratepayers of Site C and the Illustrative Alternative Portfolio are virtually equivalent, within the
uncertainty inherent in the assumptions." Corrected Table on p. 15 of the Executive Summary:
Summary Results of the Illustrative Alternative Portfolio (2018$)
Revised Alternative
High Load Forecast
Medium Load Forecast
Low Load Forecast
•
•
•
441 MW of wind
Portfolio composition
•
444 MW of wind
starting between F2029 and
projects starting
F2025, 288MW in F2026
F2031
between F2040 and
DSM initiatives (energy
F2041
DSM initiatives (energy
•
efficiency, optional time
efficiency, optional TOU
of use (TOU) rate,
rate, capacity focused DSM,
(energy efficiency,
capacity focused DSM,
industrial curtailment)
optional TOU rate,
81 MW of geothermal
capacity focused
projects starting in F2025
DSM)
industrial curtailment)
•
438 MW of wind projects
projects starting in
81 MW of geothermal
•
•
DSM initiatives
projects starting in F2025
Rate Impact of portfolio
$ 5,121 million
Site C Inquiry | Final Report
$4,618 million
$ 3,147 million
2 of 11
ERRATA
Corrected Illustrative Alternative Portfolio Rate Impact Sensitivity Analysis on p. 15 of the Executive Summary
Load
Termination costs
Financing costs
Term costs Amortization
Wind costs
Geothermal costs
Market price of surplus
$3,000
I $3,500
$4,000 I High Value
$4,500
$5,000
$5,500
$6,000
Low Value
Finding: The Panel confirms that the paragraph starting with "The graph shows" in the middle of page 16 should read: "The graph shows the cost to ratepayers of the Base Case described below, and variations
around the base case. The Base Case is in the centre of the graph and is $4,918 billion. Then, each variable is changed to a low or high value and the cost to ratepayers of that single change (while holding the other inputs constant) is shown. For example, if the Load forecast is changed to Low instead of Medium, the cost
| to ratepayers would be reduced by $1.558$1.647 billion from $4,918 billion to $3.36$3.271 billion, while all the other inputs remained as defined in the Base Case."
Corrected Site C Rate Impact Sensitivity Analysis on p. 16 of the Executive Summary
Totil Site C
Load
Market price ct surplus
$2,/.b0
II Si.ibU
B Mign V.jfi
Si,/bO
>4
$4 /bO
Low V.li-.ir
Finding: The Panel confirms there is no change to its finding that "For Site C, as seen in the graph above, the
base case is completion costs of $10 billion, BC Hydro's mid load forecast and the Panel's Mid C forecast assumptions. The inputs and assumptions that have the greatest impact on rates are the Site C total costs and the load forecast. The market price of surplus energy has much less impact on the costs to ratepayers."
Site C Inquiry | Final Report
3 of 11
ERRATA Corrected Sensitivity Analysis on page 17 of the Executive Summary Rate Impact ($'m) Scenarios
A. Revised
B. Site C
Illustrative
Unit energy cost ($/MWh) Difference
Revised
(A-B)
Illustrative
Alternative
Alternative
Portfolio
Portfolio
Commission Assumptions
Site C
$3,147
$2,852
$295
$31
$44
$4,618
$3,901
$717
$34
$44
$4,618
$4,842
($224)
$34
$54
$3,147
$3,793
($646)
$31
$54
$3,271
$2,852
$419
$32
$44
$5,121
$4,325
$796
$31
$44
$5,121
$5,266
($145)
$31
$54
Scenarios
Medium load forecast Medium load forecast
+ $12 billion Site C cost Low load forecast, $12 billion Site C cost Low load forecast + higher windgeothermal financing
High load forecast
High load forecast, $12 billion Site C cost
Findings: The Panel confirms there is no change to the paragraph introducing the sensitivity analysis: "The sensitivity analysis illustrates the effect of changing one input assumption at a time. To see the effect of changing more than one variable at a time, we provide a few sample scenario results below."
The Panel also confirms there is no change to the paragraph immediately below the sensitivity analysis: "The Illustrative Alternative Portfolio indicates that it is possible to design an alternative portfolio of commercially feasible generating projects and demand-side management initiatives that could provide similar benefits to ratepayers as Site C."
Site C Inquiry | Final Report
4 of 11
ERRATA
1.3
"Copy & Paste Error" in Table 43 ($4.9 billion, -$293 million)
Issue
In Table 43 in the Final Report, in the scenario "Medium load forecast + $12 billion Site C cost", Site C NPV
should read $4,911 million and the difference (-$293 million). Table 43: Summary of Sample Scenarios Rate Impact ($'m) Scenarios
A. Revised
B. Site C
Illustrative
Unit energy cost ($/MWh) Difference
Revised
(A-B)
Illustrative
Alternative
Alternative
Portfolio Commission
$3,234
SiteC
Portfolio
$3,188
$46
$32
$44
Assumptions Scenarios
Medium load forecast
$4,618
$3,969
$649
$34
$44
Medium load forecast
$4,618
$1,129
$489
$34
$54
$4,911
($293)
$3,234
$4,129
($895)
$32
$54
$3,360
$3,188
$172
$33
$44
High load forecast
$5,121
$4,325
$796
$31
$44
High load forecast, $12
$5,121
$5,266
($145)
$31
$54
+ $12 billion Site C cost Low load forecast, $12 billion Site C cost Low load forecast + higher wind-
geothermal financing
billion Site C cost
Commission comments The Panel confirms there was a copy and paste error in Table 43. The numbers should have been $4,911 and
(-$293), therefore adding an additional scenario where the Alternative Portfolio is less expensive than Site C. Finding: The Panel notes that these numbers are now outdated due to the need to correct the Mid C price forecast and the issues pertaining to the low load case in the Commission Illustrative Alternative Portfolio. The Panel also notes that the correction to Mid C price forecasts results in changes to a number of scenarios.
Site C Inquiry | Final Report
5 of 11
ERRATA
1.4
Other Corrected Tables and Figures in the Final Report
The following tables and figure in the Final Report would read correctly as follows: Corrected table for Illustrative Alternative Portfolio Results (p. 165)
Summary Results of the Revised Illustrative Alternative Portfolios (2018$) v ;•
High Load Forecast
Medium Load Forecast
Low Load Forecast
•
•
. •• i.
Revised Alternative
•
Portfolio composition
441 MW of wind
444 MW of wind
starting between F2029 and
projects starting
F2025, 288MW in F2026
F2031
between F2039
DSM initiatives (energy
F2040 and F2041
•
DSM initiatives (energy
•
efficiency, optional time
efficiency, optional TOU
of use (TOU) rate,
rate, capacity focused DSM,
capacity focused DSM,
industrial curtailment)
optional TOU rate,
81 MW of geothermal
capacity focused
industrial curtailment)
•
438 MW of wind projects
projects starting in
•
•
DSM initiatives
(energy efficiency,
DSM, industrial
projects starting in F20252
81 MW of geothermal
curtailment)3
projects starting in
F20251 Rate Impact of
$ 5,121 million5
portfolio4
$ 4,618 million6
$^t2M3,147 million7
Corrected Table 39: Cost to ratepayers and UEC of Site C (p. 167) Output : Low LF - Alternative Portfo I i o
|
A
Site C Termination Cost (F$18)
$
1,395
million
B
Alternative Portfolio Cost (FS18)
$
2,539
million
C
Surplus Energy Sale (F$18)
$
D
Total Rate Impact (A+B+C)
$
E
Alt. Portfolio Volume (F18)
F_
UEC (FS18) (B/E)
(788) million 3,147
million
82,784
$
30.67
per MWh
1 Appendix HC- Commission Illustrative Alternative Portfolio, Tab 'High LF - portfolio', with costs in Tab 'High LF - portfolio costs'. 2 Ibid, Tab 'Med LF - portfolio', with costs in Tab 'Med LF - portfolio costs'. 3 Ibid, Tab 'Low LF - portfolio', with costs in Tab 'Low LF - portfolio costs'. 4 Discount rate of 4% real, 6% nominal; export revenues valued at Panel's Mid C Forecast (at plant gate location), Site C $1.8 billion termination costs amortized over 30 years and assuming all resources are financed at BC Hydro's financing rate.
| 5 Appendix WC- Commission Illustrative Alternative Portfolio, Tab 'Input and Output', Cell 026. 6 Ibid, Tab 'Input and Output', Cell 017. | 7 Ibid., Tab 'Input and Output', Cell 08. Site C Inquiry | Final Report
6 of 11
ERRATA
Corrected Table 40: Cost to ratepayers and UEC of Site C (p. 167) Output: Low LF - Site C
A
Sunk Costs (F$18)
$
2,100 million
B
Site C Cost to Complete (FS18)
$
4,391
C
Flexibility Credit (F$18)
$
(66) million
D
Surplus Energy Sales (F$ 18)
$
(1,473) million
E
Total Rate Impact (B+C+D)
$
F
Volume (F18)
G
UEC (FS18) (B/F)
2,852
million
million
98,993
$_
44.35 p er MWh :
Finding: The Panel confirms that the paragraph below Table 40 should read: "The comparison in the tables above show that the cost to ratepayers Illustrative Alternative Portfolio has a lower UEC than Site C
($31.6430.67/MWh compared to $44.35/MWh) but a cost to ratepayers slightly higher ($3.234$3.147 billion compared to $3,188 $2.852 billion for Site C)."
Site C Inquiry | Final Report
7 of 11
British Columbia November 15, 2017
Rcf.:
This is Exhibit
102700
ÂŤ f~
" referrad to in the ia;
affidavit
Mr. David Morton
sworn before me"3t
6C
BC Utilities Commission
this3]
20 Ji.
Email: David.Morton@bcuc.com
A Commissioner for
Chair
Re: Inquiry Respecting Site C
Bmi$tor snd Solicitor
The Ministry of Energy, Mines and Petroleum Resources and Ministry of Finance are supporting the government decision process surrounding the future of the Site C project.
On behalf of our respective Ministers, we would like to thank the BC Utilities Commission (Commission) for the report Inquiry Respecting Site C. Completing an inquiry of this scope over an abbreviated timeframe and with high levels of public and First Nations input is a considerable achievement. As our ministries analyze the Commission's report, along with other implications associated with government proceeding with or terminating the Site C project, we want to ensure that we fully understand the assumptions and computations that the Commission made in the analysis of potential alternative sources of energy generation and capacity. Accordingly, we are requesting further explanation or additional information on the points listed below and in the Appendix attached to this letter. 1.
Did the Commission include sunk costs (the estimated $2.1 billion that has been spent to date on the project) and termination costs (the $ 1 .8 billion determined by the
Commission) in comparing the costs to ratepayers of completing Site C against the costs of pursuing an alternative portfolio of generation resources? . We were not able to determine whether the sensitivity analysis included on Page 17 of the report's executive summary includes sunk costs and termination costs consistently. If it does not, could the Commission advise on how including these
sunk and termination costs might change the cost to ratepayers and the unit energy cost (UEC) in both scenarios? 2.
In the event that government elects to terminate the Site C project, has the Commission assumed that BC Hydro would develop and finance the projects
Page 1 of 3
Ministry of
Office of the
Energy, Mines and Petroleum Resources
Deputy Minister
Mailing Address: PO Box 9319, Stn Prov Govt Victoria, BC V8W 9N3 Telephone: 250 952-0120 Facsimile: 250 952-0269
Location:
8lh Floor, 1810 Blanshard Street Victoria Website: www.em.gov.bc.ca/
included in the alternative portfolio (wind, geothemial) rather than independent power producers (IPPs)? We observe that the Commission has in some cases used BC Hydro's lower cost of capital financing to calculate the cost of the alternative portfolio presented in the
report, affecting the valuation of those projects. Could the Commission offer its view of the impact that a higher cost of capital would have on ratepayers if the alternative portfolio were developed by independent power producers rather than directly by BC Hydro? 3.
Government will need to consider the total cost of potential demand side management initiatives (rather than just the utility's costs) as it considers the alternatives. Could the Commission advise how the inquiry Terms of Reference led to assessing demandside measures based on the Utility Resource Cost standard, when Total Resource Cost has been the standard for prior Commission proceedings?
4.
If the Site C project were terminated, the $4 billion sunk and remediation costs would need to be recovered, and the amortization period of that recovery would affect BC Hydro rales. Could the Commission please clarify whether it assumed that that these costs would be recovered over 10, 30 or 70 years? •
Fair and appropriate rate-setting principles for rate-regulated utilities typically aim to avoid causing future generations to pay for investments from which they will derive no benefit. From the Commission's perspective, can recovery of the sunk and remediation costs of Site C over longer periods of 30 to 70 years remain consistent with these inter-generational principles?
•
Recently it has been stated that recovering the project's sunk and remediation costs over a 10-year period would lead to a 10 per cent hike in BC Flydro rates. Is
this assertion consistent with the Commission's thinking? 5.
We are unaware of prior instances when anything other than BC Hydro's mid-load forecast has been used for planning purposes. For that reason, we would like to clarify:
•
Did the Commission assume lower demand for electricity (reflected in the lowload forecast used in the report) because it is forecasting a period of lower
economic growth for the province in which major power consumers such as mining, forestry, technology and commercial sectors are in decline? •
Does the Commission include in its load forecast the potential increased electrical power demand of meeting the province's stated objectives to reduce greenhouse gas emissions through greater electrification of our economy?
Page 2 of 3
We sincerely appreciate the Commission's timely response to these questions and requests for clarification. Government has committed to making a decision on the Site C project before the end of the year. The Commission's responses to our questions will assist our ministries in better understanding the report and the assumptions that underlie it as we prepare advice to support government in making a decision that will be in the best
interests of British Columbians.
L
I C 'CX j \c~. ( > , fc Dave Nikolejsin
Lori Wanamaker
Deputy Minister
Deputy Minister
Ministry of Energy, Mines
Ministry of Finance
and Petroleum Resources
Attachment
Page 3 of 3
Appendix: Detailed Questions for the Commission
We understand that while BC Hydro modelled over 60 scenarios and tested various assumptions, including a number of alternatives requested by the Commission, the alternative portfolio that the Commission included in the final report was not analyzed using BC Hydro's modelling tools. On this basis, government has asked BC Hydro to provide an assessment of the model used to develop the Commission's final alternative portfolio. BC Hydro will provide the Commission with the results of that assessment separately.
In our initial analysis of the report, our ministries have identified several areas that we would appreciate the Commission's feedback on. Several of our questions relate to the impact of certain assumptions made in the report, and how the costs of those assumptions would be recovered from ratepayers. We understand that BC Hydro follows standards for rate-regulated utilities in its financial statements and in preparing its applications for review by the Commission. This accounting framework follows a number of principles in relation to the amortization of capital assets and the deferral of other costs for the purpose of matching recoveries from ratepayers to periods over which benefits are provided. It would be helpful if the Commission could clarify how the choices of cost amortization and recovery periods in the Termination scenario fit within appropriate utility rate-setting principles that recognize and avoid unnecessarily transferring current utility costs to future user generations when there are clearly no longer directly-related assets or benefits
being provided. Such decisions lead rate-regulated accounting practice and use of regulatory accounts, which are areas of particular interest by the provincial Auditor
General as well as credit rating agencies. The Commission's process involved some deliberations on the cost of capital. The alternative portfolio presented in tire report assumes that BC Hydro will finance all newresources on its balance sheet. However, other than redevelopment of existing sites and
Site C, BC Hydro has, for almost three decades, been primarily procuring new supply from competitive processes or bilateral agreements that are benchmarked to competitive processes. This effectively means that BC Hydro avoids assuming such debt on its balance sheet and only recognizes the incremental costs of new energy purchases which would include the private sector's annual debt servicing costs and equity return within approved purchase contracts.
It would be helpful to understand how the Commission assesses the impact on ratepayers of the additional debt associated with the assumptions underlying the alternative portfolio. We would particularly appreciate better understanding the Commission's approach to using BC Hydro's cost of capital for IPP projects and the approach used for the cost of capital faced by an IPP (i.e. what IPPs actually pay) and the resultant rate impacts. For example, on page 159-160, the Commission appears to conclude that IPP financing is the relevant assumption for the alternative portfolio, and the BC Hydro
financing assumption should only be used for the Unit Energy Cost (UEC) analysis. However, on pages 1 67, 1 70 and Appendix C (Assumption 2), it appears that the
Commission has used BC Hydro financing (100% debt financing at a cost of 3.43%) for the alternative portfolio. If we are interpreting this correctly, we would appreciate clarification on which cost of capital should be used in analysing rate impacts.
BC Hydro has suggested that recovery in rates of sunk costs in a termination scenario should occur over a 10-year period. If the project were to continue as planned, the sunk costs, as part of the overall project costs, will be recovered over a 70-year period, consistent with the amortization of the Site C asset. The Commission model appears to exclude sunk costs in the termination scenario, and has removed those costs from the
completion scenario as well. Effectively this assumes that sunk costs will be recovered through rates over 70 years if the project is terminated. Recovering costs in rates over a shorter period has a material impact on the costs of the alternative portfolio. It would be helpful i f the Commission could provide an estimate of the impact on rates of using these two timeframes. The tables on page 17 of the executive summary and page 170 in the main report include a summary of the Commission's sample scenarios showing the effect of modifying one or more variables to the resulting Net Present Value cost to ratepayers. As noted above, the Commission's alternative portfolio does not appear to include sunk costs, and sunk costs
have also been removed on the continue scenario. The tables also include UECs. For the Site C scenario, the UECs reflect costs, including sunk costs, of Site C being either
$10 billion or $12 billion depending on assumptions. Our review of the Commission report suggests that the alternative portfolio does not include termination costs. It would be helpful if the Commission could confirm this and provide a version of the UEC portion of the table with termination costs included in the alternative portfolio. This would help provide a consistent basis for comparing costs between the scenarios of completing or terminating the project. It is our understanding that in previous proceedings the Commission has concluded that the Total Resource Cost (TRC) test is the appropriate way to evaluate demand side management (DSM) in comparison to other resources. In this inquiry, the Commissio n's model uses the Utility Resource Cost (URC) standard. We believe that using the URC
may underestimate the actual cost of DSM to ratepayers. It would be helpful for us to understand the Commission's rationale in choosing a test methodology that differs from past practice. Could the Commission confirm that the TRC test remains the appropriate metric, and if so, what impact would this have on the analysis? We have noted that the Commission has concluded that BC Hydro's low load forecast was most appropriate for an assessment of the need for the capacity of Site C. It would be helpful for us to further understand the rationale, and whether the assessment includes the load requirements needed to meet the Province's Clean Energy Act energy objectives of:
â&#x20AC;˘ â&#x20AC;˘ â&#x20AC;˘
Reducing greenhouse gas emissions by 2050 by 80% less than 2007 levels; Encouraging the switching from one kind of energy source or use to another that decreases greenhouse gas emissions in British Columbia; and, Encouraging communities to reduce greenhouse gas emissions and use energy efficiently.
It would also be useful to know if the Commission examined the value of "dispatchable" resources versus intermittent resources, particularly as applied to the goal of moving industrial energy requirements now and in future to low carbon electricity. It has been government's assumption that electrification with low carbon electricity would be a key initiative to achieve greenhouse gas reductions. The provincial government is working with the Government of Canada on electricity system infrastructure investments to reduce and avoid greenhouse gas emissions, and has enabled
BC- Hydro to pursue electrification initiatives under the Greenhouse Gas Reduction (Clean Energy) Regulation under the Clean Energy Act. It would be. helpful for our ministries to understand if the Commission has a different outlook, and if the Commission could further describe the impact on its analysis of electrification initiatives to meet greenhouse gas reduction objectives. The report identifies an aggressive DSM program, coupled with load curtailments as a way to achieve the alternative portfolio scenario. We would appreciate further information from the Commission on how such load curtailments would practically be achieved in the natural resource sector without impairing operations, jobs and economic
growth for sectors already facing trade sanctions and pressures. We understand that BC Hydro has provided the Commission with a description of its view of what BC's economic environment would look like under a low load outlook scenario. It would helpful if the Commission could further describe its interpretation of the low load outlook. We observe that the Commission's view is that the outlook could be even lower than that presented in BC Hydro's low-load scenario, and we are interested in understanding how that outlook is based on realistic economic sustainability around
which the alternative portfolio would be premised.
i
$»*>#» •
* 9
* » » » ®
« • ••• «•
bcuc British Columbia
Utilities Commission
Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com
P:
604.660.4700
TF: 1.800.663.1385 F:
604.660.1102
INFORMATION RELEASE - BCUC responds to the Provincial Government's additional questions in the Inquiry Respecting Site C
November 23, 2017
Vancouver-The British Columbia Utilities Commission (BCUC) has responded to the joint letterfrom the Ministry of Energy, Mines and Petroleum Resources and Ministry of Finance seeking additional information in the BCUC's Inquiry respecting Site C. The BCUC's response is attached to this information release.
The BCUC's Inquiry into Site C was initiated by Order in Council No. 244 on August 2, 2017 and was completed with the issuance of the Inquiry Panel's Final Report on November 1, 2017. The Final Report, and all information submitted during the course of the Inquiry is publically available at www.sitecinciuirv.com. The BCUC is a regulatory agency responsible for oversight of energy utilities and compulsory auto insurance in the province of British Columbia. It is the BCUC's role to balance the interests of customers with the interests of the businesses we regulate. The BCUC carries out fair and transparent reviews of matters within its jurisdiction and considers public input where public interest is impacted.
CONTACT INFORMATION:
Erica Hamilton Director, Communications
Phone: 604.660.4727 Email: erica.hamilton@bcuc.com
Website: http://www.bcuc.com
This is Exhibit " (5) " referred to in the affidavit of SVtP.\fl(Y\ .£^£)Ai A sworn before me at NilCtfrrna. t fe_C— this day of -71 AAU/VI , 20 J2. A"Comm i ssi o n e r YoHaj^ntf'Affidavits Within British Columbia
SONYA A. MORGAN Barrister and Solicitor
»©«>##» •
• •#§#©» • ® ® s» ®
« •
• •©« »® • « ©•
®®©»
David Morton
Suite 410, 900 Howe Street
bcuc
Chair and CEO
Vancouver, BC Canada V6Z2N3
British Columbia
David.Morton@bcuc.com
TF: 1.800.663.1385
Utilities Commission
bcuc.com
F:
P:
604.660.4700
604.660.1102
November 23, 2017
Sent via email
Dave Nikolejsin
Lori Wanamaker
Deputy Minister
Deputy Minister
Ministry of Energy, Mines and Petroleum Resources
Ministry of Finance
PO Box 9319, Stn Prov Govt
PO Box 9417, Stn Prov Govt
Victoria, BC V8W 9N3
Victoria, BC V8W 9V1
EMPR.Minister@gov.bc.ca
FIN.Minister@gov.bc.ca
Re:
British Columbia Hydro and Power Authority - British Columbia Utilities Commission Inquiry Respecting Site C - Project No. 1598922
Dear Dave Nikolejsin and Lori Wanamaker:
The Deputy Ministers' letter of November 15, 2017 poses a series of questions to the Commission regarding its Final Report on the Site C Inquiry, which was initiated by the Lieutenant Governor by Order in Council 244. The Commission thanks the Deputy Ministers for their inquiry and sets out its response below, trusting that any additional clarity or amplification of the messages in the Final Report will assist the government in its decision regarding Site C.
Sincerely,
Original signed by:
David Morton Chair and Chief Executive Officer
DM/kbb Enclosure
55604 1 Site C Additional Questions
1 of 1
Introduction The Inquiry initiated by Order in Council (OIC) 244 requested that the Commission evaluate the cost to BC Hydro ratepayers of continuing, suspending or terminating construction of the Site C dam. In its Final Report, the Commission drew two overall conclusions: â&#x20AC;˘
The cost to ratepayers of suspending construction would be significantly higher than either continuing
or terminating the project, to the tune of $3.6 billion.1 In addition, there are significant risks that it would not be possible to restart the project due to permitting and other issues.
â&#x20AC;˘
The cost to ratepayers of continuing or terminating construction is similar,2 given the assumptions that the Commission finds to be most reasonable. Both alternatives also have risks which may cause one or the other to be more costly to ratepayers either in the short-term or over a longer period.
Many of the questions posed in the Deputy Ministers' letter, in one way or another, relate to the estimates underlying these conclusions. We believe it will be helpful to provide some background and context before addressing the specific questions. In reaching its conclusions, the Commission was required to estimate the costs of each of the three options, and in the case of termination, the cost of the alternative energy that might be required. It is important to recognize
that each estimate comes with a degree of uncertainty. For example, when considering the cost of terminating the Site C project, the Commission found, based on information from BC Hydro and Deloitte, that costs could
range from $750 million to $2.3 billion.3 In order to make a comparison between the options, the Commission chose a reasonable "point estimate" of $1.8 billion based on BC Hydro's P90 estimate.4 But it would be quite possible, based on the information available to conclude that the cost of termination could be up to a billion dollars less, or half a billion dollars more. Nonetheless, in spite of this uncertainty, it was quite reasonable for
the Commission to conclude that the option of suspending the project, estimated to be $3.6 billion more than either continuing or terminating construction, would be significantly more expensive for ratepayers.
By comparison, the estimated costs to ratepayers of continuing or terminating construction, at $2,852 billion
and $3,147 billion respectively,5 were so close that it would be unreasonable for the Commission to draw a meaningful distinction between them. Given the range of estimates to terminate the project ($750 million to $2.3 billion) an even larger difference between the estimated costs to continue or to terminate would have resulted in the Commission drawing the same conclusion they were similar.
To further illustrate how using point estimates for input assumptions masks the potential variability of
assumptions, consider the original Site C completion costs. The original estimate of $8.35 billion was based on a
1 2 3 4 5
BCUC Site C Inquiry Respecting Site C Executive Summary (Executive Summary), p. 3. BCUC Site C Inquiry Respecting Site C Final Report (Final Report), p. 187. Final Report p. 128. This is BC Hydro's P90 estimate, which should only have a 10% chance of being exceeded. Final Report, Errata, p. 10 of 11.
lof 26
Class 3 estimate, which means that the expected accuracy range is from 20% under the budgeted amount to
30% over the budgeted amount - in this case a variance of $4.2 billion.6 Similarly, some of the costs associated with the Illustrative Alternative Portfolio are highly uncertain. Costs of acquiring wind generation equipment post 2025 for example, are estimates of future costs and, as such, may not
share the accuracy level of a Class 3 estimate. Accordingly, in order to rely on a numeric analysis of the costs of various options, the differences in results should be greater than the amount of uncertainty in the input assumptions. In the Inquiry, BC Hydro calculated the incremental cost to ratepayers of terminating the Site C project - including the cost of an alternative
portfolio - compared to the cost of completing, to be in the range of $6.2 billion to $11.1 billion. If this amount could be substantiated, it would provide a compelling case to continue. However, based on the evidence
available to the Inquiry we were unable to verify these amounts.7 That said, the estimates provided in the Final Report are based on many assumptions the Commission was required to make based on the information available to it during the Inquiry. To assist the government in its decision-making, the Commission included in the Final Report some sensitivity analyses to show how the cost
estimates would change if different assumptions were applied. An example of this is the forecast for energy demand.
The Commission has found that the forecast of energy demand is most likely to be at BC Hydro's "low load" or lower, based on available information, government policies in place and other factors. Should the government undertake future policy changes resulting in an increase in demand as high as BC Hydro's high load forecast, the
cost of Site C would be more attractive by $796 million.8 Likewise, the Commission estimates that Site C will cost $10 billion to complete. Should the government estimate that the project will end up costing $12 billion, the present value of the overall cost to ratepayers of Site C would be higher by $646 million. In the two examples just described, the difference in the estimates caused by changing the assumptions is less
than $1 billion. While this is a significant sum, recall that the estimate of termination costs could vary by that same figure. The Commission concluded based on its findings, that the cost to ratepayers of continuing or terminating the Site C project is similar. The Commission concedes that the Government might take a different view on one or
more of these assumptions, and the sensitivity analysis already provided in the Final Report should allow it to adequately evaluate the consequential effect of a change on the estimated cost to ratepayers. However, the Commission cautions that it would require a very significant difference between the estimates to conclude
reliably that one would be more expensive than the other.
In addition to the evaluation of ratepayer costs, the OIC requested that the Commission advise on the broader implications of the three options under consideration. The Final Report stated:
6 American Association of Cost Engineers, Cost Estimate Classification System - As Applied in Engineering, Procurement and Construction for the Process Industries.
7 Exhibit Fl-1, pp. 66-67 and 96-97. 3 Executive Summary, p. 17.
2 of 26
We have not been asked to make recommendations or to identify which option has the highest cost to ratepayers or more significant implications than others. Nevertheless, we have provided our view that not only is the suspension scenario the greatest cost to ratepayers of the three scenarios, it also has other negative implications.
We take no position on which of the termination or completion scenarios has the greatest cost to ratepayers. The Illustrative Alternative Portfolio we have analyzed, in the low-load forecast case, has a similar cost to ratepayers as Site C. If Site C finishes further over budget, it will tend to be more costly than the Illustrative Alternative Portfolio is for ratepayers. If a higher load
forecast materializes, the cost to ratepayers for Site C will be less than the Illustrative Alternative Portfolio. We have provided a discussion of the risk implications of each alternative in order to assist in
the evaluation.9 We trust that the information in the Final Report, including the discussion of risk, and the results of the province-wide Community Input Sessions and First Nations Input Sessions, will provide useful guidance to the government beyond the question of cost.
9 Final Report, p. 187.
3 of 26
Question 1: Inclusion of Site C sunk/termination costs The Deputy Ministers ask:
Did the Commission include sunk costs (the estimated $2.1 billion that has been spent to date on the project) and termination costs (the $1.8 billion determined by the Commission) in comparing the costs to ratepayers of completing Site C against the costs of pursuing an alternative portfolio of generation resources? Response
The Commission did not include sunk costs in the analysis of ratepayer impact for either Site C or the
Illustrative Alternate Portfolio of generation resources. The costs assumed in this analysis were, in both cases, only costs incurred from January 2018 onward. These costs include the termination costs of Site C which are included in the ratepayer impact of the Illustrative Alternative Portfolio. The Final Report states: In order to evaluate the cost to ratepayers of the termination case, and compare that rate
impact to the cost of completing Site C, we compare the cost to ratepayers of the energy for the alternative portfolio to the cost of completing Site C from January 1, 2018. The sunk costs of
$2.1 billion, which include the Site C regulatory account balance of approximately $0.5 billion, must be recovered in both scenarios. Accordingly, we do not consider the rate impact of the
sunk costs in the termination scenario. 10 The ratepayer impact analysis identifies the present value (PV) of the costs to ratepayers of Site C compared to an Illustrative Alternative Portfolio. The costs are modelled as a cost of service that is recovered in a revenue
requirement for the utility. The amounts are calculated annually for seventy years and are discounted (in a net present value [NPV] Analysis) to F2018 dollars. Thus we characterize the cost to ratepayers as the NPV of the seventy-year rate impact.
It is important to note that this does not necessarily reflect the same bill impact as would be faced by an individual ratepayer. That analysis would require further input assumptions, including the number of ratepayers that the revenue requirement is being collected from each year.
10 Final Report, p. 163.
4 of 26
This treatment is illustrated in the tables on page 167 of the Site C Final Report:
Table 1: Site C Final Report, Tables 39 and 40u
Output: Low LF - Alternative Portfolio A
Site C Termination Cost (F$18)
$
1,395
million
D
Alternative Portfolio Cost (F$1 8}
$
2,539
million
C
Surplus Energy Sale (F$18)
$
D
Total Rate Impact (A+B+C)
(788) million
3,147 1 million
Output: Low LF - Site C
A
Sunk Costs (F$ 18)
$
2,100 million
B
Site C Cost to Complete (F$18)
$
4,391
C
Flexibility Credit (F$18)
$
(66) million
D
Surplus Energy Sales (F$18)
$
(1,473) million
E
Total Rate Impact (B+C+D)
$
2,852^ million
million
In the table above, the $1,395 billion for "Site C Termination Costs" represents the PV of the $1.8 billion of Site C termination costs amortized over 30 years.
Table 2: Rate Impact ($ million) of Site C compared to the Illustrative Alternative Portfolio â&#x20AC;˘f **
!
Illustrative SiteC
Alternative Portfolio
As provided in the Final Report Errata
â&#x20AC;˘
Ratepayer impact
$2, 852 million
$3, 147 million12
If sunk costs are included, the ratepayer impact of both the continue and terminate options would be affected. If
the same amortization period was chosen the effect would be the same for each alternative. We discuss the issue of amortization period for both sunk and termination costs further in our response to question 3. The Deputy Ministers also ask: We were not able to determine whether the sensitivity analysis included on Page 17 of the
report's executive summary includes sunk costs and termination costs consistently. If it does not,
11 Final Report, p. 167, as updated by A-25 errata. 12 In a letter dated November 16, 2017, BC Hydro identified an additional errata related to application of inflation factors and discount rates which would reduce the PV cost of the Illustrative Alternative Portfolio by $60 million. The Final Report was not adjusted for this subsequent errata on the grounds of materiality.
5 of 26
could the Commission advise on how including these sunk and termination costs might change
the cost to ratepayers and the unit energy cost (UEC) in both scenarios? Response
The calculation of the Unit Energy Cost differs from the calculation of cost to ratepayers. The Panel found that there is no generally accepted definition of "unit energy cost." In the Inquiry, BC Hydro stated that "Unit Energy Cost simply expresses the cost for a resource by its levelized annual cost per unit of energy produced. n
13
The term "levelized cost of energy" or "levelized cost of electricity" (both often referred to as LCOE), are in general use in the industry to compare the costs of energy projects. For example, the US Energy Information
Administration (EIA) describes LCOE as follows: Levelized cost of electricity (LCOE) is often cited as a convenient summary measure of the overall competitiveness of different generating technologies. It represents the per-kilowatt hour cost (in discounted real dollars) of building and operating a generating plant over an assumed financial life and duty cycle. Key inputs to calculating LCOE include capital costs, fuel costs, fixed and variable operations and maintenance (O&M) costs, financing costs, and an assumed
utilization rate for each plant type. ...14 In the Preliminary Report, the Panel defined "unit energy cost" as: "Unit Energy Cost simply expresses the cost for a resource by its levelized annual cost per unit of energy produced. n 15 There were no submissions received on this issue, and in the Final Report the Panel stated: The Panel therefore confirms the unit energy cost definition proposed in the Preliminary Report, that the Unit Energy Cost simply expresses the cost for a resource by its levelized annual cost per unit of energy produced. ... Given the definition of UEC, the Panel finds it inappropriate that the unit energy cost be adjusted for sunk costs [i.e. that the sunk costs be added to Site C cost to complete or to the
Alternative Portfolio costs, as they are sunk so only future costs matter] and termination costs [i.e. that the termination costs be added to the Alternative Portfolio cost] and will not consider
these costs in the unit energy cost analysis. 16 If sunk and termination costs are included in the UEC analysis: â&#x20AC;˘
The Site C UEC, would increase.
â&#x20AC;˘
The UEC of the Illustrative Alternative Portfolio would increase
The quantum of the increases depends upon the assumptions made concerning recovery periods. The following tables provide a sensitivity analysis. Please also refer to our response to question 4 for a more complete discussion about recovery of sunk and termination costs.
13 Fl-1 Submission, p. 61. 14 EIA Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2017, p. 1, https://www.eia.gov/outlooks/aeo/pdf/electricity_generation.pdf
15 Final Report, p. 154. lo The wording in the Final Report has been corrected above to clarify that Site C sunk costs are excluded from the unit energy cost comparison.
6 of 26
Table 3: Unit Energy Cost Sensitivity Analysis - Sunk and Termination Costs SiteC
Sunk costs18
Amortization
added?
period (years)
Illustrative Alternative Portfolio17 Unit Energy
Sunk costs
Termination
Amortization
Unit Energy
Cost
added?
costs19 added?
period (years)
Cost
(F18$/MWh)
(F18$/MWh)
No
n/a
$44
No
No
n/a
$31
Yes
70
$57
Yes
No
70
$48
70
$57
50
$49
70
$57
30
$50
70
$57
20
$52
n/a
$44
70
$45
$44
50
$46
$44
30
$48
$44
20
$49
70
$63
No
Yes
No
Yes
70
$57
70
$57
50
$64
70
$57
30
$67
70
$57
20
$70
Yes
Yes
Table 4: Total Rate Impact Sensitivity Analysis - Sunk Costs
K
iil
SiteC
Illustrative Alternative Portfolio20
Sunk costs21
Amortization
Total Rate Impact
Sunk costs
Amortization period for
Total Rate Impact
added?
period (years)
(F18$million)
added?22
sunk and termination
(F18$million)
costs (years) No
n/a
$2,852
No
30
$3,147
Yes
70
$4,086
Yes
70
$4,399
70
$4,086
50
$4,530
70
$4,086
30
$4,775
70
$4,086
20
$4,969
17 All scenarios are for the low load forecast, Panel market price assumption, BC Hydro financing, Medium Wind and Geothermal costs.
18 Sunk costs of $2,100 million (F2018$) 19 Termination costs of $1,800 million (F2018$). 20 All scenarios are for the Low load forecast, Panel market price assumption, BC Hydro financing, Medium Wind and Geothermal costs.
21 Sunk costs of $2,100 million (F2018$) 22 Note that termination costs were included in the Total Rate Impact for the Alternative portfolio.
7 of 26
Question 2: Financing costs The Deputy Ministers ask:
In the event that government elects to terminate the Site C project, has the Commission assumed that BC Hydro would develop and finance the projects included in the alternative portfolio (wind, geothermai) rather than independent power producers (IPPs)? Response
The Commission did not assume that BC Hydro would develop and finance the projects included in the
alternative portfolio. Specifically, the Final Report states that "[t] he Panel makes no determination on whether BC Hydro or IPPs should undertake the investments included in the Illustrative Alternative Portfolio. Âť 23 The Deputy Ministers also ask: We observe that the Commission has in some cases used BC Hydro's lower cost of capital financing to calculate the cost of the alternative portfolio presented in the report, affecting the valuation of those projects. Could the Commission offer its view of the impact that a higher cost of capital would have on ratepayers if the alternative portfolio were developed by independent power producers rather than directly by BC Hydro? Response
The Final Report, to assist users in performing sensitivity analysis on the financing cost assumptions, described how users can perform an analysis of the effect of using IPP financing assumptions: The updated spreadsheet now allows for the application of different financing costs for wind and geothermai projects. If financing costs are assumed to be the same as BC Hydro's financing
cost for Site C (100% debt financing at a cost of 3.43%), the user should select 'BCH rate' in the drop-down menu of the 'Financing Option' variable of the 'Input and Output' tab. If these projects are assumed to be undertaken by IPPs and financed at the IPP financing rate assumed by BC Hydro at 6.4%, the user should select 'IPP rate' instead. If a different rate than 6.4% is
assumed, the user can change the value of 'IPP Financing Rate in %' directly.24
The Commission notes that selecting the IPP rate in the model results in a financing rate assumption of 6.4% in real terms, whereas BC Hydro's IPP financing rate assumption is 6.4% in nominal terms. In orderto model the
effect of use of BC Hydro's IPP financing rate, the rate in the model should therefore be set to 8.5 percent. The table below provides the results of the Illustrative Alternative Portfolio model if changes are made to the Commission financing cost assumptions. Please note that the sensitivity analysis below only reflects the increase
in financing costs of IPP financed projects, and does not reflect the corresponding decrease in ratepayer risk:
23 Final Report, pp. 159-160. 24 Final Report, Appendix C, p. 2.
8 of 26
Table 5: Sensitivity analysis regarding wind/geothermal financing cost assumption25 Illustrative Alternative Portfolio PV Cost 7,7.
Load forecast scenario
•—
Commission
Alternative financing
lncrease/(Decrease)
Assumptions 26 (BC
cost assumption (BC
in Alternative Portfolio PV cost
Hydro financing rate of
Hydro IPP financing
3.43%)
rate of 8.5%)
•
High load forecast
$5,121 million
$5,831 million
$710 million
•
Med load forecast
$4,618 million
$5,130 million
$512 million
•
Low load forecast
$3,147 million
$3,359 million
$212 million
The Deputy Ministers ask:
[By procuring new supply from competitive processes] BC Hydro avoids assuming such debt on its balance sheet and only recognizes the incremental costs of new energy purchases which would include the private sector's annual debt servicing costs and equity return within approved purchase contracts. It would be helpful to understand how the Commission assesses the impact on ratepayers of the additional debt associated with the assumptions underlying the alternative portfolio. We would particularly appreciate better understanding the Commission's approach to using BC Hydro's cost
of capital for IPP projects and the approach used for the cost of capital faced by an IPP (i.e. what IPPs actually pay) and the
resultant rate
impacts.
For example,
on page
159-160,
the
Commission appears to conclude that IPP financing is the relevant assumption for the alternative portfolio ... Response
On page 160 of the Final Report, the Commission stated that "the same financing cost should be assumed for
Site C and the Illustrative Alternative Portfolio." The Commission consistently used the BC Hydro financing rate in its comparison between Site C and the Illustrative Alternative Portfolio, for the reasons set out in the Final Report, which are repeated below for convenience. The Final Report goes on to provide an analysis of the effect of using the IPP financing rate for the alternative portfolio, as provided above. The Commission concluded that an analysis comparing Site C to an alternative portfolio should be agnostic as to the ownership structure used. The rationale for this approach is discussed in the Final Report: The question posed in the OIC- whether there is an alternative portfolio that will deliver the benefits of Site C at an equivalent or lesser cost - will yield a different response depending on
what assumptions are made regarding whether the alternative portfolio is developed by BC Hydro or by an IPP. ...
25 Results in this table are based on the revised Illustrative Alternative Portfolio spreadsheet published on Nov. 16 with the A-26 errata.
26 Final Report, p. 70, footnote 600.
9 of 26
By contracting for the supply of energy from an IPP, as opposed to developing an energy source directly, BC Hydro will transfer development, construction and operating risk to the IPP. In the Panel's view, the analysis should reflect this transfer of risk. CEABC suggests that the effect of
this transfer of risk should be reflected in the discount rate that is applied to each project. BC Hydro submits that it isn't practical to conduct such an analysis on a project to project basis. ... The Panel makes no determination on whether BC Hydro or IPPs should undertake the investments included in the Illustrative Alternative Portfolio. This Inquiry is not the place to address the question of BC Hydro versus IPP ownership and determine the optimal price/risk allocation in energy purchase agreements between BC Hydro and IPPs. Indeed, this review is agnostic with respect to ownership structure and instead focuses on the inherent cost and performance attributes of the generating assets, and how those assets will meet needs and address risk within the broader generation portfolio. In order to ensure that the outcome of this review is not biased for or against a particular ownership structure, the Panel therefore determines that an "apples to apples" comparison requires that the same financing costs be assumed for both Site C and the Illustrative Alternative Portfolio. However, to address the concerns raised by BC Hydro, the Panel provides additional scenarios with different financing assumptions. For these scenarios, BC Hydro financing will only
be applied to DSM initiatives, and IPP financing costs for all other generation sources. ...21
With regards to the reference to "additional debt" associated with the alternative portfolio, the Commission
notes that BC Hydro will be financing the Site C project with debt. Therefore, given the similar cost of Site C and the alternative portfolio, the Commission sees no "additional debt" in the event that BC Hydro were to build
alternative generating projects instead of Site C.
27 Final Report, pp. 159, 160.
10 of 26
Question 3: Demand-side management The Deputy Ministers ask: Government will need to consider the total cost of potential demand side managemen t
initiatives (rather than just the utility's costs) as it considers the alternatives. Could the Commission advise how the inquiry Terms of Reference led to assessing demand-side measures based on the Utility Resource Cost standard, when Total Resource Cost has been the standard for prior Commission proceedings? Response
The Report stated: With regard to what DSM cost should be included in the Alternative Portfolio, the Panel finds that the
cost should be the utility cost as section 3(b)(iv) of the OIC [questions] refers to the cost to
ratepayers.23 The terms of reference for the Inquiry requested that the Commission evaluate the costs to ratepayers of continuing, suspending or terminating construction of Site C. The Commission interpreted the phrase "costs to ratepayers" as referring to costs that would recovered through BC Hydro's revenue requirement . The Report also stated: "When calculating cost to ratepayers, we calculate the NPV of the incremental revenue requirement of the item in question.
ii 29
The Commission did not include costs that would be incurred by other parties, such as the government or individuals; neither did the Commission consider broader societal costs or benefits in the financial analysis. Therefore, when considering the costs to ratepayers of the DSM programs, the Commission included only the costs incurred by BC Hydro. The Deputy Ministers ask:
It is our understanding that in previous proceedings the Commission has concluded that the Total Resource Cost (TRC) test is the appropriate way to evaluate demand side management (DSM) in comparison to other resources. In this inquiry, the Commission's model uses the Utility Resource
Cost (URC) standard. We believe that using the URC model may underestimate the actual cost of DSM to ratepayers. It would be helpful for us to understand the Commission's rationale in choosing a test methodology that differs from past practice. Could the Commission confirm that
the TRC test remains the appropriate metric, and if so, what impact would this have on the analysis. Response
The total resource cost test remains an appropriate metric for analyzing whether or not to proceed with DSM programs. As we noted in the final report: "Regarding the use of the utility cost compared to the total resource
28 Final Report, p. 38. 29 Final Report, p. 164.
11 of 26
cost, the Panel agrees that BC Hydro should not be undertaking DSM programs that do not pass the total resource cost test.
Âť30
We also noted that the level of DSM investment included in the Illustrative Alternative Portfolio, a level
originally recommended by BC Hydro in the 2013 IRP,31 could reasonably be considered to pass this test: "However, the illustrative DSM portfolio only includes the first (lowest cost) block of BC Hydro's estimated incremental DSM opportunities. The Panel considers that the Illustrative Alternative Portfolio assumption that
the programs in this first block all pass the total resource cost test is reasonable. ,/32 The Commission did not use a utility resource cost standard in determining the appropriate level of DSM investment to include in the Illustrative Alternative Portfolio. Therefore, the Commission sees no impact to the analysis.
Once the level of DSM investment in the Illustrative Alternative Portfolio was determined, the Commission then addressed the question of its costs to ratepayers, as set out in the terms of reference. As explained in the answer to the question above, the Commission included only the costs that would be incurred by BC Hydro, and
thus passed on to ratepayers. The rationale for this approach is addressed in the Final Report: With regard to what DSM cost should be included in the Alternative Portfolio, the Panel finds that the cost should be the utility cost as section 3 (b)(iv) of the OIC refers to the cost to ratepayers, as opposed to the BC cost or the societal cost.
For example, the industrial load curtailment DSM program has a utility cost of $75/kW-year, while BC estimates that the total resource cost (i.e. the cost to the customer of curtailing) is $60/kW-year. The Panel considers it would not be consistent with the treatment of Site C to include in the Alternative Portfolio the cost to the industrial customer of curtailing supply (total
resource cost), instead of the cost to the utility of obtaining the curtailment (utility cost).33 The Deputy Ministers also ask: The report identifies an aggressive DSM program, coupled with load curtailments as a way to achieve the alternative portfolio scenario. We would appreciate further information from the
Commission on how such load curtailments would practically be achieved in the natural resource sector without impairing operations, jobs and economic growth for sectors already facing trade
sanctions and pressures Response
The Commission would not characterize the DSM plan included in the Illustrative Alternative Portfolio as aggressive. The level of DSM included in the Illustrative Alternative Portfolio is, in fact, the level recommended by BC Hydro in its 2013 Integrated Resource Plan, and was the least aggressive apart from one
of the five levels of DSM spending that BC Hydro modelled at that time.34
30 31 32 33 34
Final Final Final Final Final
Report, Report, Report, Report, Report,
appendix A, Appendix A, appendix A, Appendix A, Appendix A,
p. 38. p. 34. p. 38. pp. 38, 39. p. 34.
12 of 26
The Commission believes that load curtailment can be a mechanism to retain and attract additional industrial load, and so enhance, rather than impair, operations, jobs and economic growth. The Final Report identifies a desire by industry for higher levels of industrial curtailment opportunities than included in the Illustrative Alternative Portfolio. Specifically, the Association of Major Power Customers (AMPC) has argued for BC Hydro to offer higher levels of load curtailment as being in the interests of its members: Curtailable loads have already demonstrated that they can feasibly, cost-effectively and
dependably provide system capacity for the necessary duration of peak load events. AMPC's October 11 submission details the specifics of AMPC's position. Once long term curtailable tariffs are established; scalable capacity resources can be delivered in appropriate quantities and at very short notice compared to generation sources. From BC Hydro's forecasts of capacity and energy need, the immediate implementation of curtailable contracts and/or tariffs could provide the necessary time to take a more detailed look at how future energy needs are most reliably and affordably provided. This time is particularly valuable during a period of significant technological development in energy storage, to reduce the risk of adopting a potentially short
lived technology path. Moreover, this provides a non-rate mechanism to retain existing, and attract additional, industrial load. ...the Commission should, as part of any alternative energy portfolio evaluated, consider the full use of industrial load curtailment to generate needed system capacity, because load curtailment is a well-developed, well-studied program that can be implemented economically and quickly,
without the need to speculate on the its potential availability in the future.35
35 Final Report, Appendix A, pp. 72, 74, 75. Emphasis added.
13 of 26
Question 4: Amortization of sunk/termination costs The Deputy Ministers ask:
If the Site C project were terminated, the $4 billion sunk and remediation costs would need to be recovered, and the amortization period of that recovery would affect BC Hydro rates. Could the Commission please clarify whether it assumed that that these costs would be recovered over 10, 30 or 70 years? Response
The Commission made no assumptions on the recovery of sunk and termination costs. The Final Report states: Regarding the potential mechanisms to recover termination costs, the options available are either from BC Hydro ratepayers, the shareholder or some combination of the two. If these costs are to be recovered from ratepayers a further issue is over what period they should be recovered. Generally speaking, a regulated utility is entitled to recover from its ratepayers, all prudently incurred expenditures. Therefore, the issue would be whether the costs to terminate the project were prudently incurred and this can only be determined after the expenditures have been made. In regard to the recovery period, this requires further analysis. Considerations include intergenerational equity - too long a period risks forcing customers who may not benefit from the expenditure to pay for it. If the payback period is too short, there is a risk of rate shock. This Panel takes no position at this time what the recovery period should be and notes that it would be subject to Commission approval. The same principles apply to the recovery of the sunk costs. There are some that suggest that if the project is terminated, this could be an indicator that the decision to go ahead with the project was not prudent. Others argue that since the project was not approved by the Commission, the costs were, by definition, not prudently incurred.
The Panel takes no position on the recoverability from ratepayers for sunk and termination costs. Further, we take no position on the recovery period for sunk and termination costs. However, for the analysis of ratepayer impacts of the termination scenario, we have assumed that termination costs will be recovered from ratepayers over a 10, 30 and 70 year recovery period.
Although we do not consider the rate impact of sunk costs when comparing the continue and termination scenario, the costs must be recovered. In the case of Site C being completed these
costs would be included in the project costs, and barring any disallowance, would be recovered from ratepayers over the 70-year amortization period proposed. In a terminate scenario, again assuming the costs are to be recovered from ratepayers, to determine the cost impact to ratepayers requires assumptions regarding the amortization period.
14 of 26
The Deputy Ministers also ask: Fair and appropriate rate-setting principles for rate-regulated utilities typically aim to avoid
causing future generations to pay for investments from which they will derive no benefit. From
the Commission's perspective, can recovery of the sunk and remediation costs of Site C over longer periods of 30 to 70 years remain consistent with these inter-generational principles? Response
The Commission reiterates that we take no position on the recovery period for sunk and termination costs.
The recovery period would be the subject of Commission review if, and when these costs are incurred. When considering the recoverability of any costs, there are a number of regulatory principles considered, including:
Price signals that encourage efficient use and discourage inefficient use (economic efficiency); Fair apportionment of costs among customers (fairness); Avoid undue discrimination (fairness); Customer understanding and acceptance, practical and cost effective to implement (practicality); Freedom of controversies as to proper interpretation (practicality); Recovery of the revenue requirement (stability);
Revenue stability (stability); and
â&#x20AC;˘
Rate stability (stability).36
The above considerations would apply to the recovery period of both termination costs and sunk costs. We generally agree with the Deputy Ministers' statement "Fair and appropriate rate-setting principles for rateregulated utilities typically aim to avoid causing future generations to pay for investments from which they will
derive no benefit." Intergenerational equity is an important consideration when considering the deferral of cost recovery. However, in the termination case, both the sunk and termination costs relate to a stranded asset, and
it is important to note that no-one benefits from a stranded asset. Therefore there is no more - or less justification that any particular generation should be more liable than another for the costs related to that stranded asset.
The Deputy Ministers also ask: Recently it has been stated that recovering the project's sunk and remediation costs over a 10year period would lead to a 10 per cent hike in BC Hydro rates. Is this assertion consistent with
the Commission's thinking ? Response
The table below shows the initial effect on the revenue requirement of amortization of Site C sunk costs, followed by the combined effect when estimated termination costs have been incurred. BC Hydro's F2018
revenue requirement request of $4,626 million has been used to estimate the year one rate impact effect of the
3° Bonbright principles, BC Hydro 2015 Rate Design Application, Decision dated January 20, 2017, pp. 11, 12
15 of 26
alternative amortization options.37 BC Hydro real rate increases subsequent to F2018 will result in a lower percentage impact than that indicated on the table below. Table 6: Rate impact of alternative amortization period for Site C sunk and termination costs
Amortization Period
Year one costs recovered
(years)
Revenue requirement
impact
Site C sunk costs only ($2.1 billion) 10
302
6.5%
30
152
3.3%
50
122
2.6%
70
109
2.4%
Total Site C sunk costs and termination costs ($3.9 billion) 10
560
12.1%
30
282
6.1%
50
226
4.9%
70
203
4.4%
The Panel therefore confirms that the use of a 10-year amortization period for Site C sunk and termination costs have a potential rate impact of 10 percent. However, the actual rate impact of Site C termination will reflect the amortization period selected, which will in turn be driven by intergeneration equity and rate shock concerns,
and the degree to which sunk or termination costs prove to have been prudently incurred. The Panel notes that
the year one revenue requirement impact of Site C (before export revenues) is estimated at $499 million
(F2025).38 The scenarios for the total rate impact of the Illustrative Alternative Portfolio as presented in the Final Report39 include termination costs of $1,800 million. The analysis in the tables above suggests a situation whereby the sunk and termination costs of Site C would be recovered separately from the costs of the Illustrative Alternative Portfolio. To avoid double counting, it is therefore appropriate to present accompanying analysis that demonstrates the impact of removing termination costs from the total rate impact of the Alternative Portfolio.
Table 7 below indicates that the illustrative Portfolio would be less costly in all load forecast scenarios with termination costs excluded from the rate impact.
37 BC Hydro F2017-F2019 Revenue Requirement Application, Exhibit B-l-1, p. 1-38 33 BC Hydro Site C cost calculator (Submission Fl-4, BC Hydro, IR 2, Attachment 3), as adjusted to show total Site C costs (including sunk costs) as $10 billion.
39 Final Report Executive Summary Errata, Corrected Table 43, p. 10
16 of 26
Table 7: Total Rate Impact -Termination Costs Excluded from Alternative Portfolio
Site C- Total Rate
Illustrative Alternative Portfolio - Total
Impact
Rate Impact
(F18$milllions)
Difference between Site C and Alternative
Termination costs
Termination costs
Portfolio - Termination
included
excluded
costs excluded
(F18$milllions)
(F18$milllions)
(F18$milllions)
Low Load Forecast
2,852
3,147
1,752
($1,100)
Medium Load
3,901
4,618
3,222
($679)
4,325
5,121
3,726
($599)
Forecast
High Load Forecast
In addition, the Appendix to the Deputy Ministers' letter asks:
It would be helpful if the Commission could clarify how the choices of cost amortization and recovery periods in the Termination scenario fit within appropriate utility rate-setting principles that
recognize
and
avoid
unnecessarily
transferring
current
utility
costs
to future
user
generations when there are clearly no longer directly-related assets or benefits being provided. Such decisions lead rate-regulated accounting practice and use of regulatory accounts, which are areas of particular interest by the provincial Auditor General as well as credit rating agencies. Response
The issue of the appropriate period to recover Site C sunk and remediation costs is addressed in the Site C Final Report:
In regard to the recovery period, this requires further analysis. Considerations include intergenerational equity - too long a period risks forcing customers who may not benefit from the expenditure to pay for it. If the payback period is too short, there is a risk of rate shock. This Panel takes no position at this time what the recovery period should be and notes that it would be subject to Commission approval. ... Further, we take no position on the recovery period for sunk and termination costs. However, for the analysis of ratepayer impacts of the termination scenario, we have assumed that termination costs will be recovered from ratepayers over a 10, 30 and 70 year recovery period.
Although we do not consider the rate impact of sunk costs when comparing the continue and termination scenario, the costs must be recovered. In the case of Site C being completed these costs would be included in the project costs, and barring any disallowance, would be recovered from ratepayers over the 70-year amortization period proposed. In a terminate scenario, again assuming the costs are to be recovered from ratepayers, to determine the cost impact to
ratepayers requires assumptions regarding the amortization period.40 As noted above, the Commission considers numerous factors in determining the appropriate amortization period to use to recover Site C sunk costs and termination costs.
40 Final Report, pp. 163-164.
17 of 26
Question 5: Load forecast The Deputy Ministers ask:
We are unaware of prior instances when anything other than BC Hydro's mid-load forecast has been used for planning purposes. For that reason, we would like to clarify: Did the Commission assume lower demand for electricity (reflected in the low-load forecast used in the report) because it is forecasting a period of lower economic growth for the province in which major power consumers such as mining, forestry, technology and commercial sectors are in decline? Response
The Commission did not assume a lower demand for electricity "because it is forecasting a period of lower economic growth for the province." Further, the Report does not state, nor does it suggest, that "major power consumers such as mining, forestry, technology and commercial sectors" are in or are going into "decline". On the contrary, the Report specifically acknowledges that there have been some positive developments in the nonLNG large industrial load, but goes on to conclude that these positive developments are not sufficient to offset the negative developments in the potential BC LNG sector.
The Commission's consideration of the load forecast was based on a holistic assessment of the factors that drive demand for electricity. In our answer to the Deputy Ministers' question below regarding the rationale for the Commission's position, we present a description of the seven factors we considered. These include three factors that are directly related to economic growth: recent developments in the industrial sectors, GDP and other forecast drivers, and flattening electricity demand. The Deputy Ministers also ask: Does the Commission include in its load forecast the potential increased electrical power demand of meeting the province's stated objectives to reduce greenhouse gas emissions through greater
electrification of our economy? Response
The Commission does not have a load forecast. The terms of reference required us to use BC Hydro's load forecast from the 2016 Revenue Requirements Application, which has a mid-level projection within a high and a low band. We were also required to seek BC Hydro's view on factors which might influence expected demand toward the high or low cases. The Commission did consider electrification in the Final Report both from the perspective of impacts on the load forecast over the 20-year period and disrupting trends over time. These are considered below. In its submissions, BC Hydro highlights the emerging potential for load growth from initiatives targeting greenhouse gas emission reductions through electrification of fossil-fuel powered end uses. BC Hydro states "electrification of energy loads currently served by fossil fuels such as space and water heating, vehicles and industrial equipment could reasonably cause demand for electricity to exceed BC Hydro's mid forecast in the
Current Load Forecast."
18 of 26
However, BC Hydro does not account for electrification initiatives directed at reducing greenhouse gas emissions in its Current Load Forecast because the timing and magnitude of the potential increase is uncertain at this early stage. BC Hydro presents the potential for electrification to have an upward impact on the load forecast in the figure below. Figure 1: BC Hydro's Load Forecast Range, Impact of Electrification, and Deloitte's "Alternative" Load Scenario
90,000 80,000 70,000 •A-r.'rt:
60,000 V
_
50,000
5 g
40,000
m
30,000
CD
>5 20,000
Load Forecast Range
—
Deloitte Load Forecast
10,000
» BC Hydro Current Forecast
---Electrification
o
<$> qv"
yr <pP /V <pP yp yr
yp yP
^
^
yp <pP <pv <pp <pP
yp yP
^\p y? yp
Fiscal Year
(year ending Mar 31)
Although available information indicates that the effects of electrification on BC Hydro's load forecast could potentially be significant, the timing and extent of those increases remain highly uncertain. Given the uncertainty, the Site C Inquiry Panel agreed with BC Hydro that additional load requirements from potential electrification initiatives should not be included in the load forecast for the purpose of resource planning.
The extent and timing of electrification initiatives will be a matter of government policy. In the absence of such policy, it is not appropriate to include any potential additional load requirements from electrification initiatives in the load forecast for resource planning. Should the government set further policy with respect to electrification, BC Hydro would need to prepare an updated load forecast reflecting the impact of such policies. Although not taken into account in the load forecast, electrification is still an issue for consideration. In its report, the Panel noted that if electrification does materialize in the future, it is possible that some of the
higher electricity demand could be offset with aggressive conservation measures, including DSM programs that achieve
load reductions similar in magnitude to those experienced in New England.41
41 Page 75 of the Final Report includes the following submission by CanWEA: "These [downside risks] are very real risks that are being realized in many other North American electricity markets. In New England, where I am from, the most recent long-term electricity demand forecast by the Independent System Operator is for a .6% compound annual decline in energy
19 of 26
The Panel also acknowledged numerous submissions identifying disruptive factors that could potentially decrease demand, including the potential impact of expanded distributed generation . However, because these downward impacts on load are uncertain, the Panel did not identify any specific trends that would suggest an adjustment to the Current Load Forecast is required. The Deputy Ministers further ask:
We have noted that the Commission has concluded that BC Hydro's low load forecast was most appropriate for an assessment of the need for the capacity of Site C. It would be helpful for us to further understand the rationale, and whether the assessment includes the load requirements needed to meet the Province's Clean Energy Act energy objectives of: â&#x20AC;˘
Reducing greenhouse gas emissions by 2050 by 80% less than 2007 levels;
â&#x20AC;˘
Encouraging the switching from one kind of energy source or use to another that decreases greenhouse gas emissions in British Columbia; and,
â&#x20AC;˘
Encouraging
communities
to
reduce
greenhouse
gas
emissions
and
use
energy
efficiently. Response
To recap the Final Report, the Commission concluded:
Overall, the Panel finds BC Hydro's mid load forecast to be excessively optimistic and considers it more appropriate to use the low load forecast in making our applicable determinations as required by the OIC. In addition, the Panel is of the view that there are risks
that could result in demand being less than the low case.42 In making findings on BC Hydro's load forecast, the Commission considered the following factors: 1.
Recent developments in the industrial sectors
2.
Accuracy of Historical Load forecasts
3.
GDP and other forecast drivers
4.
Price Elasticity assumptions
5.
Future Rate increases
6.
Potential disrupting trends
7.
Flattening electricity demand
Each of the seven items considered by the Commission in arriving at its determina tion on BC Hydro's load forecast are addressed in detail in the Final Report and are summarized below.
consumption over the next ten years, with no meaningful increase in peak load. New York ISO is also forecasting a decline in energy consumption (-.2% per year)."
42 Final Report, p. 77.
20 of 26
Recent developments in the industrial sectors The Panel reviewed recent developments in the industrial sector and concluded: The Panel finds the developments since the Current Load Forecast was prepared, as reported by BC Hydro, can reasonably be expected to reduce demand from the expected case or mid forecast. The Panel acknowledges there have been some positive developments in the non-LNG large industrial load that BC Hydro suggests provide a net increase in demand since the Current Load Forecast was prepared (an anticipated positive total variance is approximately 750 GWh/100 MW in the short and medium term and 965 GWh/114 MW over the long-term). However, given the risk and volatility of the industrial load and its susceptibility to cyclical ups and downs, and the risks to the large industrial load set out by AMPC, the Panel is unable to draw any conclusions that these recent developments will result in a permanently positive impact on industrial demand. In any event, in the Panel's view these positive developments in the non-LNG sector are not enough to offset negative developments for a potential BC LNG sector. The Panel finds that developments since the Current Load Forecast was prepared have significantly reduced the probability that the majority of BC Hydro's forecast LNG load will materialize. Regarding the potential LNG industrial load, BC Hydro itself states there are questions as to whether BC has missed the window of opportunity for LNG. While BC Hydro points to certain third-party market views that still show some support for the opportunity to develop LNG in BC, the Panel notes the significant uncertainty expressed in most market views, the recent cancellation and postponement of several large potential BC LNG projects, and the higher costs of potential BC LNG projects compared to existing and potential projects in other jurisdictions. The Panel also agrees with several parties who express concern with the fact that BC Hydro had not made a probabilistic assessment of the likelihood of the LNG load materializing. The Panel agrees with Finn that the three projects cited by BC Hydro face
uphill
battles, especially given the current poor market conditions. 43 Accuracy of historical load forecasts After reviewing the accuracy of BC Hydro's historical load forecasts, the Panel stated: As noted in its Preliminary Report, the Panel finds that the historical instances of overforecasts are greater than under-forecasts, especially in the industrial load, and that the accuracy of BC Hydro's historical industrial forecasts looking out three and six years has been considerably below industry benchmarks.
The Panel acknowledges BC Hydro's argument that the drivers of historical industrial forecast variances are not relevant to the expected accuracy of the Current Load Forecast, especially considering the impacts of large discrete customer load attrition between 2006 and 2010 and the steps BC Hydro describes it has taken to ensure its existing industrial forecasts are reasonable. However, as pointed out by CEC, some of these declines in industrial load could or should have been anticipated and may represent a bias towards over-forecasting. Accordingly , while the Panel does not place significant weight on the historical inaccuracies in the load
43 Final Report, p. 78.
21 of 26
forecast, it does approach the Current Load Forecast with some skepticism, especially as it
relates to the industrial load forecast.44 GDP and other forecast drivers After reviewing BC Hydro's GDP growth assumptions, the Panel stated: ...The Conference Board of Canada forecast projects the real GDP will grow by 2.6 percent on average between 2016 and 2020 and then drop to an average of 2.3 percent between 2021 and
2025. In contrast, BC Hydro's projection results in an average growth rate of 3.5 percent over the same five years. BC Hydro's forecast results in the BC economy being six percent larger than the CBoC's forecast by 2025. The Panel considers BC Hydro's average growth rate of 3.5 percent to be excessive.
The Panel remains concerned that BC Hydro's GDP and disposable income forecast drivers are higher than other comparable third party estimates, such as the CBoC. Based on the evidence presented in this Inquiry, the Panel can make no definitive finding on the appropriate GDP or disposable income driver to apply. However, considering the historical over-estimates in the
load forecast as noted above, the Panel approaches BC Hydro's estimates with skepticism given that these key drivers are both considerably higher than otherthird party estimates and use of the lower estimates would result in a lower load forecast. Accordingly, the Panel finds BC Hydro's mid load forecast is higher than if it used the CBoC estimates and adjusting for this
could reasonably be expected to influence demand towards the low load case. 45 Price elasticity assumptions
With regard to price elasticity, the Panel made the following findings: The Panel finds the -0.05 long-run price elasticity used by BC Hydro for all rate classes to be too low in magnitude to reflect the degree of change in demand for a given change in price. Accordingly, the Panel finds BC Hydro's mid load forecast is higher than would otherwise be the case if it used lower price elasticity factors, and that adjusting for this would reduce demand towards BC Hydro's low load forecast case. The Panel finds that BC Hydro should be using a long-run price elasticity given the long 70 year time horizon of Site C. The Panel also finds that the international literature shows that longrun elasticities are higher than short-run elasticity. It is not clear to the Panel that BC Hydro's empirical studies have appropriately estimated long-run price elasticities since the residential inclining block rate and the transmission stepped rates have not been in place over a long time horizon.
The Panel finds the residential long-run price elasticity is likely to be more than -0.05. BC Hydro's empirical evidence shows a range from 0 to -0.13; however, the zero in the low-end of the range with no price response indicates the study results may not be reliable. The Panel
44 Final Report, P. 78. 45 Final Report, pp. 78-79.
22 of 26
notes the study by Paul, Myers and Palmer shows the low-end of the range to be at -0.14 for
residential long-run elasticity. BC Hydro's empirical evidence shows that the price elasticity for commercial and industrial general service customers is close to zero so BC Hydro adopted -0.05. The Panel finds that BC Hydro's empirical evidence for the price elasticity of commercial customers is unreliable in determining the long-run price elasticity. The Panel notes the international literature shows varied results for commercial customers. Paul, Myers, and Palmer had a long-run elasticity average of -0.29 with a range of -0.02 to -0.70. Bernstein and Griffin had a single estimate
of -
0.97 which suggests the elasticity could be higher than -0.05. 46 In addition, the Panel noted BC Hydro's consultant GDS's recommendation that BC Hydro's price elasticity coefficients used to estimate "rate impacts," which were developed in 2007, need to be updated. Future rate increases
BC Hydro assumed no real rate increases beyond the end of the 10 Year Rates Plan (F2024).47 The Commission concluded with regard to this assumption: The Panel finds BC Hydro's demand forecast is sensitive to rate changes even using BC Hydro's low price elasticity factors. Accordingly, any real increase in rates beyond the rates reflected in the 2013 10 Year Rates Plan and any subsequent real rate increase could reasonably be expected to influence demand towards the low load case. The Panel finds there will be considerable upward pressure on rates for the remainder of the 2013 10 Year Rates Plan and beyond fiscal 2024. The Panel finds the risk associated with this upward pressure on rates is especially concerning given the submissions related to potential "demand destruction" that could result from the impact of real rate increases on already vulnerable industrial customers and the likelihood that even nominal rate increases will increase energy poverty among BC's low income households. 48
Potential disrupting trends The Panel raised as a concern that, given the long life of the Site C asset, BC Hydro has only identified a potential upside risk to the load forecast from electrification, and had not identified any potential downside risk. The Panel concluded: Given the uncertainty, the Panel finds additional load requirements from potential electrification initiatives should not be included in BC Hydro's load forecast for the purpose of resource planning. Although available information indicates that the effects of electrificatio n on BC Hydro's load forecast could potentially be significant, the timing and extent of those increases remain highly uncertain. BC Hydro has not included in its Current Load Forecast additional load requirements from electrification initiatives to reduce greenhouse gas emissions. The Panel agrees with BC Hydro and Hendriks etal. that the timing and magnitude of the increase is uncertain at this time. However, electrification is still an issue for consideration. The Panel notes that if electrificatio n
46 Final Report, pp. 79-80. 47 Final Report, p. 65. 43
Final Report, p. 80.
23 of 26
does materialize in the future, it is possible that some of the higher electricity demand could be offset with aggressive conservation measures, including DSM programs that achieve load reductions similar in magnitude to those experienced in the New England states.
The Panel acknowledges the numerous submissions identifying disruptive factors that could potentially decrease demand, including the potential impact of expanded distributed generation. However, because these downward impacts on load are uncertain, the Panel did not identify any specific trends that would suggest an adjustment to the Current Load Forecast is
required.49 Flattening electricity demand CEC, Surplus Energy Match and CanWEA all provide evidence that total demand is not growing in most jurisdictions in North America - in most cases it is flat or declining. In British Columbia
the declining use per customer over the last 10 years has largely offset the effects of population
growth.50 Figure 2: US Residential Electricity Consumption
US Residential Electricity Consumption 6
5 5 :c.
c 4 .9
1 3 "C
9
a 2 i ID
CD
r-
co
gt
O
r-l
ro
T
LA
O
r-
oo
cn
o
xh
t-H
tâ&#x20AC;&#x201D;I
tH
rH
tâ&#x20AC;&#x201D;i
(N
rsi
r-f
rd
o
o
rsj
o
CN
o
(N
o
N
O
M
O
IN
O
rA
O
fO
cnj
r-i
O
rsi
O
r-4
O
r>4
r-i
rsi
ru
cm
r-j
rd
ru
ooooooooooo
cm
cm
<N
rsj
<n
m ro rsi
n ro cm
t ro cm
LTS
CD
r-
m
ro
ro
rsj
rsj
cm
Residential Electricity Consumption
The Deputy Ministers ask:
It has been government's assumption that electrification with low carbon electricity would be a key initiative to achieve greenhouse gas reductions. The provincial government is working with the Government of Canada on electricity system infrastructure investments to reduce and avoid greenhouse gas emissions, and has enabled BC Hydro to pursue electrification initiatives under the Greenhouse Gas Reduction (Clean Energy) Regulation under the Clean Energy Act. It would be helpful for our ministries to understand if the Commission has a different outlook, and if the
49 Final Report, pp. 81-82. 50 Final Report, p. 82.
24 of 26
Commission could further describe the impact on its analysis of electrification initiatives to meet greenhouse gas reduction objectives. Response
The Commission's outlook on electrification and its effects on the load forecast are provided in the Final Report. We refer the Deputy Ministers to our previous answer for a summary of the material. The Deputy Ministers also ask: We understand that BC Hydro has provided the Commission with a description of its view of
what BC's economic environment would look like under a low load outlook scenario. It would [be] helpful if the Commission could further describe its interpretation of the low load outlook. We
observe that the Commission's view is that the outlook could be even lower than that presented in BC Hydro's low-load scenario, and we are interested in understanding how that outlook is based on realistic economic sustainability around which the alternative portfolio would be premised. Response
The Commission's consideration of the load forecast was based on a holistic assessment of the factors that drive demand for electricity. In our answer to the question above regarding the rationale for the Commission's position, we have included a description of the seven factors we considered. These include three factors that are directly related to economic growth: recent developments in the industrial sectors, GDP and other forecast drivers, and flattening electricity demand.
25 of 26
Additional question: Dispatchability The Deputy Ministers ask:
It would also be useful to know if the Commission examined the value of "dispatchable" resources versus intermittent resources, particularly as applied to the goal of moving industrial energy requirements now and in future to low carbon electricity. Response
The Commission examined the value of "dispatchable" versus intermittent resources in its selection of generation options in the Illustrative Alternative Portfolio, and concluded that "increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers
as the Site C project with an equal or lower Unit Energy Cost. n 51 Appendix A of the Final Report contains the Commission's analysis of each generation option in the Illustrative Alternative Portfolio, and the degree to which they provide "dispatchable" energy. With regards to wind energy, for example, the largest single contributor to the Illustrative Alternative Portfolio, the Commission stated: BC Hydro states that Site C (capacity 1,145 MW) can integrate 900 MW of wind. However, the Panel notes that BC Hydro's existing modest level of wind penetration (780 MW) and high levels of hydro generation providing reserves (GM Shrum, Mica and Revelstoke with a combined capacity around 8,000 MW) means that BC Hydro would not be expected to need Site C to
integrate these additional wind farms.52 In comparison, the Illustrative Alternative Portfolio includes 444 MW of wind generation in the low load forecast
and 729 MW in the high load forecast.53
51 Executive Summary, p. 3. 52 Final Report, Appendix A, p. 32. 53 Final Report, Errata, p. 6.
26 of 26