SECO Energy is locally owned and operated for the sole benefit of our members, which means our priorities align with your needs. We focus on providing reliable, affordable electric service that benefits the entire community. To enhance the reliability of our services and address the growing needs of the communities we serve, SECO Energy has recently made several significant investments in our existing infrastructure:
Timberwood Substation (Marion County):
We’ve installed a new power transformer and added three additional distribution circuits, increasing capacity to 75 megawatts — doubling its previous capacity. This upgrade also includes an automatic transfer scheme that connects to another distribution feeder. During a power outage, crews can transfer load between feeders for faster and safer restoration.
Clermont Substation (Lake County): Ranking among SECO Energy’s top five substations for load and member count, we’ve added two new power transformers, boosting capacity to 112 megawatts – an increase of nearly 50%.
Webster Substation (Sumter County):
To improve reliability, we’ve replaced an older fuse system with a more advanced transmission fuse breaker and upgraded three single-phase power transformers to three-phase power transformers.
Sumterville Substation (Sumter County):
We’re expanding this substation and tripling the capacity from 37 to 112 megawatts by building a second side, replacing one power transformer, and installing two new power transformers. Construction is scheduled for completion by the end of 2024.
On tap for 2025 is a brand-new substation in Lake County. The Dilly Lake substation near Howey-in-the-Hills and Minneola is undergoing a major rebuild. The capacity of the substation is almost quadrupling from 28 to 112 megawatts. We’re increasing the distribution circuits from two to eight and adding two new power transformers.
These upgrades support new and existing homes and businesses and ensure reliable power during peak demand as Central Florida grows. We understand that reliability, value, and trust are what SECO Energy members expect. That’s why we’ve made these proactive improvements to address today’s needs and support future growth.
Sincerely,
CURTIS WYNN CHIEF EXECUTIVE OFFICER
A Legacy of GROWTH AND SERVICE
October is National Co-op Month, and SECO Energy is proud to join REI, Land O' Lakes, Ocean Spray, Florida's Natural Growers, Inc., and other cooperatives across the United States in celebrating co-ops' impact on their communities. Co-ops come in various shapes and sizes, but no matter how big or how small, they all share a common goal: to provide exceptional goods or services to their members.
Founded in 1938 as Sumter Electric Cooperative, Inc., SECO Energy has evolved from a small rural utility into a leading not-for-profit Touchstone Energy Cooperative serving Central Florida. SECO powers over 245,000 homes and businesses across seven counties today, providing reliable, safe, and affordable electric service to over half a million consumers. This remarkable growth has made SECO Energy the seventh-largest in the nation among over 900 electric cooperatives.
PROTECT YOUR HOME WITH SURGE MITIGATOR™ – FREE INSTALLATION!
Power surges can wreak havoc on your appliances and electronics. SECO Energy’s Surge MitiGator™ program can help safeguard your home. From October 1 to November 12, SECO Energy is running a promotion for FREE installation when you enroll in this essential protection plan. The Surge MitiGator™ program is the first step in defending your large appliances by reducing surges at the meter before they can enter your home. Don't wait for disaster—invest in peace of mind today.
SECO ENERGY YOUTH TOUR LEADERSHIP
OPPORTUNITY
CALLING ALL HIGH SCHOOL JUNIORS! Apply now to win a sponsorship for the 2025 Tallahassee Youth Tour.
ELIGIBILITY: Any high school junior living in a home that receives electric service from SECO Energy. Up to ten students will be selected to attend the Tallahassee Youth Tour – one from each of our nine Districts and one at large.
TALLAHASSEE YOUTH TOUR DATES: February 12 – 13, 2025
APPLICATION DEADLINE: December 13, 2024
TALLAHASSEE YOUTH TOUR HIGHLIGHTS:
• Visit the State Capitol
• Venture the Florida Supreme Court
• Tour the Governor's Mansion
• Explore museums
• Develop leadership skills
• Learn about the Cooperative Business Model
WASHINGTON YOUTH TOUR COMPETITION:
After the Tallahassee Youth Tour, each of the ten participants will have a second opportunity to compete for one of two spots to attend a once-in-a-lifetime, sponsored trip to tour our Nation's Capital as SECO Energy's 2025 Washington Youth Tour delegates.
In June 2025, the two selected students will join more than 1,800 students from across the country to learn about our great nation, develop leadership skills, better understand electric cooperatives, and make lasting friendships.
Students selected for the SECO Energy Youth Tour will be notified in early January 2025. The two Washington D.C. Youth Tour representatives will be announced during the SECO Energy Youth Tour banquet in April 2025.
THE 7 COOPERATIVE PRINCIPLES POWERING SECO ENERGY
A MESSAGE FROM JAMES LAMOTTE
At SECO Energy, you’re not just connected to an electric provider. You’re a valued member of a Touchstone Energy Cooperative guided by seven cooperative principles that put your needs first:
1. Voluntary and Open Membership:
Membership is open to all individuals who purchase electric service from SECO Energy.
2. Democratic Member Control: Your vote matters. Members elect fellow members like me to SECO’s Board of Trustees to ensure cooperative decisions reflect your interests.
3. Members’ Economic Participation: Members contribute by paying their monthly utility bill. At the end of the year, profits are then distributed to members, not investors.
4. Autonomy and Independence: SECO is controlled by a nine-member Board of Trustees that is focused on the needs of our members and communities.
5. Education, Training, and Information: SECO provides the tools and knowledge to help you understand your energy use and make informed decisions.
6. Cooperation Among Cooperatives: SECO collaborates with other cooperatives, enhancing service reliability and sharing resources in times of need.
7. Concern for Community:
SECO is committed to improving the communities we serve, from supporting local schools to investing in renewable energy.
These principles aren’t just words; they’re the foundation of how SECO Energy operates, ensuring that we serve you, our members, with fairness, transparency, and care.
The Board of Trustees will meet on Monday, October 28, 2024, at 2:30 p.m. in the Corporate Offices at 330 South US HWY 301 in Sumterville. A Trustees’ meeting will also be held on Monday, November 18, 2024.
ACSI ® is one of the oldest and most highly regarded industry satisfaction studies which publishes annual customer satisfaction results for approximately 400 companies across about 40 industries and 10 economic sectors based on roughly 200,000 customer interviews.