PORTFOLIO S I R A G E
S A U D I
I B R E E K
THE ENCLOSED WORK IS FOR THE PURPOSE OF THE JOB APPLICATION ONLY AND SHOULD BE TREATED AS CONFIDENTIAL
CONTENTS
1
ROGERS STIRK HARBOUR + PARTNERS THE M ACALLAN DISTILLE RY BAY STRE E T TORONTO KE NTUCKY OW L DISTILLE RY M E LBOURNE M E TRO
2
UNIVERSITY OF BATH “THE BALKAN FORUM ” “SAVE THE SAVA” - ZAGRE B M ASTE RP LAN
3
JO COWEN ARCHITECTS ARM OURE R’S COURT KINGSTON GATE
ROGERS STIRK HARBOUR + PARTNERS THE MACALLAN DISTILLERY
ROGERS STIRK HARBOUR + PARTNERS THE MACALLAN DISTILLERY CLIENT Edrington Group WORKSTAGE Stage 5 (Construction) • • •
PERSONAL ROLE/RESPONSIBILITIES: Contributed to construction drawings related to the structure, roof anf fit-out information. Attended client and site meetings. Provided comments on consultant information.
1 - Entrance approach
PROJECT DESCRIPTION The new distillery for The Macallan is located alongside their existing facility within the extensive 390-acre estate of Easter Elchies House. In response to the environmental status of the proposed site an “A r e a o f G r e a t L a n d s c a p e Va l u e”, t h e d e s i g n i s a l a n d s c a p e r e s p o n s e . Dug into the naturally sloping contours of the site, the building has minimal visual impact on the landscape. The soft undulating rood speaks to the hills of the surrounding countryside yet the clearly man-made and engineered forms of the uniform peaks reflect the industrial production cells contained within.
3 - R o o f Ve n t D e t a i l
2 - Drone aerial photograph
5
4
4 - R o o f Ve n t
7
2
5 - The Cave Privee
6 - Ground Floor Plan
7 - The Cave Privee
ROGERS STIRK HARBOUR + PARTNERS 30 BAY STREET CLIENT Oxford Properties
24 30 Bay Street – Toronto
WORKSTAGE Competition
Tower Superstructure PERSONAL ROLE/RESPONSIBILITIES: • •
Contributed to developing the 3D model Assisted with the production of Section drawings It is intended that these corners will be hung for the purpose of the competition from the primary mega columns by a framework of diagonal steel structure on a three storey module. As these hangers will be working primarily in tension, their sizes will be minimised to optimise the steels performance and thereby reduce the tonnage for the building. As the floor loads will be transferred back to the primary columns on a 3 storey module, the sizes of the hangers can be kept relatively standardised throughout the height of the tower. These hangers will suspend a lightweight steel deck floor system on each corner of the tower, thereby allowing the south west corner in particular to float free of the heritage building below. Structurally there will be many ways of achieving this same design intent. These options will be interrogated and evaluated throughout the design evolution from a cost and buildability perspective.
PROJECT DESCRIPTION N a m e d f o r i t s p r o x i m i t y t o H a r b o u r, U n i o n S t a t i o n a n d B a y S t r e e t , t h e H U B w i l l b e o n e o f t h e t a l l e s t t o w e r s i n d o w n t o w n To r o n t o’ s v i b r a n t South Core neighbourhood, located close to the shores of Lake Ontario and the CBD. The scheme creates a contemporary dialogue with its historical context, allowing the heritage building breathing space to coexist with a large new office tower development and maintaining integrity within the overall urban configuration. 24
30 Bay Street – Toronto
Tower Superstructure
In effect this can be seen primarily as a concrete building with lightweight steel suspended corners, allowing traditional and established local construction techniques to be adopted in the majority of the towers‘ construction. This provides a clear interface between the two primary trades, with a simple delineation between the concrete and steel work.
Concrete core, mega columns and floor plates, with lightweight steel suspended corners
It is intended that these corners will be hung for the purpose of the competition from the primary mega columns by a framework of diagonal steel structure on a three storey module. As these hangers will be working primarily in tension, their sizes will be minimised to optimise the steels performance and thereby reduce the tonnage for the building. As the floor loads will be transferred back to the primary columns on a 3 storey module, the sizes of the hangers can be kept relatively standardised throughout the height of the tower. These hangers will suspend a lightweight steel deck floor system on each corner of the tower, thereby allowing the south west corner in particular to float free of the heritage building below. Structurally there will be many ways of achieving this same design intent. These options will be interrogated and evaluated throughout the design evolution from a cost and buildability perspective. In effect this can be seen primarily as a concrete building with lightweight steel suspended corners, allowing traditional and established local construction techniques to be adopted in the majority of the towers‘ construction. This provides a clear interface between the two primary trades, with a simple delineation between the concrete and steel work.
Concrete core, mega columns and floor plates, with lightweight steel suspended corners
Concept sketch of structural system
Rogers Stirk Harbour + Partners
128
Concept sketch of structural system
Rogers Stirk Harbour + Partners
To r o n t o s k y l i n e e l e v a t i o n
Rhino model tructural strategy development
Full height perspective view - Dusk
Section drawing
’
24 Kentucky Owl Park : 2018
ROGERS STIRK HARBOUR + PARTNERS
Site Response
KENTUCKY OWL DISTILLERY CLIENT SPI Group
Kentucky Owl Park : 2018
23
WORKSTAGE Competition •
PERSONAL ROLE/RESPONSIBILITIES: Contributed to the competition deliverables
PROJECT DESCRIPTION T h e Ke n t u c k y O w l P a r k i s a d e s i g n p r o p o s a l f o r a b o u r b o n d i s t i l l e r y l o c a t e d i n B a r d s t o w n , Ke n t u c k y, U S A . A s w i t h a l l w h i s k e y p r o d u c t i o n , the principles of honesty and integrity are paramount to the product’s branding, with the finest ingredients carefully sourced, crafted t o g e t h e r a n d m a t u r e d o v e r t i m e . To c e l e b r a t e t h e s e p r i n c i p l e s , t h e design intention was to devise a simple and clear production process, set within a simple skeletal structure. Inspiration was drawn from t h e g r e a t We s t e r n A m e r i c a n n o b l e b a r n s f r o n t i e r s p i r i t o f 1 8 7 9, t h e year of the whiskey’s founding.
?
?
Siting Opportunities
Sitting on the headland
Flexible Framework
The distillery building is centrally located but situated off of the headland and set low within the quarry walls to experience the quarry edges and as a remnant to the site’s industrial past. Strong and horizontal geometries tame the undulations of the quarry and yet create a framework which is flexible and robust enough as a concept to endure not only developments within the briefing, design and construction phases but also allows flexibility as an operational building in the future.
Sitting within quarry Concept Diagram
d
Maximising the plateau for minimum intervention and addressing primary and secondary site geometries
Response Diagram Rogers Stirk Harbour + Partners
Response diagram
Rogers Stirk Harbour + Partners
View 01. South Elevation across the lake at night.
Visitor centre west elevation at dusk
South elevation across lake at night
Aerial perspective at dusk
Detailed building cross-section
Visitor centre - upper level looking back towards reception
ROGERS STIRK HARBOUR + PARTNERS MELBOURNE METRO CLIENT C r o s s Ya r r a P a r t n e r s h i p / L e n d l e a s e WORKSTAGE Competition + Concept Design • • • •
PERSONAL ROLE/RESPONSIBILITIES: Developed Anzac Station from Competition to Concept Stage. Wo r k e d o n t h e f u l l s e t o f d e l i v e r a b l e s i n c l u d i n g P l a n s , S e c t i o n s , RCPs and 3D views. Fo c u s e d o n a b o v e - g r o u n d e l e m e n t s ( i n c l u d i n g t h e T i m b e r C a n o p y as well as secondary entrances). Assisted in coordination of consultant information.
PROJECT DESCRIPTION T h e M e t r o Tu n n e l P r o j e c t i n M e l b o u r n e i s b u i l d i n g t w i n n i n e - k i l o m e t r e tunnels and five new underground stations at North Melbourne (near Arden Street), Parkville, State Library at the northern end of S w a n s t o n S t r e e t , To w n H a l l a t t h e s o u t h e r n e n d o f S w a n s t o n S t r e e t and Anzac at St Kilda Road. Anzac station will feature three main entrances: one on the edge of the historical Shrine Reserve, one in Albert Road Reserve and one leading directly to the train-tram interchange in the middle of St Kilda Road to cater for the many thousands of passengers who will t r a n s f e r e v e r y d a y. Domain | Domain Proposals & Design Integrity
Domain | Domain Proposals & Design Integrity
17
17
1 - Site Strategy
2 - Perspective Long Section for Competition Stage Melbourne Metro Tunnel
3 - G e o m e t r i c a l d e f i n i t i o n o f C a n o p y u s i n g To r u s
4 - Perspective Short Section for Competition Stage
5 - Tr a m i n t e r c h a n g e e n t r a n c e a t d u s k
SB SETTING OUT CORRELATION (DATE)
12000
COLUMN TOP CONNECTION TO CANOPY
SETTING OUT CORRELATION
12000
3000
(SIGNATURE)
COLUMN TOP CONNECTION TO CANOPY
3000120003000
3000
(BLOCK LETTERS)
SETTING OUT CORRELATION
3000
3000
3000
3000120003000
3000
3000
3000
COLUMN TOP CONNECTION TO CANOPY
3000
3000
3000
3000
12000 3000
3000
3000
3000
3000
12000 3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
12000 3000120003000
3000
3000
3000
3000
3000
12000 3000
3000
3000
3000
3000
3000
3000
3000
3000120003000
12000 3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000120003000
3000
3000
3000
3000
12000 3000
3000
12000
3000
3000
12000 3000
3000
3000
3000
12000
3000
3000
157-3
157-4
157-3
157-4
3000
12000
12000
3000
3000
12000
12000
3000
3000
12000
12000
12000
3000
3000
12000
3000
12000
12000
12000
3000
3000
12000
12000
3000
3000
12000
3000
3000
12000 3000
3000
12000
3000
3000
3000
3000
3000
3000
3000
CX
3000
CX
11000
11000
11000 11000
3000
3000120003000
12000
12000
BRACING TOP CONNECTION TO CANOPY
3000
12000
12000
11000
3000
3000
12000
CY12000
12000
12000 3000
3000120003000
3000
12000
11000
BRACING TOP CONNECTION TO CANOPY
3000
12000
12000
12000
12000
SETTING OUT CORRELATION
12000
12000
12000
BRACING TOP CONNECTION TO CANOPY
Certified By:
12000
12000
BRACING TOP CONNECTION TO CANOPY
COLUMN TOP CONNECTION TO CANOPY
CY
SB
CX 2118
3882
3000
2118
3882
3000
27000 157-3
27000 157-4
3000
3882
2118
3000
3882
2118
R6 3000
3882
2118
11000
PORTAL GATE FRAMES
10000
27000 11000
10000
11000
157-3
12000
11000 27000
12000
11000
10000
157-4
11000
CANOPY COLUMN BASE PORTAL GATE FRAMES
R3
R4
CONCEPT SUBMISSION NOTES
Certified By:
CY3
R6
34.0 °
36.4 °
2700 800
3500 3500
90 .0 °
2700
1810
1810
800
800
800
39.1 °
2700
90 .0 °
35.4 °
3306
3500
2700
28.3°
15.2°
800
3000
1810
---
850 4000
850 4000
850 4000
850 4000
CENTRAL VOID CONCRETE PANELS
2000
86 .2 °
° .2 86
FFL 1.340 B1 - CONCOURSE LEVEL
Up Location East. North. ID#
1850
1900
1900
1725
1900
25
150
1850
° .0 90
FFL 1.340 B1 - CONCOURSE LEVEL
° .0 78
77 .6 °
3710
---
GF - RCP Canopy
PAID CONCOURSE
Up Location East. North. ID#
1
1
1 : 50
1 : 50
REFER TO PROJECT AND DESIGNER HAZARD MITIGATION REGISTER FOR FURTHER INFORMATION ON NUMBERS LISTED.
4
CONSTRUCTION RISKS
MAINT./CLEANING RISKS
DEMOL./ADAPTATION RISKS
IN ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE OF WORKS DETAILED ON THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS ASSUMED THAT ALL WORKS ON THIS DRAWING WILL BE CARRIED OUT BY A COMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN APPROPRIATE METHOD STATEMENT. SAFETY HEALTH AND ENVIRONMENTAL INFORMATION BOX
LINEWIDE NOTE
CONCEPT SUBMISSION NOTES
Given the evolving nature of the design process not all of the following technical requirements are fully understood or coordinated into the design to date. · MEP consultancy is not aligned with architectural team programme · The structural design is ongoing this is particularly a risk but not limited to trinocular stations · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to sizes and assembly details of all linings and components · Lighting consultancy is not aligned with architectural team programme. Design intent is described in the drawings · Acoustic testing and analysis has commenced but is incomplete at the time of writing. The brief will be based upon typical conditions and a range of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes · Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. · DDA / PRM requirements are ongoing and may well impact design beyond this point throughout all stations and may effect colour and finishes line wide
The designs of all stations have developed following contract close. A significant amount of work has be undertaken to understand the various technical requirements which the architectural system will be required to meet. Given the evolving nature of the design process not all of the following aspects are fully understood or coor-dinated into the design to date. These include MEP design, structural design, bomb blast requirements, lighting, acoustics, fire strategies, dda requirements, wind and rain analysis. These drawings are intended fot the purpose of architectural concept only and are subject to futher development. All drawings to be read in conjunction with the architectural concept design report.
Key Plan
REFER TO PROJECT AND DESIGNER HAZARD MITIGATION REGISTER FOR FURTHER INFORMATION ON NUMBERS LISTED.
CONSTRUCTION RISKS
MAINT./CLEANING RISKS
DEMOL./ADAPTATION RISKS
IN ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE OF WORKS DETAILED ON THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS ASSUMED THAT ALL WORKS ON THIS DRAWING WILL BE CARRIED OUT BY A COMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN APPROPRIATE METHOD STATEMENT. SAFETY HEALTH AND ENVIRONMENTAL INFORMATION BOX
LINEWIDE NOTE
CONCEPT SUBMISSION NOTES
Given the evolving nature of the design process not all of the following technical requirements are fully understood or coordinated into the design to date. · MEP consultancy is not aligned with architectural team programme · The structural design is ongoing this is particularly a risk but not limited to trinocular stations · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to sizes and assembly details of all linings and components · Lighting consultancy is not aligned with architectural team programme. Design intent is described in the drawings · AcousticNumber testing and analysis has commenced but is incomplete at the time of writing.Revision The brief will be based upon typical conditions and a range of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes Project Drawing · Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. · DDA / PRM requirements are ongoing and may well impact design beyond this point throughout all stations and may effect colour and finishes line wide
The designs of all stations have developed following contract close. A significant amount of work has be undertaken to understand the various technical requirements which the architectural system will be required to meet. Given the evolving nature of the design process not all of the following aspects are fully understood or coor-dinated into the design to date. These include MEP design, structural design, bomb blast requirements, lighting, acoustics, fire strategies, dda requirements, wind and rain analysis. These drawings are intended fot the purpose of architectural concept only and are subject to futher development. All drawings to be read in conjunction with the architectural concept design report.
Key Plan
REFER TO PROJECT AND DESIGNER HAZARD MITIGATION REGISTER FOR FURTHER INFORMATION ON NUMBERS LISTED.
CONSTRUCTION RISKS
MAINT./CLEANING RISKS
DEMOL./ADAPTATION RISKS
IN ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE OF WORKS DETAILED ON THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS ASSUMED THAT ALL WORKS ON THIS DRAWING WILL BE CARRIED OUT BY A COMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN APPROPRIATE METHOD STATEMENT. SAFETY HEALTH AND ENVIRONMENTAL INFORMATION BOX
CONCEPT DESIGN FOR INFORMATION ONLY TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A0023 Project Drawing Number
Vehicle barrier formed by inner concrete structural core clad with stone panels
ARCHITECTURAL Domain GROUND FLOOR RCP MAIN ENTRANCE
ARCHITECTURAL Down Location Datum East. Domain North. FLOOR RCP GROUND ID# MAIN ENTRANCE PAID CONCOURSE
103
1
1 : 50
South Portal Gate with incorporated coordianted services, main ones being: • Vertical Roller Shutter • RWPs • CCTV cameras • Digital screen • Occupant warning systems - Emergency lighting, audible alarms, directional signage and intercom systems. • PA system. • Station intercommunication system. • Lighting
° 45.0
30.0°
R6
13206
30.0°
45.0 °
Steel structural bracing elements. Final noding geometry in abeyance pending structural input from AAW
15.2°
5283
Canopy glulam structural beams and soffit pan bracing layer
28.3°
° 39.1
FFL 9.900 GROUND FLOOR LEVEL
CONCEPT DESIGN FOR INFORMATION ONLY
Canopy RWPs runs into portal gate frame
° 35.4
° 36.4
FFL 9.900 GROUND FLOOR LEVEL
° 34.0
Vehicle barrier formed by inner concrete structural core clad with stone panels
25.3°
GF - RCP Canopy
CY4
Central row of skylights
ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE Key Plan R4 R5 WORKS DETAILED THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS REFER TO ON PROJECT AND DESIGNER HAZARD MITIGATION REGISTER 12449 SUMED THAT WORKS ON THIS DRAWING WILL BELISTED. CARRIED OUT BY A FOR ALL FURTHER INFORMATION ON NUMBERS OMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN PROPRIATE METHOD ONSTRUCTION RISKS STATEMENT. MAINT./CLEANING RISKS DEMOL./ADAPTATION RISKS Transparent glass screen around the FETY HEALTH AND ENVIRONMENTAL INFORMATION BOX central void central void central void Canopy glulam structural columns. · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings 9a0.0 general risk to Final noding geometry in abeyance understood or coor-dinated into the design to date. ° ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE pending structural input from AAW sizes and assembly details of all linings and components Consultant OTES This drawing has been prepared by, or compiled from These include MEP design, structural design, bomb blast requirements, lighting, WORKS DETAILED ON1THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS NORTHwith MAIN architectural team programme. Design intent is described in the drawings Lighting consultancy is not aligned NORTH BRIDGE SOUTHprovided BRIDGE by, persons other than PTV. To the information ALL DRAWINGS ARE TO READ IN CONJUNCTION WITH GENERAL NOTES DRAWING.· SOUTH BRIDGE ENTRANCE NORTH BRIDGE acoustics, fire strategies, dda requirements, wind and rain analysis.maximum extent permissible by law, PTV takes no responsibility SUMED THAT ALL WORKS ON THIS DRAWING WILL BE CARRIED OUT BY A · Acoustic testing and analysis has commenced but is incomplete at the time of writing. The brief will be based upon typical conditions and a range of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes 1 : 150 / SETTING OUT, REFER TO MEP ENGINEER'S DOCUMENTATION. FOR BACK OF HOUSE EQUIPMENT Obscured glass screen around Obscured glass screen around glass screen around These drawings are intended fot the purpose of architectural concept onlymakes andno representations in relation to, the- Obscured for, and OMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN central void from the top of the central glulam void from the topcolumns. of the Canopy structural central void from the top of the Canopy glulam structural columns. · Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. vehicle barrier downwards completeness, accuracy or quality of any information contained vehicle barrier downwards REFER TO MEP ENGINEER'S DOCUMENTATION FOR LUMINARIE SCHEDULE. Final noding geometry in abeyance Finalare nodingsubject geometry in abeyance vehicle barrier downwards to futher development. PROPRIATE METHOD STATEMENT. pending structural input from AAW pending structural input from AAW in this drawing. Each user of this drawing releases PTV from all DDA / PRM requirements ongoing andDOCUMENTATION. may well impact design beyond this point throughout all stations and may effect colour and finishes line wide OVERHEAD LINE ELECTRIFICATION (OLE) SHOWN INDICATIVELY. FOR OLE DESIGN· AND SETTING OUT REFER TOare ENGINEER'S All drawings to be read in conjunction with the architectural conceptanddesign any loss,report. damage, cost, expense or liability in relation to the FETY HEALTH AND ENVIRONMENTAL INFORMATION BOX FOR SIGNAGE REFER TO WAYFINDING SCHEDULE AND DRAWINGS. 7290 use of, or any reliance on, this drawing or the information Key Plan LINEWIDE NOTE CONCEPT SUBMISSION NOTES contained in it. Glass and precast panel Glass and precast panel DOOR AND IRONMONGERY INFORMATION REFER TO DOORREGISTER SCHEDULE AND DETAILED DRAWINGS. Consultant Franchisee / Lessee TO PROJECT AND DESIGNER HAZARD MITIGATION OTESFOR REFER joints to be staggered This drawing has been prepared by, or compiled from joints to be staggered 6294 LEVELS AHD.ARE MMRA = AHD1+ 100M. The designs of all stations have developed following contract close.All Awritten significant dimensions take precedence over PTV. scaledTodimensions. information provided by, persons other than the FORTOFURTHER INFORMATION ON NUMBERS LISTED. ALL DRAWINGS TO HEIGHT READ INDATUM CONJUNCTION WITH GENERAL NOTES DRAWING.Given the evolving nature of the design process not all of the following technical requirements are fully understood or coordinated into the design to date. maximum extent permissible by law, PTV takes no responsibility PIPEWORK AND OUTLET LOCATIONS SHOWNOUT, INDICATIVELY. ROUTES NOT SHOWN FOR CLARITY. REFER TO SERVICES ENGINEER'S DOCUMENTATION. amount of work has be undertaken to understand the various technical 1 : 150 FOR BACK OF HOUSE EQUIPMENT / SETTING REFER TOFULL MEP HYDRAULICS ENGINEER'S DOCUMENTATION. This drawing is provided only for the information of the person for, and makes no representations in relation to, the MEP consultancy is not aligned with architectural team programme FALL RESTRAINT SYSTEM SHOWN INDICATIVELY. LOCATION OFSCHEDULE. FIXINGRISKS POINTS TO· BE AGREED WITH SUPPLIER THROUGH SHOP DRAWINGS. requirements which the architectural system will be required to meet. Given the or organisation to whom or PTV provides It may not becontained provided completeness, accuracy quality of anyit. information REFER TORISKS MEP ENGINEER'S DOCUMENTATION LUMINARIE ONSTRUCTION MAINT./CLEANING RISKS FOR DEMOL./ADAPTATION · REVIEW. The structural design isBLOCKWORK ongoing this isDETAILS particularly a risk TO but ARCHITECTURAL not limited to trinocular stations 415 750 to, or by, any other priorPTV written ALL BLOCKWORK PROPOSAL'S AND(OLE) DETAILS SUBJECT TO STRUCTURAL FOR TYPICAL REFER DETAILS. in this drawing. Each userperson of thiswithout drawingPTV's releases from all panels around theRev. Revised ByPrefabricated In Serv Date Description Designed Checked Approv. Prefabricated panels around the Extended structural island evolving nature of the design process not all ofInd. theRev. following aspects areused fully OVERHEAD LINE ELECTRIFICATION SHOWN INDICATIVELY. FOR OLEENGINEER'S DESIGN· AND SETTING OUT REFER ENGINEER'S DOCUMENTATION. Prefabricated panels around the central void. of the requirements ring beam, Bomb blast. There is a TO general assumption that architectural systems will need to conform withsupported similar utilisedcentral onvoid.Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to consent. and any loss, damage, cost, expense or liability in relation to the central void. Currently GRC and precast RC Currently GRC and precast RC SECONDARY SUPPORT SHOWN INDICATIVELY. TO BE DETAILED BY SUBCONTRACTOR. supports stair 152.4 and understood or coor-dinated into the design to date. Currentlyon, GRCthis anddrawing precast RC or the information FOR SIGNAGE REFER TO WAYFINDING SCHEDULE AND DRAWINGS. ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE being studied use of, or any reliance being studied RC base to canopy glulam structural escalator 153.9 sizes and assembly details of all linings and components SIGNALLING being studied ? LINEWIDE NOTE CONCEPT SUBMISSION NOTES columns. Key Plan COOLING ROOM EQUIPMENT ROOM containedlighting, in it. These include MEP design, structural design, bomb blast requirements, FOR DETAILED DOOR ANDON IRONMONGERY INFORMATION REFER TO DOOR DETAILED DRAWINGS. WORKS THIS DRAWING TAKETO NOTE OF THEAND ABOVE. ITSCHEDULE IS HAZARDAND Final noding geometry in abeyance ? Franchisee / Lessee REFER PROJECT DESIGNER MITIGATION REGISTER h850x d750mm chamfer · Lighting consultancy is not aligned with architectural team programme. Design intent is described in the drawings 691-5 501 RC base to canopy glulam pending structural input from AAW around the central void acoustics, fire strategies, dda requirements, and rainhave analysis. LEVELS AHD. MMRAONHEIGHT DATUM = WILL AHD +BE 100M. structural columns. SUMED THATTO ALL WORKS THIS DRAWING CARRIED OUT A The designs ofwind all stations developed followingtakecontract close. A significant All written dimensions precedence over scaled dimensions. FOR FURTHER INFORMATION ONBYNUMBERS LISTED. · Acoustic testing and analysis has commenced butofisthe incomplete at the time of of writing. The brieftechnical will be based upon typical conditions and aorrange of parameters. However analysis of unique spaces may alter any acoustic outcomes Final noding geometry in abeyance to detailed STAFF OPEN Staff open area Given the evolving nature design process not all the following requirements are fully understood coordinated into the design date. RC These base to canopydrawings glulam structural are intended fot the purpose of architectural concept only and Protective stair rail pending structural input from AAW AREA glazed screen PIPEWORK AND OUTLET LOCATIONS SHOWN INDICATIVELY. NOTthe SHOWN REFER TO SERVICES ENGINEER'S DOCUMENTATION. OMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO ANFULL HYDRAULICS ROUTES amount of work has be undertaken to understand the various technical columns. · Fire: detailedFOR fireCLARITY. strategy is under development and bespoke components will need to undergo specific testing. This drawing is provided only for the information of the person · MEP consultancy is not aligned with architectural team programme Finalare nodingsubject geometry in abeyance to futher development. FALL RESTRAINT SYSTEM SHOWN INDICATIVELY. LOCATION OF FIXING TO· BE AGREED WITH SUPPLIER THROUGH SHOP DRAWINGS. PROPRIATE METHOD STATEMENT. pending structural input from AAW requirements which the architecturalorsystem willto whom be required to it.meet. Given the organisation PTV provides It may not be provided DDA / PRM requirements and may well impact design this point throughout all stations and maystations effect colour and finishes line wide CONSTRUCTION RISKS MAINT./CLEANING RISKSPOINTS DEMOL./ADAPTATION RISKS · are ongoing The structural design is ongoing thisbeyond is particularly a risk but not limited to trinocular All drawings to be read inDesigned conjunction with theInd. architectural concept to,design ornot used person without PTV's prior BLOCKWORK PROPOSAL'S AND DETAILS SUBJECT Revised By In Serv Rev. Date Description Checked Rev.design Approv. FETYALL HEALTH AND ENVIRONMENTAL INFORMATION BOX TO STRUCTURAL ENGINEER'S REVIEW. FOR TYPICAL BLOCKWORK DETAILS REFER TO ARCHITECTURAL DETAILS. evolving nature of the process allby,report. ofanytheotherfollowing aspects arewritten fully · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to SECONDARY SUPPORT SHOWN INDICATIVELY. TO BE DETAILED BY SUBCONTRACTOR. understood or coor-dinated into the consent. design to date. IN ADDITION TO THE HAZARDS/RISKS NORMALLY ASSOCIATED WITH THE TYPE sizes and assembly details of all linings and components Consultant OTES Thisdesign, drawing has been prepared by, or compiled fromlighting, These include MEP design, structural bomb blast requirements, OF WORKS DETAILED ON THIS DRAWING TAKE NOTE OF THE ABOVE. IT IS · Lighting consultancy is not aligned with architectural team programme. Design intent is described in the drawings information provided by, persons other than PTV. To the ALL DRAWINGS ARE TO READ IN CONJUNCTION WITH GENERAL NOTES DRAWING. Final roof finishes in abeyance pending further studies. Final roof finishes in abeyance pending further studies. acoustics, fire strategies, dda requirements, wind and rain analysis. ASSUMED THAT ALL WORKS ON THIS DRAWING WILL BE CARRIED OUT BY A The current systems being considered are copper/zinc The current systems being considered are copper/zinc maximum extent permissible by law, PTV takes no responsibility · Acoustic testing and analysis has commenced but is incomplete at the time of writing. The brief will be based upon typical conditions and a range of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes Main EntranceDOCUMENTATION. - Section CX - Callout 1 standing seam and fully welded stainless steel. standing seam and fully welded stainless steel. FOR BACK OF HOUSE EQUIPMENT / SETTING OUT, REFER TO MEP ENGINEER'S These drawings are intended fot the purpose of architectural concept only and for, and makes no representations in relation to, the Main Entrance Section CX Callout 3 Final canopy noding geometry and coordination of bracing Final canopy noding geometry and coordination of bracing COMPETENT CONTRACTOR WORKING WHERE APPROPRIATE, TO AN Main Entrance - Section CX - Callout 2 · Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. ans lifts in abeyance pending structural input from AAW. REFER TO MEP ENGINEER'S DOCUMENTATION FOR LUMINARIE SCHEDULE. are subject to futher development. completeness, accuracy or quality of any information contained ans lifts in abeyance pending structural input from AAW. APPROPRIATE METHOD STATEMENT. in this drawing. Each user of this drawing releases PTV from all DDA / PRMDOCUMENTATION. requirements are ongoing and may well impact design beyond this point throughout all stations and may effect colour and finishes line wide OVERHEAD LINE ELECTRIFICATION (OLE) SHOWN INDICATIVELY. FOR OLE DESIGN AND SETTING OUT REFER ·TO ENGINEER'S All drawings to be read in conjunction with the architectural concept design report. CONCEPT DESIGN CONCEPT DESIGN and any loss, damage, cost, expense or liability in relation to the SAFETY HEALTH AND ENVIRONMENTAL INFORMATION BOX FOR INFORMATION ONLY FOR INFORMATION ONLY FOR SIGNAGE REFER TO WAYFINDING SCHEDULE AND DRAWINGS. use of, or any reliance on, this drawing or the information contained in it. FOR DOOR AND IRONMONGERY INFORMATION REFER TO DOOR SCHEDULE AND DETAILED DRAWINGS. Consultant Franchisee / Lessee NOTES This drawing has been prepared by, or compiled from LEVELS TO AHD. MMRA DATUM = AHD All written dimensions take precedence over information scaled dimensions. providedTAS-RSH-DOM-ZWD-DRG-ARC-DMA-A1051 by, persons other than PTV. To the TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A1050 1. HEIGHT ALL DRAWINGS ARE+ 100M. TO READ IN CONJUNCTION WITH GENERAL NOTES DRAWING. North Portal Gate with incorporated coordianted services, main ones being: • Vertical Roller Shutter • RWPs • CCTV cameras • Digital screen • Occupant warning systems - Emergency lighting, audible alarms, directional signage and intercom systems. • PA system. • Station intercommunication system. • Lighting
2118
10
R6
Key Plan R5
3882
10000
R5
The designs of all stations have developed following contract close. A significant amount of work has be undertaken to understand the various technical requirements which the architectural system will be required to meet. Given the evolving nature of the design process not all of the following aspects are fully Canopy glulam structural beams and soffit pan bracing layer understood or coor-dinated into the design to date. CONCEPT R3SUBMISSION These include MEP design,NOTES structural design, bomb blast requirements, lighting, Steel structural bracing elements. Finalacoustics, noding geometry in abeyance fireofstrategies, wind andcontract rain analysis. Thestructural designs all stationsdda haverequirements, developed following close. A significant pending input from AAW These drawings are be intended fot thetopurpose of architectural only and amount of work has undertaken understand the various90.0concept technical ° are subject to futher development. requirements which the architectural system will be required to meet. Given 12070 the All drawings to be readdesign in conjunction report. evolving nature of the process with not alltheofarchitectural the followingconcept aspectsdesign are fully
3000
6 - Timber Roof Canopy RCP
103
Down Location East. North. ID#
Datum
Drawn By SOUTH MAIN ENTRANCE
Revisio
5301
R2
Given the evolving nature of the design process not all of the following technical requirements are fully understood or coordinated into the design to date. · MEP consultancy is not aligned with architectural team programme · The structural design is ongoing this is particularly a risk but not limited to trinocular stations Canopy glulam structural beams and · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to soffit pan bracing layer sizesNOTE and assembly details of all linings and components LINEWIDE R1 R2 ° Steel structural bracing elements. 45.0 is not aligned with architectural team programme. Design intent is described in the drawings · Lighting consultancy Final noding geometry in abeyance 13211 pending structural input from AAW · Acoustic analysis hasprocess commenced is incomplete at the time of writing. The briefunderstood will be based upon typical into conditions and to a range Given the evolvingtesting natureand of the design not all but of the following technical requirements are fully or coordinated the design date. of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes ·· Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. 12449 MEP consultancy is not aligned with architectural team programme 12070 DDAstructural / PRM requirements are ongoing may wella risk impact beyond this pointstations throughout all stations and may effectTransparent colourglassand finishes line wide ·· The design is ongoing this is and particularly but design not limited to trinocular screen around the Transparent glass screen around the Canopy RWPs runs into portal gate frame
R4
R6
3000
Central row of skylights
Final roof finishes in abeyance pending further studies. The currently systems being considered are copper/zinc standing seam and fully welded stainless steel
6
11000
Central row of skylights
10000
R5 27000
12000 CY
R3
11000
3306
(SIGNATURE)
R1
LINEWIDE NOTE
CY2 CY2
(BLOCK LETTERS)
(BLOCK LETTERS)
Certified By:
R2 R2
R1
R5
27000
R4
11
11000
(DATE)
(DATE)
CY1
(SIGNATURE)
GF - RCP Canopy
REFER TO PROJECT AND DESIGNER HAZARD MITIGATION REGISTER 1 FOR FURTHER INFORMATION ON NUMBERS LISTED. 1 : 150 ONSTRUCTION RISKS MAINT./CLEANING RISKS DEMOL./ADAPTATION RISKS
12000
R3
27000
10000
CANOPY COLUMN BASE GF - RCP Canopy 1 : 150
11000
R2
R4
25.3°
300010000
R3
27000
(DATE)
R2
(SIGNATURE)
3882 R1
2118
CANOPY COLUMN BASE PORTAL GATE FRAMES
1
3000 R1
3882
(BLOCK LETTERS)
2118
PORTAL GATE FRAMES
10000
Certified By:
CANOPY COLUMN BASE
Project Drawing Number
9.900 FFL GROUND FLOOR LEVEL
Designed By
Author
Designer
Checked By
Ind. Review
Checker TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A0023 File Name 7390 Approved Drawn By Sheet No. Approver
Approval Date Designed By
CONCEPT Author DESIGN Designer Drawing Number Checked By ONLY Ind. Review FOR INFORMATION
In Serv Scale File Name 1 : 150
Sheet Size
A1
Revisio
Revisio
Checker
Approved
Approval Date
Drawn By
Designed By
CONCEPT DESIGN Revisio Drawing Number Revisio In Serv FOR INFORMATION O TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A0023 Approver
Sheet No. Project Drawing Number Scale
1.340 FFL B1 - CONCOURSE LEVEL
Sheet Size
1 : 150
A1
ARCHITECTURAL Author Designer 7 Domain - L o n g S e c t i o n M a i n C a nProject o pDrawing y Number E nChecked t r aBy n c e Ind. Review GROUND FLOOR RCP MAIN ENTRANCE
LINEWIDE NOTE
CONCEPT SUBMISSION NOTES
Given the evolving nature of the design process not all of the following technical requirements are fully understood or coordinated into the design to date. · MEP consultancy is not aligned with architectural team programme · The structural design is ongoing this is particularly a risk but not limited to trinocular stations · Bomb blast. There is a general assumption that architectural systems will need to conform with similar requirements utilised on Crossrail in the UK. Metro projects bomb blast requirements need to be instructed to the team. This brings a general risk to sizes and assembly details of all linings and components · Lighting consultancy is not aligned with architectural team programme. Design intent is described in the drawings · Acoustic testing analysis has commenced but is incomplete at the time of writing. The brief will beRevision based upon typical conditions and a range of parameters. However detailed analysis of unique spaces may alter any acoustic outcomes Project and Drawing Number · Fire: the detailed fire strategy is under development and bespoke components will need to undergo specific testing. · DDA / PRM requirements are ongoing and may well impact design beyond this point throughout all stations and may effect colour and finishes line wide
The designs of all stations have developed following contract close. A significant amount of work has be undertaken to understand the various technical requirements which the architectural system will be required to meet. Given the evolving nature of the design process not all of the following aspects are fully understood or coor-dinated into the design to date. These include MEP design, structural design, bomb blast requirements, lighting, acoustics, fire strategies, dda requirements, wind and rain analysis. These drawings are intended fot the purpose of architectural concept only and are subject to futher development. All drawings to be read in conjunction with the architectural concept design report.
Key Plan
Final roof finishes in abeyance pending further studies. The current systems being considered are copper/zinc standing seam and fully welded stainless steel. Final canopy noding geometry and coordination of bracing ans lifts in abeyance pending structural input from AAW.
File Name
Sheet No. ARCHITECTURAL
Checker TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A0023
CONCEPT DESIGN FOR INFORMATION ONLY Project Drawing Number
TAS-RSH-DOM-ZWD-DRG-ARC-DMA-A1052
Approved
Revision
Approver
Approval Date Drawn By
8 - Passageway RCP
9 - Passageway Plan
10 - Passgeway Perspective View
11 - Concourse Level View
UNIVERSITY OF BATH SAVING THE SAVA
UNIVERSITY OF BATH 1970
SAVING THE SAVA PROJECT DESCRIPTION Threatened by dredging, planned hydropower dams, and increasing nutrient pollution, the masterplan offers a roadmap to save the Sava, while preparing the capital for the challenges of the coming century. The tool kit developed for the masterplan focuses on three key issues: strengthening the city’s green and blue infrastructure, encouraging the use of public and soft transport, and enabling its fossil fuel phase-out with a holistic renewable resource strategy. These principles are integrated into a pedestrian boulevard bridging the void between the historic centre of Zagreb and the modernist satellite town of Novi Zagreb. Along its way, the masterplan proposes the regeneration of two disregarded brownfields, transforming the central railway site as a gateway to the capital and rehabilitating the Sava’s river realm as the city’s functional green lungs.
2020
205 0
Re-wilding the River Sava
EXIST ING C ONDI T I ON
P R O P O S E D C O N D ITIO N
U N D E R PA SS P R O P O SE D C O N D IT IO N
LOCALE P ROP OS ED CONDIT ION
Masterplan Physical Model
Condition resolution
UNIVERSITY OF BATH THE BALKAN FORUM
UNIVERSITY OF BATH THE BALKAN FORUM PROJECT DESCRIPTION Fo l l o w i n g t h e r i g o r o u s m a s t e r p l a n n i n g p r o j e c t o f s e m e s t e r 1 , B a t h students were asked to each select a site of interest within their masterplans to develop a design proposal addressing an issue particular to the city at question. In order to stretch myself as a d e s i g n e r, I r e f r a i n e d f r o m d e s i g n i n g a “ p r o c e s s b u i l d i n g ”, a s i t i s a typology I have experienced in the past, both at university and in practice. My aim was to tackle a social issue, in this case human d i s p l a c e m e n t a n d Z a g r e b’ s u r g e n t i s s u e o f s o c i a l l y i n t e g r a t i n g refugees in Zagreb. O p p o s i t e t h e Z a g r e b Tr a i n S t a t i o n , t h e s i t e s i t s a t t h e f r o n t i e r b e t w e e n t h e 1 9 t h C e n t u r y a n d P o s t - w a r l a y e r s o f t h e c i t y. Fo l l o w i n g the overarching philosophy of the scheme, the Janus Condition, the project will aim to acknowledge and build upon the heritage within which it exists, with a series of contemporary architectural interventions that respond appropriately and sustainably to social, historical and cultural contexts. Integrating the synergy between the University of Zagreb students and the refugees in a shared building, a l o n g w i t h t h e c e l e b r a t i o n o f Z a g r e b’ s r i c h h i s t o r i c a l h e r i t a g e , t h i s b u i l d i n g a i m s t o b e a b e a c o n o f s o c i a l c o e x i s t e n c e , t h e B a l k a n Fo r u m .
SITE
“A building looking to address the urgent issue of socially integrating refugees in Zagreb, manifested as a cultural beacon within the Balkans.”
The problem
Physical model of focus site
“The world is in the grip of one of the greatest refugee crisis ever...” UK Refugee Council, February 2019
0
10
20
30
40
50
60
70
80
90
100
Unit: million
I N T E R N A L LY D I S P L AC E D
REFUGEES
ASYLUM SEEKERS
Rail as a physical barrier
Eastern entrance approach
Eastern entrance approach - Dusk
8m
2
3
4
5
16m
16m
8m
6
1 . C1 o n c e r t i n a f o l d i n g p o l y c a r b o n a t e / m a r b l e s h e e t s c r e e n 2. Engineered timber cassettes with internal cross bracing and treated croatian oak 3. Timber framed superstructure 4. Hollow core termodeck floors 5. Cantilevering concrete transfer structure 6. Non-processed limestone “ruin” walls
Exploded Axonometric - Main Building
1
5. Cantilevering concrete transfer structure
Structural Diagram - Main Building
Structural Diagram - Timber cloyster
Z A G R E B T R A I N S TAT I O N
RAIL MUSEUM EXHIBIT
RAIL TUNNEL
OCULUS LANDFORM OPPORTUNITY
H e r i t a g e M u s e u m - V i e w t o Z a g r e b Tr a i n S t a t i o n
JO COWEN ARCHITECTS ARMOURER’S COURT CLIENT Berkeley Homes WORKSTAGE Planning (Incl. Concept Design) • • •
PERSONAL ROLE/RESPONSIBILITIES: Managed the development of the Revit Model Orchestrated set of devlierables for Planning Co-ordinated consultant information for integration with latest design proposal
PRO JECT DESCRIPTION The client for this project is Berkeley Homes. On this scheme Berkeley H o m e s a r e w o r k i n g w i t h Tr a n s p o r t f o r L o n d o n g i v e n t h e s i t e o w n e d by Berkeley Homes surrounds an existing Crossrail station box owned by TfL. This project is one of many projects that Berkeley Homes are working on as part of a wider Royal Arsenal regeneration project. The homes are split into 4 buildings of varying heights, brought together by a two storey podium activating the street frontages. The scheme was submitted to the client for Planning on the 12th November 2020. The scheme proposal delivers over 500 mixed tenure homes, arranged to conceal the existing “East Box” Crossrail station ventilation and escape building at the centre of the site, utilising the existing structure to transform into well landscaped amenity gardens.
Armourer’s Court - North Entrance London city airport outer London city airport outer London city airport outer London city airport outer transitional surface lower transitional limit surface lower transitional limit surface lower limittransitional surface lower limit
Jo Cowen Architects Jo Cowen takeArchitects no Jo responsibility takeArchitects nofor responsibility anyJo information take Cowen nofor responsibility Architects any supplied information take for any no supplied responsibility information Jo Cowen supplied forArchitects anyJo information Cowen takeArchitects no supplied responsi ta transitional surface lower transitional limitCowen surface lower limit by third partiesby asthird the accuracy partiesby asof third the which accuracy parties cannot asofthe be which byguaranteed. accuracy third cannot parties ofbe which as guaranteed. thecannot accuracy be guaranteed. of which by third cannot parties be by as guaranteed. third the accuracy parties asofthe whia
89815
89815 89815 89815 Do not scale from Do not thisscale drawing. from DoAll not this dimensions scale drawing. from All should this Do dimensions drawing. not be scale checked All should from dimensions onthis be checked drawing. should on Allbe Do dimensions checked not scale on should from Do not this be scale checked drawing. fromon All this dim d site. Any omissions site. Any or discrepancies omissions site. Any or should discrepancies omissions be reported or site. should discrepancies Any in omissions writing be reported to should orindiscrepancies writing be reported to site. inshould writing Any omissions betoreported site. Any orindiscrepancies omissions writing to or sd Jo Cowen Architects. Jo Cowen Architects. Jo Cowen Architects.Jo Cowen Architects. Jo Cowen Architects. Jo Cowen Architects.
89815
89815
London city airport outer London city airport outer
This work is copyright This work and is cannot copyright This work be and reproduced, is cannot copyright be This copied, and reproduced, work cannot orismodified copyright be copied, reproduced, and or modified cannot copied, be This reproduced, orwork modified is copyright This copied, work and orismodified cannot copyright be ar in any form or by in any any form means; or by in graphic any any form means; electronic or by graphic any orinmechanical, means; any electronic form graphic ororbymechanical, any electronic means; orgraphic mechanical, in any electronic form ororby inmechanical, any any form means; or by graphic any m including photocopying includingwithout photocopying including permission without photocopying in writing. permission including without inphotocopying writing. permission inwithout writing.permission includinginphotocopying writing. includingwithout photocopying permis
© Jo Cowen Architects © Jo Cowen - 2019 Architects ©- Jo AllCowen Rights - 2019 Architects Reserved - All © Rights Jo - 2019 Cowen Reserved - All Architects Rights Reserved - 2019 - All © Rights Jo Cowen Reserved Architects © Jo Cowen - 2019 Architects - All Rig
General Notes General Notes General Notes
Top of Parapet +74.625 AODTop of Parapet +74.625 AODTop of Parapet +74.625 AOD
+64.900 AOD
Top of Parapet +55.950 AODTop of Parapet +55.950 AODTop of Parapet +55.950 AOD
Top of Parapet +55.950 AOD
L15
L15
L15
L15
L15
L15
54.125
54.125
54.125
54.125
54.125
54.125
L14
L14
L14
L14
L14
L14
51.125
51.125
51.125
51.125
51.125
51.125
L13
L13
L13
L13
L13
L13
48.125
48.125
48.125
48.125
48.125
48.125
L12
L12
L12
L12
L12
L12
45.125
45.125
45.125
45.125
45.125
45.125
L11
L11
L11
L11
L11
L11
42.125
42.125
42.125
42.125
42.125
42.125
Top of Parapet +43.225 AODTop of Parapet +43.225 AODTop of Parapet +43.225 AOD
Top of Parapet +43.225 AOD
Top of Parapet +55.950 AODTop of Parapet +55.950 AOD
+64.900 AOD
Top of Parapet +74.625 AODTop of Parapet +74.625 AOD
Top of Parapet +74.625 AOD
2
L21_B2
L21_B2
L21_B2
L21_B2
L21_B2
73.125
73.125
73.125
73.125
73.125
73.125
L20_B2
L20_B2
L20_B2
L20_B2
L20_B2
L20_B2
69.800
69.800
69.800
69.800
L19_B2
L19_B2
L19_B2
L19_B2
66.800
66.800
66.800
66.800
+64.900 AOD
+64.900 AOD
+64.900 AOD
69.800
L19_B2
3
2
L21_B2
General Notes
3
2
General Notes General Notes
2
3
3
2
2
69.800
1
L19_B2
66.800
66.800
1
4
1
4
41
4
1
+64.900 AOD
L18_B2
L18_B2
L18_B2
L18_B2
L18_B2
L18_B2
63.800
63.800
63.800
63.800
63.800
63.800
L17_B2
L17_B2
L17_B2
L17_B2
L17_B2
L17_B2
60.575
60.575
60.575
60.575
60.575
60.575
L16_B2
L16_B2
L16_B2
L16_B2
L16_B2
L16_B2
57.350
57.350
57.350
57.350
57.350
57.350
L15_B2
L15_B2
L15_B2
L15_B2
L15_B2
L15_B2
54.350
54.350
54.350
54.350
54.350
54.350
L14
L14
L14
L14
L14
L14
51.125
51.125
51.125
51.125
51.125
51.125
L13
L13
L13
L13
L13
L13
48.125
48.125
48.125
48.125
48.125
48.125
L12
L12
L12
L12
L12
L12
45.125
45.125
45.125
45.125
45.125
45.125
N
N
N
N
Top of Parapet +43.225 AODTop of Parapet +43.225 AOD
L10
L10
L10
L10
L10
L10
39.125
39.125
39.125
39.125
39.125
39.125
L09
L09
L09
L09
L09
L09
36.125
36.125
36.125
36.125
36.125
36.125
L08
L08
L08
L08
L08
L08
33.125
33.125
33.125
33.125
33.125
33.125
L07
L07
L07
L07
L07
L07
30.125
30.125
30.125
30.125
30.125
30.125
L06
L06
L06
L06
L06
L06
27.125
27.125
27.125
27.125
27.125
27.125
L05
L05
L05
L05
L05
L05
24.125
24.125
24.125
24.125
24.125
24.125
L04
L04
L04
L04
L04
L04
21.125
21.125
21.125
21.125
21.125
21.125
L11
L11
L11
L11
L11
L11
42.125
42.125
42.125
42.125
42.125
42.125
L10
L10
L10
L10
L10
L10
39.125
39.125
39.125
39.125
39.125
39.125
L09
L09
L09
L09
L09
L09
36.125
36.125
36.125
36.125
36.125
36.125
L08
L08
L08
L08
L08
L08
33.125
33.125
33.125
33.125
33.125
33.125
L07
L07
L07
L07
L07
L07
30.125
30.125
30.125
30.125
30.125
30.125
L06
L06
L06
L06
L06
L06
27.125
27.125
27.125
27.125
27.125
27.125
L05
L05
L05
L05
L05
L05
24.125
24.125
24.125
24.125
24.125
24.125
L04
L04
L04
L04
L04
L04
21.125
21.125
21.125
21.125
21.125
21.125
APPLICATIONAPPLICATION EXTENT APPLICATION EXTENT EXTENT APPLICATION EXTENT L03
L03
L03
L03
L03
L03
18.125
18.125
18.125
18.125
18.125
18.125
L02
L02
L02
L02
L02
L02
15.125
15.125
15.125
15.125
15.125
15.125
NA
SE
AR
East Box Roof Level East SSL Box Roof Level East SSL Box Roof Level SSL
East Box Roof Level SSL
East Box Roof Level East SSL Box Roof Level SSL
13.510
13.510
13.510
13.510
13.510
13.510
L01_West L01_North
L01_West L01_North
L01_West L01_North
L01_West L01_North
L01_West L01_North
L01_West L01_North
11.405
11.405
11.405
11.405
11.405
11.405
G00_South
G00_South
G00_South
G00_South
G00_South
G00_South
8.290
8.290
8.290
8.290
8.290
8.290
G00
G00
G00
G00
G00
G00
6.700
6.700
6.700
6.700
6.700
6.700
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
3.410 3.400
3.410 3.400
3.410 3.400
3.410 3.400
3.410 3.400
3.410 3.400
PLUMSTEAD PLUMSTEAD ROADPLUMSTEAD ROAD PLUMSTEAD ROAD ROAD BUILDING PLUMSTEAD BUILDING 1 PLUMSTEAD BUILDING ROAD 1 ROAD 1 BUILDING 1
+15.125 AOD
+15.125 AOD
+15.125 AOD
+15.125 AOD
+15.125 AOD
+15.125 AOD
L03
L03
L03
L03
L03
L03
18.125
18.125
18.125
18.125
18.125
18.125
L02
L02
L02
L02
L02
L02
15.125
15.125
East Box Roof Level East SSL Box Roof Level East SSL Box Roof Level SSL
15.125
East Box Roof Level SSL
13.510
13.510
13.510
L01_North L01_West
L01_North L01_West
L01_North L01_West
11.405
11.405
11.405
11.405
G00 G00_North
BUILDINGBUILDING 1 1
BUILDINGBUILDING 2 BUILDING 2 2 BUILDING 2
15.125
13.510 L01_North L01_West
G00 G00_North
G00 G00_North
G00_North G00
6.700
6.700
6.700
6.700
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
Max. Excavation East Box SSL
3.410 3.400
3.410 3.400
3.410 3.400
3.410 3.400
BUILDINGBUILDING 2 2
15.125
APPLICATIONAPPLICA EXTENT
15.125
East Box Roof Level East SSL Box Roof Level SSL 13.510
P04 P03 P02 P01
Revision
11/12/2020 Planning P04 11.405 23/10/2020 P03 Information 23/10/2020 Information P03 23/10/2020 P02 For Approval 23/10/2020 For Approval P02 12/10/2020 P01 For Approval 12/10/2020 For Approval P01
11.405 23/10/2020 P03 23/10/2020 P02 12/10/2020 P01
Revision Date
G00 G00_North
Scale 1:200@A1
0m
13.510
L01_North L01_West L01_North L01_West 11/12/2020 P04 11/12/2020 P04 Planning
Revision Date Description
G00 G00_North
6.700 Scale 1:200@A1
Revision Description Date Description Date
6.700 Scale 1:200@A1
0mSSL Max. Excavation East Box
0mSSL 10m Max. Excavation East Box
3.410 3.400
3.410 3.400
Planning 11/12/2020 Information 23/10/2020 For Approval 23/10/2020 For Approval 12/10/2020
Planning P04 Information P03 For Approval P02 For Approval P01
Revision Description
Scale 1:200@A1
10m0m
10m 20m
Scale 1:200@A1
20m 10m0m
20m
11/12/2020 P04 23/10/2020 P03 23/10/2020 P02 12/10/2020 P01
11/12/20 Plannin 23/10/20 Informa 23/10/20 For App 12/10/20 For App
Revision Date
Date Descrip
Scale 1:200@A1
0m
20m 10m
AY LW
Purpose of Drawing Purpose of Drawing Purpose of Drawing Purpose of Drawing
Purpose of Drawing Purpose of Drawing
PLANNING PLANNING PLANNING
PLANNING
PLANNING PLANNING
Project
Project
Project
Project
Project
Project
ARMOURER'S ARMOURER'S COURT ARMOURER'S COURT ARMOURER'S COURT COURT ARMOURER'S ARMOURER'S COURT C Drawing Title Drawing Title Drawing Title
M
U PL
AD
E ST
Drawing Title Drawing Title
GENERALGENERAL ARRANGEMENT GENERAL ARRANGEMENT SECTION ARRANGEMENT GENERAL SECTION DD ARRANGEMENT SECTION DD GENERAL DD SECTION GENERAL ARRANGEMEN DD ARR
D OA
R
P r o x i m i t y t o e x i s t i n g C r o s s r a i l S t a t i o n Ve n t B o x
Drawing Title
Drawing Number Drawing Number Drawing Number
Drawing Number
Drawing Number Drawing Number
0699-JCA-ZZ-XXX-DR-A-00303 0699-JCA-ZZ-XXX-DR-A-00303 0699-JCA-ZZ-XXX-DR-A-00303 0699-JCA-ZZ-XXX-DR-A-00303 0699-JCA-ZZ-XXX-DR-A-0 0699-JCA-ZZ-XX JCA Project No. JCA Project Scale@A1 No. JCA Scale@A3 Project Scale@A1 No.
EXISTINGEXISTING EAST BOX EXISTING EAST BOXEAST EXISTING BOX EAST BOX EXISTINGEXISTING EAST BOXEAST BOX EXTENT OF EXTENT APPLICATION OF EXTENT APPLICATION OF APPLICATION EXTENT OF APPLICATION EXTENT OF EXTENT APPLICATION OF APPLICATION
0699
0699
1 : 2000699 1:400 1 : 200
Scale@A3 Status JCA Scale@A1 ProjectRevision No. Scale@A3 Status Scale@A1 Revision StatusScale@A3 JCA Project Revision No. Status JCA Project Scale@A1 Revision No. Sca Sc 1:400 1 : 200 0699
1:400 1 : 200 P04 P04
1:400 P04 0699
0699
1 : 200 P04
www.jocowenarchitects.com www.jocowenarchitects.com www.jocowenarchitects.com www.jocowenarchitects.com
North/South Section
1:1
3D Modelling facade conditions
Eastern entrance approach
JO COWEN ARCHITECTS KINGSTON GATE CLIENT Apache Capital WORKSTAGE Planning (Incl. Concept Design) • • •
PERSONAL ROLE/RESPONSIBILITIES: Assisted with design development of facades Developed the 3D model Coordinated consultant information (Structures/MEP)
PROJECT DESCRIPTION In 2018 JCA won a design competition for a large Build to Rent development in the heart of Kingston. The key aim is to develop a market leading PRS development, taking advantage of the location w i t h i n o n e o f S o u t h We s t L o n d o n ’ s m o s t a f f l u e n t s u b u r b s . T h e s i t e is adjacent ro Kingston’s mainline railway station and within a short w a l k o f t h e p r i n c i p a l r e t a i l / l e i s u r e a r e a s a l o n g w i t h i t s C B D . To d a t e , principal activity has centred around assembling the various land parcels required to bring this development forward with obtaining advice on planning, transportation, and statutory services. It is now our intention to commence with the design development of the s c h e m e t o m a x i m i s e t h e p l a n n i n g p o t e n t i a l o f t h e s i t e a n d u l t i m a t e l y, deliver the scheme through design and build procurement methods.
S I T I N G A N E W B U I L D - T O - R E N T D E V E L O P M E N T O P P O RT U N I T Y W I T H I N C A N B U RY WA R D
Lobby
Commercial
Nursery
Gym
Retail
LINEAR PARK
ON D
SEVEN KING
ROAD
S WAY
RICHM
WALTER STREET GARDENS
SOPWITH GARDENS
SOPWIT
12
H WAY
JO COWEN ARCHITECTS
Ground Floor Plan
New proposed Kingston public square
Kingston Gate North Elevation
Proposed Site Thoroughfare