Research Report: India Utility Scale Solar Market Outlook 2022

Page 1

Table of Content
Introduction to Solar Industry .2
Cumulatively Solar PV installations . . . . 2
Yearly Solar PV Installation (Utility-scale) ………………………………………………………..……….……………………………………………….… 4 ● Quarterly Solar PV Installation (Utility) . .. . 5 ● Power Mix 6 ● Renewable Energy Generation Mix 8 ● SECI Payment to Power Generators 10 ● Electricity Market ..11 ● Solar PV Auction 13 ● Solar PV Tender 14 ● Market Outlook 15
State-wise Solar PV Installed Capacity (Utility-scale) 17 ● Discom Ratings ……………………………………………………………………………………………………………….…. 18 ● Policy & Regulation . ...21
Tariff-Rate in the Solar Auction 23
IREDA (Funding/loan Portfolio) 24 ● ALMM 24 ● Funding and M&A ..28 ● EV & Hydrogen Update ..29 ● Conclusion & Suggestion ..33 Abbreviation ACS Average Cost of Supply MNRE Ministry of New and Renewable Energy ALMM Approved List of Models and Module manufacturers MoU Memorandum of Understanding ARR Average Realisable Revenue MU Million Unit BCD Basic Custom Duty MW Megawatt BU Billion Unit NPA Non-performing Asset CY Calendar Year PLI Production Linked Incentive EV Electric Vehicle PV Photovoltaic FOB Freight on Board RE Renewable Energy FY Financial Year REC Renewable Energy Certificate GW Gigawatt RPO Renewable Purchase Obligation ISTS Inter-State Transmission System SECI Solar Energy Corporation of India JNNSM Jawaharlal Nehru National Solar Mission SERC State Electricity Regulatory Commissions kWh Kilowatt Hour VGF Viability Gap Funding

Disclaimer:

Even though every attempt has been taken to ensure the high calibre and correctness of SolarQuarter and all our research, we give no promise regarding its content. In addition to not being responsible for the availability of external websites or their contents, SolarQuarter is also not liable for any content created by third parties or for any error, omission, or inaccuracy in any advertising material. The data and information presented in this report are given solely for informational purposes; SolarQuarter, its affiliates, information providers, and content providers disclaim all responsibility for any investment choices made in reliance on this information or for the outcomes of those decisions.

International copyright and trademark laws protect the information in this publication. Any portion of the report may not be altered, copied, reproduced, republished, posted, transmitted, or distributed in any way If you maintain all copyright and other property notices, you may only use the content for personal, non-commercial purposes. You must obtain written consent from FirstView Group to utilize the content for any non-personal or non-commercial purpose.

Introduction to the Indian Solar Industry

India's Solar PV installed capacity as of October 2022 has crossed 60 GW The government had set a JNNSM target by 2022 to install 100 GW of Solar PV capacities which includes 60 GW of utility-scale (Large/ground mount) and 40 GW of Solar rooftop capacity. The growth of large-scale projects had picked up after the announcement of the Solar Park as well as reverse auctions after 2016 before the government used to go for Viability Gap Funding (VGF) along with fixed tariffs where the bidders used to compete over VGF. After the announcement of a reverse auction, the pace of utility-scale solar projects has increased, followed by many other factors such as Solar parks, Solar RPO as well as state-level tenders The growth of Solar has outpaced all the other renewable sources of energy and covers a market of around 51.74% of the total Renewable installed capacities of above 119 GW by October 2022, but India missed the target of 100 GW by December 2022. In renewables, India has become one of the global leaders. In 2021, it ranked third in the world by installed renewable capacity and is the only country in the G20 that is on track to achieve its targets under the Paris Agreement During the first 5 years after the signing of the agreement, India has witnessed the fastest rate of growth in renewable energy capacity addition among all large economies, with renewable energy capacity (including large hydro) growing around two times.

Cumulatively Solar PV installations (Utility & Rooftop)

Solar capacity additions grew by around 20% in September 2022 over the previous year with around 47.89 GW installed Solar PV capacity as of September 2021, an exponential increase compared to around 9 5 GW installed in the first three quarters of the calendar year 2022 Installations were up by above 27% compared to 7 45 GW installed in the first nine months of 2021

In the first nine months of 2022, large-scale installations totaled around 9.6 GW compared to around 5.38 GW installed in the first three quarters of 2021 altogether. Y-o-Y, large-scale installations increased by over 78.19 percent The large-scale Solar PV project installation figures were the highest since the Solar installation was started in the year 2009-10 As the market opened after the second half of 2021 after COVID-19 restrictions, so many projects which were not able to get commissioned during the lock-down period due to COVID-19 restrictions were commissioned mostly in 2022, also there is a duty-free window in Q1 2022, which allowed the developers to commission their projects during this period, as large-scale developers used to procure their panels few weeks before the commissioning due date Even though the installations are estimated to be high in Q4 2022, due to BCD, many uncertainties arise in the market, such as whether to procure the panels duty-free or have to pay duty MNRE recently clarified that tenders before 09th March 2021, and whose commissioning date is coming after BCD can take the benefit of change in law and procure the panel duty-free. The Solar PV/Solar PV-Wind Hybrid power projects, wherein the last date of bid submission was on or before the announcement on 09th March 2021, regarding the imposition of BCD on import of Solar PV cells and modules with effect from 01st April 2022 and wherein the scheduled commissioning date, including time extension granted, if any, was on or After 01st April 2022, may consider the imposition of BCD on import of Solar PV cells and modules with effect from 01st April 2022, under “Change-in-Law’ unless the same is disallowed by specific provision in the tender document/contracts.

The market has substantially improved since Q4 of 2020 due to which the Solar PV installations crossed 2 GW in all five quarters since a quarter third of 2021. The market is slowly recovering from a pandemic, and projects are getting commissioned that were stuck in 2020 but one issue of rising in the Solar PV modules continues in the Indian Solar industry, as per PVInfo Link the price of Solar PV modules (FOB) fell marginally to USD 0.24-0.27/W in Europe, USD 0.24-0.25/W in the Asia Pacific region, and USD 0.24-0.25/W in Brazil. Local module prices in India translate to around USD 0.32-0.359/W (FOB)

The share of utility-scale in the total Solar PV installations as of September 2022 was around 87 percent, while in CY 2022 for all three quarters, it has increased to 88 percent. While the share of rooftop Solar as of

September 2022 was around 13 percent of the country's total Solar PV installations, it has gained a 20% share compared to September 2021 installations The share of the rooftop especially in the commercial and industrial space will grow substantially as the net-metering policy which was pending for a few months has been approved by the Ministry of Power where the new amendment allows the net-metering users to go for loads up to 500 kW or up to the sanctioned load, whichever is lower.

Yearly Solar PV Installation (Utility-scale)

The growth rate of Solar PV installations is quite impressive in 2021, as India commissioned capacity in the Calendar year (CY) in 2021 was around 10.4 GW compared to the installations in 2020 were 3.7 GW in the full twelve months Installations in the calendar year 2022 will be around 13 6 GW, while the utility-scale Solar PV installation is estimated to be around 11 5 GW Solar Installation in the first nine months of utility-scale was around 9 6 GW by September 2022 Since COVID-19, the installations in the utility-scale segment have slowed down drastically but they gained momentum since the second half of 2021 and India installed a whooping capacity of 16.7 GW in the past five quarters since Q3 2021.

The projects which were not able to be commissioned in 2020 due to COVID-19 restrictions, those projects are commissioned in the calendar year 2021 and also continue through 2022, but the shortage of modules is still looming in the sector. After safeguard duty ended in July 2021, the utility-scale installations have jumped many folds and installed maximum capacity till March 2022. But after the announcement of BCD on 01st April 2022, uncertainty in the market aroused, and there was utmost confusion about whether the developers have to pay BCD on modules & cells Along with that, the government has raised GST on Solar along with compulsory use of ALMM-l listed panels in the government tenders to pull the already struggling installation due to high module prices.

Quarterly Solar PV Installation (Utility)

In CY Q3 2022, utility-scale projects accounted for 83 percent of the total Solar PV installed, which was down by 8 4 percent from CY Q2 2022 and up by 9 6 percent from CY Q3 2021, where the installations were around 2 28 GW The installations in CY 2022 would have been more but due to an increase in the raw materials, also basic customs duty came into the picture from 01st April 2022, many projects were still on hold which might get commissioned in the coming quarter. Due to BCD implementations in April, India installed around 9.6 GW in the first nine months compared to around 5 4 GW installed in the first nine months of 2021

The growth of utility-scale/large projects is taking a stand in the growth of the success story of India. India pledged to become 100% renewable in the coming decades and Solar is going to play a significant role.

Power Mix

Renewable capacity additions continue to increase at a rapid pace in India, accounting for approximately 29.1 percent of India’s power capacity mix at the end of October 2022 India’s total installed power capacity stood at over 408 GW at the start of the calendar year Q4 2022 from all the sources, with renewables accounting for ~119 GW, compared to cumulative renewable energy installations of 103.05 GW at the end of October 2021, which represented a 15.56 percent growth year-over-year.

Solar power accounted for approximately 61 62 GW of installations, which is 15 1 percent of the total installed power capacity. The share of Solar power in the installation mix grew from 12.2 percent in October 2021 to 15.1 percent in October 2022. Among renewables (excluding Hydro), Solar accounted for approximately 51.74 percent of the installed capacity. Wind accounted for 35.1 GW of the total renewable installed power capacity and nearly 10 2 percent of the overall power capacity mix as of October 2022 As 2022 is the last year for the JNNSM target, the overall installed Solar capacity in the country has increased by 24 88 percent which was 49.34 at the end of December 2021 to 61.62 GW by October 2022.

Among renewables, Solar Power has shown the highest growth year-over-year by 29 28 percent from October 2021 to the same month of 2022, while Wind Power has grown by 4.64 percent, and Bio-Power by 1.17 percent. Hydro power’s cumulative installations stood at 46.85 GW, making up 11.5 percent of India’s total installed capacity.

Small hydro had installed over 4.92 GW and represented 1.2 percent of the overall power mix capacity at the end of October 2022 The share of nuclear power remains constant for a few quarters which represents 1 7 percent of the total power mix installed capacity by October 2022, with no capacity added during the full calendar year of 2021 & 2022 Nuclear power is not only clean and environmentally friendly, but it is also a source of base load power available 24x7 like thermal power. As the other segments in the power mix were adding their capacities it resulted in a decrease in the share of nuclear power in the overall power mix. The actual commercial generation has increased from 34,162 million Units in the calendar year 2014 to 43,918 million units in 2021 for nuclear power Total power generation from nuclear power in September 2022 was 3,412.52 million units.

Thermal power (which includes coal, lignite, gas, and diesel) is still the significant source of energy in the country - with its cumulative installations reaching 235 99 GW, representing 57 7 percent of the total installed power capacity. Coal accounted for a dominant share of the mix, with 49.9 percent of the total installed power capacity, followed by natural gas at 6.1 percent, lignite at 1.6 percent, and diesel at 0.14 percent share. However, thermal power’s share in the overall power mix is gradually declining as the government is shutting down old thermal plants, especially coal, and moving towards the non-conventional source of energy But in the recent past, the country suffered outages across the country due to a shortage of coal in the thermal power coal unit. It’s a long way before renewable power generation will be able to dominate the country's electricity demand as mainstream renewable energy is intermittent.

In the recent update from the ministry of power for “Concept note on Pooling of Tariff of 25 years Plus Thermal/Gas Generating Stations” the availability of ample generation capacity, low cost of some recently signed renewable PPAs, and low tariffs in the market, has led States, specifically those that are surplus in power to approach Ministry of Power for relinquishment of their share from Central Generating Stations (CGS) The Ministry of Power, considering the request of the States, allowed the States to exit from PPAs with Central Power Sector Utilities after 25 years vide guidelines dated 22.03.2021. Thereafter, many States/ Distribution companies based on commercial considerations are exiting PPAs of costlier plants (non-pit head coal stations and Gas based thermal generating stations) while retaining the PPAs of cheaper plants

Renewable Energy Generation Mix

Total renewable energy generations in September 2022 reaches 16,943 29 million units, there is an increase of RE generators by 16 94% over September 2021, where the RE generations were 14,488 86 million units, also there is an increase of over 28.9% in September 2022 over January 2022 where the generation from RE was 13.149.60 million. There is a year-over-year growth of 51.74% in Solar power generation from September 2021 to September 2022, while Wind Power has shown a decline of 4.68% in the same period.

Solar Power generation is having the largest percentage in terms of generation overtook Wind Power with 8,207.73 million units and contributed 48.44 percent of the total renewable generation share in September 2022, Wind Power with 39.28 percent of the market by generating 6,654.49 million units in September 2022. Other sources such as Bagasse, small Hydro, and Biomass contribute 0 97 percent, 9 09 percent, and 1 02 percent respectively Solar and Wind Power together contributed 87 72 percent of the total renewable energy generation in September 2021

The total renewable generation has grown by 32 84 percent from December 2021 to September 2022 While there is an exponential growth of 40 11 percent in Solar power generation from December 2021 till the end of Q3 2022, Wind Power has increased by 86.03 percent in generation in the same period.

In terms of generation for Wind vs Solar, Wind overtakes the actual generation in May, June, July, and August generally due to high wind speed and monsoon season. Even though the installation of Wind in terms of Solar power was lower, the generation overtook in these four months of the year. Generally, generation is high during these seasons for Hydro, wind, as well as small hydro on the other hand generation, used to be low for Solar, and thermal due to the monsoon season The hybrid project developers should make use of this algorithm and can save money by doing the right scheduling and forecasting of power from different sources of electricity

The RE capacity has shown a sudden spike in the generation from May 2022 due to an increase in wind generation as well as capacities addition in Solar PV. The generation from Solar is usually less during the monsoon season, and high during the summer season But the Solar power plant can be installed at any location while the Wind turbine cannot be installed in those locations where the wind speed is less, a minimum required wind speed (generally 12-14 km/h) to begin turning and generate electricity strong winds (50-60 km/h) to generate power at full capacity. winds speed beyond 90 km/h the turbines must be stopped to avoid damage.

SECI Payment to Power Generators

Solar Energy Corporation of India (SECI) paid ₹65 81 billion (~$805 92 million) for Solar and Wind power purchased in the first nine months of 2022, there is a decent growth of SECI payments to Wind and Solar power generators for September 2021 to September 2022 of over 45 percent. The disbursed amount was highest in July followed by June & September. There is a gradual increase in the payment to generators from October 2021 to September 2022.

In the last year from October 2021 to September 2022, SECI has made a payment of around ₹81.47 billion ($997.69 Million). The payment of Solar and wind generators will start increasing in 2022, as lots many projects are coming online in the coming quarters SECI is the major power purchaser for Solar in the country, and monthly payments to power generators are increasing year on year basis

Electricity Market

The entities showing aggressiveness in buying Renewable Energy Certificates (REC) to meet their renewable purchase obligation (RPO), there is a growth of 13 02 percent year over year from October 2021 to October 2022 In March 2022, Power Market traded the highest monthly volume of 9,605 MU in the calendar year 2022 The average Day Ahead Market prices increased to ₹5 40 per unit during Q2 FY23, as against ₹4 14 in Q2 FY22

As India moves towards carbon neutrality and harnesses vast amounts of renewable power to meet its growing appetite for energy, IEX will continue to make use of technology and innovation to facilitate the nation’s energy transition.

India recently surpassed the UK to become the fifth-largest economy and is expected to become the third-largest economy by the end of this decade. For FY ’23, the Indian economy is expected to grow by 6.8% as per IMF. During Q2FY23 both the Manufacturing and Services PMI (Purchasing Manager Index) remained strong on account of increased Industrial activity leading to an increase in electricity consumption by 6% YoY to 385 BU

In September 2022, the installed power generation capacity reached 408 GW. The contribution of renewable energy (RE) grew to 165 GW, which is 40% of the total installed power capacity It is evident from the rapidly expanding green energy capacity that the nation is advancing towards a carbon-neutral economy by 2070 and achieving a 50% clean energy share by 2030.

During the quarter (CY Q3), electricity volumes on the Exchange fell by 1 40% YoY with 23 1 BU volumes traded versus 23 43 BU in Q2 CY 2022 The volume comprised 19 72 BU in the conventional power market, and 1 47 BU in the Green Market segment.

In the previous quarter, IEX launched the web-based bidding platform to provide anytime, anywhere easy and secure access to the trading system. IEX also launched its web-based financial reconciliation system to enable the easy and efficient online settlement of exchange-based transactions for customers. On 27th June 2022, IEX successfully launched the much-awaited Longer Duration Contracts up to 90 days on the Exchange which will help to bolster its presence in the short-term market

Solar PV Auction
Solar PV Tender

Market Outlook

The installations for Solar PV in the calendar year 2022 for the first nine months were around 10.9 GW (utility-scale & rooftop), and there was a growth of 46% compared to 9M CY 2021 installations. COVID-19 restrictions are gone days, but the significant issue is with the supply of Solar PV modules, as there is a fluctuation in the price of raw materials in China, and there is a huge demand for Solar PV modules across the world Developers can delay projects and call for greater collaboration among upstream and downstream players. Polysilicon prices recorded a rise, and glass prices are increasing. Many signed orders will cause serious losses and seriously endanger the sustainable development of the industry due to the rising prices of materials followed by transport

As capacity utilization rates of Chinese manufacturers fall, manufacturers negotiate with customers. The module manufacturers have also called upon the relevant PV industry associations along with other bodies to monitor the upstream and downstream production capacity more closely to assist in the planning of production capacities beforehand and balance upstream and downstream supply and demand Basic customs duty on Solar PV cells and modules has been imposed from 1st April 2022, which creates ambiguity in the market.

As per the latest update on ALMM list l, 75 companies have been enlisted with 18 788 GW under the Approved list of models and manufacturers. All the government Solar tenders coming these days are mandated to use modules listed under ALMM. On the other hand, none of the Chinese companies are there on the list so far, which might hamper and increase the tariff rate of future bids

PLI (Production Linked Incentive) scheme for Solar manufacturing concludes that the cell and module manufacturing facilities have a minimum gestation period of 18 months. Therefore, the first batch of the Solar module from the facilities is expected before 2024 Also, SECI issued RfS for the Selection of Solar PV Module Manufacturers for Setting up Manufacturing Capacities for High-Efficiency Solar PV Modules in India under the Production Linked Incentive Scheme (Tranche-II) has been issued under the "Scheme Guidelines for Implementation of the Production Linked Incentive Scheme (Tranche II) under ‘National Programme on High-Efficiency Solar PV Modules’ for achieving manufacturing capacity of Giga Watt (GW) scale in High-Efficiency Solar PV modules"

India’s current Solar PV module manufacturing installed capacities are in the range of ~20-25 GW, a significant portion of which is based on multi-crystalline technology, again many new expansions are happening these days with the highest-rated panels of Mono PERC after the announcement of BCD Solar developers have engineered and designed all upcoming Solar plants using Mono-PERC and bifacial technologies.

India’s target to accomplish 280 GW Solar PV installed capacity by 2030 required a capacity addition of nearly 25 GWp per annum In the National draft electricity, five years plan the capacity addition required during 2022-27 to meet the peak demand and energy requirement for the year 2026-27 is 2,28541 MW, which comprises (Coal- 25580 MW, Gas-370 MW, and Nuclear-7000 MW) and 187,909 MW of Renewable based Capacity Addition (Large Hydro-10951 MW, Solar -132,080 MW, Wind-40500 MW, Biomass-2318 MW, PSP-2700 MW) excluding 5,856 MW of likely Hydro based Imports The capacity addition required during 2027-32 to meet the peak demand and energy requirement for the year 2031-32 is 2,43,042 MW comprising 18,134 MW of Conventional capacity addition (Coal-9,434 MW, Nuclear-8700 MW) and 224,908 MW of Renewable based Capacity Addition (Large Hydro-10,888 MW, Solar-147,400, Wind 53,100 MW (Onshore- 43,100 MW and Offshore 10,000 MW, Biomass-1,500 MW, PSP-12,020 MW) excluding 5,856 MW of likely Hydro based Imports

The domestic module manufacturing capacity is not sufficient to meet the yearly requirements and will cause a supply crunch Factors creating issues stating that the sector is going through a perfect storm The prices of major raw materials for the manufacturing of modules like polysilicon, aluminum, silver, and more have increased substantially Sea freight has also increased enormously

The year 2022 is a pivotal one for India’s energy transition. Many big companies such as Reliance, Adani, ReNew Power, and NTPC had announced massive investments in renewable energy (RE), mostly Solar, to slowly move their transition to a low-carbon future This is the last year for the JNNSM target which needs to be fulfilled as India installed around 61 GW of Solar PV capacity by the end of October 2022 as per the CEA monthly update.

In 2022, the installations will be a record year and will surpass an all-time high of Solar PV installations There will be challenges for raw material price and supply. There will also be a growth in Wind-Solar hybrid projects, along with green hydrogen. The Solar rooftop installation will also grow especially in the Commercial and Industrial (C&I) segment, as the electricity demand is increasing due to a sudden surge in demand in the economy after the upliftment of COVID restriction, and to reduce the cost of electricity C&I consumers will go for Solar installation

After the imposition of BCD on Solar, the duty of 40% on the module and 25% on the cell, affects the 2022 installation The installations in the calendar year 2022 will be on the higher side, as this is the last year for the JNNSM target which was 100 GW till December 2022.

The ministry has issued the concept note on Pooling of Tariff of 25 years Plus Therma/Gas

Generating Stations

The power situation in the country has changed from deficit to surplus over the years There were times when States had been keen to enter into a long-term Power Purchase Agreement (PPA) to secure power. However, the situation has changed now. The emergence of cheaper renewable energy, especially Solar, has attracted the attention of everyone Today, the procurers are scouting for cheaper power and are hesitant to enter long-term PPAs, anticipating a further reduction in power prices Further, an often-ignored fact is that the volume of power transacted on the exchange is only about 12% of the total energy requirement in the country.

The availability of ample generation capacity, the low cost of some recently signed renewable PPAs, and low tariffs in the market have led States, specifically those that are surplus in power to approach the Ministry of Power for relinquishment of their share from Central Generating Stations (CGS) The Ministry of Power, considering the request of the States, allowed the States to exit from PPAs with Central Power Sector Utilities after 25 years vide guidelines dated 22.03.2021. Thereafter, many States/ Distribution companies based on commercial considerations are exiting PPAs of costlier plants (non-pit head coal stations and Gas based thermal generating stations) while retaining the PPAs of cheaper plants State-wise Solar PV Installed Capacity (Utility-scale)

India installed around 49.85 GW of Solar PV installations as of September 2022 as per the MNRE update. Rajasthan, Karnataka, Gujarat, Tamil Nadu, Telangana, and Andhra Pradesh were the top states who have installed grid-connected utility-scale Solar projects of above 4 GW and cover 81.25 percent of the total installed large-scale capacity The top ten states installed a cumulative capacity of around 47 75 GW and covered a market share of more than 96 percent by the end of September 2022

India's total installed Solar PV capacity has crossed the 60 GW milestone by the end of September 2022, out of which large-scale projects contribute 49 85 GW while the rest come from rooftop solar as well as off-grid systems The government has targeted the installation of 60 GW of Solar PV large-scale as of December 2022, but India has achieved above 49 85 GW of Solar PV installation in the utility/large-scale segment A quarter is left for the JNNSM target, and around 10 GW of the shortfall is left to be installed in these three months before 2022 comes to an end. It seems the target might not be fulfilled as expected due to uncertainty arising in the market after BCD from April 2022 Also, the price of the module is on the higher side and is slowly moving in a downward trend after the pandemic restriction It doesn’t seem feasible for the project developers to commission the projects before the due date as the price of the modules are not matching with the tariff rate which the bidders had expected while biddings.

The large-scale Solar projects between October 2021 to September 2022 installed around 9 6 GW, Rajasthan installed a whooping capacity of 4.5 GW, while Gujarat and Tamil Nadu installed 1.52 GW and 1.45 GW, the rest of the state installed below 1 GW in that period. Nine States installed below 100 MW of large-scale Solar capacity, while only one state installed above 500 MW and below 1 GW Around 19 states have not installed any Solar PV capacity under utility-scale Solar PV capacity in the past year since October 2022

Discoms Rating

Since 2012, the Integrated Rating Exercise has been carried out under the framework approved by the Ministry of Power annually to evaluate the performance of Power Distribution utilities on a range of parameters covering financial, operational, regulatory, and reform aspects and their ability to sustain improvements year over year The Ministry of Power has mandated Power Finance Corporation (PFC) to co-ordinate the rating exercise This Exercise has been based on the Integrated Rating Methodology, which is used to rate discoms based on their financial performance and their ability to sustain improvements year over year.

Ratings that reflect the true picture

• All calculations based on actual cash received instead of accruals, to factor in the impact of realization of cash from consumer dues, government dues, and tariff subsidies Metrics that have improved due to this change include the ACS-ARR gap, debt service coverage ratio, and leverage

• Increased weightage of quantitative metrics (derived from audited accounts and regulatory filings and orders), to improve the accuracy and transparency of ratings.

• Negative scoring for non-compliance with specific metrics, such as unavailability of audited accounts and defaults to banks and financial institutions For power departments, a subset of metrics relevant to them has been used

• Establishment of protocols and a committee for a trigger-based review of ratings, to factor in the impact of events of significance and to ensure that ratings reflect the latest performance of discoms. A rating review can be triggered by new payment defaults, publication of audited accounts, issuance of tariff orders, etc.

The 10th Integrated Rating Methodology evaluates discoms’ performance against three main parameters:

1. Financial Sustainability (75% weightage): Includes metrics such as ACS-ARR gap (cash adjusted), days payable to Genco and Transco, adjusted quick ratio, and debt service coverage ratio (cash adjusted)

2 Performance Excellence (13% weightage): Includes metrics focusing on operational performance, such as billing efficiency and collection efficiency

3. External Environment (12% weightage): Includes metrics to cover the impact of state government action and regulator action, such as subsidy realized and adherence to tariff cycle timelines.

Based on the methodology approved by the Ministry of Power, the discoms have been given a ranking and rating for the 10th Integrated Rating exercise below:-

For certain parameters, evaluation covers three years of performance as well as improvements from year to year For Power Departments, a subset of metrics is being used, because of their non-corporatized nature of operations

The following 8 utilities mentioned below have not been included in the main ranking list because they have not completed the full three years of operations yet The rating for these utilities is based on their reported performance for FY21 only.

Policy & Regulation

Greenfield Coal-Based Plants Must Have 25% Compulsory Renewable Power Generation Clause

The Ministry of Power (MoP) proposed that any coal-based thermal generation station built after April 1, 2024, must install or procure renewable electricity equivalent to 25% of its thermal generation capacity. To implement the regulation, the ministry intends to amend the Tariff Policy 2016, to add the provision of "Renewable Generation Obligation (RGO)” This regulation proposes that thermal generators may procure power from grid-connected renewable power projects with a minimum of 5 MW capacity by purchasing power through competitive bidding. The obligated entity is deemed to have fulfilled its RPO by the SERC. If setting up a greenfield renewable project is not feasible, thermal generators may also consider virtual power purchase agreements (VPPA)

Central Regulatory Commission Announced Levelized Tariffs For Small Hydro, Biomass, And Biogas Projects For FY 2023

CERC has issued levelized generic tariffs for small hydro projects, biomass power projects with ranking cycle technology, non-fossil fuel-based cogeneration projects, biomass gasifier-based power projects, and biogas-based power projects for the financial year (FY) 2022-23. Levelized Tariff for Small Hydro Projects for FY 2022-23 in Himachal Pradesh, Uttarakhand, West Bengal, North East States, and Union Territories of Jammu and Kashmir & Ladakh with project size <5 MW, and Levelized New Tariff ₹5.3/kWh. In Himachal Pradesh, Uttarakhand, West Bengal, North East States, and Union Territories of Jammu and Kashmir & Ladakh with project size ranges from 5-25 MW and Levelized New Tariff ₹4.76/kWh. Other states such as project size <5 MW will have a Levelized New Tariff of ₹5.84/kWh and from 5-25 MW project sizes have a Levelized New Tariff of ₹5.76/kWh.

Amendments To The Guidelines For Tariff-Based Competitive Bidding Process For Procurement Of RTC

Ministry of Power (MoP) has amended the tariff-based competitive bidding process guidelines to procure round-the-clock (RTC) power from grid-connected RE projects, complemented with power from any other

source or storage. As per the recent amendments, RE power generators must supply RTC power maintaining 90% availability annually. The RE generators can combine storage to achieve the minimum annual availability of 90% and maintain at least 90% availability monthly for at least 11 months in a year. The RE generator must ensure 51% of supplied energy comes from renewable energy sources. This 51% power should include power from the storage system, provided renewable sources are used to store the energy.

Power Ministry Notifies 'Green Energy Open Access' Rules To Accelerate RE Programs

Ministry of Power has notified Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022 on June 06, 2022. The reduction of the Open Access Transaction limit from 1 MW to 100 kW and appropriate provisions for cross-subsidy surcharge, additional surcharge, and standby charge, will incentivize the common consumers to get Green Power at reasonable rates. These rules are notified for promoting the generation, purchase, and consumption of green energy including the energy from Waste-to-Energy plants The Green Open Access is allowed to any consumer and the limit of Open Access Transaction has been reduced from 1 MW to 100 kW for green energy These Rules will also streamline the overall approval process for granting open access & so on

Bill To Set Up Carbon Markets Introduced In Lok Sabha

A bill that seeks to make it mandatory for buildings with a minimum connected load of 100 kW to meet their energy requirements from renewable sources was introduced in the Lok Sabha. Power Minister introduced in the Lok Sabha the Energy Conservation (Amendment) Bill which also has provisions to establish carbon markets and empower state electricity regulatory commissions to make regulations for a smooth discharge of its functions The Bill seeks to mandate the use of non-fossil sources, including green hydrogen, green ammonia, biomass, and ethanol for energy and feedstock

Electricity Amendment Bill 2022

The Bill, introduced in Lok Sabha on August 8, 2022, aims to provide consumers with options to choose between multiple service providers in an area and create competition in the power distribution sector. However, it was referred for scrutiny to the Parliamentary Standing Committee on Energy on the same day According to the Electricity Act 2003, a utility cannot be denied a license if they apply for a distribution license in one area The new provision in the Act will remove public as well as private monopolies in the power distribution sector, the customers will have options to choose from multiple service providers in an area. The competition in the power distribution sector will also improve the quality of services.

Implementation Of The “Electricity (Late Payment Surcharge & Related Matters) Rules, 2022

These rules provide a mechanism for the settlement of outstanding dues of Generating Companies, Inter-State Transmission Licensees, and Electricity Trading Licensees The rules provide for clubbing of all outstanding dues (as of 03 06 2022) including Principal, Late Payment Surcharge, etc into a consolidated amount which can be paid in interest-free Equated Monthly Instalments (EMI) The maximum number of such EMIs can be forty-eight (48) based on the quantum of the total outstanding dues The rules also indicate modalities for implementation and also penalties for not making payments, in line with the Re-determined Payment Schedule Further, non-payment of current dues by DISCOMs, one month after the due date of payment or two and half months after the presentation of the power bill, whichever is later, shall attract regulation of power as laid down in the LPS rules, 2022.

Government Exempts CPSES In RE Projects From China-Centric Import Curbs

CPSEs will now be able to import four categories of items freely from any country, including China, which heavily dominates the RE supply chain The exempted categories are 1) solar photovoltaic cells, wafers, EVA, backsheet, and frames 2) inverters 3)trackers and 4) battery energy storage system components which include

cells, battery packs, and power conditioning systems. There are over 360 CPSEs in India and several of them like the NTPC is now working on RE projects as India looks to ramp up to meet ambitious targets. This exemption from Rule 144 (xi) will, in effect, enable NTPC and other CPSEs engaged in RE projects to cut costs by directly importing from bidders/companies from China without the requirement of their registration in India. China and other countries that shared a land border with it citing Mission Aatmanirbhar Bharat. The change was introduced through Rule 144 (xi) of the General Financial Rules that govern public procurement in India.

Part Commissioning Of ISTS-Connected Solar Power Projects In Lots Which Are Not Less Than 10 MW

The request has been examined and it has been decided that to facilitate expeditious commissioning of solar PV power projects and in line with similar facilitation already provided to wind power projects under all SECI tranches, notwithstanding the provisions of the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects’ ISTS connected solar PV power projects bid out as per the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Proiects’ will be allowed to part-commission in steps of 10 MW or more. This will be applicable till 31st March 2023

Tariff Trends in the Solar Auctions

The lowest bid discovered in the recent Solar auction in the Solar Energy Corporation of India’s (SECI) auction for 1,785 MW of solar power projects (Tranche IV) in Rajasthan, where NTPC Renewable Energy (NTPC Limited subsidiary) won a capacity of 500 MW, Sprng Energy Natural Power Source (a special purpose vehicle (SPV) of Sprng Energy) won 200 MW, Calpine Subsico Solar Energy (an SPV of UPC Renewables) 90 MW, and Metka EGN Singapore Pte 20 MW, each quoting ₹2 17 (~$0 0289)/kWh, this auction conducted in December 2021

State Solar auction conducted by Gujarat Urja Vikas Nigam Limited’s (GUVNL) under GUVNL 500 MW Phase-XII Solar Auction Result shows Sprng Ujjvala Energy won a capacity of 120 MW quoting ₹2 20 (~$0 030)/kWh Meanwhile, NTPC Renewable Energy, Coal India, and TP Saurya won 150 MW, 100 MW, and 60 MW, respectively, quoting ₹2 20 (~$0 030)/kWh each as this is the first auction after the announcement of BCD

IREDA (Funding/loan Portfolio)

Indian Renewable Energy Development Agency (IREDA), a PSU under the Ministry of New & Renewable Energy (MNRE) Net Non-Performing Assets (NPAs) have been reduced to 2.72% by September 2022, from 4.87% in Q2, FY 2021-22, a significant reduction of 44% YoY.

Net worth reached ₹5,638.31 crores as against ₹3,333.19 crores (up by 69.16%), Loan Book achieved ₹33,783.36 crores as against ₹28,856.48 crores (up by 17.07%), Loan Sanction increases to ₹11,226.49 crores as against ₹5925.12 crores (up by 89.47%), Net NPAs reduced by 2.72% as against 4.87% (reduction by 44%), Gross NPAs by 5 06% as against 8 05% (reduction by 37 17%) as of September 2022

ALMM

The Ministry of New & Renewable Energy (MNRE) has issued an Approved List of Models and Manufacturers (ALMM) order dated 2nd January 2019. Due to the pandemic, government officials were not able to inspect the foreign production unit, even domestic players were facing issues to enlist their capacity. Below are the only Indian manufacturers who can get their registration under the ALMM list-l by August 2022 as per the last update

Many large Solar PV tenders are mentioning the requirement of ALMM-registered panels, but the Indian Solar Market is being dominated by Chinese players who are not able to get their capacity under ALMM to be supplied to this project As of December 2021, around 10,726 MW of manufacturing installed capacity has been enlisted with 41 companies, compared to around 75 companies listed with 18,788 MW of capacity as of August 2022.

Gujarat has maximum capacities enlisted under ALMM List-l with 32 manufacturers followed by Telangana with 9 manufacturers Karnataka, Maharashtra, and Uttar Pradesh each with 7 manufacturers followed by Haryana, Rajasthan, and West Bengal each with 3 manufacturers Whereas four states have only single manufacturers enlisted under ALMM List-l to date from Chhattisgarh, Odisha, Tamil Nadu & Uttarakhand

B Chinese manufacturers failed to register themselves on the list. In the past, due to COVID-19 restrictions, government officials were not able to complete their inspection, now there is a high chance for the Chinese suppliers to get themselves listed as all restrictions globally have been removed and officials are ready to do the inspection There is a high possibility to get Chinese series panels listed in the next updated list when MNRE will issue.

Blupine Energy Acquires 404 MW Operating Solar Portfolio From Atha Group

Actis-backed BluPine Energy, a renewable wind and solar power generation and storage business, has completed the acquisition of a 404 MWp operating pan-India solar portfolio from the Atha Group. The acquisition will enable BluPine to support India’s energy transition by targeting 4 GWs of portfolio capacity over the next 4-5 years

Waaree Energies Catapults India’s Green Energy Sector Through ₹1,000 Crores Funding From Private Funding

Waaree Energies has raised around ₹1,000 crores from various investors through primary funding The funds will be used for expansion plans of the company to increase its manufacturing capabilities in India from 2 GW to 9 GW for PV modules, of which 5 GW is operational and the balance 4 GW is expected to be operational by January 2023 Waaree also has plans for backward integration in the manufacturing of Solar Cells with a capacity of 5 4 GW

Sangam Renewables Divests Its Entire Stake In Its Subsidiary WAACOX Energy To Aditya Birla Renewables

Sangam Renewables announced the completion of its entire stake sale (51%) in its subsidiary, WAACOX Energy Pvt Ltd (WEPL) to Aditya Birla Renewables Ltd, ABRel, for an amount of ~₹416 million ABRel earlier held 49% in WEPL and increased to a 100% stake The company shall use these proceeds to reduce its short-term debt by ₹403 million on a standalone basis WEPL had 24 MWp of operational solar plants which were co-developed by SARel and ABRel The PPA of these projects in WEPL is held by Mahagenco and Mahadiscom

Hero Electric Raises ₹220 Crore In Gulf Islamic Investments-led Funding

Hero Electric Vehicles has raised ₹220 crores in a Series B funding round led by Gulf Islamic Investments (GII) Hero Electric will direct this investment towards the objective of further supporting the electric vehicle industry and ecosystem Avendus Capital was the exclusive financial advisor to Hero Electric on the transaction Hero Electric will allocate this investment towards expanding production capacity, consolidating its market position to strengthen market leadership, investing in futuristic technology, and growing its footprint across India-like markets

Adani Green Energy Raises $750 Million At 4.375%

Adani Green Energy has priced its ListCo senior issuance of $750 million through a three-year issuance at a fixed coupon of 4.375%. The funds shall be utilized towards equity funding of the CAPEX for underlying renewable projects under construction by AGEL. Under the structure, AGEL can draw up to $1,700 million (including the present issuance) over time subject to the covenants of the structure. The notes were rated Ba3 (Stable) by Moodys.

ReNew Raises $400 Million By Issuing Green Bonds

ReNew Energy Global Plc announced that India Clean Energy Holdings, a Mauritian entity, and a wholly owned subsidiary of ReNew Energy Global Plc (the parent company of ReNew Power Private Limited), has raised US$400 million at 4.5% by issuing senior secured dollar notes. The dollar notes are certified green bonds by Climate Bond Initiative and will be listed on the Singapore Exchange (SGX). These Green Bonds have a tenor of 5 25 years

Fourth Partner Energy Acquires On-site Solar Assets of ReNew Power

Funding & M&A

Fourth Partner Energy has acquired the onsite distributed solar generation portfolio of 140 MW spread over 100 projects in India of ReNew Power for ₹650 crores Most of these projects are operational and the energy generated is consumed locally The deal marks ReNew’s exit from the segment ReNew Power henceforth intends to concentrate on areas like energy storage, green hydrogen, and large-scale corporate deployments

Adani Green Energy Raises For Debt Refinancing Of Solar

Projects

Three subsidiaries of Adani Green Energy Ltd – Adani Green Energy (UP) Ltd, Prayatna Developers Pvt Ltd, and Parampujya Solar Energy Pvt Ltd, collectively housing 930 MW of operational solar power projects have raised ₹612.30 Cr by their maiden domestic bond issuance, on private placement basis. The Rated, Listed, Secured, Redeemable, Non-Convertible Debentures (NCDs) of the face value of ₹10,00,000 each, in multiple series, have an average annualized coupon rate of 7 83% p a (fixed) and a tenure upto 12 years

Reliance Completes Acquisition Of 40% Stake In Sterling & Wilson Solar

Reliance Industries Limited (RIL) has completed the acquisition of a 40% stake of Shapoorji Pallonji (SP) Group in Sterling & Wilson Renewable Energy Limited (SWREL) for ₹2,845 crores Reliance subsidiary RNEL bought 1 96 crore shares or a 10 37% stake in SWREL This was the last tranche of the transaction, culminating in a 40% stake for RIL in SWERL

Tata Power Renewables Raises ₹4,000 Cr From BlackRock-led Consortium

BlackRock Real Assets, together with Mubadala, shall invest ₹4,000 crores (~$525 million) by way of equity/compulsorily convertible instruments for a 10 53% stake in Tata Power Renewables, translating to a base equity valuation of ₹34,000 crores. The final shareholding will range from 9.76% to 11.43% on the final conversion. This newly created platform will consist of five distinct businesses as all renewable energy businesses including utility-scale Solar, Wind & Hybrid generation assets; Solar Cell & Module Manufacturing; EPC contracting; Rooftop Solar infrastructure; Solar Pumps and Electric Vehicle Charging infrastructure

Hydrogen, as well as EV Updates:

EV

Jio-bp And Mahindra & Mahindra Strengthen EV Partnership

Mahindra & Mahindra (M&M) and Jio-bp, a fuel and mobility joint venture between Reliance Industries Limited (RIL) and bp are strengthening their existing partnership with Jio-bp setting up a robust charging network for Mahindra’s upcoming e-SUVs launches. The companies had signed an MoU for exploring the creation of EV products and services, alongside identifying synergies in low-carbon and conventional fuels. Starting with 16 cities, Jio-bp will install DC fast chargers at the M&M dealership network and workshops across the country. M&M launched its first all-electric C segment SUV – the XUV400 at Mahindra Research Valley, Chennai earlier in October 2022

BEL Collaborates With HPCL To Set Up A Fast EV Charging Station

Bharat Electronics Ltd (BEL), in collaboration with Maharatna PSU Hindustan Petroleum Corporation Ltd (HPCL), has set up a fast Electric Vehicle (EV) charging station at the HPCL Retail Outlet at Amravati Enclave near Pinjore on the Chandigarh-Shimla Highway to promote the Government of India’s Green Energy drive. The charging station has two guns of 25 KW each of CCS-2 protocol. BEL has indigenously developed EV Slow and Fast Chargers, in addition to creating EV charging infrastructure in cities and highways

Hero Electric Set to Partner With Jio-bp For 2-wheeler EV Adoption

Hero Electric is set to partner with Jio-bp to strengthen mobility solutions for electric two-wheelers Under this proposed partnership, the customers of Hero Electric are expected to get access to the widespread charging and swapping network of Jio-bp, which is also open to other vehicles. Jio-bp is operating its EV charging and swapping stations under the brand Jio-bp pulse.

Tata Motors Wins Order Of 921 Electric Buses From BMTC

Tata Motors announced that the company has won an order of 921 electric buses from Bengaluru Metropolitan Transport Corporation (BMTC) Under the larger tender by Convergence Energy Services Limited (CESL), Tata Motors will supply, operate and maintain 12-meter electric buses for 12 years, as per the contract. Tata Starbus is an indigenously developed vehicle with superior design and best-in-class features designed for sustainable and comfortable travel.

Chandigarh's EV Policy Seeks To Have 70% Of All Vehicles Be Electric By 2027

In the next five years, Chandigarh wants to see 70% of all new vehicles registered in the Union Territory (UT) be electric vehicles According to the recently released Chandigarh Electric Car Policy 2022, the UT aspires to become a "Model EV City" by having one of the highest rates of zero-emission vehicle penetration among all Indian cities. Chandigarh wants to encourage the use of electric bicycles as an alternative to two and four-wheelers, especially for short trips, by utilizing the city's infrastructure for cycling lanes. To charge EVs, the UT also plans to capture renewable energy sources

Hydrogen

NTPC, MHI, And MPI Sign MoU For Demonstrating Hydrogen co-firing In Auraiya Gas Power Plant

NTPC signed an MoU with Mitsubishi Heavy Industries Ltd , Japan, and its subsidiary Mitsubishi Power India Private Limited to demonstrate the feasibility of Hydrogen co-firing blended with natural gas in MHI 701D gas turbines installed at NTPC Auraiya Gas Power Plant in Uttar Pradesh. The total installed capacity of the Auraiya Gas Power Plant is 663 MW with four gas turbines operating in combined cycle mode. Under this MoU, both companies will collaborate to carry out the study and identify key actions for introducing hydrogen co-firing at NTPC Auraiya Gas-based combined cycle power plant The study will identify key actions for co-firing for various percentages of hydrogen e g , 5%, 15%, 30%, 50%, and 100%, and the hydrogen required for the project will be supplied by NTPC.

POSCO, Greenko Partner On Green Hydrogen And Ammonia Production In India

Posco Holdings, one of the leading Korean steelmakers, and Greenkco subsidiary ZeroC have entered into a strategic partnership for producing Green Hydrogen, Ammonia, and related derivatives in India for both the domestic and export markets The partnership will also jointly develop solar and wind power using Greenko’s pumped hydro storage platform, and Energy Storage Cloud This will supply continuous renewable power to the Green Ammonia plants and take advantage of Posco’s hydrogen and ammonia expertise

Avaada

Group

Inks

MoU For ₹40,000 Crore Green Ammonia Plant In Rajasthan

The MoU was signed as part of the investment promotion strategy for the “Investment Rajasthan Summit” in New Delhi. It proposes an investment of ₹40,000 crores and provides direct employment opportunities for about 3,500 people. In addition, it offers indirect jobs to more than 10,500 people. The green energy transition is vital to the country’s Atmanirbharta and will pave the way toward net-zero goals Aligning with the nation’s vision of self-reliance, at Avaada, we aim to make India energy independent by focusing on green energy security, said V Mittal of Avaada ”

L&T Sets Up Green Hydrogen Plant At Hazira

L&T commissioned its first green hydrogen plant at its complex in Gujarat, and is in talks with a dozen companies for setting up similar units, a company official said. As part of its Environmental Social Governance (ESG) commitments, L&T is planning to achieve water neutrality by 2035 and carbon neutrality by 2040, making green hydrogen an integral part of its clean fuel adoption policy

Jakson Green To Develop US$ 2.8 Billion Green Ammonia and Green Hydrogen Project In Rajasthan

Jakson Green (Jakson Group) has signed MOU with the Government of Rajasthan to invest about ₹22,400 Crore i h d h k ll

p
G
3
e
c Conclusion & Sug I t w I a t s s s I f s p

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.