Application Instruction
(foto)
Sealing of cable duct
(foto)
02-07-2013
APPLICATION INSTRUCTION
Outside
Duct to be sealed with a barrier, 2100 Aquastop and Stopaq Mortar FR or WR.
Basement side
Sealing of cable duct
2
1. 2. 3.
02-07-2013
Barrier Stopaq 2100 Aquastop, 100mm Mortar, 50mm FR = Flame retardant WR = Water resistant
APPLICATION INSTRUCTION
Outside
The complete system:
Basement side
Sealing of cable duct
3
2
50mm
100mm
1
3
Outside
Clean the duct with a brush, cleaning pad or similar equipment. Total length approx. 175mm. Rinse with clean water is allowed as 2100 Aquastop can be applied on a wet surface. Adhesion can be improved when pipe and duct are pre-applied with 2100 Aquastop.
Basement side
Sealing of cable duct
Âą175mm
02-07-2013
APPLICATION INSTRUCTION
4
Outside
Insert barrier at a depth of 150mm into the duct. Use a foam tape or, cloth to separate the cables from each other.
Basement side
Sealing of cable duct
150mm
02-07-2013
APPLICATION INSTRUCTION
5
Sealing of cable duct
Cables separated by foam tape
Cables separated by pre impregnated cloth 02-07-2013
APPLICATION INSTRUCTION
6
Sealing of cable duct Preheat the 2100 Aquastop up to a temperature 30째C. A bucket of water and a water heating coil can be used. STOPAQ
STOPAQ
STOPAQ
STOPAQ STOPAQ
STOPAQ
30째C
02-07-2013
APPLICATION INSTRUCTION
7
Outside
Apply 100mm of 2100 Aquastop without air enclosures. Work from inside out to prevent air-enclosures. Lift the cables and apply the 2100 Aquastop with an appropriate application gun around the cables. Clean the remaining 50mm of the duct prior to the installation of Mortar FR or WR.
Basement side
Sealing of cable duct
STOPAQ
STOPAQ
STOPAQ
STOPAQ
STOPAQ
STOPAQ
100mm
30째C
02-07-2013
APPLICATION INSTRUCTION
8
Sealing of cable duct Prepare Mortar WR to a mouldable mass. Mortar WR shall be used as a waterproofing barrier in wall inlets that frequently exposed to huge amounts of water. Mixing ratio by volume, mixing time 1 minute: 4 parts Mortar WR 1 part of Water. 1 min
Mortar WR
02-07-2013
Mortar WR
Mortar WR
Mortar WR
APPLICATION INSTRUCTION
H20
9
Sealing of cable duct Prepare Mortar FR to a mouldable mass. Mortar FR shall be used in fire rated walls and floors. Mixing ratio by weight, mixing time 3-5 minutes: 1 kg Mortar FR 0,6 – 0,8 litres of water Mixing ratio by volume, mixing time 3-5 minutes: 2 – 4 parts Mortar WR 1 part of Water. 0,6 – 0,8 litres H20
Mortar FR
02-07-2013
Mortar FR
Mortar FR
Mortar FR
H20
APPLICATION INSTRUCTION
3–5 min
1 kg Mortar FR
KG 10
Outside
Check the malleability of the Mortar by moulding the Mortar to a ball shape without it falling apart. Apply Mortar in the remaining 50mm of the duct. Start at the bottom between the cables. Smoothen the surface of the mortar by using a putty knife and some water.
Basement side
Sealing of cable duct
50mm
02-07-2013
APPLICATION INSTRUCTION
11
02-07-2013
APPLICATION INSTRUCTION
Outside
If an extra cable has to be put through the duct, first drill a hole with a larger diameter as the cable on the position where the cable has to go through.
Basement side
Sealing of cable duct
12
Outside
Insert the cable and inject 2100 Aquastop and apply Mortar WR or Mortar FR. Smoothen the surface with a putty knife. A cable can be removed with the same procedure; remove cable new 2100 Aquastop New mortar.
Basement side
Sealing of cable duct
STOPAQ
STOPAQ
STOPAQ
STOPAQ
STOPAQ
STOPAQ
30째C
02-07-2013
APPLICATION INSTRUCTION
13
Outside
Basement side
Sealing of cable duct
Note: Simplified representation of the application, Please check PDS, SDS, Scope of work for detailed product- and application descriptions. 02-07-2013
APPLICATION INSTRUCTION
14