Scheduling project - Construction planning & Scheduling

Page 1


CAE 471: Primavera Schedule Project Spring Semester 2014 Team Olu Oluduro Charles Massaro Thomas Lagarde Lazar Sretkovic Project Plan and Summary of Project This narrative focuses on the overall approach and project plan for the Northampton Community College located at the junction of Route 715 and Railroad Avenue in Tannersville, Monroe County, Pennsylvania. The project plan was to simultaneously develop and construct the three new campus buildings with a clear and concise explanation of the activity report sorted by Total Float and Early Start (TF-ES). Included were the activity id, description, early dates, late dates, original duration, and total float. Defining the Project Milestones Milestones are the key events or significant points in time during the life of the project. We have arranged them in this order: • Project Start Milestones (Temporary Construction) o Installation of the General Contractor and subcontractors’ staging area o Installation of all temporary heating and/or cooling systems for on-site personnel •

Project Start Milestones (Site work) o Preparation of the Construction entrance to the site o Installation of the Sediment Basins o Installation of all the additional Staging areas o Installation of the Storm sewer water system o Installation of temporary water to contractor staging area o Installation of all Site utilities o Installation of final paving for parking lots and drives o Installation of walkway surfaces, pavements and all landscaping

Substantial Completion Milestones (Building Envelope Construction) o Construction complete for sub-grade of Building pad o Construction complete for concrete foundations o Construction complete for mechanical and plumbing contractor underground rough In o Construction complete for structural steel o Construction complete for electrical contractor underground rough In o Construction complete for concrete slab on grade o Construction complete for exterior envelope o Construction complete (including checks) for building to be water tight

Substantial Completion Milestones (Building Finishes) o Construction and installations complete for interior partitions and MEP Rough Ins o Construction and installations complete for wall rough Ins and inspections o Construction and installations complete for MEP Above-ceilings rough Ins o Construction complete for all interior wall finishes and trims o Installations complete for all ceiling grids o Installations complete for all finished ceilings o Installations and energizing the main permanent electricity


Final Completion Milestone (including Close-Outs and Warranties) o Commissioning and start-up of all equipment and systems o Construction complete for all remaining construction activities o Obtaining the certificate of occupancy, punch list preparation and project completion

Calendars used in the schedule • • • •

Five day and Seven day calendars were used in the schedule In addition, as instructed in class, no activity was longer than 20 days (or longer than 1 month) Normal workday involves an 8-hour shift, Monday through Friday excluding major holidays Pre-construction, bidding, permits and submittals were given a separate calendar because they are in Volume 1 of the project

Constraints and their basis • • • • •

One of the important constraints in the project were the milestones, many of which had to be completed before a major step in the construction process could proceed The next set of constrains were the sequential orders in which the contractors and their respective crews were allowed to complete their schedules. For instance, the electrical contractor could not begin his activities until the HVAC/mechanical contractors had finished their work; who in turn could only have completed their work after the Plumbing contractor was done. Volume 1 needed to be separate because it consisted mainly of bidding, general requirements and contract requirements Additional constraints were the orders in which the project evolved o Temporary construction o Site work o Building shell and envelope construction o Building finishes o Building closeouts and warranties

List of Assumptions • All open-ended relationships were closed • All activities had predecessors and successors • Site layout begins at start of project with site procurement • Work is all year round – Weatherchannel.com shows all the weather averages for Pennsylvania • Critical path was highlighted in the report • Total Float, Free float, Early Start and Late start dates were assumed by the Primavera software • Typical schedule system was assumed to be used for the entirety of the project. These include o Mobilizing and delivery of stock materials o Clearing and Grubbing o Grading for Road o Finishing the grade o Erection of Prefab and structural systems o Landscaping o Paving the roadways and commissioning of power equipment o Final inspection, close outs and clean up


Work Breakdown Structure (WBS) The Work Breakdown Structure that was used in this scheduling planning was to consolidate and encompasses the entire project at Level 1 and then subsequently subdivide the project into four separate descending groups as follows: The three buildings, then the various volumes (as designated in Addendum 1of the official documents), then the Divisions and lastly, the activities WBS Level 1

Title Project

Description Designated as “Monroe Campus” This is the title for the project This level subdivides the main bulk of the scheduling project into each of the three main buildings

2

Building

3

Volume

This level subdivides each of the three buildings into the volumes as described in Addendum 1 of the official documents. Although there are actually four volumes listed in the Addendum, Volume 1 was mainly about the bidding and pre-submittal stage of the project.

4

Division

This level subdivides each of the three main volumes into their divisions. In this manner, all the major work elements are listed by divisions so that the WBS is coherent with the development design explained in the Addendum.

5

Activities

This level subdivides each of the divisions into the specific activities and work items that are within the project. Also included are the successors and predecessors; with all milestones adequately projected on the activities chart.

Resources included in the schedule • • • •

Official cost estimating wages for the state of Pennsylvania was referred to in order to get a basic understanding of the salaries, fringe benefits and average crew sizes for the project. The various crews (steel structure crews, electrical crews, MEP crews, carpenters and scaffolding teams) were all staggered and scheduled consecutively across all three buildings. Equipment resources used included three cranes (one for each building) Power resources included additional temporary on-site power generators which also had to be refueled with diesel (delivery of the diesel was scheduled on a monthly basis)


5 days calendar 8 hours/day


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

MONROE CAMPUS A7080

Install all site utilties

02-Apr-14*

09-Jul-14

27-Mar-14

02-Jul-14

-5

A8670

S86, S96, T77

A7090

Metal stairs

25-Aug-15*

01-Sep-15

25-Aug-15

01-Sep-15

0

A8820, ST944

A7100, A7700

A7100

Install railings

01-Sep-15*

07-Sep-15

01-Sep-15

07-Sep-15

0

A7090

A7110

A7110

Interior H.M frames

07-Sep-15*

24-Sep-15

07-Sep-15

24-Sep-15

0

A7100

A7120

A7120

Drywall and spackliing

24-Sep-15*

07-Oct-15

24-Sep-15

07-Oct-15

0

A7110

A7130

A7130

Caulking

07-Oct-15*

14-Oct-15

07-Oct-15

14-Oct-15

0

A7120

A7140

A7140

Ceramic and porcelain wall/floor tiles

14-Oct-15*

23-Oct-15

14-Oct-15

23-Oct-15

0

A7130

A7150

A7150

Painting

23-Oct-15*

05-Nov-15

23-Oct-15

05-Nov-15

0

A7140

A7160

A7160

Wall coverings

05-Nov-15*

16-Nov-15

05-Nov-15

16-Nov-15

0

A7150

A7170

A7170

Acoustical ceiling grid

16-Nov-15*

25-Nov-15

16-Nov-15

25-Nov-15

0

A7160

A7180

A7180

PC AG san/rw

25-Nov-15*

09-Dec-15

25-Nov-15

09-Dec-15

0

A7170

A7190

A7190

PC overhead pipe

09-Dec-15*

23-Dec-15

09-Dec-15

23-Dec-15

0

A7180

A9430

A7200

PC insulation

24-Dec-15*

31-Dec-15

24-Dec-15

31-Dec-15

0

A9430

A7210

A7210

PC drop sprinkler head

31-Dec-15*

14-Jan-16

31-Dec-15

14-Jan-16

0

A7200

A7220

A7220

PC casework fixtures

14-Jan-16*

21-Jan-16

14-Jan-16

21-Jan-16

0

A7210

A7230

A7230

PC toilet fixtures

21-Jan-16*

28-Jan-16

21-Jan-16

28-Jan-16

0

A7220

A7240

A7240

PC kitchen equipment hookups

28-Jan-16*

05-Feb-16

28-Jan-16

05-Feb-16

0

A7230

A7250

A7250

HC hangers

05-Feb-16*

12-Feb-16

05-Feb-16

12-Feb-16

0

A7240

A7260

A7260

HC pipe install

12-Feb-16*

23-Feb-16

12-Feb-16

23-Feb-16

0

A7250

A7270

A7270

HC duct install

23-Feb-16*

01-Mar-16

23-Feb-16

01-Mar-16

0

A7260

A7280

A7280

HC ATC rough-in

01-Mar-16*

16-Mar-16

01-Mar-16

16-Mar-16

0

A7270

A7290

A7290

HC GRD install

16-Mar-16*

05-Apr-16

16-Mar-16

05-Apr-16

0

A7280

A7300

A7300

HC equipment and final connections

05-Apr-16*

21-Apr-16

05-Apr-16

21-Apr-16

0

A7290

A7310

A7310

HC kitchen equipment and hookups

21-Apr-16*

05-May-16

21-Apr-16

05-May-16

0

A7300

A7320

A7320

EC rough-in walls

05-May-16*

23-May-16

05-May-16

23-May-16

0

A7310

A7330

A7330

EC overhead rough-in

23-May-16*

10-Jun-16

23-May-16

10-Jun-16

0

A7320

A7340

A7340

EC cable tray

10-Jun-16*

30-Jun-16

10-Jun-16

30-Jun-16

0

A7330

A7350

A7350

EC wiring

30-Jun-16*

13-Jul-16

30-Jun-16

13-Jul-16

0

A7340

A7360

A7360

EC light fixtures

13-Jul-16*

25-Jul-16

13-Jul-16

25-Jul-16

0

A7350

A7370

A7370

EC wring devices

25-Jul-16*

01-Aug-16

25-Jul-16

01-Aug-16

0

A7360

A7380

A7380

EC fire alarm and security

01-Aug-16*

09-Aug-16

01-Aug-16

09-Aug-16

0

A7370

A7390

A7390

EC kitchen equipment and hookups

09-Aug-16*

23-Aug-16

09-Aug-16

23-Aug-16

0

A7380

A7400

A7400

EC hook ups and connections

23-Aug-16*

30-Aug-16

23-Aug-16

30-Aug-16

0

A7390

A7410

A7410

Casework/millwork

30-Aug-16*

09-Sep-16

30-Aug-16

09-Sep-16

0

A7400

A7420

A7420

Resilent tile base and floor

09-Sep-16*

21-Sep-16

09-Sep-16

21-Sep-16

0

A7410

A7430

A7430

Seamless vinyl flooring

21-Sep-16*

03-Oct-16

21-Sep-16

03-Oct-16

0

A7420

A7440

A7440

Carpet tiles

03-Oct-16*

18-Oct-16

03-Oct-16

18-Oct-16

0

A7430

A7450

A7450

Install rubber stairs, treads and landings

18-Oct-16*

27-Oct-16

18-Oct-16

27-Oct-16

0

A7440

A7460

A7460

Doors and Hardware

27-Oct-16*

04-Nov-16

27-Oct-16

04-Nov-16

0

A7450

A7470

A7470

Interior glass partitions

04-Nov-16*

16-Nov-16

04-Nov-16

16-Nov-16

0

A7460

A7480

A7480

Wood wall panels

16-Nov-16*

23-Nov-16

16-Nov-16

23-Nov-16

0

A7470

A7490

A7490

Visual display surfaces

23-Nov-16*

30-Nov-16

23-Nov-16

30-Nov-16

0

A7480

A7500

A7500

Signage

30-Nov-16*

07-Dec-16

30-Nov-16

07-Dec-16

0

A7490

A7510

A7510

Wood ceiling

07-Dec-16*

12-Dec-16

07-Dec-16

12-Dec-16

0

A7500

A7520

A7520

Place Acoustical ceiling tiles

12-Dec-16*

26-Dec-16

12-Dec-16

26-Dec-16

0

A7510

A7530

A7530

Tiolet complartments

26-Dec-16*

05-Jan-17

26-Dec-16

05-Jan-17

0

A7520

A7540

A7540

Fire protection specialities

05-Jan-17*

13-Jan-17

05-Jan-17

13-Jan-17

0

A7530

A7560

Footer 1

Page 1 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A7550

Motorized projection screens

21-Jun-17*

04-Jul-17

21-Jun-17

04-Jul-17

0

A7600

A7560

Window shades

13-Jan-17*

27-Jan-17

13-Jan-17

27-Jan-17

0

A7540

A7570

A7570

Wire mesh partitions

27-Jan-17*

07-Feb-17

27-Jan-17

07-Feb-17

0

A7560

A7580

A7580

Install lockers

07-Feb-17*

24-Feb-17

07-Feb-17

24-Feb-17

0

A7570

A7590

A7590

Install hood and walk-ins

24-Feb-17*

09-Mar-17

24-Feb-17

09-Mar-17

0

A7580

A7610

A7600

Install kitchen tiles

07-Jun-17*

21-Jun-17

07-Jun-17

21-Jun-17

0

A7690

A7550

A7610

Install and setup food service equipment

09-Mar-17*

16-Mar-17

09-Mar-17

16-Mar-17

0

A7590

A7620

A7620

Glass wall folding partition

16-Mar-17*

23-Mar-17

16-Mar-17

23-Mar-17

0

A7610

A7630

A7630

Loading dock equipment

23-Mar-17*

10-Apr-17

23-Mar-17

10-Apr-17

0

A7620

A7640

A7640

Paint gym ceiling

10-Apr-17*

17-Apr-17

10-Apr-17

17-Apr-17

0

A7630

A7650

A7650

Gym equipment

17-Apr-17*

26-Apr-17

17-Apr-17

26-Apr-17

0

A7640

A7660

A7660

Gym dividers

26-Apr-17*

09-May-17

26-Apr-17

09-May-17

0

A7650

A7670

A7670

Install hardwood flooring

09-May-17*

18-May-17

09-May-17

18-May-17

0

A7660

A7680

A7680

Install collapsable belachers

18-May-17*

26-May-17

18-May-17

26-May-17

0

A7670

A7690

A7690

Hydraulic elevators

26-May-17*

07-Jun-17

26-May-17

07-Jun-17

0

A7680

A7600, A8710

A7700

Metal stairs

09-Nov-15*

16-Nov-15

09-Nov-15

16-Nov-15

0

ST734, A7090

A7710

A7710

Install railings

16-Nov-15*

20-Nov-15

16-Nov-15

20-Nov-15

0

A7700

A7720

A7720

Interior H.M frames

20-Nov-15*

09-Dec-15

20-Nov-15

09-Dec-15

0

A7710

A7730

A7730

Drywall and spackliing

09-Dec-15*

22-Dec-15

09-Dec-15

22-Dec-15

0

A7720

A7740

A7740

Caulking

22-Dec-15*

29-Dec-15

22-Dec-15

29-Dec-15

0

A7730

A7750

A7750

Ceramic and porcelain wall/floor tiles

29-Dec-15*

07-Jan-16

29-Dec-15

07-Jan-16

0

A7740

A7760

A7760

Painting

07-Jan-16*

20-Jan-16

07-Jan-16

20-Jan-16

0

A7750

A7770

A7770

Wall coverings

20-Jan-16*

29-Jan-16

20-Jan-16

29-Jan-16

0

A7760

A7780

A7780

Acoustical ceiling grid

29-Jan-16*

09-Feb-16

29-Jan-16

09-Feb-16

0

A7770

A7790

A7790

PC AG san/rw

09-Feb-16*

23-Feb-16

09-Feb-16

23-Feb-16

0

A7780

A7800

A7800

PC overhead pipe

23-Feb-16*

08-Mar-16

23-Feb-16

08-Mar-16

0

A7790

A7810

A7810

PC insulation

08-Mar-16*

15-Mar-16

08-Mar-16

15-Mar-16

0

A7800

A7820

A7820

PC drop sprinkler head

15-Mar-16*

29-Mar-16

15-Mar-16

29-Mar-16

0

A7810

A7830

A7830

PC casework fixtures

29-Mar-16*

05-Apr-16

29-Mar-16

05-Apr-16

0

A7820

A7840

A7840

PC toilet fixtures

05-Apr-16*

12-Apr-16

05-Apr-16

12-Apr-16

0

A7830

A7850

A7850

PC kitchen equipment hookups

12-Apr-16*

20-Apr-16

12-Apr-16

20-Apr-16

0

A7840

A7860

A7860

HC hangers

20-Apr-16*

27-Apr-16

20-Apr-16

27-Apr-16

0

A7850

A7870

A7870

HC pipe install

27-Apr-16*

06-May-16

27-Apr-16

06-May-16

0

A7860

A7880

A7880

HC duct install

06-May-16*

13-May-16

06-May-16

13-May-16

0

A7870

A7890

A7890

HC ATC rough-in

13-May-16*

30-May-16

13-May-16

30-May-16

0

A7880

A7900

A7900

HC GRD install

30-May-16*

17-Jun-16

30-May-16

17-Jun-16

0

A7890

A7910

A7910

HC equipment and final connections

17-Jun-16*

05-Jul-16

17-Jun-16

05-Jul-16

0

A7900

A7920

A7920

HC kitchen equipment and hookups

05-Jul-16*

19-Jul-16

05-Jul-16

19-Jul-16

0

A7910

A7930

A7930

EC rough-in walls

19-Jul-16*

04-Aug-16

19-Jul-16

04-Aug-16

0

A7920

A7940

A7940

EC overhead rough-in

04-Aug-16*

24-Aug-16

04-Aug-16

24-Aug-16

0

A7930

A7950

A7950

EC cable tray

24-Aug-16*

13-Sep-16

24-Aug-16

13-Sep-16

0

A7940

A7960

A7960

EC wiring

13-Sep-16*

26-Sep-16

13-Sep-16

26-Sep-16

0

A7950

A7970

A7970

EC light fixtures

26-Sep-16*

06-Oct-16

26-Sep-16

06-Oct-16

0

A7960

A7980

A7980

EC wring devices

06-Oct-16*

13-Oct-16

06-Oct-16

13-Oct-16

0

A7970

A7990

A7990

EC fire alarm and security

13-Oct-16*

21-Oct-16

13-Oct-16

21-Oct-16

0

A7980

A8000

A8000

EC kitchen equipment and hookups

21-Oct-16*

04-Nov-16

21-Oct-16

04-Nov-16

0

A7990

A8010

A8010

EC hook ups and connections

04-Nov-16*

11-Nov-16

04-Nov-16

11-Nov-16

0

A8000

A8020

A8020

Casework/millwork

11-Nov-16*

23-Nov-16

11-Nov-16

23-Nov-16

0

A8010

A8030

A8030

Resilent tile base and floor

23-Nov-16*

05-Dec-16

23-Nov-16

05-Dec-16

0

A8020

A8040

A8040

Seamless vinyl flooring

05-Dec-16*

15-Dec-16

05-Dec-16

15-Dec-16

0

A8030

A8050

Footer 1

Page 2 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A8050

Carpet tiles

15-Dec-16*

30-Dec-16

15-Dec-16

30-Dec-16

0

A8040

A8060

A8060

Install rubber stairs, treads and landings

30-Dec-16*

10-Jan-17

30-Dec-16

10-Jan-17

0

A8050

A8070

A8070

Doors and Hardware

10-Jan-17*

18-Jan-17

10-Jan-17

18-Jan-17

0

A8060

A8080

A8080

Interior glass partitions

18-Jan-17*

30-Jan-17

18-Jan-17

30-Jan-17

0

A8070

A8090

A8090

Wood wall panels

30-Jan-17*

06-Feb-17

30-Jan-17

06-Feb-17

0

A8080

A8100

A8100

Visual display surfaces

06-Feb-17*

13-Feb-17

06-Feb-17

13-Feb-17

0

A8090

A8110

A8110

Signage

13-Feb-17*

20-Feb-17

13-Feb-17

20-Feb-17

0

A8100

A8120

A8120

Wood ceiling

20-Feb-17*

23-Feb-17

20-Feb-17

23-Feb-17

0

A8110

A8130

A8130

Place Acoustical ceiling tiles

23-Feb-17*

09-Mar-17

23-Feb-17

09-Mar-17

0

A8120

A8140

A8140

Tiolet complartments

09-Mar-17*

21-Mar-17

09-Mar-17

21-Mar-17

0

A8130

A8150

A8150

Fire protection specialities

21-Mar-17*

29-Mar-17

21-Mar-17

29-Mar-17

0

A8140

A8170

A8170

Window shades

29-Mar-17*

12-Apr-17

29-Mar-17

12-Apr-17

0

A8150

A8180

A8180

Wire mesh partitions

12-Apr-17*

21-Apr-17

12-Apr-17

21-Apr-17

0

A8170

A8190

A8190

Install lockers

21-Apr-17*

10-May-17

21-Apr-17

10-May-17

0

A8180

A8200

A8200

Observation deck

10-May-17*

23-May-17

10-May-17

23-May-17

0

A8190

A8210

A8210

Install Medical reclined chair

23-May-17*

30-May-17

23-May-17

30-May-17

0

A8200

A8220

A8220

Glass wall folding partition

30-May-17*

06-Jun-17

30-May-17

06-Jun-17

0

A8210

A8230

A8230

Place additional medical equipment

06-Jun-17*

22-Jun-17

06-Jun-17

22-Jun-17

0

A8220

A8240

A8240

Install lecture seating

22-Jun-17*

29-Jun-17

22-Jun-17

29-Jun-17

0

A8230

A8250

A8250

Install Student Desks and chairs

29-Jun-17*

10-Jul-17

29-Jun-17

10-Jul-17

0

A8240

A8260

A8260

Lab Desks

10-Jul-17*

21-Jul-17

10-Jul-17

21-Jul-17

0

A8250

A8270

A8270

Install hardwood flooring

21-Jul-17*

01-Aug-17

21-Jul-17

01-Aug-17

0

A8260

A8280

A8280

Teacher desks

01-Aug-17*

09-Aug-17

01-Aug-17

09-Aug-17

0

A8270

A8290

A8290

Hydraulic elevators

09-Aug-17*

21-Aug-17

09-Aug-17

21-Aug-17

0

A8280

A8780, A8700

A8300

Prevailing wage documents

26-Feb-14

10-Mar-14

26-Feb-14

10-Mar-14

0

A8610

A8310

Bid security

01-Apr-14

16-Apr-14

01-Apr-14

16-Apr-14

0

A8390

A8320

Electrical Construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8610

A8330

Plumbing construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8610

A8340

Hvac construction bid

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8610

A8350

General construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8610

A8360

Geotechnical investigation

10-Oct-13

27-Jan-14

03-Oct-13

21-Jan-14

-5

A8370

Instruction to bidders

26-Feb-14

14-Mar-14

26-Feb-14

14-Mar-14

0

A8390

A8380

Qualification questionnaire

26-Feb-14

05-Mar-14

26-Feb-14

05-Mar-14

0

A8390

A8390

invitation to bid

26-Feb-14

01-Apr-14

19-Feb-14

25-Mar-14

-5

A8610

A8400

Execution

02-Apr-14

07-Feb-18

02-Apr-14

07-Feb-18

0

A8670, A8780

A8410

Product requirements

01-Apr-14

26-May-14

01-Apr-14

26-May-14

0

A8390

A8420

Temporary Facilities & controls

02-Apr-14

16-Nov-17

02-Apr-14

16-Nov-17

0

A8670, A8780

A8430

References

02-May-14

22-May-14

02-May-14

22-May-14

0

A8600

A8440

Quality requirements

02-May-14

10-Jul-14

02-May-14

10-Jul-14

0

A8600

A8450

Alteration Project procedures

10-Oct-13

15-Oct-13

10-Oct-13

15-Oct-13

0

A8610, A8570

A8460

LEED submital Form

06-Nov-13

30-Dec-13

06-Nov-13

30-Dec-13

0

A8730, A8740

A8470

Submittal form

02-May-14

08-Jul-14

02-May-14

08-Jul-14

0

A8390, A8600

A8480

Construction Progress documentation

02-Apr-14

14-Dec-17

02-Apr-14

14-Dec-17

0

A8670, A8780

A8490

Web based project management

02-Apr-14

30-Nov-17

02-Apr-14

30-Nov-17

0

A8670, A8780

A8500

Coordination drawings

28-Jan-14

20-Feb-14

24-Mar-14

16-Apr-14

39

A8610

A8510

Project Management & coordination

02-Apr-14

25-Jan-18

02-Apr-14

25-Jan-18

0

A8670, A8780

A8520

Payement procedures

02-Apr-14

12-Feb-18

02-Apr-14

12-Feb-18

0

A8670

Footer 1

Page 3 of 8

A8600

A8380, A8370, A8310, A8680, A8620, A8650, A8660, A8630, A8670, A8470, A8550, A8410

A8600


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A8530

Contract Modification

10-Oct-13

19-Dec-13

10-Oct-13

19-Dec-13

A8540

Alternates

02-May-14

21-May-14

02-May-14

21-May-14

0 0

A8600

A8550

Unit prices

01-Apr-14

02-Jun-14

01-Apr-14

02-Jun-14

0

A8390

A8560

Quantity allowances

02-May-14

09-Jun-14

02-May-14

09-Jun-14

0

A8600

A8570

Field engineering

28-Jan-14

10-Feb-14

28-Jan-14

10-Feb-14

0

A8360

A8580

Work restrictions

02-May-14

07-Jul-14

02-May-14

07-Jul-14

0

A8600

A8590

Summary of multiple contracts

02-May-14

12-May-14

02-May-14

12-May-14

0

A8600

A8600

Summary

16-Apr-14

02-May-14

16-Apr-14

02-May-14

0

A8500, A8310

A8690, A8540, A8440, A8590, A8560, A8430, A8580, A8470

A8610

List of drawings

28-Jan-14

25-Feb-14

21-Jan-14

19-Feb-14

-5

A8360

A8340, A8350, A8320, A8330, A8500, A8390, A8300, A8640

A8620

Safety and health management plan

01-Apr-14

07-Apr-14

01-Apr-14

07-Apr-14

0

A8390

A8630

Standard General conditions

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8390

A8640

Sample Insurance certificates

26-Feb-14

04-Mar-14

26-Feb-14

04-Mar-14

0

A8610

A8650

Payment bond

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8390

A8660

Performance bond

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8390

A8670

AIA document a132

01-Apr-14

02-Apr-14

26-Mar-14

26-Mar-14

-5

A8390

A8760, A8790, A8770, A8400, A8510, A8420, A8750, A8480, A8490, A8520, A7080, A8970

A8680

Non collusion affidavit

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8390

A8690

General Commissioning requirements

02-May-14

09-May-14

02-May-14

09-May-14

0

A8600

A8700

Checklist classroom roe

21-Aug-17

01-Sep-17

21-Aug-17

01-Sep-17

0

A8290

A8780

A8710

Checklist student life building

07-Jun-17

20-Jun-17

21-Aug-17

01-Sep-17

53

A7690

A8780

A8720

Checklist enrollment building

24-Jan-17

06-Feb-17

21-Aug-17

01-Sep-17

149

A9420

A8780

A8730

Leed & sustainable design requirements

10-Oct-13

18-Oct-13

28-Oct-13

05-Nov-13

12

A8740

Testing for indoor air quality

10-Oct-13

05-Nov-13

10-Oct-13

05-Nov-13

0

A8750

Demonstration & training

02-Apr-14

08-Jul-15

02-Apr-14

08-Jul-15

0

A8670

A8760

Project record documents

12-Feb-15

01-Sep-17

12-Feb-15

01-Sep-17

0

A8670, A8780

A8770

Operation and maintenance data

02-Jun-14

01-Sep-17

02-Jun-14

01-Sep-17

0

A8670, A8780

A8780

Close out procedures

01-Sep-17

21-Dec-17

01-Sep-17

21-Dec-17

0

A8790, A8290, A8720, A8710, A8700

A9440, A8810, A8770, A8760, A8510, A8490, A8480, A8420, A8400

A8790

Construction waste mangement

02-Apr-14

31-Jul-17

06-May-14

01-Sep-17

24

A8670

A8780

A8800

Cutting and patching

10-Oct-13

07-Nov-13

10-Oct-13

07-Nov-13

0

A8810

Demobilize job trailers

01-Sep-17

07-May-18

01-Sep-17

07-May-18

0

A8780

A9440

A8820

Metal stairs

22-Apr-15*

29-Apr-15

22-Apr-15

29-Apr-15

0

ST1084

A8830, A7090

A8830

Install railings

29-Apr-15*

05-May-15

29-Apr-15

05-May-15

0

A8820

A8840

A8840

Interior H.M frames

05-May-15*

22-May-15

05-May-15

22-May-15

0

A8830

A8850

A8850

Drywall and spackliing

22-May-15*

04-Jun-15

22-May-15

04-Jun-15

0

A8840

A8860

A8860

Caulking

04-Jun-15*

11-Jun-15

04-Jun-15

11-Jun-15

0

A8850

A8870

A8870

Ceramic and porcelain wall/floor tiles

11-Jun-15*

22-Jun-15

11-Jun-15

22-Jun-15

0

A8860

A8880

A8880

Painting

22-Jun-15*

03-Jul-15

22-Jun-15

03-Jul-15

0

A8870

A8890

A8890

Wall coverings

03-Jul-15*

14-Jul-15

03-Jul-15

14-Jul-15

0

A8880

A8900

A8900

Acoustical ceiling grid

14-Jul-15*

23-Jul-15

14-Jul-15

23-Jul-15

0

A8890

A8910

A8910

PC AG san/rw

23-Jul-15*

06-Aug-15

23-Jul-15

06-Aug-15

0

A8900

A8920

A8920

PC overhead pipe

06-Aug-15*

20-Aug-15

06-Aug-15

20-Aug-15

0

A8910

A8930

A8930

PC insulation

20-Aug-15*

27-Aug-15

20-Aug-15

27-Aug-15

0

A8920

A8940

Footer 1

Page 4 of 8

A8460 A8460


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

A8940

PC drop sprinkler head

27-Aug-15*

10-Sep-15

27-Aug-15

10-Sep-15

0

A8930

A8950

A8950

PC casework fixtures

10-Sep-15*

17-Sep-15

10-Sep-15

17-Sep-15

0

A8940

A8960

A8960

PC toilet fixtures

17-Sep-15*

24-Sep-15

17-Sep-15

24-Sep-15

0

A8950

A8980

A8970

Start milestone

02-Apr-14*

03-Apr-14

02-Apr-14

03-Apr-14

0

A8670

S86

A8980

HC hangers

24-Sep-15*

01-Oct-15

24-Sep-15

01-Oct-15

0

A8960

A8990

A8990

HC pipe install

01-Oct-15*

12-Oct-15

01-Oct-15

12-Oct-15

0

A8980

A9000

A9000

HC duct install

12-Oct-15*

19-Oct-15

12-Oct-15

19-Oct-15

0

A8990

A9010

A9010

HC ATC rough-in

19-Oct-15*

03-Nov-15

19-Oct-15

03-Nov-15

0

A9000

A9020

A9020

HC GRD install

03-Nov-15*

23-Nov-15

03-Nov-15

23-Nov-15

0

A9010

A9030

A9030

HC equipment and final connections

23-Nov-15*

09-Dec-15

23-Nov-15

09-Dec-15

0

A9020

A9040

A9040

HC kitchen equipment and hookups

09-Dec-15*

23-Dec-15

09-Dec-15

23-Dec-15

0

A9030

A9050

A9050

EC rough-in walls

23-Dec-15*

08-Jan-16

23-Dec-15

08-Jan-16

0

A9040

A9060

A9060

EC overhead rough-in

08-Jan-16*

28-Jan-16

08-Jan-16

28-Jan-16

0

A9050

A9070

A9070

EC cable tray

28-Jan-16*

17-Feb-16

28-Jan-16

17-Feb-16

0

A9060

A9080

A9080

EC wiring

17-Feb-16*

01-Mar-16

17-Feb-16

01-Mar-16

0

A9070

A9090

A9090

EC light fixtures

01-Mar-16*

11-Mar-16

01-Mar-16

11-Mar-16

0

A9080

A9100

A9100

EC wring devices

11-Mar-16*

18-Mar-16

11-Mar-16

18-Mar-16

0

A9090

A9110

A9110

EC fire alarm and security

18-Mar-16*

28-Mar-16

18-Mar-16

28-Mar-16

0

A9100

A9120

A9120

EC kitchen equipment and hookups

28-Mar-16*

11-Apr-16

28-Mar-16

11-Apr-16

0

A9110

A9130

A9130

EC hook ups and connections

11-Apr-16*

18-Apr-16

11-Apr-16

18-Apr-16

0

A9120

A9140

A9140

Casework/millwork

18-Apr-16*

28-Apr-16

18-Apr-16

28-Apr-16

0

A9130

A9150

A9150

Resilent tile base and floor

28-Apr-16*

10-May-16

28-Apr-16

10-May-16

0

A9140

A9160

A9160

Seamless vinyl flooring

10-May-16*

20-May-16

10-May-16

20-May-16

0

A9150

A9170

A9170

Carpet tiles

20-May-16*

06-Jun-16

20-May-16

06-Jun-16

0

A9160

A9180

A9180

Install rubber stairs, treads and landings

06-Jun-16*

15-Jun-16

06-Jun-16

15-Jun-16

0

A9170

A9190

A9190

Doors and Hardware

15-Jun-16*

23-Jun-16

15-Jun-16

23-Jun-16

0

A9180

A9200

A9200

Interior glass partitions

23-Jun-16*

05-Jul-16

23-Jun-16

05-Jul-16

0

A9190

A9210

A9210

Wood wall panels

05-Jul-16*

12-Jul-16

05-Jul-16

12-Jul-16

0

A9200

A9220

A9220

Visual display surfaces

12-Jul-16*

19-Jul-16

12-Jul-16

19-Jul-16

0

A9210

A9230

A9230

Signage

19-Jul-16*

26-Jul-16

19-Jul-16

26-Jul-16

0

A9220

A9240

A9240

Wood ceiling

26-Jul-16*

29-Jul-16

26-Jul-16

29-Jul-16

0

A9230

A9250

A9250

Place Acoustical ceiling tiles

29-Jul-16*

12-Aug-16

29-Jul-16

12-Aug-16

0

A9240

A9260

A9260

Tiolet complartments

12-Aug-16*

24-Aug-16

12-Aug-16

24-Aug-16

0

A9250

A9270

A9270

Fire protection specialities

24-Aug-16*

01-Sep-16

24-Aug-16

01-Sep-16

0

A9260

A9290

A9280

Motorized projection screens

07-Feb-17

20-Feb-17

07-Feb-17

20-Feb-17

0

A9330

A9290

Window shades

01-Sep-16*

15-Sep-16

01-Sep-16

15-Sep-16

0

A9270

A9300

A9300

Wire mesh partitions

15-Sep-16*

26-Sep-16

15-Sep-16

26-Sep-16

0

A9290

A9310

A9310

Install lockers

26-Sep-16*

13-Oct-16

26-Sep-16

13-Oct-16

0

A9300

A9320

A9320

Install hood and walk-ins

13-Oct-16*

26-Oct-16

13-Oct-16

26-Oct-16

0

A9310

A9340

A9330

Install kitchen tiles

24-Jan-17

07-Feb-17

24-Jan-17

07-Feb-17

0

A9420

A9280

A9340

Install and setup food service equipment

26-Oct-16*

02-Nov-16

26-Oct-16

02-Nov-16

0

A9320

A9350

A9350

Glass wall folding partition

02-Nov-16*

09-Nov-16

02-Nov-16

09-Nov-16

0

A9340

A9360

A9360

Loading dock equipment

09-Nov-16*

25-Nov-16

09-Nov-16

25-Nov-16

0

A9350

A9370

A9370

Paint gym ceiling

25-Nov-16*

02-Dec-16

25-Nov-16

02-Dec-16

0

A9360

A9380

A9380

Gym equipment

02-Dec-16*

13-Dec-16

02-Dec-16

13-Dec-16

0

A9370

A9390

A9390

Gym dividers

13-Dec-16*

26-Dec-16

13-Dec-16

26-Dec-16

0

A9380

A9400

A9400

Install hardwood flooring

26-Dec-16*

04-Jan-17

26-Dec-16

04-Jan-17

0

A9390

A9410

A9410

Install collapsable belachers

04-Jan-17*

12-Jan-17

04-Jan-17

12-Jan-17

0

A9400

A9420

A9420

Hydraulic elevators

12-Jan-17*

24-Jan-17

12-Jan-17

24-Jan-17

0

A9410

A9330, A8720

A9430

Substantial milestone

23-Dec-15*

24-Dec-15

23-Dec-15

24-Dec-15

0

A7190

A7200

Footer 1

Page 5 of 8

Late Start

Late Finish

Total Float

Predecessors

Successors


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

A9440

Final Milestone

07-May-18*

08-May-18

07-May-18

08-May-18

0

A8780, A8810

S106

Erosion controls

10-Apr-14*

15-May-14

10-Apr-14

15-May-14

0

S86

S116, S206, S136

S116

Site Clearing and Strip Topsoil

15-May-14*

21-Aug-14

15-May-14

21-Aug-14

0

S106

S146, S176

S126

Temporary Basin and Swales

15-May-14*

03-Jul-14

12-Aug-14

29-Sep-14

62

S86

S216

S136

Site grading

15-May-14*

30-Oct-14

15-May-14

30-Oct-14

0

S106

S386

S146

Install Sediment Basin

21-Aug-14*

30-Oct-14

21-Aug-14

30-Oct-14

0

S116, S156

S156

Install Paving binder access roads and staging areas

15-May-14*

12-Jun-14

15-May-14

12-Jun-14

0

S86, S96

S166

Install additional staging areas

24-Jul-14*

03-Sep-14

24-Jul-14

03-Sep-14

0

S156

S176

Electrical ductbank

21-Aug-14*

30-Oct-14

21-Aug-14

30-Oct-14

0

S116

S186

Install Storm Sewer

12-May-14 A

23-Apr-15

15-May-14

23-Apr-15

0

S86

S236, S406

S196

Install Sanitary Sewer

30-Jun-14*

29-Aug-14

11-Aug-15

12-Oct-15

291

S156

S236

S206

Water system

05-May-14 A

17-Oct-14 A

15-May-14

15-May-14

S216

Concrete curbs

25-Aug-14*

09-Jan-15

30-Sep-14

16-Feb-15

26

S126, S226

S376

S226

Site lighting

30-Jun-14*

22-Aug-14

05-Aug-14

29-Sep-14

26

S156

S216, S396

S236

Final Landscaping

13-Oct-15*

21-Dec-15

13-Oct-15

21-Dec-15

0

S186, S196, S276, S326

S416, S316, S336

S246

Place trees and shrubbery

14-May-15*

09-Jul-15

14-May-15

09-Jul-15

0

S386, S396, S376

S256

site linestripping and signage

22-Apr-16*

27-May-16

22-Apr-16

27-May-16

0

S266

S266

Concrete bumper blocks

25-Mar-16*

21-Apr-16

25-Mar-16

21-Apr-16

0

S306, S416

S256

S276

sidewalks and ramp concrete pour

26-May-15*

24-Aug-15

26-May-15

24-Aug-15

0

S296

S236, S346, S326, S366

S286

Unit Pavers

29-Sep-15*

01-Dec-15

30-Sep-15

02-Dec-15

1

S346, S366

S416, S306

S296

Exterior masonry seat walls and site walls

13-Apr-15*

22-May-15

14-Apr-15

25-May-15

1

S376

S276, S356

S306

Exterior site railings

02-Dec-15*

22-Jan-16

03-Dec-15

25-Jan-16

1

S286

S266, S416

S316

Position Site seating

22-Dec-15*

25-Jan-16

22-Dec-15

25-Jan-16

0

S236

S416

S326

Fiberglass bus stations

25-Aug-15*

12-Oct-15

25-Aug-15

12-Oct-15

0

S276

S236

S336

Install flagpoles

02-Apr-14

27-May-16

27-Mar-14

27-May-16

-5

S236

S416

S346

Parking control equipment

25-Aug-15*

28-Sep-15

26-Aug-15

29-Sep-15

1

S276, S356

S286

S356

Retaining wall for landscaping

25-May-15*

19-Jun-15

29-Jul-15

25-Aug-15

47

S296

S346

S366

Timber guide railings

25-Aug-15*

21-Sep-15

02-Sep-15

29-Sep-15

6

S276

S286

S376

Retaining wall

12-Jan-15*

06-Mar-15

17-Feb-15

13-Apr-15

26

S216

S296, S246

S386

Site excavation

30-Oct-14*

14-May-15

30-Oct-14

14-May-15

0

S136

S246

S396

Install new topsoil

25-Aug-14 A

18-Dec-14

26-Mar-15

14-May-15

105

S176, S226

S246

S406

Install Geo Exchange Field

23-Apr-15*

10-Sep-15

23-Apr-15

10-Sep-15

0

S186

T57

S416

Final placement of trees and shrubbery

26-Jan-16*

24-Mar-16

26-Jan-16

24-Mar-16

0

S286, S236, S316, S336, S306

S266

S86

Site Layout

03-Apr-14

15-May-14

03-Apr-14

15-May-14

0

A7080, A8970

S106, S126, S156, S186

S96

Install Rock Construction Entrance

02-Apr-14

23-Apr-14

24-Apr-14

15-May-14

16

A7080

S156

SF25

Layout for foundation

11-Jul-14*

22-Jul-14

11-Jul-14

22-Jul-14

0

SF55

SF35, SF45, ST744

SF35

Footing excavation

19-Aug-14*

21-Oct-14

19-Aug-14

21-Oct-14

0

SF25, SF45

SF45

Tie Rebar

22-Jul-14*

19-Aug-14

22-Jul-14

19-Aug-14

0

SF25

SF35, SF65

SF55

Construct building pad

12-Jun-14*

11-Jul-14

12-Jun-14

11-Jul-14

0

S156

SF25

SF65

Concrete foundation

19-Aug-14*

21-Oct-14

19-Aug-14

21-Oct-14

0

SF45

ST1054, ST1224

ST1004

Deep underground rough-in

18-Nov-14*

09-Dec-14

02-Dec-14

23-Dec-14

10

ST984

ST994

ST1014

Stone under slab rough-in

20-Feb-15

10-Mar-15

20-Feb-15

10-Mar-15

0

ST784, ST1254

ST804, ST774

ST1024

Erect structural steel and deck

23-Dec-14

23-Jan-15

23-Dec-14

23-Jan-15

0

ST1234

ST1074, ST1254

ST1034

Pour concrete slab on deck

03-Mar-15

16-Apr-15

03-Mar-15

16-Apr-15

0

ST1044

ST1064

ST1044

Stone under slab

10-Feb-15

03-Mar-15

10-Feb-15

03-Mar-15

0

ST1234, ST1254

ST1064, ST1054, ST1034

ST1054

CMU walls

07-May-15

04-Jun-15

07-May-15

04-Jun-15

0

ST1064, ST1044, SF65

ST1204, ST1264, ST814

ST1064

Pour concrete slab on grade

16-Apr-15

07-May-15

16-Apr-15

07-May-15

0

ST1044, ST1034

ST1054

Footer 1

Page 6 of 8

Late Start

Late Finish

Total Float

Predecessors

Successors

S196, S226, S146, SF55, S166 S396, T47

S106


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

ST1074

Cold formed metal framing and sheathing

23-Jan-15

27-Feb-15

23-Jan-15

27-Feb-15

0

ST1024

ST1094

ST1084

Spray urethane insulation

25-Mar-15

22-Apr-15

25-Mar-15

22-Apr-15

0

ST1094

ST1104, ST1144, A8820

ST1094

Install air membrane

27-Feb-15

25-Mar-15

27-Feb-15

25-Mar-15

0

ST1074

ST1084

ST1104

Wood blocking & sheathing on roof

22-Apr-15

06-May-15

22-Apr-15

06-May-15

0

ST1084

ST1114, ST1124

ST1114

Roof curbs

06-May-15

15-May-15

12-Jun-15

23-Jun-15

27

ST1104

ST1134

ST1124

Roof Drains

06-May-15

21-May-15

06-May-15

21-May-15

0

ST1104

ST1154

ST1134

Roof top equipment

15-May-15

22-May-15

23-Jun-15

30-Jun-15

27

ST1114

ST1184

ST1144

Insulated metal wall panels

22-Apr-15

20-May-15

30-Jun-15

28-Jul-15

49

ST1084

ST1194

ST1154

Metal soffit and fascia

21-May-15

11-Jun-15

21-May-15

11-Jun-15

0

ST1124

ST1164

ST1164

Roof metal edges

11-Jun-15

30-Jun-15

11-Jun-15

30-Jun-15

0

ST1154

ST1184

ST1174

Exterior Caulking

27-Jul-15

10-Aug-15

28-Jul-15

11-Aug-15

1

ST1204

ST1214

ST1184

Metal roof ladders

30-Jun-15

28-Jul-15

30-Jun-15

28-Jul-15

0

ST1164, ST1134

ST1194

ST1194

Aluminum windows & curtain walls

28-Jul-15

11-Aug-15

28-Jul-15

11-Aug-15

0

ST1144, ST1184

ST1214

ST1204

Masonry veneer

04-Jun-15

27-Jul-15

05-Jun-15

28-Jul-15

1

ST1054

ST1174

ST1214

Aluminum entrance doors/sliding doors

11-Aug-15

15-Sep-15

11-Aug-15

15-Sep-15

0

ST1174, ST1194

ST1224

Plumbing underground sanitary/storm rough-in

21-Oct-14*

04-Nov-14

21-Oct-14

04-Nov-14

0

SF65

ST1234, ST1244, ST984

ST1234

Waterproofing

25-Nov-14*

23-Dec-14

25-Nov-14

23-Dec-14

0

ST1224, ST1244

ST1044, ST1024, ST994

ST1244

Deep underground rough-in

04-Nov-14*

25-Nov-14

04-Nov-14

25-Nov-14

0

ST1224

ST1234

ST1254

Stone under slab rough-in

23-Jan-15

10-Feb-15

23-Jan-15

10-Feb-15

0

ST1024

ST1044, ST1014

ST1264

Layout stone veneer

04-Jun-15

15-Jul-15

04-Jun-15

15-Jul-15

0

ST1054

ST544

Erect structural steel and deck

20-Jan-15

20-Feb-15

16-Feb-15

19-Mar-15

19

ST754

ST594, ST774

ST554

Pour concrete slab on deck

16-Apr-15

01-Jun-15

28-Apr-15

11-Jun-15

8

ST564

ST584

ST564

Stone under slab

26-Mar-15

16-Apr-15

07-Apr-15

28-Apr-15

8

ST754, ST774

ST584, ST574, ST554

ST574

CMU walls

02-Jul-15

30-Jul-15

02-Jul-15

30-Jul-15

0

ST584, ST564, ST814

ST724

ST584

Pour concrete slab on grade

01-Jun-15

22-Jun-15

11-Jun-15

02-Jul-15

8

ST564, ST554

ST574

ST594

Cold formed metal framing and sheathing

20-Feb-15

27-Mar-15

19-Mar-15

23-Apr-15

19

ST544

ST614

ST604

Spray urethane insulation

22-Apr-15

20-May-15

19-May-15

16-Jun-15

19

ST614

ST624, ST664

ST614

Install air membrane

27-Mar-15

22-Apr-15

23-Apr-15

19-May-15

19

ST594

ST604

ST624

Wood blocking & sheathing on roof

20-May-15

03-Jun-15

16-Jun-15

30-Jun-15

19

ST604

ST634, ST644

ST634

Roof curbs

03-Jun-15

12-Jun-15

06-Aug-15

17-Aug-15

46

ST624

ST654

ST644

Roof Drains

03-Jun-15

18-Jun-15

30-Jun-15

15-Jul-15

19

ST624

ST674

ST654

Roof top equipment

12-Jun-15

19-Jun-15

17-Aug-15

24-Aug-15

46

ST634

ST704

ST664

Insulated metal wall panels

20-May-15

17-Jun-15

24-Aug-15

21-Sep-15

68

ST604

ST714

ST674

Metal soffit and fascia

18-Jun-15

09-Jul-15

15-Jul-15

05-Aug-15

19

ST644

ST684

ST684

Roof metal edges

09-Jul-15

28-Jul-15

05-Aug-15

24-Aug-15

19

ST674

ST704

ST694

Exterior Caulking

21-Sep-15

05-Oct-15

21-Sep-15

05-Oct-15

0

ST724

ST734

ST704

Metal roof ladders

28-Jul-15

25-Aug-15

24-Aug-15

21-Sep-15

19

ST684, ST654

ST714

ST714

Aluminum windows & curtain walls

25-Aug-15

08-Sep-15

21-Sep-15

05-Oct-15

19

ST664, ST704

ST734

ST724

Masonry veneer

30-Jul-15

21-Sep-15

30-Jul-15

21-Sep-15

0

ST574

ST694

ST734

Aluminum entrance doors/sliding doors

05-Oct-15

09-Nov-15

05-Oct-15

09-Nov-15

0

ST694, ST714

A7700 ST754, ST764

ST744

Plumbing underground sanitary/storm rough-in

18-Nov-14*

02-Dec-14

15-Dec-14

29-Dec-14

19

SF25, ST984

ST754

Waterproofing

23-Dec-14*

20-Jan-15

19-Jan-15

16-Feb-15

19

ST744, ST764

ST564, ST544

ST764

Deep underground rough-in

02-Dec-14*

23-Dec-14

29-Dec-14

19-Jan-15

19

ST744

ST754

ST774

Stone under slab rough-in

10-Mar-15

26-Mar-15

20-Mar-15

07-Apr-15

8

ST544, ST1014

ST564

ST784

Erect structural steel and deck

20-Jan-15

20-Feb-15

20-Jan-15

20-Feb-15

0

ST994

ST834, ST1014

ST794

Pour concrete slab on deck

31-Mar-15

14-May-15

31-Mar-15

14-May-15

0

ST804

ST824

ST804

Stone under slab

10-Mar-15

31-Mar-15

10-Mar-15

31-Mar-15

0

ST994, ST1014

ST824, ST814, ST794

ST814

CMU walls

04-Jun-15

02-Jul-15

04-Jun-15

02-Jul-15

0

ST824, ST804, ST1054

ST964, ST574

Footer 1

Page 7 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:51

Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

ST824

Pour concrete slab on grade

14-May-15

04-Jun-15

14-May-15

04-Jun-15

0

ST804, ST794

ST814

ST834

Cold formed metal framing and sheathing

20-Feb-15

27-Mar-15

20-Feb-15

27-Mar-15

0

ST784

ST854

ST844

Spray urethane insulation

22-Apr-15

20-May-15

22-Apr-15

20-May-15

0

ST854

ST864, ST904

ST854

Install air membrane

27-Mar-15

22-Apr-15

27-Mar-15

22-Apr-15

0

ST834

ST844

ST864

Wood blocking & sheathing on roof

20-May-15

03-Jun-15

20-May-15

03-Jun-15

0

ST844

ST874, ST884

ST874

Roof curbs

03-Jun-15

12-Jun-15

10-Jul-15

21-Jul-15

27

ST864

ST894

ST884

Roof Drains

03-Jun-15

18-Jun-15

03-Jun-15

18-Jun-15

0

ST864

ST914

ST894

Roof top equipment

12-Jun-15

19-Jun-15

21-Jul-15

28-Jul-15

27

ST874

ST944

ST904

Insulated metal wall panels

20-May-15

17-Jun-15

28-Jul-15

25-Aug-15

49

ST844

ST954 ST924

ST914

Metal soffit and fascia

18-Jun-15

09-Jul-15

18-Jun-15

09-Jul-15

0

ST884

ST924

Roof metal edges

09-Jul-15

28-Jul-15

09-Jul-15

28-Jul-15

0

ST914

ST944

ST934

Exterior Caulking

24-Aug-15

07-Sep-15

25-Aug-15

08-Sep-15

1

ST964

ST974

ST944

Metal roof ladders

28-Jul-15

25-Aug-15

28-Jul-15

25-Aug-15

0

ST924, ST894

ST954, A7090

ST954

Aluminum windows & curtain walls

25-Aug-15

08-Sep-15

25-Aug-15

08-Sep-15

0

ST904, ST944

ST974

ST964

Masonry veneer

02-Jul-15

24-Aug-15

03-Jul-15

25-Aug-15

1

ST814

ST934

ST974

Aluminum entrance doors/sliding doors

08-Sep-15

13-Oct-15

08-Sep-15

13-Oct-15

0

ST934, ST954

ST984

Plumbing underground sanitary/storm rough-in

04-Nov-14*

18-Nov-14

18-Nov-14

02-Dec-14

10

ST1224

ST994, ST1004, ST744

ST994

Waterproofing

23-Dec-14*

20-Jan-15

23-Dec-14

20-Jan-15

0

ST984, ST1004, ST1234

ST804, ST784

T27

Install Temporary Fence

06-Aug-14*

22-Aug-14

06-Aug-14

22-Aug-14

0

T37

T87, T67

T37

Mobilize Job Trailers

23-Jul-14*

06-Aug-14

23-Jul-14

06-Aug-14

0

T77

T27

T47

Provide temporary electric and lighting to buildings

30-Oct-14*

11-Dec-14

30-Oct-14

11-Dec-14

0

T67, S176

T57

Provide temporary heat

10-Sep-15*

05-Nov-15

10-Sep-15

05-Nov-15

0

S406

T67

Temporary utility poles

22-Aug-14*

12-Sep-14

09-Oct-14

30-Oct-14

34

T27

T47

T77

Site Preparation

09-Jul-14

23-Jul-14

09-Jul-14

23-Jul-14

0

A7080

T37

T87

Temporary electric to trailers

22-Aug-14*

05-Sep-14

22-Aug-14

05-Sep-14

0

T27

Footer 1

Page 8 of 8


MONROE CAMPUS... Activ Activity Name ID

Project: MONRO WBS: Volume 1

BASELINE nal Start

vity Qtr 4, 2013

ion 94 10-Oct-13 A 19 10-Oct-13

Oct N %

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

WBS: Division 00 b 135 10-Oct-13

Qtr 3, 2014

M Jun Jul Aug

78 10-Oct-13 0%

List A of drawings

21 28-Jan-14 0%

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

S Oct N Dec Jan F Mar Apr

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

M Jun Jul

A

Qtr 4, 2017

Geotechnical investigation List of drawings

8 26-Feb-14 0%

Prevailing wage documents

Electrical A Constructio

7 26-Feb-14 0%

Electrical Construction bid form

Plumbing A constructio

6 26-Feb-14 0%

Plumbing construction bid form

Hvac A construction bid

6 26-Feb-14 0%

Hvac construction bid

General A construction

7 26-Feb-14 0%

General construction bid form

Instruction A to bidders

13 26-Feb-14 0%

Qualification A question

6 26-Feb-14 0%

Bid A security

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Prevailing A wage docu

Sample A Insurance ce

Qtr 1, 2015

16-Apr-14, WBS: Division 00 bidding & contract requirements

Geotechnical A investig

invitation A to bid

Qtr 4, 2014

14-Apr-14 20:48

Instruction to bidders Qualification questionnaire

25 26-Feb-14 0%

invitation to bid

5 26-Feb-14 0%

Sample Insurance certificates

11 01-Apr-14

0%

Safety A and health ma

4 01-Apr-14

0%

Bid security

Standard A General co

1 01-Apr-14

0%

Standard General conditions

Payment A bond

1 01-Apr-14

0%

Payment bond

Performance A bond

1 01-Apr-14

0%

Performance bond

AIA A document a132

1 01-Apr-14

0%

AIA document a132

Non A collusion affidavit

1 01-Apr-14

0%

Non collusion affidavit

WBS: Division 01 G

19 10-Oct-13

Safety and health management plan

Alteration A Project pro

4 10-Oct-13 0%

Contract A Modification

51 10-Oct-13 0%

Contract Modification

Leed A & sustainable d

7 10-Oct-13 0%

Leed & sustainable design requirements

Testing A for indoor air

19 10-Oct-13 0%

Testing for indoor air quality

Cutting A and patching

21 10-Oct-13 0%

Cutting and patching

LEED A submital Form

38 06-Nov-13 0%

Coordination A drawings

17 28-Jan-14 0%

Field A engineering

10 28-Jan-14 0%

Product A requirements

39 01-Apr-14

0%

Unit A prices

43 01-Apr-14

0%

Execution A

00 02-Apr-14

0%

Temporary A Facilities &

946 02-Apr-14

0%

Construction A Progres

966 02-Apr-14

0%

Construction Progres

Web A based project m

955 02-Apr-14

0%

Web based project man

Project A Management

996 02-Apr-14

0%

Project Manag

Payement A procedures

00 02-Apr-14

0%

Payement p

Demonstration A & train

330 02-Apr-14

0%

Construction A waste m

868 02-Apr-14

0%

Start A milestone

Alteration Project procedures

1 02-Apr-14* 0% 0%

LEED submital Form Coordination drawings Field engineering Product requirements Unit prices Execution Temporary Facilities & con

Demonstration & training Construction waste mangement Start milestone

Summary A

12 16-Apr-14

References A

14 02-May-14 0%

Quality A requirements

49 02-May-14 0%

Quality requirements

Submittal A form

46 02-May-14 0%

Submittal form

Alternates A

12 02-May-14 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary References

Alternates Summary

Page 1 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE nal Start

vity Qtr 4, 2013

Quantity A allowances

Oct N ion % 26 02-May-14 0%

Work A restrictions

46 02-May-14 0%

Summary A of multiple c

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

Qtr 3, 2014

M Jun Jul Aug

Qtr 4, 2014

Qtr 1, 2015

S Oct N Dec Jan F Mar Apr

General A Commission

5 02-May-14 0%

General Commissioning requirements

Operation A and mainte

850 02-Jun-14 0%

Project A record docum

666 12-Feb-15 0%

Checklist A enrollment

9 24-Jan-17 0%

Checklist A student life

9 07-Jun-17 0%

Checklist A classroom

9 21-Aug-17 0%

Close A out procedures

79 01-Sep-17 0%

Demobilize A job trailers

176 01-Sep-17 0%

Final A Milestone

WBS: Sitework

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

S Oct N Dec Jan F Mar Apr

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

M Jun Jul

A

Qtr 4, 2017

Work restrictions Summary of multiple contracts

1 23-Dec-15* 0%

Qtr 3, 2015

Quantity allowances

6 02-May-14 0%

Substantial A milestone

Qtr 2, 2015

14-Apr-14 20:48

Operation and maintenance data Project record documents Substantial milestone Checklist enrollment building Checklist student life building Checklist classroom roe Close out procedure

1 07-May-18* 0% 562 02-Apr-14

27-May-16, WBS: Sitework

WBS: Division 33: U 354 05-May-14

10-Sep-15, WBS: Division 33: Utilities

Water system

120 05-May-14 00%

Install Storm Sewer

245 12-May-14 0%

Install Sanitary Sewer

45 30-Jun-14* 0%

Site lighting

40 30-Jun-14* 0%

Electrical ductbank

50 21-Aug-14* 0%

Install Geo Exchange

100 23-Apr-15* 0%

Water system Install Storm Sewer Install Sanitary Sewer Site lighting Electrical ductbank Install Geo Exchange Field

WBS: Division 10: S 562 02-Apr-14

27-May-16, WBS: Division 10: Specialties

Install flagpoles

562 02-Apr-14

Install A all site utilties

70 02-Apr-14* 0%

0%

Parking control equip

25 25-Aug-15* 0%

Timber guide railings

20 25-Aug-15* 0%

Exterior site railings

38 02-Dec-15* 0%

site linestripping and

26 22-Apr-16* 0%

Install flagpoles Install all site utilties Parking control equipment Timber guide railings Exterior site railings site linestripping and signage

WBS: Division 31: E 290 03-Apr-14

14-May-15, WBS: Division 31: Earthwork

Site Layout

30 03-Apr-14

Erosion controls

25 10-Apr-14* 0%

0%

Site Layout

Site Clearing and Stri

70 15-May-14* 0%

Temporary Basin and

35 15-May-14* 0%

Site grading

120 15-May-14* 0%

Site grading

Install Sediment Basin

50 21-Aug-14* 0%

Install Sediment Basin

Site excavation

140 30-Oct-14* 0%

Erosion controls Site Clearing and Strip Topsoil Temporary Basin and Swales

Site excavation

WBS: Division 32: S 536 02-Apr-14

21-Apr-16, WBS: Division 32: Site Improvements

Install Rock Construc

15 02-Apr-14

0%

Install Paving binder a

20 15-May-14* 0%

Install Rock Construction Entrance Install Paving binder access roads and staging areas

Install additional stagi

30 24-Jul-14* 0%

Concrete curbs

100 25-Aug-14* 0%

Install new topsoil

35 25-Aug-14 0%

Retaining wall

40 12-Jan-15* 0%

Exterior masonry sea

30 13-Apr-15* 0%

Place trees and shru

40 14-May-15* 0%

Place trees and shrubbery

Retaining wall for land

20 25-May-15* 0%

Retaining wall for landscaping

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Install additional staging areas Concrete curbs Install new topsoil Retaining wall Exterior masonry seat walls and site walls

Summary

Page 2 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE nal Start

vity Qtr 4, 2013

sidewalks and ramp c

Oct N ion % 65 26-May-15* 0%

Fiberglass bus statio

35 25-Aug-15* 0%

Unit Pavers

46 29-Sep-15* 0%

Final Landscaping

50 13-Oct-15* 0%

Position Site seating

25 22-Dec-15* 0%

Final placement of tre

43 26-Jan-16* 0%

Concrete bumper blo

20 25-Mar-16* 0%

WBS: Foundatio Construct building pad Layout for foundation

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

Qtr 3, 2014

M Jun Jul Aug

Qtr 4, 2014

M Jun Jul

A

S Oct N Dec Jan F Mar Apr

21 12-Jun-14* 0%

S Oct N Dec Jan F Mar Apr

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

M Jun Jul

A

Qtr 4, 2017

Construct building pad

0%

Layout for foundation Tie Rebar

346 09-Jul-14

05-Nov-15, WBS: Temporary Construction

Site Preparation

10 09-Jul-14

Mobilize Job Trailers

10 23-Jul-14* 0%

Install Temporary Fen

12 06-Aug-14* 0%

Temporary utility poles

15 22-Aug-14* 0%

Temporary electric to

10 22-Aug-14* 0%

Provide temporary ele

30 30-Oct-14* 0%

Provide temporary he

40 10-Sep-15* 0%

0%

Site Preparation Mobilize Job Trailers Install Temporary Fence Temporary utility poles Temporary electric to trailers Provide temporary electric and lighting to buildings Provide temporary heat

609 21-Oct-14

20-Feb-17, WBS: Building 1 ( Administration building )

WBS: Structure an and 235 21-Oct-14

15-Sep-15, WBS: Structure and Rough In

142 21-Oct-14

07-May-15, WBS: Division 3

Plumbing undergroun

10 21-Oct-14* 0%

Deep underground ro

15 04-Nov-14* 0%

Stone under slab rou

12 23-Jan-15 0%

Stone under slab

15 10-Feb-15 0%

Pour concrete slab o

32 03-Mar-15 0%

Pour concrete slab o

15 16-Apr-15

Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck

0%

Pour concrete slab on grade

35 28-Jul-15

15-Sep-15, WBS: Division 8

Aluminum windows &

10 28-Jul-15

Aluminum entrance d

25 11-Aug-15 0%

0%

Aluminum windows & curtain walls Aluminum entrance doors/sliding doors

57 07-May-15

27-Jul-15, WBS: Division 4

CMU walls

20 07-May-15 0%

Masonry veneer

37 04-Jun-15 0%

Masonry veneer

29 04-Jun-15 0%

Layout stone veneer

CMU walls

155 23-Dec-14

28-Jul-15, WBS: Division 5

Erect structural steel

23 23-Dec-14 0%

Cold formed metal fra

25 23-Jan-15 0%

WBS: Division 7

Qtr 2, 2017

21-Oct-14, WBS: Foundation

Concrete foundation

Metal roof ladders

Qtr 1, 2017

Concrete bumper blocks

Footing excavation

WBS: Division 5

M Jun Jul Aug

Qtr 4, 2016

Final placement of trees and shrubbery

45 19-Aug-14* 0%

Layout stone veneer

Qtr 3, 2016

Position Site seating

Concrete foundation

WBS: Division 4

Qtr 2, 2016

Final Landscaping

45 19-Aug-14* 0%

WBS: Division 8

Qtr 1, 2016

Unit Pavers

Footing excavation

WBS: Division 3

Qtr 4, 2015

Fiberglass bus stations

20 22-Jul-14* 0%

WBS: Building 1

Qtr 3, 2015

sidewalks and ramp concrete pour

Tie Rebar

WBS: Temporar

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

93 12-Jun-14

7 11-Jul-14*

Qtr 1, 2015

14-Apr-14 20:48

Erect structural steel and deck Cold formed metal framing and sheathing

20 30-Jun-15 0%

Metal roof ladders

184 25-Nov-14

10-Aug-15, WBS: Division 7

Waterproofing

20 25-Nov-14* 0%

Install air membrane

18 27-Feb-15 0%

Spray urethane insula

20 25-Mar-15 0%

Wood blocking & she

10 22-Apr-15

Waterproofing Install air membrane Spray urethane insulation

0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Wood blocking & sheathing on roof Summary

Page 3 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Insulated metal wall p

BASELINE nal Start

vity Qtr 4, 2013

ion 20 22-Apr-15

Oct N % 0%

Roof curbs

7 06-May-15 0%

Roof Drains

11 06-May-15 0%

Roof top equipment

15 21-May-15 0%

Roof metal edges

13 11-Jun-15

0%

Exterior Caulking

10 27-Jul-15

0%

WBS: Finishes

478 22-Apr-15

Install A railings Interior A H.M frames

5 04-Jun-15* 0%

Ceramic A and porcela

7 11-Jun-15* 0%

Painting A

9 22-Jun-15* 0%

Wall A coverings

6 03-Jul-15* 0% 10 23-Jul-15* 0%

PC A overhead pipe

10 06-Aug-15* 0%

Qtr 1, 2015

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

S Oct N Dec Jan F Mar Apr

Exterior Caulking 20-Feb-17, WBS: Finishes Metal stairs Install railings Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe PC insulation PC drop sprinkler head

5 10-Sep-15* 0%

PC casework fixtures

PC A toilet fixtures

5 17-Sep-15* 0%

HC A hangers

5 24-Sep-15* 0%

HC A pipe install

7 01-Oct-15* 0%

HC A duct install

5 12-Oct-15* 0%

PC toilet fixtures HC hangers HC pipe install HC duct install

HC A ATC rough-in

11 19-Oct-15* 0%

HC A GRD install

15 03-Nov-15* 0%

HC A equipment and fin

12 23-Nov-15* 0%

HC A kitchen equipmen

10 09-Dec-15* 0%

EC A rough-in walls

12 23-Dec-15* 0%

EC A overhead rough-in

14 08-Jan-16* 0%

EC A cable tray

14 28-Jan-16* 0%

EC cable tray

EC A wiring

9 17-Feb-16* 0%

EC wiring

EC A light fixtures

8 01-Mar-16* 0%

EC A wring devices

5 11-Mar-16* 0%

EC A fire alarm and sec

6 18-Mar-16* 0%

EC A kitchen equipmen

10 28-Mar-16* 0%

EC A hook ups and con

5 11-Apr-16* 0%

Casework/millwork A

8 18-Apr-16* 0%

Resilent A tile base and

8 28-Apr-16* 0%

Resilent tile base and floor

HC ATC rough-in

8 10-May-16* 0%

Seamless vinyl flooring

HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 20-May-16* 0%

Doors A and Hardware

6 15-Jun-16* 0%

Interior A glass partitions

8 23-Jun-16* 0%

Wood A wall panels

5 05-Jul-16* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

A

Roof metal edges

10 27-Aug-15* 0%

7 06-Jun-16* 0%

M Jun Jul

Qtr 4, 2017

Metal soffit and fascia

5 20-Aug-15* 0%

Install A rubber stairs, t

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

Roof top equipment

PC A casework fixtures

Carpet A tiles

Qtr 2, 2017

Roof Drains

PC A drop sprinkler hea

Seamless A vinyl floorin

Qtr 1, 2017

Roof curbs

7 14-Jul-15* 0%

PC A AG san/rw

Qtr 4, 2014

Insulated metal wall panels

4 29-Apr-15* 0% 9 22-May-15* 0%

Qtr 3, 2014

M Jun Jul Aug

13 05-May-15* 0%

Caulking A

PC A insulation

D Jan F Mar Apr

5 22-Apr-15* 0%

Drywall A and spackliing

Acoustical A ceiling grid

Qtr 2, 2014

5 15-May-15 0%

Metal soffit and fascia

Metal A stairs

Qtr 1, 2014

14-Apr-14 20:48

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Summary

Page 4 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Visual A display surface

BASELINE nal Start

vity Qtr 4, 2013

Oct N ion % 5 12-Jul-16* 0%

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

Qtr 3, 2014

M Jun Jul Aug

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

14-Apr-14 20:48

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

S Oct N Dec Jan F Mar Apr

5 19-Jul-16* 0%

Signage

Wood A ceiling

3 26-Jul-16* 0%

Wood ceiling

11 29-Jul-16* 0%

Tiolet A complartments

8 12-Aug-16* 0%

Fire A protection specia

6 24-Aug-16* 0%

Window A shades Wire A mesh partitions Install A lockers

5 26-Oct-16* 0%

Glass A wall folding par

5 02-Nov-16* 0%

Loading A dock equipm

12 09-Nov-16* 0%

Window shades Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment

Paint A gym ceiling

5 25-Nov-16* 0%

Gym A equipment

7 02-Dec-16* 0%

Gym equipment

Gym A dividers

9 13-Dec-16* 0%

Gym dividers

Install A hardwood floor

7 26-Dec-16* 0%

Install A collapsable bel

6 04-Jan-17* 0%

Hydraulic A elevators

8 12-Jan-17* 0%

Install A kitchen tiles

10 24-Jan-17 0%

Motorized A projection

WBS: Building 2

Paint gym ceiling

Install hardwood flooring Install collapsable belachers Hydraulic elevators Install kitchen tiles

9 07-Feb-17 0%

Motorized projection screens

695 04-Nov-14

04-Jul-17, WBS: Building 2 (Student Life)

WBS: Structure an and 245 04-Nov-14 WBS: Division 3

13-Oct-15, WBS: Structure and Rough In

152 04-Nov-14

04-Jun-15, WBS: Division 3

Plumbing undergroun

10 04-Nov-14* 0%

Deep underground ro

15 18-Nov-14* 0%

Stone under slab rou

12 20-Feb-15 0%

Stone under slab

15 10-Mar-15 0%

Pour concrete slab o

32 31-Mar-15 0%

Pour concrete slab o

15 14-May-15 0%

WBS: Division 8 Aluminum entrance d

25 08-Sep-15 0%

Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade Aluminum windows & curtain walls Aluminum entrance doors/sliding doors

57 04-Jun-15

24-Aug-15, WBS: Division 4

CMU walls

20 04-Jun-15 0%

Masonry veneer

37 02-Jul-15

CMU walls

0%

Masonry veneer

155 20-Jan-15

25-Aug-15, WBS: Division 5

Erect structural steel

23 20-Jan-15 0%

Cold formed metal fra

25 20-Feb-15 0%

Metal roof ladders

20 28-Jul-15

WBS: Division 7

184 23-Dec-14

Erect structural steel and deck Cold formed metal framing and sheathing

0%

Metal roof ladders 07-Sep-15, WBS: Division 7

Waterproofing

20 23-Dec-14* 0%

Install air membrane

18 27-Mar-15 0%

Spray urethane insula

20 22-Apr-15

Wood blocking & she

10 20-May-15 0%

Insulated metal wall p

20 20-May-15 0%

Roof curbs

Deep underground rough-in

13-Oct-15, WBS: Division 8

10 25-Aug-15 0%

WBS: Division 5

Plumbing underground sanitary/storm rough-in

35 25-Aug-15

Aluminum windows & WBS: Division 4

A

Fire protection specialities

7 15-Sep-16* 0%

Install A and setup food

M Jun Jul

Qtr 4, 2017

Tiolet complartments

13 26-Sep-16* 0% 9 13-Oct-16* 0%

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

Place Acoustical ceiling tiles

10 01-Sep-16* 0%

Install A hood and walk

Qtr 2, 2017

Visual display surfaces

Signage A Place A Acoustical ceilin

Qtr 1, 2017

Waterproofing Install air membrane

0%

Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels

7 03-Jun-15 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Roof curbs Summary

Page 5 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Roof Drains Roof top equipment

BASELINE nal Start

vity Qtr 4, 2013

Oct N ion % 11 03-Jun-15 0% 15 18-Jun-15 0%

Roof metal edges

13 09-Jul-15

Exterior Caulking

10 24-Aug-15 0%

WBS: Finishes

485 25-Aug-15

Install A railings Interior A H.M frames

D Jan F Mar Apr

Ceramic A and porcela

7 14-Oct-15* 0%

Painting A

9 23-Oct-15* 0%

Wall A coverings

6 05-Nov-15* 0%

Acoustical A ceiling grid

7 16-Nov-15* 0%

PC A AG san/rw

10 25-Nov-15* 0%

PC A overhead pipe

10 09-Dec-15* 0%

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

M Jun Jul Aug

Qtr 4, 2016

Qtr 1, 2017

S Oct N Dec Jan F Mar Apr

Install railings Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe PC insulation PC drop sprinkler head

5 14-Jan-16* 0%

PC casework fixtures

PC A toilet fixtures

5 21-Jan-16* 0%

PC A kitchen equipmen

6 28-Jan-16* 0%

HC A hangers

5 05-Feb-16* 0%

HC A pipe install

7 12-Feb-16* 0%

PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install

5 23-Feb-16* 0%

HC duct install

HC A ATC rough-in

11 01-Mar-16* 0%

HC A GRD install

15 16-Mar-16* 0%

HC A equipment and fin

12 05-Apr-16* 0%

HC A kitchen equipmen

10 21-Apr-16* 0%

EC A rough-in walls

12 05-May-16* 0%

EC A overhead rough-in

14 23-May-16* 0%

EC A cable tray

14 10-Jun-16* 0%

EC cable tray

EC A wiring

9 30-Jun-16* 0%

EC wiring

EC A light fixtures

8 13-Jul-16* 0%

EC A wring devices

5 25-Jul-16* 0%

EC A fire alarm and sec

6 01-Aug-16* 0%

EC A kitchen equipmen

10 09-Aug-16* 0%

EC A hook ups and con

5 23-Aug-16* 0%

Casework/millwork A

8 30-Aug-16* 0%

Resilent A tile base and

8 09-Sep-16* 0%

Resilent tile base and floor

Seamless A vinyl floorin

8 21-Sep-16* 0%

Seamless vinyl flooring

HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 03-Oct-16* 0%

Doors A and Hardware

6 27-Oct-16* 0%

Interior A glass partitions

8 04-Nov-16* 0%

Wood A wall panels

5 16-Nov-16* 0%

Visual A display surface

5 23-Nov-16* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

A

04-Jul-17, WBS: Finishes

PC A casework fixtures

7 18-Oct-16* 0%

M Jun Jul

Qtr 4, 2017

Metal stairs

5 24-Dec-15* 0%

Install A rubber stairs, t

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

Exterior Caulking

10 31-Dec-15* 0%

Carpet A tiles

Qtr 2, 2017

Roof metal edges

PC A drop sprinkler hea

HC A duct install

Qtr 3, 2016

Metal soffit and fascia

4 01-Sep-15* 0%

5 07-Oct-15* 0%

Qtr 1, 2015

Roof top equipment

13 07-Sep-15* 0%

Caulking A

Qtr 4, 2014

Roof Drains

5 25-Aug-15* 0%

9 24-Sep-15* 0%

Qtr 3, 2014

M Jun Jul Aug

0%

Drywall A and spackliing

PC A insulation

Qtr 2, 2014

5 12-Jun-15 0%

Metal soffit and fascia

Metal A stairs

Qtr 1, 2014

14-Apr-14 20:48

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Summary

Page 6 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Signage A Wood A ceiling

BASELINE nal Start

vity Qtr 4, 2013

Oct N ion % 5 30-Nov-16* 0% 11 12-Dec-16* 0%

Tiolet A complartments

8 26-Dec-16* 0%

Fire A protection specia

6 05-Jan-17* 0%

Wire A mesh partitions Install A lockers

Qtr 2, 2014

D Jan F Mar Apr

Qtr 3, 2014

M Jun Jul Aug

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

5 09-Mar-17* 0%

Glass A wall folding par

5 16-Mar-17* 0%

Loading A dock equipm

12 23-Mar-17* 0%

M Jun Jul

A

Tiolet complartments Fire protection specialities Window shades Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment

Paint A gym ceiling

5 10-Apr-17* 0%

Paint gym ceiling

Gym A equipment

7 17-Apr-17* 0%

Gym equipment

Gym A dividers

9 26-Apr-17* 0%

Gym dividers

Install A hardwood floor

7 09-May-17* 0%

Install A collapsable bel

6 18-May-17* 0%

Hydraulic A elevators

8 26-May-17* 0%

Install A kitchen tiles

10 07-Jun-17* 0%

Motorized A projection

WBS: Building 3

Install hardwood flooring Install collapsable belachers Hydraulic elevators Install kitchen tiles

9 21-Jun-17* 0%

Motorized projection screens

719 18-Nov-14

21-Aug-17, WBS: Building 3 (ClassRoo

WBS: Structure an and 254 18-Nov-14 WBS: Division 4

09-Nov-15, WBS: Structure and Rough In

57 02-Jul-15

21-Sep-15, WBS: Division 4

CMU walls

20 02-Jul-15

0%

Masonry veneer

37 30-Jul-15

0%

WBS: Division 5

Masonry veneer 25-Aug-15, WBS: Division 5

23 20-Jan-15 0%

Cold formed metal fra

25 20-Feb-15 0%

Metal roof ladders

20 28-Jul-15

WBS: Division 7

204 23-Dec-14

Erect structural steel and deck Cold formed metal framing and sheathing

0%

Metal roof ladders 05-Oct-15, WBS: Division 7

Waterproofing

20 23-Dec-14* 0%

Install air membrane

18 27-Mar-15 0%

Spray urethane insula

20 22-Apr-15

Wood blocking & she

10 20-May-15 0%

Insulated metal wall p

20 20-May-15 0%

Waterproofing Install air membrane

0%

Roof curbs

7 03-Jun-15 0%

Roof Drains

11 03-Jun-15 0%

Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels Roof curbs Roof Drains

5 12-Jun-15 0%

Metal soffit and fascia

15 18-Jun-15 0%

Roof metal edges

13 09-Jul-15

Exterior Caulking

10 21-Sep-15 0%

WBS: Division 3

CMU walls

155 20-Jan-15

Erect structural steel

Roof top equipment

Qtr 4, 2017

Place Acoustical ceiling tiles

13 07-Feb-17* 0%

Install A and setup food

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

Wood ceiling

7 27-Jan-17* 0% 9 24-Feb-17* 0%

Qtr 2, 2017

Signage

10 13-Jan-17* 0%

Install A hood and walk

Qtr 1, 2017

S Oct N Dec Jan F Mar Apr

3 07-Dec-16* 0%

Place A Acoustical ceilin

Window A shades

Qtr 1, 2014

14-Apr-14 20:48

Roof top equipment Metal soffit and fascia

0%

Roof metal edges Exterior Caulking

154 18-Nov-14

22-Jun-15, WBS: Division 3

Plumbing undergroun

10 18-Nov-14* 0%

Deep underground ro

15 02-Dec-14* 0%

Stone under slab rou

12 10-Mar-15 0%

Stone under slab

15 26-Mar-15 0%

Pour concrete slab o

32 16-Apr-15

Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab

0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Pour concrete slab on deck Summary

Page 7 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Pour concrete slab o WBS: Division 8 Aluminum windows &

BASELINE nal Start

vity Qtr 4, 2013

Oct N ion % 15 01-Jun-15 0%

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

M Jun Jul Aug

25 05-Oct-15 0% 465 09-Nov-15

Qtr 1, 2015

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Qtr 3, 2015

M Jun Jul

A

Qtr 4, 2015

Qtr 1, 2016

S Oct N Dec Jan F Mar Apr

Install A railings

4 16-Nov-15* 0%

Install railings

13 20-Nov-15* 0%

Caulking A

5 22-Dec-15* 0%

Ceramic A and porcela

7 29-Dec-15* 0%

Painting A

9 07-Jan-16* 0%

Wall A coverings

6 20-Jan-16* 0%

Acoustical A ceiling grid

7 29-Jan-16* 0%

PC A AG san/rw

10 09-Feb-16* 0%

PC A overhead pipe

10 23-Feb-16* 0%

PC A insulation

Qtr 1, 2017

Qtr 2, 2017

S Oct N Dec Jan F Mar Apr

M Jun Jul

Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe

5 08-Mar-16* 0%

PC insulation

10 15-Mar-16* 0%

PC drop sprinkler head

PC A casework fixtures

5 29-Mar-16* 0%

PC casework fixtures

PC A toilet fixtures

5 05-Apr-16* 0%

PC A kitchen equipmen

6 12-Apr-16* 0%

HC A hangers

5 20-Apr-16* 0%

HC A pipe install

7 27-Apr-16* 0%

HC A duct install

5 06-May-16* 0%

PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install HC duct install

HC A ATC rough-in

11 13-May-16* 0%

HC A GRD install

15 30-May-16* 0%

HC A equipment and fin

12 17-Jun-16* 0%

HC A kitchen equipmen

10 05-Jul-16* 0%

EC A rough-in walls

12 19-Jul-16* 0%

EC A overhead rough-in

14 04-Aug-16* 0%

EC A cable tray

14 24-Aug-16* 0%

EC cable tray

EC A wiring

9 13-Sep-16* 0%

EC wiring

EC A light fixtures

8 26-Sep-16* 0%

EC A wring devices

5 06-Oct-16* 0%

EC A fire alarm and sec

6 13-Oct-16* 0%

EC A kitchen equipmen

10 21-Oct-16* 0%

EC A hook ups and con

5 04-Nov-16* 0%

Casework/millwork A

8 11-Nov-16* 0%

Resilent A tile base and

8 23-Nov-16* 0%

Resilent tile base and floor

Seamless A vinyl floorin

8 05-Dec-16* 0%

HC ATC rough-in

Seamless vinyl flooring

HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 15-Dec-16* 0%

Install A rubber stairs, t

7 30-Dec-16* 0%

Doors A and Hardware

6 10-Jan-17* 0%

Interior A glass partitions

8 18-Jan-17* 0%

Wood A wall panels

5 30-Jan-17* 0%

Visual A display surface

5 06-Feb-17* 0%

Signage A

5 13-Feb-17* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

A

Qtr 4, 2017

Interior H.M frames

PC A drop sprinkler hea

Carpet A tiles

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

21-Aug-17, WBS: Finishes Metal stairs

9 09-Dec-15* 0%

M Jun Jul Aug

Qtr 4, 2016

Aluminum entrance doors/sliding doors

5 09-Nov-15* 0%

Drywall A and spackliing

Qtr 3, 2016

Aluminum windows & curtain walls

Metal A stairs Interior A H.M frames

Qtr 2, 2016

09-Nov-15, WBS: Division 8

10 25-Aug-15 0%

Aluminum entrance d

Qtr 4, 2014

Pour concrete slab on grade

54 25-Aug-15

WBS: Finishes

Qtr 3, 2014

14-Apr-14 20:48

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Signage Summary

Page 8 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE nal Start

vity Qtr 4, 2013

Wood A ceiling

Oct N ion % 3 20-Feb-17* 0%

Place A Acoustical ceilin

11 23-Feb-17* 0%

Tiolet A complartments

8 09-Mar-17* 0%

Fire A protection specia Window A shades Wire A mesh partitions Install A lockers

Qtr 1, 2014

Qtr 2, 2014

D Jan F Mar Apr

Qtr 3, 2014

M Jun Jul Aug

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

S Oct N Dec Jan F Mar Apr

Qtr 3, 2015

M Jun Jul

A

14-Apr-14 20:48 Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

S Oct N Dec Jan F Mar Apr

Qtr 3, 2016

M Jun Jul Aug

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

S Oct N Dec Jan F Mar Apr

Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M

Qtr 3, 2017

M Jun Jul

A

Qtr 4, 2017

Wood ceiling Place Acoustical ceiling tiles Tiolet complartments

6 21-Mar-17* 0%

Fire protection specialities

10 29-Mar-17* 0%

Window shades

7 12-Apr-17* 0%

Wire mesh partitions

13 21-Apr-17* 0%

Install lockers

Observation A deck

9 10-May-17* 0%

Install A Medical recline

5 23-May-17* 0%

Install Medical reclined chair

Glass A wall folding par

5 30-May-17* 0%

Glass wall folding partition

Place A additional medi

12 06-Jun-17* 0%

Install A lecture seating

5 22-Jun-17* 0%

Install A Student Desks

7 29-Jun-17* 0%

Lab A Desks

9 10-Jul-17* 0%

Install A hardwood floor

7 21-Jul-17* 0%

Teacher A desks

6 01-Aug-17* 0%

Hydraulic A elevators

8 09-Aug-17* 0%

Project: Monroe

0

Project: Monroe

0

Project: Monroe Project: Monroe

0

Observation deck

Place additional medical equipment Install lecture seating Install Student Desks and chairs Lab Desks Install hardwood flooring Teacher desks Hydraulic elevators

0

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 9 of 9

TASK filter: All Activities Š Oracle Corporation


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8360

78

78 Standard 5 Day Workweek

0

Geotechnical investigation

10-Oct-13

27-Jan-14

03-Oct-13

21-Jan-14

-5

A8450

4

4 Standard 5 Day Workweek

0

Alteration Project procedures

10-Oct-13

15-Oct-13

10-Oct-13

15-Oct-13

0

A8530

51

51 Standard 5 Day Workweek

0

Contract Modification

10-Oct-13

19-Dec-13

10-Oct-13

19-Dec-13

0

A8740

19

19 Standard 5 Day Workweek

0

Testing for indoor air quality

10-Oct-13

05-Nov-13

10-Oct-13

05-Nov-13

0

A8800

21

21 Standard 5 Day Workweek

0

Cutting and patching

10-Oct-13

07-Nov-13

10-Oct-13

07-Nov-13

0

A8730

7

7 Standard 5 Day Workweek

0

Leed & sustainable design requirements

10-Oct-13

18-Oct-13

28-Oct-13

05-Nov-13

12

A8460

38

38 Standard 5 Day Workweek

0

LEED submital Form

06-Nov-13

30-Dec-13

06-Nov-13

30-Dec-13

0

A8610

21

21 Standard 5 Day Workweek

0

List of drawings

28-Jan-14

25-Feb-14

21-Jan-14

19-Feb-14

-5

A8570

10

10 Standard 5 Day Workweek

0

Field engineering

28-Jan-14

10-Feb-14

28-Jan-14

10-Feb-14

0

A8500

17

17 Standard 5 Day Workweek

0

Coordination drawings

28-Jan-14

20-Feb-14

24-Mar-14

16-Apr-14

39

A8390

25

25 Standard 5 Day Workweek

0

invitation to bid

26-Feb-14

01-Apr-14

19-Feb-14

25-Mar-14

-5

A8300

8

8 Standard 5 Day Workweek

0

Prevailing wage documents

26-Feb-14

10-Mar-14

26-Feb-14

10-Mar-14

0

A8320

7

7 Standard 5 Day Workweek

0

Electrical Construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8330

6

6 Standard 5 Day Workweek

0

Plumbing construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8340

6

6 Standard 5 Day Workweek

0

Hvac construction bid

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8350

7

7 Standard 5 Day Workweek

0

General construction bid form

26-Feb-14

06-Mar-14

26-Feb-14

06-Mar-14

0

A8370

13

13 Standard 5 Day Workweek

0

Instruction to bidders

26-Feb-14

14-Mar-14

26-Feb-14

14-Mar-14

0

A8380

6

6 Standard 5 Day Workweek

0

Qualification questionnaire

26-Feb-14

05-Mar-14

26-Feb-14

05-Mar-14

0

A8640

5

5 Standard 5 Day Workweek

0

Sample Insurance certificates

26-Feb-14

04-Mar-14

26-Feb-14

04-Mar-14

0

A8670

1

1 Standard 5 Day Workweek

0

AIA document a132

01-Apr-14

02-Apr-14

26-Mar-14

26-Mar-14

-5

A8310

11

11 Standard 5 Day Workweek

0

Bid security

01-Apr-14

16-Apr-14

01-Apr-14

16-Apr-14

0

A8410

39

39 Standard 5 Day Workweek

0

Product requirements

01-Apr-14

26-May-14

01-Apr-14

26-May-14

0

A8550

43

43 Standard 5 Day Workweek

0

Unit prices

01-Apr-14

02-Jun-14

01-Apr-14

02-Jun-14

0

A8620

4

4 Standard 5 Day Workweek

0

Safety and health management plan

01-Apr-14

07-Apr-14

01-Apr-14

07-Apr-14

0

A8630

1

1 Standard 5 Day Workweek

0

Standard General conditions

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

Page 1 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8650

1

1 Standard 5 Day Workweek

0

Payment bond

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8660

1

1 Standard 5 Day Workweek

0

Performance bond

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

A8680

1

1 Standard 5 Day Workweek

0

Non collusion affidavit

01-Apr-14

02-Apr-14

01-Apr-14

02-Apr-14

0

S336

562

562 Standard 5 Day Workweek

0

Install flagpoles

02-Apr-14

27-May-16

27-Mar-14

27-May-16

-5

A7080

70

70 Standard 5 Day Workweek

0

Install all site utilties

02-Apr-14*

09-Jul-14

27-Mar-14

02-Jul-14

-5

1005 1005 Standard 5 Day Workweek

0

Execution

02-Apr-14

07-Feb-18

02-Apr-14

07-Feb-18

0

A8400

A8420

946

946 Standard 5 Day Workweek

0

Temporary Facilities & controls

02-Apr-14

16-Nov-17

02-Apr-14

16-Nov-17

0

A8480

966

966 Standard 5 Day Workweek

0

Construction Progress documentation

02-Apr-14

14-Dec-17

02-Apr-14

14-Dec-17

0

A8490

955

955 Standard 5 Day Workweek

0

Web based project management

02-Apr-14

30-Nov-17

02-Apr-14

30-Nov-17

0

A8510

996

996 Standard 5 Day Workweek

0

Project Management & coordination

02-Apr-14

25-Jan-18

02-Apr-14

25-Jan-18

0

1008 1008 Standard 5 Day Workweek

0

Payement procedures

02-Apr-14

12-Feb-18

02-Apr-14

12-Feb-18

0

A8520

A8750

330

330 Standard 5 Day Workweek

0

Demonstration & training

02-Apr-14

08-Jul-15

02-Apr-14

08-Jul-15

0

A8970

1

1 Standard 5 Day Workweek

0

Start milestone

02-Apr-14*

03-Apr-14

02-Apr-14

03-Apr-14

0

15

15 Standard 5 Day Workweek

0

Install Rock Construction Entrance

02-Apr-14

23-Apr-14

24-Apr-14

15-May-14

16

868

868 Standard 5 Day Workweek

0

Construction waste mangement

02-Apr-14

31-Jul-17

06-May-14

01-Sep-17

24

S86

30

30 Standard 5 Day Workweek

0

Site Layout

03-Apr-14

15-May-14

03-Apr-14

15-May-14

0

S106

25

25 Standard 5 Day Workweek

0

Erosion controls

10-Apr-14*

15-May-14

10-Apr-14

15-May-14

0

A8600

12

12 Standard 5 Day Workweek

0

Summary

16-Apr-14

02-May-14

16-Apr-14

02-May-14

0

A8430

14

14 Standard 5 Day Workweek

0

References

02-May-14

22-May-14

02-May-14

22-May-14

0

A8440

49

49 Standard 5 Day Workweek

0

Quality requirements

02-May-14

10-Jul-14

02-May-14

10-Jul-14

0

A8470

46

46 Standard 5 Day Workweek

0

Submittal form

02-May-14

08-Jul-14

02-May-14

08-Jul-14

0

A8540

12

12 Standard 5 Day Workweek

0

Alternates

02-May-14

21-May-14

02-May-14

21-May-14

0

A8560

26

26 Standard 5 Day Workweek

0

Quantity allowances

02-May-14

09-Jun-14

02-May-14

09-Jun-14

0

A8580

46

46 Standard 5 Day Workweek

0

Work restrictions

02-May-14

07-Jul-14

02-May-14

07-Jul-14

0

A8590

6

6 Standard 5 Day Workweek

0

Summary of multiple contracts

02-May-14

12-May-14

02-May-14

12-May-14

0

S96

A8790

Page 2 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

A8690

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

General Commissioning requirements

02-May-14

09-May-14

02-May-14

09-May-14

Water system

05-May-14 A 17-Oct-14 A

15-May-14

15-May-14

Total Float

5

5 Standard 5 Day Workweek

0

S206

120

0 Standard 5 Day Workweek

100

S186

245

245 Standard 5 Day Workweek

0

Install Storm Sewer

12-May-14 A 23-Apr-15

15-May-14

23-Apr-15

0

S116

70

70 Standard 5 Day Workweek

0

Site Clearing and Strip Topsoil

15-May-14*

21-Aug-14

15-May-14

21-Aug-14

0

S136

120

120 Standard 5 Day Workweek

0

Site grading

15-May-14*

30-Oct-14

15-May-14

30-Oct-14

0

S156

20

20 Standard 5 Day Workweek

0

Install Paving binder access roads and staging areas

15-May-14*

12-Jun-14

15-May-14

12-Jun-14

0

S126

35

35 Standard 5 Day Workweek

0

Temporary Basin and Swales

15-May-14*

03-Jul-14

12-Aug-14

29-Sep-14

62

A8770

850

850 Standard 5 Day Workweek

0

Operation and maintenance data

02-Jun-14

01-Sep-17

02-Jun-14

01-Sep-17

0

SF55

21

21 Standard 5 Day Workweek

0

Construct building pad

12-Jun-14*

11-Jul-14

12-Jun-14

11-Jul-14

0

S226

40

40 Standard 5 Day Workweek

0

Site lighting

30-Jun-14*

22-Aug-14

05-Aug-14

29-Sep-14

26

S196

45

45 Standard 5 Day Workweek

0

Install Sanitary Sewer

30-Jun-14*

29-Aug-14

11-Aug-15

12-Oct-15

291

T77

10

10 Standard 5 Day Workweek

0

Site Preparation

09-Jul-14

23-Jul-14

09-Jul-14

23-Jul-14

0

SF25

7

7 Standard 5 Day Workweek

0

Layout for foundation

11-Jul-14*

22-Jul-14

11-Jul-14

22-Jul-14

0

SF45

20

20 Standard 5 Day Workweek

0

Tie Rebar

22-Jul-14*

19-Aug-14

22-Jul-14

19-Aug-14

0

T37

10

10 Standard 5 Day Workweek

0

Mobilize Job Trailers

23-Jul-14*

06-Aug-14

23-Jul-14

06-Aug-14

0

S166

30

30 Standard 5 Day Workweek

0

Install additional staging areas

24-Jul-14*

03-Sep-14

24-Jul-14

03-Sep-14

0

T27

12

12 Standard 5 Day Workweek

0

Install Tempor ary Fence

06-Aug-14*

22-Aug-14

06-Aug-14

22-Aug-14

0

SF35

45

45 Standard 5 Day Workweek

0

Footing excavation

19-Aug-14*

21-Oct-14

19-Aug-14

21-Oct-14

0

SF65

45

45 Standard 5 Day Workweek

0

Concrete foundation

19-Aug-14*

21-Oct-14

19-Aug-14

21-Oct-14

0

S146

50

50 Standard 5 Day Workweek

0

Install Sediment Basin

21-Aug-14*

30-Oct-14

21-Aug-14

30-Oct-14

0

S176

50

50 Standard 5 Day Workweek

0

Electrical ductbank

21-Aug-14*

30-Oct-14

21-Aug-14

30-Oct-14

0

T87

10

10 Standard 5 Day Workweek

0

Temporary electric to trailers

22-Aug-14*

05-Sep-14

22-Aug-14

05-Sep-14

0

T67

15

15 Standard 5 Day Workweek

0

Temporary utility poles

22-Aug-14*

12-Sep-14

09-Oct-14

30-Oct-14

34

S216

100

100 Standard 5 Day Workweek

0

Concrete curbs

25-Aug-14*

09-Jan-15

30-Sep-14

16-Feb-15

26

S396

35

35 Standard 5 Day Workweek

0

Install new topsoil

25-Aug-14 A 18-Dec-14

26-Mar-15

14-May-15

105

Page 3 of 15

0


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

ST1224

10

10 Standard 5 Day Workweek

0

Plumbing underground sanitary/storm rough-in

21-Oct-14*

04-Nov-14

21-Oct-14

04-Nov-14

0

T47

30

30 Standard 5 Day Workweek

0

Provide temporary electric and lighting to buildings

30-Oct-14*

11-Dec-14

30-Oct-14

11-Dec-14

0

S386

140

140 Standard 5 Day Workweek

0

Site excavation

30-Oct-14*

14-May-15

30-Oct-14

14-May-15

0

ST1244

15

15 Standard 5 Day Workweek

0

Deep underground rough-in

04-Nov-14*

25-Nov-14

04-Nov-14

25-Nov-14

0

ST984

10

10 Standard 5 Day Workweek

0

Plumbing underground sanitary/storm rough-in

04-Nov-14*

18-Nov-14

18-Nov-14

02-Dec-14

10

ST1004

15

15 Standard 5 Day Workweek

0

Deep underground rough-in

18-Nov-14*

09-Dec-14

02-Dec-14

23-Dec-14

10

ST744

10

10 Standard 5 Day Workweek

0

Plumbing underground sanitary/storm rough-in

18-Nov-14*

02-Dec-14

15-Dec-14

29-Dec-14

19

ST1234

20

20 Standard 5 Day Workweek

0

Waterproofing

25-Nov-14*

23-Dec-14

25-Nov-14

23-Dec-14

0

ST764

15

15 Standard 5 Day Workweek

0

Deep underground rough-in

02-Dec-14*

23-Dec-14

29-Dec-14

19-Jan-15

19

ST994

20

20 Standard 5 Day Workweek

0

Waterproofing

23-Dec-14*

20-Jan-15

23-Dec-14

20-Jan-15

0

ST1024

23

23 Standard 5 Day Workweek

0

Erect structural steel and deck

23-Dec-14

23-Jan-15

23-Dec-14

23-Jan-15

0

ST754

20

20 Standard 5 Day Workweek

0

Waterproofing

23-Dec-14*

20-Jan-15

19-Jan-15

16-Feb-15

19

S376

40

40 Standard 5 Day Workweek

0

Retaining wall

12-Jan-15*

06-Mar-15

17-Feb-15

13-Apr-15

26

ST784

23

23 Standard 5 Day Workweek

0

Erect structural steel and deck

20-Jan-15

20-Feb-15

20-Jan-15

20-Feb-15

0

ST544

23

23 Standard 5 Day Workweek

0

Erect structural steel and deck

20-Jan-15

20-Feb-15

16-Feb-15

19-Mar-15

19

ST1074

25

25 Standard 5 Day Workweek

0

Cold formed metal framing and sheathing

23-Jan-15

27-Feb-15

23-Jan-15

27-Feb-15

0

ST1254

12

12 Standard 5 Day Workweek

0

Stone under slab rough-in

23-Jan-15

10-Feb-15

23-Jan-15

10-Feb-15

0

ST1044

15

15 Standard 5 Day Workweek

0

Stone under slab

10-Feb-15

03-Mar-15

10-Feb-15

03-Mar-15

0

A8760

666

666 Standard 5 Day Workweek

0

Project record documents

12-Feb-15

01-Sep-17

12-Feb-15

01-Sep-17

0

ST834

25

25 Standard 5 Day Workweek

0

Cold formed metal framing and sheathing

20-Feb-15

27-Mar-15

20-Feb-15

27-Mar-15

0

ST1014

12

12 Standard 5 Day Workweek

0

Stone under slab rough-in

20-Feb-15

10-Mar-15

20-Feb-15

10-Mar-15

0

ST594

25

25 Standard 5 Day Workweek

0

Cold formed metal framing and sheathing

20-Feb-15

27-Mar-15

19-Mar-15

23-Apr-15

19

ST1094

18

18 Standard 5 Day Workweek

0

Install air membrane

27-Feb-15

25-Mar-15

27-Feb-15

25-Mar-15

0

ST1034

32

32 Standard 5 Day Workweek

0

Pour concrete slab on deck

03-Mar-15

16-Apr-15

03-Mar-15

16-Apr-15

0

ST804

15

15 Standard 5 Day Workweek

0

Stone under slab

10-Mar-15

31-Mar-15

10-Mar-15

31-Mar-15

0

Page 4 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

ST774

12

12 Standard 5 Day Workweek

0

Stone under slab rough-in

10-Mar-15

26-Mar-15

20-Mar-15

07-Apr-15

8

ST1084

20

20 Standard 5 Day Workweek

0

Spray urethane insulation

25-Mar-15

22-Apr-15

25-Mar-15

22-Apr-15

0

ST564

15

15 Standard 5 Day Workweek

0

Stone under slab

26-Mar-15

16-Apr-15

07-Apr-15

28-Apr-15

8

ST854

18

18 Standard 5 Day Workweek

0

Install air membrane

27-Mar-15

22-Apr-15

27-Mar-15

22-Apr-15

0

ST614

18

18 Standard 5 Day Workweek

0

Install air membrane

27-Mar-15

22-Apr-15

23-Apr-15

19-May-15

19

ST794

32

32 Standard 5 Day Workweek

0

Pour concrete slab on deck

31-Mar-15

14-May-15

31-Mar-15

14-May-15

0

S296

30

30 Standard 5 Day Workweek

0

Exterior masonry seat walls and site walls

13-Apr-15*

22-May-15

14-Apr-15

25-May-15

1

ST1064

15

15 Standard 5 Day Workweek

0

Pour concrete slab on grade

16-Apr-15

07-May-15

16-Apr-15

07-May-15

0

ST554

32

32 Standard 5 Day Workweek

0

Pour concrete slab on deck

16-Apr-15

01-Jun-15

28-Apr-15

11-Jun-15

8

ST844

20

20 Standard 5 Day Workweek

0

Spray urethane insulation

22-Apr-15

20-May-15

22-Apr-15

20-May-15

0

ST1104

10

10 Standard 5 Day Workweek

0

Wood blocking & sheathing on roof

22-Apr-15

06-May-15

22-Apr-15

06-May-15

0

A8820

5

5 Standard 5 Day Workweek

0

Metal stairs

22-Apr-15*

29-Apr-15

22-Apr-15

29-Apr-15

0

ST604

20

20 Standard 5 Day Workweek

0

Spray urethane insulation

22-Apr-15

20-May-15

19-May-15

16-Jun-15

19

ST1144

20

20 Standard 5 Day Workweek

0

Insulated metal wall panels

22-Apr-15

20-May-15

30-Jun-15

28-Jul-15

49

100

100 Standard 5 Day Workweek

0

Install Geo Exchange Field

23-Apr-15*

10-Sep-15

23-Apr-15

10-Sep-15

0

A8830

4

4 Standard 5 Day Workweek

0

Install railings

29-Apr-15*

05-May-15

29-Apr-15

05-May-15

0

A8840

13

13 Standard 5 Day Workweek

0

Interior H.M frames

05-May-15*

22-May-15

05-May-15

22-May-15

0

ST1124

11

11 Standard 5 Day Workweek

0

Roof Drains

06-May-15

21-May-15

06-May-15

21-May-15

0

ST1114

7

7 Standard 5 Day Workweek

0

Roof curbs

06-May-15

15-May-15

12-Jun-15

23-Jun-15

27

ST1054

20

20 Standard 5 Day Workweek

0

CMU walls

07-May-15

04-Jun-15

07-May-15

04-Jun-15

0

S246

40

40 Standard 5 Day Workweek

0

Place trees and shrubbery

14-May-15*

09-Jul-15

14-May-15

09-Jul-15

0

ST824

15

15 Standard 5 Day Workweek

0

Pour concrete slab on grade

14-May-15

04-Jun-15

14-May-15

04-Jun-15

0

ST1134

5

5 Standard 5 Day Workweek

0

Roof top equipment

15-May-15

22-May-15

23-Jun-15

30-Jun-15

27

ST864

10

10 Standard 5 Day Workweek

0

Wood blocking & sheathing on roof

20-May-15

03-Jun-15

20-May-15

03-Jun-15

0

ST624

10

10 Standard 5 Day Workweek

0

Wood blocking & sheathing on roof

20-May-15

03-Jun-15

16-Jun-15

30-Jun-15

19

S406

Page 5 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

ST904

20

20 Standard 5 Day Workweek

0

Insulated metal wall panels

20-May-15

17-Jun-15

28-Jul-15

25-Aug-15

49

ST664

20

20 Standard 5 Day Workweek

0

Insulated metal wall panels

20-May-15

17-Jun-15

24-Aug-15

21-Sep-15

68

ST1154

15

15 Standard 5 Day Workweek

0

Metal soffit and fascia

21-May-15

11-Jun-15

21-May-15

11-Jun-15

0

A8850

9

9 Standard 5 Day Workweek

0

Drywall and spackliing

22-May-15*

04-Jun-15

22-May-15

04-Jun-15

0

S356

20

20 Standard 5 Day Workweek

0

Retaining wall for landscaping

25-May-15*

19-Jun-15

29-Jul-15

25-Aug-15

47

S276

65

65 Standard 5 Day Workweek

0

sidewalks and ramp concrete pour

26-May-15*

24-Aug-15

26-May-15

24-Aug-15

0

ST584

15

15 Standard 5 Day Workweek

0

Pour concrete slab on grade

01-Jun-15

22-Jun-15

11-Jun-15

02-Jul-15

8

ST884

11

11 Standard 5 Day Workweek

0

Roof Drains

03-Jun-15

18-Jun-15

03-Jun-15

18-Jun-15

0

ST644

11

11 Standard 5 Day Workweek

0

Roof Drains

03-Jun-15

18-Jun-15

30-Jun-15

15-Jul-15

19

ST874

7

7 Standard 5 Day Workweek

0

Roof curbs

03-Jun-15

12-Jun-15

10-Jul-15

21-Jul-15

27

ST634

7

7 Standard 5 Day Workweek

0

Roof curbs

03-Jun-15

12-Jun-15

06-Aug-15

17-Aug-15

46

ST814

20

20 Standard 5 Day Workweek

0

CMU walls

04-Jun-15

02-Jul-15

04-Jun-15

02-Jul-15

0

A8860

5

5 Standard 5 Day Workweek

0

Caulking

04-Jun-15*

11-Jun-15

04-Jun-15

11-Jun-15

0

ST1264

29

29 Standard 5 Day Workweek

0

Layout stone veneer

04-Jun-15

15-Jul-15

04-Jun-15

15-Jul-15

0

ST1204

37

37 Standard 5 Day Workweek

0

Masonry veneer

04-Jun-15

27-Jul-15

05-Jun-15

28-Jul-15

1

ST1164

13

13 Standard 5 Day Workweek

0

Roof metal edges

11-Jun-15

30-Jun-15

11-Jun-15

30-Jun-15

0

A8870

7

7 Standard 5 Day Workweek

0

Ceramic and porcelain wall/floor tiles

11-Jun-15*

22-Jun-15

11-Jun-15

22-Jun-15

0

ST894

5

5 Standard 5 Day Workweek

0

Roof top equipment

12-Jun-15

19-Jun-15

21-Jul-15

28-Jul-15

27

ST654

5

5 Standard 5 Day Workweek

0

Roof top equipment

12-Jun-15

19-Jun-15

17-Aug-15

24-Aug-15

46

ST914

15

15 Standard 5 Day Workweek

0

Metal soffit and fascia

18-Jun-15

09-Jul-15

18-Jun-15

09-Jul-15

0

ST674

15

15 Standard 5 Day Workweek

0

Metal soffit and fascia

18-Jun-15

09-Jul-15

15-Jul-15

05-Aug-15

19

A8880

9

9 Standard 5 Day Workweek

0

Painting

22-Jun-15*

03-Jul-15

22-Jun-15

03-Jul-15

0

ST1184

20

20 Standard 5 Day Workweek

0

Metal roof ladders

30-Jun-15

28-Jul-15

30-Jun-15

28-Jul-15

0

ST574

20

20 Standard 5 Day Workweek

0

CMU walls

02-Jul-15

30-Jul-15

02-Jul-15

30-Jul-15

0

ST964

37

37 Standard 5 Day Workweek

0

Masonry veneer

02-Jul-15

24-Aug-15

03-Jul-15

25-Aug-15

1

Page 6 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8890

6

6 Standard 5 Day Workweek

0

Wall coverings

03-Jul-15*

14-Jul-15

03-Jul-15

14-Jul-15

0

ST924

13

13 Standard 5 Day Workweek

0

Roof metal edges

09-Jul-15

28-Jul-15

09-Jul-15

28-Jul-15

0

ST684

13

13 Standard 5 Day Workweek

0

Roof metal edges

09-Jul-15

28-Jul-15

05-Aug-15

24-Aug-15

19

A8900

7

7 Standard 5 Day Workweek

0

Acoustical ceiling grid

14-Jul-15*

23-Jul-15

14-Jul-15

23-Jul-15

0

A8910

10

10 Standard 5 Day Workweek

0

PC AG san/rw

23-Jul-15*

06-Aug-15

23-Jul-15

06-Aug-15

0

ST1174

10

10 Standard 5 Day Workweek

0

Exterior Caulking

27-Jul-15

10-Aug-15

28-Jul-15

11-Aug-15

1

ST944

20

20 Standard 5 Day Workweek

0

Metal roof ladders

28-Jul-15

25-Aug-15

28-Jul-15

25-Aug-15

0

ST1194

10

10 Standard 5 Day Workweek

0

Aluminum windows & curtain walls

28-Jul-15

11-Aug-15

28-Jul-15

11-Aug-15

0

ST704

20

20 Standard 5 Day Workweek

0

Metal roof ladders

28-Jul-15

25-Aug-15

24-Aug-15

21-Sep-15

19

ST724

37

37 Standard 5 Day Workweek

0

Masonry veneer

30-Jul-15

21-Sep-15

30-Jul-15

21-Sep-15

0

A8920

10

10 Standard 5 Day Workweek

0

PC overhead pipe

06-Aug-15*

20-Aug-15

06-Aug-15

20-Aug-15

0

ST1214

25

25 Standard 5 Day Workweek

0

Aluminum entrance doors/sliding doors

11-Aug-15

15-Sep-15

11-Aug-15

15-Sep-15

0

A8930

5

5 Standard 5 Day Workweek

0

PC insulation

20-Aug-15*

27-Aug-15

20-Aug-15

27-Aug-15

0

ST934

10

10 Standard 5 Day Workweek

0

Exterior Caulking

24-Aug-15

07-Sep-15

25-Aug-15

08-Sep-15

1

S326

35

35 Standard 5 Day Workweek

0

Fiberglass bus stations

25-Aug-15*

12-Oct-15

25-Aug-15

12-Oct-15

0

S346

25

25 Standard 5 Day Workweek

0

Parking control equipment

25-Aug-15*

28-Sep-15

26-Aug-15

29-Sep-15

1

S366

20

20 Standard 5 Day Workweek

0

Timber guide railin gs

25-Aug-15*

21-Sep-15

02-Sep-15

29-Sep-15

6

ST954

10

10 Standard 5 Day Workweek

0

Aluminum windows & curtain walls

25-Aug-15

08-Sep-15

25-Aug-15

08-Sep-15

0

A7090

5

5 Standard 5 Day Workweek

0

Metal stairs

25-Aug-15*

01-Sep-15

25-Aug-15

01-Sep-15

0

ST714

10

10 Standard 5 Day Workweek

0

Aluminum windows & curtain walls

25-Aug-15

08-Sep-15

21-Sep-15

05-Oct-15

19

A8940

10

10 Standard 5 Day Workweek

0

PC drop sprinkler head

27-Aug-15*

10-Sep-15

27-Aug-15

10-Sep-15

0

A7100

4

4 Standard 5 Day Workweek

0

Install railings

01-Sep-15*

07-Sep-15

01-Sep-15

07-Sep-15

0

A7110

13

13 Standard 5 Day Workweek

0

Interior H.M frames

07-Sep-15*

24-Sep-15

07-Sep-15

24-Sep-15

0

ST974

25

25 Standard 5 Day Workweek

0

Aluminum entrance doors/sliding doors

08-Sep-15

13-Oct-15

08-Sep-15

13-Oct-15

0

A8950

5

5 Standard 5 Day Workweek

0

PC casework fixtures

10-Sep-15*

17-Sep-15

10-Sep-15

17-Sep-15

0

Page 7 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

T57

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

40

40 Standard 5 Day Workweek

0

Provide temporary heat

10-Sep-15*

05-Nov-15

10-Sep-15

05-Nov-15

0

A8960

5

5 Standard 5 Day Workweek

0

PC toilet fixtures

17-Sep-15*

24-Sep-15

17-Sep-15

24-Sep-15

0

ST694

10

10 Standard 5 Day Workweek

0

Exterior Caulking

21-Sep-15

05-Oct-15

21-Sep-15

05-Oct-15

0

A8980

5

5 Standard 5 Day Workweek

0

HC hangers

24-Sep-15*

01-Oct-15

24-Sep-15

01-Oct-15

0

A7120

9

9 Standard 5 Day Workweek

0

Drywall and spackliing

24-Sep-15*

07-Oct-15

24-Sep-15

07-Oct-15

0

S286

46

46 Standard 5 Day Workweek

0

Unit Pavers

29-Sep-15*

01-Dec-15

30-Sep-15

02-Dec-15

1

A8990

7

7 Standard 5 Day Workweek

0

HC pipe install

01-Oct-15*

12-Oct-15

01-Oct-15

12-Oct-15

0

ST734

25

25 Standard 5 Day Workweek

0

Aluminum entrance doors/sliding doors

05-Oct-15

09-Nov-15

05-Oct-15

09-Nov-15

0

A7130

5

5 Standard 5 Day Workweek

0

Caulking

07-Oct-15*

14-Oct-15

07-Oct-15

14-Oct-15

0

A9000

5

5 Standard 5 Day Workweek

0

HC duct install

12-Oct-15*

19-Oct-15

12-Oct-15

19-Oct-15

0

S236

50

50 Standard 5 Day Workweek

0

Final Landscaping

13-Oct-15*

21-Dec-15

13-Oct-15

21-Dec-15

0

A7140

7

7 Standard 5 Day Workweek

0

Ceramic and porcelain wall/floor tiles

14-Oct-15*

23-Oct-15

14-Oct-15

23-Oct-15

0

A9010

11

11 Standard 5 Day Workweek

0

HC ATC rough-in

19-Oct-15*

03-Nov-15

19-Oct-15

03-Nov-15

0

A7150

9

9 Standard 5 Day Workweek

0

Painting

23-Oct-15*

05-Nov-15

23-Oct-15

05-Nov-15

0

A9020

15

15 Standard 5 Day Workweek

0

HC GRD install

03-Nov-15*

23-Nov-15

03-Nov-15

23-Nov-15

0

A7160

6

6 Standard 5 Day Workweek

0

Wall coverings

05-Nov-15*

16-Nov-15

05-Nov-15

16-Nov-15

0

A7700

5

5 Standard 5 Day Workweek

0

Metal stairs

09-Nov-15*

16-Nov-15

09-Nov-15

16-Nov-15

0

A7170

7

7 Standard 5 Day Workweek

0

Acoustical ceiling grid

16-Nov-15*

25-Nov-15

16-Nov-15

25-Nov-15

0

A7710

4

4 Standard 5 Day Workweek

0

Install railings

16-Nov-15*

20-Nov-15

16-Nov-15

20-Nov-15

0

A7720

13

13 Standard 5 Day Workweek

0

Interior H.M frames

20-Nov-15*

09-Dec-15

20-Nov-15

09-Dec-15

0

A9030

12

12 Standard 5 Day Workweek

0

HC equipment and final connections

23-Nov-15*

09-Dec-15

23-Nov-15

09-Dec-15

0

A7180

10

10 Standard 5 Day Workweek

0

PC AG san/rw

25-Nov-15*

09-Dec-15

25-Nov-15

09-Dec-15

0

S306

38

38 Standard 5 Day Workweek

0

Exterior site railings

02-Dec-15*

22-Jan-16

03-Dec-15

25-Jan-16

1

A7190

10

10 Standard 5 Day Workweek

0

PC overhead pipe

09-Dec-15*

23-Dec-15

09-Dec-15

23-Dec-15

0

A7730

9

9 Standard 5 Day Workweek

0

Drywall and spackliing

09-Dec-15*

22-Dec-15

09-Dec-15

22-Dec-15

0

Page 8 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A9040

10

10 Standard 5 Day Workweek

0

HC kitchen equipment and hookups

09-Dec-15*

23-Dec-15

09-Dec-15

23-Dec-15

0

S316

25

25 Standard 5 Day Workweek

0

Position Site seating

22-Dec-15*

25-Jan-16

22-Dec-15

25-Jan-16

0

A7740

5

5 Standard 5 Day Workweek

0

Caulking

22-Dec-15*

29-Dec-15

22-Dec-15

29-Dec-15

0

A9430

1

1 Standard 5 Day Workweek

0

Substantial milestone

23-Dec-15*

24-Dec-15

23-Dec-15

24-Dec-15

0

A9050

12

12 Standard 5 Day Workweek

0

EC rough-in walls

23-Dec-15*

08-Jan-16

23-Dec-15

08-Jan-16

0

A7200

5

5 Standard 5 Day Workweek

0

PC insulation

24-Dec-15*

31-Dec-15

24-Dec-15

31-Dec-15

0

A7750

7

7 Standard 5 Day Workweek

0

Ceramic and porcelain wall/floor tiles

29-Dec-15*

07-Jan-16

29-Dec-15

07-Jan-16

0

A7210

10

10 Standard 5 Day Workweek

0

PC drop sprinkler head

31-Dec-15*

14-Jan-16

31-Dec-15

14-Jan-16

0

A7760

9

9 Standard 5 Day Workweek

0

Painting

07-Jan-16*

20-Jan-16

07-Jan-16

20-Jan-16

0

A9060

14

14 Standard 5 Day Workweek

0

EC overhead rough-in

08-Jan-16*

28-Jan-16

08-Jan-16

28-Jan-16

0

A7220

5

5 Standard 5 Day Workweek

0

PC casework fixtures

14-Jan-16*

21-Jan-16

14-Jan-16

21-Jan-16

0

A7770

6

6 Standard 5 Day Workweek

0

Wall coverings

20-Jan-16*

29-Jan-16

20-Jan-16

29-Jan-16

0

A7230

5

5 Standard 5 Day Workweek

0

PC toilet fixtures

21-Jan-16*

28-Jan-16

21-Jan-16

28-Jan-16

0

S416

43

43 Standard 5 Day Workweek

0

Final placement of trees and shrubbery

26-Jan-16*

24-Mar-16

26-Jan-16

24-Mar-16

0

A7240

6

6 Standard 5 Day Workweek

0

PC kitchen equipment hookups

28-Jan-16*

05-Feb-16

28-Jan-16

05-Feb-16

0

A9070

14

14 Standard 5 Day Workweek

0

EC cable tray

28-Jan-16*

17-Feb-16

28-Jan-16

17-Feb-16

0

A7780

7

7 Standard 5 Day Workweek

0

Acoustical ceiling grid

29-Jan-16*

09-Feb-16

29-Jan-16

09-Feb-16

0

A7250

5

5 Standard 5 Day Workweek

0

HC hangers

05-Feb-16*

12-Feb-16

05-Feb-16

12-Feb-16

0

A7790

10

10 Standard 5 Day Workweek

0

PC AG san/rw

09-Feb-16*

23-Feb-16

09-Feb-16

23-Feb-16

0

A7260

7

7 Standard 5 Day Workweek

0

HC pipe install

12-Feb-16*

23-Feb-16

12-Feb-16

23-Feb-16

0

A9080

9

9 Standard 5 Day Workweek

0

EC wiring

17-Feb-16*

01-Mar-16

17-Feb-16

01-Mar-16

0

A7270

5

5 Standard 5 Day Workweek

0

HC duct install

23-Feb-16*

01-Mar-16

23-Feb-16

01-Mar-16

0

A7800

10

10 Standard 5 Day Workweek

0

PC overhead pipe

23-Feb-16*

08-Mar-16

23-Feb-16

08-Mar-16

0

A9090

8

8 Standard 5 Day Workweek

0

EC light fixtures

01-Mar-16*

11-Mar-16

01-Mar-16

11-Mar-16

0

A7280

11

11 Standard 5 Day Workweek

0

HC ATC rough-in

01-Mar-16*

16-Mar-16

01-Mar-16

16-Mar-16

0

Page 9 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7810

5

5 Standard 5 Day Workweek

0

PC insulation

08-Mar-16*

15-Mar-16

08-Mar-16

15-Mar-16

0

A9100

5

5 Standard 5 Day Workweek

0

EC wring devices

11-Mar-16*

18-Mar-16

11-Mar-16

18-Mar-16

0

A7820

10

10 Standard 5 Day Workweek

0

PC drop sprinkler head

15-Mar-16*

29-Mar-16

15-Mar-16

29-Mar-16

0

A7290

15

15 Standard 5 Day Workweek

0

HC GRD install

16-Mar-16*

05-Apr-16

16-Mar-16

05-Apr-16

0

A9110

6

6 Standard 5 Day Workweek

0

EC fire alarm and security

18-Mar-16*

28-Mar-16

18-Mar-16

28-Mar-16

0

S266

20

20 Standard 5 Day Workweek

0

Concrete bumper blocks

25-Mar-16*

21-Apr-16

25-Mar-16

21-Apr-16

0

A9120

10

10 Standard 5 Day Workweek

0

EC kitchen equipment and hookups

28-Mar-16*

11-Apr-16

28-Mar-16

11-Apr-16

0

A7830

5

5 Standard 5 Day Workweek

0

PC casework fixtures

29-Mar-16*

05-Apr-16

29-Mar-16

05-Apr-16

0

A7840

5

5 Standard 5 Day Workweek

0

PC toilet fixtures

05-Apr-16*

12-Apr-16

05-Apr-16

12-Apr-16

0

A7300

12

12 Standard 5 Day Workweek

0

HC equipment and final connections

05-Apr-16*

21-Apr-16

05-Apr-16

21-Apr-16

0

A9130

5

5 Standard 5 Day Workweek

0

EC hook ups and connections

11-Apr-16*

18-Apr-16

11-Apr-16

18-Apr-16

0

A7850

6

6 Standard 5 Day Workweek

0

PC kitchen equipment hookups

12-Apr-16*

20-Apr-16

12-Apr-16

20-Apr-16

0

A9140

8

8 Standard 5 Day Workweek

0

Casework/millwork

18-Apr-16*

28-Apr-16

18-Apr-16

28-Apr-16

0

A7860

5

5 Standard 5 Day Workweek

0

HC hangers

20-Apr-16*

27-Apr-16

20-Apr-16

27-Apr-16

0

A7310

10

10 Standard 5 Day Workweek

0

HC kitchen equipment and hookups

21-Apr-16*

05-May-16

21-Apr-16

05-May-16

0

S256

26

26 Standard 5 Day Workweek

0

site linestripping and signage

22-Apr-16*

27-May-16

22-Apr-16

27-May-16

0

A7870

7

7 Standard 5 Day Workweek

0

HC pipe install

27-Apr-16*

06-May-16

27-Apr-16

06-May-16

0

A9150

8

8 Standard 5 Day Workweek

0

Resilent tile base and floor

28-Apr-16*

10-May-16

28-Apr-16

10-May-16

0

A7320

12

12 Standard 5 Day Workweek

0

EC rough-in walls

05-May-16*

23-May-16

05-May-16

23-May-16

0

A7880

5

5 Standard 5 Day Workweek

0

HC duct install

06-May-16*

13-May-16

06-May-16

13-May-16

0

A9160

8

8 Standard 5 Day Workweek

0

Seamless vinyl flooring

10-May-16*

20-May-16

10-May-16

20-May-16

0

A7890

11

11 Standard 5 Day Workweek

0

HC ATC rough-in

13-May-16*

30-May-16

13-May-16

30-May-16

0

A9170

11

11 Standard 5 Day Workweek

0

Carpet tiles

20-May-16*

06-Jun-16

20-May-16

06-Jun-16

0

A7330

14

14 Standard 5 Day Workweek

0

EC overhead rough-in

23-May-16*

10-Jun-16

23-May-16

10-Jun-16

0

A7900

15

15 Standard 5 Day Workweek

0

HC GRD install

30-May-16*

17-Jun-16

30-May-16

17-Jun-16

0

Page 10 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A9180

7

7 Standard 5 Day Workweek

0

Install rubber stairs, treads and landings

06-Jun-16*

15-Jun-16

06-Jun-16

15-Jun-16

0

A7340

14

14 Standard 5 Day Workweek

0

EC cable tray

10-Jun-16*

30-Jun-16

10-Jun-16

30-Jun-16

0

A9190

6

6 Standard 5 Day Workweek

0

Doors and Hardware

15-Jun-16*

23-Jun-16

15-Jun-16

23-Jun-16

0

A7910

12

12 Standard 5 Day Workweek

0

HC equipment and final connections

17-Jun-16*

05-Jul-16

17-Jun-16

05-Jul-16

0

A9200

8

8 Standard 5 Day Workweek

0

Interior glass partitions

23-Jun-16*

05-Jul-16

23-Jun-16

05-Jul-16

0

A7350

9

9 Standard 5 Day Workweek

0

EC wiring

30-Jun-16*

13-Jul-16

30-Jun-16

13-Jul-16

0

A9210

5

5 Standard 5 Day Workweek

0

Wood wall panels

05-Jul-16*

12-Jul-16

05-Jul-16

12-Jul-16

0

A7920

10

10 Standard 5 Day Workweek

0

HC kitchen equipment and hookups

05-Jul-16*

19-Jul-16

05-Jul-16

19-Jul-16

0

A9220

5

5 Standard 5 Day Workweek

0

Visual display surfaces

12-Jul-16*

19-Jul-16

12-Jul-16

19-Jul-16

0

A7360

8

8 Standard 5 Day Workweek

0

EC light fixtures

13-Jul-16*

25-Jul-16

13-Jul-16

25-Jul-16

0

A9230

5

5 Standard 5 Day Workweek

0

Signage

19-Jul-16*

26-Jul-16

19-Jul-16

26-Jul-16

0

A7930

12

12 Standard 5 Day Workweek

0

EC rough-in walls

19-Jul-16*

04-Aug-16

19-Jul-16

04-Aug-16

0

A7370

5

5 Standard 5 Day Workweek

0

EC wring devices

25-Jul-16*

01-Aug-16

25-Jul-16

01-Aug-16

0

A9240

3

3 Standard 5 Day Workweek

0

Wood ceiling

26-Jul-16*

29-Jul-16

26-Jul-16

29-Jul-16

0

A9250

11

11 Standard 5 Day Workweek

0

Place Acoustical ceiling tiles

29-Jul-16*

12-Aug-16

29-Jul-16

12-Aug-16

0

A7380

6

6 Standard 5 Day Workweek

0

EC fire alarm and security

01-Aug-16*

09-Aug-16

01-Aug-16

09-Aug-16

0

A7940

14

14 Standard 5 Day Workweek

0

EC overhead rough-in

04-Aug-16*

24-Aug-16

04-Aug-16

24-Aug-16

0

A7390

10

10 Standard 5 Day Workweek

0

EC kitchen equipment and hookups

09-Aug-16*

23-Aug-16

09-Aug-16

23-Aug-16

0

A9260

8

8 Standard 5 Day Workweek

0

Tiolet complartments

12-Aug-16*

24-Aug-16

12-Aug-16

24-Aug-16

0

A7400

5

5 Standard 5 Day Workweek

0

EC hook ups and connections

23-Aug-16*

30-Aug-16

23-Aug-16

30-Aug-16

0

A7950

14

14 Standard 5 Day Workweek

0

EC cable tray

24-Aug-16*

13-Sep-16

24-Aug-16

13-Sep-16

0

A9270

6

6 Standard 5 Day Workweek

0

Fire protection specialities

24-Aug-16*

01-Sep-16

24-Aug-16

01-Sep-16

0

A7410

8

8 Standard 5 Day Workweek

0

Casework/millwork

30-Aug-16*

09-Sep-16

30-Aug-16

09-Sep-16

0

A9290

10

10 Standard 5 Day Workweek

0

Window shades

01-Sep-16*

15-Sep-16

01-Sep-16

15-Sep-16

0

A7420

8

8 Standard 5 Day Workweek

0

Resilent tile base and floor

09-Sep-16*

21-Sep-16

09-Sep-16

21-Sep-16

0

Page 11 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7960

9

9 Standard 5 Day Workweek

0

EC wiring

13-Sep-16*

26-Sep-16

13-Sep-16

26-Sep-16

0

A9300

7

7 Standard 5 Day Workweek

0

Wire mesh partitions

15-Sep-16*

26-Sep-16

15-Sep-16

26-Sep-16

0

A7430

8

8 Standard 5 Day Workweek

0

Seamless vinyl flooring

21-Sep-16*

03-Oct-16

21-Sep-16

03-Oct-16

0

A7970

8

8 Standard 5 Day Workweek

0

EC light fixtures

26-Sep-16*

06-Oct-16

26-Sep-16

06-Oct-16

0

A9310

13

13 Standard 5 Day Workweek

0

Install lockers

26-Sep-16*

13-Oct-16

26-Sep-16

13-Oct-16

0

A7440

11

11 Standard 5 Day Workweek

0

Carpet tiles

03-Oct-16*

18-Oct-16

03-Oct-16

18-Oct-16

0

A7980

5

5 Standard 5 Day Workweek

0

EC wring devices

06-Oct-16*

13-Oct-16

06-Oct-16

13-Oct-16

0

A7990

6

6 Standard 5 Day Workweek

0

EC fire alarm and security

13-Oct-16*

21-Oct-16

13-Oct-16

21-Oct-16

0

A9320

9

9 Standard 5 Day Workweek

0

Install hood and walk-ins

13-Oct-16*

26-Oct-16

13-Oct-16

26-Oct-16

0

A7450

7

7 Standard 5 Day Workweek

0

Install rubber stairs, treads and landings

18-Oct-16*

27-Oct-16

18-Oct-16

27-Oct-16

0

A8000

10

10 Standard 5 Day Workweek

0

EC kitchen equipment and hookups

21-Oct-16*

04-Nov-16

21-Oct-16

04-Nov-16

0

A9340

5

5 Standard 5 Day Workweek

0

Install and setup food service equipment

26-Oct-16*

02-Nov-16

26-Oct-16

02-Nov-16

0

A7460

6

6 Standard 5 Day Workweek

0

Doors and Hardware

27-Oct-16*

04-Nov-16

27-Oct-16

04-Nov-16

0

A9350

5

5 Standard 5 Day Workweek

0

Glass wall folding partition

02-Nov-16*

09-Nov-16

02-Nov-16

09-Nov-16

0

A7470

8

8 Standard 5 Day Workweek

0

Interior glass partitions

04-Nov-16*

16-Nov-16

04-Nov-16

16-Nov-16

0

A8010

5

5 Standard 5 Day Workweek

0

EC hook ups and connections

04-Nov-16*

11-Nov-16

04-Nov-16

11-Nov-16

0

A9360

12

12 Standard 5 Day Workweek

0

Loading dock equipment

09-Nov-16*

25-Nov-16

09-Nov-16

25-Nov-16

0

A8020

8

8 Standard 5 Day Workweek

0

Casework/millwork

11-Nov-16*

23-Nov-16

11-Nov-16

23-Nov-16

0

A7480

5

5 Standard 5 Day Workweek

0

Wood wall panels

16-Nov-16*

23-Nov-16

16-Nov-16

23-Nov-16

0

A8030

8

8 Standard 5 Day Workweek

0

Resilent tile base and floor

23-Nov-16*

05-Dec-16

23-Nov-16

05-Dec-16

0

A7490

5

5 Standard 5 Day Workweek

0

Visual display surfaces

23-Nov-16*

30-Nov-16

23-Nov-16

30-Nov-16

0

A9370

5

5 Standard 5 Day Workweek

0

Paint gym ceiling

25-Nov-16*

02-Dec-16

25-Nov-16

02-Dec-16

0

A7500

5

5 Standard 5 Day Workweek

0

Signage

30-Nov-16*

07-Dec-16

30-Nov-16

07-Dec-16

0

A9380

7

7 Standard 5 Day Workweek

0

Gym equipment

02-Dec-16*

13-Dec-16

02-Dec-16

13-Dec-16

0

A8040

8

8 Standard 5 Day Workweek

0

Seamless vinyl flooring

05-Dec-16*

15-Dec-16

05-Dec-16

15-Dec-16

0

Page 12 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7510

3

3 Standard 5 Day Workweek

0

Wood ceiling

07-Dec-16*

12-Dec-16

07-Dec-16

12-Dec-16

0

A7520

11

11 Standard 5 Day Workweek

0

Place Acoustical ceiling tiles

12-Dec-16*

26-Dec-16

12-Dec-16

26-Dec-16

0

A9390

9

9 Standard 5 Day Workweek

0

Gym dividers

13-Dec-16*

26-Dec-16

13-Dec-16

26-Dec-16

0

A8050

11

11 Standard 5 Day Workweek

0

Carpet tiles

15-Dec-16*

30-Dec-16

15-Dec-16

30-Dec-16

0

A9400

7

7 Standard 5 Day Workweek

0

Install hardwood flooring

26-Dec-16*

04-Jan-17

26-Dec-16

04-Jan-17

0

A7530

8

8 Standard 5 Day Workweek

0

Tiolet complartments

26-Dec-16*

05-Jan-17

26-Dec-16

05-Jan-17

0

A8060

7

7 Standard 5 Day Workweek

0

Install rubber stairs, treads and landings

30-Dec-16*

10-Jan-17

30-Dec-16

10-Jan-17

0

A9410

6

6 Standard 5 Day Workweek

0

Install collapsable belachers

04-Jan-17*

12-Jan-17

04-Jan-17

12-Jan-17

0

A7540

6

6 Standard 5 Day Workweek

0

Fire protection specialities

05-Jan-17*

13-Jan-17

05-Jan-17

13-Jan-17

0

A8070

6

6 Standard 5 Day Workweek

0

Doors and Hardware

10-Jan-17*

18-Jan-17

10-Jan-17

18-Jan-17

0

A9420

8

8 Standard 5 Day Workweek

0

Hydraulic elevators

12-Jan-17*

24-Jan-17

12-Jan-17

24-Jan-17

0

A7560

10

10 Standard 5 Day Workweek

0

Window shades

13-Jan-17*

27-Jan-17

13-Jan-17

27-Jan-17

0

A8080

8

8 Standard 5 Day Workweek

0

Interior glass partitions

18-Jan-17*

30-Jan-17

18-Jan-17

30-Jan-17

0

A9330

10

10 Standard 5 Day Workweek

0

Install kitchen tiles

24-Jan-17

07-Feb-17

24-Jan-17

07-Feb-17

0

A8720

9

9 Standard 5 Day Workweek

0

Checklist enrollment building

24-Jan-17

06-Feb-17

21-Aug-17

01-Sep-17

149

A7570

7

7 Standard 5 Day Workweek

0

Wire mesh partitions

27-Jan-17*

07-Feb-17

27-Jan-17

07-Feb-17

0

A8090

5

5 Standard 5 Day Workweek

0

Wood wall panels

30-Jan-17*

06-Feb-17

30-Jan-17

06-Feb-17

0

A8100

5

5 Standard 5 Day Workweek

0

Visual display surfaces

06-Feb-17*

13-Feb-17

06-Feb-17

13-Feb-17

0

A7580

13

13 Standard 5 Day Workweek

0

Install lockers

07-Feb-17*

24-Feb-17

07-Feb-17

24-Feb-17

0

A9280

9

9 Standard 5 Day Workweek

0

Motorized projection screens

07-Feb-17

20-Feb-17

07-Feb-17

20-Feb-17

0

A8110

5

5 Standard 5 Day Workweek

0

Signage

13-Feb-17*

20-Feb-17

13-Feb-17

20-Feb-17

0

A8120

3

3 Standard 5 Day Workweek

0

Wood ceiling

20-Feb-17*

23-Feb-17

20-Feb-17

23-Feb-17

0

A8130

11

11 Standard 5 Day Workweek

0

Place Acoustical ceiling tiles

23-Feb-17*

09-Mar-17

23-Feb-17

09-Mar-17

0

A7590

9

9 Standard 5 Day Workweek

0

Install hood and walk-ins

24-Feb-17*

09-Mar-17

24-Feb-17

09-Mar-17

0

A7610

5

5 Standard 5 Day Workweek

0

Install and setup food service equipment

09-Mar-17*

16-Mar-17

09-Mar-17

16-Mar-17

0

Page 13 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8140

8

8 Standard 5 Day Workweek

0

Tiolet complartments

09-Mar-17*

21-Mar-17

09-Mar-17

21-Mar-17

0

A7620

5

5 Standard 5 Day Workweek

0

Glass wall folding partition

16-Mar-17*

23-Mar-17

16-Mar-17

23-Mar-17

0

A8150

6

6 Standard 5 Day Workweek

0

Fire protection specialities

21-Mar-17*

29-Mar-17

21-Mar-17

29-Mar-17

0

A7630

12

12 Standard 5 Day Workweek

0

Loading dock equipment

23-Mar-17*

10-Apr-17

23-Mar-17

10-Apr-17

0

A8170

10

10 Standard 5 Day Workweek

0

Window shades

29-Mar-17*

12-Apr-17

29-Mar-17

12-Apr-17

0

A7640

5

5 Standard 5 Day Workweek

0

Paint gym ceiling

10-Apr-17*

17-Apr-17

10-Apr-17

17-Apr-17

0

A8180

7

7 Standard 5 Day Workweek

0

Wire mesh partitions

12-Apr-17*

21-Apr-17

12-Apr-17

21-Apr-17

0

A7650

7

7 Standard 5 Day Workweek

0

Gym equipment

17-Apr-17*

26-Apr-17

17-Apr-17

26-Apr-17

0

A8190

13

13 Standard 5 Day Workweek

0

Install lockers

21-Apr-17*

10-May-17

21-Apr-17

10-May-17

0

A7660

9

9 Standard 5 Day Workweek

0

Gym dividers

26-Apr-17*

09-May-17

26-Apr-17

09-May-17

0

A7670

7

7 Standard 5 Day Workweek

0

Install hardwood flooring

09-May-17*

18-May-17

09-May-17

18-May-17

0

A8200

9

9 Standard 5 Day Workweek

0

Observation deck

10-May-17*

23-May-17

10-May-17

23-May-17

0

A7680

6

6 Standard 5 Day Workweek

0

Install collapsable belachers

18-May-17*

26-May-17

18-May-17

26-May-17

0

A8210

5

5 Standard 5 Day Workweek

0

Install Medical reclined chair

23-May-17*

30-May-17

23-May-17

30-May-17

0

A7690

8

8 Standard 5 Day Workweek

0

Hydraulic elevators

26-May-17*

07-Jun-17

26-May-17

07-Jun-17

0

A8220

5

5 Standard 5 Day Workweek

0

Glass wall folding partition

30-May-17*

06-Jun-17

30-May-17

06-Jun-17

0

A8230

12

12 Standard 5 Day Workweek

0

Place additional medical equipment

06-Jun-17*

22-Jun-17

06-Jun-17

22-Jun-17

0

A7600

10

10 Standard 5 Day Workweek

0

Install kitchen tiles

07-Jun-17*

21-Jun-17

07-Jun-17

21-Jun-17

0

A8710

9

9 Standard 5 Day Workweek

0

Checklist student life building

07-Jun-17

20-Jun-17

21-Aug-17

01-Sep-17

53

A7550

9

9 Standard 5 Day Workweek

0

Motorized projection screens

21-Jun-17*

04-Jul-17

21-Jun-17

04-Jul-17

0

A8240

5

5 Standard 5 Day Workweek

0

Install lecture seating

22-Jun-17*

29-Jun-17

22-Jun-17

29-Jun-17

0

A8250

7

7 Standard 5 Day Workweek

0

Install Student Desks and chairs

29-Jun-17*

10-Jul-17

29-Jun-17

10-Jul-17

0

A8260

9

9 Standard 5 Day Workweek

0

Lab Desks

10-Jul-17*

21-Jul-17

10-Jul-17

21-Jul-17

0

A8270

7

7 Standard 5 Day Workweek

0

Install hardwood flooring

21-Jul-17*

01-Aug-17

21-Jul-17

01-Aug-17

0

A8280

6

6 Standard 5 Day Workweek

0

Teacher desks

01-Aug-17*

09-Aug-17

01-Aug-17

09-Aug-17

0

Page 14 of 15


Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:50

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8290

8

8 Standard 5 Day Workweek

0

Hydraulic elevators

09-Aug-17*

21-Aug-17

09-Aug-17

21-Aug-17

0

A8700

9

9 Standard 5 Day Workweek

0

Checklist classroom roe

21-Aug-17

01-Sep-17

21-Aug-17

01-Sep-17

0

A8780

79

79 Standard 5 Day Workweek

0

Close out procedures

01-Sep-17

21-Dec-17

01-Sep-17

21-Dec-17

0

A8810

176

176 Standard 5 Day Workweek

0

Demobilize job trailers

01-Sep-17

07-May-18

01-Sep-17

07-May-18

0

A9440

1

1 Standard 5 Day Workweek

0

Final Milestone

07-May-18*

08-May-18

07-May-18

08-May-18

0

Page 15 of 15


7 days calendar 8 hours/day


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

MONROE CAMPUS A7080

Install all site utilties

27-Mar-14*

04-Jun-14

27-Mar-14

04-Jun-14

0

A8670

S86, S96, T77

A7090

Metal stairs

26-Apr-15*

30-Apr-15

17-Sep-15

22-Sep-15

144

A8820, ST944

A7100, A7700

A7100

Install railings

01-May-15*

04-May-15

26-Sep-15

30-Sep-15

148

A7090

A7110

A7110

Interior H.M frames

05-May-15*

17-May-15

30-Sep-15

13-Oct-15

148

A7100

A7120

A7120

Drywall and spackliing

18-May-15*

26-May-15

13-Oct-15

22-Oct-15

148

A7110

A7130

A7130

Caulking

27-May-15*

31-May-15

22-Oct-15

27-Oct-15

148

A7120

A7140

A7140

Ceramic and porcelain wall/floor tiles

01-Jun-15*

07-Jun-15

27-Oct-15

03-Nov-15

148

A7130

A7150

A7150

Painting

08-Jun-15*

16-Jun-15

03-Nov-15

12-Nov-15

148

A7140

A7160

A7160

Wall coverings

17-Jun-15*

23-Jun-15

12-Nov-15

18-Nov-15

148

A7150

A7170

A7170

Acoustical ceiling grid

23-Jun-15*

30-Jun-15

18-Nov-15

25-Nov-15

148

A7160

A7180

A7180

PC AG san/rw

30-Jun-15*

10-Jul-15

25-Nov-15

05-Dec-15

148

A7170

A7190

A7190

PC overhead pipe

10-Jul-15*

20-Jul-15

06-Dec-15

15-Dec-15

148

A7180

A9430

A7200

PC insulation

17-Dec-15*

21-Dec-15

17-Dec-15

21-Dec-15

0

A9430

A7210

A7210

PC drop sprinkler head

22-Dec-15*

31-Dec-15

22-Dec-15

31-Dec-15

0

A7200

A7220

A7220

PC casework fixtures

01-Jan-16*

05-Jan-16

01-Jan-16

05-Jan-16

0

A7210

A7230

A7230

PC toilet fixtures

06-Jan-16*

10-Jan-16

06-Jan-16

10-Jan-16

0

A7220

A7240

A7240

PC kitchen equipment hookups

11-Jan-16*

16-Jan-16

11-Jan-16

16-Jan-16

0

A7230

A7250

A7250

HC hangers

17-Jan-16*

21-Jan-16

17-Jan-16

21-Jan-16

0

A7240

A7260

A7260

HC pipe install

22-Jan-16*

28-Jan-16

22-Jan-16

28-Jan-16

0

A7250

A7270

A7270

HC duct install

29-Jan-16*

02-Feb-16

29-Jan-16

02-Feb-16

0

A7260

A7280

A7280

HC ATC rough-in

03-Feb-16*

13-Feb-16

03-Feb-16

13-Feb-16

0

A7270

A7290

A7290

HC GRD install

14-Feb-16*

28-Feb-16

14-Feb-16

28-Feb-16

0

A7280

A7300

A7300

HC equipment and final connections

28-Feb-16*

11-Mar-16

28-Feb-16

11-Mar-16

0

A7290

A7310

A7310

HC kitchen equipment and hookups

11-Mar-16*

21-Mar-16

11-Mar-16

21-Mar-16

0

A7300

A7320

A7320

EC rough-in walls

21-Mar-16*

02-Apr-16

21-Mar-16

02-Apr-16

0

A7310

A7330

A7330

EC overhead rough-in

02-Apr-16*

15-Apr-16

02-Apr-16

15-Apr-16

0

A7320

A7340

A7340

EC cable tray

16-Apr-16*

30-Apr-16

16-Apr-16

30-Apr-16

0

A7330

A7350

A7350

EC wiring

30-Apr-16*

08-May-16

30-Apr-16

08-May-16

0

A7340

A7360

A7360

EC light fixtures

08-May-16*

16-May-16

08-May-16

16-May-16

0

A7350

A7370

A7370

EC wring devices

16-May-16*

21-May-16

16-May-16

21-May-16

0

A7360

A7380

A7380

EC fire alarm and security

21-May-16*

28-May-16

21-May-16

28-May-16

0

A7370

A7390

A7390

EC kitchen equipment and hookups

28-May-16*

07-Jun-16

28-May-16

07-Jun-16

0

A7380

A7400

A7400

EC hook ups and connections

07-Jun-16*

12-Jun-16

07-Jun-16

12-Jun-16

0

A7390

A7410

A7410

Casework/millwork

12-Jun-16*

19-Jun-16

12-Jun-16

19-Jun-16

0

A7400

A7420

A7420

Resilent tile base and floor

19-Jun-16*

27-Jun-16

19-Jun-16

27-Jun-16

0

A7410

A7430

A7430

Seamless vinyl flooring

27-Jun-16*

05-Jul-16

27-Jun-16

05-Jul-16

0

A7420

A7440

A7440

Carpet tiles

05-Jul-16*

16-Jul-16

05-Jul-16

16-Jul-16

0

A7430

A7450

A7450

Install rubber stairs, treads and landings

16-Jul-16*

23-Jul-16

16-Jul-16

23-Jul-16

0

A7440

A7460

A7460

Doors and Hardware

23-Jul-16*

29-Jul-16

23-Jul-16

29-Jul-16

0

A7450

A7470

A7470

Interior glass partitions

29-Jul-16*

06-Aug-16

29-Jul-16

06-Aug-16

0

A7460

A7480

A7480

Wood wall panels

07-Aug-16*

11-Aug-16

07-Aug-16

11-Aug-16

0

A7470

A7490

A7490

Visual display surfaces

12-Aug-16*

16-Aug-16

12-Aug-16

16-Aug-16

0

A7480

A7500

A7500

Signage

17-Aug-16*

21-Aug-16

17-Aug-16

21-Aug-16

0

A7490

A7510

A7510

Wood ceiling

22-Aug-16*

24-Aug-16

22-Aug-16

24-Aug-16

0

A7500

A7520

A7520

Place Acoustical ceiling tiles

25-Aug-16*

04-Sep-16

25-Aug-16

04-Sep-16

0

A7510

A7530

A7530

Tiolet complartments

04-Sep-16*

11-Sep-16

04-Sep-16

11-Sep-16

0

A7520

A7540

A7540

Fire protection specialities

12-Sep-16*

17-Sep-16

12-Sep-16

17-Sep-16

0

A7530

A7560

Footer 1

Page 1 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A7550

Motorized projection screens

09-Jan-17*

18-Jan-17

09-Jan-17

18-Jan-17

0

A7600

A7560

Window shades

18-Sep-16*

27-Sep-16

18-Sep-16

27-Sep-16

0

A7540

A7570

A7570

Wire mesh partitions

28-Sep-16*

04-Oct-16

28-Sep-16

04-Oct-16

0

A7560

A7580

A7580

Install lockers

05-Oct-16*

17-Oct-16

05-Oct-16

17-Oct-16

0

A7570

A7590

A7590

Install hood and walk-ins

18-Oct-16*

26-Oct-16

18-Oct-16

26-Oct-16

0

A7580

A7610

A7600

Install kitchen tiles

30-Dec-16*

09-Jan-17

30-Dec-16

09-Jan-17

0

A7690

A7550

A7610

Install and setup food service equipment

27-Oct-16*

31-Oct-16

27-Oct-16

31-Oct-16

0

A7590

A7620

A7620

Glass wall folding partition

01-Nov-16*

05-Nov-16

01-Nov-16

05-Nov-16

0

A7610

A7630

A7630

Loading dock equipment

06-Nov-16*

17-Nov-16

06-Nov-16

17-Nov-16

0

A7620

A7640

A7640

Paint gym ceiling

18-Nov-16*

22-Nov-16

18-Nov-16

22-Nov-16

0

A7630

A7650

A7650

Gym equipment

23-Nov-16*

29-Nov-16

23-Nov-16

29-Nov-16

0

A7640

A7660

A7660

Gym dividers

30-Nov-16*

08-Dec-16

30-Nov-16

08-Dec-16

0

A7650

A7670

A7670

Install hardwood flooring

09-Dec-16*

15-Dec-16

09-Dec-16

15-Dec-16

0

A7660

A7680

A7680

Install collapsable belachers

16-Dec-16*

22-Dec-16

16-Dec-16

22-Dec-16

0

A7670

A7690

A7690

Hydraulic elevators

22-Dec-16*

30-Dec-16

22-Dec-16

30-Dec-16

0

A7680

A7600, A8710

A7700

Metal stairs

19-Jun-15*

23-Jun-15

22-Sep-15

27-Sep-15

95

ST734, A7090

A7710

A7710

Install railings

24-Jun-15*

27-Jun-15

27-Sep-15

01-Oct-15

95

A7700

A7720

A7720

Interior H.M frames

28-Jun-15*

10-Jul-15

01-Oct-15

14-Oct-15

95

A7710

A7730

A7730

Drywall and spackliing

11-Jul-15*

19-Jul-15

14-Oct-15

23-Oct-15

95

A7720

A7740

A7740

Caulking

20-Jul-15*

24-Jul-15

23-Oct-15

28-Oct-15

95

A7730

A7750

A7750

Ceramic and porcelain wall/floor tiles

25-Jul-15*

31-Jul-15

28-Oct-15

04-Nov-15

95

A7740

A7760

A7760

Painting

01-Aug-15*

09-Aug-15

04-Nov-15

13-Nov-15

95

A7750

A7770

A7770

Wall coverings

10-Aug-15*

16-Aug-15

13-Nov-15

19-Nov-15

95

A7760

A7780

A7780

Acoustical ceiling grid

16-Aug-15*

23-Aug-15

19-Nov-15

26-Nov-15

95

A7770

A7790

A7790

PC AG san/rw

23-Aug-15*

02-Sep-15

26-Nov-15

06-Dec-15

95

A7780

A7800

A7800

PC overhead pipe

02-Sep-15*

12-Sep-15

07-Dec-15

16-Dec-15

95

A7790

A7810

A7810

PC insulation

12-Sep-15*

17-Sep-15

17-Dec-15

21-Dec-15

95

A7800

A7820

A7820

PC drop sprinkler head

17-Sep-15*

27-Sep-15

22-Dec-15

31-Dec-15

95

A7810

A7830

A7830

PC casework fixtures

27-Sep-15*

02-Oct-15

01-Jan-16

05-Jan-16

95

A7820

A7840

A7840

PC toilet fixtures

02-Oct-15*

07-Oct-15

06-Jan-16

10-Jan-16

95

A7830

A7850

A7850

PC kitchen equipment hookups

07-Oct-15*

13-Oct-15

11-Jan-16

16-Jan-16

95

A7840

A7860

A7860

HC hangers

13-Oct-15*

18-Oct-15

17-Jan-16

21-Jan-16

95

A7850

A7870

A7870

HC pipe install

18-Oct-15*

25-Oct-15

22-Jan-16

28-Jan-16

95

A7860

A7880

A7880

HC duct install

25-Oct-15*

30-Oct-15

29-Jan-16

02-Feb-16

95

A7870

A7890

A7890

HC ATC rough-in

30-Oct-15*

10-Nov-15

03-Feb-16

13-Feb-16

95

A7880

A7900

A7900

HC GRD install

10-Nov-15*

25-Nov-15

14-Feb-16

28-Feb-16

95

A7890

A7910

A7910

HC equipment and final connections

25-Nov-15*

07-Dec-15

28-Feb-16

11-Mar-16

95

A7900

A7920

A7920

HC kitchen equipment and hookups

07-Dec-15*

17-Dec-15

11-Mar-16

21-Mar-16

95

A7910

A7930

A7930

EC rough-in walls

17-Dec-15*

29-Dec-15

21-Mar-16

02-Apr-16

95

A7920

A7940

A7940

EC overhead rough-in

29-Dec-15*

11-Jan-16

02-Apr-16

15-Apr-16

95

A7930

A7950

A7950

EC cable tray

11-Jan-16*

26-Jan-16

16-Apr-16

30-Apr-16

95

A7940

A7960

A7960

EC wiring

26-Jan-16*

03-Feb-16

30-Apr-16

08-May-16

95

A7950

A7970

A7970

EC light fixtures

03-Feb-16*

11-Feb-16

08-May-16

16-May-16

95

A7960

A7980

A7980

EC wring devices

11-Feb-16*

16-Feb-16

16-May-16

21-May-16

95

A7970

A7990

A7990

EC fire alarm and security

16-Feb-16*

22-Feb-16

21-May-16

28-May-16

95

A7980

A8000

A8000

EC kitchen equipment and hookups

22-Feb-16*

03-Mar-16

28-May-16

07-Jun-16

95

A7990

A8010

A8010

EC hook ups and connections

03-Mar-16*

08-Mar-16

07-Jun-16

12-Jun-16

95

A8000

A8020

A8020

Casework/millwork

08-Mar-16*

16-Mar-16

12-Jun-16

19-Jun-16

95

A8010

A8030

A8030

Resilent tile base and floor

16-Mar-16*

24-Mar-16

19-Jun-16

27-Jun-16

95

A8020

A8040

A8040

Seamless vinyl flooring

24-Mar-16*

01-Apr-16

27-Jun-16

05-Jul-16

95

A8030

A8050

Footer 1

Page 2 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

A8050

Carpet tiles

A8060

Install rubber stairs, treads and landings

A8070

Total Float

Predecessors

01-Apr-16*

12-Apr-16

05-Jul-16

16-Jul-16

95

A8040

A8060

12-Apr-16*

19-Apr-16

16-Jul-16

23-Jul-16

95

A8050

A8070

Doors and Hardware

19-Apr-16*

25-Apr-16

23-Jul-16

29-Jul-16

95

A8060

A8080

A8080

Interior glass partitions

25-Apr-16*

03-May-16

29-Jul-16

06-Aug-16

95

A8070

A8090

A8090

Wood wall panels

03-May-16*

08-May-16

07-Aug-16

11-Aug-16

95

A8080

A8100

A8100

Visual display surfaces

08-May-16*

13-May-16

12-Aug-16

16-Aug-16

95

A8090

A8110

A8110

Signage

13-May-16*

18-May-16

17-Aug-16

21-Aug-16

95

A8100

A8120

A8120

Wood ceiling

18-May-16*

21-May-16

22-Aug-16

24-Aug-16

95

A8110

A8130

A8130

Place Acoustical ceiling tiles

21-May-16*

01-Jun-16

25-Aug-16

04-Sep-16

95

A8120

A8140

A8140

Tiolet complartments

01-Jun-16*

08-Jun-16

04-Sep-16

11-Sep-16

95

A8130

A8150

A8150

Fire protection specialities

08-Jun-16*

14-Jun-16

12-Sep-16

17-Sep-16

95

A8140

A8170

A8170

Window shades

14-Jun-16*

24-Jun-16

18-Sep-16

27-Sep-16

95

A8150

A8180

A8180

Wire mesh partitions

24-Jun-16*

01-Jul-16

28-Sep-16

04-Oct-16

95

A8170

A8190

A8190

Install lockers

01-Jul-16*

14-Jul-16

05-Oct-16

17-Oct-16

95

A8180

A8200

A8200

Observation deck

14-Jul-16*

23-Jul-16

18-Oct-16

26-Oct-16

95

A8190

A8210

A8210

Install Medical reclined chair

23-Jul-16*

28-Jul-16

27-Oct-16

31-Oct-16

95

A8200

A8220

A8220

Glass wall folding partition

28-Jul-16*

02-Aug-16

01-Nov-16

05-Nov-16

95

A8210

A8230

A8230

Place additional medical equipment

02-Aug-16*

14-Aug-16

06-Nov-16

17-Nov-16

95

A8220

A8240

A8240

Install lecture seating

14-Aug-16*

19-Aug-16

18-Nov-16

22-Nov-16

95

A8230

A8250

A8250

Install Student Desks and chairs

19-Aug-16*

26-Aug-16

23-Nov-16

29-Nov-16

95

A8240

A8260

A8260

Lab Desks

26-Aug-16*

04-Sep-16

30-Nov-16

08-Dec-16

95

A8250

A8270

A8270

Install hardwood flooring

04-Sep-16*

11-Sep-16

09-Dec-16

15-Dec-16

95

A8260

A8280

A8280

Teacher desks

11-Sep-16*

18-Sep-16

16-Dec-16

22-Dec-16

95

A8270

A8290

A8290

Hydraulic elevators

18-Sep-16*

26-Sep-16

22-Dec-16

30-Dec-16

95

A8280

A8780, A8700

A8300

Prevailing wage documents

17-Jan-14

25-Jan-14

17-Jan-14

25-Jan-14

0

A8610

A8310

Bid security

10-Feb-14

21-Feb-14

10-Feb-14

21-Feb-14

0

A8390

A8320

Electrical Construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8610

A8330

Plumbing construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8610

A8340

Hvac construction bid

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8610

A8350

General construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8610

A8360

Geotechnical investigation

10-Oct-13

26-Dec-13

10-Oct-13

26-Dec-13

0

A8370

Instruction to bidders

17-Jan-14

29-Jan-14

17-Jan-14

29-Jan-14

0

A8390

A8380

Qualification questionnaire

17-Jan-14

22-Jan-14

17-Jan-14

22-Jan-14

0

A8390

A8390

invitation to bid

17-Jan-14

10-Feb-14

17-Jan-14

10-Feb-14

0

A8610

A8400

Execution

09-Apr-14

08-Jan-17

09-Apr-14

08-Jan-17

0

A8670, A8780

A8410

Product requirements

10-Feb-14

21-Mar-14

10-Feb-14

21-Mar-14

0

A8390

A8420

Temporary Facilities & controls

07-Jun-14

08-Jan-17

07-Jun-14

08-Jan-17

0

A8670, A8780

A8430

References

05-Mar-14

19-Mar-14

05-Mar-14

19-Mar-14

0

A8600

A8440

Quality requirements

05-Mar-14

23-Apr-14

05-Mar-14

23-Apr-14

0

A8600

A8450

Alteration Project procedures

10-Oct-13

13-Oct-13

10-Oct-13

13-Oct-13

0

LEED submital Form

29-Oct-13

06-Dec-13

29-Oct-13

06-Dec-13

0

A8730, A8740

A8470

Submittal form

05-Mar-14

21-Apr-14

05-Mar-14

21-Apr-14

0

A8390, A8600

A8480

Construction Progress documentation

18-May-14

08-Jan-17

18-May-14

08-Jan-17

0

A8670, A8780

A8490

Web based project management

28-May-14

08-Jan-17

28-May-14

08-Jan-17

0

A8670, A8780

A8500

Coordination drawings

27-Dec-13

13-Jan-14

04-Feb-14

21-Feb-14

39

A8610

A8510

Project Management & coordination

18-Apr-14

08-Jan-17

18-Apr-14

08-Jan-17

0

A8670, A8780

A8520

Payement procedures

11-Feb-14

15-Nov-16

11-Feb-14

15-Nov-16

0

A8670

Page 3 of 8

A8600

A8610, A8570

A8460

Footer 1

Successors

A8380, A8370, A8310, A8680, A8620, A8650, A8660, A8630, A8670, A8470, A8550, A8410

A8600


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A8530

Contract Modification

10-Oct-13

29-Nov-13

10-Oct-13

29-Nov-13

A8540

Alternates

05-Mar-14

18-Mar-14

05-Mar-14

18-Mar-14

0 0

A8600

A8550

Unit prices

10-Feb-14

26-Mar-14

10-Feb-14

26-Mar-14

0

A8390

A8560

Quantity allowances

05-Mar-14

31-Mar-14

05-Mar-14

31-Mar-14

0

A8600

A8570

Field engineering

27-Dec-13

05-Jan-14

27-Dec-13

05-Jan-14

0

A8360

A8580

Work restrictions

05-Mar-14

20-Apr-14

05-Mar-14

20-Apr-14

0

A8600

A8590

Summary of multiple contracts

05-Mar-14

11-Mar-14

05-Mar-14

11-Mar-14

0

A8600

A8600

Summary

21-Feb-14

05-Mar-14

21-Feb-14

05-Mar-14

0

A8500, A8310

A8690, A8540, A8440, A8590, A8560, A8430, A8580, A8470

A8610

List of drawings

27-Dec-13

16-Jan-14

27-Dec-13

16-Jan-14

0

A8360

A8340, A8350, A8320, A8330, A8500, A8390, A8300, A8640

A8620

Safety and health management plan

10-Feb-14

14-Feb-14

10-Feb-14

14-Feb-14

0

A8390

A8630

Standard General conditions

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8390

A8640

Sample Insurance certificates

17-Jan-14

21-Jan-14

17-Jan-14

21-Jan-14

0

A8610

A8650

Payment bond

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8390

A8660

Performance bond

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8390

A8670

AIA document a132

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8390

A8760, A8790, A8770, A8400, A8510, A8420, A8750, A8480, A8490, A8520, A7080, A8970

A8680

Non collusion affidavit

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8390

A8690

General Commissioning requirements

05-Mar-14

10-Mar-14

05-Mar-14

10-Mar-14

0

A8600

A8700

Checklist classroom roe

26-Sep-16

05-Oct-16

30-Dec-16

08-Jan-17

95

A8290

A8780

A8710

Checklist student life building

30-Dec-16

08-Jan-17

30-Dec-16

08-Jan-17

0

A7690

A8780

A8720

Checklist enrollment building

30-Apr-16

08-May-16

30-Dec-16

08-Jan-17

244

A9420

A8780

A8730

Leed & sustainable design requirements

10-Oct-13

16-Oct-13

22-Oct-13

28-Oct-13

12

A8740

Testing for indoor air quality

10-Oct-13

28-Oct-13

10-Oct-13

28-Oct-13

0

A8750

Demonstration & training

11-Feb-14

07-Jan-15

11-Feb-14

07-Jan-15

0

A8670

A8760

Project record documents

14-Mar-15

08-Jan-17

14-Mar-15

08-Jan-17

0

A8670, A8780

A8770

Operation and maintenance data

11-Sep-14

08-Jan-17

11-Sep-14

08-Jan-17

0

A8670, A8780

A8780

Close out procedures

08-Jan-17

28-Mar-17

08-Jan-17

28-Mar-17

0

A8790, A8290, A8720, A8710, A8700

A9440, A8810, A8770, A8760, A8510, A8490, A8480, A8420, A8400

A8790

Construction waste mangement

11-Feb-14

28-Jun-16

24-Aug-14

08-Jan-17

193

A8670

A8780

A8800

Cutting and patching

10-Oct-13

30-Oct-13

10-Oct-13

30-Oct-13

0

A8810

Demobilize job trailers

08-Jan-17

03-Jul-17

04-May-17

26-Oct-17

116

A8780

A9440

A8820

Metal stairs

27-Jan-15*

31-Jan-15

27-Jan-15

31-Jan-15

0

ST1084

A8830, A7090

A8830

Install railings

01-Feb-15*

04-Feb-15

01-Feb-15

04-Feb-15

0

A8820

A8840

A8840

Interior H.M frames

05-Feb-15*

17-Feb-15

05-Feb-15

17-Feb-15

0

A8830

A8850

A8850

Drywall and spackliing

18-Feb-15*

26-Feb-15

18-Feb-15

26-Feb-15

0

A8840

A8860

A8860

Caulking

27-Feb-15*

03-Mar-15

27-Feb-15

03-Mar-15

0

A8850

A8870

A8870

Ceramic and porcelain wall/floor tiles

04-Mar-15*

10-Mar-15

04-Mar-15

10-Mar-15

0

A8860

A8880

A8880

Painting

11-Mar-15*

19-Mar-15

11-Mar-15

19-Mar-15

0

A8870

A8890

A8890

Wall coverings

20-Mar-15*

26-Mar-15

20-Mar-15

26-Mar-15

0

A8880

A8900

A8900

Acoustical ceiling grid

26-Mar-15*

02-Apr-15

26-Mar-15

02-Apr-15

0

A8890

A8910

A8910

PC AG san/rw

02-Apr-15*

12-Apr-15

02-Apr-15

12-Apr-15

0

A8900

A8920

A8920

PC overhead pipe

12-Apr-15*

22-Apr-15

12-Apr-15

22-Apr-15

0

A8910

A8930

A8930

PC insulation

22-Apr-15*

27-Apr-15

22-Apr-15

27-Apr-15

0

A8920

A8940

Footer 1

Page 4 of 8

A8460 A8460


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A8940

PC drop sprinkler head

27-Apr-15*

07-May-15

27-Apr-15

07-May-15

0

A8930

A8950

A8950

PC casework fixtures

07-May-15*

12-May-15

07-May-15

12-May-15

0

A8940

A8960

A8960

PC toilet fixtures

12-May-15*

17-May-15

12-May-15

17-May-15

0

A8950

A8980

A8970

Start milestone

27-Mar-14*

27-Mar-14

27-Mar-14

27-Mar-14

0

A8670

S86

A8980

HC hangers

17-May-15*

22-May-15

17-May-15

22-May-15

0

A8960

A8990

A8990

HC pipe install

22-May-15*

29-May-15

22-May-15

29-May-15

0

A8980

A9000

A9000

HC duct install

29-May-15*

03-Jun-15

29-May-15

03-Jun-15

0

A8990

A9010

A9010

HC ATC rough-in

03-Jun-15*

14-Jun-15

03-Jun-15

14-Jun-15

0

A9000

A9020

A9020

HC GRD install

14-Jun-15*

29-Jun-15

14-Jun-15

29-Jun-15

0

A9010

A9030

A9030

HC equipment and final connections

29-Jun-15*

11-Jul-15

29-Jun-15

11-Jul-15

0

A9020

A9040

A9040

HC kitchen equipment and hookups

11-Jul-15*

21-Jul-15

11-Jul-15

21-Jul-15

0

A9030

A9050

A9050

EC rough-in walls

21-Jul-15*

02-Aug-15

21-Jul-15

02-Aug-15

0

A9040

A9060

A9060

EC overhead rough-in

02-Aug-15*

15-Aug-15

02-Aug-15

15-Aug-15

0

A9050

A9070

A9070

EC cable tray

15-Aug-15*

30-Aug-15

15-Aug-15

30-Aug-15

0

A9060

A9080

A9080

EC wiring

30-Aug-15*

07-Sep-15

30-Aug-15

07-Sep-15

0

A9070

A9090

A9090

EC light fixtures

07-Sep-15*

15-Sep-15

07-Sep-15

15-Sep-15

0

A9080

A9100

A9100

EC wring devices

15-Sep-15*

20-Sep-15

15-Sep-15

20-Sep-15

0

A9090

A9110

A9110

EC fire alarm and security

20-Sep-15*

26-Sep-15

20-Sep-15

26-Sep-15

0

A9100

A9120

A9120

EC kitchen equipment and hookups

26-Sep-15*

06-Oct-15

26-Sep-15

06-Oct-15

0

A9110

A9130

A9130

EC hook ups and connections

06-Oct-15*

11-Oct-15

06-Oct-15

11-Oct-15

0

A9120

A9140

A9140

Casework/millwork

11-Oct-15*

19-Oct-15

11-Oct-15

19-Oct-15

0

A9130

A9150

A9150

Resilent tile base and floor

19-Oct-15*

27-Oct-15

19-Oct-15

27-Oct-15

0

A9140

A9160

A9160

Seamless vinyl flooring

27-Oct-15*

04-Nov-15

27-Oct-15

04-Nov-15

0

A9150

A9170

A9170

Carpet tiles

04-Nov-15*

15-Nov-15

04-Nov-15

15-Nov-15

0

A9160

A9180

A9180

Install rubber stairs, treads and landings

15-Nov-15*

22-Nov-15

15-Nov-15

22-Nov-15

0

A9170

A9190

A9190

Doors and Hardware

22-Nov-15*

28-Nov-15

22-Nov-15

28-Nov-15

0

A9180

A9200

A9200

Interior glass partitions

28-Nov-15*

06-Dec-15

28-Nov-15

06-Dec-15

0

A9190

A9210

A9210

Wood wall panels

06-Dec-15*

11-Dec-15

06-Dec-15

11-Dec-15

0

A9200

A9220

A9220

Visual display surfaces

11-Dec-15*

16-Dec-15

11-Dec-15

16-Dec-15

0

A9210

A9230

A9230

Signage

16-Dec-15*

21-Dec-15

16-Dec-15

21-Dec-15

0

A9220

A9240

A9240

Wood ceiling

21-Dec-15*

24-Dec-15

21-Dec-15

24-Dec-15

0

A9230

A9250

A9250

Place Acoustical ceiling tiles

24-Dec-15*

04-Jan-16

24-Dec-15

04-Jan-16

0

A9240

A9260

A9260

Tiolet complartments

04-Jan-16*

11-Jan-16

04-Jan-16

11-Jan-16

0

A9250

A9270

A9270

Fire protection specialities

11-Jan-16*

17-Jan-16

11-Jan-16

17-Jan-16

0

A9260

A9290

A9280

Motorized projection screens

10-May-16

19-May-16

10-May-16

19-May-16

0

A9330

A9290

Window shades

17-Jan-16*

27-Jan-16

17-Jan-16

27-Jan-16

0

A9270

A9300

A9300

Wire mesh partitions

27-Jan-16*

03-Feb-16

27-Jan-16

03-Feb-16

0

A9290

A9310

A9310

Install lockers

03-Feb-16*

16-Feb-16

03-Feb-16

16-Feb-16

0

A9300

A9320

A9320

Install hood and walk-ins

16-Feb-16*

25-Feb-16

16-Feb-16

25-Feb-16

0

A9310

A9340

A9330

Install kitchen tiles

30-Apr-16

10-May-16

30-Apr-16

10-May-16

0

A9420

A9280

A9340

Install and setup food service equipment

25-Feb-16*

01-Mar-16

25-Feb-16

01-Mar-16

0

A9320

A9350

A9350

Glass wall folding partition

01-Mar-16*

06-Mar-16

01-Mar-16

06-Mar-16

0

A9340

A9360

A9360

Loading dock equipment

06-Mar-16*

18-Mar-16

06-Mar-16

18-Mar-16

0

A9350

A9370

A9370

Paint gym ceiling

18-Mar-16*

23-Mar-16

18-Mar-16

23-Mar-16

0

A9360

A9380

A9380

Gym equipment

23-Mar-16*

30-Mar-16

23-Mar-16

30-Mar-16

0

A9370

A9390

A9390

Gym dividers

30-Mar-16*

08-Apr-16

30-Mar-16

08-Apr-16

0

A9380

A9400

A9400

Install hardwood flooring

08-Apr-16*

15-Apr-16

08-Apr-16

15-Apr-16

0

A9390

A9410

A9410

Install collapsable belachers

15-Apr-16*

22-Apr-16

15-Apr-16

22-Apr-16

0

A9400

A9420

A9420

Hydraulic elevators

22-Apr-16*

30-Apr-16

22-Apr-16

30-Apr-16

0

A9410

A9330, A8720

A9430

Substantial milestone

16-Dec-15*

16-Dec-15

16-Dec-15

16-Dec-15

0

A7190

A7200

Footer 1

Page 5 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

A9440

Final Milestone

27-Oct-17*

28-Oct-17

27-Oct-17

28-Oct-17

0

A8780, A8810

S106

Erosion controls

02-Apr-14*

26-Apr-14

02-Apr-14

26-Apr-14

0

S86

S116, S206, S136

S116

Site Clearing and Strip Topsoil

27-Apr-14*

05-Jul-14

27-Apr-14

05-Jul-14

0

S106

S146, S176

S126

Temporary Basin and Swales

07-May-14*

10-Jun-14

29-Jul-14

01-Sep-14

83

S86

S216

S136

Site grading

05-May-14*

01-Sep-14

05-May-14

01-Sep-14

0

S106

S386

S146

Install Sediment Basin

06-Jul-14*

24-Aug-14

06-Jul-14

24-Aug-14

0

S116, S156

S156

Install Paving binder access roads and staging areas

12-May-14*

31-May-14

28-May-14

16-Jun-14

16

S86, S96

S166

Install additional staging areas

24-Jul-14*

22-Aug-14

24-Jul-14

22-Aug-14

0

S156

S176

Electrical ductbank

06-Jul-14*

24-Aug-14

06-Jul-14

24-Aug-14

0

S116

S186

Install Storm Sewer

12-May-14 A

27-Dec-14

27-Apr-14

27-Dec-14

0

S86

S236, S406

S196

Install Sanitary Sewer

30-Jun-14*

13-Aug-14

13-Sep-15

27-Oct-15

440

S156

S236

S196, S226, S146, SF55, S166 S396, T47

S206

Water system

05-May-14 A

17-Oct-14 A

26-Apr-14

26-Apr-14

S216

Concrete curbs

09-Aug-14*

16-Nov-14

02-Sep-14

10-Dec-14

24

S126, S226

S106 S376

S226

Site lighting

30-Jun-14*

08-Aug-14

24-Jul-14

01-Sep-14

24

S156

S216, S396

S236

Final Landscaping

29-Sep-15*

17-Nov-15

28-Oct-15

16-Dec-15

29

S186, S196, S276, S326

S416, S316, S336

S246

Place trees and shrubbery

20-Jan-15*

28-Feb-15

20-Jan-15

28-Feb-15

0

S386, S396, S376

S256

site linestripping and signage

14-Mar-16*

08-Apr-16

14-Mar-16

08-Apr-16

0

S266

S266

Concrete bumper blocks

08-Feb-16*

27-Feb-16

23-Feb-16

13-Mar-16

15

S306, S416

S256

S276

sidewalks and ramp concrete pour

26-May-15*

29-Jul-15

20-Jul-15

22-Sep-15

55

S296

S236, S346, S326, S366

S286

Unit Pavers

18-Sep-15*

02-Nov-15

19-Oct-15

03-Dec-15

31

S346, S366

S416, S306

S296

Exterior masonry seat walls and site walls

13-Apr-15*

12-May-15

20-Jun-15

19-Jul-15

68

S376

S276, S356

S306

Exterior site railings

03-Nov-15*

10-Dec-15

04-Dec-15

10-Jan-16

31

S286

S266, S416

S316

Position Site seating

18-Nov-15*

12-Dec-15

17-Dec-15

10-Jan-16

29

S236

S416

S326

Fiberglass bus stations

25-Aug-15*

28-Sep-15

23-Sep-15

27-Oct-15

29

S276

S236

S336

Install flagpoles

27-Mar-14

08-Apr-16

27-Mar-14

08-Apr-16

0

S236

S416

S346

Parking control equipment

24-Aug-15*

17-Sep-15

24-Sep-15

18-Oct-15

31

S276, S356

S286

S356

Retaining wall for landscaping

25-May-15*

13-Jun-15

04-Sep-15

23-Sep-15

102

S296

S346

S366

Timber guide railings

25-Aug-15*

13-Sep-15

29-Sep-15

18-Oct-15

35

S276

S286

S376

Retaining wall

17-Nov-14*

26-Dec-14

11-Dec-14

19-Jan-15

24

S216

S296, S246

S386

Site excavation

02-Sep-14*

19-Jan-15

02-Sep-14

19-Jan-15

0

S136

S246

S396

Install new topsoil

25-Aug-14 A

28-Sep-14

16-Dec-14

19-Jan-15

113

S406

Install Geo Exchange Field

28-Dec-14*

06-Apr-15

28-Dec-14

06-Apr-15

S416

Final placement of trees and shrubbery

13-Dec-15*

24-Jan-16

11-Jan-16

S86

Site Layout

28-Mar-14

26-Apr-14

28-Mar-14

S96

Install Rock Construction Entrance

27-Mar-14

10-Apr-14

SF25

Layout for foundation

08-Jul-14*

14-Jul-14

SF35

Footing excavation

04-Aug-14*

17-Sep-14

04-Aug-14

SF45

Tie Rebar

15-Jul-14*

03-Aug-14

SF55

Construct building pad

09-Jun-14*

29-Jun-14

SF65

Concrete foundation

04-Aug-14*

17-Sep-14

ST1004

Deep underground rough-in

08-Oct-14*

ST1014

Stone under slab rough-in

ST1024

Erect structural steel and deck

ST1034 ST1044

S176, S226

S246

0

S186

T57

22-Feb-16

29

S286, S236, S316, S336, S306

S266

26-Apr-14

0

A7080, A8970

S106, S126, S156, S186

13-May-14

27-May-14

47

A7080

S156

08-Jul-14

14-Jul-14

0

SF55

SF35, SF45, ST744

17-Sep-14

0

SF25, SF45

15-Jul-14

03-Aug-14

0

SF25

SF35, SF65

17-Jun-14

07-Jul-14

8

S156

SF25

04-Aug-14

17-Sep-14

0

SF45

ST1054, ST1224

22-Oct-14

18-Oct-14

01-Nov-14

10

ST984

ST994

15-Dec-14

26-Dec-14

16-Dec-14

27-Dec-14

1

ST784, ST1254

ST804, ST774

02-Nov-14

24-Nov-14

02-Nov-14

24-Nov-14

0

ST1234

ST1074, ST1254

Pour concrete slab on deck

22-Dec-14

22-Jan-15

22-Dec-14

22-Jan-15

0

ST1044

ST1064

Stone under slab

07-Dec-14

21-Dec-14

07-Dec-14

21-Dec-14

0

ST1234, ST1254

ST1064, ST1054, ST1034

ST1054

CMU walls

07-Feb-15

26-Feb-15

07-Feb-15

26-Feb-15

0

ST1064, ST1044, SF65

ST1204, ST1264, ST814

ST1064

Pour concrete slab on grade

23-Jan-15

06-Feb-15

23-Jan-15

06-Feb-15

0

ST1044, ST1034

ST1054

Footer 1

Page 6 of 8


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

ST1074

Cold formed metal framing and sheathing

25-Nov-14

19-Dec-14

25-Nov-14

19-Dec-14

0

ST1024

ST1094

ST1084

Spray urethane insulation

07-Jan-15

26-Jan-15

07-Jan-15

26-Jan-15

0

ST1094

ST1104, ST1144, A8820

ST1094

Install air membrane

20-Dec-14

06-Jan-15

20-Dec-14

06-Jan-15

0

ST1074

ST1084

ST1104

Wood blocking & sheathing on roof

27-Jan-15

05-Feb-15

27-Jan-15

05-Feb-15

0

ST1084

ST1114, ST1124

ST1114

Roof curbs

06-Feb-15

12-Feb-15

05-Mar-15

11-Mar-15

27

ST1104

ST1134

ST1124

Roof Drains

06-Feb-15

16-Feb-15

06-Feb-15

16-Feb-15

0

ST1104

ST1154

ST1134

Roof top equipment

13-Feb-15

17-Feb-15

12-Mar-15

16-Mar-15

27

ST1114

ST1184

ST1144

Insulated metal wall panels

27-Jan-15

15-Feb-15

17-Mar-15

05-Apr-15

49

ST1084

ST1194 ST1164

ST1154

Metal soffit and fascia

17-Feb-15

03-Mar-15

17-Feb-15

03-Mar-15

0

ST1124

ST1164

Roof metal edges

04-Mar-15

16-Mar-15

04-Mar-15

16-Mar-15

0

ST1154

ST1184

ST1174

Exterior Caulking

05-Apr-15

14-Apr-15

06-Apr-15

15-Apr-15

1

ST1204

ST1214

ST1184

Metal roof ladders

17-Mar-15

05-Apr-15

17-Mar-15

05-Apr-15

0

ST1164, ST1134

ST1194

ST1194

Aluminum windows & curtain walls

06-Apr-15

15-Apr-15

06-Apr-15

15-Apr-15

0

ST1144, ST1184

ST1214

ST1204

Masonry veneer

27-Feb-15

04-Apr-15

28-Feb-15

05-Apr-15

1

ST1054

ST1174

ST1214

Aluminum entrance doors/sliding doors

16-Apr-15

10-May-15

16-Apr-15

10-May-15

0

ST1174, ST1194

ST1224

Plumbing underground sanitary/storm rough-in

18-Sep-14*

27-Sep-14

18-Sep-14

27-Sep-14

0

SF65

ST1234, ST1244, ST984

ST1234

Waterproofing

13-Oct-14*

01-Nov-14

13-Oct-14

01-Nov-14

0

ST1224, ST1244

ST1044, ST1024, ST994

ST1244

Deep underground rough-in

28-Sep-14*

12-Oct-14

28-Sep-14

12-Oct-14

0

ST1224

ST1234

ST1254

Stone under slab rough-in

25-Nov-14

06-Dec-14

25-Nov-14

06-Dec-14

0

ST1024

ST1044, ST1014

ST1264

Layout stone veneer

27-Feb-15

27-Mar-15

27-Feb-15

27-Mar-15

0

ST1054

ST544

Erect structural steel and deck

22-Nov-14

14-Dec-14

16-Mar-15

08-Apr-15

114

ST754

ST594, ST774

ST554

Pour concrete slab on deck

23-Jan-15

23-Feb-15

06-May-15

07-Jun-15

103

ST564

ST584

ST564

Stone under slab

08-Jan-15

22-Jan-15

21-Apr-15

06-May-15

103

ST754, ST774

ST584, ST574, ST554

ST574

CMU walls

19-Mar-15

07-Apr-15

22-Jun-15

12-Jul-15

95

ST584, ST564, ST814

ST724

ST584

Pour concrete slab on grade

24-Feb-15

10-Mar-15

07-Jun-15

22-Jun-15

103

ST564, ST554

ST574

ST594

Cold formed metal framing and sheathing

15-Dec-14

08-Jan-15

08-Apr-15

03-May-15

114

ST544

ST614

ST604

Spray urethane insulation

27-Jan-15

15-Feb-15

21-May-15

10-Jun-15

114

ST614

ST624, ST664

ST614

Install air membrane

09-Jan-15

26-Jan-15

03-May-15

21-May-15

114

ST594

ST604

ST624

Wood blocking & sheathing on roof

16-Feb-15

25-Feb-15

10-Jun-15

20-Jun-15

114

ST604

ST634, ST644

ST634

Roof curbs

26-Feb-15

04-Mar-15

17-Jul-15

24-Jul-15

141

ST624

ST654

ST644

Roof Drains

26-Feb-15

08-Mar-15

20-Jun-15

01-Jul-15

114

ST624

ST674

ST654

Roof top equipment

05-Mar-15

09-Mar-15

24-Jul-15

29-Jul-15

141

ST634

ST704

ST664

Insulated metal wall panels

16-Feb-15

07-Mar-15

29-Jul-15

18-Aug-15

163

ST604

ST714

ST674

Metal soffit and fascia

09-Mar-15

23-Mar-15

01-Jul-15

16-Jul-15

114

ST644

ST684

ST684

Roof metal edges

24-Mar-15

05-Apr-15

16-Jul-15

29-Jul-15

114

ST674

ST704

ST694

Exterior Caulking

15-May-15

24-May-15

18-Aug-15

28-Aug-15

95

ST724

ST734

ST704

Metal roof ladders

06-Apr-15

25-Apr-15

29-Jul-15

18-Aug-15

114

ST684, ST654

ST714

ST714

Aluminum windows & curtain walls

26-Apr-15

05-May-15

18-Aug-15

28-Aug-15

114

ST664, ST704

ST734

ST724

Masonry veneer

08-Apr-15

14-May-15

12-Jul-15

18-Aug-15

95

ST574

ST694

ST734

Aluminum entrance doors/sliding doors

25-May-15

18-Jun-15

28-Aug-15

22-Sep-15

95

ST694, ST714

A7700

ST744

Plumbing underground sanitary/storm rough-in

08-Oct-14*

17-Oct-14

30-Jan-15

09-Feb-15

114

SF25, ST984

ST754, ST764

ST754

Waterproofing

02-Nov-14*

21-Nov-14

24-Feb-15

16-Mar-15

114

ST744, ST764

ST564, ST544

ST764

Deep underground rough-in

18-Oct-14*

01-Nov-14

09-Feb-15

24-Feb-15

114

ST744

ST754

ST774

Stone under slab rough-in

27-Dec-14

07-Jan-15

09-Apr-15

21-Apr-15

103

ST784

Erect structural steel and deck

22-Nov-14

14-Dec-14

22-Nov-14

14-Dec-14

0

ST794

Pour concrete slab on deck

11-Jan-15

11-Feb-15

12-Jan-15

12-Feb-15

ST804

Stone under slab

27-Dec-14

10-Jan-15

28-Dec-14

11-Jan-15

ST814

CMU walls

27-Feb-15

18-Mar-15

28-Feb-15

19-Mar-15

1

Footer 1

Page 7 of 8

ST544, ST1014

ST564

ST994

ST834, ST1014

1

ST804

ST824

1

ST994, ST1014

ST824, ST814, ST794

ST824, ST804, ST1054

ST964, ST574


MONROE CAMPUS... Report Date 14-Apr-14 20:57

Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

SR-06 Schedule Report - Predecessors Successors Activity ID

Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

Predecessors

Successors

ST824

Pour concrete slab on grade

12-Feb-15

26-Feb-15

13-Feb-15

27-Feb-15

1

ST804, ST794

ST814

ST834

Cold formed metal framing and sheathing

15-Dec-14

08-Jan-15

15-Dec-14

08-Jan-15

0

ST784

ST854

ST844

Spray urethane insulation

27-Jan-15

15-Feb-15

27-Jan-15

15-Feb-15

0

ST854

ST864, ST904

ST854

Install air membrane

09-Jan-15

26-Jan-15

09-Jan-15

26-Jan-15

0

ST834

ST844

ST864

Wood blocking & sheathing on roof

16-Feb-15

25-Feb-15

16-Feb-15

25-Feb-15

0

ST844

ST874, ST884

ST874

Roof curbs

26-Feb-15

04-Mar-15

25-Mar-15

31-Mar-15

27

ST864

ST894

ST884

Roof Drains

26-Feb-15

08-Mar-15

26-Feb-15

08-Mar-15

0

ST864

ST914

ST894

Roof top equipment

05-Mar-15

09-Mar-15

01-Apr-15

05-Apr-15

27

ST874

ST944

ST904

Insulated metal wall panels

16-Feb-15

07-Mar-15

06-Apr-15

25-Apr-15

49

ST844

ST954

ST914

Metal soffit and fascia

09-Mar-15

23-Mar-15

09-Mar-15

23-Mar-15

0

ST884

ST924

ST924

Roof metal edges

24-Mar-15

05-Apr-15

24-Mar-15

05-Apr-15

0

ST914

ST944

ST934

Exterior Caulking

25-Apr-15

04-May-15

26-Apr-15

05-May-15

1

ST964

ST974

ST944

Metal roof ladders

06-Apr-15

25-Apr-15

06-Apr-15

25-Apr-15

0

ST924, ST894

ST954, A7090

ST954

Aluminum windows & curtain walls

26-Apr-15

05-May-15

26-Apr-15

05-May-15

0

ST904, ST944

ST974

ST964

Masonry veneer

19-Mar-15

24-Apr-15

20-Mar-15

25-Apr-15

1

ST814

ST934

ST974

Aluminum entrance doors/sliding doors

06-May-15

30-May-15

06-May-15

30-May-15

0

ST934, ST954

ST984

Plumbing underground sanitary/storm rough-in

28-Sep-14*

07-Oct-14

08-Oct-14

17-Oct-14

10

ST1224

ST994, ST1004, ST744

ST994

Waterproofing

02-Nov-14*

21-Nov-14

02-Nov-14

21-Nov-14

0

ST984, ST1004, ST1234

ST804, ST784

T27

Install Temporary Fence

24-Jun-14*

06-Jul-14

24-Jun-14

06-Jul-14

0

T37

T87, T67

T37

Mobilize Job Trailers

14-Jun-14*

24-Jun-14

14-Jun-14

24-Jun-14

0

T77

T27

T47

Provide temporary electric and lighting to buildings

25-Aug-14*

23-Sep-14

25-Aug-14

23-Sep-14

0

T67, S176

T57

Provide temporary heat

07-Apr-15*

16-May-15

07-Apr-15

16-May-15

0

S406

T67

Temporary utility poles

06-Jul-14*

21-Jul-14

10-Aug-14

24-Aug-14

34

T27

T47

T77

Site Preparation

04-Jun-14

14-Jun-14

04-Jun-14

14-Jun-14

0

A7080

T37

T87

Temporary electric to trailers

06-Jul-14*

16-Jul-14

06-Jul-14

16-Jul-14

0

T27

Footer 1

Page 8 of 8


MONROE CAMPUS... Activ Activity Name ID

Project: MONRO WBS: Volume 1

BASELINE nal Start

vity Qtr 4, 2013

ion 479 10-Oct-13 A 47 10-Oct-13

Qtr 1, 2014

Qtr 2, 2014

Qtr 3, 2014

78 10-Oct-13 0%

List A of drawings

21 27-Dec-13 0%

Prevailing wage documents

Electrical A Constructio

7 17-Jan-14 0%

Electrical Construction bid form

Plumbing A constructio

6 17-Jan-14 0%

Plumbing construction bid form

Hvac A construction bid

6 17-Jan-14 0%

Hvac construction bid

General A construction

7 17-Jan-14 0%

General construction bid form

Instruction A to bidders

13 17-Jan-14 0%

Qualification A question

6 17-Jan-14 0%

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

Qtr 3, 2017

2017

Instruction to bidders Qualification questionnaire

25 17-Jan-14 0%

invitation to bid

5 17-Jan-14 0%

Sample Insurance certificates

11 10-Feb-14 0%

Bid security

Safety A and health ma

4 10-Feb-14 0%

Safety and health management plan

Standard A General co

1 10-Feb-14 0%

Standard General conditions

Payment A bond

1 10-Feb-14 0%

Payment bond

Performance A bond

1 10-Feb-14 0%

Performance bond

AIA A document a132

1 10-Feb-14 0%

AIA document a132

Non A collusion affidavit

1 10-Feb-14 0%

Non collusion affidavit

47 10-Oct-13

Alteration A Project pro

4 10-Oct-13 0%

Contract A Modification

51 10-Oct-13 0%

Leed A & sustainable d

7 10-Oct-13 0%

Testing A for indoor air

19 10-Oct-13 0%

Testing for indoor air quality

Cutting A and patching

21 10-Oct-13 0%

Cutting and patching

LEED A submital Form

38 29-Oct-13 0%

Coordination A drawings

17 27-Dec-13 0%

Field A engineering

10 27-Dec-13 0%

Product A requirements

39 10-Feb-14 0%

Unit A prices

43 10-Feb-14 0%

Payement A procedures

00 11-Feb-14 0%

Demonstration A & train

330 11-Feb-14 0%

Construction A waste m

868 11-Feb-14 0%

Summary A

12 21-Feb-14 0%

References A

14 05-Mar-14 0%

Quality A requirements

49 05-Mar-14 0%

Submittal A form

46 05-Mar-14 0%

Alternates A

12 05-Mar-14 0%

Quantity A allowances

26 05-Mar-14 0%

Work A restrictions

46 05-Mar-14 0%

Alteration Project procedures Contract Modification Leed & sustainable design requirements

LEED submital Form Coordination drawings Field engineering Product requirements Unit prices Payement procedures Demonstration & training Construction waste mangement Summary References Quality requirements Submittal form Alternates Quantity allowances Work restrictions

Summary A of multiple c

6 05-Mar-14 0%

Summary of multiple contracts

General A Commission

5 05-Mar-14 0%

General Commissioning requirements

Start A milestone

1 27-Mar-14* 0%

Execution A

Qtr 4, 2015

List of drawings

8 17-Jan-14 0%

WBS: Division 01 G

Qtr 3, 2015

Geotechnical investigation

Prevailing A wage docu

Bid A security

Qtr 2, 2015

21-Feb-14, WBS: Division 00 bidding & contract requirements

Geotechnical A investig

Sample A Insurance ce

Qtr 1, 2015

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct %

WBS: Division 00 b 135 10-Oct-13

invitation A to bid

Qtr 4, 2014

14-Apr-14 20:55

00 09-Apr-14

Start milestone

0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Execution Summary

Page 1 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE vity Qtr 4, 2013

Project A Management

ion 996 18-Apr-14

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct % 0% Project Management & coordination

Construction A Progres

966 18-May-14 0%

Construction Progress documentation

Web A based project m

955 28-May-14 0%

Web based project management

Temporary A Facilities &

946 07-Jun-14 0%

Temporary Facilities & controls

Operation A and mainte

850 11-Sep-14 0%

Operation and maintenance data

Project A record docum

666 14-Mar-15 0% 1 16-Dec-15* 0%

Checklist A enrollment

9 30-Apr-16

Checklist A classroom

9 26-Sep-16 0% 9 30-Dec-16 0%

Close A out procedures

79 08-Jan-17 0%

Demobilize A job trailers

176 08-Jan-17 0%

WBS: Sitework

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

Qtr 3, 2017

Project record documents Substantial milestone

0%

Checklist A student life

Final A Milestone

Qtr 2, 2014

2017

nal Start

Substantial A milestone

Qtr 1, 2014

14-Apr-14 20:55

Checklist enrollment building Checklist classroom roe Checklist student life building Close out procedures Demobilize job traile

1 27-Oct-17* 0% 744 27-Mar-14

08-Apr-16, WBS: Sitework

WBS: Division 33: U 337 05-May-14 Water system

120 05-May-14 00%

Install Storm Sewer

245 12-May-14 0%

Install Sanitary Sewer

45 30-Jun-14* 0%

Site lighting

40 30-Jun-14* 0%

Electrical ductbank

50 06-Jul-14* 0%

Install Geo Exchange

100 28-Dec-14* 0%

06-Apr-15, WBS: Division 33: Utilities Water system Install Storm Sewer Install Sanitary Sewer Site lighting Electrical ductbank Install Geo Exchange Field

WBS: Division 10: S 744 27-Mar-14

08-Apr-16, WBS: Division 10: Specialties

Install flagpoles

744 27-Mar-14 0%

Install A all site utilties

70 27-Mar-14* 0%

Install flagpoles

Parking control equip

25 24-Aug-15* 0%

Parking control equipment

Timber guide railings

20 25-Aug-15* 0%

Timber guide railings

Exterior site railings

38 03-Nov-15* 0%

site linestripping and

26 14-Mar-16* 0%

Install all site utilties

Exterior site railings site linestripping and signage

WBS: Division 31: E 298 28-Mar-14

19-Jan-15, WBS: Division 31: Earthwork

Site Layout

30 28-Mar-14 0%

Site Layout

Erosion controls

25 02-Apr-14* 0%

Erosion controls

Site Clearing and Stri

70 27-Apr-14* 0%

Site grading

120 05-May-14* 0%

Temporary Basin and

35 07-May-14* 0%

Install Sediment Basin

50 06-Jul-14* 0%

Site excavation

140 02-Sep-14* 0%

Site Clearing and Strip Topsoil Site grading Temporary Basin and Swales Install Sediment Basin Site excavation

WBS: Division 32: S 703 27-Mar-14 Install Rock Construc

15 27-Mar-14 0%

Install Paving binder a

20 12-May-14* 0%

27-Feb-16, WBS: Division 32: Site Improvements Install Rock Construction Entrance Install Paving binder access roads and staging areas

Install additional stagi

30 24-Jul-14* 0%

Concrete curbs

100 09-Aug-14* 0%

Install new topsoil

35 25-Aug-14 0%

Retaining wall

40 17-Nov-14* 0%

Place trees and shru

40 20-Jan-15* 0%

Exterior masonry sea

30 13-Apr-15* 0%

Exterior masonry seat walls and site walls

Retaining wall for land

20 25-May-15* 0%

Retaining wall for landscaping

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Install additional staging areas Concrete curbs Install new topsoil Retaining wall Place trees and shrubbery

Summary

Page 2 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE nal Start

vity Qtr 4, 2013

Qtr 1, 2014

Qtr 2, 2014

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

14-Apr-14 20:55 Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

Qtr 3, 2017

2017

sidewalks and ramp c

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 65 26-May-15* 0% sidewalks and ramp concrete pour

Fiberglass bus statio

35 25-Aug-15* 0%

Fiberglass bus stations

Unit Pavers

46 18-Sep-15* 0%

Unit Pavers

Final Landscaping

50 29-Sep-15* 0%

Position Site seating

25 18-Nov-15* 0%

Final placement of tre

43 13-Dec-15* 0%

Concrete bumper blo

20 08-Feb-16* 0%

WBS: Foundatio Construct building pad Layout for foundation

Final Landscaping Position Site seating Final placement of trees and shrubbery Concrete bumper blocks

101 09-Jun-14

17-Sep-14, WBS: Foundation

21 09-Jun-14* 0%

Construct building pad

7 08-Jul-14* 0%

Layout for foundation

Tie Rebar

20 15-Jul-14* 0%

Footing excavation

45 04-Aug-14* 0%

Footing excavation

Concrete foundation

45 04-Aug-14* 0%

Concrete foundation

WBS: Temporar

Tie Rebar

346 04-Jun-14

16-May-15, WBS: Temporary Construction

Site Preparation

10 04-Jun-14 0%

Mobilize Job Trailers

10 14-Jun-14* 0%

Install Temporary Fen

12 24-Jun-14* 0%

Install Temporary Fence

Temporary utility poles

15 06-Jul-14* 0%

Temporary utility poles

Temporary electric to

10 06-Jul-14* 0%

Provide temporary ele

30 25-Aug-14* 0%

Provide temporary he

40 07-Apr-15* 0%

WBS: Building 1

Site Preparation Mobilize Job Trailers

Temporary electric to trailers Provide temporary electric and lighting to buildings Provide temporary heat

609 18-Sep-14

19-May-16, WBS: Building 1 ( Administration building )

WBS: Structure an and 235 18-Sep-14 WBS: Division 3

10-May-15, WBS: Structure and Rough In

142 18-Sep-14

06-Feb-15, WBS: Division 3

Plumbing undergroun

10 18-Sep-14* 0%

Deep underground ro

15 28-Sep-14* 0%

Stone under slab rou

12 25-Nov-14 0%

Stone under slab

15 07-Dec-14 0%

Pour concrete slab o

32 22-Dec-14 0%

Pour concrete slab o

15 23-Jan-15 0%

WBS: Division 8

Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade

35 06-Apr-15

10-May-15, WBS: Division 8

Aluminum windows &

10 06-Apr-15

0%

Aluminum entrance d

25 16-Apr-15

0%

WBS: Division 4

Plumbing underground sanitary/storm rough-in

Aluminum windows & curtain walls Aluminum entrance doors/sliding doors

57 07-Feb-15

04-Apr-15, WBS: Division 4

CMU walls

20 07-Feb-15 0%

Masonry veneer

37 27-Feb-15 0%

Masonry veneer

29 27-Feb-15 0%

Layout stone veneer

Layout stone veneer WBS: Division 5

155 02-Nov-14

Erect structural steel

23 02-Nov-14 0%

Cold formed metal fra

25 25-Nov-14 0%

Metal roof ladders WBS: Division 7

CMU walls

05-Apr-15, WBS: Division 5 Erect structural steel and deck Cold formed metal framing and sheathing

20 17-Mar-15 0%

Metal roof ladders

184 13-Oct-14

Waterproofing

20 13-Oct-14* 0%

Install air membrane

18 20-Dec-14 0%

Spray urethane insula

20 07-Jan-15 0%

Wood blocking & she

10 27-Jan-15 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

14-Apr-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Summary

Page 3 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Insulated metal wall p

BASELINE nal Start

vity Qtr 4, 2013

Qtr 2, 2014

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

Qtr 3, 2015

7 06-Feb-15 0%

Roof Drains

11 06-Feb-15 0% 5 13-Feb-15 0%

Metal soffit and fascia

13 04-Mar-15 0%

Roof metal edges

Exterior Caulking

10 05-Apr-15

WBS: Finishes

478 27-Jan-15

0%

4 01-Feb-15* 0%

Install railings

13 05-Feb-15* 0% 9 18-Feb-15* 0% 5 27-Feb-15* 0%

Ceramic A and porcela

7 04-Mar-15* 0%

Painting A

9 11-Mar-15* 0%

Wall A coverings

6 20-Mar-15* 0% 10 02-Apr-15* 0%

PC A overhead pipe

10 12-Apr-15* 0%

Qtr 3, 2017

2017

Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe

5 22-Apr-15* 0%

PC insulation

PC A drop sprinkler hea

10 27-Apr-15* 0%

PC drop sprinkler head

PC A casework fixtures

5 07-May-15* 0%

PC casework fixtures

PC A toilet fixtures

5 12-May-15* 0%

HC A hangers

5 17-May-15* 0%

HC A pipe install

7 22-May-15* 0%

HC A duct install

5 29-May-15* 0%

PC toilet fixtures HC hangers HC pipe install HC duct install

HC A ATC rough-in

11 03-Jun-15* 0%

HC A GRD install

15 14-Jun-15* 0%

HC A equipment and fin

12 29-Jun-15* 0%

HC A kitchen equipmen

10 11-Jul-15*

EC A rough-in walls

12 21-Jul-15* 0%

EC A overhead rough-in

14 02-Aug-15* 0%

EC A cable tray

14 15-Aug-15* 0%

EC cable tray

EC A wiring

9 30-Aug-15* 0%

EC wiring

EC A light fixtures

8 07-Sep-15* 0%

EC A wring devices

5 15-Sep-15* 0%

EC A fire alarm and sec

6 20-Sep-15* 0%

EC A kitchen equipmen

10 26-Sep-15* 0%

EC A hook ups and con

5 06-Oct-15* 0%

Casework/millwork A

8 11-Oct-15* 0%

Resilent A tile base and

8 19-Oct-15* 0%

Resilent tile base and floor

8 27-Oct-15* 0%

Seamless vinyl flooring

Carpet A tiles

Qtr 2, 2017

Interior H.M frames

7 26-Mar-15* 0%

PC A AG san/rw

Seamless A vinyl floorin

Qtr 1, 2017

19-May-16, WBS: Finishes Metal stairs

Caulking A

PC A insulation

Qtr 4, 2016

Exterior Caulking

5 27-Jan-15* 0%

Drywall A and spackliing

Acoustical A ceiling grid

Qtr 3, 2016

Roof top equipment

Roof metal edges

Interior A H.M frames

Qtr 2, 2016

Roof Drains

15 17-Feb-15 0%

Install A railings

Qtr 1, 2016

Roof curbs

Metal soffit and fascia

Metal A stairs

Qtr 4, 2015

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 20 27-Jan-15 0% Insulated metal wall panels

Roof curbs Roof top equipment

Qtr 1, 2014

14-Apr-14 20:55

HC ATC rough-in HC GRD install HC equipment and final connections

0%

HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 04-Nov-15* 0%

Install A rubber stairs, t

7 15-Nov-15* 0%

Doors A and Hardware

6 22-Nov-15* 0%

Interior A glass partitions

8 28-Nov-15* 0%

Wood A wall panels

5 06-Dec-15* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Summary

Page 4 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Visual A display surface

BASELINE nal Start

vity Qtr 4, 2013

Qtr 1, 2014

Qtr 2, 2014

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

14-Apr-14 20:55 Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

5 16-Dec-15* 0%

Signage

Wood A ceiling

3 21-Dec-15* 0%

Wood ceiling

Place A Acoustical ceilin

11 24-Dec-15* 0%

Tiolet A complartments

8 04-Jan-16* 0%

Fire A protection specia

6 11-Jan-16* 0%

Wire A mesh partitions Install A lockers

Qtr 3, 2016

5 25-Feb-16* 0%

Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment

5 01-Mar-16* 0%

Glass wall folding partition

Loading A dock equipm

12 06-Mar-16* 0%

Loading dock equipment

Paint A gym ceiling

5 18-Mar-16* 0%

Paint gym ceiling

Gym A equipment

7 23-Mar-16* 0%

Gym equipment

Gym A dividers

9 30-Mar-16* 0%

Gym dividers

Install A hardwood floor

7 08-Apr-16* 0%

Install A collapsable bel

6 15-Apr-16* 0%

Hydraulic A elevators

8 22-Apr-16* 0% 10 30-Apr-16

Install hardwood flooring Install collapsable belachers Hydraulic elevators

0%

Install kitchen tiles

9 10-May-16 0%

Motorized projection screens

843 28-Sep-14

18-Jan-17, WBS: Building 2 (Student Life)

WBS: Structure an and 245 28-Sep-14

30-May-15, WBS: Structure and Rough In

152 28-Sep-14

26-Feb-15, WBS: Division 3

Plumbing undergroun

10 28-Sep-14* 0%

Deep underground ro

15 08-Oct-14* 0%

Stone under slab rou

12 15-Dec-14 0%

Stone under slab

15 27-Dec-14 0%

Pour concrete slab o

32 11-Jan-15

Pour concrete slab o

15 12-Feb-15 0%

WBS: Division 8

Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade 30-May-15, WBS: Division 8

Aluminum entrance d

25 06-May-15 0%

0%

Aluminum windows & curtain walls Aluminum entrance doors/sliding doors

57 27-Feb-15

24-Apr-15, WBS: Division 4

CMU walls

20 27-Feb-15 0%

Masonry veneer

37 19-Mar-15 0%

CMU walls Masonry veneer

155 22-Nov-14

25-Apr-15, WBS: Division 5

Erect structural steel

23 22-Nov-14 0%

Cold formed metal fra

25 15-Dec-14 0%

Metal roof ladders

20 06-Apr-15

WBS: Division 7

184 02-Nov-14

Erect structural steel and deck Cold formed metal framing and sheathing

0%

Waterproofing

20 02-Nov-14* 0%

Install air membrane

18 09-Jan-15 0%

Spray urethane insula

20 27-Jan-15 0%

Wood blocking & she

10 16-Feb-15 0%

Insulated metal wall p

20 16-Feb-15 0%

Roof curbs

Deep underground rough-in

35 26-Apr-15 10 26-Apr-15

WBS: Division 5

Plumbing underground sanitary/storm rough-in

0%

Aluminum windows & WBS: Division 4

2017

Window shades

Glass A wall folding par

WBS: Division 3

Qtr 3, 2017

Fire protection specialities

7 27-Jan-16* 0%

Install A and setup food

WBS: Building 2

Qtr 2, 2017

Tiolet complartments

13 03-Feb-16* 0% 9 16-Feb-16* 0%

Motorized A projection

Qtr 1, 2017

Place Acoustical ceiling tiles

10 17-Jan-16* 0%

Install A hood and walk

Install A kitchen tiles

Qtr 4, 2016

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 5 11-Dec-15* 0% Visual display surfaces

Signage A

Window A shades

Qtr 2, 2016

Metal roof ladders 04-May-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels

7 26-Feb-15 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Roof curbs Summary

Page 5 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Roof Drains Roof top equipment

BASELINE nal Start

vity Qtr 4, 2013

Qtr 1, 2014

Qtr 2, 2014

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

14-Apr-14 20:55

Qtr 2, 2015

Qtr 3, 2015

5 05-Mar-15 0%

Metal soffit and fascia

Roof metal edges

13 24-Mar-15 0%

Roof metal edges

Exterior Caulking

10 25-Apr-15

WBS: Finishes

633 26-Apr-15

Interior A H.M frames

0%

Qtr 4, 2016

4 01-May-15* 0%

Install railings

13 05-May-15* 0%

Caulking A

5 27-May-15* 0%

Ceramic A and porcela

7 01-Jun-15* 0%

Painting A

9 08-Jun-15* 0%

Wall A coverings

6 17-Jun-15* 0%

Acoustical A ceiling grid

7 23-Jun-15* 0%

PC A AG san/rw

10 30-Jun-15* 0%

PC A overhead pipe

10 10-Jul-15* 0%

Qtr 2, 2017

Qtr 3, 2017

2017

Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe

5 17-Dec-15* 0%

PC insulation

PC A drop sprinkler hea

10 22-Dec-15* 0%

PC drop sprinkler head

PC A casework fixtures

5 01-Jan-16* 0%

PC casework fixtures

PC A toilet fixtures

5 06-Jan-16* 0%

PC A kitchen equipmen

6 11-Jan-16* 0%

HC A hangers

5 17-Jan-16* 0%

HC A pipe install

7 22-Jan-16* 0%

PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install

5 29-Jan-16* 0%

HC duct install

HC A ATC rough-in

11 03-Feb-16* 0%

HC A GRD install

15 14-Feb-16* 0%

HC A equipment and fin

12 28-Feb-16* 0%

HC A kitchen equipmen

10 11-Mar-16* 0%

EC A rough-in walls

12 21-Mar-16* 0%

EC A overhead rough-in

14 02-Apr-16* 0%

EC A cable tray

14 16-Apr-16* 0%

EC cable tray

EC A wiring

9 30-Apr-16* 0%

EC wiring

EC A light fixtures

8 08-May-16* 0%

EC A wring devices

5 16-May-16* 0%

EC A fire alarm and sec

6 21-May-16* 0%

EC A kitchen equipmen

10 28-May-16* 0%

EC A hook ups and con

5 07-Jun-16* 0%

Casework/millwork A

8 12-Jun-16* 0%

Resilent A tile base and

8 19-Jun-16* 0%

Resilent tile base and floor

Seamless A vinyl floorin

8 27-Jun-16* 0%

Seamless vinyl flooring

Carpet A tiles

Qtr 1, 2017

18-Jan-17, WBS: Finishes Metal stairs

9 18-May-15* 0%

HC A duct install

Qtr 3, 2016

Exterior Caulking

5 26-Apr-15* 0%

Drywall A and spackliing

PC A insulation

Qtr 2, 2016

Roof top equipment

15 09-Mar-15 0%

Install A railings

Qtr 1, 2016

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 11 26-Feb-15 0% Roof Drains

Metal soffit and fascia

Metal A stairs

Qtr 4, 2015

HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 05-Jul-16* 0%

Install A rubber stairs, t

7 16-Jul-16* 0%

Doors A and Hardware

6 23-Jul-16* 0%

Interior A glass partitions

8 29-Jul-16* 0%

Wood A wall panels

5 07-Aug-16* 0%

Visual A display surface

5 12-Aug-16* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Summary

Page 6 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Signage A Wood A ceiling

BASELINE nal Start

vity Qtr 4, 2013

Tiolet A complartments

8 04-Sep-16* 0%

Fire A protection specia

6 12-Sep-16* 0%

Install A lockers

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

3 22-Aug-16* 0% 11 25-Aug-16* 0%

Wire A mesh partitions

Qtr 2, 2014

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

Place Acoustical ceiling tiles Tiolet complartments Fire protection specialities Window shades

7 28-Sep-16* 0%

Wire mesh partitions

13 05-Oct-16* 0% 9 18-Oct-16* 0%

Install A and setup food

5 27-Oct-16* 0%

Glass A wall folding par

5 01-Nov-16* 0%

Loading A dock equipm

12 06-Nov-16* 0%

Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment

Paint A gym ceiling

5 18-Nov-16* 0%

Paint gym ceiling

Gym A equipment

7 23-Nov-16* 0%

Gym equipment

Gym A dividers

9 30-Nov-16* 0%

Gym dividers

Install A hardwood floor

7 09-Dec-16* 0%

Install A collapsable bel

6 16-Dec-16* 0%

Hydraulic A elevators

8 22-Dec-16* 0%

Hydraulic elevators

Install A kitchen tiles

10 30-Dec-16* 0%

Install kitchen tiles

WBS: Building 3

Install hardwood flooring Install collapsable belachers

9 09-Jan-17* 0%

Motorized projection screens

719 08-Oct-14

26-Sep-16, WBS: Building 3 (ClassRooms)

WBS: Structure an and 254 08-Oct-14 WBS: Division 4

18-Jun-15, WBS: Structure and Rough In

57 19-Mar-15

14-May-15, WBS: Division 4

CMU walls

20 19-Mar-15 0%

Masonry veneer

37 08-Apr-15

WBS: Division 5

CMU walls

0%

Masonry veneer

155 22-Nov-14

25-Apr-15, WBS: Division 5

Erect structural steel

23 22-Nov-14 0%

Cold formed metal fra

25 15-Dec-14 0%

Metal roof ladders

20 06-Apr-15

WBS: Division 7

204 02-Nov-14

Erect structural steel and deck Cold formed metal framing and sheathing

0%

Waterproofing

20 02-Nov-14* 0%

Install air membrane

18 09-Jan-15 0%

Spray urethane insula

20 27-Jan-15 0%

Wood blocking & she

10 16-Feb-15 0%

Insulated metal wall p

20 16-Feb-15 0%

Roof curbs

7 26-Feb-15 0%

Roof Drains

11 26-Feb-15 0%

Roof top equipment

Metal roof ladders 24-May-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels Roof curbs Roof Drains

5 05-Mar-15 0%

Roof top equipment

Metal soffit and fascia

15 09-Mar-15 0%

Metal soffit and fascia

Roof metal edges

13 24-Mar-15 0%

Roof metal edges

Exterior Caulking

10 15-May-15 0%

WBS: Division 3

2017

Wood ceiling

10 18-Sep-16* 0%

Install A hood and walk

Motorized A projection

Qtr 3, 2017

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 5 17-Aug-16* 0% Signage

Place A Acoustical ceilin

Window A shades

Qtr 1, 2014

14-Apr-14 20:55

Exterior Caulking

154 08-Oct-14

Plumbing undergroun

10 08-Oct-14* 0%

Deep underground ro

15 18-Oct-14* 0%

Stone under slab rou

12 27-Dec-14 0%

Stone under slab

15 08-Jan-15 0%

Pour concrete slab o

32 23-Jan-15 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

10-Mar-15, WBS: Division 3 Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck Summary

Page 7 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID Pour concrete slab o WBS: Division 8 Aluminum windows &

BASELINE nal Start

vity Qtr 4, 2013

54 26-Apr-15 10 26-Apr-15

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

25 25-May-15 0% 465 19-Jun-15

Qtr 1, 2017

Qtr 2, 2017

Qtr 3, 2017

2017

Aluminum windows & curtain walls Aluminum entrance doors/sliding doors 26-Sep-16, WBS: Finishes

Metal A stairs

5 19-Jun-15* 0%

Install A railings

4 24-Jun-15* 0%

Metal stairs Install railings

13 28-Jun-15* 0%

Drywall A and spackliing

9 11-Jul-15*

Caulking A

5 20-Jul-15* 0%

Ceramic A and porcela

7 25-Jul-15* 0%

Painting A

9 01-Aug-15* 0%

Wall A coverings

6 10-Aug-15* 0%

Acoustical A ceiling grid

7 16-Aug-15* 0%

Interior H.M frames

0%

PC A AG san/rw

10 23-Aug-15* 0%

PC A overhead pipe

10 02-Sep-15* 0%

Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe

5 12-Sep-15* 0%

PC insulation

PC A drop sprinkler hea

10 17-Sep-15* 0%

PC drop sprinkler head

PC A casework fixtures

5 27-Sep-15* 0%

PC casework fixtures

PC A toilet fixtures

5 02-Oct-15* 0%

PC A kitchen equipmen

6 07-Oct-15* 0%

HC A hangers

5 13-Oct-15* 0%

HC A pipe install

7 18-Oct-15* 0%

HC A duct install

5 25-Oct-15* 0%

PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install HC duct install

HC A ATC rough-in

11 30-Oct-15* 0%

HC A GRD install

15 10-Nov-15* 0%

HC A equipment and fin

12 25-Nov-15* 0%

HC A kitchen equipmen

10 07-Dec-15* 0%

EC A rough-in walls

12 17-Dec-15* 0%

EC A overhead rough-in

14 29-Dec-15* 0%

EC A cable tray

14 11-Jan-16* 0%

EC cable tray

EC A wiring

9 26-Jan-16* 0%

EC wiring

EC A light fixtures

8 03-Feb-16* 0%

EC A wring devices

5 11-Feb-16* 0%

EC A fire alarm and sec

6 16-Feb-16* 0%

EC A kitchen equipmen

10 22-Feb-16* 0%

EC A hook ups and con

5 03-Mar-16* 0%

Casework/millwork A

8 08-Mar-16* 0%

Resilent A tile base and

8 16-Mar-16* 0%

Resilent tile base and floor

Seamless A vinyl floorin

8 24-Mar-16* 0%

Seamless vinyl flooring

Carpet A tiles

Qtr 4, 2016

18-Jun-15, WBS: Division 8 0%

Aluminum entrance d

PC A insulation

Qtr 2, 2014

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 15 24-Feb-15 0% Pour concrete slab on grade

WBS: Finishes

Interior A H.M frames

Qtr 1, 2014

14-Apr-14 20:55

HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in

EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork

11 01-Apr-16* 0%

Install A rubber stairs, t

7 12-Apr-16* 0%

Doors A and Hardware

6 19-Apr-16* 0%

Interior A glass partitions

8 25-Apr-16* 0%

Wood A wall panels

5 03-May-16* 0%

Visual A display surface

5 08-May-16* 0%

Signage A

5 13-May-16* 0%

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Signage Summary

Page 8 of 9

TASK filter: All Activities Š Oracle Corporation


MONROE CAMPUS... Activ Activity Name ID

BASELINE nal Start

vity Qtr 4, 2013

Qtr 1, 2014

Qtr 2, 2014

Qtr 3, 2014

Qtr 4, 2014

Qtr 1, 2015

Qtr 2, 2015

14-Apr-14 20:55 Qtr 3, 2015

Qtr 4, 2015

Qtr 1, 2016

Qtr 2, 2016

Qtr 3, 2016

Qtr 4, 2016

Qtr 1, 2017

Qtr 2, 2017

Qtr 3, 2017

2017

Wood A ceiling

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 3 18-May-16* 0% Wood ceiling

Place A Acoustical ceilin

11 21-May-16* 0%

Tiolet A complartments

8 01-Jun-16* 0%

Fire A protection specia Window A shades Wire A mesh partitions Install A lockers

Place Acoustical ceiling tiles Tiolet complartments

6 08-Jun-16* 0%

Fire protection specialities

10 14-Jun-16* 0%

Window shades

7 24-Jun-16* 0%

Wire mesh partitions

13 01-Jul-16* 0%

Install lockers

Observation A deck

9 14-Jul-16* 0%

Install A Medical recline

5 23-Jul-16* 0%

Install Medical reclined chair

Glass A wall folding par

5 28-Jul-16* 0%

Glass wall folding partition

Place A additional medi

12 02-Aug-16* 0%

Install A lecture seating

5 14-Aug-16* 0%

Install A Student Desks

7 19-Aug-16* 0%

Lab A Desks

9 26-Aug-16* 0%

Install A hardwood floor

7 04-Sep-16* 0%

Teacher A desks

6 11-Sep-16* 0%

Hydraulic A elevators

8 18-Sep-16* 0%

Project: Monroe

0

Project: Monroe

0

Project: Monroe Project: Monroe

0

Observation deck

Place additional medical equipment Install lecture seating Install Student Desks and chairs Lab Desks Install hardwood flooring Teacher desks Hydraulic elevators

0

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Page 9 of 9

TASK filter: All Activities Š Oracle Corporation


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8360

78

78 7-Day Workweek

0

Geotechnical investigation

10-Oct-13

26-Dec-13

10-Oct-13

26-Dec-13

0

A8450

4

4 7-Day Workweek

0

Alteration Project procedures

10-Oct-13

13-Oct-13

10-Oct-13

13-Oct-13

0

A8530

51

51 7-Day Workweek

0

Contract Modification

10-Oct-13

29-Nov-13

10-Oct-13

29-Nov-13

0

A8740

19

19 7-Day Workweek

0

Testing for indoor air quality

10-Oct-13

28-Oct-13

10-Oct-13

28-Oct-13

0

A8800

21

21 7-Day Workweek

0

Cutting and patching

10-Oct-13

30-Oct-13

10-Oct-13

30-Oct-13

0

A8730

7

7 7-Day Workweek

0

Leed & sustainable design requirements

10-Oct-13

16-Oct-13

22-Oct-13

28-Oct-13

12

A8460

38

38 7-Day Workweek

0

LEED submital Form

29-Oct-13

06-Dec-13

29-Oct-13

06-Dec-13

0

A8570

10

10 7-Day Workweek

0

Field engineering

27-Dec-13

05-Jan-14

27-Dec-13

05-Jan-14

0

A8610

21

21 7-Day Workweek

0

List of drawings

27-Dec-13

16-Jan-14

27-Dec-13

16-Jan-14

0

A8500

17

17 7-Day Workweek

0

Coordination drawings

27-Dec-13

13-Jan-14

04-Feb-14

21-Feb-14

39

A8300

8

8 7-Day Workweek

0

Prevailing wage documents

17-Jan-14

25-Jan-14

17-Jan-14

25-Jan-14

0

A8320

7

7 7-Day Workweek

0

Electrical Construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8330

6

6 7-Day Workweek

0

Plumbing construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8340

6

6 7-Day Workweek

0

Hvac construction bid

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8350

7

7 7-Day Workweek

0

General construction bid form

17-Jan-14

23-Jan-14

17-Jan-14

23-Jan-14

0

A8370

13

13 7-Day Workweek

0

Instruction to bidders

17-Jan-14

29-Jan-14

17-Jan-14

29-Jan-14

0

A8380

6

6 7-Day Workweek

0

Qualification questionnaire

17-Jan-14

22-Jan-14

17-Jan-14

22-Jan-14

0

A8390

25

25 7-Day Workweek

0

invitation to bid

17-Jan-14

10-Feb-14

17-Jan-14

10-Feb-14

0

A8640

5

5 7-Day Workweek

0

Sample Insurance certificates

17-Jan-14

21-Jan-14

17-Jan-14

21-Jan-14

0

A8310

11

11 7-Day Workweek

0

Bid security

10-Feb-14

21-Feb-14

10-Feb-14

21-Feb-14

0

A8410

39

39 7-Day Workweek

0

Product requirements

10-Feb-14

21-Mar-14

10-Feb-14

21-Mar-14

0

A8550

43

43 7-Day Workweek

0

Unit prices

10-Feb-14

26-Mar-14

10-Feb-14

26-Mar-14

0

A8620

4

4 7-Day Workweek

0

Safety and health management plan

10-Feb-14

14-Feb-14

10-Feb-14

14-Feb-14

0

A8630

1

1 7-Day Workweek

0

Standard General conditions

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8650

1

1 7-Day Workweek

0

Payment bond

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8660

1

1 7-Day Workweek

0

Performance bond

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8670

1

1 7-Day Workweek

0

AIA document a132

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

A8680

1

1 7-Day Workweek

0

Non collusion affidavit

10-Feb-14

11-Feb-14

10-Feb-14

11-Feb-14

0

1008 1008 7-Day Workweek

0

Payement procedures

11-Feb-14

15-Nov-16

11-Feb-14

15-Nov-16

0

A8520 A8750

330

330 7-Day Workweek

0

Demonstration & training

11-Feb-14

07-Jan-15

11-Feb-14

07-Jan-15

0

A8790

868

868 7-Day Workweek

0

Construction waste mangement

11-Feb-14

28-Jun-16

24-Aug-14

08-Jan-17

193

A8600

12

12 7-Day Workweek

0

Summary

21-Feb-14

05-Mar-14

21-Feb-14

05-Mar-14

0

A8430

14

14 7-Day Workweek

0

References

05-Mar-14

19-Mar-14

05-Mar-14

19-Mar-14

0

A8440

49

49 7-Day Workweek

0

Quality requirements

05-Mar-14

23-Apr-14

05-Mar-14

23-Apr-14

0

A8470

46

46 7-Day Workweek

0

Submittal form

05-Mar-14

21-Apr-14

05-Mar-14

21-Apr-14

0

A8540

12

12 7-Day Workweek

0

Alternates

05-Mar-14

18-Mar-14

05-Mar-14

18-Mar-14

0

A8560

26

26 7-Day Workweek

0

Quantity allowances

05-Mar-14

31-Mar-14

05-Mar-14

31-Mar-14

0

Page 1 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8580

46

46 7-Day Workweek

0

Work restrictions

05-Mar-14

20-Apr-14

05-Mar-14

20-Apr-14

0

A8590

6

6 7-Day Workweek

0

Summary of multiple contracts

05-Mar-14

11-Mar-14

05-Mar-14

11-Mar-14

0

A8690

5

5 7-Day Workweek

0

General Commissioning requirements

05-Mar-14

10-Mar-14

05-Mar-14

10-Mar-14

0

S336

744

744 7-Day Workweek

0

Install flagpoles

27-Mar-14

08-Apr-16

27-Mar-14

08-Apr-16

0

A7080

70

70 7-Day Workweek

0

Install all site utilties

27-Mar-14*

04-Jun-14

27-Mar-14

04-Jun-14

0

S96

15

15 7-Day Workweek

0

Install Rock Construction Entrance

27-Mar-14

10-Apr-14

13-May-14

27-May-14

47

1

1 7-Day Workweek

0

Start milestone

27-Mar-14*

27-Mar-14

27-Mar-14

27-Mar-14

0

A8970 S86

30

30 7-Day Workweek

0

Site Layout

28-Mar-14

26-Apr-14

28-Mar-14

26-Apr-14

0

S106

25

25 7-Day Workweek

0

Erosion controls

02-Apr-14*

26-Apr-14

02-Apr-14

26-Apr-14

0

1005 1005 7-Day Workweek

0

Execution

09-Apr-14

08-Jan-17

09-Apr-14

08-Jan-17

0

A8400 A8510

996

996 7-Day Workweek

0

Project Management & coordination

18-Apr-14

08-Jan-17

18-Apr-14

08-Jan-17

0

S116

70

70 7-Day Workweek

0

Site Clearing and Strip Topsoil

27-Apr-14*

05-Jul-14

27-Apr-14

05-Jul-14

0

S136

120

120 7-Day Workweek

0

Site grading

05-May-14*

01-Sep-14

05-May-14

01-Sep-14

0

S206

120

0 7-Day Workweek

100

Water system

05-May-14 A 17-Oct-14 A

26-Apr-14

26-Apr-14

S126

35

35 7-Day Workweek

0

Temporary Basin and Swales

07-May-14*

10-Jun-14

29-Jul-14

01-Sep-14

83

S186

245

245 7-Day Workweek

0

Install Storm Sewer

12-May-14 A 27-Dec-14

27-Apr-14

27-Dec-14

0

S156

20

20 7-Day Workweek

0

Install Paving binder access roads and staging areas

12-May-14*

31-May-14

28-May-14

16-Jun-14

16

A8480

966

966 7-Day Workweek

0

Construction Progress documentation

18-May-14

08-Jan-17

18-May-14

08-Jan-17

0

A8490

955

955 7-Day Workweek

0

Web based project management

28-May-14

08-Jan-17

28-May-14

08-Jan-17

0

10

10 7-Day Workweek

0

Site Preparation

04-Jun-14

14-Jun-14

04-Jun-14

14-Jun-14

0

A8420

946

946 7-Day Workweek

0

Temporary Facilities & controls

07-Jun-14

08-Jan-17

07-Jun-14

08-Jan-17

0

SF55

21

21 7-Day Workweek

0

Construct building pad

09-Jun-14*

29-Jun-14

17-Jun-14

07-Jul-14

8

T77

T37

10

10 7-Day Workweek

0

Mobilize Job Trailers

14-Jun-14*

24-Jun-14

14-Jun-14

24-Jun-14

0

T27

12

12 7-Day Workweek

0

Install Tempor ary Fence

24-Jun-14*

06-Jul-14

24-Jun-14

06-Jul-14

0

S226

40

40 7-Day Workweek

0

Site lighting

30-Jun-14*

08-Aug-14

24-Jul-14

01-Sep-14

24

S196

45

45 7-Day Workweek

0

Install Sanitary Sewer

30-Jun-14*

13-Aug-14

13-Sep-15

27-Oct-15

440

S146

50

50 7-Day Workweek

0

Install Sediment Basin

06-Jul-14*

24-Aug-14

06-Jul-14

24-Aug-14

0

S176

50

50 7-Day Workweek

0

Electrical ductbank

06-Jul-14*

24-Aug-14

06-Jul-14

24-Aug-14

0

T87

10

10 7-Day Workweek

0

Temporary electric to trailers

06-Jul-14*

16-Jul-14

06-Jul-14

16-Jul-14

0

T67

15

15 7-Day Workweek

0

Temporary utility poles

06-Jul-14*

21-Jul-14

10-Aug-14

24-Aug-14

34

SF25

7

7 7-Day Workweek

0

Layout for foundation

08-Jul-14*

14-Jul-14

08-Jul-14

14-Jul-14

0

SF45

20

20 7-Day Workweek

0

Tie Rebar

15-Jul-14*

03-Aug-14

15-Jul-14

03-Aug-14

0

S166

30

30 7-Day Workweek

0

Install additional staging areas

24-Jul-14*

22-Aug-14

24-Jul-14

22-Aug-14

0

SF35

45

45 7-Day Workweek

0

Footing excavation

04-Aug-14*

17-Sep-14

04-Aug-14

17-Sep-14

0

SF65

45

45 7-Day Workweek

0

Concrete foundation

04-Aug-14*

17-Sep-14

04-Aug-14

17-Sep-14

0

S216

100

100 7-Day Workweek

0

Concrete curbs

09-Aug-14*

16-Nov-14

02-Sep-14

10-Dec-14

24

T47

30

30 7-Day Workweek

0

Provide temporary electric and lighting to buildings

25-Aug-14*

23-Sep-14

25-Aug-14

23-Sep-14

0

Page 2 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

S396

35

35 7-Day Workweek

0

Install new topsoil

25-Aug-14 A 28-Sep-14

16-Dec-14

19-Jan-15

113

S386

140

140 7-Day Workweek

0

Site excavation

02-Sep-14*

19-Jan-15

02-Sep-14

19-Jan-15

0

A8770

850

850 7-Day Workweek

0

Operation and maintenance data

11-Sep-14

08-Jan-17

11-Sep-14

08-Jan-17

0

ST1224

10

10 7-Day Workweek

0

Plumbing underground sanitary/storm rough-in

18-Sep-14*

27-Sep-14

18-Sep-14

27-Sep-14

0

ST1244

15

15 7-Day Workweek

0

Deep underground rough-in

28-Sep-14*

12-Oct-14

28-Sep-14

12-Oct-14

0

ST984

10

10 7-Day Workweek

0

Plumbing underground sanitary/storm rough-in

28-Sep-14*

07-Oct-14

08-Oct-14

17-Oct-14

10

ST1004

15

15 7-Day Workweek

0

Deep underground rough-in

08-Oct-14*

22-Oct-14

18-Oct-14

01-Nov-14

10

ST744

10

10 7-Day Workweek

0

Plumbing underground sanitary/storm rough-in

08-Oct-14*

17-Oct-14

30-Jan-15

09-Feb-15

114

ST1234

20

20 7-Day Workweek

0

Waterproofing

13-Oct-14*

01-Nov-14

13-Oct-14

01-Nov-14

0

ST764

15

15 7-Day Workweek

0

Deep underground rough-in

18-Oct-14*

01-Nov-14

09-Feb-15

24-Feb-15

114

ST994

20

20 7-Day Workweek

0

Waterproofing

02-Nov-14*

21-Nov-14

02-Nov-14

21-Nov-14

0

ST1024

23

23 7-Day Workweek

0

Erect structural steel and deck

02-Nov-14

24-Nov-14

02-Nov-14

24-Nov-14

0

ST754

20

20 7-Day Workweek

0

Waterproofing

02-Nov-14*

21-Nov-14

24-Feb-15

16-Mar-15

114

S376

40

40 7-Day Workweek

0

Retaining wall

17-Nov-14*

26-Dec-14

11-Dec-14

19-Jan-15

24

ST784

23

23 7-Day Workweek

0

Erect structural steel and deck

22-Nov-14

14-Dec-14

22-Nov-14

14-Dec-14

0

ST544

23

23 7-Day Workweek

0

Erect structural steel and deck

22-Nov-14

14-Dec-14

16-Mar-15

08-Apr-15

114

ST1074

25

25 7-Day Workweek

0

Cold formed metal framing and sheathing

25-Nov-14

19-Dec-14

25-Nov-14

19-Dec-14

0

ST1254

12

12 7-Day Workweek

0

Stone under slab rough-in

25-Nov-14

06-Dec-14

25-Nov-14

06-Dec-14

0

ST1044

15

15 7-Day Workweek

0

Stone under slab

07-Dec-14

21-Dec-14

07-Dec-14

21-Dec-14

0

ST834

25

25 7-Day Workweek

0

Cold formed metal framing and sheathing

15-Dec-14

08-Jan-15

15-Dec-14

08-Jan-15

0

ST1014

12

12 7-Day Workweek

0

Stone under slab rough-in

15-Dec-14

26-Dec-14

16-Dec-14

27-Dec-14

1

ST594

25

25 7-Day Workweek

0

Cold formed metal framing and sheathing

15-Dec-14

08-Jan-15

08-Apr-15

03-May-15

114

ST1094

18

18 7-Day Workweek

0

Install air membrane

20-Dec-14

06-Jan-15

20-Dec-14

06-Jan-15

0

ST1034

32

32 7-Day Workweek

0

Pour concrete slab on deck

22-Dec-14

22-Jan-15

22-Dec-14

22-Jan-15

0

ST804

15

15 7-Day Workweek

0

Stone under slab

27-Dec-14

10-Jan-15

28-Dec-14

11-Jan-15

1

ST774

12

12 7-Day Workweek

0

Stone under slab rough-in

27-Dec-14

07-Jan-15

09-Apr-15

21-Apr-15

103

100

100 7-Day Workweek

0

Install Geo Exchange Field

28-Dec-14*

06-Apr-15

28-Dec-14

06-Apr-15

0

ST1084

20

20 7-Day Workweek

0

Spray urethane insulation

07-Jan-15

26-Jan-15

07-Jan-15

26-Jan-15

0

ST564

15

15 7-Day Workweek

0

Stone under slab

08-Jan-15

22-Jan-15

21-Apr-15

06-May-15

103

S406

ST854

18

18 7-Day Workweek

0

Install air membrane

09-Jan-15

26-Jan-15

09-Jan-15

26-Jan-15

0

ST614

18

18 7-Day Workweek

0

Install air membrane

09-Jan-15

26-Jan-15

03-May-15

21-May-15

114

ST794

32

32 7-Day Workweek

0

Pour concrete slab on deck

11-Jan-15

11-Feb-15

12-Jan-15

12-Feb-15

1

S246

40

40 7-Day Workweek

0

Place trees and shrubbery

20-Jan-15*

28-Feb-15

20-Jan-15

28-Feb-15

0

ST1064

15

15 7-Day Workweek

0

Pour concrete slab on grade

23-Jan-15

06-Feb-15

23-Jan-15

06-Feb-15

0

ST554

32

32 7-Day Workweek

0

Pour concrete slab on deck

23-Jan-15

23-Feb-15

06-May-15

07-Jun-15

103

ST844

20

20 7-Day Workweek

0

Spray urethane insulation

27-Jan-15

15-Feb-15

27-Jan-15

15-Feb-15

0

ST1104

10

10 7-Day Workweek

0

Wood blocking & sheathing on roof

27-Jan-15

05-Feb-15

27-Jan-15

05-Feb-15

0

Page 3 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8820

5

5 7-Day Workweek

0

Metal stairs

27-Jan-15*

31-Jan-15

27-Jan-15

31-Jan-15

0

ST1144

20

20 7-Day Workweek

0

Insulated metal wall panels

27-Jan-15

15-Feb-15

17-Mar-15

05-Apr-15

49

ST604

20

20 7-Day Workweek

0

Spray urethane insulation

27-Jan-15

15-Feb-15

21-May-15

10-Jun-15

114

A8830

4

4 7-Day Workweek

0

Install railings

01-Feb-15*

04-Feb-15

01-Feb-15

04-Feb-15

0

A8840

13

13 7-Day Workweek

0

Interior H.M frames

05-Feb-15*

17-Feb-15

05-Feb-15

17-Feb-15

0

ST1124

11

11 7-Day Workweek

0

Roof Drains

06-Feb-15

16-Feb-15

06-Feb-15

16-Feb-15

0

ST1114

7

7 7-Day Workweek

0

Roof curbs

06-Feb-15

12-Feb-15

05-Mar-15

11-Mar-15

27

ST1054

20

20 7-Day Workweek

0

CMU walls

07-Feb-15

26-Feb-15

07-Feb-15

26-Feb-15

0

ST824

15

15 7-Day Workweek

0

Pour concrete slab on grade

12-Feb-15

26-Feb-15

13-Feb-15

27-Feb-15

1

ST1134

5

5 7-Day Workweek

0

Roof top equipment

13-Feb-15

17-Feb-15

12-Mar-15

16-Mar-15

27

ST864

10

10 7-Day Workweek

0

Wood blocking & sheathing on roof

16-Feb-15

25-Feb-15

16-Feb-15

25-Feb-15

0

ST904

20

20 7-Day Workweek

0

Insulated metal wall panels

16-Feb-15

07-Mar-15

06-Apr-15

25-Apr-15

49

ST624

10

10 7-Day Workweek

0

Wood blocking & sheathing on roof

16-Feb-15

25-Feb-15

10-Jun-15

20-Jun-15

114

ST664

20

20 7-Day Workweek

0

Insulated metal wall panels

16-Feb-15

07-Mar-15

29-Jul-15

18-Aug-15

163

ST1154

15

15 7-Day Workweek

0

Metal soffit and fascia

17-Feb-15

03-Mar-15

17-Feb-15

03-Mar-15

0

A8850

9

9 7-Day Workweek

0

Drywall and spackliing

18-Feb-15*

26-Feb-15

18-Feb-15

26-Feb-15

0

ST584

15

15 7-Day Workweek

0

Pour concrete slab on grade

24-Feb-15

10-Mar-15

07-Jun-15

22-Jun-15

103

ST884

11

11 7-Day Workweek

0

Roof Drains

26-Feb-15

08-Mar-15

26-Feb-15

08-Mar-15

0

ST874

7

7 7-Day Workweek

0

Roof curbs

26-Feb-15

04-Mar-15

25-Mar-15

31-Mar-15

27

ST644

11

11 7-Day Workweek

0

Roof Drains

26-Feb-15

08-Mar-15

20-Jun-15

01-Jul-15

114

ST634

7

7 7-Day Workweek

0

Roof curbs

26-Feb-15

04-Mar-15

17-Jul-15

24-Jul-15

141

A8860

5

5 7-Day Workweek

0

Caulking

27-Feb-15*

03-Mar-15

27-Feb-15

03-Mar-15

0

ST1264

29

29 7-Day Workweek

0

Layout stone veneer

27-Feb-15

27-Mar-15

27-Feb-15

27-Mar-15

0

ST814

20

20 7-Day Workweek

0

CMU walls

27-Feb-15

18-Mar-15

28-Feb-15

19-Mar-15

1

ST1204

37

37 7-Day Workweek

0

Masonry veneer

27-Feb-15

04-Apr-15

28-Feb-15

05-Apr-15

1

ST1164

13

13 7-Day Workweek

0

Roof metal edges

04-Mar-15

16-Mar-15

04-Mar-15

16-Mar-15

0

A8870

7

7 7-Day Workweek

0

Ceramic and porcelain wall/floor tiles

04-Mar-15*

10-Mar-15

04-Mar-15

10-Mar-15

0

ST894

5

5 7-Day Workweek

0

Roof top equipment

05-Mar-15

09-Mar-15

01-Apr-15

05-Apr-15

27

ST654

5

5 7-Day Workweek

0

Roof top equipment

05-Mar-15

09-Mar-15

24-Jul-15

29-Jul-15

141

ST914

15

15 7-Day Workweek

0

Metal soffit and fascia

09-Mar-15

23-Mar-15

09-Mar-15

23-Mar-15

ST674

15

15 7-Day Workweek

0

Metal soffit and fascia

09-Mar-15

23-Mar-15

01-Jul-15

16-Jul-15

A8880

9

9 7-Day Workweek

0

Painting

11-Mar-15*

19-Mar-15

11-Mar-15

19-Mar-15

0

A8760

666

666 7-Day Workweek

0

Project record documents

14-Mar-15

08-Jan-17

14-Mar-15

08-Jan-17

0

ST1184

20

20 7-Day Workweek

0

Metal roof ladders

17-Mar-15

05-Apr-15

17-Mar-15

05-Apr-15

0

ST964

37

37 7-Day Workweek

0

Masonry veneer

19-Mar-15

24-Apr-15

20-Mar-15

25-Apr-15

1

ST574

20

20 7-Day Workweek

0

CMU walls

19-Mar-15

07-Apr-15

22-Jun-15

12-Jul-15

95

A8890

6

6 7-Day Workweek

0

Wall coverings

20-Mar-15*

26-Mar-15

20-Mar-15

26-Mar-15

0

Page 4 of 10

0 114


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

ST924

13

13 7-Day Workweek

0

Roof metal edges

24-Mar-15

05-Apr-15

24-Mar-15

05-Apr-15

0

ST684

13

13 7-Day Workweek

0

Roof metal edges

24-Mar-15

05-Apr-15

16-Jul-15

29-Jul-15

114

A8900

7

7 7-Day Workweek

0

Acoustical ceiling grid

26-Mar-15*

02-Apr-15

26-Mar-15

02-Apr-15

0

A8910

10

10 7-Day Workweek

0

PC AG san/rw

02-Apr-15*

12-Apr-15

02-Apr-15

12-Apr-15

0

ST1174

10

10 7-Day Workweek

0

Exterior Caulking

05-Apr-15

14-Apr-15

06-Apr-15

15-Apr-15

1

ST944

20

20 7-Day Workweek

0

Metal roof ladders

06-Apr-15

25-Apr-15

06-Apr-15

25-Apr-15

0

ST1194

10

10 7-Day Workweek

0

Aluminum windows & curtain walls

06-Apr-15

15-Apr-15

06-Apr-15

15-Apr-15

0

ST704

20

20 7-Day Workweek

0

Metal roof ladders

06-Apr-15

25-Apr-15

29-Jul-15

18-Aug-15

114

T57

40

40 7-Day Workweek

0

Provide temporary heat

07-Apr-15*

16-May-15

07-Apr-15

16-May-15

0

ST724

37

37 7-Day Workweek

0

Masonry veneer

08-Apr-15

14-May-15

12-Jul-15

18-Aug-15

95

A8920

10

10 7-Day Workweek

0

PC overhead pipe

12-Apr-15*

22-Apr-15

12-Apr-15

22-Apr-15

0

S296

30

30 7-Day Workweek

0

Exterior masonry seat walls and site walls

13-Apr-15*

12-May-15

20-Jun-15

19-Jul-15

68

ST1214

25

25 7-Day Workweek

0

Aluminum entrance doors/sliding doors

16-Apr-15

10-May-15

16-Apr-15

10-May-15

0

5

5 7-Day Workweek

0

PC insulation

22-Apr-15*

27-Apr-15

22-Apr-15

27-Apr-15

0

A8930 ST934

10

10 7-Day Workweek

0

Exterior Caulking

25-Apr-15

04-May-15

26-Apr-15

05-May-15

1

ST954

10

10 7-Day Workweek

0

Aluminum windows & curtain walls

26-Apr-15

05-May-15

26-Apr-15

05-May-15

0

ST714

10

10 7-Day Workweek

0

Aluminum windows & curtain walls

26-Apr-15

05-May-15

18-Aug-15

28-Aug-15

114

A7090

5

5 7-Day Workweek

0

Metal stairs

26-Apr-15*

30-Apr-15

17-Sep-15

22-Sep-15

144

A8940

10

10 7-Day Workweek

0

PC drop sprinkler head

27-Apr-15*

07-May-15

27-Apr-15

07-May-15

0

A7100

4

4 7-Day Workweek

0

Install railings

01-May-15*

04-May-15

26-Sep-15

30-Sep-15

148

A7110

13

13 7-Day Workweek

0

Interior H.M frames

05-May-15*

17-May-15

30-Sep-15

13-Oct-15

148

ST974

25

25 7-Day Workweek

0

Aluminum entrance doors/sliding doors

06-May-15

30-May-15

06-May-15

30-May-15

0

A8950

5

5 7-Day Workweek

0

PC casework fixtures

07-May-15*

12-May-15

07-May-15

12-May-15

0

A8960

5

5 7-Day Workweek

0

PC toilet fixtures

12-May-15*

17-May-15

12-May-15

17-May-15

0

ST694

10

10 7-Day Workweek

0

Exterior Caulking

15-May-15

24-May-15

18-Aug-15

28-Aug-15

95

A8980

5

5 7-Day Workweek

0

HC hangers

17-May-15*

22-May-15

17-May-15

22-May-15

0

A7120

9

9 7-Day Workweek

0

Drywall and spackliing

18-May-15*

26-May-15

13-Oct-15

22-Oct-15

148

A8990

7

7 7-Day Workweek

0

HC pipe install

22-May-15*

29-May-15

22-May-15

29-May-15

0

ST734

25

25 7-Day Workweek

0

Aluminum entrance doors/sliding doors

25-May-15

18-Jun-15

28-Aug-15

22-Sep-15

95

S356

20

20 7-Day Workweek

0

Retaining wall for landscaping

25-May-15*

13-Jun-15

04-Sep-15

23-Sep-15

102

S276

65

65 7-Day Workweek

0

sidewalks and ramp concrete pour

26-May-15*

29-Jul-15

20-Jul-15

22-Sep-15

55

A7130

5

5 7-Day Workweek

0

Caulking

27-May-15*

31-May-15

22-Oct-15

27-Oct-15

148

A9000

5

5 7-Day Workweek

0

HC duct install

29-May-15*

03-Jun-15

29-May-15

03-Jun-15

0

A7140

7

7 7-Day Workweek

0

Ceramic and porcelain wall/floor tiles

01-Jun-15*

07-Jun-15

27-Oct-15

03-Nov-15

148

A9010

11

11 7-Day Workweek

0

HC ATC rough-in

03-Jun-15*

14-Jun-15

03-Jun-15

14-Jun-15

0

A7150

9

9 7-Day Workweek

0

Painting

08-Jun-15*

16-Jun-15

03-Nov-15

12-Nov-15

148

A9020

15

15 7-Day Workweek

0

HC GRD install

14-Jun-15*

29-Jun-15

14-Jun-15

29-Jun-15

0

Page 5 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7160

6

6 7-Day Workweek

0

Wall coverings

17-Jun-15*

23-Jun-15

12-Nov-15

18-Nov-15

148

A7700

5

5 7-Day Workweek

0

Metal stairs

19-Jun-15*

23-Jun-15

22-Sep-15

27-Sep-15

95

A7170

7

7 7-Day Workweek

0

Acoustical ceiling grid

23-Jun-15*

30-Jun-15

18-Nov-15

25-Nov-15

148

A7710

4

4 7-Day Workweek

0

Install railings

24-Jun-15*

27-Jun-15

27-Sep-15

01-Oct-15

95

A7720

13

13 7-Day Workweek

0

Interior H.M frames

28-Jun-15*

10-Jul-15

01-Oct-15

14-Oct-15

95

A9030

12

12 7-Day Workweek

0

HC equipment and final connections

29-Jun-15*

11-Jul-15

29-Jun-15

11-Jul-15

0

A7180

10

10 7-Day Workweek

0

PC AG san/rw

30-Jun-15*

10-Jul-15

25-Nov-15

05-Dec-15

148

A7190

10

10 7-Day Workweek

0

PC overhead pipe

10-Jul-15*

20-Jul-15

06-Dec-15

15-Dec-15

148

A7730

9

9 7-Day Workweek

0

Drywall and spackliing

11-Jul-15*

19-Jul-15

14-Oct-15

23-Oct-15

95

A9040

10

10 7-Day Workweek

0

HC kitchen equipment and hookups

11-Jul-15*

21-Jul-15

11-Jul-15

21-Jul-15

0

A7740

5

5 7-Day Workweek

0

Caulking

20-Jul-15*

24-Jul-15

23-Oct-15

28-Oct-15

95

A9050

12

12 7-Day Workweek

0

EC rough-in walls

21-Jul-15*

02-Aug-15

21-Jul-15

02-Aug-15

0

A7750

7

7 7-Day Workweek

0

Ceramic and porcelain wall/floor tiles

25-Jul-15*

31-Jul-15

28-Oct-15

04-Nov-15

95

A7760

9

9 7-Day Workweek

0

Painting

01-Aug-15*

09-Aug-15

04-Nov-15

13-Nov-15

95

A9060

14

14 7-Day Workweek

0

EC overhead rough-in

02-Aug-15*

15-Aug-15

02-Aug-15

15-Aug-15

0

A7770

6

6 7-Day Workweek

0

Wall coverings

10-Aug-15*

16-Aug-15

13-Nov-15

19-Nov-15

95

A9070

14

14 7-Day Workweek

0

EC cable tray

15-Aug-15*

30-Aug-15

15-Aug-15

30-Aug-15

0

A7780

7

7 7-Day Workweek

0

Acoustical ceiling grid

16-Aug-15*

23-Aug-15

19-Nov-15

26-Nov-15

95

A7790

10

10 7-Day Workweek

0

PC AG san/rw

23-Aug-15*

02-Sep-15

26-Nov-15

06-Dec-15

95

S346

25

25 7-Day Workweek

0

Parking control equipment

24-Aug-15*

17-Sep-15

24-Sep-15

18-Oct-15

31

S326

35

35 7-Day Workweek

0

Fiberglass bus stations

25-Aug-15*

28-Sep-15

23-Sep-15

27-Oct-15

29

S366

20

20 7-Day Workweek

0

Timber guide railin gs

25-Aug-15*

13-Sep-15

29-Sep-15

18-Oct-15

35

A9080

9

9 7-Day Workweek

0

EC wiring

30-Aug-15*

07-Sep-15

30-Aug-15

07-Sep-15

0

A7800

10

10 7-Day Workweek

0

PC overhead pipe

02-Sep-15*

12-Sep-15

07-Dec-15

16-Dec-15

95

A9090

8

8 7-Day Workweek

0

EC light fixtures

07-Sep-15*

15-Sep-15

07-Sep-15

15-Sep-15

0

A7810

5

5 7-Day Workweek

0

PC insulation

12-Sep-15*

17-Sep-15

17-Dec-15

21-Dec-15

95

A9100

5

5 7-Day Workweek

0

EC wring devices

15-Sep-15*

20-Sep-15

15-Sep-15

20-Sep-15

0

A7820

10

10 7-Day Workweek

0

PC drop sprinkler head

17-Sep-15*

27-Sep-15

22-Dec-15

31-Dec-15

95

S286

46

46 7-Day Workweek

0

Unit Pavers

18-Sep-15*

02-Nov-15

19-Oct-15

03-Dec-15

31

A9110

6

6 7-Day Workweek

0

EC fire alarm and security

20-Sep-15*

26-Sep-15

20-Sep-15

26-Sep-15

0

A9120

10

10 7-Day Workweek

0

EC kitchen equipment and hookups

26-Sep-15*

06-Oct-15

26-Sep-15

06-Oct-15

0

A7830

5

5 7-Day Workweek

0

PC casework fixtures

27-Sep-15*

02-Oct-15

01-Jan-16

05-Jan-16

95

S236

50

50 7-Day Workweek

0

Final Landscaping

29-Sep-15*

17-Nov-15

28-Oct-15

16-Dec-15

29

A7840

5

5 7-Day Workweek

0

PC toilet fixtures

02-Oct-15*

07-Oct-15

06-Jan-16

10-Jan-16

95

A9130

5

5 7-Day Workweek

0

EC hook ups and connections

06-Oct-15*

11-Oct-15

06-Oct-15

11-Oct-15

0

A7850

6

6 7-Day Workweek

0

PC kitchen equipment hookups

07-Oct-15*

13-Oct-15

11-Jan-16

16-Jan-16

95

A9140

8

8 7-Day Workweek

0

Casework/millwork

11-Oct-15*

19-Oct-15

11-Oct-15

19-Oct-15

0

Page 6 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7860

5

5 7-Day Workweek

0

HC hangers

13-Oct-15*

18-Oct-15

17-Jan-16

21-Jan-16

95

A7870

7

7 7-Day Workweek

0

HC pipe install

18-Oct-15*

25-Oct-15

22-Jan-16

28-Jan-16

95

A9150

8

8 7-Day Workweek

0

Resilent tile base and floor

19-Oct-15*

27-Oct-15

19-Oct-15

27-Oct-15

0

A7880

5

5 7-Day Workweek

0

HC duct install

25-Oct-15*

30-Oct-15

29-Jan-16

02-Feb-16

95

A9160

8

8 7-Day Workweek

0

Seamless vinyl flooring

27-Oct-15*

04-Nov-15

27-Oct-15

04-Nov-15

0

A7890

11

11 7-Day Workweek

0

HC ATC rough-in

30-Oct-15*

10-Nov-15

03-Feb-16

13-Feb-16

95

S306

38

38 7-Day Workweek

0

Exterior site railings

03-Nov-15*

10-Dec-15

04-Dec-15

10-Jan-16

31

A9170

11

11 7-Day Workweek

0

Carpet tiles

04-Nov-15*

15-Nov-15

04-Nov-15

15-Nov-15

0

A7900

15

15 7-Day Workweek

0

HC GRD install

10-Nov-15*

25-Nov-15

14-Feb-16

28-Feb-16

95

A9180

7

7 7-Day Workweek

0

Install rubber stairs, treads and landings

15-Nov-15*

22-Nov-15

15-Nov-15

22-Nov-15

0

S316

25

25 7-Day Workweek

0

Position Site seating

18-Nov-15*

12-Dec-15

17-Dec-15

10-Jan-16

29

A9190

6

6 7-Day Workweek

0

Doors and Hardware

22-Nov-15*

28-Nov-15

22-Nov-15

28-Nov-15

0

A7910

12

12 7-Day Workweek

0

HC equipment and final connections

25-Nov-15*

07-Dec-15

28-Feb-16

11-Mar-16

95

A9200

8

8 7-Day Workweek

0

Interior glass partitions

28-Nov-15*

06-Dec-15

28-Nov-15

06-Dec-15

0

A9210

5

5 7-Day Workweek

0

Wood wall panels

06-Dec-15*

11-Dec-15

06-Dec-15

11-Dec-15

0

A7920

10

10 7-Day Workweek

0

HC kitchen equipment and hookups

07-Dec-15*

17-Dec-15

11-Mar-16

21-Mar-16

95

A9220

5

5 7-Day Workweek

0

Visual display surfaces

11-Dec-15*

16-Dec-15

11-Dec-15

16-Dec-15

0

S416

43

43 7-Day Workweek

0

Final placement of trees and shrubbery

13-Dec-15*

24-Jan-16

11-Jan-16

22-Feb-16

29

A9430

1

1 7-Day Workweek

0

Substantial milestone

16-Dec-15*

16-Dec-15

16-Dec-15

16-Dec-15

0

A9230

5

5 7-Day Workweek

0

Signage

16-Dec-15*

21-Dec-15

16-Dec-15

21-Dec-15

0

A7200

5

5 7-Day Workweek

0

PC insulation

17-Dec-15*

21-Dec-15

17-Dec-15

21-Dec-15

0

A7930

12

12 7-Day Workweek

0

EC rough-in walls

17-Dec-15*

29-Dec-15

21-Mar-16

02-Apr-16

95

A9240

3

3 7-Day Workweek

0

Wood ceiling

21-Dec-15*

24-Dec-15

21-Dec-15

24-Dec-15

0

A7210

10

10 7-Day Workweek

0

PC drop sprinkler head

22-Dec-15*

31-Dec-15

22-Dec-15

31-Dec-15

0

A9250

11

11 7-Day Workweek

0

Place Acoustical ceiling tiles

24-Dec-15*

04-Jan-16

24-Dec-15

04-Jan-16

0

A7940

14

14 7-Day Workweek

0

EC overhead rough-in

29-Dec-15*

11-Jan-16

02-Apr-16

15-Apr-16

95

A7220

5

5 7-Day Workweek

0

PC casework fixtures

01-Jan-16*

05-Jan-16

01-Jan-16

05-Jan-16

0

A9260

8

8 7-Day Workweek

0

Tiolet complartments

04-Jan-16*

11-Jan-16

04-Jan-16

11-Jan-16

0

A7230

5

5 7-Day Workweek

0

PC toilet fixtures

06-Jan-16*

10-Jan-16

06-Jan-16

10-Jan-16

0

A7240

6

6 7-Day Workweek

0

PC kitchen equipment hookups

11-Jan-16*

16-Jan-16

11-Jan-16

16-Jan-16

0

A9270

6

6 7-Day Workweek

0

Fire protection specialities

11-Jan-16*

17-Jan-16

11-Jan-16

17-Jan-16

0

A7950

14

14 7-Day Workweek

0

EC cable tray

11-Jan-16*

26-Jan-16

16-Apr-16

30-Apr-16

95

A7250

5

5 7-Day Workweek

0

HC hangers

17-Jan-16*

21-Jan-16

17-Jan-16

21-Jan-16

0

A9290

10

10 7-Day Workweek

0

Window shades

17-Jan-16*

27-Jan-16

17-Jan-16

27-Jan-16

0

A7260

7

7 7-Day Workweek

0

HC pipe install

22-Jan-16*

28-Jan-16

22-Jan-16

28-Jan-16

0

A7960

9

9 7-Day Workweek

0

EC wiring

26-Jan-16*

03-Feb-16

30-Apr-16

08-May-16

95

A9300

7

7 7-Day Workweek

0

Wire mesh partitions

27-Jan-16*

03-Feb-16

27-Jan-16

03-Feb-16

0

Page 7 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7270

5

5 7-Day Workweek

0

HC duct install

29-Jan-16*

02-Feb-16

29-Jan-16

02-Feb-16

0

A7280

11

11 7-Day Workweek

0

HC ATC rough-in

03-Feb-16*

13-Feb-16

03-Feb-16

13-Feb-16

0

A7970

8

8 7-Day Workweek

0

EC light fixtures

03-Feb-16*

11-Feb-16

08-May-16

16-May-16

95

A9310

13

13 7-Day Workweek

0

Install lockers

03-Feb-16*

16-Feb-16

03-Feb-16

16-Feb-16

0

S266

20

20 7-Day Workweek

0

Concrete bumper blocks

08-Feb-16*

27-Feb-16

23-Feb-16

13-Mar-16

15

A7980

5

5 7-Day Workweek

0

EC wring devices

11-Feb-16*

16-Feb-16

16-May-16

21-May-16

95

A7290

15

15 7-Day Workweek

0

HC GRD install

14-Feb-16*

28-Feb-16

14-Feb-16

28-Feb-16

0

A7990

6

6 7-Day Workweek

0

EC fire alarm and security

16-Feb-16*

22-Feb-16

21-May-16

28-May-16

95

A9320

9

9 7-Day Workweek

0

Install hood and walk-ins

16-Feb-16*

25-Feb-16

16-Feb-16

25-Feb-16

0

A8000

10

10 7-Day Workweek

0

EC kitchen equipment and hookups

22-Feb-16*

03-Mar-16

28-May-16

07-Jun-16

95

A9340

5

5 7-Day Workweek

0

Install and setup food service equipment

25-Feb-16*

01-Mar-16

25-Feb-16

01-Mar-16

0

A7300

12

12 7-Day Workweek

0

HC equipment and final connections

28-Feb-16*

11-Mar-16

28-Feb-16

11-Mar-16

0

A9350

5

5 7-Day Workweek

0

Glass wall folding partition

01-Mar-16*

06-Mar-16

01-Mar-16

06-Mar-16

0

A8010

5

5 7-Day Workweek

0

EC hook ups and connections

03-Mar-16*

08-Mar-16

07-Jun-16

12-Jun-16

95

A9360

12

12 7-Day Workweek

0

Loading dock equipment

06-Mar-16*

18-Mar-16

06-Mar-16

18-Mar-16

0

A8020

8

8 7-Day Workweek

0

Casework/millwork

08-Mar-16*

16-Mar-16

12-Jun-16

19-Jun-16

95

A7310

10

10 7-Day Workweek

0

HC kitchen equipment and hookups

11-Mar-16*

21-Mar-16

11-Mar-16

21-Mar-16

0

S256

26

26 7-Day Workweek

0

site linestripping and signage

14-Mar-16*

08-Apr-16

14-Mar-16

08-Apr-16

0

A8030

8

8 7-Day Workweek

0

Resilent tile base and floor

16-Mar-16*

24-Mar-16

19-Jun-16

27-Jun-16

95

A9370

5

5 7-Day Workweek

0

Paint gym ceiling

18-Mar-16*

23-Mar-16

18-Mar-16

23-Mar-16

0

A7320

12

12 7-Day Workweek

0

EC rough-in walls

21-Mar-16*

02-Apr-16

21-Mar-16

02-Apr-16

0

A9380

7

7 7-Day Workweek

0

Gym equipment

23-Mar-16*

30-Mar-16

23-Mar-16

30-Mar-16

0

A8040

8

8 7-Day Workweek

0

Seamless vinyl flooring

24-Mar-16*

01-Apr-16

27-Jun-16

05-Jul-16

95

A9390

9

9 7-Day Workweek

0

Gym dividers

30-Mar-16*

08-Apr-16

30-Mar-16

08-Apr-16

0

A8050

11

11 7-Day Workweek

0

Carpet tiles

01-Apr-16*

12-Apr-16

05-Jul-16

16-Jul-16

95

A7330

14

14 7-Day Workweek

0

EC overhead rough-in

02-Apr-16*

15-Apr-16

02-Apr-16

15-Apr-16

0

A9400

7

7 7-Day Workweek

0

Install hardwood flooring

08-Apr-16*

15-Apr-16

08-Apr-16

15-Apr-16

0

A8060

7

7 7-Day Workweek

0

Install rubber stairs, treads and landings

12-Apr-16*

19-Apr-16

16-Jul-16

23-Jul-16

95

A9410

6

6 7-Day Workweek

0

Install collapsable belachers

15-Apr-16*

22-Apr-16

15-Apr-16

22-Apr-16

0

A7340

14

14 7-Day Workweek

0

EC cable tray

16-Apr-16*

30-Apr-16

16-Apr-16

30-Apr-16

0

A8070

6

6 7-Day Workweek

0

Doors and Hardware

19-Apr-16*

25-Apr-16

23-Jul-16

29-Jul-16

95

A9420

8

8 7-Day Workweek

0

Hydraulic elevators

22-Apr-16*

30-Apr-16

22-Apr-16

30-Apr-16

0

A8080

8

8 7-Day Workweek

0

Interior glass partitions

25-Apr-16*

03-May-16

29-Jul-16

06-Aug-16

95

A9330

10

10 7-Day Workweek

0

Install kitchen tiles

30-Apr-16

10-May-16

30-Apr-16

10-May-16

0

A8720

9

9 7-Day Workweek

0

Checklist enrollment building

30-Apr-16

08-May-16

30-Dec-16

08-Jan-17

244

A7350

9

9 7-Day Workweek

0

EC wiring

30-Apr-16*

08-May-16

30-Apr-16

08-May-16

0

A8090

5

5 7-Day Workweek

0

Wood wall panels

03-May-16*

08-May-16

07-Aug-16

11-Aug-16

95

Page 8 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A8100

5

5 7-Day Workweek

0

Visual display surfaces

08-May-16*

13-May-16

12-Aug-16

16-Aug-16

95

A7360

8

8 7-Day Workweek

0

EC light fixtures

08-May-16*

16-May-16

08-May-16

16-May-16

0

A9280

9

9 7-Day Workweek

0

Motorized projection screens

10-May-16

19-May-16

10-May-16

19-May-16

0

A8110

5

5 7-Day Workweek

0

Signage

13-May-16*

18-May-16

17-Aug-16

21-Aug-16

95

A7370

5

5 7-Day Workweek

0

EC wring devices

16-May-16*

21-May-16

16-May-16

21-May-16

0

A8120

3

3 7-Day Workweek

0

Wood ceiling

18-May-16*

21-May-16

22-Aug-16

24-Aug-16

95

A8130

11

11 7-Day Workweek

0

Place Acoustical ceiling tiles

21-May-16*

01-Jun-16

25-Aug-16

04-Sep-16

95

A7380

6

6 7-Day Workweek

0

EC fire alarm and security

21-May-16*

28-May-16

21-May-16

28-May-16

0

A7390

10

10 7-Day Workweek

0

EC kitchen equipment and hookups

28-May-16*

07-Jun-16

28-May-16

07-Jun-16

0

A8140

8

8 7-Day Workweek

0

Tiolet complartments

01-Jun-16*

08-Jun-16

04-Sep-16

11-Sep-16

95

A7400

5

5 7-Day Workweek

0

EC hook ups and connections

07-Jun-16*

12-Jun-16

07-Jun-16

12-Jun-16

0

A8150

6

6 7-Day Workweek

0

Fire protection specialities

08-Jun-16*

14-Jun-16

12-Sep-16

17-Sep-16

95

A7410

8

8 7-Day Workweek

0

Casework/millwork

12-Jun-16*

19-Jun-16

12-Jun-16

19-Jun-16

0

A8170

10

10 7-Day Workweek

0

Window shades

14-Jun-16*

24-Jun-16

18-Sep-16

27-Sep-16

95

A7420

8

8 7-Day Workweek

0

Resilent tile base and floor

19-Jun-16*

27-Jun-16

19-Jun-16

27-Jun-16

0

A8180

7

7 7-Day Workweek

0

Wire mesh partitions

24-Jun-16*

01-Jul-16

28-Sep-16

04-Oct-16

95

A7430

8

8 7-Day Workweek

0

Seamless vinyl flooring

27-Jun-16*

05-Jul-16

27-Jun-16

05-Jul-16

0

A8190

13

13 7-Day Workweek

0

Install lockers

01-Jul-16*

14-Jul-16

05-Oct-16

17-Oct-16

95

A7440

11

11 7-Day Workweek

0

Carpet tiles

05-Jul-16*

16-Jul-16

05-Jul-16

16-Jul-16

0

A8200

9

9 7-Day Workweek

0

Observation deck

14-Jul-16*

23-Jul-16

18-Oct-16

26-Oct-16

95

A7450

7

7 7-Day Workweek

0

Install rubber stairs, treads and landings

16-Jul-16*

23-Jul-16

16-Jul-16

23-Jul-16

0

A7460

6

6 7-Day Workweek

0

Doors and Hardware

23-Jul-16*

29-Jul-16

23-Jul-16

29-Jul-16

0

A8210

5

5 7-Day Workweek

0

Install Medical reclined chair

23-Jul-16*

28-Jul-16

27-Oct-16

31-Oct-16

95

A8220

5

5 7-Day Workweek

0

Glass wall folding partition

28-Jul-16*

02-Aug-16

01-Nov-16

05-Nov-16

95

A7470

8

8 7-Day Workweek

0

Interior glass partitions

29-Jul-16*

06-Aug-16

29-Jul-16

06-Aug-16

0

A8230

12

12 7-Day Workweek

0

Place additional medical equipment

02-Aug-16*

14-Aug-16

06-Nov-16

17-Nov-16

95

A7480

5

5 7-Day Workweek

0

Wood wall panels

07-Aug-16*

11-Aug-16

07-Aug-16

11-Aug-16

0

A7490

5

5 7-Day Workweek

0

Visual display surfaces

12-Aug-16*

16-Aug-16

12-Aug-16

16-Aug-16

0

A8240

5

5 7-Day Workweek

0

Install lecture seating

14-Aug-16*

19-Aug-16

18-Nov-16

22-Nov-16

95

A7500

5

5 7-Day Workweek

0

Signage

17-Aug-16*

21-Aug-16

17-Aug-16

21-Aug-16

0

A8250

7

7 7-Day Workweek

0

Install Student Desks and chairs

19-Aug-16*

26-Aug-16

23-Nov-16

29-Nov-16

95

A7510

3

3 7-Day Workweek

0

Wood ceiling

22-Aug-16*

24-Aug-16

22-Aug-16

24-Aug-16

0

A7520

11

11 7-Day Workweek

0

Place Acoustical ceiling tiles

25-Aug-16*

04-Sep-16

25-Aug-16

04-Sep-16

0

A8260

9

9 7-Day Workweek

0

Lab Desks

26-Aug-16*

04-Sep-16

30-Nov-16

08-Dec-16

95

A7530

8

8 7-Day Workweek

0

Tiolet complartments

04-Sep-16*

11-Sep-16

04-Sep-16

11-Sep-16

0

A8270

7

7 7-Day Workweek

0

Install hardwood flooring

04-Sep-16*

11-Sep-16

09-Dec-16

15-Dec-16

95

A8280

6

6 7-Day Workweek

0

Teacher desks

11-Sep-16*

18-Sep-16

16-Dec-16

22-Dec-16

95

Page 9 of 10


Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13

MONROE CAMPUS... Report Date 14-Apr-14 20:56

SR-01 Classic Schedule Report - Sort by ES, TF

Activity ID

Orig Rem Calendar Dur Dur

% Department Activity Name

Early Start

Early Finish

Late Start

Late Finish

Total Float

A7540

6

6 7-Day Workweek

0

Fire protection specialities

12-Sep-16*

17-Sep-16

12-Sep-16

17-Sep-16

0

A7560

10

10 7-Day Workweek

0

Window shades

18-Sep-16*

27-Sep-16

18-Sep-16

27-Sep-16

0

A8290

8

8 7-Day Workweek

0

Hydraulic elevators

18-Sep-16*

26-Sep-16

22-Dec-16

30-Dec-16

95

A8700

9

9 7-Day Workweek

0

Checklist classroom roe

26-Sep-16

05-Oct-16

30-Dec-16

08-Jan-17

95

A7570

7

7 7-Day Workweek

0

Wire mesh partitions

28-Sep-16*

04-Oct-16

28-Sep-16

04-Oct-16

0

A7580

13

13 7-Day Workweek

0

Install lockers

05-Oct-16*

17-Oct-16

05-Oct-16

17-Oct-16

0

A7590

9

9 7-Day Workweek

0

Install hood and walk-ins

18-Oct-16*

26-Oct-16

18-Oct-16

26-Oct-16

0

A7610

5

5 7-Day Workweek

0

Install and setup food service equipment

27-Oct-16*

31-Oct-16

27-Oct-16

31-Oct-16

0

A7620

5

5 7-Day Workweek

0

Glass wall folding partition

01-Nov-16*

05-Nov-16

01-Nov-16

05-Nov-16

0

A7630

12

12 7-Day Workweek

0

Loading dock equipment

06-Nov-16*

17-Nov-16

06-Nov-16

17-Nov-16

0

A7640

5

5 7-Day Workweek

0

Paint gym ceiling

18-Nov-16*

22-Nov-16

18-Nov-16

22-Nov-16

0

A7650

7

7 7-Day Workweek

0

Gym equipment

23-Nov-16*

29-Nov-16

23-Nov-16

29-Nov-16

0

A7660

9

9 7-Day Workweek

0

Gym dividers

30-Nov-16*

08-Dec-16

30-Nov-16

08-Dec-16

0

A7670

7

7 7-Day Workweek

0

Install hardwood flooring

09-Dec-16*

15-Dec-16

09-Dec-16

15-Dec-16

0

A7680

6

6 7-Day Workweek

0

Install collapsable belachers

16-Dec-16*

22-Dec-16

16-Dec-16

22-Dec-16

0

A7690

8

8 7-Day Workweek

0

Hydraulic elevators

22-Dec-16*

30-Dec-16

22-Dec-16

30-Dec-16

0

A7600

10

10 7-Day Workweek

0

Install kitchen tiles

30-Dec-16*

09-Jan-17

30-Dec-16

09-Jan-17

0

A8710

9

9 7-Day Workweek

0

Checklist student life building

30-Dec-16

08-Jan-17

30-Dec-16

08-Jan-17

0

A8780

79

79 7-Day Workweek

0

Close out procedures

08-Jan-17

28-Mar-17

08-Jan-17

28-Mar-17

0

A8810

176

176 7-Day Workweek

0

Demobilize job trailers

08-Jan-17

03-Jul-17

04-May-17

26-Oct-17

116

A7550

9

9 7-Day Workweek

0

Motorized projection screens

09-Jan-17*

18-Jan-17

09-Jan-17

18-Jan-17

0

A9440

1

1 7-Day Workweek

0

Final Milestone

27-Oct-17*

28-Oct-17

27-Oct-17

28-Oct-17

0

Page 10 of 10


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.