Fidelity Headquarters - Pre Design Proposal

Page 1

8 0 0 E . F I R S T, S U I T E 1 4 0

|

WICHITA, KANSAS

|

316.263.4300

|

SHELDENARCHITECTURE.COM



PRE DESIGN PROPOSAL FIDELITY BANK HEADQUARTERS FEBRUARY 21, 2022



PROPOSAL


February 21, 2022 Fidelity Bank Terri Rosenhamer, CFM/BOC 100 E. English Wichita, KS 67202 Re: Fidelity Bank Headquarters Expansion: Masterplan and Pre-Design Dear Terri: Thank you for the opportunity to submit our proposal for the Fidelity HQ Masterplan and Pre-Design Services. Our proposal is based on our understanding of your project scope and the architectural services you desire. For this project we have assembled a great group of consultants some of which you already know, but others will be new to you. All their resumes are attached (along with the Shelden team).       

Baughman Company will continue with us as civil engineer SCA Consulting Engineers will continue with us as structural engineer AWS (Nathan Mittag) will continue with us as curtainwall consultant Integrated Consulting Engineers, Inc. is being added to the team for MEP engineering Façade Forensics is being added to the team as an enclosure and structural expert FSC, Inc. is being added to the team as a code analysis consultant We understand that Conco will continue to assist and review our design direction with budgets, schedules, and constructability reviews along the way. It is understood that bidding the project to other GC’s is likely, but Conco will continue to operate in a guiding and reviewing capacity.

We are very excited about the entire team and the new additions are very strong and ready to get going. We see the early design process being divided into at least 3 major steps. I will outline these steps in our PROJECT SCOPE below: PROJECT SCOPE Step 1: Discovery (6-8 weeks)  Confirm/Draw As-Builts of existing facilities and understand what existing areas need to stay as is and what areas are recommended for change. This would be accomplished with much consultation directly with the Facilities Team.  Develop/Confirm the Building’s “Program of Spaces”. We understand the executive team has identified an initial list of spaces and functions for the new HQ expansion. We further recommend that Fidelity fully vet all departments of the bank and verify current space allocations as well as what the possible growth needs are for each to better forecast the future; (i.e., are we making appropriate assumptions for the numbers and types of spaces that will be needed over the next 5, 10 and years beyond). We will assist your Facilities Team by meeting with the appropriate department leaders as we define the current and long-term space needs of each group. The “Program of Spaces” will translate the above information into an approximate amount of square footage and volume of space needed to accomplish the identified goals with an assumed amount of growth/future needs factored into the document.


Step 2: Test Fit and Site Options (8-12 weeks)  Based on the “Discovery” step above we will proceed to review the 2 identified site options for where the HQ expansion could occur (attached to the existing HQ or free-standing across the street). This “Test Fit” step will involve several layers of review. Although this list below may not be comprehensive, we know it will include the following:  Review Building Codes and apply general code analysis for both sites to understand pros and cons of each site as it relates to the building. FSC, Inc. will assist Shelden Architecture with the code analysis/review along with the City of Wichita code officials.  Explore Site/Building Layout Options & Associated Studies (Plan studies and 3-D models)  Review the impact on the existing HQ plan-wise and regarding the exterior curtainwall of the new and the old. With assistants from AWS (Nathan Mittag) and Facade Forensics.  Review the impact on the existing Sanitary Sewer and other underground utilities if the new expansion is directly attached to the existing HQ  Review the impact of how does a freestanding building option across the street change the existing HQ, its connection to the parking garage and each other?  Deliverables include the above items plus: Drone aerial footage at each site (Courtesy of Conco), Master Site and Building Concept Plans, complete exterior 3-D site and building model with the ability to create multiple views from any number of selected angles and/or a fly around video as you have seen before. We will also include a physical site model to better communicate the design direction for use in future phases of development.  Explore/determine structural systems for each site and outline pros and cons for the various systems. SCA Consulting Engineers will assist Shelden Architecture with this review.  Explore/determine HVAC and Electrical system options for the building as it relates to each site and in general. Integrated Consulting Engineers will assist Shelden Architecture with this review.  Estimate the Budget (with the assistance of G.C.) to a Rough Order of Magnitude level. This would be broken into site costs, building shell costs and interior buildout cost ranges. Step 3: Visit Related Projects and Determine Remaining Steps (4-8 weeks)  Based on having thought through the needs and focus of the project we can tour various related projects with an eye towards the specific issues our project will address.  Fine-tune list of various mid and high-rise buildings in the mid-west to tour. (See attached list as a starting point)  Outline a more detailed Project Schedule – we believe a rough Project Schedule to be: Approximately 12 Months for Shell Building Design and 18-24 months for Construction but this will be confirmed as the scope of the building project is defined.  Determine remaining scope and fee for A/E services and schedule ongoing design meetings to finalize building design and prepare for construction. ARCHITECTURAL SERVICES  Architectural services will be provided in accordance with the AIA Standard Form of Agreement Between Owner and Architect (AIA Document B101, 2017 Edition) and will include the Masterplan and Pre-Design phases. After this initial phase is completed, we will define the remainder of the scope of services and associated fees.

Page 2 of 3


ARCHITECTURAL FEES  Architectural and Engineering “Pre-Design” fees will be billed monthly on an hourly basis for the above scope of work to a cap not to exceed $90,000. An approximate breakdown of the fee is as follows:  Program of Spaces, Test Fit and Site Options: $37,000  Curtainwall and enclosure review $8,000  Code analysis and review $15,000  Structural analysis and review $15,000  MEP analysis and review $10,000  Civil utilities and City Engineering review $5,000  If we approach this fee cap, we will make you aware of this and not go beyond it without your prior approval. REIMBURSABLE EXPENSES  Expenses, including printing, out of town travel for our team, courier service, express deliveries and any other miscellaneous expenses incurred during project production, would be billed at 1.1 times original cost. In no event shall the Reimbursable Expenses include the Architect’s ordinary overhead costs. FULL SITE SURVEY (already completed and paid for)  Full Site Survey: Baughman Company PA has provided full architectural survey. Architect to coordinate additional Civil and City of Wichita review as outlined above. Again, thank you for the opportunity to submit our proposal. We are looking forward to working with you and ready to proceed upon your approval. Please sign below and return a copy to our office to indicate your acceptance. This proposal letter will serve as a contract between Shelden Architecture, Inc. and you, the project Owner. If you have any questions or need further information, please don’t hesitate to call. Sincerely,

Shelden Architecture, Inc. Stan Shelden, AIA – President Authorized and accepted:

By:

Cc:

“Terri Rosenhamer/Fidelity Bank”

Date:

PROPOSED BUILDING TOUR SITES Resumes

Page 3 of 3


Fidelity HQ Expansion and Remodel PROPOSED BUILDING TOUR SITES: KANSAS CITY AREA: University of Kansas Health Systems, Kansas City, KS University of Kansas Health Education Building, Kansas City, KS Dairy Farmers of America Headquarters, Kansas City, KS Polsinelli, Kansas City, KS Black & Veatch, Overland Park, KS LAWRENCE, KS AREA: University of Kansas Capital Federal Hall, Lawrence, KS OMAHA AREA: The Foundation Offices Interiors, Omaha, NE Core Bank HQ, Omaha, NE DES MOINES, IA AREA: 111 East Grand, Des Moines, IA MINNEAPOLIS, MN AREA: New Public Service Building, Minneapolis, MN Land O’Lakes HQ, Arden Hills, MN MADISON, WI AREA: Zendesk Interiors, Madison, WI CHICAGO AREA: Columbia College Student Center, Chicago, IL Sterling Bay Office Interiors, Chicago, Il INDIANAPOLIS AREA: Cummins Indy Distribution HQ, Indianapolis, IN DALLAS AREA: Westdale HQ Interiors, Dallas, TX Polsinelli, Dallas, TX Baylor Scott & White Administrative Building, Dallas, TX JP Morgan Chase Regional HQ Interiors, Plano, TX HOUSTON AREA: 609 Main, Houston, TX AUSTIN, TX AREA: 2010 South Lamar, Austin, TX Oracle Campus, Austin, TX 2010 South Lamar, Austin, TX 1836 San Jacinto, (In Progress) Austin, TX Indeed Office Interiors at the Domain, Austin, TX DENVER, CO AREA: Polsinelli, Denver, CO PORTLAND, OR AREA: 100 Stewart Hotel and Apartments, Portland, OR NASHVILLE, TN AREA: Gulch Crossing, Nashville, TN NEW YORK CITY AREA: White & Case, New York, NY 152 Elizabeth Street, New York, NY



OUR TEAM


STAN SHELDEN, AIA President/Owner since 2002 Shelden Architecture stan@sheldenarch.com

EDUCATION Bachelor of Architecture Kansas State University, 1987

PROFESSIONAL REGISTRATIONS Kansas License 4158

• RELEVANT PROJECT EXPERIENCE Fidelity Car Park - Wichita, KS IMA Headquarters - Wichita, KS Martin Pringle Headquarters - Wichita, KS Spaghetti works Apartments & District Wichita, KS Lyons Federal Bank - Lyons, KS Intrust Bank Downtown Headquarters Wichita, KS Intrust Bank Branches Various Locations - Wichita, KS Grene Vision Medical Office Building Various Locations - Wichita, KS Kansas Health & Science Center/DO School Wichita, KS Equity Bank Headquarters Overland Park, KS & Wichita, KS Equity Bank Branches Various Locations - Wichita, KS Sterling College Master Plan & Various Projects Sterling, KS Hesston College Master Plan & Various Projects Hesston, KS Friends University Master Plan & Various Projects - Wichita, KS

Positive. Upbeat. To Stan Shelden, the glass is always half full. Whether he’s sketching out a design or spending time with his wife and five daughters, Stan is likely to have a smile on his face. “If you’re not having fun, then please find something else to do!” You can see Stan’s optimism reflected in his work. As owner and founder of the firm, he takes personal pride and ownership in each project. He believes in his team and the work they produce. Stan serves on the Wichita Douglas Avenue Steering Committee, the Wichita Design Council and is a past member of the Wichita Historic Board. He is also serves as an Elder at Heartland Community Church. MANTRA: CORAM DEO - “Before the face of God”


DANIEL GENSCH, AIA Executive Vice President Shelden Architecture daniel@sheldenarch.com

EDUCATION Master of Architecture Kansas State University, 2009

PROFESSIONAL REGISTRATIONS

Kansas License 6834

• RELEVANT PROJECT EXPERIENCE Fidelity Car Park - Wichita, KS Fidelity RISE Farm - Wichita, KS Spaghetti works Apartments & District Wichita, KS Martin Pringle Headquaters - Wichita, KS Bokeh Development - Broadway Auto Park Wichita, KS Bokeh Development - Revolutsia - Wichita, KS Sterling College Gleason Physical Education Center - Sterling, Kansas Hesston College Master Plan - Hesston, Kansas Hesston College Yost Center & Bonnie Sowers Nursing Center – Hesston, KS

For Daniel Gensch, there is a purpose for everything and everyone. He believes that we are not merely products of our environment and therefore strives to positively influence his clients, coworkers, and community. His motivation is to unlock potential, lead by example, and never stop learning. Daniel’s diverse experience ranges from years of International Master Planning for large-scale complex projects to highly detailed aspects of architectural design. His goals are to naturally discover design, be relational, and exceed clients’ expectations. As Executive Vice President at Shelden Architecture, he focuses on management efficiencies and client business development and leads projects as a Project Manager. Daniel is reminded each day that our greatest influence on the world rests directly in our relationships at home. “If I by God’s grace can be successful with the responsibilities I have at home, then I am exceedingly more equipped to fulfill my role in the firm.” MANTRA: “In everything, strive for excellence above perfection.”


RANDY CROOK,

AIA, CDT, CCCA

Sr. Project Manager randy@sheldenarch.com

EDUCATION Bachelor of Environmental Design, Architecture University of Kansas, 1984

PROFESSIONAL REGISTRATIONS Certified Construction Document Technologist Certified Construction Contract Administrator Construction Specifiers Institute

• RELEVANT PROJECT EXPERIENCE House of Formation - Wichita, KS The Alley - Salina, KS Schellenberg/Remax Headquarters - Wichita, KS Berry Companies Headquarters Various Locations - Wichita, KS Ditch Witch - Wichita, KS Noah’s Event Centers - Wichita, KS St. John Clommel - Wichita, KS St. Thomas Aquimas - Wichita, KS St. Rose of Lima Masterplan and Church Mt. Hope, KS Hesston College - Yost Center and Bonnie Sowers Nursing Center - Hesston, KS Grene Vision Group - Wichita, KS

Randy Crook is one of those guys who seems to know someone everywhere he goes. If he doesn’t, he soon will. He likes talking to people and is even known to actually call someone rather than text, fax, email, or facebook them. That said, he also is known to text, email, and facebook if that is what it takes to communicate a message, idea, or image. Having worked with steel, masonry, pre-cast concrete, wood, and pre-engineered construction, and having worked for three years for a General Contractor, Randy has an emphasis on materials and methods of construction. His responsibilities include marketing, master planning, schematic design, preparation of construction documents, and construction administration. He is a current member and Past President of Blessed Sacrament Men’s Club, a member of the Knights of Columbus and is the Facilities Chair for the School Council of Kapaun Mt. Carmel High School. His many volunteer associations include Habitat for Humanity, Sisters of St. Joseph Golf Tournament, and a golf committee member for Newman University Jet Open. Along with photography, golf is one on his favorite past times (you may have guessed that!) MANTRA: “Pre-destiny is a convenient way to look at the past but no way to look at your future”


RIANNE MCDONALD,

NCIDQ, IIDA

Interior Designer rianne@sheldenarch.com

EDUCATION Bachelor of Interior Design Kansas State University, 2016

PROFESSIONAL REGISTRATIONS

National Council For Interior Design International Interior Design Association

• RELEVANT PROJECT EXPERIENCE IMA Headquarters - Wichita, KS American State Bank - Wichita, KS Equity Bank Branch - Overland Park, KS Hayes Company - Wichita, KS Equity Bank Headquarters Various Locations, Wichita, KS Hesston College Nursing & Athletic Addition Wichita, KS Martin Pringle Headquarters - Wichita, KS Spaghetti works Apartments - Wichita, KS Heartspring Expantion - Wichita, KS Schellenberg/Remax Headquarters Wichita, KS MB Foundation - Hillsboro, KS Grene Vision Group - Wichita, KS

Rianne’s main passion is people. As an emerging designer, it is her intent to improve the quality of life and promote a strong sense of place for the client and community as a whole while sculpting the interior form into something functional, beautiful and environmentally sensitive. She is motivated by creative and technical problem solving. Her experiences have provided the opportunities to fully realize the importance of details, design articulation, and collaboration. Her academic background of human ecology, gerontology and interior design has provided her a unique perspective when working with clients and their design vision. Eager to obtain more knowledge in every aspect of the profession, she is working towards her LEED certification. When out of the office, she’s always looking for her next creative venture; whether that be painting, home projects or trying new things around Wichita with her family. MANTRA: “I am not going to be. I am always becoming.”


DEYAN TRIFONOV, ASSOC. AIA

Architectural Designer deyan@sheldenarch.com

EDUCATION Masters in Architecture New Bulgarian University, 2013

• RELEVANT PROJECT EXPERIENCE Fidelity Car Park - Wichita, KS Douglas Avenue Development - Wichita, KS Sterling College - Gleason Center Sterling, KS Martin Pringle Headquarters - Wichita, KS Heartland Credit Union Various Locations - Wichita KS

Deyan is an organized, detail-oriented, and conscientious intern architect. Having lived in America for a few years now, Deyan is still eager to learn what motivates and influences American architecture while bringing to the table a fresh approach with the latest international ideas. Back home in Bulgaria, Deyan attained a Masters of Architecture from New Bulgarian University in Sofia and participated in a number of prestigious European forums and exhibitions. He was also a student participant in a workshop with Daniel Libeskind, the master plan architect for the reconstruction of the World Trade Center site in Manhattan. Deyan is a logical thinker and is blessed with the ability to take difficult conditions and express a considered and simple solution and is a valuable member of our architectural team. Deyan and his wife, Martina, are active explorers of their new country and spend much of their off time discovering what the Midwest has to offer. MANTRA: “Learning never exhausts the mind.”


BRANDON WILSON Project Coordinator Integra Building Advisors LLC brandon.wilson@integrabldgadvisors.com

EDUCATION Bachelor of Construction Science & Management Kansas State University, 1998

PROFESSIONAL REGISTRATIONS & LICENSES Associate General Contractors of America (AGC) General Contractor Real Estate License

• RELEVANT PROJECT EXPERIENCE Meritrust Credit Union - Wichita KS Emprise Bank - Wichita, KS Kansas State Bank - Wichita, KS Stillwater National Bank (SNB) - Wichita KS Bank of Oklahoma - Wichita KS Community National Bank - Wichita KS Union State Bank - Winfield, KS Newspring Church - Wichita KS Hartman Oil Building - Wichita, KS Doubletree Hotel at Airport - Wichita, KS Pinnacle Apartments - Wichita, KS MKEC Engineering Corporate Office - Wichita, KS Wesley Medical Arts Tower - Wichita, KS Wesley Health Strategies - Wichita, KS Wilson Estates Office Park - Wichita, KS Waterfront Office Park - Wichita, KS

Brandon brings a wealth of construction knowledge and experience to the table. Having created and operated his own construction company for over 17 years, he understands the entrepreneurial mindset and spirit and the day-to-day concerns of the project owner. He merges this knowledge with the demands of the project to help the team produce a smooth process for the Owner and as well as the Design/Construction team. Brandon’s positive approach to life and his professionalism in the workplace is evident to all who’ve worked with him. His quiet, confident nature along with his track record delivers the necessary level of trust required in large, complicated projects. He is currently a member of the Envisions Andover Strategic Planning Group, Young Professionals of Wichita, the City of Andover’s Site Plan Review committee and formerly on the Bulter County Community College Engineering Advisory Council. He also gives back to the area with his active volunteerism with the Food Bank, YMCA, Newspring Church and Northeast Baseball Association.



SPECIALITY CONSULTANTS


Ali Alaman, P.E. Code & Life Safety Consultant

-

Education: B.S., Civil Engineering Registration: Professional Engineer: KS, MO, NE Affiliations: Society of Fire Protection Engineers (SFPE) International Code Council (ICC) ALI ALAMAN, P.E., is the Principal-in-Charge and a Code and Life Safety Consultant of FSC’s Code and Life Safety Division. He has more than 31 years of experience in code consulting, including eight years as a plan examiner for the City of Kansas City, MO. He will ensure that all resources are available for the project team for the execution of a successful project and will be the executive level code and life safety contact for the team providing management and oversight while facilitating smooth communications. Ali’s knowledge of numerous code and life safety requirements has led him to be an expert in his field. His consulting experience provides clients with code strategies, applications and interpretations, alternate design methods, exit studies, inspections, evaluation of fire resistive assemblies, and fire and smoke modeling services. Ali has served as an expert witness, presented code presentations to architects and Authorities Having Jurisdiction (AHJ). In addition, he has acted as an AHJ performing reviews and inspections for code compliance on behalf of municipalities, universities, and school districts. -

-

-

-

-

-

-

-

Cargill Protein HQ Building & Garage, Wichita, KS new four-story, 188,000 SF office building with café, conference center, wellness rooms, and a five-level garage. Polsinelli Law Firm HQ & Garage, Kansas City, MO new two-building development with a 10-story, 253,800 SF high-rise office building with retail and restaurant space, and a 940-space garage. Polsinelli Law Firm TIs – provided code consulting on TIs in Denver, Minneapolis, Houston, and Kansas City. Dairy Farmers of America HQ, Kansas City, KS - new three-story, 106,000 SF office building with open and closed offices, conferencing space, a training facility, a workout space, and a café. 46 Penn Centre/Garage, Kansas City, MO - new 16story, 260,450 SF office building with 6,500 SF of retail space, restaurant space, and eight-stories (188,500 SF) of office space that is placed over a six-level parking garage. 1400 Baltimore/Garage, Kansas City, MO - new 18story, 590,000 SF high-rise office building that includes eight stories of core-and-shell office space above a ten-level, 900-space garage. Waddell & Reed Tenant Finish at 1400 Baltimore – tenant finish of eight floors includes offices, a variety of meeting rooms and a cafeteria on the top story with outdoor dining and seating areas. H&R Block Offices & Garage, Kansas City, MO - new 17-story, 530,000 SF high-rise office building with offices, a Tier-3-Plus data center, food service, lobby area, theater / auditorium, service and dock area, and 1,250-space garage. Tampa Sky Center One Office Building & Garage, Tampa, FL - new nine-story, 272,000 SF office building with a conference center, fitness center, and café., with an attached 4 level garage.

FSC, INC. HEADQUARTERS 8675 W. 96th Street, Overland Park, KS 66212 Tel: (913) 722-3473

-

-

-

-

-

Kiewit Regional HQ Campus & Garage, Lenexa, KS (suburb of Kansas City) - new six-story, 181,680 SF office building and remodel of two existing four-story buildings with an atrium. Kiewit TIs – provided code consulting on TIs in Seattle, Fort Worth, and Dallas. Cerner HQ Office Complex, Kansas City, MO two new eight-story high-rise office towers. 4800 Main, Kansas City, MO - core and shell renovation the existing seven-story, 205,000 SF Board of Trade building. Populous TI – provided code consulting on the three-story TI for Populous at 4800 Main. Aspiria, Overland Park, KS - a new 10-story, 252,350 office building. 1800 Walnut Apartments/Garage, Kansas City, MO - new 14-story, 145,000 SF high-rise building with 130 apartments, a rooftop public bar, and a 975-space garage. Loews KC Convention Center Hotel/Garage, Kansas City, MO - new 23-story, 818,000 SF hotel with restaurants, a fitness center, retail space, and 60,000 SF of meeting and event space. Two Light Apartments/Garage, Kansas City, MO - new 24-story, 361,100 SF building with two levels of mixed-use areas, sixteen levels of residential units, and a 500-space garage. Three Light Apartments, Kansas City, MO - new 26-story building with apartments and seven garage levels. Residential Tower Buildings/Garage - Phoenix, AZ, Memphis, TN, and Raleigh, NC - three new 20+ story apartment buildings with garages. Broadwest Hotel and Condos, Nashville, TN new 34-story tower.

OTHER LOCATIONS Kansas City, KS / Bhopal, India www.fsc-inc.com


Nathan Mittag VP, ARCHITECTURAL WALL SYSTEMS Architectural Wall Systems (AWS) is an industry-leading partner in building envelope solutions. With experience across the country, AWS specializes in design-assist partnerships for high-performing facades. Nathan has been with AWS for more than 16 years, currently serving as a Vice President in our Omaha region. He works day-in and day-out to make sure current clients are receiving quality execution, while also helping new clients discover innovative project solutions.

Experience

Fidelity Car Park Wichita, KS $2,300,000 Completed in 2020 Design-assist partner for the 550-stall parking structure’s unitized curtain wall and hook-and-pin enclosure. All systems were shopassembled and glazed at AWS’ fabrication facility. UNITIZED | DESIGN ASSIST

HDR Headquarters Omaha, NE $10,500,000, Completed in 2018 Design-assist exterior enclosure subcontractor responsible for unitized curtainwall, structural studs & sheathing, air barrier, thermal insulation, masonry, point supported glass, metal panel and ceramic tile rainscreen systems.

HDR Headquarters

COMMERCIAL OFFICE | UNITIZED | DESIGN ASSIST

TD Ameritrade Headquarters Omaha, NE $27,000,000 Completed in 2013 Design-assist partner for the custom unitized double-skin curtainwall facade on this 12-story office building. COMMERCIAL OFFICE | UNITIZED | DESIGN ASSIST

TD Ameritrade Headquarters

FIDELITY CAR PARK Wichita, KS

Fidelity Car Park is a partnering model for concept design to construction delivery. AWS worked directly with the project team to deliver the most efficient design achievable. From an initial bid, scheduled allowance to refine the design, city tours for inspiration, a final design that drove cost down and added architectural elements, Fidelity Car Park’s project success is a tangible model for future collaborative work.


! fixing skins before and after they’re built facade forensics, inc. 5311 Salem Road Suite 100 Cincinnati, Ohio 45230 p:513-383-9906 f:513-232-0425 e:mlewis4@cinci.rr.com

Michael Lewis AIA NCARB FASTM MSEng is a forensic architect specializing in building enclosure design and rehabilitation. He has diagnosed deficiencies and created remedies for over $900 million of enclosures on nearly $9 billion of new, existing and historic buildings internationally. Superior capability to recognize and cure problems results from his unique experience as licensed architect, engineering graduate, adjunct professor, facade contractor, and expert witness. As an ASTM Fellow and TMS member, he authors code and standards used internationally to improve building quality. Enclosures he has repaired or improved include some designed by Gilbert, Hake, Hannaford, Graber & Woodward, Durrell Stone, Studios, Ennead, IMPei, HOK, SOM, HDR, HGA, DLR, NBBJ, GBBN, KPF, WRL, VOA, ZGF, Yamasaki, Johnson, Gehry, Safdie, Stern, Pelli, Graves, Gensler, Eisenmann, Pei-Cobb-Freed, Porphyrios, Leo A Daly, Cooper Carry, DeStefano Goettsch, Libeskind. Education: BArch, Architecture, University of Cincinnati, Cum Laude MSEng, Structural Engineering, University of Cincinnati, Magna Cum Laude Member:

2008 recipient of ASTM’s Walter C. Voss Award for distinguished contributions to knowledge 2010 recipient of ASTM’s Award of Merit for distinguished service and outstanding participation American Institute of Architects American Society of Civil Engineers American Society for Testing & Materials Association for Preservation Technology International Code Council The Masonry Society National Trust for Historic Preservation

History:

Consultant: Facade Forensics since 2002; THP Limited 1993-2002; Osborne Engineering 1984-1986 Professor: University of Cincinnati School of Architecture 1989-2011 Graduate Program 2002-2011 Contractor: Industrial First, Inc. 1986-1989, & Harmon Contract W.S.A. 1989-1993

Published: Modern Stone Cladding, Design & Installation of Stone Systems, author of ASTM Manual 21 ASTM Standard C1242 “Guide for Selection, Design & Installation of Stone Anchorages” Characteristics That Affect the Integrity of Existing Thin Stone Cladding, and Status on Development of Code Requirements For Exterior Stone Cladding, author of two papers in ASTM STP 1499 Performance of Exterior Building Walls, co-author of paper in ASTM STP 1422 Degradation of Natural Building Stone, co-author of paper in ASCE GSP No.72 “Restoring Building Facade Durability by Performance Principles”,“Logical Design & Engineering of Stone Building Facades”, “Choosing Stone Cladding for Building Facades”, Stone World “Current Thoughts on Testing”, “Understanding Exterior Wall Behavior Principles”, “Engineering Approaches to Cladding”, “Stone Anchorage Design”; “Fundamental Principles”, Dimensional Stone “Anchoring Thin Stone Veneers”, Architecture; “Turning Architecture into…Art”, Standardization News Presented: “Attaining a High-Performance Enclosure”, PEDCo High Performance Buildings Seminar “Structural Performance Critical to Proper Curtainwall Function”, Structural Engineers Assoc of Ohio “Critical Considerations in Exterior Stone Cladding” University of Minnesota, Int’l Masonry Institute “Establishing the Integrity of Existing Thin Stone Cladding”, ASTM Oct 06 Symposium, Atlanta “Essential Tasks to Commissioning an Exterior Wall”, Turner Construction Company, Ohio, statewide “Developing Code Requirements for Stone Cladding”, The Masonry Society, Cincinnati “Diverse Limestone Applications”; “Cladding Case Studies”, Indiana Limestone Institute, Bedford “Improving Quality of Masonry Walls”, Turner Construction Company Seminar, Cincinnati “From Wrecking Ball to New Supreme Court”, ASTM Symposium, New Orleans “Importance of Studying Exemplars…”, ASTM Symposium, New Orleans & Phoenix “Assuring Durability of Stone Facades in New Construction”, ASCE, Minneapolis “Restoring Stone Facade Durability”, ASTM–CIB–ISO-RILEM Symposium, Israel “Achieving An Optimum Skin”, Salon Internacional de la Piedra Natural, Spain “Terracotta Case Study Rehabilitations”, Terracotta Symposium, Cleveland “Applying ASTM Standards”, Marble Institute of America, Cincinnati “Contractor's Perspective on Stone Anchorage”, Harmon Contract National Seminar, Minneapolis


RESUME

Larry Funk, LEED AP Vice President

Larry has been with SCA for over 30 years. He is a principal client relationship executive for the firm and oversees the production department for particular projects. Larry’s design expertise includes structural steel, concrete, masonry, and tilt-up construction for a full range of commercial structures, including retail space, hotels, and churches. He is SCA’s representative to the USGBC as a LEED accredited professional and is a certified verifier with NAHB. His focus is on providing client service, maintaining long-term client relationships and establishing dependability with new clients through adept project management which includes performing site visits, discussing concepts and schedules, and coordinating between different disciplines that include architectural, mechanical and civil. PROJECT EXPERIENCE PROFESSIONAL ORGANIZATIONS Lakeside at Waterfront, Murfin Inc. Wichita, Kansas U.S. Green Building Council LEED A seven (7) story Class A concrete office building with 110,456 SF and 6,500 SF of upper level outdoor space. Each floor footprint is unique and offers a variety of distinctive layouts with Accredited Professional private veranda style balconies and secured access.

NAHB - National Green Building Fidelity Investments Parking Garage, Wichita, Kansas A five story mixed use parking structure with 189,000 SF and 500+ parking spaces. The projCertification ect has public and secure parking, dining, retail and office space.

430 East Douglas Ave., Wichita, Kansas A five (5) story Class A office building with approximately 84,000 GSF. The structural system will be steel frame. II City Plaza, 400 Convention Street, Baton Rouge, Louisiana An eighteen (18) story 377,000 SF tower with 276,000 SF of Class A office space and an additional 101,000 SF of parking. The structural system is composed of concrete columns with post-tensioned beams and slab. The project also has a separate parking structure with seven (7) levels, 288,786 SF and 800 spaces located next to the building. Aloft Hotel, Wichita, Kansas Five (5) story steel fame hotel with 127 guest rooms and approximately 67,371 GSF. Douglas Ave. Development, Wichita, Kansas A mixed-use, adaptive reuse and new construction with a total development area of 100,000 SF. High Wickham Place Buildings 6 & 7, Louisville, Kentucky Two (2) three story office buildings. Building six is 64,000 SF and building 7 is 63,500 SF. The buildings are structural steel frame with composite bar joist floor and concrete on metal deck. Pioneer Natural Resources, Midland,Texas Six (6) story Class A concrete corporate office building with 272,000 SF for an oil and gas firm. The project also includes a 450 car parking garage. The Reserve at Park Ten - The Energy Corridor, Houston, TX A 365,200 SF “Class A” 6-story office building with an 8-story concrete parking garage. Flat plate cast in place concrete midrise office building with an adjacent 500 space cast in place concrete parking garage. LEED Certified. Structural Consultants Associates • 12511 Emily Court • Sugar Land, Texas 77478 • 713.779.7252

scaengineers.com


RESUME

Brock L. Shepard,P.E. Chief Business Development Officer/Owner Engineer of Record As Chief Business Development Officer of SCA Consulting Engineers, Brock is responsible for the design of efficient and effective structural systems for various types of commercial and residential projects. He is involved in all phase of the design process from initial concept through completion of construction documents, including calculations, coordination of design and production of drawings and specifications. Brock’s expertise in the latest building and design codes for steel, concrete, masonry, and wood structures contributes to his overall understanding of various building systems and engineering techniques which assists in cost effective quality designed projects. EDUCATION

Bachelor of Science in Construction Management, University of Houston 2006

Master of Engineering in Civil/Structural Engineering, Norwich University 2010

REGISTRATIONS

Registered Professional Engineer in the State of Texas, Alabama, Arkansas, Arizona, Colorado, Connecticut, Delaware, Florida, Georgia, Idaho, Indiana, Kansas, Kentucky, Louisiana, Maryland, Maine, Michigan, Minnesota, Missouri, Mississippi, Montana, North Carolina, Nebraska, New Hampshire, New Mexico, Ohio, Oklahoma, Pennsylvania, South Carolina, Virgina, Wisconsin and Wyoming

PROFESSIONAL ORGANIZATIONS

American Concrete Institute (ACI) Post Tensioning Institute (PTI) American Institute of Steel Construction (AISC) American Society of Civil Engineers (ASCE) Structural Engineers Association of Texas (SEAoT)

PROJECT EXPERIENCE REVE Building II & III, Boulder, Colorado Multi-family residential project with a total of four buildings for an approximate total building area of 721,700 GSF to create a business complex with Mixed Use residential and office buildings. Two, six (6) story residential buildings. The buildings are two levels of below grade parking and four levels of apartments above. A three (3) story building with the 2 levels of below grade as well and a four story Class A concrete office building approximately 124,000 SF. The two (2) level parking garage below grade is located under Buildings 1, 2, 3 and 4 with approximate total area of 169,338 SF. New Brunswick Student Housing at Rutgers, New Brunswick, New Jersey A 208 unit/624 bed, nine (9) story steel building over a two story 160 space parking structure. Approximately 370,000 GSF. Aspire Student Housing, Eugene, Oregon A twelve (12) story 286,000 GSF student housing project with 230 units/417 beds. Parking for 214 spaces is provided and located on the first four lower levels of the structure with residential units above. The project is post tension concrete construction. Aspire, San Marcos, Texas Thirteen (13) story, 220 unit complex with retail space, offices and a parking garage, a total of 754 bedrooms. Aspire Tucson Student Housing, Tucson, Arizona Fourteen (14) story residential project with a construction area of 351,000 SF. The structure has two levels of garage parking below grade. The structural system will be two way flat plate concrete construction. Aspire Tucson Phase 2, Tucson, Arizona Ten (10) story, 133 unit (477 beds) student housing project with a total construction area of 314,000.00± SF. The structure has two levels of garage parking below grade. The first floor has retail and amenity with eight levels of apartment units above, including a mezzanine level at level eight. The structural system is two way flat plate concrete construction. 430 East Douglas Ave., Wichita, Kansas A five (5) story Class A office building with approximately 84,000 GSF. The structural system will be steel frame.

Structural Consultants Associates • 12511 Emily Court • Sugar Land, Texas 77478 • 713.779.7252

scaengineers.com


RESUME

Westley Hinton,P.E.,S.E. Vice President/Senior Associate

As a Vice President/Senior Associate of SCA Consulting Engineers, Wes is responsible for the design of efficient and effective structural systems for various types of commercial and residential projects. He is involved in all phase of the design process from initial concept through completion of construction documents, including calculations, coordination of design and production of drawings and specifications. Wes’s expertise in the latest building and design codes for steel, concrete, masonry, and wood structures contributes to his overall understanding of various building systems and engineering techniques which assists in cost effective quality designed projects. EDUCATION Masters of Civil Engineering, University of Virginia (2006) Commonwealth Graduate Engineering Program Bachelors of Architectural Engineering – Structural emphasis, Pennsylvania State University (2000) 5 Year Professional Degree – ABET Accredited REGISTRATIONS Registered Professional Engineer in the State of California (Civil and Structural), Colorado, Kentucky, Louisiana, Michigan, Nevada, New Jersey, North Carolina, South Carolina, Texas, District of Columbia, Virginia, Washington State (Civil and Structural). PROFESSIONAL ORGANIZATIONS American Institute of Steel Constructors (AISC)

PROJECT EXPERIENCE Lakeside at Waterfront, Murfin Inc. Wichita, Kansas A seven (7) story Class A concrete office building with 110,456 SF and 6,500 SF of upper level outdoor space. Each floor footprint is unique and offers a variety of distinctive layouts with private veranda style balconies and secured access. Fidelity Investments Parking Garage, Wichita, Kansas A five story mixed use parking structure with 189,000 SF and 500+ parking spaces. The project has public and secure parking, dining, retail and office space. II City Plaza, 400 Convention Street, Baton Rouge, Louisiana An eighteen (18) story 377,000 SF tower with 276,000 SF of Class A office space and an additional 101,000 SF of parking. The structural system is composed of concrete columns with post-tensioned beams and slab. The project also has a separate parking structure with seven (7) levels, 288,786 SF and 800 spaces located next to the building. Arabella, Houston, Texas Thirty-three (33) story luxury high rise residential tower with 115 units. Residential, amenities, etc is 354,634 SF, parking garage is 139,148 SF. The structural system is flat plate post tension concrete construction. Vantage Medical Center, Houston, Texas Twenty-two (22) story residential tower with 378 units and 693,000 SF. The structure has five levels of parking (579 spaces) with seventeen levels of residential units above. The structural system is flat plate post tension concrete construction. Katy Station, Victory Park, Dallas, Texas Thirty (30) story residential building with 461 units. The project includes a six level plus one level below grade parking garage for approximately 625 cars. The total project area is 714,721 GSF. Structural system for the residential tower is tunnel form concrete (Outinord). The parking garage is flat plate post tension concrete. The Marshall, Louisville, Kentucky A ten (10) story, 231 unit student housing project. The complex includes two parking floors beneath 8 stories of residential apartments and amenities. Embassy Suites Denver. Colorado An eighteen (18) story hotel with three levels of parking below grade. Total area of the building is 428,821 SF. Structural system is a blend of cast-in-place flat plate post tensioned concrete, conventional reinforced walls and tunnel form construction. The Callaway House, Austin, Texas Seventeen (17) story student housing tower with 521,500 SF including five levels of parking, 730 spaces. The structural system is post tension concrete construction.

Structural Consultants Associates • 12511 Emily Court • Sugar Land, Texas 77478 • 713.779.7252

scaengineers.com


Drew Rose, P.E. LEED® AP BD+C Professional Engineer Licensure

EDUCATION

Kansas Colorado Oklahoma Texas

Bachelor of Science, Architectural Engineering Kansas State University, May 2005

Professional Afliations IAEI IES NCEES USGBC

WORK EXPERIENCE Drew is an electrical engineer with over 16 years of experience in electrical design and engineering. His responsibilities include the complete design of power and lighting systems, power distribution, equipment sizing from main service entrance switchboards to branch panel boards, site electrical, branch power circuiting, and mechanical equipment connections. Drew also has experience with special systems such as re alarm, AV systems, nurse call, and security systems. His project experience ranges from high-rise hospital bed towers to educational facilities. His design experience includes new construction, additions, and existing facility renovations. He has also designed various types of mission critical facilities such as data centers and other commercial projects.

PORTFOLIO • • • • • • • • • • • • • • • • •

Broadway Autopark – Wichita, KS C.S. Mott Children’s Hospital - Von Voigtlander Women’s Hospital – Ann Arbor, MI Comfort Inn – Garden City, KS Comfort Suites – Liberal, KS Dodge City Public Schools USD 443 - New Administration Building – Dodge City KS Dodge City Community College – Student Union – Dodge City, KS Epic Center – 4th Floor Renovation – Wichita, KS Great Bend Hospital – MRI & Central Sterile Addition – Great Bend, KS Goodland Schools USD 352 – New High School – Goodland, KS Hyatt Place at Wichita State University – Wichita, KS James Smalley & Co Seed Office Building – McPherson, KS Parkview Health - Parkview Regional Medical Center – Fort Wayne, IN Spaghetti Works Apartments – Wichita, KS Stevens County Courthouse – HVAC Renovation – Hugoton, KS Texas Health – Presbyterian Hospital – Flower Mound, TX Texas Health Presbyterian Hospital – Hamon Tower – Dallas, TX Wichita State University – Innovation Campus – Wichita, KS ° Partnership Building 4 - NetApp • Wichita State University – The Flats Apartments – Wichita, KS

349 S. Hydraulic z Wichita, KS 67211 Tel 316.264.3588 z Fax 316.264.3948 z www.iconengineers.net


Phil J. Voegeli, P.E. LEED® AP BD+C, CBCP, CxA, EMP Principal/Professional Engineer Licensure

EDUCATION

All 48 Contiguous States

Bachelor of Science, Electrical Engineering Wichita State University, December 1984

Professional Afliations ACG AEE IAEI KAFAA NCEES NFPA USBGC

WORK EXPERIENCE Phil is an electrical engineer with over 37 years of experience in electrical design and engineering. His responsibilities include design formulation, presentation, inspection and construction supervision, commissioning, and arc ash evaluations for new and existing structures. Phil has experience in electrical power, controls, audio-visual, communications, security, clock systems, re detection/alarm, emergency power, and lighting systems. Phil has designed electrical plans for high-prole projects such as military installations, aircraft hangars, and hospitals. His project experience includes electrical designs for a wide range of facilities, including schools, nancial institutions, industrial plants, and emergency generating stations.

PORTFOLIO • 125 N Main – Wichita, KS ° 1st Floor Reception & Restaurant ° 10th, 11th, and 14th Floor ° Oxford Senior Living • 430 Douglas Development – IMA Financial – Wichita, KS • Archer Hotel – Redmond, WA • Bitting Building Renovation – Exchange Place Apartments – Wichita, KS • Epic Center – Wichita, KS • Exchange Building Renovation – Exchange Place Apartments – Wichita, KS • Garvey Center – Wichita, KS • Exploration Place – Wichita, KS • Koch Industries - Building C – Wichita, KS • McConnell Air Force Base – Wichita, KS ° Airman’s Dorm • One Brittany Place – Wichita, KS • Sedgwick County Courthouse – Wichita, KS • Spirit Aerosystems Northeast Manufacturing – Wichita, KS • SWBT Toll Building – Wichita, KS • Ronald Reagan Building – Wichita, KS • The University of Kansas Health Systems – Kansas City, KS ° Bell Memorial Hospital ° Cambridge North Tower Commissioning ° Generator Addition ° Indian Creek Campus Commissioning • Two Brittany Place – Wichita, KS • Via Christi Hospital – St. Francis – Wichita, KS • Via Christi Hospital – St. Joseph – Wichita, KS • Waterwalk Building C – Wichita, KS • Wichita City Hall – Wichita, KS • Wichita State University – Innovation Campus – Wichita, KS ° Partnership Building 4 - NetApp

349 S. Hydraulic z Wichita, KS 67211 Tel 316.264.3588 z Fax 316.264.3948 z www.iconengineers.net


Dwayne D. Vaughn, P.E. LEED® AP BD+C, CxA Principal/Professional Engineer Licensure

EDUCATION

Kansas Alabama Arizona Arkansas California Colorado Florida Georgia Illinois Louisiana Michigan Mississippi Missouri Montana Nebraska New Hampshire North Carolina Ohio Oklahoma Pennsylvania South Carolina South Dakota Tennessee Texas Utah Virginia Washington West Virginia Wisconsin

Bachelor of Science, Architectural Engineering Kansas State University, December 1993

Professional Afliations ACG ASHE ASHRAE ASPE IGSHPA NCEES USGBC

WORK EXPERIENCE Dwayne is a mechanical engineer with over 28 years of experience in HVAC, re protection and plumbing engineering. His responsibilities include mechanical system cost estimating, heating and cooling load analysis, mechanical system energy analysis, life cycle cost analysis, equipment selection, piping and duct design and building mechanical condition surveys. Dwayne also provides scheduling, quality control, project coordination, and construction administration services encompassing all aspects of the design and construction process. His project experience includes mechanical system designs for health care facilities, schools, multi-story hotels, university buildings, retail shopping centers, churches, restaurants, banks, manufacturing plants, commercial ofce buildings, and detention facilities.

PORTFOLIO • 125 N. Market Building Renovation – Wichita, KS ° 1st Floor Reception & Restaurant ° 10th, 11th, and 14th Floor ° Oxford Senior Living • 430 Douglas Development – IMA Financial – Wichita, KS • Comanche Gaming Commission New Ofce Building – Devol, OK • Cranbrook Offices – Wichita, KS • Douglas Avenue Development • Epic Center Renovation – Wichita, KS ° Basement, 2nd, 4th, 8th, 21st, & 22nd Floor • Heartspring – Wichita, KS ° Cafeteria Remodel ° CIE Remodel and Expansion ° Pediatric Remodel and Expansion • Hyatt Place at Wichita State University – Wichita, KS • James Smalley & Co Seed Ofce Building – McPherson, KS • Koch Industries A/B Boiler Replacement – Wichita, KS • Manhattan Medical Center – Manhattan, KS • Northrock Ofce Building – Wichita, KS • Via Christi Hospital – St. Teresa Medical Ofce Building – Wichita, KS • Wichita State University – The Flats Apartments – Wichita, KS • Wichita State University Innovation Campus – Wichita, KS ° Partnership Building 1 - Airbus Engineering Center ° Partnership Building 2 - Two Story Office Building ° Partnership Building 3 - Three Story Office Building ° Partnership Building 4 - NetApp ° Partnership Building 7 - Deloitte Smart Factory 349 S. Hydraulic z Wichita, KS 67211 Tel 316.264.3588 z Fax 316.264.3948 z www.iconengineers.net


Sean Miller, P.E./C.E.M. LEED® AP, GBE, MBA Professional Engineer / Certified Energy Manager Licensure

EDUCATION

Kansas Colorado Minnesota Oklahoma Texas

Bachelor of Science, Mechanical Engineering Wichita State University, May 2002 Master of Business Administration Southwestern College, May 2004

WORK EXPERIENCE

Professional Afliations AEE ASHRAE NCEES

Sean is a mechanical/energy engineer with over 25 years of experience in HVAC, and plumbing engineering. His responsibilities include system design, energy analysis, energy auditing (ASHRAE levels 1,2,& 3), energy modeling, energy monitoring, hydraulic analysis, heating/cooling load calculations, project development, quality control, and equipment selection. His project experience includes office buildings, churches, schools, medical facilities, restaurants, industrial, hotels, higher education, commissioning, city, and governmental organizations.

PORTFOLIO • Ambassador Hotel Renovation – Wichita, KS • Boeing - Building 23L Chiller Remodel – Wichita, KS • Brush District RE-2J - New Middle/High School – Brush, CO • Dodge City Public Schools USD 443 - New Administration Building – Dodge City KS • Equity Bank Building – Wichita, KS • Hutchinson Community College - Energy Project • Koch Industries - Building C – Wichita, KS • Player Piano Building/McCormick Harvester Apartments – Wichita, KS • Quarterage Hotel – Kansas City, MO • Saline County - Authority Building – Salina, KS • Sierra Suites Hotel – Savannah, GA • Spirit Aerosystems – Wichita, KS ° 787 CFF Widebay & Infrastructure ° 787 South Hangar Remodel Spirit ° IPB4 Chiller Addition ° MPF Chiller Addition ° Northeast Manufacturing Facility • Tabor College - Residence Hall – Hillsboro, KS • Union Station Renovation – Wichita, KS • Wichita State University - Duerksen Fine Arts Center – Wichita, KS

349 S. Hydraulic z Wichita, KS 67211 Tel 316.264.3588 z Fax 316.264.3948 z www.iconengineers.net