CAE 471: Primavera Schedule Project Spring Semester 2014 Team Olu Oluduro Charles Massaro Thomas Lagarde Lazar Sretkovic Project Plan and Summary of Project This narrative focuses on the overall approach and project plan for the Northampton Community College located at the junction of Route 715 and Railroad Avenue in Tannersville, Monroe County, Pennsylvania. The project plan was to simultaneously develop and construct the three new campus buildings with a clear and concise explanation of the activity report sorted by Total Float and Early Start (TF-ES). Included were the activity id, description, early dates, late dates, original duration, and total float. Defining the Project Milestones Milestones are the key events or significant points in time during the life of the project. We have arranged them in this order: • Project Start Milestones (Temporary Construction) o Installation of the General Contractor and subcontractors’ staging area o Installation of all temporary heating and/or cooling systems for on-site personnel •
Project Start Milestones (Site work) o Preparation of the Construction entrance to the site o Installation of the Sediment Basins o Installation of all the additional Staging areas o Installation of the Storm sewer water system o Installation of temporary water to contractor staging area o Installation of all Site utilities o Installation of final paving for parking lots and drives o Installation of walkway surfaces, pavements and all landscaping
•
Substantial Completion Milestones (Building Envelope Construction) o Construction complete for sub-grade of Building pad o Construction complete for concrete foundations o Construction complete for mechanical and plumbing contractor underground rough In o Construction complete for structural steel o Construction complete for electrical contractor underground rough In o Construction complete for concrete slab on grade o Construction complete for exterior envelope o Construction complete (including checks) for building to be water tight
•
Substantial Completion Milestones (Building Finishes) o Construction and installations complete for interior partitions and MEP Rough Ins o Construction and installations complete for wall rough Ins and inspections o Construction and installations complete for MEP Above-ceilings rough Ins o Construction complete for all interior wall finishes and trims o Installations complete for all ceiling grids o Installations complete for all finished ceilings o Installations and energizing the main permanent electricity
•
Final Completion Milestone (including Close-Outs and Warranties) o Commissioning and start-up of all equipment and systems o Construction complete for all remaining construction activities o Obtaining the certificate of occupancy, punch list preparation and project completion
Calendars used in the schedule • • • •
Five day and Seven day calendars were used in the schedule In addition, as instructed in class, no activity was longer than 20 days (or longer than 1 month) Normal workday involves an 8-hour shift, Monday through Friday excluding major holidays Pre-construction, bidding, permits and submittals were given a separate calendar because they are in Volume 1 of the project
Constraints and their basis • • • • •
One of the important constraints in the project were the milestones, many of which had to be completed before a major step in the construction process could proceed The next set of constrains were the sequential orders in which the contractors and their respective crews were allowed to complete their schedules. For instance, the electrical contractor could not begin his activities until the HVAC/mechanical contractors had finished their work; who in turn could only have completed their work after the Plumbing contractor was done. Volume 1 needed to be separate because it consisted mainly of bidding, general requirements and contract requirements Additional constraints were the orders in which the project evolved o Temporary construction o Site work o Building shell and envelope construction o Building finishes o Building closeouts and warranties
List of Assumptions • All open-ended relationships were closed • All activities had predecessors and successors • Site layout begins at start of project with site procurement • Work is all year round – Weatherchannel.com shows all the weather averages for Pennsylvania • Critical path was highlighted in the report • Total Float, Free float, Early Start and Late start dates were assumed by the Primavera software • Typical schedule system was assumed to be used for the entirety of the project. These include o Mobilizing and delivery of stock materials o Clearing and Grubbing o Grading for Road o Finishing the grade o Erection of Prefab and structural systems o Landscaping o Paving the roadways and commissioning of power equipment o Final inspection, close outs and clean up
Work Breakdown Structure (WBS) The Work Breakdown Structure that was used in this scheduling planning was to consolidate and encompasses the entire project at Level 1 and then subsequently subdivide the project into four separate descending groups as follows: The three buildings, then the various volumes (as designated in Addendum 1of the official documents), then the Divisions and lastly, the activities WBS Level 1
Title Project
Description Designated as “Monroe Campus” This is the title for the project This level subdivides the main bulk of the scheduling project into each of the three main buildings
2
Building
3
Volume
This level subdivides each of the three buildings into the volumes as described in Addendum 1 of the official documents. Although there are actually four volumes listed in the Addendum, Volume 1 was mainly about the bidding and pre-submittal stage of the project.
4
Division
This level subdivides each of the three main volumes into their divisions. In this manner, all the major work elements are listed by divisions so that the WBS is coherent with the development design explained in the Addendum.
5
Activities
This level subdivides each of the divisions into the specific activities and work items that are within the project. Also included are the successors and predecessors; with all milestones adequately projected on the activities chart.
Resources included in the schedule • • • •
Official cost estimating wages for the state of Pennsylvania was referred to in order to get a basic understanding of the salaries, fringe benefits and average crew sizes for the project. The various crews (steel structure crews, electrical crews, MEP crews, carpenters and scaffolding teams) were all staggered and scheduled consecutively across all three buildings. Equipment resources used included three cranes (one for each building) Power resources included additional temporary on-site power generators which also had to be refueled with diesel (delivery of the diesel was scheduled on a monthly basis)
5 days calendar 8 hours/day
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
MONROE CAMPUS A7080
Install all site utilties
02-Apr-14*
09-Jul-14
27-Mar-14
02-Jul-14
-5
A8670
S86, S96, T77
A7090
Metal stairs
25-Aug-15*
01-Sep-15
25-Aug-15
01-Sep-15
0
A8820, ST944
A7100, A7700
A7100
Install railings
01-Sep-15*
07-Sep-15
01-Sep-15
07-Sep-15
0
A7090
A7110
A7110
Interior H.M frames
07-Sep-15*
24-Sep-15
07-Sep-15
24-Sep-15
0
A7100
A7120
A7120
Drywall and spackliing
24-Sep-15*
07-Oct-15
24-Sep-15
07-Oct-15
0
A7110
A7130
A7130
Caulking
07-Oct-15*
14-Oct-15
07-Oct-15
14-Oct-15
0
A7120
A7140
A7140
Ceramic and porcelain wall/floor tiles
14-Oct-15*
23-Oct-15
14-Oct-15
23-Oct-15
0
A7130
A7150
A7150
Painting
23-Oct-15*
05-Nov-15
23-Oct-15
05-Nov-15
0
A7140
A7160
A7160
Wall coverings
05-Nov-15*
16-Nov-15
05-Nov-15
16-Nov-15
0
A7150
A7170
A7170
Acoustical ceiling grid
16-Nov-15*
25-Nov-15
16-Nov-15
25-Nov-15
0
A7160
A7180
A7180
PC AG san/rw
25-Nov-15*
09-Dec-15
25-Nov-15
09-Dec-15
0
A7170
A7190
A7190
PC overhead pipe
09-Dec-15*
23-Dec-15
09-Dec-15
23-Dec-15
0
A7180
A9430
A7200
PC insulation
24-Dec-15*
31-Dec-15
24-Dec-15
31-Dec-15
0
A9430
A7210
A7210
PC drop sprinkler head
31-Dec-15*
14-Jan-16
31-Dec-15
14-Jan-16
0
A7200
A7220
A7220
PC casework fixtures
14-Jan-16*
21-Jan-16
14-Jan-16
21-Jan-16
0
A7210
A7230
A7230
PC toilet fixtures
21-Jan-16*
28-Jan-16
21-Jan-16
28-Jan-16
0
A7220
A7240
A7240
PC kitchen equipment hookups
28-Jan-16*
05-Feb-16
28-Jan-16
05-Feb-16
0
A7230
A7250
A7250
HC hangers
05-Feb-16*
12-Feb-16
05-Feb-16
12-Feb-16
0
A7240
A7260
A7260
HC pipe install
12-Feb-16*
23-Feb-16
12-Feb-16
23-Feb-16
0
A7250
A7270
A7270
HC duct install
23-Feb-16*
01-Mar-16
23-Feb-16
01-Mar-16
0
A7260
A7280
A7280
HC ATC rough-in
01-Mar-16*
16-Mar-16
01-Mar-16
16-Mar-16
0
A7270
A7290
A7290
HC GRD install
16-Mar-16*
05-Apr-16
16-Mar-16
05-Apr-16
0
A7280
A7300
A7300
HC equipment and final connections
05-Apr-16*
21-Apr-16
05-Apr-16
21-Apr-16
0
A7290
A7310
A7310
HC kitchen equipment and hookups
21-Apr-16*
05-May-16
21-Apr-16
05-May-16
0
A7300
A7320
A7320
EC rough-in walls
05-May-16*
23-May-16
05-May-16
23-May-16
0
A7310
A7330
A7330
EC overhead rough-in
23-May-16*
10-Jun-16
23-May-16
10-Jun-16
0
A7320
A7340
A7340
EC cable tray
10-Jun-16*
30-Jun-16
10-Jun-16
30-Jun-16
0
A7330
A7350
A7350
EC wiring
30-Jun-16*
13-Jul-16
30-Jun-16
13-Jul-16
0
A7340
A7360
A7360
EC light fixtures
13-Jul-16*
25-Jul-16
13-Jul-16
25-Jul-16
0
A7350
A7370
A7370
EC wring devices
25-Jul-16*
01-Aug-16
25-Jul-16
01-Aug-16
0
A7360
A7380
A7380
EC fire alarm and security
01-Aug-16*
09-Aug-16
01-Aug-16
09-Aug-16
0
A7370
A7390
A7390
EC kitchen equipment and hookups
09-Aug-16*
23-Aug-16
09-Aug-16
23-Aug-16
0
A7380
A7400
A7400
EC hook ups and connections
23-Aug-16*
30-Aug-16
23-Aug-16
30-Aug-16
0
A7390
A7410
A7410
Casework/millwork
30-Aug-16*
09-Sep-16
30-Aug-16
09-Sep-16
0
A7400
A7420
A7420
Resilent tile base and floor
09-Sep-16*
21-Sep-16
09-Sep-16
21-Sep-16
0
A7410
A7430
A7430
Seamless vinyl flooring
21-Sep-16*
03-Oct-16
21-Sep-16
03-Oct-16
0
A7420
A7440
A7440
Carpet tiles
03-Oct-16*
18-Oct-16
03-Oct-16
18-Oct-16
0
A7430
A7450
A7450
Install rubber stairs, treads and landings
18-Oct-16*
27-Oct-16
18-Oct-16
27-Oct-16
0
A7440
A7460
A7460
Doors and Hardware
27-Oct-16*
04-Nov-16
27-Oct-16
04-Nov-16
0
A7450
A7470
A7470
Interior glass partitions
04-Nov-16*
16-Nov-16
04-Nov-16
16-Nov-16
0
A7460
A7480
A7480
Wood wall panels
16-Nov-16*
23-Nov-16
16-Nov-16
23-Nov-16
0
A7470
A7490
A7490
Visual display surfaces
23-Nov-16*
30-Nov-16
23-Nov-16
30-Nov-16
0
A7480
A7500
A7500
Signage
30-Nov-16*
07-Dec-16
30-Nov-16
07-Dec-16
0
A7490
A7510
A7510
Wood ceiling
07-Dec-16*
12-Dec-16
07-Dec-16
12-Dec-16
0
A7500
A7520
A7520
Place Acoustical ceiling tiles
12-Dec-16*
26-Dec-16
12-Dec-16
26-Dec-16
0
A7510
A7530
A7530
Tiolet complartments
26-Dec-16*
05-Jan-17
26-Dec-16
05-Jan-17
0
A7520
A7540
A7540
Fire protection specialities
05-Jan-17*
13-Jan-17
05-Jan-17
13-Jan-17
0
A7530
A7560
Footer 1
Page 1 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A7550
Motorized projection screens
21-Jun-17*
04-Jul-17
21-Jun-17
04-Jul-17
0
A7600
A7560
Window shades
13-Jan-17*
27-Jan-17
13-Jan-17
27-Jan-17
0
A7540
A7570
A7570
Wire mesh partitions
27-Jan-17*
07-Feb-17
27-Jan-17
07-Feb-17
0
A7560
A7580
A7580
Install lockers
07-Feb-17*
24-Feb-17
07-Feb-17
24-Feb-17
0
A7570
A7590
A7590
Install hood and walk-ins
24-Feb-17*
09-Mar-17
24-Feb-17
09-Mar-17
0
A7580
A7610
A7600
Install kitchen tiles
07-Jun-17*
21-Jun-17
07-Jun-17
21-Jun-17
0
A7690
A7550
A7610
Install and setup food service equipment
09-Mar-17*
16-Mar-17
09-Mar-17
16-Mar-17
0
A7590
A7620
A7620
Glass wall folding partition
16-Mar-17*
23-Mar-17
16-Mar-17
23-Mar-17
0
A7610
A7630
A7630
Loading dock equipment
23-Mar-17*
10-Apr-17
23-Mar-17
10-Apr-17
0
A7620
A7640
A7640
Paint gym ceiling
10-Apr-17*
17-Apr-17
10-Apr-17
17-Apr-17
0
A7630
A7650
A7650
Gym equipment
17-Apr-17*
26-Apr-17
17-Apr-17
26-Apr-17
0
A7640
A7660
A7660
Gym dividers
26-Apr-17*
09-May-17
26-Apr-17
09-May-17
0
A7650
A7670
A7670
Install hardwood flooring
09-May-17*
18-May-17
09-May-17
18-May-17
0
A7660
A7680
A7680
Install collapsable belachers
18-May-17*
26-May-17
18-May-17
26-May-17
0
A7670
A7690
A7690
Hydraulic elevators
26-May-17*
07-Jun-17
26-May-17
07-Jun-17
0
A7680
A7600, A8710
A7700
Metal stairs
09-Nov-15*
16-Nov-15
09-Nov-15
16-Nov-15
0
ST734, A7090
A7710
A7710
Install railings
16-Nov-15*
20-Nov-15
16-Nov-15
20-Nov-15
0
A7700
A7720
A7720
Interior H.M frames
20-Nov-15*
09-Dec-15
20-Nov-15
09-Dec-15
0
A7710
A7730
A7730
Drywall and spackliing
09-Dec-15*
22-Dec-15
09-Dec-15
22-Dec-15
0
A7720
A7740
A7740
Caulking
22-Dec-15*
29-Dec-15
22-Dec-15
29-Dec-15
0
A7730
A7750
A7750
Ceramic and porcelain wall/floor tiles
29-Dec-15*
07-Jan-16
29-Dec-15
07-Jan-16
0
A7740
A7760
A7760
Painting
07-Jan-16*
20-Jan-16
07-Jan-16
20-Jan-16
0
A7750
A7770
A7770
Wall coverings
20-Jan-16*
29-Jan-16
20-Jan-16
29-Jan-16
0
A7760
A7780
A7780
Acoustical ceiling grid
29-Jan-16*
09-Feb-16
29-Jan-16
09-Feb-16
0
A7770
A7790
A7790
PC AG san/rw
09-Feb-16*
23-Feb-16
09-Feb-16
23-Feb-16
0
A7780
A7800
A7800
PC overhead pipe
23-Feb-16*
08-Mar-16
23-Feb-16
08-Mar-16
0
A7790
A7810
A7810
PC insulation
08-Mar-16*
15-Mar-16
08-Mar-16
15-Mar-16
0
A7800
A7820
A7820
PC drop sprinkler head
15-Mar-16*
29-Mar-16
15-Mar-16
29-Mar-16
0
A7810
A7830
A7830
PC casework fixtures
29-Mar-16*
05-Apr-16
29-Mar-16
05-Apr-16
0
A7820
A7840
A7840
PC toilet fixtures
05-Apr-16*
12-Apr-16
05-Apr-16
12-Apr-16
0
A7830
A7850
A7850
PC kitchen equipment hookups
12-Apr-16*
20-Apr-16
12-Apr-16
20-Apr-16
0
A7840
A7860
A7860
HC hangers
20-Apr-16*
27-Apr-16
20-Apr-16
27-Apr-16
0
A7850
A7870
A7870
HC pipe install
27-Apr-16*
06-May-16
27-Apr-16
06-May-16
0
A7860
A7880
A7880
HC duct install
06-May-16*
13-May-16
06-May-16
13-May-16
0
A7870
A7890
A7890
HC ATC rough-in
13-May-16*
30-May-16
13-May-16
30-May-16
0
A7880
A7900
A7900
HC GRD install
30-May-16*
17-Jun-16
30-May-16
17-Jun-16
0
A7890
A7910
A7910
HC equipment and final connections
17-Jun-16*
05-Jul-16
17-Jun-16
05-Jul-16
0
A7900
A7920
A7920
HC kitchen equipment and hookups
05-Jul-16*
19-Jul-16
05-Jul-16
19-Jul-16
0
A7910
A7930
A7930
EC rough-in walls
19-Jul-16*
04-Aug-16
19-Jul-16
04-Aug-16
0
A7920
A7940
A7940
EC overhead rough-in
04-Aug-16*
24-Aug-16
04-Aug-16
24-Aug-16
0
A7930
A7950
A7950
EC cable tray
24-Aug-16*
13-Sep-16
24-Aug-16
13-Sep-16
0
A7940
A7960
A7960
EC wiring
13-Sep-16*
26-Sep-16
13-Sep-16
26-Sep-16
0
A7950
A7970
A7970
EC light fixtures
26-Sep-16*
06-Oct-16
26-Sep-16
06-Oct-16
0
A7960
A7980
A7980
EC wring devices
06-Oct-16*
13-Oct-16
06-Oct-16
13-Oct-16
0
A7970
A7990
A7990
EC fire alarm and security
13-Oct-16*
21-Oct-16
13-Oct-16
21-Oct-16
0
A7980
A8000
A8000
EC kitchen equipment and hookups
21-Oct-16*
04-Nov-16
21-Oct-16
04-Nov-16
0
A7990
A8010
A8010
EC hook ups and connections
04-Nov-16*
11-Nov-16
04-Nov-16
11-Nov-16
0
A8000
A8020
A8020
Casework/millwork
11-Nov-16*
23-Nov-16
11-Nov-16
23-Nov-16
0
A8010
A8030
A8030
Resilent tile base and floor
23-Nov-16*
05-Dec-16
23-Nov-16
05-Dec-16
0
A8020
A8040
A8040
Seamless vinyl flooring
05-Dec-16*
15-Dec-16
05-Dec-16
15-Dec-16
0
A8030
A8050
Footer 1
Page 2 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A8050
Carpet tiles
15-Dec-16*
30-Dec-16
15-Dec-16
30-Dec-16
0
A8040
A8060
A8060
Install rubber stairs, treads and landings
30-Dec-16*
10-Jan-17
30-Dec-16
10-Jan-17
0
A8050
A8070
A8070
Doors and Hardware
10-Jan-17*
18-Jan-17
10-Jan-17
18-Jan-17
0
A8060
A8080
A8080
Interior glass partitions
18-Jan-17*
30-Jan-17
18-Jan-17
30-Jan-17
0
A8070
A8090
A8090
Wood wall panels
30-Jan-17*
06-Feb-17
30-Jan-17
06-Feb-17
0
A8080
A8100
A8100
Visual display surfaces
06-Feb-17*
13-Feb-17
06-Feb-17
13-Feb-17
0
A8090
A8110
A8110
Signage
13-Feb-17*
20-Feb-17
13-Feb-17
20-Feb-17
0
A8100
A8120
A8120
Wood ceiling
20-Feb-17*
23-Feb-17
20-Feb-17
23-Feb-17
0
A8110
A8130
A8130
Place Acoustical ceiling tiles
23-Feb-17*
09-Mar-17
23-Feb-17
09-Mar-17
0
A8120
A8140
A8140
Tiolet complartments
09-Mar-17*
21-Mar-17
09-Mar-17
21-Mar-17
0
A8130
A8150
A8150
Fire protection specialities
21-Mar-17*
29-Mar-17
21-Mar-17
29-Mar-17
0
A8140
A8170
A8170
Window shades
29-Mar-17*
12-Apr-17
29-Mar-17
12-Apr-17
0
A8150
A8180
A8180
Wire mesh partitions
12-Apr-17*
21-Apr-17
12-Apr-17
21-Apr-17
0
A8170
A8190
A8190
Install lockers
21-Apr-17*
10-May-17
21-Apr-17
10-May-17
0
A8180
A8200
A8200
Observation deck
10-May-17*
23-May-17
10-May-17
23-May-17
0
A8190
A8210
A8210
Install Medical reclined chair
23-May-17*
30-May-17
23-May-17
30-May-17
0
A8200
A8220
A8220
Glass wall folding partition
30-May-17*
06-Jun-17
30-May-17
06-Jun-17
0
A8210
A8230
A8230
Place additional medical equipment
06-Jun-17*
22-Jun-17
06-Jun-17
22-Jun-17
0
A8220
A8240
A8240
Install lecture seating
22-Jun-17*
29-Jun-17
22-Jun-17
29-Jun-17
0
A8230
A8250
A8250
Install Student Desks and chairs
29-Jun-17*
10-Jul-17
29-Jun-17
10-Jul-17
0
A8240
A8260
A8260
Lab Desks
10-Jul-17*
21-Jul-17
10-Jul-17
21-Jul-17
0
A8250
A8270
A8270
Install hardwood flooring
21-Jul-17*
01-Aug-17
21-Jul-17
01-Aug-17
0
A8260
A8280
A8280
Teacher desks
01-Aug-17*
09-Aug-17
01-Aug-17
09-Aug-17
0
A8270
A8290
A8290
Hydraulic elevators
09-Aug-17*
21-Aug-17
09-Aug-17
21-Aug-17
0
A8280
A8780, A8700
A8300
Prevailing wage documents
26-Feb-14
10-Mar-14
26-Feb-14
10-Mar-14
0
A8610
A8310
Bid security
01-Apr-14
16-Apr-14
01-Apr-14
16-Apr-14
0
A8390
A8320
Electrical Construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8610
A8330
Plumbing construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8610
A8340
Hvac construction bid
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8610
A8350
General construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8610
A8360
Geotechnical investigation
10-Oct-13
27-Jan-14
03-Oct-13
21-Jan-14
-5
A8370
Instruction to bidders
26-Feb-14
14-Mar-14
26-Feb-14
14-Mar-14
0
A8390
A8380
Qualification questionnaire
26-Feb-14
05-Mar-14
26-Feb-14
05-Mar-14
0
A8390
A8390
invitation to bid
26-Feb-14
01-Apr-14
19-Feb-14
25-Mar-14
-5
A8610
A8400
Execution
02-Apr-14
07-Feb-18
02-Apr-14
07-Feb-18
0
A8670, A8780
A8410
Product requirements
01-Apr-14
26-May-14
01-Apr-14
26-May-14
0
A8390
A8420
Temporary Facilities & controls
02-Apr-14
16-Nov-17
02-Apr-14
16-Nov-17
0
A8670, A8780
A8430
References
02-May-14
22-May-14
02-May-14
22-May-14
0
A8600
A8440
Quality requirements
02-May-14
10-Jul-14
02-May-14
10-Jul-14
0
A8600
A8450
Alteration Project procedures
10-Oct-13
15-Oct-13
10-Oct-13
15-Oct-13
0
A8610, A8570
A8460
LEED submital Form
06-Nov-13
30-Dec-13
06-Nov-13
30-Dec-13
0
A8730, A8740
A8470
Submittal form
02-May-14
08-Jul-14
02-May-14
08-Jul-14
0
A8390, A8600
A8480
Construction Progress documentation
02-Apr-14
14-Dec-17
02-Apr-14
14-Dec-17
0
A8670, A8780
A8490
Web based project management
02-Apr-14
30-Nov-17
02-Apr-14
30-Nov-17
0
A8670, A8780
A8500
Coordination drawings
28-Jan-14
20-Feb-14
24-Mar-14
16-Apr-14
39
A8610
A8510
Project Management & coordination
02-Apr-14
25-Jan-18
02-Apr-14
25-Jan-18
0
A8670, A8780
A8520
Payement procedures
02-Apr-14
12-Feb-18
02-Apr-14
12-Feb-18
0
A8670
Footer 1
Page 3 of 8
A8600
A8380, A8370, A8310, A8680, A8620, A8650, A8660, A8630, A8670, A8470, A8550, A8410
A8600
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A8530
Contract Modification
10-Oct-13
19-Dec-13
10-Oct-13
19-Dec-13
A8540
Alternates
02-May-14
21-May-14
02-May-14
21-May-14
0 0
A8600
A8550
Unit prices
01-Apr-14
02-Jun-14
01-Apr-14
02-Jun-14
0
A8390
A8560
Quantity allowances
02-May-14
09-Jun-14
02-May-14
09-Jun-14
0
A8600
A8570
Field engineering
28-Jan-14
10-Feb-14
28-Jan-14
10-Feb-14
0
A8360
A8580
Work restrictions
02-May-14
07-Jul-14
02-May-14
07-Jul-14
0
A8600
A8590
Summary of multiple contracts
02-May-14
12-May-14
02-May-14
12-May-14
0
A8600
A8600
Summary
16-Apr-14
02-May-14
16-Apr-14
02-May-14
0
A8500, A8310
A8690, A8540, A8440, A8590, A8560, A8430, A8580, A8470
A8610
List of drawings
28-Jan-14
25-Feb-14
21-Jan-14
19-Feb-14
-5
A8360
A8340, A8350, A8320, A8330, A8500, A8390, A8300, A8640
A8620
Safety and health management plan
01-Apr-14
07-Apr-14
01-Apr-14
07-Apr-14
0
A8390
A8630
Standard General conditions
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8390
A8640
Sample Insurance certificates
26-Feb-14
04-Mar-14
26-Feb-14
04-Mar-14
0
A8610
A8650
Payment bond
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8390
A8660
Performance bond
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8390
A8670
AIA document a132
01-Apr-14
02-Apr-14
26-Mar-14
26-Mar-14
-5
A8390
A8760, A8790, A8770, A8400, A8510, A8420, A8750, A8480, A8490, A8520, A7080, A8970
A8680
Non collusion affidavit
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8390
A8690
General Commissioning requirements
02-May-14
09-May-14
02-May-14
09-May-14
0
A8600
A8700
Checklist classroom roe
21-Aug-17
01-Sep-17
21-Aug-17
01-Sep-17
0
A8290
A8780
A8710
Checklist student life building
07-Jun-17
20-Jun-17
21-Aug-17
01-Sep-17
53
A7690
A8780
A8720
Checklist enrollment building
24-Jan-17
06-Feb-17
21-Aug-17
01-Sep-17
149
A9420
A8780
A8730
Leed & sustainable design requirements
10-Oct-13
18-Oct-13
28-Oct-13
05-Nov-13
12
A8740
Testing for indoor air quality
10-Oct-13
05-Nov-13
10-Oct-13
05-Nov-13
0
A8750
Demonstration & training
02-Apr-14
08-Jul-15
02-Apr-14
08-Jul-15
0
A8670
A8760
Project record documents
12-Feb-15
01-Sep-17
12-Feb-15
01-Sep-17
0
A8670, A8780
A8770
Operation and maintenance data
02-Jun-14
01-Sep-17
02-Jun-14
01-Sep-17
0
A8670, A8780
A8780
Close out procedures
01-Sep-17
21-Dec-17
01-Sep-17
21-Dec-17
0
A8790, A8290, A8720, A8710, A8700
A9440, A8810, A8770, A8760, A8510, A8490, A8480, A8420, A8400
A8790
Construction waste mangement
02-Apr-14
31-Jul-17
06-May-14
01-Sep-17
24
A8670
A8780
A8800
Cutting and patching
10-Oct-13
07-Nov-13
10-Oct-13
07-Nov-13
0
A8810
Demobilize job trailers
01-Sep-17
07-May-18
01-Sep-17
07-May-18
0
A8780
A9440
A8820
Metal stairs
22-Apr-15*
29-Apr-15
22-Apr-15
29-Apr-15
0
ST1084
A8830, A7090
A8830
Install railings
29-Apr-15*
05-May-15
29-Apr-15
05-May-15
0
A8820
A8840
A8840
Interior H.M frames
05-May-15*
22-May-15
05-May-15
22-May-15
0
A8830
A8850
A8850
Drywall and spackliing
22-May-15*
04-Jun-15
22-May-15
04-Jun-15
0
A8840
A8860
A8860
Caulking
04-Jun-15*
11-Jun-15
04-Jun-15
11-Jun-15
0
A8850
A8870
A8870
Ceramic and porcelain wall/floor tiles
11-Jun-15*
22-Jun-15
11-Jun-15
22-Jun-15
0
A8860
A8880
A8880
Painting
22-Jun-15*
03-Jul-15
22-Jun-15
03-Jul-15
0
A8870
A8890
A8890
Wall coverings
03-Jul-15*
14-Jul-15
03-Jul-15
14-Jul-15
0
A8880
A8900
A8900
Acoustical ceiling grid
14-Jul-15*
23-Jul-15
14-Jul-15
23-Jul-15
0
A8890
A8910
A8910
PC AG san/rw
23-Jul-15*
06-Aug-15
23-Jul-15
06-Aug-15
0
A8900
A8920
A8920
PC overhead pipe
06-Aug-15*
20-Aug-15
06-Aug-15
20-Aug-15
0
A8910
A8930
A8930
PC insulation
20-Aug-15*
27-Aug-15
20-Aug-15
27-Aug-15
0
A8920
A8940
Footer 1
Page 4 of 8
A8460 A8460
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
A8940
PC drop sprinkler head
27-Aug-15*
10-Sep-15
27-Aug-15
10-Sep-15
0
A8930
A8950
A8950
PC casework fixtures
10-Sep-15*
17-Sep-15
10-Sep-15
17-Sep-15
0
A8940
A8960
A8960
PC toilet fixtures
17-Sep-15*
24-Sep-15
17-Sep-15
24-Sep-15
0
A8950
A8980
A8970
Start milestone
02-Apr-14*
03-Apr-14
02-Apr-14
03-Apr-14
0
A8670
S86
A8980
HC hangers
24-Sep-15*
01-Oct-15
24-Sep-15
01-Oct-15
0
A8960
A8990
A8990
HC pipe install
01-Oct-15*
12-Oct-15
01-Oct-15
12-Oct-15
0
A8980
A9000
A9000
HC duct install
12-Oct-15*
19-Oct-15
12-Oct-15
19-Oct-15
0
A8990
A9010
A9010
HC ATC rough-in
19-Oct-15*
03-Nov-15
19-Oct-15
03-Nov-15
0
A9000
A9020
A9020
HC GRD install
03-Nov-15*
23-Nov-15
03-Nov-15
23-Nov-15
0
A9010
A9030
A9030
HC equipment and final connections
23-Nov-15*
09-Dec-15
23-Nov-15
09-Dec-15
0
A9020
A9040
A9040
HC kitchen equipment and hookups
09-Dec-15*
23-Dec-15
09-Dec-15
23-Dec-15
0
A9030
A9050
A9050
EC rough-in walls
23-Dec-15*
08-Jan-16
23-Dec-15
08-Jan-16
0
A9040
A9060
A9060
EC overhead rough-in
08-Jan-16*
28-Jan-16
08-Jan-16
28-Jan-16
0
A9050
A9070
A9070
EC cable tray
28-Jan-16*
17-Feb-16
28-Jan-16
17-Feb-16
0
A9060
A9080
A9080
EC wiring
17-Feb-16*
01-Mar-16
17-Feb-16
01-Mar-16
0
A9070
A9090
A9090
EC light fixtures
01-Mar-16*
11-Mar-16
01-Mar-16
11-Mar-16
0
A9080
A9100
A9100
EC wring devices
11-Mar-16*
18-Mar-16
11-Mar-16
18-Mar-16
0
A9090
A9110
A9110
EC fire alarm and security
18-Mar-16*
28-Mar-16
18-Mar-16
28-Mar-16
0
A9100
A9120
A9120
EC kitchen equipment and hookups
28-Mar-16*
11-Apr-16
28-Mar-16
11-Apr-16
0
A9110
A9130
A9130
EC hook ups and connections
11-Apr-16*
18-Apr-16
11-Apr-16
18-Apr-16
0
A9120
A9140
A9140
Casework/millwork
18-Apr-16*
28-Apr-16
18-Apr-16
28-Apr-16
0
A9130
A9150
A9150
Resilent tile base and floor
28-Apr-16*
10-May-16
28-Apr-16
10-May-16
0
A9140
A9160
A9160
Seamless vinyl flooring
10-May-16*
20-May-16
10-May-16
20-May-16
0
A9150
A9170
A9170
Carpet tiles
20-May-16*
06-Jun-16
20-May-16
06-Jun-16
0
A9160
A9180
A9180
Install rubber stairs, treads and landings
06-Jun-16*
15-Jun-16
06-Jun-16
15-Jun-16
0
A9170
A9190
A9190
Doors and Hardware
15-Jun-16*
23-Jun-16
15-Jun-16
23-Jun-16
0
A9180
A9200
A9200
Interior glass partitions
23-Jun-16*
05-Jul-16
23-Jun-16
05-Jul-16
0
A9190
A9210
A9210
Wood wall panels
05-Jul-16*
12-Jul-16
05-Jul-16
12-Jul-16
0
A9200
A9220
A9220
Visual display surfaces
12-Jul-16*
19-Jul-16
12-Jul-16
19-Jul-16
0
A9210
A9230
A9230
Signage
19-Jul-16*
26-Jul-16
19-Jul-16
26-Jul-16
0
A9220
A9240
A9240
Wood ceiling
26-Jul-16*
29-Jul-16
26-Jul-16
29-Jul-16
0
A9230
A9250
A9250
Place Acoustical ceiling tiles
29-Jul-16*
12-Aug-16
29-Jul-16
12-Aug-16
0
A9240
A9260
A9260
Tiolet complartments
12-Aug-16*
24-Aug-16
12-Aug-16
24-Aug-16
0
A9250
A9270
A9270
Fire protection specialities
24-Aug-16*
01-Sep-16
24-Aug-16
01-Sep-16
0
A9260
A9290
A9280
Motorized projection screens
07-Feb-17
20-Feb-17
07-Feb-17
20-Feb-17
0
A9330
A9290
Window shades
01-Sep-16*
15-Sep-16
01-Sep-16
15-Sep-16
0
A9270
A9300
A9300
Wire mesh partitions
15-Sep-16*
26-Sep-16
15-Sep-16
26-Sep-16
0
A9290
A9310
A9310
Install lockers
26-Sep-16*
13-Oct-16
26-Sep-16
13-Oct-16
0
A9300
A9320
A9320
Install hood and walk-ins
13-Oct-16*
26-Oct-16
13-Oct-16
26-Oct-16
0
A9310
A9340
A9330
Install kitchen tiles
24-Jan-17
07-Feb-17
24-Jan-17
07-Feb-17
0
A9420
A9280
A9340
Install and setup food service equipment
26-Oct-16*
02-Nov-16
26-Oct-16
02-Nov-16
0
A9320
A9350
A9350
Glass wall folding partition
02-Nov-16*
09-Nov-16
02-Nov-16
09-Nov-16
0
A9340
A9360
A9360
Loading dock equipment
09-Nov-16*
25-Nov-16
09-Nov-16
25-Nov-16
0
A9350
A9370
A9370
Paint gym ceiling
25-Nov-16*
02-Dec-16
25-Nov-16
02-Dec-16
0
A9360
A9380
A9380
Gym equipment
02-Dec-16*
13-Dec-16
02-Dec-16
13-Dec-16
0
A9370
A9390
A9390
Gym dividers
13-Dec-16*
26-Dec-16
13-Dec-16
26-Dec-16
0
A9380
A9400
A9400
Install hardwood flooring
26-Dec-16*
04-Jan-17
26-Dec-16
04-Jan-17
0
A9390
A9410
A9410
Install collapsable belachers
04-Jan-17*
12-Jan-17
04-Jan-17
12-Jan-17
0
A9400
A9420
A9420
Hydraulic elevators
12-Jan-17*
24-Jan-17
12-Jan-17
24-Jan-17
0
A9410
A9330, A8720
A9430
Substantial milestone
23-Dec-15*
24-Dec-15
23-Dec-15
24-Dec-15
0
A7190
A7200
Footer 1
Page 5 of 8
Late Start
Late Finish
Total Float
Predecessors
Successors
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
A9440
Final Milestone
07-May-18*
08-May-18
07-May-18
08-May-18
0
A8780, A8810
S106
Erosion controls
10-Apr-14*
15-May-14
10-Apr-14
15-May-14
0
S86
S116, S206, S136
S116
Site Clearing and Strip Topsoil
15-May-14*
21-Aug-14
15-May-14
21-Aug-14
0
S106
S146, S176
S126
Temporary Basin and Swales
15-May-14*
03-Jul-14
12-Aug-14
29-Sep-14
62
S86
S216
S136
Site grading
15-May-14*
30-Oct-14
15-May-14
30-Oct-14
0
S106
S386
S146
Install Sediment Basin
21-Aug-14*
30-Oct-14
21-Aug-14
30-Oct-14
0
S116, S156
S156
Install Paving binder access roads and staging areas
15-May-14*
12-Jun-14
15-May-14
12-Jun-14
0
S86, S96
S166
Install additional staging areas
24-Jul-14*
03-Sep-14
24-Jul-14
03-Sep-14
0
S156
S176
Electrical ductbank
21-Aug-14*
30-Oct-14
21-Aug-14
30-Oct-14
0
S116
S186
Install Storm Sewer
12-May-14 A
23-Apr-15
15-May-14
23-Apr-15
0
S86
S236, S406
S196
Install Sanitary Sewer
30-Jun-14*
29-Aug-14
11-Aug-15
12-Oct-15
291
S156
S236
S206
Water system
05-May-14 A
17-Oct-14 A
15-May-14
15-May-14
S216
Concrete curbs
25-Aug-14*
09-Jan-15
30-Sep-14
16-Feb-15
26
S126, S226
S376
S226
Site lighting
30-Jun-14*
22-Aug-14
05-Aug-14
29-Sep-14
26
S156
S216, S396
S236
Final Landscaping
13-Oct-15*
21-Dec-15
13-Oct-15
21-Dec-15
0
S186, S196, S276, S326
S416, S316, S336
S246
Place trees and shrubbery
14-May-15*
09-Jul-15
14-May-15
09-Jul-15
0
S386, S396, S376
S256
site linestripping and signage
22-Apr-16*
27-May-16
22-Apr-16
27-May-16
0
S266
S266
Concrete bumper blocks
25-Mar-16*
21-Apr-16
25-Mar-16
21-Apr-16
0
S306, S416
S256
S276
sidewalks and ramp concrete pour
26-May-15*
24-Aug-15
26-May-15
24-Aug-15
0
S296
S236, S346, S326, S366
S286
Unit Pavers
29-Sep-15*
01-Dec-15
30-Sep-15
02-Dec-15
1
S346, S366
S416, S306
S296
Exterior masonry seat walls and site walls
13-Apr-15*
22-May-15
14-Apr-15
25-May-15
1
S376
S276, S356
S306
Exterior site railings
02-Dec-15*
22-Jan-16
03-Dec-15
25-Jan-16
1
S286
S266, S416
S316
Position Site seating
22-Dec-15*
25-Jan-16
22-Dec-15
25-Jan-16
0
S236
S416
S326
Fiberglass bus stations
25-Aug-15*
12-Oct-15
25-Aug-15
12-Oct-15
0
S276
S236
S336
Install flagpoles
02-Apr-14
27-May-16
27-Mar-14
27-May-16
-5
S236
S416
S346
Parking control equipment
25-Aug-15*
28-Sep-15
26-Aug-15
29-Sep-15
1
S276, S356
S286
S356
Retaining wall for landscaping
25-May-15*
19-Jun-15
29-Jul-15
25-Aug-15
47
S296
S346
S366
Timber guide railings
25-Aug-15*
21-Sep-15
02-Sep-15
29-Sep-15
6
S276
S286
S376
Retaining wall
12-Jan-15*
06-Mar-15
17-Feb-15
13-Apr-15
26
S216
S296, S246
S386
Site excavation
30-Oct-14*
14-May-15
30-Oct-14
14-May-15
0
S136
S246
S396
Install new topsoil
25-Aug-14 A
18-Dec-14
26-Mar-15
14-May-15
105
S176, S226
S246
S406
Install Geo Exchange Field
23-Apr-15*
10-Sep-15
23-Apr-15
10-Sep-15
0
S186
T57
S416
Final placement of trees and shrubbery
26-Jan-16*
24-Mar-16
26-Jan-16
24-Mar-16
0
S286, S236, S316, S336, S306
S266
S86
Site Layout
03-Apr-14
15-May-14
03-Apr-14
15-May-14
0
A7080, A8970
S106, S126, S156, S186
S96
Install Rock Construction Entrance
02-Apr-14
23-Apr-14
24-Apr-14
15-May-14
16
A7080
S156
SF25
Layout for foundation
11-Jul-14*
22-Jul-14
11-Jul-14
22-Jul-14
0
SF55
SF35, SF45, ST744
SF35
Footing excavation
19-Aug-14*
21-Oct-14
19-Aug-14
21-Oct-14
0
SF25, SF45
SF45
Tie Rebar
22-Jul-14*
19-Aug-14
22-Jul-14
19-Aug-14
0
SF25
SF35, SF65
SF55
Construct building pad
12-Jun-14*
11-Jul-14
12-Jun-14
11-Jul-14
0
S156
SF25
SF65
Concrete foundation
19-Aug-14*
21-Oct-14
19-Aug-14
21-Oct-14
0
SF45
ST1054, ST1224
ST1004
Deep underground rough-in
18-Nov-14*
09-Dec-14
02-Dec-14
23-Dec-14
10
ST984
ST994
ST1014
Stone under slab rough-in
20-Feb-15
10-Mar-15
20-Feb-15
10-Mar-15
0
ST784, ST1254
ST804, ST774
ST1024
Erect structural steel and deck
23-Dec-14
23-Jan-15
23-Dec-14
23-Jan-15
0
ST1234
ST1074, ST1254
ST1034
Pour concrete slab on deck
03-Mar-15
16-Apr-15
03-Mar-15
16-Apr-15
0
ST1044
ST1064
ST1044
Stone under slab
10-Feb-15
03-Mar-15
10-Feb-15
03-Mar-15
0
ST1234, ST1254
ST1064, ST1054, ST1034
ST1054
CMU walls
07-May-15
04-Jun-15
07-May-15
04-Jun-15
0
ST1064, ST1044, SF65
ST1204, ST1264, ST814
ST1064
Pour concrete slab on grade
16-Apr-15
07-May-15
16-Apr-15
07-May-15
0
ST1044, ST1034
ST1054
Footer 1
Page 6 of 8
Late Start
Late Finish
Total Float
Predecessors
Successors
S196, S226, S146, SF55, S166 S396, T47
S106
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
ST1074
Cold formed metal framing and sheathing
23-Jan-15
27-Feb-15
23-Jan-15
27-Feb-15
0
ST1024
ST1094
ST1084
Spray urethane insulation
25-Mar-15
22-Apr-15
25-Mar-15
22-Apr-15
0
ST1094
ST1104, ST1144, A8820
ST1094
Install air membrane
27-Feb-15
25-Mar-15
27-Feb-15
25-Mar-15
0
ST1074
ST1084
ST1104
Wood blocking & sheathing on roof
22-Apr-15
06-May-15
22-Apr-15
06-May-15
0
ST1084
ST1114, ST1124
ST1114
Roof curbs
06-May-15
15-May-15
12-Jun-15
23-Jun-15
27
ST1104
ST1134
ST1124
Roof Drains
06-May-15
21-May-15
06-May-15
21-May-15
0
ST1104
ST1154
ST1134
Roof top equipment
15-May-15
22-May-15
23-Jun-15
30-Jun-15
27
ST1114
ST1184
ST1144
Insulated metal wall panels
22-Apr-15
20-May-15
30-Jun-15
28-Jul-15
49
ST1084
ST1194
ST1154
Metal soffit and fascia
21-May-15
11-Jun-15
21-May-15
11-Jun-15
0
ST1124
ST1164
ST1164
Roof metal edges
11-Jun-15
30-Jun-15
11-Jun-15
30-Jun-15
0
ST1154
ST1184
ST1174
Exterior Caulking
27-Jul-15
10-Aug-15
28-Jul-15
11-Aug-15
1
ST1204
ST1214
ST1184
Metal roof ladders
30-Jun-15
28-Jul-15
30-Jun-15
28-Jul-15
0
ST1164, ST1134
ST1194
ST1194
Aluminum windows & curtain walls
28-Jul-15
11-Aug-15
28-Jul-15
11-Aug-15
0
ST1144, ST1184
ST1214
ST1204
Masonry veneer
04-Jun-15
27-Jul-15
05-Jun-15
28-Jul-15
1
ST1054
ST1174
ST1214
Aluminum entrance doors/sliding doors
11-Aug-15
15-Sep-15
11-Aug-15
15-Sep-15
0
ST1174, ST1194
ST1224
Plumbing underground sanitary/storm rough-in
21-Oct-14*
04-Nov-14
21-Oct-14
04-Nov-14
0
SF65
ST1234, ST1244, ST984
ST1234
Waterproofing
25-Nov-14*
23-Dec-14
25-Nov-14
23-Dec-14
0
ST1224, ST1244
ST1044, ST1024, ST994
ST1244
Deep underground rough-in
04-Nov-14*
25-Nov-14
04-Nov-14
25-Nov-14
0
ST1224
ST1234
ST1254
Stone under slab rough-in
23-Jan-15
10-Feb-15
23-Jan-15
10-Feb-15
0
ST1024
ST1044, ST1014
ST1264
Layout stone veneer
04-Jun-15
15-Jul-15
04-Jun-15
15-Jul-15
0
ST1054
ST544
Erect structural steel and deck
20-Jan-15
20-Feb-15
16-Feb-15
19-Mar-15
19
ST754
ST594, ST774
ST554
Pour concrete slab on deck
16-Apr-15
01-Jun-15
28-Apr-15
11-Jun-15
8
ST564
ST584
ST564
Stone under slab
26-Mar-15
16-Apr-15
07-Apr-15
28-Apr-15
8
ST754, ST774
ST584, ST574, ST554
ST574
CMU walls
02-Jul-15
30-Jul-15
02-Jul-15
30-Jul-15
0
ST584, ST564, ST814
ST724
ST584
Pour concrete slab on grade
01-Jun-15
22-Jun-15
11-Jun-15
02-Jul-15
8
ST564, ST554
ST574
ST594
Cold formed metal framing and sheathing
20-Feb-15
27-Mar-15
19-Mar-15
23-Apr-15
19
ST544
ST614
ST604
Spray urethane insulation
22-Apr-15
20-May-15
19-May-15
16-Jun-15
19
ST614
ST624, ST664
ST614
Install air membrane
27-Mar-15
22-Apr-15
23-Apr-15
19-May-15
19
ST594
ST604
ST624
Wood blocking & sheathing on roof
20-May-15
03-Jun-15
16-Jun-15
30-Jun-15
19
ST604
ST634, ST644
ST634
Roof curbs
03-Jun-15
12-Jun-15
06-Aug-15
17-Aug-15
46
ST624
ST654
ST644
Roof Drains
03-Jun-15
18-Jun-15
30-Jun-15
15-Jul-15
19
ST624
ST674
ST654
Roof top equipment
12-Jun-15
19-Jun-15
17-Aug-15
24-Aug-15
46
ST634
ST704
ST664
Insulated metal wall panels
20-May-15
17-Jun-15
24-Aug-15
21-Sep-15
68
ST604
ST714
ST674
Metal soffit and fascia
18-Jun-15
09-Jul-15
15-Jul-15
05-Aug-15
19
ST644
ST684
ST684
Roof metal edges
09-Jul-15
28-Jul-15
05-Aug-15
24-Aug-15
19
ST674
ST704
ST694
Exterior Caulking
21-Sep-15
05-Oct-15
21-Sep-15
05-Oct-15
0
ST724
ST734
ST704
Metal roof ladders
28-Jul-15
25-Aug-15
24-Aug-15
21-Sep-15
19
ST684, ST654
ST714
ST714
Aluminum windows & curtain walls
25-Aug-15
08-Sep-15
21-Sep-15
05-Oct-15
19
ST664, ST704
ST734
ST724
Masonry veneer
30-Jul-15
21-Sep-15
30-Jul-15
21-Sep-15
0
ST574
ST694
ST734
Aluminum entrance doors/sliding doors
05-Oct-15
09-Nov-15
05-Oct-15
09-Nov-15
0
ST694, ST714
A7700 ST754, ST764
ST744
Plumbing underground sanitary/storm rough-in
18-Nov-14*
02-Dec-14
15-Dec-14
29-Dec-14
19
SF25, ST984
ST754
Waterproofing
23-Dec-14*
20-Jan-15
19-Jan-15
16-Feb-15
19
ST744, ST764
ST564, ST544
ST764
Deep underground rough-in
02-Dec-14*
23-Dec-14
29-Dec-14
19-Jan-15
19
ST744
ST754
ST774
Stone under slab rough-in
10-Mar-15
26-Mar-15
20-Mar-15
07-Apr-15
8
ST544, ST1014
ST564
ST784
Erect structural steel and deck
20-Jan-15
20-Feb-15
20-Jan-15
20-Feb-15
0
ST994
ST834, ST1014
ST794
Pour concrete slab on deck
31-Mar-15
14-May-15
31-Mar-15
14-May-15
0
ST804
ST824
ST804
Stone under slab
10-Mar-15
31-Mar-15
10-Mar-15
31-Mar-15
0
ST994, ST1014
ST824, ST814, ST794
ST814
CMU walls
04-Jun-15
02-Jul-15
04-Jun-15
02-Jul-15
0
ST824, ST804, ST1054
ST964, ST574
Footer 1
Page 7 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:51
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
ST824
Pour concrete slab on grade
14-May-15
04-Jun-15
14-May-15
04-Jun-15
0
ST804, ST794
ST814
ST834
Cold formed metal framing and sheathing
20-Feb-15
27-Mar-15
20-Feb-15
27-Mar-15
0
ST784
ST854
ST844
Spray urethane insulation
22-Apr-15
20-May-15
22-Apr-15
20-May-15
0
ST854
ST864, ST904
ST854
Install air membrane
27-Mar-15
22-Apr-15
27-Mar-15
22-Apr-15
0
ST834
ST844
ST864
Wood blocking & sheathing on roof
20-May-15
03-Jun-15
20-May-15
03-Jun-15
0
ST844
ST874, ST884
ST874
Roof curbs
03-Jun-15
12-Jun-15
10-Jul-15
21-Jul-15
27
ST864
ST894
ST884
Roof Drains
03-Jun-15
18-Jun-15
03-Jun-15
18-Jun-15
0
ST864
ST914
ST894
Roof top equipment
12-Jun-15
19-Jun-15
21-Jul-15
28-Jul-15
27
ST874
ST944
ST904
Insulated metal wall panels
20-May-15
17-Jun-15
28-Jul-15
25-Aug-15
49
ST844
ST954 ST924
ST914
Metal soffit and fascia
18-Jun-15
09-Jul-15
18-Jun-15
09-Jul-15
0
ST884
ST924
Roof metal edges
09-Jul-15
28-Jul-15
09-Jul-15
28-Jul-15
0
ST914
ST944
ST934
Exterior Caulking
24-Aug-15
07-Sep-15
25-Aug-15
08-Sep-15
1
ST964
ST974
ST944
Metal roof ladders
28-Jul-15
25-Aug-15
28-Jul-15
25-Aug-15
0
ST924, ST894
ST954, A7090
ST954
Aluminum windows & curtain walls
25-Aug-15
08-Sep-15
25-Aug-15
08-Sep-15
0
ST904, ST944
ST974
ST964
Masonry veneer
02-Jul-15
24-Aug-15
03-Jul-15
25-Aug-15
1
ST814
ST934
ST974
Aluminum entrance doors/sliding doors
08-Sep-15
13-Oct-15
08-Sep-15
13-Oct-15
0
ST934, ST954
ST984
Plumbing underground sanitary/storm rough-in
04-Nov-14*
18-Nov-14
18-Nov-14
02-Dec-14
10
ST1224
ST994, ST1004, ST744
ST994
Waterproofing
23-Dec-14*
20-Jan-15
23-Dec-14
20-Jan-15
0
ST984, ST1004, ST1234
ST804, ST784
T27
Install Temporary Fence
06-Aug-14*
22-Aug-14
06-Aug-14
22-Aug-14
0
T37
T87, T67
T37
Mobilize Job Trailers
23-Jul-14*
06-Aug-14
23-Jul-14
06-Aug-14
0
T77
T27
T47
Provide temporary electric and lighting to buildings
30-Oct-14*
11-Dec-14
30-Oct-14
11-Dec-14
0
T67, S176
T57
Provide temporary heat
10-Sep-15*
05-Nov-15
10-Sep-15
05-Nov-15
0
S406
T67
Temporary utility poles
22-Aug-14*
12-Sep-14
09-Oct-14
30-Oct-14
34
T27
T47
T77
Site Preparation
09-Jul-14
23-Jul-14
09-Jul-14
23-Jul-14
0
A7080
T37
T87
Temporary electric to trailers
22-Aug-14*
05-Sep-14
22-Aug-14
05-Sep-14
0
T27
Footer 1
Page 8 of 8
MONROE CAMPUS... Activ Activity Name ID
Project: MONRO WBS: Volume 1
BASELINE nal Start
vity Qtr 4, 2013
ion 94 10-Oct-13 A 19 10-Oct-13
Oct N %
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
WBS: Division 00 b 135 10-Oct-13
Qtr 3, 2014
M Jun Jul Aug
78 10-Oct-13 0%
List A of drawings
21 28-Jan-14 0%
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
S Oct N Dec Jan F Mar Apr
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
M Jun Jul
A
Qtr 4, 2017
Geotechnical investigation List of drawings
8 26-Feb-14 0%
Prevailing wage documents
Electrical A Constructio
7 26-Feb-14 0%
Electrical Construction bid form
Plumbing A constructio
6 26-Feb-14 0%
Plumbing construction bid form
Hvac A construction bid
6 26-Feb-14 0%
Hvac construction bid
General A construction
7 26-Feb-14 0%
General construction bid form
Instruction A to bidders
13 26-Feb-14 0%
Qualification A question
6 26-Feb-14 0%
Bid A security
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Prevailing A wage docu
Sample A Insurance ce
Qtr 1, 2015
16-Apr-14, WBS: Division 00 bidding & contract requirements
Geotechnical A investig
invitation A to bid
Qtr 4, 2014
14-Apr-14 20:48
Instruction to bidders Qualification questionnaire
25 26-Feb-14 0%
invitation to bid
5 26-Feb-14 0%
Sample Insurance certificates
11 01-Apr-14
0%
Safety A and health ma
4 01-Apr-14
0%
Bid security
Standard A General co
1 01-Apr-14
0%
Standard General conditions
Payment A bond
1 01-Apr-14
0%
Payment bond
Performance A bond
1 01-Apr-14
0%
Performance bond
AIA A document a132
1 01-Apr-14
0%
AIA document a132
Non A collusion affidavit
1 01-Apr-14
0%
Non collusion affidavit
WBS: Division 01 G
19 10-Oct-13
Safety and health management plan
Alteration A Project pro
4 10-Oct-13 0%
Contract A Modification
51 10-Oct-13 0%
Contract Modification
Leed A & sustainable d
7 10-Oct-13 0%
Leed & sustainable design requirements
Testing A for indoor air
19 10-Oct-13 0%
Testing for indoor air quality
Cutting A and patching
21 10-Oct-13 0%
Cutting and patching
LEED A submital Form
38 06-Nov-13 0%
Coordination A drawings
17 28-Jan-14 0%
Field A engineering
10 28-Jan-14 0%
Product A requirements
39 01-Apr-14
0%
Unit A prices
43 01-Apr-14
0%
Execution A
00 02-Apr-14
0%
Temporary A Facilities &
946 02-Apr-14
0%
Construction A Progres
966 02-Apr-14
0%
Construction Progres
Web A based project m
955 02-Apr-14
0%
Web based project man
Project A Management
996 02-Apr-14
0%
Project Manag
Payement A procedures
00 02-Apr-14
0%
Payement p
Demonstration A & train
330 02-Apr-14
0%
Construction A waste m
868 02-Apr-14
0%
Start A milestone
Alteration Project procedures
1 02-Apr-14* 0% 0%
LEED submital Form Coordination drawings Field engineering Product requirements Unit prices Execution Temporary Facilities & con
Demonstration & training Construction waste mangement Start milestone
Summary A
12 16-Apr-14
References A
14 02-May-14 0%
Quality A requirements
49 02-May-14 0%
Quality requirements
Submittal A form
46 02-May-14 0%
Submittal form
Alternates A
12 02-May-14 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Summary References
Alternates Summary
Page 1 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE nal Start
vity Qtr 4, 2013
Quantity A allowances
Oct N ion % 26 02-May-14 0%
Work A restrictions
46 02-May-14 0%
Summary A of multiple c
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
Qtr 3, 2014
M Jun Jul Aug
Qtr 4, 2014
Qtr 1, 2015
S Oct N Dec Jan F Mar Apr
General A Commission
5 02-May-14 0%
General Commissioning requirements
Operation A and mainte
850 02-Jun-14 0%
Project A record docum
666 12-Feb-15 0%
Checklist A enrollment
9 24-Jan-17 0%
Checklist A student life
9 07-Jun-17 0%
Checklist A classroom
9 21-Aug-17 0%
Close A out procedures
79 01-Sep-17 0%
Demobilize A job trailers
176 01-Sep-17 0%
Final A Milestone
WBS: Sitework
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
S Oct N Dec Jan F Mar Apr
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
M Jun Jul
A
Qtr 4, 2017
Work restrictions Summary of multiple contracts
1 23-Dec-15* 0%
Qtr 3, 2015
Quantity allowances
6 02-May-14 0%
Substantial A milestone
Qtr 2, 2015
14-Apr-14 20:48
Operation and maintenance data Project record documents Substantial milestone Checklist enrollment building Checklist student life building Checklist classroom roe Close out procedure
1 07-May-18* 0% 562 02-Apr-14
27-May-16, WBS: Sitework
WBS: Division 33: U 354 05-May-14
10-Sep-15, WBS: Division 33: Utilities
Water system
120 05-May-14 00%
Install Storm Sewer
245 12-May-14 0%
Install Sanitary Sewer
45 30-Jun-14* 0%
Site lighting
40 30-Jun-14* 0%
Electrical ductbank
50 21-Aug-14* 0%
Install Geo Exchange
100 23-Apr-15* 0%
Water system Install Storm Sewer Install Sanitary Sewer Site lighting Electrical ductbank Install Geo Exchange Field
WBS: Division 10: S 562 02-Apr-14
27-May-16, WBS: Division 10: Specialties
Install flagpoles
562 02-Apr-14
Install A all site utilties
70 02-Apr-14* 0%
0%
Parking control equip
25 25-Aug-15* 0%
Timber guide railings
20 25-Aug-15* 0%
Exterior site railings
38 02-Dec-15* 0%
site linestripping and
26 22-Apr-16* 0%
Install flagpoles Install all site utilties Parking control equipment Timber guide railings Exterior site railings site linestripping and signage
WBS: Division 31: E 290 03-Apr-14
14-May-15, WBS: Division 31: Earthwork
Site Layout
30 03-Apr-14
Erosion controls
25 10-Apr-14* 0%
0%
Site Layout
Site Clearing and Stri
70 15-May-14* 0%
Temporary Basin and
35 15-May-14* 0%
Site grading
120 15-May-14* 0%
Site grading
Install Sediment Basin
50 21-Aug-14* 0%
Install Sediment Basin
Site excavation
140 30-Oct-14* 0%
Erosion controls Site Clearing and Strip Topsoil Temporary Basin and Swales
Site excavation
WBS: Division 32: S 536 02-Apr-14
21-Apr-16, WBS: Division 32: Site Improvements
Install Rock Construc
15 02-Apr-14
0%
Install Paving binder a
20 15-May-14* 0%
Install Rock Construction Entrance Install Paving binder access roads and staging areas
Install additional stagi
30 24-Jul-14* 0%
Concrete curbs
100 25-Aug-14* 0%
Install new topsoil
35 25-Aug-14 0%
Retaining wall
40 12-Jan-15* 0%
Exterior masonry sea
30 13-Apr-15* 0%
Place trees and shru
40 14-May-15* 0%
Place trees and shrubbery
Retaining wall for land
20 25-May-15* 0%
Retaining wall for landscaping
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Install additional staging areas Concrete curbs Install new topsoil Retaining wall Exterior masonry seat walls and site walls
Summary
Page 2 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE nal Start
vity Qtr 4, 2013
sidewalks and ramp c
Oct N ion % 65 26-May-15* 0%
Fiberglass bus statio
35 25-Aug-15* 0%
Unit Pavers
46 29-Sep-15* 0%
Final Landscaping
50 13-Oct-15* 0%
Position Site seating
25 22-Dec-15* 0%
Final placement of tre
43 26-Jan-16* 0%
Concrete bumper blo
20 25-Mar-16* 0%
WBS: Foundatio Construct building pad Layout for foundation
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
Qtr 3, 2014
M Jun Jul Aug
Qtr 4, 2014
M Jun Jul
A
S Oct N Dec Jan F Mar Apr
21 12-Jun-14* 0%
S Oct N Dec Jan F Mar Apr
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
M Jun Jul
A
Qtr 4, 2017
Construct building pad
0%
Layout for foundation Tie Rebar
346 09-Jul-14
05-Nov-15, WBS: Temporary Construction
Site Preparation
10 09-Jul-14
Mobilize Job Trailers
10 23-Jul-14* 0%
Install Temporary Fen
12 06-Aug-14* 0%
Temporary utility poles
15 22-Aug-14* 0%
Temporary electric to
10 22-Aug-14* 0%
Provide temporary ele
30 30-Oct-14* 0%
Provide temporary he
40 10-Sep-15* 0%
0%
Site Preparation Mobilize Job Trailers Install Temporary Fence Temporary utility poles Temporary electric to trailers Provide temporary electric and lighting to buildings Provide temporary heat
609 21-Oct-14
20-Feb-17, WBS: Building 1 ( Administration building )
WBS: Structure an and 235 21-Oct-14
15-Sep-15, WBS: Structure and Rough In
142 21-Oct-14
07-May-15, WBS: Division 3
Plumbing undergroun
10 21-Oct-14* 0%
Deep underground ro
15 04-Nov-14* 0%
Stone under slab rou
12 23-Jan-15 0%
Stone under slab
15 10-Feb-15 0%
Pour concrete slab o
32 03-Mar-15 0%
Pour concrete slab o
15 16-Apr-15
Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck
0%
Pour concrete slab on grade
35 28-Jul-15
15-Sep-15, WBS: Division 8
Aluminum windows &
10 28-Jul-15
Aluminum entrance d
25 11-Aug-15 0%
0%
Aluminum windows & curtain walls Aluminum entrance doors/sliding doors
57 07-May-15
27-Jul-15, WBS: Division 4
CMU walls
20 07-May-15 0%
Masonry veneer
37 04-Jun-15 0%
Masonry veneer
29 04-Jun-15 0%
Layout stone veneer
CMU walls
155 23-Dec-14
28-Jul-15, WBS: Division 5
Erect structural steel
23 23-Dec-14 0%
Cold formed metal fra
25 23-Jan-15 0%
WBS: Division 7
Qtr 2, 2017
21-Oct-14, WBS: Foundation
Concrete foundation
Metal roof ladders
Qtr 1, 2017
Concrete bumper blocks
Footing excavation
WBS: Division 5
M Jun Jul Aug
Qtr 4, 2016
Final placement of trees and shrubbery
45 19-Aug-14* 0%
Layout stone veneer
Qtr 3, 2016
Position Site seating
Concrete foundation
WBS: Division 4
Qtr 2, 2016
Final Landscaping
45 19-Aug-14* 0%
WBS: Division 8
Qtr 1, 2016
Unit Pavers
Footing excavation
WBS: Division 3
Qtr 4, 2015
Fiberglass bus stations
20 22-Jul-14* 0%
WBS: Building 1
Qtr 3, 2015
sidewalks and ramp concrete pour
Tie Rebar
WBS: Temporar
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
93 12-Jun-14
7 11-Jul-14*
Qtr 1, 2015
14-Apr-14 20:48
Erect structural steel and deck Cold formed metal framing and sheathing
20 30-Jun-15 0%
Metal roof ladders
184 25-Nov-14
10-Aug-15, WBS: Division 7
Waterproofing
20 25-Nov-14* 0%
Install air membrane
18 27-Feb-15 0%
Spray urethane insula
20 25-Mar-15 0%
Wood blocking & she
10 22-Apr-15
Waterproofing Install air membrane Spray urethane insulation
0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Wood blocking & sheathing on roof Summary
Page 3 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Insulated metal wall p
BASELINE nal Start
vity Qtr 4, 2013
ion 20 22-Apr-15
Oct N % 0%
Roof curbs
7 06-May-15 0%
Roof Drains
11 06-May-15 0%
Roof top equipment
15 21-May-15 0%
Roof metal edges
13 11-Jun-15
0%
Exterior Caulking
10 27-Jul-15
0%
WBS: Finishes
478 22-Apr-15
Install A railings Interior A H.M frames
5 04-Jun-15* 0%
Ceramic A and porcela
7 11-Jun-15* 0%
Painting A
9 22-Jun-15* 0%
Wall A coverings
6 03-Jul-15* 0% 10 23-Jul-15* 0%
PC A overhead pipe
10 06-Aug-15* 0%
Qtr 1, 2015
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
S Oct N Dec Jan F Mar Apr
Exterior Caulking 20-Feb-17, WBS: Finishes Metal stairs Install railings Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe PC insulation PC drop sprinkler head
5 10-Sep-15* 0%
PC casework fixtures
PC A toilet fixtures
5 17-Sep-15* 0%
HC A hangers
5 24-Sep-15* 0%
HC A pipe install
7 01-Oct-15* 0%
HC A duct install
5 12-Oct-15* 0%
PC toilet fixtures HC hangers HC pipe install HC duct install
HC A ATC rough-in
11 19-Oct-15* 0%
HC A GRD install
15 03-Nov-15* 0%
HC A equipment and fin
12 23-Nov-15* 0%
HC A kitchen equipmen
10 09-Dec-15* 0%
EC A rough-in walls
12 23-Dec-15* 0%
EC A overhead rough-in
14 08-Jan-16* 0%
EC A cable tray
14 28-Jan-16* 0%
EC cable tray
EC A wiring
9 17-Feb-16* 0%
EC wiring
EC A light fixtures
8 01-Mar-16* 0%
EC A wring devices
5 11-Mar-16* 0%
EC A fire alarm and sec
6 18-Mar-16* 0%
EC A kitchen equipmen
10 28-Mar-16* 0%
EC A hook ups and con
5 11-Apr-16* 0%
Casework/millwork A
8 18-Apr-16* 0%
Resilent A tile base and
8 28-Apr-16* 0%
Resilent tile base and floor
HC ATC rough-in
8 10-May-16* 0%
Seamless vinyl flooring
HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 20-May-16* 0%
Doors A and Hardware
6 15-Jun-16* 0%
Interior A glass partitions
8 23-Jun-16* 0%
Wood A wall panels
5 05-Jul-16* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
A
Roof metal edges
10 27-Aug-15* 0%
7 06-Jun-16* 0%
M Jun Jul
Qtr 4, 2017
Metal soffit and fascia
5 20-Aug-15* 0%
Install A rubber stairs, t
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
Roof top equipment
PC A casework fixtures
Carpet A tiles
Qtr 2, 2017
Roof Drains
PC A drop sprinkler hea
Seamless A vinyl floorin
Qtr 1, 2017
Roof curbs
7 14-Jul-15* 0%
PC A AG san/rw
Qtr 4, 2014
Insulated metal wall panels
4 29-Apr-15* 0% 9 22-May-15* 0%
Qtr 3, 2014
M Jun Jul Aug
13 05-May-15* 0%
Caulking A
PC A insulation
D Jan F Mar Apr
5 22-Apr-15* 0%
Drywall A and spackliing
Acoustical A ceiling grid
Qtr 2, 2014
5 15-May-15 0%
Metal soffit and fascia
Metal A stairs
Qtr 1, 2014
14-Apr-14 20:48
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Summary
Page 4 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Visual A display surface
BASELINE nal Start
vity Qtr 4, 2013
Oct N ion % 5 12-Jul-16* 0%
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
Qtr 3, 2014
M Jun Jul Aug
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
14-Apr-14 20:48
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
S Oct N Dec Jan F Mar Apr
5 19-Jul-16* 0%
Signage
Wood A ceiling
3 26-Jul-16* 0%
Wood ceiling
11 29-Jul-16* 0%
Tiolet A complartments
8 12-Aug-16* 0%
Fire A protection specia
6 24-Aug-16* 0%
Window A shades Wire A mesh partitions Install A lockers
5 26-Oct-16* 0%
Glass A wall folding par
5 02-Nov-16* 0%
Loading A dock equipm
12 09-Nov-16* 0%
Window shades Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment
Paint A gym ceiling
5 25-Nov-16* 0%
Gym A equipment
7 02-Dec-16* 0%
Gym equipment
Gym A dividers
9 13-Dec-16* 0%
Gym dividers
Install A hardwood floor
7 26-Dec-16* 0%
Install A collapsable bel
6 04-Jan-17* 0%
Hydraulic A elevators
8 12-Jan-17* 0%
Install A kitchen tiles
10 24-Jan-17 0%
Motorized A projection
WBS: Building 2
Paint gym ceiling
Install hardwood flooring Install collapsable belachers Hydraulic elevators Install kitchen tiles
9 07-Feb-17 0%
Motorized projection screens
695 04-Nov-14
04-Jul-17, WBS: Building 2 (Student Life)
WBS: Structure an and 245 04-Nov-14 WBS: Division 3
13-Oct-15, WBS: Structure and Rough In
152 04-Nov-14
04-Jun-15, WBS: Division 3
Plumbing undergroun
10 04-Nov-14* 0%
Deep underground ro
15 18-Nov-14* 0%
Stone under slab rou
12 20-Feb-15 0%
Stone under slab
15 10-Mar-15 0%
Pour concrete slab o
32 31-Mar-15 0%
Pour concrete slab o
15 14-May-15 0%
WBS: Division 8 Aluminum entrance d
25 08-Sep-15 0%
Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade Aluminum windows & curtain walls Aluminum entrance doors/sliding doors
57 04-Jun-15
24-Aug-15, WBS: Division 4
CMU walls
20 04-Jun-15 0%
Masonry veneer
37 02-Jul-15
CMU walls
0%
Masonry veneer
155 20-Jan-15
25-Aug-15, WBS: Division 5
Erect structural steel
23 20-Jan-15 0%
Cold formed metal fra
25 20-Feb-15 0%
Metal roof ladders
20 28-Jul-15
WBS: Division 7
184 23-Dec-14
Erect structural steel and deck Cold formed metal framing and sheathing
0%
Metal roof ladders 07-Sep-15, WBS: Division 7
Waterproofing
20 23-Dec-14* 0%
Install air membrane
18 27-Mar-15 0%
Spray urethane insula
20 22-Apr-15
Wood blocking & she
10 20-May-15 0%
Insulated metal wall p
20 20-May-15 0%
Roof curbs
Deep underground rough-in
13-Oct-15, WBS: Division 8
10 25-Aug-15 0%
WBS: Division 5
Plumbing underground sanitary/storm rough-in
35 25-Aug-15
Aluminum windows & WBS: Division 4
A
Fire protection specialities
7 15-Sep-16* 0%
Install A and setup food
M Jun Jul
Qtr 4, 2017
Tiolet complartments
13 26-Sep-16* 0% 9 13-Oct-16* 0%
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
Place Acoustical ceiling tiles
10 01-Sep-16* 0%
Install A hood and walk
Qtr 2, 2017
Visual display surfaces
Signage A Place A Acoustical ceilin
Qtr 1, 2017
Waterproofing Install air membrane
0%
Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels
7 03-Jun-15 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Roof curbs Summary
Page 5 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Roof Drains Roof top equipment
BASELINE nal Start
vity Qtr 4, 2013
Oct N ion % 11 03-Jun-15 0% 15 18-Jun-15 0%
Roof metal edges
13 09-Jul-15
Exterior Caulking
10 24-Aug-15 0%
WBS: Finishes
485 25-Aug-15
Install A railings Interior A H.M frames
D Jan F Mar Apr
Ceramic A and porcela
7 14-Oct-15* 0%
Painting A
9 23-Oct-15* 0%
Wall A coverings
6 05-Nov-15* 0%
Acoustical A ceiling grid
7 16-Nov-15* 0%
PC A AG san/rw
10 25-Nov-15* 0%
PC A overhead pipe
10 09-Dec-15* 0%
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
M Jun Jul Aug
Qtr 4, 2016
Qtr 1, 2017
S Oct N Dec Jan F Mar Apr
Install railings Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe PC insulation PC drop sprinkler head
5 14-Jan-16* 0%
PC casework fixtures
PC A toilet fixtures
5 21-Jan-16* 0%
PC A kitchen equipmen
6 28-Jan-16* 0%
HC A hangers
5 05-Feb-16* 0%
HC A pipe install
7 12-Feb-16* 0%
PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install
5 23-Feb-16* 0%
HC duct install
HC A ATC rough-in
11 01-Mar-16* 0%
HC A GRD install
15 16-Mar-16* 0%
HC A equipment and fin
12 05-Apr-16* 0%
HC A kitchen equipmen
10 21-Apr-16* 0%
EC A rough-in walls
12 05-May-16* 0%
EC A overhead rough-in
14 23-May-16* 0%
EC A cable tray
14 10-Jun-16* 0%
EC cable tray
EC A wiring
9 30-Jun-16* 0%
EC wiring
EC A light fixtures
8 13-Jul-16* 0%
EC A wring devices
5 25-Jul-16* 0%
EC A fire alarm and sec
6 01-Aug-16* 0%
EC A kitchen equipmen
10 09-Aug-16* 0%
EC A hook ups and con
5 23-Aug-16* 0%
Casework/millwork A
8 30-Aug-16* 0%
Resilent A tile base and
8 09-Sep-16* 0%
Resilent tile base and floor
Seamless A vinyl floorin
8 21-Sep-16* 0%
Seamless vinyl flooring
HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 03-Oct-16* 0%
Doors A and Hardware
6 27-Oct-16* 0%
Interior A glass partitions
8 04-Nov-16* 0%
Wood A wall panels
5 16-Nov-16* 0%
Visual A display surface
5 23-Nov-16* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
A
04-Jul-17, WBS: Finishes
PC A casework fixtures
7 18-Oct-16* 0%
M Jun Jul
Qtr 4, 2017
Metal stairs
5 24-Dec-15* 0%
Install A rubber stairs, t
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
Exterior Caulking
10 31-Dec-15* 0%
Carpet A tiles
Qtr 2, 2017
Roof metal edges
PC A drop sprinkler hea
HC A duct install
Qtr 3, 2016
Metal soffit and fascia
4 01-Sep-15* 0%
5 07-Oct-15* 0%
Qtr 1, 2015
Roof top equipment
13 07-Sep-15* 0%
Caulking A
Qtr 4, 2014
Roof Drains
5 25-Aug-15* 0%
9 24-Sep-15* 0%
Qtr 3, 2014
M Jun Jul Aug
0%
Drywall A and spackliing
PC A insulation
Qtr 2, 2014
5 12-Jun-15 0%
Metal soffit and fascia
Metal A stairs
Qtr 1, 2014
14-Apr-14 20:48
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Summary
Page 6 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Signage A Wood A ceiling
BASELINE nal Start
vity Qtr 4, 2013
Oct N ion % 5 30-Nov-16* 0% 11 12-Dec-16* 0%
Tiolet A complartments
8 26-Dec-16* 0%
Fire A protection specia
6 05-Jan-17* 0%
Wire A mesh partitions Install A lockers
Qtr 2, 2014
D Jan F Mar Apr
Qtr 3, 2014
M Jun Jul Aug
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
5 09-Mar-17* 0%
Glass A wall folding par
5 16-Mar-17* 0%
Loading A dock equipm
12 23-Mar-17* 0%
M Jun Jul
A
Tiolet complartments Fire protection specialities Window shades Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment
Paint A gym ceiling
5 10-Apr-17* 0%
Paint gym ceiling
Gym A equipment
7 17-Apr-17* 0%
Gym equipment
Gym A dividers
9 26-Apr-17* 0%
Gym dividers
Install A hardwood floor
7 09-May-17* 0%
Install A collapsable bel
6 18-May-17* 0%
Hydraulic A elevators
8 26-May-17* 0%
Install A kitchen tiles
10 07-Jun-17* 0%
Motorized A projection
WBS: Building 3
Install hardwood flooring Install collapsable belachers Hydraulic elevators Install kitchen tiles
9 21-Jun-17* 0%
Motorized projection screens
719 18-Nov-14
21-Aug-17, WBS: Building 3 (ClassRoo
WBS: Structure an and 254 18-Nov-14 WBS: Division 4
09-Nov-15, WBS: Structure and Rough In
57 02-Jul-15
21-Sep-15, WBS: Division 4
CMU walls
20 02-Jul-15
0%
Masonry veneer
37 30-Jul-15
0%
WBS: Division 5
Masonry veneer 25-Aug-15, WBS: Division 5
23 20-Jan-15 0%
Cold formed metal fra
25 20-Feb-15 0%
Metal roof ladders
20 28-Jul-15
WBS: Division 7
204 23-Dec-14
Erect structural steel and deck Cold formed metal framing and sheathing
0%
Metal roof ladders 05-Oct-15, WBS: Division 7
Waterproofing
20 23-Dec-14* 0%
Install air membrane
18 27-Mar-15 0%
Spray urethane insula
20 22-Apr-15
Wood blocking & she
10 20-May-15 0%
Insulated metal wall p
20 20-May-15 0%
Waterproofing Install air membrane
0%
Roof curbs
7 03-Jun-15 0%
Roof Drains
11 03-Jun-15 0%
Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels Roof curbs Roof Drains
5 12-Jun-15 0%
Metal soffit and fascia
15 18-Jun-15 0%
Roof metal edges
13 09-Jul-15
Exterior Caulking
10 21-Sep-15 0%
WBS: Division 3
CMU walls
155 20-Jan-15
Erect structural steel
Roof top equipment
Qtr 4, 2017
Place Acoustical ceiling tiles
13 07-Feb-17* 0%
Install A and setup food
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
Wood ceiling
7 27-Jan-17* 0% 9 24-Feb-17* 0%
Qtr 2, 2017
Signage
10 13-Jan-17* 0%
Install A hood and walk
Qtr 1, 2017
S Oct N Dec Jan F Mar Apr
3 07-Dec-16* 0%
Place A Acoustical ceilin
Window A shades
Qtr 1, 2014
14-Apr-14 20:48
Roof top equipment Metal soffit and fascia
0%
Roof metal edges Exterior Caulking
154 18-Nov-14
22-Jun-15, WBS: Division 3
Plumbing undergroun
10 18-Nov-14* 0%
Deep underground ro
15 02-Dec-14* 0%
Stone under slab rou
12 10-Mar-15 0%
Stone under slab
15 26-Mar-15 0%
Pour concrete slab o
32 16-Apr-15
Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab
0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Pour concrete slab on deck Summary
Page 7 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Pour concrete slab o WBS: Division 8 Aluminum windows &
BASELINE nal Start
vity Qtr 4, 2013
Oct N ion % 15 01-Jun-15 0%
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
M Jun Jul Aug
25 05-Oct-15 0% 465 09-Nov-15
Qtr 1, 2015
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Qtr 3, 2015
M Jun Jul
A
Qtr 4, 2015
Qtr 1, 2016
S Oct N Dec Jan F Mar Apr
Install A railings
4 16-Nov-15* 0%
Install railings
13 20-Nov-15* 0%
Caulking A
5 22-Dec-15* 0%
Ceramic A and porcela
7 29-Dec-15* 0%
Painting A
9 07-Jan-16* 0%
Wall A coverings
6 20-Jan-16* 0%
Acoustical A ceiling grid
7 29-Jan-16* 0%
PC A AG san/rw
10 09-Feb-16* 0%
PC A overhead pipe
10 23-Feb-16* 0%
PC A insulation
Qtr 1, 2017
Qtr 2, 2017
S Oct N Dec Jan F Mar Apr
M Jun Jul
Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe
5 08-Mar-16* 0%
PC insulation
10 15-Mar-16* 0%
PC drop sprinkler head
PC A casework fixtures
5 29-Mar-16* 0%
PC casework fixtures
PC A toilet fixtures
5 05-Apr-16* 0%
PC A kitchen equipmen
6 12-Apr-16* 0%
HC A hangers
5 20-Apr-16* 0%
HC A pipe install
7 27-Apr-16* 0%
HC A duct install
5 06-May-16* 0%
PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install HC duct install
HC A ATC rough-in
11 13-May-16* 0%
HC A GRD install
15 30-May-16* 0%
HC A equipment and fin
12 17-Jun-16* 0%
HC A kitchen equipmen
10 05-Jul-16* 0%
EC A rough-in walls
12 19-Jul-16* 0%
EC A overhead rough-in
14 04-Aug-16* 0%
EC A cable tray
14 24-Aug-16* 0%
EC cable tray
EC A wiring
9 13-Sep-16* 0%
EC wiring
EC A light fixtures
8 26-Sep-16* 0%
EC A wring devices
5 06-Oct-16* 0%
EC A fire alarm and sec
6 13-Oct-16* 0%
EC A kitchen equipmen
10 21-Oct-16* 0%
EC A hook ups and con
5 04-Nov-16* 0%
Casework/millwork A
8 11-Nov-16* 0%
Resilent A tile base and
8 23-Nov-16* 0%
Resilent tile base and floor
Seamless A vinyl floorin
8 05-Dec-16* 0%
HC ATC rough-in
Seamless vinyl flooring
HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 15-Dec-16* 0%
Install A rubber stairs, t
7 30-Dec-16* 0%
Doors A and Hardware
6 10-Jan-17* 0%
Interior A glass partitions
8 18-Jan-17* 0%
Wood A wall panels
5 30-Jan-17* 0%
Visual A display surface
5 06-Feb-17* 0%
Signage A
5 13-Feb-17* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
A
Qtr 4, 2017
Interior H.M frames
PC A drop sprinkler hea
Carpet A tiles
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
21-Aug-17, WBS: Finishes Metal stairs
9 09-Dec-15* 0%
M Jun Jul Aug
Qtr 4, 2016
Aluminum entrance doors/sliding doors
5 09-Nov-15* 0%
Drywall A and spackliing
Qtr 3, 2016
Aluminum windows & curtain walls
Metal A stairs Interior A H.M frames
Qtr 2, 2016
09-Nov-15, WBS: Division 8
10 25-Aug-15 0%
Aluminum entrance d
Qtr 4, 2014
Pour concrete slab on grade
54 25-Aug-15
WBS: Finishes
Qtr 3, 2014
14-Apr-14 20:48
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Signage Summary
Page 8 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE nal Start
vity Qtr 4, 2013
Wood A ceiling
Oct N ion % 3 20-Feb-17* 0%
Place A Acoustical ceilin
11 23-Feb-17* 0%
Tiolet A complartments
8 09-Mar-17* 0%
Fire A protection specia Window A shades Wire A mesh partitions Install A lockers
Qtr 1, 2014
Qtr 2, 2014
D Jan F Mar Apr
Qtr 3, 2014
M Jun Jul Aug
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
S Oct N Dec Jan F Mar Apr
Qtr 3, 2015
M Jun Jul
A
14-Apr-14 20:48 Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
S Oct N Dec Jan F Mar Apr
Qtr 3, 2016
M Jun Jul Aug
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
S Oct N Dec Jan F Mar Apr
Qtr 1, 2018 , 2018 S Oct N Dec Jan F Mar Apr M
Qtr 3, 2017
M Jun Jul
A
Qtr 4, 2017
Wood ceiling Place Acoustical ceiling tiles Tiolet complartments
6 21-Mar-17* 0%
Fire protection specialities
10 29-Mar-17* 0%
Window shades
7 12-Apr-17* 0%
Wire mesh partitions
13 21-Apr-17* 0%
Install lockers
Observation A deck
9 10-May-17* 0%
Install A Medical recline
5 23-May-17* 0%
Install Medical reclined chair
Glass A wall folding par
5 30-May-17* 0%
Glass wall folding partition
Place A additional medi
12 06-Jun-17* 0%
Install A lecture seating
5 22-Jun-17* 0%
Install A Student Desks
7 29-Jun-17* 0%
Lab A Desks
9 10-Jul-17* 0%
Install A hardwood floor
7 21-Jul-17* 0%
Teacher A desks
6 01-Aug-17* 0%
Hydraulic A elevators
8 09-Aug-17* 0%
Project: Monroe
0
Project: Monroe
0
Project: Monroe Project: Monroe
0
Observation deck
Place additional medical equipment Install lecture seating Install Student Desks and chairs Lab Desks Install hardwood flooring Teacher desks Hydraulic elevators
0
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Summary
Page 9 of 9
TASK filter: All Activities Š Oracle Corporation
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8360
78
78 Standard 5 Day Workweek
0
Geotechnical investigation
10-Oct-13
27-Jan-14
03-Oct-13
21-Jan-14
-5
A8450
4
4 Standard 5 Day Workweek
0
Alteration Project procedures
10-Oct-13
15-Oct-13
10-Oct-13
15-Oct-13
0
A8530
51
51 Standard 5 Day Workweek
0
Contract Modification
10-Oct-13
19-Dec-13
10-Oct-13
19-Dec-13
0
A8740
19
19 Standard 5 Day Workweek
0
Testing for indoor air quality
10-Oct-13
05-Nov-13
10-Oct-13
05-Nov-13
0
A8800
21
21 Standard 5 Day Workweek
0
Cutting and patching
10-Oct-13
07-Nov-13
10-Oct-13
07-Nov-13
0
A8730
7
7 Standard 5 Day Workweek
0
Leed & sustainable design requirements
10-Oct-13
18-Oct-13
28-Oct-13
05-Nov-13
12
A8460
38
38 Standard 5 Day Workweek
0
LEED submital Form
06-Nov-13
30-Dec-13
06-Nov-13
30-Dec-13
0
A8610
21
21 Standard 5 Day Workweek
0
List of drawings
28-Jan-14
25-Feb-14
21-Jan-14
19-Feb-14
-5
A8570
10
10 Standard 5 Day Workweek
0
Field engineering
28-Jan-14
10-Feb-14
28-Jan-14
10-Feb-14
0
A8500
17
17 Standard 5 Day Workweek
0
Coordination drawings
28-Jan-14
20-Feb-14
24-Mar-14
16-Apr-14
39
A8390
25
25 Standard 5 Day Workweek
0
invitation to bid
26-Feb-14
01-Apr-14
19-Feb-14
25-Mar-14
-5
A8300
8
8 Standard 5 Day Workweek
0
Prevailing wage documents
26-Feb-14
10-Mar-14
26-Feb-14
10-Mar-14
0
A8320
7
7 Standard 5 Day Workweek
0
Electrical Construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8330
6
6 Standard 5 Day Workweek
0
Plumbing construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8340
6
6 Standard 5 Day Workweek
0
Hvac construction bid
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8350
7
7 Standard 5 Day Workweek
0
General construction bid form
26-Feb-14
06-Mar-14
26-Feb-14
06-Mar-14
0
A8370
13
13 Standard 5 Day Workweek
0
Instruction to bidders
26-Feb-14
14-Mar-14
26-Feb-14
14-Mar-14
0
A8380
6
6 Standard 5 Day Workweek
0
Qualification questionnaire
26-Feb-14
05-Mar-14
26-Feb-14
05-Mar-14
0
A8640
5
5 Standard 5 Day Workweek
0
Sample Insurance certificates
26-Feb-14
04-Mar-14
26-Feb-14
04-Mar-14
0
A8670
1
1 Standard 5 Day Workweek
0
AIA document a132
01-Apr-14
02-Apr-14
26-Mar-14
26-Mar-14
-5
A8310
11
11 Standard 5 Day Workweek
0
Bid security
01-Apr-14
16-Apr-14
01-Apr-14
16-Apr-14
0
A8410
39
39 Standard 5 Day Workweek
0
Product requirements
01-Apr-14
26-May-14
01-Apr-14
26-May-14
0
A8550
43
43 Standard 5 Day Workweek
0
Unit prices
01-Apr-14
02-Jun-14
01-Apr-14
02-Jun-14
0
A8620
4
4 Standard 5 Day Workweek
0
Safety and health management plan
01-Apr-14
07-Apr-14
01-Apr-14
07-Apr-14
0
A8630
1
1 Standard 5 Day Workweek
0
Standard General conditions
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
Page 1 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8650
1
1 Standard 5 Day Workweek
0
Payment bond
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8660
1
1 Standard 5 Day Workweek
0
Performance bond
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
A8680
1
1 Standard 5 Day Workweek
0
Non collusion affidavit
01-Apr-14
02-Apr-14
01-Apr-14
02-Apr-14
0
S336
562
562 Standard 5 Day Workweek
0
Install flagpoles
02-Apr-14
27-May-16
27-Mar-14
27-May-16
-5
A7080
70
70 Standard 5 Day Workweek
0
Install all site utilties
02-Apr-14*
09-Jul-14
27-Mar-14
02-Jul-14
-5
1005 1005 Standard 5 Day Workweek
0
Execution
02-Apr-14
07-Feb-18
02-Apr-14
07-Feb-18
0
A8400
A8420
946
946 Standard 5 Day Workweek
0
Temporary Facilities & controls
02-Apr-14
16-Nov-17
02-Apr-14
16-Nov-17
0
A8480
966
966 Standard 5 Day Workweek
0
Construction Progress documentation
02-Apr-14
14-Dec-17
02-Apr-14
14-Dec-17
0
A8490
955
955 Standard 5 Day Workweek
0
Web based project management
02-Apr-14
30-Nov-17
02-Apr-14
30-Nov-17
0
A8510
996
996 Standard 5 Day Workweek
0
Project Management & coordination
02-Apr-14
25-Jan-18
02-Apr-14
25-Jan-18
0
1008 1008 Standard 5 Day Workweek
0
Payement procedures
02-Apr-14
12-Feb-18
02-Apr-14
12-Feb-18
0
A8520
A8750
330
330 Standard 5 Day Workweek
0
Demonstration & training
02-Apr-14
08-Jul-15
02-Apr-14
08-Jul-15
0
A8970
1
1 Standard 5 Day Workweek
0
Start milestone
02-Apr-14*
03-Apr-14
02-Apr-14
03-Apr-14
0
15
15 Standard 5 Day Workweek
0
Install Rock Construction Entrance
02-Apr-14
23-Apr-14
24-Apr-14
15-May-14
16
868
868 Standard 5 Day Workweek
0
Construction waste mangement
02-Apr-14
31-Jul-17
06-May-14
01-Sep-17
24
S86
30
30 Standard 5 Day Workweek
0
Site Layout
03-Apr-14
15-May-14
03-Apr-14
15-May-14
0
S106
25
25 Standard 5 Day Workweek
0
Erosion controls
10-Apr-14*
15-May-14
10-Apr-14
15-May-14
0
A8600
12
12 Standard 5 Day Workweek
0
Summary
16-Apr-14
02-May-14
16-Apr-14
02-May-14
0
A8430
14
14 Standard 5 Day Workweek
0
References
02-May-14
22-May-14
02-May-14
22-May-14
0
A8440
49
49 Standard 5 Day Workweek
0
Quality requirements
02-May-14
10-Jul-14
02-May-14
10-Jul-14
0
A8470
46
46 Standard 5 Day Workweek
0
Submittal form
02-May-14
08-Jul-14
02-May-14
08-Jul-14
0
A8540
12
12 Standard 5 Day Workweek
0
Alternates
02-May-14
21-May-14
02-May-14
21-May-14
0
A8560
26
26 Standard 5 Day Workweek
0
Quantity allowances
02-May-14
09-Jun-14
02-May-14
09-Jun-14
0
A8580
46
46 Standard 5 Day Workweek
0
Work restrictions
02-May-14
07-Jul-14
02-May-14
07-Jul-14
0
A8590
6
6 Standard 5 Day Workweek
0
Summary of multiple contracts
02-May-14
12-May-14
02-May-14
12-May-14
0
S96
A8790
Page 2 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
A8690
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
General Commissioning requirements
02-May-14
09-May-14
02-May-14
09-May-14
Water system
05-May-14 A 17-Oct-14 A
15-May-14
15-May-14
Total Float
5
5 Standard 5 Day Workweek
0
S206
120
0 Standard 5 Day Workweek
100
S186
245
245 Standard 5 Day Workweek
0
Install Storm Sewer
12-May-14 A 23-Apr-15
15-May-14
23-Apr-15
0
S116
70
70 Standard 5 Day Workweek
0
Site Clearing and Strip Topsoil
15-May-14*
21-Aug-14
15-May-14
21-Aug-14
0
S136
120
120 Standard 5 Day Workweek
0
Site grading
15-May-14*
30-Oct-14
15-May-14
30-Oct-14
0
S156
20
20 Standard 5 Day Workweek
0
Install Paving binder access roads and staging areas
15-May-14*
12-Jun-14
15-May-14
12-Jun-14
0
S126
35
35 Standard 5 Day Workweek
0
Temporary Basin and Swales
15-May-14*
03-Jul-14
12-Aug-14
29-Sep-14
62
A8770
850
850 Standard 5 Day Workweek
0
Operation and maintenance data
02-Jun-14
01-Sep-17
02-Jun-14
01-Sep-17
0
SF55
21
21 Standard 5 Day Workweek
0
Construct building pad
12-Jun-14*
11-Jul-14
12-Jun-14
11-Jul-14
0
S226
40
40 Standard 5 Day Workweek
0
Site lighting
30-Jun-14*
22-Aug-14
05-Aug-14
29-Sep-14
26
S196
45
45 Standard 5 Day Workweek
0
Install Sanitary Sewer
30-Jun-14*
29-Aug-14
11-Aug-15
12-Oct-15
291
T77
10
10 Standard 5 Day Workweek
0
Site Preparation
09-Jul-14
23-Jul-14
09-Jul-14
23-Jul-14
0
SF25
7
7 Standard 5 Day Workweek
0
Layout for foundation
11-Jul-14*
22-Jul-14
11-Jul-14
22-Jul-14
0
SF45
20
20 Standard 5 Day Workweek
0
Tie Rebar
22-Jul-14*
19-Aug-14
22-Jul-14
19-Aug-14
0
T37
10
10 Standard 5 Day Workweek
0
Mobilize Job Trailers
23-Jul-14*
06-Aug-14
23-Jul-14
06-Aug-14
0
S166
30
30 Standard 5 Day Workweek
0
Install additional staging areas
24-Jul-14*
03-Sep-14
24-Jul-14
03-Sep-14
0
T27
12
12 Standard 5 Day Workweek
0
Install Tempor ary Fence
06-Aug-14*
22-Aug-14
06-Aug-14
22-Aug-14
0
SF35
45
45 Standard 5 Day Workweek
0
Footing excavation
19-Aug-14*
21-Oct-14
19-Aug-14
21-Oct-14
0
SF65
45
45 Standard 5 Day Workweek
0
Concrete foundation
19-Aug-14*
21-Oct-14
19-Aug-14
21-Oct-14
0
S146
50
50 Standard 5 Day Workweek
0
Install Sediment Basin
21-Aug-14*
30-Oct-14
21-Aug-14
30-Oct-14
0
S176
50
50 Standard 5 Day Workweek
0
Electrical ductbank
21-Aug-14*
30-Oct-14
21-Aug-14
30-Oct-14
0
T87
10
10 Standard 5 Day Workweek
0
Temporary electric to trailers
22-Aug-14*
05-Sep-14
22-Aug-14
05-Sep-14
0
T67
15
15 Standard 5 Day Workweek
0
Temporary utility poles
22-Aug-14*
12-Sep-14
09-Oct-14
30-Oct-14
34
S216
100
100 Standard 5 Day Workweek
0
Concrete curbs
25-Aug-14*
09-Jan-15
30-Sep-14
16-Feb-15
26
S396
35
35 Standard 5 Day Workweek
0
Install new topsoil
25-Aug-14 A 18-Dec-14
26-Mar-15
14-May-15
105
Page 3 of 15
0
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
ST1224
10
10 Standard 5 Day Workweek
0
Plumbing underground sanitary/storm rough-in
21-Oct-14*
04-Nov-14
21-Oct-14
04-Nov-14
0
T47
30
30 Standard 5 Day Workweek
0
Provide temporary electric and lighting to buildings
30-Oct-14*
11-Dec-14
30-Oct-14
11-Dec-14
0
S386
140
140 Standard 5 Day Workweek
0
Site excavation
30-Oct-14*
14-May-15
30-Oct-14
14-May-15
0
ST1244
15
15 Standard 5 Day Workweek
0
Deep underground rough-in
04-Nov-14*
25-Nov-14
04-Nov-14
25-Nov-14
0
ST984
10
10 Standard 5 Day Workweek
0
Plumbing underground sanitary/storm rough-in
04-Nov-14*
18-Nov-14
18-Nov-14
02-Dec-14
10
ST1004
15
15 Standard 5 Day Workweek
0
Deep underground rough-in
18-Nov-14*
09-Dec-14
02-Dec-14
23-Dec-14
10
ST744
10
10 Standard 5 Day Workweek
0
Plumbing underground sanitary/storm rough-in
18-Nov-14*
02-Dec-14
15-Dec-14
29-Dec-14
19
ST1234
20
20 Standard 5 Day Workweek
0
Waterproofing
25-Nov-14*
23-Dec-14
25-Nov-14
23-Dec-14
0
ST764
15
15 Standard 5 Day Workweek
0
Deep underground rough-in
02-Dec-14*
23-Dec-14
29-Dec-14
19-Jan-15
19
ST994
20
20 Standard 5 Day Workweek
0
Waterproofing
23-Dec-14*
20-Jan-15
23-Dec-14
20-Jan-15
0
ST1024
23
23 Standard 5 Day Workweek
0
Erect structural steel and deck
23-Dec-14
23-Jan-15
23-Dec-14
23-Jan-15
0
ST754
20
20 Standard 5 Day Workweek
0
Waterproofing
23-Dec-14*
20-Jan-15
19-Jan-15
16-Feb-15
19
S376
40
40 Standard 5 Day Workweek
0
Retaining wall
12-Jan-15*
06-Mar-15
17-Feb-15
13-Apr-15
26
ST784
23
23 Standard 5 Day Workweek
0
Erect structural steel and deck
20-Jan-15
20-Feb-15
20-Jan-15
20-Feb-15
0
ST544
23
23 Standard 5 Day Workweek
0
Erect structural steel and deck
20-Jan-15
20-Feb-15
16-Feb-15
19-Mar-15
19
ST1074
25
25 Standard 5 Day Workweek
0
Cold formed metal framing and sheathing
23-Jan-15
27-Feb-15
23-Jan-15
27-Feb-15
0
ST1254
12
12 Standard 5 Day Workweek
0
Stone under slab rough-in
23-Jan-15
10-Feb-15
23-Jan-15
10-Feb-15
0
ST1044
15
15 Standard 5 Day Workweek
0
Stone under slab
10-Feb-15
03-Mar-15
10-Feb-15
03-Mar-15
0
A8760
666
666 Standard 5 Day Workweek
0
Project record documents
12-Feb-15
01-Sep-17
12-Feb-15
01-Sep-17
0
ST834
25
25 Standard 5 Day Workweek
0
Cold formed metal framing and sheathing
20-Feb-15
27-Mar-15
20-Feb-15
27-Mar-15
0
ST1014
12
12 Standard 5 Day Workweek
0
Stone under slab rough-in
20-Feb-15
10-Mar-15
20-Feb-15
10-Mar-15
0
ST594
25
25 Standard 5 Day Workweek
0
Cold formed metal framing and sheathing
20-Feb-15
27-Mar-15
19-Mar-15
23-Apr-15
19
ST1094
18
18 Standard 5 Day Workweek
0
Install air membrane
27-Feb-15
25-Mar-15
27-Feb-15
25-Mar-15
0
ST1034
32
32 Standard 5 Day Workweek
0
Pour concrete slab on deck
03-Mar-15
16-Apr-15
03-Mar-15
16-Apr-15
0
ST804
15
15 Standard 5 Day Workweek
0
Stone under slab
10-Mar-15
31-Mar-15
10-Mar-15
31-Mar-15
0
Page 4 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
ST774
12
12 Standard 5 Day Workweek
0
Stone under slab rough-in
10-Mar-15
26-Mar-15
20-Mar-15
07-Apr-15
8
ST1084
20
20 Standard 5 Day Workweek
0
Spray urethane insulation
25-Mar-15
22-Apr-15
25-Mar-15
22-Apr-15
0
ST564
15
15 Standard 5 Day Workweek
0
Stone under slab
26-Mar-15
16-Apr-15
07-Apr-15
28-Apr-15
8
ST854
18
18 Standard 5 Day Workweek
0
Install air membrane
27-Mar-15
22-Apr-15
27-Mar-15
22-Apr-15
0
ST614
18
18 Standard 5 Day Workweek
0
Install air membrane
27-Mar-15
22-Apr-15
23-Apr-15
19-May-15
19
ST794
32
32 Standard 5 Day Workweek
0
Pour concrete slab on deck
31-Mar-15
14-May-15
31-Mar-15
14-May-15
0
S296
30
30 Standard 5 Day Workweek
0
Exterior masonry seat walls and site walls
13-Apr-15*
22-May-15
14-Apr-15
25-May-15
1
ST1064
15
15 Standard 5 Day Workweek
0
Pour concrete slab on grade
16-Apr-15
07-May-15
16-Apr-15
07-May-15
0
ST554
32
32 Standard 5 Day Workweek
0
Pour concrete slab on deck
16-Apr-15
01-Jun-15
28-Apr-15
11-Jun-15
8
ST844
20
20 Standard 5 Day Workweek
0
Spray urethane insulation
22-Apr-15
20-May-15
22-Apr-15
20-May-15
0
ST1104
10
10 Standard 5 Day Workweek
0
Wood blocking & sheathing on roof
22-Apr-15
06-May-15
22-Apr-15
06-May-15
0
A8820
5
5 Standard 5 Day Workweek
0
Metal stairs
22-Apr-15*
29-Apr-15
22-Apr-15
29-Apr-15
0
ST604
20
20 Standard 5 Day Workweek
0
Spray urethane insulation
22-Apr-15
20-May-15
19-May-15
16-Jun-15
19
ST1144
20
20 Standard 5 Day Workweek
0
Insulated metal wall panels
22-Apr-15
20-May-15
30-Jun-15
28-Jul-15
49
100
100 Standard 5 Day Workweek
0
Install Geo Exchange Field
23-Apr-15*
10-Sep-15
23-Apr-15
10-Sep-15
0
A8830
4
4 Standard 5 Day Workweek
0
Install railings
29-Apr-15*
05-May-15
29-Apr-15
05-May-15
0
A8840
13
13 Standard 5 Day Workweek
0
Interior H.M frames
05-May-15*
22-May-15
05-May-15
22-May-15
0
ST1124
11
11 Standard 5 Day Workweek
0
Roof Drains
06-May-15
21-May-15
06-May-15
21-May-15
0
ST1114
7
7 Standard 5 Day Workweek
0
Roof curbs
06-May-15
15-May-15
12-Jun-15
23-Jun-15
27
ST1054
20
20 Standard 5 Day Workweek
0
CMU walls
07-May-15
04-Jun-15
07-May-15
04-Jun-15
0
S246
40
40 Standard 5 Day Workweek
0
Place trees and shrubbery
14-May-15*
09-Jul-15
14-May-15
09-Jul-15
0
ST824
15
15 Standard 5 Day Workweek
0
Pour concrete slab on grade
14-May-15
04-Jun-15
14-May-15
04-Jun-15
0
ST1134
5
5 Standard 5 Day Workweek
0
Roof top equipment
15-May-15
22-May-15
23-Jun-15
30-Jun-15
27
ST864
10
10 Standard 5 Day Workweek
0
Wood blocking & sheathing on roof
20-May-15
03-Jun-15
20-May-15
03-Jun-15
0
ST624
10
10 Standard 5 Day Workweek
0
Wood blocking & sheathing on roof
20-May-15
03-Jun-15
16-Jun-15
30-Jun-15
19
S406
Page 5 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
ST904
20
20 Standard 5 Day Workweek
0
Insulated metal wall panels
20-May-15
17-Jun-15
28-Jul-15
25-Aug-15
49
ST664
20
20 Standard 5 Day Workweek
0
Insulated metal wall panels
20-May-15
17-Jun-15
24-Aug-15
21-Sep-15
68
ST1154
15
15 Standard 5 Day Workweek
0
Metal soffit and fascia
21-May-15
11-Jun-15
21-May-15
11-Jun-15
0
A8850
9
9 Standard 5 Day Workweek
0
Drywall and spackliing
22-May-15*
04-Jun-15
22-May-15
04-Jun-15
0
S356
20
20 Standard 5 Day Workweek
0
Retaining wall for landscaping
25-May-15*
19-Jun-15
29-Jul-15
25-Aug-15
47
S276
65
65 Standard 5 Day Workweek
0
sidewalks and ramp concrete pour
26-May-15*
24-Aug-15
26-May-15
24-Aug-15
0
ST584
15
15 Standard 5 Day Workweek
0
Pour concrete slab on grade
01-Jun-15
22-Jun-15
11-Jun-15
02-Jul-15
8
ST884
11
11 Standard 5 Day Workweek
0
Roof Drains
03-Jun-15
18-Jun-15
03-Jun-15
18-Jun-15
0
ST644
11
11 Standard 5 Day Workweek
0
Roof Drains
03-Jun-15
18-Jun-15
30-Jun-15
15-Jul-15
19
ST874
7
7 Standard 5 Day Workweek
0
Roof curbs
03-Jun-15
12-Jun-15
10-Jul-15
21-Jul-15
27
ST634
7
7 Standard 5 Day Workweek
0
Roof curbs
03-Jun-15
12-Jun-15
06-Aug-15
17-Aug-15
46
ST814
20
20 Standard 5 Day Workweek
0
CMU walls
04-Jun-15
02-Jul-15
04-Jun-15
02-Jul-15
0
A8860
5
5 Standard 5 Day Workweek
0
Caulking
04-Jun-15*
11-Jun-15
04-Jun-15
11-Jun-15
0
ST1264
29
29 Standard 5 Day Workweek
0
Layout stone veneer
04-Jun-15
15-Jul-15
04-Jun-15
15-Jul-15
0
ST1204
37
37 Standard 5 Day Workweek
0
Masonry veneer
04-Jun-15
27-Jul-15
05-Jun-15
28-Jul-15
1
ST1164
13
13 Standard 5 Day Workweek
0
Roof metal edges
11-Jun-15
30-Jun-15
11-Jun-15
30-Jun-15
0
A8870
7
7 Standard 5 Day Workweek
0
Ceramic and porcelain wall/floor tiles
11-Jun-15*
22-Jun-15
11-Jun-15
22-Jun-15
0
ST894
5
5 Standard 5 Day Workweek
0
Roof top equipment
12-Jun-15
19-Jun-15
21-Jul-15
28-Jul-15
27
ST654
5
5 Standard 5 Day Workweek
0
Roof top equipment
12-Jun-15
19-Jun-15
17-Aug-15
24-Aug-15
46
ST914
15
15 Standard 5 Day Workweek
0
Metal soffit and fascia
18-Jun-15
09-Jul-15
18-Jun-15
09-Jul-15
0
ST674
15
15 Standard 5 Day Workweek
0
Metal soffit and fascia
18-Jun-15
09-Jul-15
15-Jul-15
05-Aug-15
19
A8880
9
9 Standard 5 Day Workweek
0
Painting
22-Jun-15*
03-Jul-15
22-Jun-15
03-Jul-15
0
ST1184
20
20 Standard 5 Day Workweek
0
Metal roof ladders
30-Jun-15
28-Jul-15
30-Jun-15
28-Jul-15
0
ST574
20
20 Standard 5 Day Workweek
0
CMU walls
02-Jul-15
30-Jul-15
02-Jul-15
30-Jul-15
0
ST964
37
37 Standard 5 Day Workweek
0
Masonry veneer
02-Jul-15
24-Aug-15
03-Jul-15
25-Aug-15
1
Page 6 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8890
6
6 Standard 5 Day Workweek
0
Wall coverings
03-Jul-15*
14-Jul-15
03-Jul-15
14-Jul-15
0
ST924
13
13 Standard 5 Day Workweek
0
Roof metal edges
09-Jul-15
28-Jul-15
09-Jul-15
28-Jul-15
0
ST684
13
13 Standard 5 Day Workweek
0
Roof metal edges
09-Jul-15
28-Jul-15
05-Aug-15
24-Aug-15
19
A8900
7
7 Standard 5 Day Workweek
0
Acoustical ceiling grid
14-Jul-15*
23-Jul-15
14-Jul-15
23-Jul-15
0
A8910
10
10 Standard 5 Day Workweek
0
PC AG san/rw
23-Jul-15*
06-Aug-15
23-Jul-15
06-Aug-15
0
ST1174
10
10 Standard 5 Day Workweek
0
Exterior Caulking
27-Jul-15
10-Aug-15
28-Jul-15
11-Aug-15
1
ST944
20
20 Standard 5 Day Workweek
0
Metal roof ladders
28-Jul-15
25-Aug-15
28-Jul-15
25-Aug-15
0
ST1194
10
10 Standard 5 Day Workweek
0
Aluminum windows & curtain walls
28-Jul-15
11-Aug-15
28-Jul-15
11-Aug-15
0
ST704
20
20 Standard 5 Day Workweek
0
Metal roof ladders
28-Jul-15
25-Aug-15
24-Aug-15
21-Sep-15
19
ST724
37
37 Standard 5 Day Workweek
0
Masonry veneer
30-Jul-15
21-Sep-15
30-Jul-15
21-Sep-15
0
A8920
10
10 Standard 5 Day Workweek
0
PC overhead pipe
06-Aug-15*
20-Aug-15
06-Aug-15
20-Aug-15
0
ST1214
25
25 Standard 5 Day Workweek
0
Aluminum entrance doors/sliding doors
11-Aug-15
15-Sep-15
11-Aug-15
15-Sep-15
0
A8930
5
5 Standard 5 Day Workweek
0
PC insulation
20-Aug-15*
27-Aug-15
20-Aug-15
27-Aug-15
0
ST934
10
10 Standard 5 Day Workweek
0
Exterior Caulking
24-Aug-15
07-Sep-15
25-Aug-15
08-Sep-15
1
S326
35
35 Standard 5 Day Workweek
0
Fiberglass bus stations
25-Aug-15*
12-Oct-15
25-Aug-15
12-Oct-15
0
S346
25
25 Standard 5 Day Workweek
0
Parking control equipment
25-Aug-15*
28-Sep-15
26-Aug-15
29-Sep-15
1
S366
20
20 Standard 5 Day Workweek
0
Timber guide railin gs
25-Aug-15*
21-Sep-15
02-Sep-15
29-Sep-15
6
ST954
10
10 Standard 5 Day Workweek
0
Aluminum windows & curtain walls
25-Aug-15
08-Sep-15
25-Aug-15
08-Sep-15
0
A7090
5
5 Standard 5 Day Workweek
0
Metal stairs
25-Aug-15*
01-Sep-15
25-Aug-15
01-Sep-15
0
ST714
10
10 Standard 5 Day Workweek
0
Aluminum windows & curtain walls
25-Aug-15
08-Sep-15
21-Sep-15
05-Oct-15
19
A8940
10
10 Standard 5 Day Workweek
0
PC drop sprinkler head
27-Aug-15*
10-Sep-15
27-Aug-15
10-Sep-15
0
A7100
4
4 Standard 5 Day Workweek
0
Install railings
01-Sep-15*
07-Sep-15
01-Sep-15
07-Sep-15
0
A7110
13
13 Standard 5 Day Workweek
0
Interior H.M frames
07-Sep-15*
24-Sep-15
07-Sep-15
24-Sep-15
0
ST974
25
25 Standard 5 Day Workweek
0
Aluminum entrance doors/sliding doors
08-Sep-15
13-Oct-15
08-Sep-15
13-Oct-15
0
A8950
5
5 Standard 5 Day Workweek
0
PC casework fixtures
10-Sep-15*
17-Sep-15
10-Sep-15
17-Sep-15
0
Page 7 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
T57
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
40
40 Standard 5 Day Workweek
0
Provide temporary heat
10-Sep-15*
05-Nov-15
10-Sep-15
05-Nov-15
0
A8960
5
5 Standard 5 Day Workweek
0
PC toilet fixtures
17-Sep-15*
24-Sep-15
17-Sep-15
24-Sep-15
0
ST694
10
10 Standard 5 Day Workweek
0
Exterior Caulking
21-Sep-15
05-Oct-15
21-Sep-15
05-Oct-15
0
A8980
5
5 Standard 5 Day Workweek
0
HC hangers
24-Sep-15*
01-Oct-15
24-Sep-15
01-Oct-15
0
A7120
9
9 Standard 5 Day Workweek
0
Drywall and spackliing
24-Sep-15*
07-Oct-15
24-Sep-15
07-Oct-15
0
S286
46
46 Standard 5 Day Workweek
0
Unit Pavers
29-Sep-15*
01-Dec-15
30-Sep-15
02-Dec-15
1
A8990
7
7 Standard 5 Day Workweek
0
HC pipe install
01-Oct-15*
12-Oct-15
01-Oct-15
12-Oct-15
0
ST734
25
25 Standard 5 Day Workweek
0
Aluminum entrance doors/sliding doors
05-Oct-15
09-Nov-15
05-Oct-15
09-Nov-15
0
A7130
5
5 Standard 5 Day Workweek
0
Caulking
07-Oct-15*
14-Oct-15
07-Oct-15
14-Oct-15
0
A9000
5
5 Standard 5 Day Workweek
0
HC duct install
12-Oct-15*
19-Oct-15
12-Oct-15
19-Oct-15
0
S236
50
50 Standard 5 Day Workweek
0
Final Landscaping
13-Oct-15*
21-Dec-15
13-Oct-15
21-Dec-15
0
A7140
7
7 Standard 5 Day Workweek
0
Ceramic and porcelain wall/floor tiles
14-Oct-15*
23-Oct-15
14-Oct-15
23-Oct-15
0
A9010
11
11 Standard 5 Day Workweek
0
HC ATC rough-in
19-Oct-15*
03-Nov-15
19-Oct-15
03-Nov-15
0
A7150
9
9 Standard 5 Day Workweek
0
Painting
23-Oct-15*
05-Nov-15
23-Oct-15
05-Nov-15
0
A9020
15
15 Standard 5 Day Workweek
0
HC GRD install
03-Nov-15*
23-Nov-15
03-Nov-15
23-Nov-15
0
A7160
6
6 Standard 5 Day Workweek
0
Wall coverings
05-Nov-15*
16-Nov-15
05-Nov-15
16-Nov-15
0
A7700
5
5 Standard 5 Day Workweek
0
Metal stairs
09-Nov-15*
16-Nov-15
09-Nov-15
16-Nov-15
0
A7170
7
7 Standard 5 Day Workweek
0
Acoustical ceiling grid
16-Nov-15*
25-Nov-15
16-Nov-15
25-Nov-15
0
A7710
4
4 Standard 5 Day Workweek
0
Install railings
16-Nov-15*
20-Nov-15
16-Nov-15
20-Nov-15
0
A7720
13
13 Standard 5 Day Workweek
0
Interior H.M frames
20-Nov-15*
09-Dec-15
20-Nov-15
09-Dec-15
0
A9030
12
12 Standard 5 Day Workweek
0
HC equipment and final connections
23-Nov-15*
09-Dec-15
23-Nov-15
09-Dec-15
0
A7180
10
10 Standard 5 Day Workweek
0
PC AG san/rw
25-Nov-15*
09-Dec-15
25-Nov-15
09-Dec-15
0
S306
38
38 Standard 5 Day Workweek
0
Exterior site railings
02-Dec-15*
22-Jan-16
03-Dec-15
25-Jan-16
1
A7190
10
10 Standard 5 Day Workweek
0
PC overhead pipe
09-Dec-15*
23-Dec-15
09-Dec-15
23-Dec-15
0
A7730
9
9 Standard 5 Day Workweek
0
Drywall and spackliing
09-Dec-15*
22-Dec-15
09-Dec-15
22-Dec-15
0
Page 8 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A9040
10
10 Standard 5 Day Workweek
0
HC kitchen equipment and hookups
09-Dec-15*
23-Dec-15
09-Dec-15
23-Dec-15
0
S316
25
25 Standard 5 Day Workweek
0
Position Site seating
22-Dec-15*
25-Jan-16
22-Dec-15
25-Jan-16
0
A7740
5
5 Standard 5 Day Workweek
0
Caulking
22-Dec-15*
29-Dec-15
22-Dec-15
29-Dec-15
0
A9430
1
1 Standard 5 Day Workweek
0
Substantial milestone
23-Dec-15*
24-Dec-15
23-Dec-15
24-Dec-15
0
A9050
12
12 Standard 5 Day Workweek
0
EC rough-in walls
23-Dec-15*
08-Jan-16
23-Dec-15
08-Jan-16
0
A7200
5
5 Standard 5 Day Workweek
0
PC insulation
24-Dec-15*
31-Dec-15
24-Dec-15
31-Dec-15
0
A7750
7
7 Standard 5 Day Workweek
0
Ceramic and porcelain wall/floor tiles
29-Dec-15*
07-Jan-16
29-Dec-15
07-Jan-16
0
A7210
10
10 Standard 5 Day Workweek
0
PC drop sprinkler head
31-Dec-15*
14-Jan-16
31-Dec-15
14-Jan-16
0
A7760
9
9 Standard 5 Day Workweek
0
Painting
07-Jan-16*
20-Jan-16
07-Jan-16
20-Jan-16
0
A9060
14
14 Standard 5 Day Workweek
0
EC overhead rough-in
08-Jan-16*
28-Jan-16
08-Jan-16
28-Jan-16
0
A7220
5
5 Standard 5 Day Workweek
0
PC casework fixtures
14-Jan-16*
21-Jan-16
14-Jan-16
21-Jan-16
0
A7770
6
6 Standard 5 Day Workweek
0
Wall coverings
20-Jan-16*
29-Jan-16
20-Jan-16
29-Jan-16
0
A7230
5
5 Standard 5 Day Workweek
0
PC toilet fixtures
21-Jan-16*
28-Jan-16
21-Jan-16
28-Jan-16
0
S416
43
43 Standard 5 Day Workweek
0
Final placement of trees and shrubbery
26-Jan-16*
24-Mar-16
26-Jan-16
24-Mar-16
0
A7240
6
6 Standard 5 Day Workweek
0
PC kitchen equipment hookups
28-Jan-16*
05-Feb-16
28-Jan-16
05-Feb-16
0
A9070
14
14 Standard 5 Day Workweek
0
EC cable tray
28-Jan-16*
17-Feb-16
28-Jan-16
17-Feb-16
0
A7780
7
7 Standard 5 Day Workweek
0
Acoustical ceiling grid
29-Jan-16*
09-Feb-16
29-Jan-16
09-Feb-16
0
A7250
5
5 Standard 5 Day Workweek
0
HC hangers
05-Feb-16*
12-Feb-16
05-Feb-16
12-Feb-16
0
A7790
10
10 Standard 5 Day Workweek
0
PC AG san/rw
09-Feb-16*
23-Feb-16
09-Feb-16
23-Feb-16
0
A7260
7
7 Standard 5 Day Workweek
0
HC pipe install
12-Feb-16*
23-Feb-16
12-Feb-16
23-Feb-16
0
A9080
9
9 Standard 5 Day Workweek
0
EC wiring
17-Feb-16*
01-Mar-16
17-Feb-16
01-Mar-16
0
A7270
5
5 Standard 5 Day Workweek
0
HC duct install
23-Feb-16*
01-Mar-16
23-Feb-16
01-Mar-16
0
A7800
10
10 Standard 5 Day Workweek
0
PC overhead pipe
23-Feb-16*
08-Mar-16
23-Feb-16
08-Mar-16
0
A9090
8
8 Standard 5 Day Workweek
0
EC light fixtures
01-Mar-16*
11-Mar-16
01-Mar-16
11-Mar-16
0
A7280
11
11 Standard 5 Day Workweek
0
HC ATC rough-in
01-Mar-16*
16-Mar-16
01-Mar-16
16-Mar-16
0
Page 9 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7810
5
5 Standard 5 Day Workweek
0
PC insulation
08-Mar-16*
15-Mar-16
08-Mar-16
15-Mar-16
0
A9100
5
5 Standard 5 Day Workweek
0
EC wring devices
11-Mar-16*
18-Mar-16
11-Mar-16
18-Mar-16
0
A7820
10
10 Standard 5 Day Workweek
0
PC drop sprinkler head
15-Mar-16*
29-Mar-16
15-Mar-16
29-Mar-16
0
A7290
15
15 Standard 5 Day Workweek
0
HC GRD install
16-Mar-16*
05-Apr-16
16-Mar-16
05-Apr-16
0
A9110
6
6 Standard 5 Day Workweek
0
EC fire alarm and security
18-Mar-16*
28-Mar-16
18-Mar-16
28-Mar-16
0
S266
20
20 Standard 5 Day Workweek
0
Concrete bumper blocks
25-Mar-16*
21-Apr-16
25-Mar-16
21-Apr-16
0
A9120
10
10 Standard 5 Day Workweek
0
EC kitchen equipment and hookups
28-Mar-16*
11-Apr-16
28-Mar-16
11-Apr-16
0
A7830
5
5 Standard 5 Day Workweek
0
PC casework fixtures
29-Mar-16*
05-Apr-16
29-Mar-16
05-Apr-16
0
A7840
5
5 Standard 5 Day Workweek
0
PC toilet fixtures
05-Apr-16*
12-Apr-16
05-Apr-16
12-Apr-16
0
A7300
12
12 Standard 5 Day Workweek
0
HC equipment and final connections
05-Apr-16*
21-Apr-16
05-Apr-16
21-Apr-16
0
A9130
5
5 Standard 5 Day Workweek
0
EC hook ups and connections
11-Apr-16*
18-Apr-16
11-Apr-16
18-Apr-16
0
A7850
6
6 Standard 5 Day Workweek
0
PC kitchen equipment hookups
12-Apr-16*
20-Apr-16
12-Apr-16
20-Apr-16
0
A9140
8
8 Standard 5 Day Workweek
0
Casework/millwork
18-Apr-16*
28-Apr-16
18-Apr-16
28-Apr-16
0
A7860
5
5 Standard 5 Day Workweek
0
HC hangers
20-Apr-16*
27-Apr-16
20-Apr-16
27-Apr-16
0
A7310
10
10 Standard 5 Day Workweek
0
HC kitchen equipment and hookups
21-Apr-16*
05-May-16
21-Apr-16
05-May-16
0
S256
26
26 Standard 5 Day Workweek
0
site linestripping and signage
22-Apr-16*
27-May-16
22-Apr-16
27-May-16
0
A7870
7
7 Standard 5 Day Workweek
0
HC pipe install
27-Apr-16*
06-May-16
27-Apr-16
06-May-16
0
A9150
8
8 Standard 5 Day Workweek
0
Resilent tile base and floor
28-Apr-16*
10-May-16
28-Apr-16
10-May-16
0
A7320
12
12 Standard 5 Day Workweek
0
EC rough-in walls
05-May-16*
23-May-16
05-May-16
23-May-16
0
A7880
5
5 Standard 5 Day Workweek
0
HC duct install
06-May-16*
13-May-16
06-May-16
13-May-16
0
A9160
8
8 Standard 5 Day Workweek
0
Seamless vinyl flooring
10-May-16*
20-May-16
10-May-16
20-May-16
0
A7890
11
11 Standard 5 Day Workweek
0
HC ATC rough-in
13-May-16*
30-May-16
13-May-16
30-May-16
0
A9170
11
11 Standard 5 Day Workweek
0
Carpet tiles
20-May-16*
06-Jun-16
20-May-16
06-Jun-16
0
A7330
14
14 Standard 5 Day Workweek
0
EC overhead rough-in
23-May-16*
10-Jun-16
23-May-16
10-Jun-16
0
A7900
15
15 Standard 5 Day Workweek
0
HC GRD install
30-May-16*
17-Jun-16
30-May-16
17-Jun-16
0
Page 10 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A9180
7
7 Standard 5 Day Workweek
0
Install rubber stairs, treads and landings
06-Jun-16*
15-Jun-16
06-Jun-16
15-Jun-16
0
A7340
14
14 Standard 5 Day Workweek
0
EC cable tray
10-Jun-16*
30-Jun-16
10-Jun-16
30-Jun-16
0
A9190
6
6 Standard 5 Day Workweek
0
Doors and Hardware
15-Jun-16*
23-Jun-16
15-Jun-16
23-Jun-16
0
A7910
12
12 Standard 5 Day Workweek
0
HC equipment and final connections
17-Jun-16*
05-Jul-16
17-Jun-16
05-Jul-16
0
A9200
8
8 Standard 5 Day Workweek
0
Interior glass partitions
23-Jun-16*
05-Jul-16
23-Jun-16
05-Jul-16
0
A7350
9
9 Standard 5 Day Workweek
0
EC wiring
30-Jun-16*
13-Jul-16
30-Jun-16
13-Jul-16
0
A9210
5
5 Standard 5 Day Workweek
0
Wood wall panels
05-Jul-16*
12-Jul-16
05-Jul-16
12-Jul-16
0
A7920
10
10 Standard 5 Day Workweek
0
HC kitchen equipment and hookups
05-Jul-16*
19-Jul-16
05-Jul-16
19-Jul-16
0
A9220
5
5 Standard 5 Day Workweek
0
Visual display surfaces
12-Jul-16*
19-Jul-16
12-Jul-16
19-Jul-16
0
A7360
8
8 Standard 5 Day Workweek
0
EC light fixtures
13-Jul-16*
25-Jul-16
13-Jul-16
25-Jul-16
0
A9230
5
5 Standard 5 Day Workweek
0
Signage
19-Jul-16*
26-Jul-16
19-Jul-16
26-Jul-16
0
A7930
12
12 Standard 5 Day Workweek
0
EC rough-in walls
19-Jul-16*
04-Aug-16
19-Jul-16
04-Aug-16
0
A7370
5
5 Standard 5 Day Workweek
0
EC wring devices
25-Jul-16*
01-Aug-16
25-Jul-16
01-Aug-16
0
A9240
3
3 Standard 5 Day Workweek
0
Wood ceiling
26-Jul-16*
29-Jul-16
26-Jul-16
29-Jul-16
0
A9250
11
11 Standard 5 Day Workweek
0
Place Acoustical ceiling tiles
29-Jul-16*
12-Aug-16
29-Jul-16
12-Aug-16
0
A7380
6
6 Standard 5 Day Workweek
0
EC fire alarm and security
01-Aug-16*
09-Aug-16
01-Aug-16
09-Aug-16
0
A7940
14
14 Standard 5 Day Workweek
0
EC overhead rough-in
04-Aug-16*
24-Aug-16
04-Aug-16
24-Aug-16
0
A7390
10
10 Standard 5 Day Workweek
0
EC kitchen equipment and hookups
09-Aug-16*
23-Aug-16
09-Aug-16
23-Aug-16
0
A9260
8
8 Standard 5 Day Workweek
0
Tiolet complartments
12-Aug-16*
24-Aug-16
12-Aug-16
24-Aug-16
0
A7400
5
5 Standard 5 Day Workweek
0
EC hook ups and connections
23-Aug-16*
30-Aug-16
23-Aug-16
30-Aug-16
0
A7950
14
14 Standard 5 Day Workweek
0
EC cable tray
24-Aug-16*
13-Sep-16
24-Aug-16
13-Sep-16
0
A9270
6
6 Standard 5 Day Workweek
0
Fire protection specialities
24-Aug-16*
01-Sep-16
24-Aug-16
01-Sep-16
0
A7410
8
8 Standard 5 Day Workweek
0
Casework/millwork
30-Aug-16*
09-Sep-16
30-Aug-16
09-Sep-16
0
A9290
10
10 Standard 5 Day Workweek
0
Window shades
01-Sep-16*
15-Sep-16
01-Sep-16
15-Sep-16
0
A7420
8
8 Standard 5 Day Workweek
0
Resilent tile base and floor
09-Sep-16*
21-Sep-16
09-Sep-16
21-Sep-16
0
Page 11 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7960
9
9 Standard 5 Day Workweek
0
EC wiring
13-Sep-16*
26-Sep-16
13-Sep-16
26-Sep-16
0
A9300
7
7 Standard 5 Day Workweek
0
Wire mesh partitions
15-Sep-16*
26-Sep-16
15-Sep-16
26-Sep-16
0
A7430
8
8 Standard 5 Day Workweek
0
Seamless vinyl flooring
21-Sep-16*
03-Oct-16
21-Sep-16
03-Oct-16
0
A7970
8
8 Standard 5 Day Workweek
0
EC light fixtures
26-Sep-16*
06-Oct-16
26-Sep-16
06-Oct-16
0
A9310
13
13 Standard 5 Day Workweek
0
Install lockers
26-Sep-16*
13-Oct-16
26-Sep-16
13-Oct-16
0
A7440
11
11 Standard 5 Day Workweek
0
Carpet tiles
03-Oct-16*
18-Oct-16
03-Oct-16
18-Oct-16
0
A7980
5
5 Standard 5 Day Workweek
0
EC wring devices
06-Oct-16*
13-Oct-16
06-Oct-16
13-Oct-16
0
A7990
6
6 Standard 5 Day Workweek
0
EC fire alarm and security
13-Oct-16*
21-Oct-16
13-Oct-16
21-Oct-16
0
A9320
9
9 Standard 5 Day Workweek
0
Install hood and walk-ins
13-Oct-16*
26-Oct-16
13-Oct-16
26-Oct-16
0
A7450
7
7 Standard 5 Day Workweek
0
Install rubber stairs, treads and landings
18-Oct-16*
27-Oct-16
18-Oct-16
27-Oct-16
0
A8000
10
10 Standard 5 Day Workweek
0
EC kitchen equipment and hookups
21-Oct-16*
04-Nov-16
21-Oct-16
04-Nov-16
0
A9340
5
5 Standard 5 Day Workweek
0
Install and setup food service equipment
26-Oct-16*
02-Nov-16
26-Oct-16
02-Nov-16
0
A7460
6
6 Standard 5 Day Workweek
0
Doors and Hardware
27-Oct-16*
04-Nov-16
27-Oct-16
04-Nov-16
0
A9350
5
5 Standard 5 Day Workweek
0
Glass wall folding partition
02-Nov-16*
09-Nov-16
02-Nov-16
09-Nov-16
0
A7470
8
8 Standard 5 Day Workweek
0
Interior glass partitions
04-Nov-16*
16-Nov-16
04-Nov-16
16-Nov-16
0
A8010
5
5 Standard 5 Day Workweek
0
EC hook ups and connections
04-Nov-16*
11-Nov-16
04-Nov-16
11-Nov-16
0
A9360
12
12 Standard 5 Day Workweek
0
Loading dock equipment
09-Nov-16*
25-Nov-16
09-Nov-16
25-Nov-16
0
A8020
8
8 Standard 5 Day Workweek
0
Casework/millwork
11-Nov-16*
23-Nov-16
11-Nov-16
23-Nov-16
0
A7480
5
5 Standard 5 Day Workweek
0
Wood wall panels
16-Nov-16*
23-Nov-16
16-Nov-16
23-Nov-16
0
A8030
8
8 Standard 5 Day Workweek
0
Resilent tile base and floor
23-Nov-16*
05-Dec-16
23-Nov-16
05-Dec-16
0
A7490
5
5 Standard 5 Day Workweek
0
Visual display surfaces
23-Nov-16*
30-Nov-16
23-Nov-16
30-Nov-16
0
A9370
5
5 Standard 5 Day Workweek
0
Paint gym ceiling
25-Nov-16*
02-Dec-16
25-Nov-16
02-Dec-16
0
A7500
5
5 Standard 5 Day Workweek
0
Signage
30-Nov-16*
07-Dec-16
30-Nov-16
07-Dec-16
0
A9380
7
7 Standard 5 Day Workweek
0
Gym equipment
02-Dec-16*
13-Dec-16
02-Dec-16
13-Dec-16
0
A8040
8
8 Standard 5 Day Workweek
0
Seamless vinyl flooring
05-Dec-16*
15-Dec-16
05-Dec-16
15-Dec-16
0
Page 12 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7510
3
3 Standard 5 Day Workweek
0
Wood ceiling
07-Dec-16*
12-Dec-16
07-Dec-16
12-Dec-16
0
A7520
11
11 Standard 5 Day Workweek
0
Place Acoustical ceiling tiles
12-Dec-16*
26-Dec-16
12-Dec-16
26-Dec-16
0
A9390
9
9 Standard 5 Day Workweek
0
Gym dividers
13-Dec-16*
26-Dec-16
13-Dec-16
26-Dec-16
0
A8050
11
11 Standard 5 Day Workweek
0
Carpet tiles
15-Dec-16*
30-Dec-16
15-Dec-16
30-Dec-16
0
A9400
7
7 Standard 5 Day Workweek
0
Install hardwood flooring
26-Dec-16*
04-Jan-17
26-Dec-16
04-Jan-17
0
A7530
8
8 Standard 5 Day Workweek
0
Tiolet complartments
26-Dec-16*
05-Jan-17
26-Dec-16
05-Jan-17
0
A8060
7
7 Standard 5 Day Workweek
0
Install rubber stairs, treads and landings
30-Dec-16*
10-Jan-17
30-Dec-16
10-Jan-17
0
A9410
6
6 Standard 5 Day Workweek
0
Install collapsable belachers
04-Jan-17*
12-Jan-17
04-Jan-17
12-Jan-17
0
A7540
6
6 Standard 5 Day Workweek
0
Fire protection specialities
05-Jan-17*
13-Jan-17
05-Jan-17
13-Jan-17
0
A8070
6
6 Standard 5 Day Workweek
0
Doors and Hardware
10-Jan-17*
18-Jan-17
10-Jan-17
18-Jan-17
0
A9420
8
8 Standard 5 Day Workweek
0
Hydraulic elevators
12-Jan-17*
24-Jan-17
12-Jan-17
24-Jan-17
0
A7560
10
10 Standard 5 Day Workweek
0
Window shades
13-Jan-17*
27-Jan-17
13-Jan-17
27-Jan-17
0
A8080
8
8 Standard 5 Day Workweek
0
Interior glass partitions
18-Jan-17*
30-Jan-17
18-Jan-17
30-Jan-17
0
A9330
10
10 Standard 5 Day Workweek
0
Install kitchen tiles
24-Jan-17
07-Feb-17
24-Jan-17
07-Feb-17
0
A8720
9
9 Standard 5 Day Workweek
0
Checklist enrollment building
24-Jan-17
06-Feb-17
21-Aug-17
01-Sep-17
149
A7570
7
7 Standard 5 Day Workweek
0
Wire mesh partitions
27-Jan-17*
07-Feb-17
27-Jan-17
07-Feb-17
0
A8090
5
5 Standard 5 Day Workweek
0
Wood wall panels
30-Jan-17*
06-Feb-17
30-Jan-17
06-Feb-17
0
A8100
5
5 Standard 5 Day Workweek
0
Visual display surfaces
06-Feb-17*
13-Feb-17
06-Feb-17
13-Feb-17
0
A7580
13
13 Standard 5 Day Workweek
0
Install lockers
07-Feb-17*
24-Feb-17
07-Feb-17
24-Feb-17
0
A9280
9
9 Standard 5 Day Workweek
0
Motorized projection screens
07-Feb-17
20-Feb-17
07-Feb-17
20-Feb-17
0
A8110
5
5 Standard 5 Day Workweek
0
Signage
13-Feb-17*
20-Feb-17
13-Feb-17
20-Feb-17
0
A8120
3
3 Standard 5 Day Workweek
0
Wood ceiling
20-Feb-17*
23-Feb-17
20-Feb-17
23-Feb-17
0
A8130
11
11 Standard 5 Day Workweek
0
Place Acoustical ceiling tiles
23-Feb-17*
09-Mar-17
23-Feb-17
09-Mar-17
0
A7590
9
9 Standard 5 Day Workweek
0
Install hood and walk-ins
24-Feb-17*
09-Mar-17
24-Feb-17
09-Mar-17
0
A7610
5
5 Standard 5 Day Workweek
0
Install and setup food service equipment
09-Mar-17*
16-Mar-17
09-Mar-17
16-Mar-17
0
Page 13 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8140
8
8 Standard 5 Day Workweek
0
Tiolet complartments
09-Mar-17*
21-Mar-17
09-Mar-17
21-Mar-17
0
A7620
5
5 Standard 5 Day Workweek
0
Glass wall folding partition
16-Mar-17*
23-Mar-17
16-Mar-17
23-Mar-17
0
A8150
6
6 Standard 5 Day Workweek
0
Fire protection specialities
21-Mar-17*
29-Mar-17
21-Mar-17
29-Mar-17
0
A7630
12
12 Standard 5 Day Workweek
0
Loading dock equipment
23-Mar-17*
10-Apr-17
23-Mar-17
10-Apr-17
0
A8170
10
10 Standard 5 Day Workweek
0
Window shades
29-Mar-17*
12-Apr-17
29-Mar-17
12-Apr-17
0
A7640
5
5 Standard 5 Day Workweek
0
Paint gym ceiling
10-Apr-17*
17-Apr-17
10-Apr-17
17-Apr-17
0
A8180
7
7 Standard 5 Day Workweek
0
Wire mesh partitions
12-Apr-17*
21-Apr-17
12-Apr-17
21-Apr-17
0
A7650
7
7 Standard 5 Day Workweek
0
Gym equipment
17-Apr-17*
26-Apr-17
17-Apr-17
26-Apr-17
0
A8190
13
13 Standard 5 Day Workweek
0
Install lockers
21-Apr-17*
10-May-17
21-Apr-17
10-May-17
0
A7660
9
9 Standard 5 Day Workweek
0
Gym dividers
26-Apr-17*
09-May-17
26-Apr-17
09-May-17
0
A7670
7
7 Standard 5 Day Workweek
0
Install hardwood flooring
09-May-17*
18-May-17
09-May-17
18-May-17
0
A8200
9
9 Standard 5 Day Workweek
0
Observation deck
10-May-17*
23-May-17
10-May-17
23-May-17
0
A7680
6
6 Standard 5 Day Workweek
0
Install collapsable belachers
18-May-17*
26-May-17
18-May-17
26-May-17
0
A8210
5
5 Standard 5 Day Workweek
0
Install Medical reclined chair
23-May-17*
30-May-17
23-May-17
30-May-17
0
A7690
8
8 Standard 5 Day Workweek
0
Hydraulic elevators
26-May-17*
07-Jun-17
26-May-17
07-Jun-17
0
A8220
5
5 Standard 5 Day Workweek
0
Glass wall folding partition
30-May-17*
06-Jun-17
30-May-17
06-Jun-17
0
A8230
12
12 Standard 5 Day Workweek
0
Place additional medical equipment
06-Jun-17*
22-Jun-17
06-Jun-17
22-Jun-17
0
A7600
10
10 Standard 5 Day Workweek
0
Install kitchen tiles
07-Jun-17*
21-Jun-17
07-Jun-17
21-Jun-17
0
A8710
9
9 Standard 5 Day Workweek
0
Checklist student life building
07-Jun-17
20-Jun-17
21-Aug-17
01-Sep-17
53
A7550
9
9 Standard 5 Day Workweek
0
Motorized projection screens
21-Jun-17*
04-Jul-17
21-Jun-17
04-Jul-17
0
A8240
5
5 Standard 5 Day Workweek
0
Install lecture seating
22-Jun-17*
29-Jun-17
22-Jun-17
29-Jun-17
0
A8250
7
7 Standard 5 Day Workweek
0
Install Student Desks and chairs
29-Jun-17*
10-Jul-17
29-Jun-17
10-Jul-17
0
A8260
9
9 Standard 5 Day Workweek
0
Lab Desks
10-Jul-17*
21-Jul-17
10-Jul-17
21-Jul-17
0
A8270
7
7 Standard 5 Day Workweek
0
Install hardwood flooring
21-Jul-17*
01-Aug-17
21-Jul-17
01-Aug-17
0
A8280
6
6 Standard 5 Day Workweek
0
Teacher desks
01-Aug-17*
09-Aug-17
01-Aug-17
09-Aug-17
0
Page 14 of 15
Project Start 10-Oct-13 Project Finish 08-May-18 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:50
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8290
8
8 Standard 5 Day Workweek
0
Hydraulic elevators
09-Aug-17*
21-Aug-17
09-Aug-17
21-Aug-17
0
A8700
9
9 Standard 5 Day Workweek
0
Checklist classroom roe
21-Aug-17
01-Sep-17
21-Aug-17
01-Sep-17
0
A8780
79
79 Standard 5 Day Workweek
0
Close out procedures
01-Sep-17
21-Dec-17
01-Sep-17
21-Dec-17
0
A8810
176
176 Standard 5 Day Workweek
0
Demobilize job trailers
01-Sep-17
07-May-18
01-Sep-17
07-May-18
0
A9440
1
1 Standard 5 Day Workweek
0
Final Milestone
07-May-18*
08-May-18
07-May-18
08-May-18
0
Page 15 of 15
7 days calendar 8 hours/day
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
MONROE CAMPUS A7080
Install all site utilties
27-Mar-14*
04-Jun-14
27-Mar-14
04-Jun-14
0
A8670
S86, S96, T77
A7090
Metal stairs
26-Apr-15*
30-Apr-15
17-Sep-15
22-Sep-15
144
A8820, ST944
A7100, A7700
A7100
Install railings
01-May-15*
04-May-15
26-Sep-15
30-Sep-15
148
A7090
A7110
A7110
Interior H.M frames
05-May-15*
17-May-15
30-Sep-15
13-Oct-15
148
A7100
A7120
A7120
Drywall and spackliing
18-May-15*
26-May-15
13-Oct-15
22-Oct-15
148
A7110
A7130
A7130
Caulking
27-May-15*
31-May-15
22-Oct-15
27-Oct-15
148
A7120
A7140
A7140
Ceramic and porcelain wall/floor tiles
01-Jun-15*
07-Jun-15
27-Oct-15
03-Nov-15
148
A7130
A7150
A7150
Painting
08-Jun-15*
16-Jun-15
03-Nov-15
12-Nov-15
148
A7140
A7160
A7160
Wall coverings
17-Jun-15*
23-Jun-15
12-Nov-15
18-Nov-15
148
A7150
A7170
A7170
Acoustical ceiling grid
23-Jun-15*
30-Jun-15
18-Nov-15
25-Nov-15
148
A7160
A7180
A7180
PC AG san/rw
30-Jun-15*
10-Jul-15
25-Nov-15
05-Dec-15
148
A7170
A7190
A7190
PC overhead pipe
10-Jul-15*
20-Jul-15
06-Dec-15
15-Dec-15
148
A7180
A9430
A7200
PC insulation
17-Dec-15*
21-Dec-15
17-Dec-15
21-Dec-15
0
A9430
A7210
A7210
PC drop sprinkler head
22-Dec-15*
31-Dec-15
22-Dec-15
31-Dec-15
0
A7200
A7220
A7220
PC casework fixtures
01-Jan-16*
05-Jan-16
01-Jan-16
05-Jan-16
0
A7210
A7230
A7230
PC toilet fixtures
06-Jan-16*
10-Jan-16
06-Jan-16
10-Jan-16
0
A7220
A7240
A7240
PC kitchen equipment hookups
11-Jan-16*
16-Jan-16
11-Jan-16
16-Jan-16
0
A7230
A7250
A7250
HC hangers
17-Jan-16*
21-Jan-16
17-Jan-16
21-Jan-16
0
A7240
A7260
A7260
HC pipe install
22-Jan-16*
28-Jan-16
22-Jan-16
28-Jan-16
0
A7250
A7270
A7270
HC duct install
29-Jan-16*
02-Feb-16
29-Jan-16
02-Feb-16
0
A7260
A7280
A7280
HC ATC rough-in
03-Feb-16*
13-Feb-16
03-Feb-16
13-Feb-16
0
A7270
A7290
A7290
HC GRD install
14-Feb-16*
28-Feb-16
14-Feb-16
28-Feb-16
0
A7280
A7300
A7300
HC equipment and final connections
28-Feb-16*
11-Mar-16
28-Feb-16
11-Mar-16
0
A7290
A7310
A7310
HC kitchen equipment and hookups
11-Mar-16*
21-Mar-16
11-Mar-16
21-Mar-16
0
A7300
A7320
A7320
EC rough-in walls
21-Mar-16*
02-Apr-16
21-Mar-16
02-Apr-16
0
A7310
A7330
A7330
EC overhead rough-in
02-Apr-16*
15-Apr-16
02-Apr-16
15-Apr-16
0
A7320
A7340
A7340
EC cable tray
16-Apr-16*
30-Apr-16
16-Apr-16
30-Apr-16
0
A7330
A7350
A7350
EC wiring
30-Apr-16*
08-May-16
30-Apr-16
08-May-16
0
A7340
A7360
A7360
EC light fixtures
08-May-16*
16-May-16
08-May-16
16-May-16
0
A7350
A7370
A7370
EC wring devices
16-May-16*
21-May-16
16-May-16
21-May-16
0
A7360
A7380
A7380
EC fire alarm and security
21-May-16*
28-May-16
21-May-16
28-May-16
0
A7370
A7390
A7390
EC kitchen equipment and hookups
28-May-16*
07-Jun-16
28-May-16
07-Jun-16
0
A7380
A7400
A7400
EC hook ups and connections
07-Jun-16*
12-Jun-16
07-Jun-16
12-Jun-16
0
A7390
A7410
A7410
Casework/millwork
12-Jun-16*
19-Jun-16
12-Jun-16
19-Jun-16
0
A7400
A7420
A7420
Resilent tile base and floor
19-Jun-16*
27-Jun-16
19-Jun-16
27-Jun-16
0
A7410
A7430
A7430
Seamless vinyl flooring
27-Jun-16*
05-Jul-16
27-Jun-16
05-Jul-16
0
A7420
A7440
A7440
Carpet tiles
05-Jul-16*
16-Jul-16
05-Jul-16
16-Jul-16
0
A7430
A7450
A7450
Install rubber stairs, treads and landings
16-Jul-16*
23-Jul-16
16-Jul-16
23-Jul-16
0
A7440
A7460
A7460
Doors and Hardware
23-Jul-16*
29-Jul-16
23-Jul-16
29-Jul-16
0
A7450
A7470
A7470
Interior glass partitions
29-Jul-16*
06-Aug-16
29-Jul-16
06-Aug-16
0
A7460
A7480
A7480
Wood wall panels
07-Aug-16*
11-Aug-16
07-Aug-16
11-Aug-16
0
A7470
A7490
A7490
Visual display surfaces
12-Aug-16*
16-Aug-16
12-Aug-16
16-Aug-16
0
A7480
A7500
A7500
Signage
17-Aug-16*
21-Aug-16
17-Aug-16
21-Aug-16
0
A7490
A7510
A7510
Wood ceiling
22-Aug-16*
24-Aug-16
22-Aug-16
24-Aug-16
0
A7500
A7520
A7520
Place Acoustical ceiling tiles
25-Aug-16*
04-Sep-16
25-Aug-16
04-Sep-16
0
A7510
A7530
A7530
Tiolet complartments
04-Sep-16*
11-Sep-16
04-Sep-16
11-Sep-16
0
A7520
A7540
A7540
Fire protection specialities
12-Sep-16*
17-Sep-16
12-Sep-16
17-Sep-16
0
A7530
A7560
Footer 1
Page 1 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A7550
Motorized projection screens
09-Jan-17*
18-Jan-17
09-Jan-17
18-Jan-17
0
A7600
A7560
Window shades
18-Sep-16*
27-Sep-16
18-Sep-16
27-Sep-16
0
A7540
A7570
A7570
Wire mesh partitions
28-Sep-16*
04-Oct-16
28-Sep-16
04-Oct-16
0
A7560
A7580
A7580
Install lockers
05-Oct-16*
17-Oct-16
05-Oct-16
17-Oct-16
0
A7570
A7590
A7590
Install hood and walk-ins
18-Oct-16*
26-Oct-16
18-Oct-16
26-Oct-16
0
A7580
A7610
A7600
Install kitchen tiles
30-Dec-16*
09-Jan-17
30-Dec-16
09-Jan-17
0
A7690
A7550
A7610
Install and setup food service equipment
27-Oct-16*
31-Oct-16
27-Oct-16
31-Oct-16
0
A7590
A7620
A7620
Glass wall folding partition
01-Nov-16*
05-Nov-16
01-Nov-16
05-Nov-16
0
A7610
A7630
A7630
Loading dock equipment
06-Nov-16*
17-Nov-16
06-Nov-16
17-Nov-16
0
A7620
A7640
A7640
Paint gym ceiling
18-Nov-16*
22-Nov-16
18-Nov-16
22-Nov-16
0
A7630
A7650
A7650
Gym equipment
23-Nov-16*
29-Nov-16
23-Nov-16
29-Nov-16
0
A7640
A7660
A7660
Gym dividers
30-Nov-16*
08-Dec-16
30-Nov-16
08-Dec-16
0
A7650
A7670
A7670
Install hardwood flooring
09-Dec-16*
15-Dec-16
09-Dec-16
15-Dec-16
0
A7660
A7680
A7680
Install collapsable belachers
16-Dec-16*
22-Dec-16
16-Dec-16
22-Dec-16
0
A7670
A7690
A7690
Hydraulic elevators
22-Dec-16*
30-Dec-16
22-Dec-16
30-Dec-16
0
A7680
A7600, A8710
A7700
Metal stairs
19-Jun-15*
23-Jun-15
22-Sep-15
27-Sep-15
95
ST734, A7090
A7710
A7710
Install railings
24-Jun-15*
27-Jun-15
27-Sep-15
01-Oct-15
95
A7700
A7720
A7720
Interior H.M frames
28-Jun-15*
10-Jul-15
01-Oct-15
14-Oct-15
95
A7710
A7730
A7730
Drywall and spackliing
11-Jul-15*
19-Jul-15
14-Oct-15
23-Oct-15
95
A7720
A7740
A7740
Caulking
20-Jul-15*
24-Jul-15
23-Oct-15
28-Oct-15
95
A7730
A7750
A7750
Ceramic and porcelain wall/floor tiles
25-Jul-15*
31-Jul-15
28-Oct-15
04-Nov-15
95
A7740
A7760
A7760
Painting
01-Aug-15*
09-Aug-15
04-Nov-15
13-Nov-15
95
A7750
A7770
A7770
Wall coverings
10-Aug-15*
16-Aug-15
13-Nov-15
19-Nov-15
95
A7760
A7780
A7780
Acoustical ceiling grid
16-Aug-15*
23-Aug-15
19-Nov-15
26-Nov-15
95
A7770
A7790
A7790
PC AG san/rw
23-Aug-15*
02-Sep-15
26-Nov-15
06-Dec-15
95
A7780
A7800
A7800
PC overhead pipe
02-Sep-15*
12-Sep-15
07-Dec-15
16-Dec-15
95
A7790
A7810
A7810
PC insulation
12-Sep-15*
17-Sep-15
17-Dec-15
21-Dec-15
95
A7800
A7820
A7820
PC drop sprinkler head
17-Sep-15*
27-Sep-15
22-Dec-15
31-Dec-15
95
A7810
A7830
A7830
PC casework fixtures
27-Sep-15*
02-Oct-15
01-Jan-16
05-Jan-16
95
A7820
A7840
A7840
PC toilet fixtures
02-Oct-15*
07-Oct-15
06-Jan-16
10-Jan-16
95
A7830
A7850
A7850
PC kitchen equipment hookups
07-Oct-15*
13-Oct-15
11-Jan-16
16-Jan-16
95
A7840
A7860
A7860
HC hangers
13-Oct-15*
18-Oct-15
17-Jan-16
21-Jan-16
95
A7850
A7870
A7870
HC pipe install
18-Oct-15*
25-Oct-15
22-Jan-16
28-Jan-16
95
A7860
A7880
A7880
HC duct install
25-Oct-15*
30-Oct-15
29-Jan-16
02-Feb-16
95
A7870
A7890
A7890
HC ATC rough-in
30-Oct-15*
10-Nov-15
03-Feb-16
13-Feb-16
95
A7880
A7900
A7900
HC GRD install
10-Nov-15*
25-Nov-15
14-Feb-16
28-Feb-16
95
A7890
A7910
A7910
HC equipment and final connections
25-Nov-15*
07-Dec-15
28-Feb-16
11-Mar-16
95
A7900
A7920
A7920
HC kitchen equipment and hookups
07-Dec-15*
17-Dec-15
11-Mar-16
21-Mar-16
95
A7910
A7930
A7930
EC rough-in walls
17-Dec-15*
29-Dec-15
21-Mar-16
02-Apr-16
95
A7920
A7940
A7940
EC overhead rough-in
29-Dec-15*
11-Jan-16
02-Apr-16
15-Apr-16
95
A7930
A7950
A7950
EC cable tray
11-Jan-16*
26-Jan-16
16-Apr-16
30-Apr-16
95
A7940
A7960
A7960
EC wiring
26-Jan-16*
03-Feb-16
30-Apr-16
08-May-16
95
A7950
A7970
A7970
EC light fixtures
03-Feb-16*
11-Feb-16
08-May-16
16-May-16
95
A7960
A7980
A7980
EC wring devices
11-Feb-16*
16-Feb-16
16-May-16
21-May-16
95
A7970
A7990
A7990
EC fire alarm and security
16-Feb-16*
22-Feb-16
21-May-16
28-May-16
95
A7980
A8000
A8000
EC kitchen equipment and hookups
22-Feb-16*
03-Mar-16
28-May-16
07-Jun-16
95
A7990
A8010
A8010
EC hook ups and connections
03-Mar-16*
08-Mar-16
07-Jun-16
12-Jun-16
95
A8000
A8020
A8020
Casework/millwork
08-Mar-16*
16-Mar-16
12-Jun-16
19-Jun-16
95
A8010
A8030
A8030
Resilent tile base and floor
16-Mar-16*
24-Mar-16
19-Jun-16
27-Jun-16
95
A8020
A8040
A8040
Seamless vinyl flooring
24-Mar-16*
01-Apr-16
27-Jun-16
05-Jul-16
95
A8030
A8050
Footer 1
Page 2 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
A8050
Carpet tiles
A8060
Install rubber stairs, treads and landings
A8070
Total Float
Predecessors
01-Apr-16*
12-Apr-16
05-Jul-16
16-Jul-16
95
A8040
A8060
12-Apr-16*
19-Apr-16
16-Jul-16
23-Jul-16
95
A8050
A8070
Doors and Hardware
19-Apr-16*
25-Apr-16
23-Jul-16
29-Jul-16
95
A8060
A8080
A8080
Interior glass partitions
25-Apr-16*
03-May-16
29-Jul-16
06-Aug-16
95
A8070
A8090
A8090
Wood wall panels
03-May-16*
08-May-16
07-Aug-16
11-Aug-16
95
A8080
A8100
A8100
Visual display surfaces
08-May-16*
13-May-16
12-Aug-16
16-Aug-16
95
A8090
A8110
A8110
Signage
13-May-16*
18-May-16
17-Aug-16
21-Aug-16
95
A8100
A8120
A8120
Wood ceiling
18-May-16*
21-May-16
22-Aug-16
24-Aug-16
95
A8110
A8130
A8130
Place Acoustical ceiling tiles
21-May-16*
01-Jun-16
25-Aug-16
04-Sep-16
95
A8120
A8140
A8140
Tiolet complartments
01-Jun-16*
08-Jun-16
04-Sep-16
11-Sep-16
95
A8130
A8150
A8150
Fire protection specialities
08-Jun-16*
14-Jun-16
12-Sep-16
17-Sep-16
95
A8140
A8170
A8170
Window shades
14-Jun-16*
24-Jun-16
18-Sep-16
27-Sep-16
95
A8150
A8180
A8180
Wire mesh partitions
24-Jun-16*
01-Jul-16
28-Sep-16
04-Oct-16
95
A8170
A8190
A8190
Install lockers
01-Jul-16*
14-Jul-16
05-Oct-16
17-Oct-16
95
A8180
A8200
A8200
Observation deck
14-Jul-16*
23-Jul-16
18-Oct-16
26-Oct-16
95
A8190
A8210
A8210
Install Medical reclined chair
23-Jul-16*
28-Jul-16
27-Oct-16
31-Oct-16
95
A8200
A8220
A8220
Glass wall folding partition
28-Jul-16*
02-Aug-16
01-Nov-16
05-Nov-16
95
A8210
A8230
A8230
Place additional medical equipment
02-Aug-16*
14-Aug-16
06-Nov-16
17-Nov-16
95
A8220
A8240
A8240
Install lecture seating
14-Aug-16*
19-Aug-16
18-Nov-16
22-Nov-16
95
A8230
A8250
A8250
Install Student Desks and chairs
19-Aug-16*
26-Aug-16
23-Nov-16
29-Nov-16
95
A8240
A8260
A8260
Lab Desks
26-Aug-16*
04-Sep-16
30-Nov-16
08-Dec-16
95
A8250
A8270
A8270
Install hardwood flooring
04-Sep-16*
11-Sep-16
09-Dec-16
15-Dec-16
95
A8260
A8280
A8280
Teacher desks
11-Sep-16*
18-Sep-16
16-Dec-16
22-Dec-16
95
A8270
A8290
A8290
Hydraulic elevators
18-Sep-16*
26-Sep-16
22-Dec-16
30-Dec-16
95
A8280
A8780, A8700
A8300
Prevailing wage documents
17-Jan-14
25-Jan-14
17-Jan-14
25-Jan-14
0
A8610
A8310
Bid security
10-Feb-14
21-Feb-14
10-Feb-14
21-Feb-14
0
A8390
A8320
Electrical Construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8610
A8330
Plumbing construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8610
A8340
Hvac construction bid
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8610
A8350
General construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8610
A8360
Geotechnical investigation
10-Oct-13
26-Dec-13
10-Oct-13
26-Dec-13
0
A8370
Instruction to bidders
17-Jan-14
29-Jan-14
17-Jan-14
29-Jan-14
0
A8390
A8380
Qualification questionnaire
17-Jan-14
22-Jan-14
17-Jan-14
22-Jan-14
0
A8390
A8390
invitation to bid
17-Jan-14
10-Feb-14
17-Jan-14
10-Feb-14
0
A8610
A8400
Execution
09-Apr-14
08-Jan-17
09-Apr-14
08-Jan-17
0
A8670, A8780
A8410
Product requirements
10-Feb-14
21-Mar-14
10-Feb-14
21-Mar-14
0
A8390
A8420
Temporary Facilities & controls
07-Jun-14
08-Jan-17
07-Jun-14
08-Jan-17
0
A8670, A8780
A8430
References
05-Mar-14
19-Mar-14
05-Mar-14
19-Mar-14
0
A8600
A8440
Quality requirements
05-Mar-14
23-Apr-14
05-Mar-14
23-Apr-14
0
A8600
A8450
Alteration Project procedures
10-Oct-13
13-Oct-13
10-Oct-13
13-Oct-13
0
LEED submital Form
29-Oct-13
06-Dec-13
29-Oct-13
06-Dec-13
0
A8730, A8740
A8470
Submittal form
05-Mar-14
21-Apr-14
05-Mar-14
21-Apr-14
0
A8390, A8600
A8480
Construction Progress documentation
18-May-14
08-Jan-17
18-May-14
08-Jan-17
0
A8670, A8780
A8490
Web based project management
28-May-14
08-Jan-17
28-May-14
08-Jan-17
0
A8670, A8780
A8500
Coordination drawings
27-Dec-13
13-Jan-14
04-Feb-14
21-Feb-14
39
A8610
A8510
Project Management & coordination
18-Apr-14
08-Jan-17
18-Apr-14
08-Jan-17
0
A8670, A8780
A8520
Payement procedures
11-Feb-14
15-Nov-16
11-Feb-14
15-Nov-16
0
A8670
Page 3 of 8
A8600
A8610, A8570
A8460
Footer 1
Successors
A8380, A8370, A8310, A8680, A8620, A8650, A8660, A8630, A8670, A8470, A8550, A8410
A8600
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A8530
Contract Modification
10-Oct-13
29-Nov-13
10-Oct-13
29-Nov-13
A8540
Alternates
05-Mar-14
18-Mar-14
05-Mar-14
18-Mar-14
0 0
A8600
A8550
Unit prices
10-Feb-14
26-Mar-14
10-Feb-14
26-Mar-14
0
A8390
A8560
Quantity allowances
05-Mar-14
31-Mar-14
05-Mar-14
31-Mar-14
0
A8600
A8570
Field engineering
27-Dec-13
05-Jan-14
27-Dec-13
05-Jan-14
0
A8360
A8580
Work restrictions
05-Mar-14
20-Apr-14
05-Mar-14
20-Apr-14
0
A8600
A8590
Summary of multiple contracts
05-Mar-14
11-Mar-14
05-Mar-14
11-Mar-14
0
A8600
A8600
Summary
21-Feb-14
05-Mar-14
21-Feb-14
05-Mar-14
0
A8500, A8310
A8690, A8540, A8440, A8590, A8560, A8430, A8580, A8470
A8610
List of drawings
27-Dec-13
16-Jan-14
27-Dec-13
16-Jan-14
0
A8360
A8340, A8350, A8320, A8330, A8500, A8390, A8300, A8640
A8620
Safety and health management plan
10-Feb-14
14-Feb-14
10-Feb-14
14-Feb-14
0
A8390
A8630
Standard General conditions
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8390
A8640
Sample Insurance certificates
17-Jan-14
21-Jan-14
17-Jan-14
21-Jan-14
0
A8610
A8650
Payment bond
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8390
A8660
Performance bond
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8390
A8670
AIA document a132
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8390
A8760, A8790, A8770, A8400, A8510, A8420, A8750, A8480, A8490, A8520, A7080, A8970
A8680
Non collusion affidavit
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8390
A8690
General Commissioning requirements
05-Mar-14
10-Mar-14
05-Mar-14
10-Mar-14
0
A8600
A8700
Checklist classroom roe
26-Sep-16
05-Oct-16
30-Dec-16
08-Jan-17
95
A8290
A8780
A8710
Checklist student life building
30-Dec-16
08-Jan-17
30-Dec-16
08-Jan-17
0
A7690
A8780
A8720
Checklist enrollment building
30-Apr-16
08-May-16
30-Dec-16
08-Jan-17
244
A9420
A8780
A8730
Leed & sustainable design requirements
10-Oct-13
16-Oct-13
22-Oct-13
28-Oct-13
12
A8740
Testing for indoor air quality
10-Oct-13
28-Oct-13
10-Oct-13
28-Oct-13
0
A8750
Demonstration & training
11-Feb-14
07-Jan-15
11-Feb-14
07-Jan-15
0
A8670
A8760
Project record documents
14-Mar-15
08-Jan-17
14-Mar-15
08-Jan-17
0
A8670, A8780
A8770
Operation and maintenance data
11-Sep-14
08-Jan-17
11-Sep-14
08-Jan-17
0
A8670, A8780
A8780
Close out procedures
08-Jan-17
28-Mar-17
08-Jan-17
28-Mar-17
0
A8790, A8290, A8720, A8710, A8700
A9440, A8810, A8770, A8760, A8510, A8490, A8480, A8420, A8400
A8790
Construction waste mangement
11-Feb-14
28-Jun-16
24-Aug-14
08-Jan-17
193
A8670
A8780
A8800
Cutting and patching
10-Oct-13
30-Oct-13
10-Oct-13
30-Oct-13
0
A8810
Demobilize job trailers
08-Jan-17
03-Jul-17
04-May-17
26-Oct-17
116
A8780
A9440
A8820
Metal stairs
27-Jan-15*
31-Jan-15
27-Jan-15
31-Jan-15
0
ST1084
A8830, A7090
A8830
Install railings
01-Feb-15*
04-Feb-15
01-Feb-15
04-Feb-15
0
A8820
A8840
A8840
Interior H.M frames
05-Feb-15*
17-Feb-15
05-Feb-15
17-Feb-15
0
A8830
A8850
A8850
Drywall and spackliing
18-Feb-15*
26-Feb-15
18-Feb-15
26-Feb-15
0
A8840
A8860
A8860
Caulking
27-Feb-15*
03-Mar-15
27-Feb-15
03-Mar-15
0
A8850
A8870
A8870
Ceramic and porcelain wall/floor tiles
04-Mar-15*
10-Mar-15
04-Mar-15
10-Mar-15
0
A8860
A8880
A8880
Painting
11-Mar-15*
19-Mar-15
11-Mar-15
19-Mar-15
0
A8870
A8890
A8890
Wall coverings
20-Mar-15*
26-Mar-15
20-Mar-15
26-Mar-15
0
A8880
A8900
A8900
Acoustical ceiling grid
26-Mar-15*
02-Apr-15
26-Mar-15
02-Apr-15
0
A8890
A8910
A8910
PC AG san/rw
02-Apr-15*
12-Apr-15
02-Apr-15
12-Apr-15
0
A8900
A8920
A8920
PC overhead pipe
12-Apr-15*
22-Apr-15
12-Apr-15
22-Apr-15
0
A8910
A8930
A8930
PC insulation
22-Apr-15*
27-Apr-15
22-Apr-15
27-Apr-15
0
A8920
A8940
Footer 1
Page 4 of 8
A8460 A8460
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A8940
PC drop sprinkler head
27-Apr-15*
07-May-15
27-Apr-15
07-May-15
0
A8930
A8950
A8950
PC casework fixtures
07-May-15*
12-May-15
07-May-15
12-May-15
0
A8940
A8960
A8960
PC toilet fixtures
12-May-15*
17-May-15
12-May-15
17-May-15
0
A8950
A8980
A8970
Start milestone
27-Mar-14*
27-Mar-14
27-Mar-14
27-Mar-14
0
A8670
S86
A8980
HC hangers
17-May-15*
22-May-15
17-May-15
22-May-15
0
A8960
A8990
A8990
HC pipe install
22-May-15*
29-May-15
22-May-15
29-May-15
0
A8980
A9000
A9000
HC duct install
29-May-15*
03-Jun-15
29-May-15
03-Jun-15
0
A8990
A9010
A9010
HC ATC rough-in
03-Jun-15*
14-Jun-15
03-Jun-15
14-Jun-15
0
A9000
A9020
A9020
HC GRD install
14-Jun-15*
29-Jun-15
14-Jun-15
29-Jun-15
0
A9010
A9030
A9030
HC equipment and final connections
29-Jun-15*
11-Jul-15
29-Jun-15
11-Jul-15
0
A9020
A9040
A9040
HC kitchen equipment and hookups
11-Jul-15*
21-Jul-15
11-Jul-15
21-Jul-15
0
A9030
A9050
A9050
EC rough-in walls
21-Jul-15*
02-Aug-15
21-Jul-15
02-Aug-15
0
A9040
A9060
A9060
EC overhead rough-in
02-Aug-15*
15-Aug-15
02-Aug-15
15-Aug-15
0
A9050
A9070
A9070
EC cable tray
15-Aug-15*
30-Aug-15
15-Aug-15
30-Aug-15
0
A9060
A9080
A9080
EC wiring
30-Aug-15*
07-Sep-15
30-Aug-15
07-Sep-15
0
A9070
A9090
A9090
EC light fixtures
07-Sep-15*
15-Sep-15
07-Sep-15
15-Sep-15
0
A9080
A9100
A9100
EC wring devices
15-Sep-15*
20-Sep-15
15-Sep-15
20-Sep-15
0
A9090
A9110
A9110
EC fire alarm and security
20-Sep-15*
26-Sep-15
20-Sep-15
26-Sep-15
0
A9100
A9120
A9120
EC kitchen equipment and hookups
26-Sep-15*
06-Oct-15
26-Sep-15
06-Oct-15
0
A9110
A9130
A9130
EC hook ups and connections
06-Oct-15*
11-Oct-15
06-Oct-15
11-Oct-15
0
A9120
A9140
A9140
Casework/millwork
11-Oct-15*
19-Oct-15
11-Oct-15
19-Oct-15
0
A9130
A9150
A9150
Resilent tile base and floor
19-Oct-15*
27-Oct-15
19-Oct-15
27-Oct-15
0
A9140
A9160
A9160
Seamless vinyl flooring
27-Oct-15*
04-Nov-15
27-Oct-15
04-Nov-15
0
A9150
A9170
A9170
Carpet tiles
04-Nov-15*
15-Nov-15
04-Nov-15
15-Nov-15
0
A9160
A9180
A9180
Install rubber stairs, treads and landings
15-Nov-15*
22-Nov-15
15-Nov-15
22-Nov-15
0
A9170
A9190
A9190
Doors and Hardware
22-Nov-15*
28-Nov-15
22-Nov-15
28-Nov-15
0
A9180
A9200
A9200
Interior glass partitions
28-Nov-15*
06-Dec-15
28-Nov-15
06-Dec-15
0
A9190
A9210
A9210
Wood wall panels
06-Dec-15*
11-Dec-15
06-Dec-15
11-Dec-15
0
A9200
A9220
A9220
Visual display surfaces
11-Dec-15*
16-Dec-15
11-Dec-15
16-Dec-15
0
A9210
A9230
A9230
Signage
16-Dec-15*
21-Dec-15
16-Dec-15
21-Dec-15
0
A9220
A9240
A9240
Wood ceiling
21-Dec-15*
24-Dec-15
21-Dec-15
24-Dec-15
0
A9230
A9250
A9250
Place Acoustical ceiling tiles
24-Dec-15*
04-Jan-16
24-Dec-15
04-Jan-16
0
A9240
A9260
A9260
Tiolet complartments
04-Jan-16*
11-Jan-16
04-Jan-16
11-Jan-16
0
A9250
A9270
A9270
Fire protection specialities
11-Jan-16*
17-Jan-16
11-Jan-16
17-Jan-16
0
A9260
A9290
A9280
Motorized projection screens
10-May-16
19-May-16
10-May-16
19-May-16
0
A9330
A9290
Window shades
17-Jan-16*
27-Jan-16
17-Jan-16
27-Jan-16
0
A9270
A9300
A9300
Wire mesh partitions
27-Jan-16*
03-Feb-16
27-Jan-16
03-Feb-16
0
A9290
A9310
A9310
Install lockers
03-Feb-16*
16-Feb-16
03-Feb-16
16-Feb-16
0
A9300
A9320
A9320
Install hood and walk-ins
16-Feb-16*
25-Feb-16
16-Feb-16
25-Feb-16
0
A9310
A9340
A9330
Install kitchen tiles
30-Apr-16
10-May-16
30-Apr-16
10-May-16
0
A9420
A9280
A9340
Install and setup food service equipment
25-Feb-16*
01-Mar-16
25-Feb-16
01-Mar-16
0
A9320
A9350
A9350
Glass wall folding partition
01-Mar-16*
06-Mar-16
01-Mar-16
06-Mar-16
0
A9340
A9360
A9360
Loading dock equipment
06-Mar-16*
18-Mar-16
06-Mar-16
18-Mar-16
0
A9350
A9370
A9370
Paint gym ceiling
18-Mar-16*
23-Mar-16
18-Mar-16
23-Mar-16
0
A9360
A9380
A9380
Gym equipment
23-Mar-16*
30-Mar-16
23-Mar-16
30-Mar-16
0
A9370
A9390
A9390
Gym dividers
30-Mar-16*
08-Apr-16
30-Mar-16
08-Apr-16
0
A9380
A9400
A9400
Install hardwood flooring
08-Apr-16*
15-Apr-16
08-Apr-16
15-Apr-16
0
A9390
A9410
A9410
Install collapsable belachers
15-Apr-16*
22-Apr-16
15-Apr-16
22-Apr-16
0
A9400
A9420
A9420
Hydraulic elevators
22-Apr-16*
30-Apr-16
22-Apr-16
30-Apr-16
0
A9410
A9330, A8720
A9430
Substantial milestone
16-Dec-15*
16-Dec-15
16-Dec-15
16-Dec-15
0
A7190
A7200
Footer 1
Page 5 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
A9440
Final Milestone
27-Oct-17*
28-Oct-17
27-Oct-17
28-Oct-17
0
A8780, A8810
S106
Erosion controls
02-Apr-14*
26-Apr-14
02-Apr-14
26-Apr-14
0
S86
S116, S206, S136
S116
Site Clearing and Strip Topsoil
27-Apr-14*
05-Jul-14
27-Apr-14
05-Jul-14
0
S106
S146, S176
S126
Temporary Basin and Swales
07-May-14*
10-Jun-14
29-Jul-14
01-Sep-14
83
S86
S216
S136
Site grading
05-May-14*
01-Sep-14
05-May-14
01-Sep-14
0
S106
S386
S146
Install Sediment Basin
06-Jul-14*
24-Aug-14
06-Jul-14
24-Aug-14
0
S116, S156
S156
Install Paving binder access roads and staging areas
12-May-14*
31-May-14
28-May-14
16-Jun-14
16
S86, S96
S166
Install additional staging areas
24-Jul-14*
22-Aug-14
24-Jul-14
22-Aug-14
0
S156
S176
Electrical ductbank
06-Jul-14*
24-Aug-14
06-Jul-14
24-Aug-14
0
S116
S186
Install Storm Sewer
12-May-14 A
27-Dec-14
27-Apr-14
27-Dec-14
0
S86
S236, S406
S196
Install Sanitary Sewer
30-Jun-14*
13-Aug-14
13-Sep-15
27-Oct-15
440
S156
S236
S196, S226, S146, SF55, S166 S396, T47
S206
Water system
05-May-14 A
17-Oct-14 A
26-Apr-14
26-Apr-14
S216
Concrete curbs
09-Aug-14*
16-Nov-14
02-Sep-14
10-Dec-14
24
S126, S226
S106 S376
S226
Site lighting
30-Jun-14*
08-Aug-14
24-Jul-14
01-Sep-14
24
S156
S216, S396
S236
Final Landscaping
29-Sep-15*
17-Nov-15
28-Oct-15
16-Dec-15
29
S186, S196, S276, S326
S416, S316, S336
S246
Place trees and shrubbery
20-Jan-15*
28-Feb-15
20-Jan-15
28-Feb-15
0
S386, S396, S376
S256
site linestripping and signage
14-Mar-16*
08-Apr-16
14-Mar-16
08-Apr-16
0
S266
S266
Concrete bumper blocks
08-Feb-16*
27-Feb-16
23-Feb-16
13-Mar-16
15
S306, S416
S256
S276
sidewalks and ramp concrete pour
26-May-15*
29-Jul-15
20-Jul-15
22-Sep-15
55
S296
S236, S346, S326, S366
S286
Unit Pavers
18-Sep-15*
02-Nov-15
19-Oct-15
03-Dec-15
31
S346, S366
S416, S306
S296
Exterior masonry seat walls and site walls
13-Apr-15*
12-May-15
20-Jun-15
19-Jul-15
68
S376
S276, S356
S306
Exterior site railings
03-Nov-15*
10-Dec-15
04-Dec-15
10-Jan-16
31
S286
S266, S416
S316
Position Site seating
18-Nov-15*
12-Dec-15
17-Dec-15
10-Jan-16
29
S236
S416
S326
Fiberglass bus stations
25-Aug-15*
28-Sep-15
23-Sep-15
27-Oct-15
29
S276
S236
S336
Install flagpoles
27-Mar-14
08-Apr-16
27-Mar-14
08-Apr-16
0
S236
S416
S346
Parking control equipment
24-Aug-15*
17-Sep-15
24-Sep-15
18-Oct-15
31
S276, S356
S286
S356
Retaining wall for landscaping
25-May-15*
13-Jun-15
04-Sep-15
23-Sep-15
102
S296
S346
S366
Timber guide railings
25-Aug-15*
13-Sep-15
29-Sep-15
18-Oct-15
35
S276
S286
S376
Retaining wall
17-Nov-14*
26-Dec-14
11-Dec-14
19-Jan-15
24
S216
S296, S246
S386
Site excavation
02-Sep-14*
19-Jan-15
02-Sep-14
19-Jan-15
0
S136
S246
S396
Install new topsoil
25-Aug-14 A
28-Sep-14
16-Dec-14
19-Jan-15
113
S406
Install Geo Exchange Field
28-Dec-14*
06-Apr-15
28-Dec-14
06-Apr-15
S416
Final placement of trees and shrubbery
13-Dec-15*
24-Jan-16
11-Jan-16
S86
Site Layout
28-Mar-14
26-Apr-14
28-Mar-14
S96
Install Rock Construction Entrance
27-Mar-14
10-Apr-14
SF25
Layout for foundation
08-Jul-14*
14-Jul-14
SF35
Footing excavation
04-Aug-14*
17-Sep-14
04-Aug-14
SF45
Tie Rebar
15-Jul-14*
03-Aug-14
SF55
Construct building pad
09-Jun-14*
29-Jun-14
SF65
Concrete foundation
04-Aug-14*
17-Sep-14
ST1004
Deep underground rough-in
08-Oct-14*
ST1014
Stone under slab rough-in
ST1024
Erect structural steel and deck
ST1034 ST1044
S176, S226
S246
0
S186
T57
22-Feb-16
29
S286, S236, S316, S336, S306
S266
26-Apr-14
0
A7080, A8970
S106, S126, S156, S186
13-May-14
27-May-14
47
A7080
S156
08-Jul-14
14-Jul-14
0
SF55
SF35, SF45, ST744
17-Sep-14
0
SF25, SF45
15-Jul-14
03-Aug-14
0
SF25
SF35, SF65
17-Jun-14
07-Jul-14
8
S156
SF25
04-Aug-14
17-Sep-14
0
SF45
ST1054, ST1224
22-Oct-14
18-Oct-14
01-Nov-14
10
ST984
ST994
15-Dec-14
26-Dec-14
16-Dec-14
27-Dec-14
1
ST784, ST1254
ST804, ST774
02-Nov-14
24-Nov-14
02-Nov-14
24-Nov-14
0
ST1234
ST1074, ST1254
Pour concrete slab on deck
22-Dec-14
22-Jan-15
22-Dec-14
22-Jan-15
0
ST1044
ST1064
Stone under slab
07-Dec-14
21-Dec-14
07-Dec-14
21-Dec-14
0
ST1234, ST1254
ST1064, ST1054, ST1034
ST1054
CMU walls
07-Feb-15
26-Feb-15
07-Feb-15
26-Feb-15
0
ST1064, ST1044, SF65
ST1204, ST1264, ST814
ST1064
Pour concrete slab on grade
23-Jan-15
06-Feb-15
23-Jan-15
06-Feb-15
0
ST1044, ST1034
ST1054
Footer 1
Page 6 of 8
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
ST1074
Cold formed metal framing and sheathing
25-Nov-14
19-Dec-14
25-Nov-14
19-Dec-14
0
ST1024
ST1094
ST1084
Spray urethane insulation
07-Jan-15
26-Jan-15
07-Jan-15
26-Jan-15
0
ST1094
ST1104, ST1144, A8820
ST1094
Install air membrane
20-Dec-14
06-Jan-15
20-Dec-14
06-Jan-15
0
ST1074
ST1084
ST1104
Wood blocking & sheathing on roof
27-Jan-15
05-Feb-15
27-Jan-15
05-Feb-15
0
ST1084
ST1114, ST1124
ST1114
Roof curbs
06-Feb-15
12-Feb-15
05-Mar-15
11-Mar-15
27
ST1104
ST1134
ST1124
Roof Drains
06-Feb-15
16-Feb-15
06-Feb-15
16-Feb-15
0
ST1104
ST1154
ST1134
Roof top equipment
13-Feb-15
17-Feb-15
12-Mar-15
16-Mar-15
27
ST1114
ST1184
ST1144
Insulated metal wall panels
27-Jan-15
15-Feb-15
17-Mar-15
05-Apr-15
49
ST1084
ST1194 ST1164
ST1154
Metal soffit and fascia
17-Feb-15
03-Mar-15
17-Feb-15
03-Mar-15
0
ST1124
ST1164
Roof metal edges
04-Mar-15
16-Mar-15
04-Mar-15
16-Mar-15
0
ST1154
ST1184
ST1174
Exterior Caulking
05-Apr-15
14-Apr-15
06-Apr-15
15-Apr-15
1
ST1204
ST1214
ST1184
Metal roof ladders
17-Mar-15
05-Apr-15
17-Mar-15
05-Apr-15
0
ST1164, ST1134
ST1194
ST1194
Aluminum windows & curtain walls
06-Apr-15
15-Apr-15
06-Apr-15
15-Apr-15
0
ST1144, ST1184
ST1214
ST1204
Masonry veneer
27-Feb-15
04-Apr-15
28-Feb-15
05-Apr-15
1
ST1054
ST1174
ST1214
Aluminum entrance doors/sliding doors
16-Apr-15
10-May-15
16-Apr-15
10-May-15
0
ST1174, ST1194
ST1224
Plumbing underground sanitary/storm rough-in
18-Sep-14*
27-Sep-14
18-Sep-14
27-Sep-14
0
SF65
ST1234, ST1244, ST984
ST1234
Waterproofing
13-Oct-14*
01-Nov-14
13-Oct-14
01-Nov-14
0
ST1224, ST1244
ST1044, ST1024, ST994
ST1244
Deep underground rough-in
28-Sep-14*
12-Oct-14
28-Sep-14
12-Oct-14
0
ST1224
ST1234
ST1254
Stone under slab rough-in
25-Nov-14
06-Dec-14
25-Nov-14
06-Dec-14
0
ST1024
ST1044, ST1014
ST1264
Layout stone veneer
27-Feb-15
27-Mar-15
27-Feb-15
27-Mar-15
0
ST1054
ST544
Erect structural steel and deck
22-Nov-14
14-Dec-14
16-Mar-15
08-Apr-15
114
ST754
ST594, ST774
ST554
Pour concrete slab on deck
23-Jan-15
23-Feb-15
06-May-15
07-Jun-15
103
ST564
ST584
ST564
Stone under slab
08-Jan-15
22-Jan-15
21-Apr-15
06-May-15
103
ST754, ST774
ST584, ST574, ST554
ST574
CMU walls
19-Mar-15
07-Apr-15
22-Jun-15
12-Jul-15
95
ST584, ST564, ST814
ST724
ST584
Pour concrete slab on grade
24-Feb-15
10-Mar-15
07-Jun-15
22-Jun-15
103
ST564, ST554
ST574
ST594
Cold formed metal framing and sheathing
15-Dec-14
08-Jan-15
08-Apr-15
03-May-15
114
ST544
ST614
ST604
Spray urethane insulation
27-Jan-15
15-Feb-15
21-May-15
10-Jun-15
114
ST614
ST624, ST664
ST614
Install air membrane
09-Jan-15
26-Jan-15
03-May-15
21-May-15
114
ST594
ST604
ST624
Wood blocking & sheathing on roof
16-Feb-15
25-Feb-15
10-Jun-15
20-Jun-15
114
ST604
ST634, ST644
ST634
Roof curbs
26-Feb-15
04-Mar-15
17-Jul-15
24-Jul-15
141
ST624
ST654
ST644
Roof Drains
26-Feb-15
08-Mar-15
20-Jun-15
01-Jul-15
114
ST624
ST674
ST654
Roof top equipment
05-Mar-15
09-Mar-15
24-Jul-15
29-Jul-15
141
ST634
ST704
ST664
Insulated metal wall panels
16-Feb-15
07-Mar-15
29-Jul-15
18-Aug-15
163
ST604
ST714
ST674
Metal soffit and fascia
09-Mar-15
23-Mar-15
01-Jul-15
16-Jul-15
114
ST644
ST684
ST684
Roof metal edges
24-Mar-15
05-Apr-15
16-Jul-15
29-Jul-15
114
ST674
ST704
ST694
Exterior Caulking
15-May-15
24-May-15
18-Aug-15
28-Aug-15
95
ST724
ST734
ST704
Metal roof ladders
06-Apr-15
25-Apr-15
29-Jul-15
18-Aug-15
114
ST684, ST654
ST714
ST714
Aluminum windows & curtain walls
26-Apr-15
05-May-15
18-Aug-15
28-Aug-15
114
ST664, ST704
ST734
ST724
Masonry veneer
08-Apr-15
14-May-15
12-Jul-15
18-Aug-15
95
ST574
ST694
ST734
Aluminum entrance doors/sliding doors
25-May-15
18-Jun-15
28-Aug-15
22-Sep-15
95
ST694, ST714
A7700
ST744
Plumbing underground sanitary/storm rough-in
08-Oct-14*
17-Oct-14
30-Jan-15
09-Feb-15
114
SF25, ST984
ST754, ST764
ST754
Waterproofing
02-Nov-14*
21-Nov-14
24-Feb-15
16-Mar-15
114
ST744, ST764
ST564, ST544
ST764
Deep underground rough-in
18-Oct-14*
01-Nov-14
09-Feb-15
24-Feb-15
114
ST744
ST754
ST774
Stone under slab rough-in
27-Dec-14
07-Jan-15
09-Apr-15
21-Apr-15
103
ST784
Erect structural steel and deck
22-Nov-14
14-Dec-14
22-Nov-14
14-Dec-14
0
ST794
Pour concrete slab on deck
11-Jan-15
11-Feb-15
12-Jan-15
12-Feb-15
ST804
Stone under slab
27-Dec-14
10-Jan-15
28-Dec-14
11-Jan-15
ST814
CMU walls
27-Feb-15
18-Mar-15
28-Feb-15
19-Mar-15
1
Footer 1
Page 7 of 8
ST544, ST1014
ST564
ST994
ST834, ST1014
1
ST804
ST824
1
ST994, ST1014
ST824, ST814, ST794
ST824, ST804, ST1054
ST964, ST574
MONROE CAMPUS... Report Date 14-Apr-14 20:57
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
SR-06 Schedule Report - Predecessors Successors Activity ID
Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
Predecessors
Successors
ST824
Pour concrete slab on grade
12-Feb-15
26-Feb-15
13-Feb-15
27-Feb-15
1
ST804, ST794
ST814
ST834
Cold formed metal framing and sheathing
15-Dec-14
08-Jan-15
15-Dec-14
08-Jan-15
0
ST784
ST854
ST844
Spray urethane insulation
27-Jan-15
15-Feb-15
27-Jan-15
15-Feb-15
0
ST854
ST864, ST904
ST854
Install air membrane
09-Jan-15
26-Jan-15
09-Jan-15
26-Jan-15
0
ST834
ST844
ST864
Wood blocking & sheathing on roof
16-Feb-15
25-Feb-15
16-Feb-15
25-Feb-15
0
ST844
ST874, ST884
ST874
Roof curbs
26-Feb-15
04-Mar-15
25-Mar-15
31-Mar-15
27
ST864
ST894
ST884
Roof Drains
26-Feb-15
08-Mar-15
26-Feb-15
08-Mar-15
0
ST864
ST914
ST894
Roof top equipment
05-Mar-15
09-Mar-15
01-Apr-15
05-Apr-15
27
ST874
ST944
ST904
Insulated metal wall panels
16-Feb-15
07-Mar-15
06-Apr-15
25-Apr-15
49
ST844
ST954
ST914
Metal soffit and fascia
09-Mar-15
23-Mar-15
09-Mar-15
23-Mar-15
0
ST884
ST924
ST924
Roof metal edges
24-Mar-15
05-Apr-15
24-Mar-15
05-Apr-15
0
ST914
ST944
ST934
Exterior Caulking
25-Apr-15
04-May-15
26-Apr-15
05-May-15
1
ST964
ST974
ST944
Metal roof ladders
06-Apr-15
25-Apr-15
06-Apr-15
25-Apr-15
0
ST924, ST894
ST954, A7090
ST954
Aluminum windows & curtain walls
26-Apr-15
05-May-15
26-Apr-15
05-May-15
0
ST904, ST944
ST974
ST964
Masonry veneer
19-Mar-15
24-Apr-15
20-Mar-15
25-Apr-15
1
ST814
ST934
ST974
Aluminum entrance doors/sliding doors
06-May-15
30-May-15
06-May-15
30-May-15
0
ST934, ST954
ST984
Plumbing underground sanitary/storm rough-in
28-Sep-14*
07-Oct-14
08-Oct-14
17-Oct-14
10
ST1224
ST994, ST1004, ST744
ST994
Waterproofing
02-Nov-14*
21-Nov-14
02-Nov-14
21-Nov-14
0
ST984, ST1004, ST1234
ST804, ST784
T27
Install Temporary Fence
24-Jun-14*
06-Jul-14
24-Jun-14
06-Jul-14
0
T37
T87, T67
T37
Mobilize Job Trailers
14-Jun-14*
24-Jun-14
14-Jun-14
24-Jun-14
0
T77
T27
T47
Provide temporary electric and lighting to buildings
25-Aug-14*
23-Sep-14
25-Aug-14
23-Sep-14
0
T67, S176
T57
Provide temporary heat
07-Apr-15*
16-May-15
07-Apr-15
16-May-15
0
S406
T67
Temporary utility poles
06-Jul-14*
21-Jul-14
10-Aug-14
24-Aug-14
34
T27
T47
T77
Site Preparation
04-Jun-14
14-Jun-14
04-Jun-14
14-Jun-14
0
A7080
T37
T87
Temporary electric to trailers
06-Jul-14*
16-Jul-14
06-Jul-14
16-Jul-14
0
T27
Footer 1
Page 8 of 8
MONROE CAMPUS... Activ Activity Name ID
Project: MONRO WBS: Volume 1
BASELINE nal Start
vity Qtr 4, 2013
ion 479 10-Oct-13 A 47 10-Oct-13
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
78 10-Oct-13 0%
List A of drawings
21 27-Dec-13 0%
Prevailing wage documents
Electrical A Constructio
7 17-Jan-14 0%
Electrical Construction bid form
Plumbing A constructio
6 17-Jan-14 0%
Plumbing construction bid form
Hvac A construction bid
6 17-Jan-14 0%
Hvac construction bid
General A construction
7 17-Jan-14 0%
General construction bid form
Instruction A to bidders
13 17-Jan-14 0%
Qualification A question
6 17-Jan-14 0%
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
Qtr 3, 2017
2017
Instruction to bidders Qualification questionnaire
25 17-Jan-14 0%
invitation to bid
5 17-Jan-14 0%
Sample Insurance certificates
11 10-Feb-14 0%
Bid security
Safety A and health ma
4 10-Feb-14 0%
Safety and health management plan
Standard A General co
1 10-Feb-14 0%
Standard General conditions
Payment A bond
1 10-Feb-14 0%
Payment bond
Performance A bond
1 10-Feb-14 0%
Performance bond
AIA A document a132
1 10-Feb-14 0%
AIA document a132
Non A collusion affidavit
1 10-Feb-14 0%
Non collusion affidavit
47 10-Oct-13
Alteration A Project pro
4 10-Oct-13 0%
Contract A Modification
51 10-Oct-13 0%
Leed A & sustainable d
7 10-Oct-13 0%
Testing A for indoor air
19 10-Oct-13 0%
Testing for indoor air quality
Cutting A and patching
21 10-Oct-13 0%
Cutting and patching
LEED A submital Form
38 29-Oct-13 0%
Coordination A drawings
17 27-Dec-13 0%
Field A engineering
10 27-Dec-13 0%
Product A requirements
39 10-Feb-14 0%
Unit A prices
43 10-Feb-14 0%
Payement A procedures
00 11-Feb-14 0%
Demonstration A & train
330 11-Feb-14 0%
Construction A waste m
868 11-Feb-14 0%
Summary A
12 21-Feb-14 0%
References A
14 05-Mar-14 0%
Quality A requirements
49 05-Mar-14 0%
Submittal A form
46 05-Mar-14 0%
Alternates A
12 05-Mar-14 0%
Quantity A allowances
26 05-Mar-14 0%
Work A restrictions
46 05-Mar-14 0%
Alteration Project procedures Contract Modification Leed & sustainable design requirements
LEED submital Form Coordination drawings Field engineering Product requirements Unit prices Payement procedures Demonstration & training Construction waste mangement Summary References Quality requirements Submittal form Alternates Quantity allowances Work restrictions
Summary A of multiple c
6 05-Mar-14 0%
Summary of multiple contracts
General A Commission
5 05-Mar-14 0%
General Commissioning requirements
Start A milestone
1 27-Mar-14* 0%
Execution A
Qtr 4, 2015
List of drawings
8 17-Jan-14 0%
WBS: Division 01 G
Qtr 3, 2015
Geotechnical investigation
Prevailing A wage docu
Bid A security
Qtr 2, 2015
21-Feb-14, WBS: Division 00 bidding & contract requirements
Geotechnical A investig
Sample A Insurance ce
Qtr 1, 2015
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct %
WBS: Division 00 b 135 10-Oct-13
invitation A to bid
Qtr 4, 2014
14-Apr-14 20:55
00 09-Apr-14
Start milestone
0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Execution Summary
Page 1 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE vity Qtr 4, 2013
Project A Management
ion 996 18-Apr-14
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct % 0% Project Management & coordination
Construction A Progres
966 18-May-14 0%
Construction Progress documentation
Web A based project m
955 28-May-14 0%
Web based project management
Temporary A Facilities &
946 07-Jun-14 0%
Temporary Facilities & controls
Operation A and mainte
850 11-Sep-14 0%
Operation and maintenance data
Project A record docum
666 14-Mar-15 0% 1 16-Dec-15* 0%
Checklist A enrollment
9 30-Apr-16
Checklist A classroom
9 26-Sep-16 0% 9 30-Dec-16 0%
Close A out procedures
79 08-Jan-17 0%
Demobilize A job trailers
176 08-Jan-17 0%
WBS: Sitework
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
Qtr 3, 2017
Project record documents Substantial milestone
0%
Checklist A student life
Final A Milestone
Qtr 2, 2014
2017
nal Start
Substantial A milestone
Qtr 1, 2014
14-Apr-14 20:55
Checklist enrollment building Checklist classroom roe Checklist student life building Close out procedures Demobilize job traile
1 27-Oct-17* 0% 744 27-Mar-14
08-Apr-16, WBS: Sitework
WBS: Division 33: U 337 05-May-14 Water system
120 05-May-14 00%
Install Storm Sewer
245 12-May-14 0%
Install Sanitary Sewer
45 30-Jun-14* 0%
Site lighting
40 30-Jun-14* 0%
Electrical ductbank
50 06-Jul-14* 0%
Install Geo Exchange
100 28-Dec-14* 0%
06-Apr-15, WBS: Division 33: Utilities Water system Install Storm Sewer Install Sanitary Sewer Site lighting Electrical ductbank Install Geo Exchange Field
WBS: Division 10: S 744 27-Mar-14
08-Apr-16, WBS: Division 10: Specialties
Install flagpoles
744 27-Mar-14 0%
Install A all site utilties
70 27-Mar-14* 0%
Install flagpoles
Parking control equip
25 24-Aug-15* 0%
Parking control equipment
Timber guide railings
20 25-Aug-15* 0%
Timber guide railings
Exterior site railings
38 03-Nov-15* 0%
site linestripping and
26 14-Mar-16* 0%
Install all site utilties
Exterior site railings site linestripping and signage
WBS: Division 31: E 298 28-Mar-14
19-Jan-15, WBS: Division 31: Earthwork
Site Layout
30 28-Mar-14 0%
Site Layout
Erosion controls
25 02-Apr-14* 0%
Erosion controls
Site Clearing and Stri
70 27-Apr-14* 0%
Site grading
120 05-May-14* 0%
Temporary Basin and
35 07-May-14* 0%
Install Sediment Basin
50 06-Jul-14* 0%
Site excavation
140 02-Sep-14* 0%
Site Clearing and Strip Topsoil Site grading Temporary Basin and Swales Install Sediment Basin Site excavation
WBS: Division 32: S 703 27-Mar-14 Install Rock Construc
15 27-Mar-14 0%
Install Paving binder a
20 12-May-14* 0%
27-Feb-16, WBS: Division 32: Site Improvements Install Rock Construction Entrance Install Paving binder access roads and staging areas
Install additional stagi
30 24-Jul-14* 0%
Concrete curbs
100 09-Aug-14* 0%
Install new topsoil
35 25-Aug-14 0%
Retaining wall
40 17-Nov-14* 0%
Place trees and shru
40 20-Jan-15* 0%
Exterior masonry sea
30 13-Apr-15* 0%
Exterior masonry seat walls and site walls
Retaining wall for land
20 25-May-15* 0%
Retaining wall for landscaping
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Install additional staging areas Concrete curbs Install new topsoil Retaining wall Place trees and shrubbery
Summary
Page 2 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE nal Start
vity Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
14-Apr-14 20:55 Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
Qtr 3, 2017
2017
sidewalks and ramp c
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 65 26-May-15* 0% sidewalks and ramp concrete pour
Fiberglass bus statio
35 25-Aug-15* 0%
Fiberglass bus stations
Unit Pavers
46 18-Sep-15* 0%
Unit Pavers
Final Landscaping
50 29-Sep-15* 0%
Position Site seating
25 18-Nov-15* 0%
Final placement of tre
43 13-Dec-15* 0%
Concrete bumper blo
20 08-Feb-16* 0%
WBS: Foundatio Construct building pad Layout for foundation
Final Landscaping Position Site seating Final placement of trees and shrubbery Concrete bumper blocks
101 09-Jun-14
17-Sep-14, WBS: Foundation
21 09-Jun-14* 0%
Construct building pad
7 08-Jul-14* 0%
Layout for foundation
Tie Rebar
20 15-Jul-14* 0%
Footing excavation
45 04-Aug-14* 0%
Footing excavation
Concrete foundation
45 04-Aug-14* 0%
Concrete foundation
WBS: Temporar
Tie Rebar
346 04-Jun-14
16-May-15, WBS: Temporary Construction
Site Preparation
10 04-Jun-14 0%
Mobilize Job Trailers
10 14-Jun-14* 0%
Install Temporary Fen
12 24-Jun-14* 0%
Install Temporary Fence
Temporary utility poles
15 06-Jul-14* 0%
Temporary utility poles
Temporary electric to
10 06-Jul-14* 0%
Provide temporary ele
30 25-Aug-14* 0%
Provide temporary he
40 07-Apr-15* 0%
WBS: Building 1
Site Preparation Mobilize Job Trailers
Temporary electric to trailers Provide temporary electric and lighting to buildings Provide temporary heat
609 18-Sep-14
19-May-16, WBS: Building 1 ( Administration building )
WBS: Structure an and 235 18-Sep-14 WBS: Division 3
10-May-15, WBS: Structure and Rough In
142 18-Sep-14
06-Feb-15, WBS: Division 3
Plumbing undergroun
10 18-Sep-14* 0%
Deep underground ro
15 28-Sep-14* 0%
Stone under slab rou
12 25-Nov-14 0%
Stone under slab
15 07-Dec-14 0%
Pour concrete slab o
32 22-Dec-14 0%
Pour concrete slab o
15 23-Jan-15 0%
WBS: Division 8
Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade
35 06-Apr-15
10-May-15, WBS: Division 8
Aluminum windows &
10 06-Apr-15
0%
Aluminum entrance d
25 16-Apr-15
0%
WBS: Division 4
Plumbing underground sanitary/storm rough-in
Aluminum windows & curtain walls Aluminum entrance doors/sliding doors
57 07-Feb-15
04-Apr-15, WBS: Division 4
CMU walls
20 07-Feb-15 0%
Masonry veneer
37 27-Feb-15 0%
Masonry veneer
29 27-Feb-15 0%
Layout stone veneer
Layout stone veneer WBS: Division 5
155 02-Nov-14
Erect structural steel
23 02-Nov-14 0%
Cold formed metal fra
25 25-Nov-14 0%
Metal roof ladders WBS: Division 7
CMU walls
05-Apr-15, WBS: Division 5 Erect structural steel and deck Cold formed metal framing and sheathing
20 17-Mar-15 0%
Metal roof ladders
184 13-Oct-14
Waterproofing
20 13-Oct-14* 0%
Install air membrane
18 20-Dec-14 0%
Spray urethane insula
20 07-Jan-15 0%
Wood blocking & she
10 27-Jan-15 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
14-Apr-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Summary
Page 3 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Insulated metal wall p
BASELINE nal Start
vity Qtr 4, 2013
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
7 06-Feb-15 0%
Roof Drains
11 06-Feb-15 0% 5 13-Feb-15 0%
Metal soffit and fascia
13 04-Mar-15 0%
Roof metal edges
Exterior Caulking
10 05-Apr-15
WBS: Finishes
478 27-Jan-15
0%
4 01-Feb-15* 0%
Install railings
13 05-Feb-15* 0% 9 18-Feb-15* 0% 5 27-Feb-15* 0%
Ceramic A and porcela
7 04-Mar-15* 0%
Painting A
9 11-Mar-15* 0%
Wall A coverings
6 20-Mar-15* 0% 10 02-Apr-15* 0%
PC A overhead pipe
10 12-Apr-15* 0%
Qtr 3, 2017
2017
Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe
5 22-Apr-15* 0%
PC insulation
PC A drop sprinkler hea
10 27-Apr-15* 0%
PC drop sprinkler head
PC A casework fixtures
5 07-May-15* 0%
PC casework fixtures
PC A toilet fixtures
5 12-May-15* 0%
HC A hangers
5 17-May-15* 0%
HC A pipe install
7 22-May-15* 0%
HC A duct install
5 29-May-15* 0%
PC toilet fixtures HC hangers HC pipe install HC duct install
HC A ATC rough-in
11 03-Jun-15* 0%
HC A GRD install
15 14-Jun-15* 0%
HC A equipment and fin
12 29-Jun-15* 0%
HC A kitchen equipmen
10 11-Jul-15*
EC A rough-in walls
12 21-Jul-15* 0%
EC A overhead rough-in
14 02-Aug-15* 0%
EC A cable tray
14 15-Aug-15* 0%
EC cable tray
EC A wiring
9 30-Aug-15* 0%
EC wiring
EC A light fixtures
8 07-Sep-15* 0%
EC A wring devices
5 15-Sep-15* 0%
EC A fire alarm and sec
6 20-Sep-15* 0%
EC A kitchen equipmen
10 26-Sep-15* 0%
EC A hook ups and con
5 06-Oct-15* 0%
Casework/millwork A
8 11-Oct-15* 0%
Resilent A tile base and
8 19-Oct-15* 0%
Resilent tile base and floor
8 27-Oct-15* 0%
Seamless vinyl flooring
Carpet A tiles
Qtr 2, 2017
Interior H.M frames
7 26-Mar-15* 0%
PC A AG san/rw
Seamless A vinyl floorin
Qtr 1, 2017
19-May-16, WBS: Finishes Metal stairs
Caulking A
PC A insulation
Qtr 4, 2016
Exterior Caulking
5 27-Jan-15* 0%
Drywall A and spackliing
Acoustical A ceiling grid
Qtr 3, 2016
Roof top equipment
Roof metal edges
Interior A H.M frames
Qtr 2, 2016
Roof Drains
15 17-Feb-15 0%
Install A railings
Qtr 1, 2016
Roof curbs
Metal soffit and fascia
Metal A stairs
Qtr 4, 2015
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 20 27-Jan-15 0% Insulated metal wall panels
Roof curbs Roof top equipment
Qtr 1, 2014
14-Apr-14 20:55
HC ATC rough-in HC GRD install HC equipment and final connections
0%
HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 04-Nov-15* 0%
Install A rubber stairs, t
7 15-Nov-15* 0%
Doors A and Hardware
6 22-Nov-15* 0%
Interior A glass partitions
8 28-Nov-15* 0%
Wood A wall panels
5 06-Dec-15* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Summary
Page 4 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Visual A display surface
BASELINE nal Start
vity Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
14-Apr-14 20:55 Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
5 16-Dec-15* 0%
Signage
Wood A ceiling
3 21-Dec-15* 0%
Wood ceiling
Place A Acoustical ceilin
11 24-Dec-15* 0%
Tiolet A complartments
8 04-Jan-16* 0%
Fire A protection specia
6 11-Jan-16* 0%
Wire A mesh partitions Install A lockers
Qtr 3, 2016
5 25-Feb-16* 0%
Wire mesh partitions Install lockers Install hood and walk-ins Install and setup food service equipment
5 01-Mar-16* 0%
Glass wall folding partition
Loading A dock equipm
12 06-Mar-16* 0%
Loading dock equipment
Paint A gym ceiling
5 18-Mar-16* 0%
Paint gym ceiling
Gym A equipment
7 23-Mar-16* 0%
Gym equipment
Gym A dividers
9 30-Mar-16* 0%
Gym dividers
Install A hardwood floor
7 08-Apr-16* 0%
Install A collapsable bel
6 15-Apr-16* 0%
Hydraulic A elevators
8 22-Apr-16* 0% 10 30-Apr-16
Install hardwood flooring Install collapsable belachers Hydraulic elevators
0%
Install kitchen tiles
9 10-May-16 0%
Motorized projection screens
843 28-Sep-14
18-Jan-17, WBS: Building 2 (Student Life)
WBS: Structure an and 245 28-Sep-14
30-May-15, WBS: Structure and Rough In
152 28-Sep-14
26-Feb-15, WBS: Division 3
Plumbing undergroun
10 28-Sep-14* 0%
Deep underground ro
15 08-Oct-14* 0%
Stone under slab rou
12 15-Dec-14 0%
Stone under slab
15 27-Dec-14 0%
Pour concrete slab o
32 11-Jan-15
Pour concrete slab o
15 12-Feb-15 0%
WBS: Division 8
Stone under slab rough-in Stone under slab Pour concrete slab on deck Pour concrete slab on grade 30-May-15, WBS: Division 8
Aluminum entrance d
25 06-May-15 0%
0%
Aluminum windows & curtain walls Aluminum entrance doors/sliding doors
57 27-Feb-15
24-Apr-15, WBS: Division 4
CMU walls
20 27-Feb-15 0%
Masonry veneer
37 19-Mar-15 0%
CMU walls Masonry veneer
155 22-Nov-14
25-Apr-15, WBS: Division 5
Erect structural steel
23 22-Nov-14 0%
Cold formed metal fra
25 15-Dec-14 0%
Metal roof ladders
20 06-Apr-15
WBS: Division 7
184 02-Nov-14
Erect structural steel and deck Cold formed metal framing and sheathing
0%
Waterproofing
20 02-Nov-14* 0%
Install air membrane
18 09-Jan-15 0%
Spray urethane insula
20 27-Jan-15 0%
Wood blocking & she
10 16-Feb-15 0%
Insulated metal wall p
20 16-Feb-15 0%
Roof curbs
Deep underground rough-in
35 26-Apr-15 10 26-Apr-15
WBS: Division 5
Plumbing underground sanitary/storm rough-in
0%
Aluminum windows & WBS: Division 4
2017
Window shades
Glass A wall folding par
WBS: Division 3
Qtr 3, 2017
Fire protection specialities
7 27-Jan-16* 0%
Install A and setup food
WBS: Building 2
Qtr 2, 2017
Tiolet complartments
13 03-Feb-16* 0% 9 16-Feb-16* 0%
Motorized A projection
Qtr 1, 2017
Place Acoustical ceiling tiles
10 17-Jan-16* 0%
Install A hood and walk
Install A kitchen tiles
Qtr 4, 2016
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 5 11-Dec-15* 0% Visual display surfaces
Signage A
Window A shades
Qtr 2, 2016
Metal roof ladders 04-May-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels
7 26-Feb-15 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Roof curbs Summary
Page 5 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Roof Drains Roof top equipment
BASELINE nal Start
vity Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
14-Apr-14 20:55
Qtr 2, 2015
Qtr 3, 2015
5 05-Mar-15 0%
Metal soffit and fascia
Roof metal edges
13 24-Mar-15 0%
Roof metal edges
Exterior Caulking
10 25-Apr-15
WBS: Finishes
633 26-Apr-15
Interior A H.M frames
0%
Qtr 4, 2016
4 01-May-15* 0%
Install railings
13 05-May-15* 0%
Caulking A
5 27-May-15* 0%
Ceramic A and porcela
7 01-Jun-15* 0%
Painting A
9 08-Jun-15* 0%
Wall A coverings
6 17-Jun-15* 0%
Acoustical A ceiling grid
7 23-Jun-15* 0%
PC A AG san/rw
10 30-Jun-15* 0%
PC A overhead pipe
10 10-Jul-15* 0%
Qtr 2, 2017
Qtr 3, 2017
2017
Interior H.M frames Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe
5 17-Dec-15* 0%
PC insulation
PC A drop sprinkler hea
10 22-Dec-15* 0%
PC drop sprinkler head
PC A casework fixtures
5 01-Jan-16* 0%
PC casework fixtures
PC A toilet fixtures
5 06-Jan-16* 0%
PC A kitchen equipmen
6 11-Jan-16* 0%
HC A hangers
5 17-Jan-16* 0%
HC A pipe install
7 22-Jan-16* 0%
PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install
5 29-Jan-16* 0%
HC duct install
HC A ATC rough-in
11 03-Feb-16* 0%
HC A GRD install
15 14-Feb-16* 0%
HC A equipment and fin
12 28-Feb-16* 0%
HC A kitchen equipmen
10 11-Mar-16* 0%
EC A rough-in walls
12 21-Mar-16* 0%
EC A overhead rough-in
14 02-Apr-16* 0%
EC A cable tray
14 16-Apr-16* 0%
EC cable tray
EC A wiring
9 30-Apr-16* 0%
EC wiring
EC A light fixtures
8 08-May-16* 0%
EC A wring devices
5 16-May-16* 0%
EC A fire alarm and sec
6 21-May-16* 0%
EC A kitchen equipmen
10 28-May-16* 0%
EC A hook ups and con
5 07-Jun-16* 0%
Casework/millwork A
8 12-Jun-16* 0%
Resilent A tile base and
8 19-Jun-16* 0%
Resilent tile base and floor
Seamless A vinyl floorin
8 27-Jun-16* 0%
Seamless vinyl flooring
Carpet A tiles
Qtr 1, 2017
18-Jan-17, WBS: Finishes Metal stairs
9 18-May-15* 0%
HC A duct install
Qtr 3, 2016
Exterior Caulking
5 26-Apr-15* 0%
Drywall A and spackliing
PC A insulation
Qtr 2, 2016
Roof top equipment
15 09-Mar-15 0%
Install A railings
Qtr 1, 2016
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 11 26-Feb-15 0% Roof Drains
Metal soffit and fascia
Metal A stairs
Qtr 4, 2015
HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 05-Jul-16* 0%
Install A rubber stairs, t
7 16-Jul-16* 0%
Doors A and Hardware
6 23-Jul-16* 0%
Interior A glass partitions
8 29-Jul-16* 0%
Wood A wall panels
5 07-Aug-16* 0%
Visual A display surface
5 12-Aug-16* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Summary
Page 6 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Signage A Wood A ceiling
BASELINE nal Start
vity Qtr 4, 2013
Tiolet A complartments
8 04-Sep-16* 0%
Fire A protection specia
6 12-Sep-16* 0%
Install A lockers
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
3 22-Aug-16* 0% 11 25-Aug-16* 0%
Wire A mesh partitions
Qtr 2, 2014
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
Place Acoustical ceiling tiles Tiolet complartments Fire protection specialities Window shades
7 28-Sep-16* 0%
Wire mesh partitions
13 05-Oct-16* 0% 9 18-Oct-16* 0%
Install A and setup food
5 27-Oct-16* 0%
Glass A wall folding par
5 01-Nov-16* 0%
Loading A dock equipm
12 06-Nov-16* 0%
Install lockers Install hood and walk-ins Install and setup food service equipment Glass wall folding partition Loading dock equipment
Paint A gym ceiling
5 18-Nov-16* 0%
Paint gym ceiling
Gym A equipment
7 23-Nov-16* 0%
Gym equipment
Gym A dividers
9 30-Nov-16* 0%
Gym dividers
Install A hardwood floor
7 09-Dec-16* 0%
Install A collapsable bel
6 16-Dec-16* 0%
Hydraulic A elevators
8 22-Dec-16* 0%
Hydraulic elevators
Install A kitchen tiles
10 30-Dec-16* 0%
Install kitchen tiles
WBS: Building 3
Install hardwood flooring Install collapsable belachers
9 09-Jan-17* 0%
Motorized projection screens
719 08-Oct-14
26-Sep-16, WBS: Building 3 (ClassRooms)
WBS: Structure an and 254 08-Oct-14 WBS: Division 4
18-Jun-15, WBS: Structure and Rough In
57 19-Mar-15
14-May-15, WBS: Division 4
CMU walls
20 19-Mar-15 0%
Masonry veneer
37 08-Apr-15
WBS: Division 5
CMU walls
0%
Masonry veneer
155 22-Nov-14
25-Apr-15, WBS: Division 5
Erect structural steel
23 22-Nov-14 0%
Cold formed metal fra
25 15-Dec-14 0%
Metal roof ladders
20 06-Apr-15
WBS: Division 7
204 02-Nov-14
Erect structural steel and deck Cold formed metal framing and sheathing
0%
Waterproofing
20 02-Nov-14* 0%
Install air membrane
18 09-Jan-15 0%
Spray urethane insula
20 27-Jan-15 0%
Wood blocking & she
10 16-Feb-15 0%
Insulated metal wall p
20 16-Feb-15 0%
Roof curbs
7 26-Feb-15 0%
Roof Drains
11 26-Feb-15 0%
Roof top equipment
Metal roof ladders 24-May-15, WBS: Division 7 Waterproofing Install air membrane Spray urethane insulation Wood blocking & sheathing on roof Insulated metal wall panels Roof curbs Roof Drains
5 05-Mar-15 0%
Roof top equipment
Metal soffit and fascia
15 09-Mar-15 0%
Metal soffit and fascia
Roof metal edges
13 24-Mar-15 0%
Roof metal edges
Exterior Caulking
10 15-May-15 0%
WBS: Division 3
2017
Wood ceiling
10 18-Sep-16* 0%
Install A hood and walk
Motorized A projection
Qtr 3, 2017
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 5 17-Aug-16* 0% Signage
Place A Acoustical ceilin
Window A shades
Qtr 1, 2014
14-Apr-14 20:55
Exterior Caulking
154 08-Oct-14
Plumbing undergroun
10 08-Oct-14* 0%
Deep underground ro
15 18-Oct-14* 0%
Stone under slab rou
12 27-Dec-14 0%
Stone under slab
15 08-Jan-15 0%
Pour concrete slab o
32 23-Jan-15 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
10-Mar-15, WBS: Division 3 Plumbing underground sanitary/storm rough-in Deep underground rough-in Stone under slab rough-in Stone under slab Pour concrete slab on deck Summary
Page 7 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID Pour concrete slab o WBS: Division 8 Aluminum windows &
BASELINE nal Start
vity Qtr 4, 2013
54 26-Apr-15 10 26-Apr-15
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
25 25-May-15 0% 465 19-Jun-15
Qtr 1, 2017
Qtr 2, 2017
Qtr 3, 2017
2017
Aluminum windows & curtain walls Aluminum entrance doors/sliding doors 26-Sep-16, WBS: Finishes
Metal A stairs
5 19-Jun-15* 0%
Install A railings
4 24-Jun-15* 0%
Metal stairs Install railings
13 28-Jun-15* 0%
Drywall A and spackliing
9 11-Jul-15*
Caulking A
5 20-Jul-15* 0%
Ceramic A and porcela
7 25-Jul-15* 0%
Painting A
9 01-Aug-15* 0%
Wall A coverings
6 10-Aug-15* 0%
Acoustical A ceiling grid
7 16-Aug-15* 0%
Interior H.M frames
0%
PC A AG san/rw
10 23-Aug-15* 0%
PC A overhead pipe
10 02-Sep-15* 0%
Drywall and spackliing Caulking Ceramic and porcelain wall/floor tiles Painting Wall coverings Acoustical ceiling grid PC AG san/rw PC overhead pipe
5 12-Sep-15* 0%
PC insulation
PC A drop sprinkler hea
10 17-Sep-15* 0%
PC drop sprinkler head
PC A casework fixtures
5 27-Sep-15* 0%
PC casework fixtures
PC A toilet fixtures
5 02-Oct-15* 0%
PC A kitchen equipmen
6 07-Oct-15* 0%
HC A hangers
5 13-Oct-15* 0%
HC A pipe install
7 18-Oct-15* 0%
HC A duct install
5 25-Oct-15* 0%
PC toilet fixtures PC kitchen equipment hookups HC hangers HC pipe install HC duct install
HC A ATC rough-in
11 30-Oct-15* 0%
HC A GRD install
15 10-Nov-15* 0%
HC A equipment and fin
12 25-Nov-15* 0%
HC A kitchen equipmen
10 07-Dec-15* 0%
EC A rough-in walls
12 17-Dec-15* 0%
EC A overhead rough-in
14 29-Dec-15* 0%
EC A cable tray
14 11-Jan-16* 0%
EC cable tray
EC A wiring
9 26-Jan-16* 0%
EC wiring
EC A light fixtures
8 03-Feb-16* 0%
EC A wring devices
5 11-Feb-16* 0%
EC A fire alarm and sec
6 16-Feb-16* 0%
EC A kitchen equipmen
10 22-Feb-16* 0%
EC A hook ups and con
5 03-Mar-16* 0%
Casework/millwork A
8 08-Mar-16* 0%
Resilent A tile base and
8 16-Mar-16* 0%
Resilent tile base and floor
Seamless A vinyl floorin
8 24-Mar-16* 0%
Seamless vinyl flooring
Carpet A tiles
Qtr 4, 2016
18-Jun-15, WBS: Division 8 0%
Aluminum entrance d
PC A insulation
Qtr 2, 2014
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 15 24-Feb-15 0% Pour concrete slab on grade
WBS: Finishes
Interior A H.M frames
Qtr 1, 2014
14-Apr-14 20:55
HC ATC rough-in HC GRD install HC equipment and final connections HC kitchen equipment and hookups EC rough-in walls EC overhead rough-in
EC light fixtures EC wring devices EC fire alarm and security EC kitchen equipment and hookups EC hook ups and connections Casework/millwork
11 01-Apr-16* 0%
Install A rubber stairs, t
7 12-Apr-16* 0%
Doors A and Hardware
6 19-Apr-16* 0%
Interior A glass partitions
8 25-Apr-16* 0%
Wood A wall panels
5 03-May-16* 0%
Visual A display surface
5 08-May-16* 0%
Signage A
5 13-May-16* 0%
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Carpet tiles Install rubber stairs, treads and landings Doors and Hardware Interior glass partitions Wood wall panels Visual display surfaces Signage Summary
Page 8 of 9
TASK filter: All Activities Š Oracle Corporation
MONROE CAMPUS... Activ Activity Name ID
BASELINE nal Start
vity Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
14-Apr-14 20:55 Qtr 3, 2015
Qtr 4, 2015
Qtr 1, 2016
Qtr 2, 2016
Qtr 3, 2016
Qtr 4, 2016
Qtr 1, 2017
Qtr 2, 2017
Qtr 3, 2017
2017
Wood A ceiling
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ion % 3 18-May-16* 0% Wood ceiling
Place A Acoustical ceilin
11 21-May-16* 0%
Tiolet A complartments
8 01-Jun-16* 0%
Fire A protection specia Window A shades Wire A mesh partitions Install A lockers
Place Acoustical ceiling tiles Tiolet complartments
6 08-Jun-16* 0%
Fire protection specialities
10 14-Jun-16* 0%
Window shades
7 24-Jun-16* 0%
Wire mesh partitions
13 01-Jul-16* 0%
Install lockers
Observation A deck
9 14-Jul-16* 0%
Install A Medical recline
5 23-Jul-16* 0%
Install Medical reclined chair
Glass A wall folding par
5 28-Jul-16* 0%
Glass wall folding partition
Place A additional medi
12 02-Aug-16* 0%
Install A lecture seating
5 14-Aug-16* 0%
Install A Student Desks
7 19-Aug-16* 0%
Lab A Desks
9 26-Aug-16* 0%
Install A hardwood floor
7 04-Sep-16* 0%
Teacher A desks
6 11-Sep-16* 0%
Hydraulic A elevators
8 18-Sep-16* 0%
Project: Monroe
0
Project: Monroe
0
Project: Monroe Project: Monroe
0
Observation deck
Place additional medical equipment Install lecture seating Install Student Desks and chairs Lab Desks Install hardwood flooring Teacher desks Hydraulic elevators
0
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Summary
Page 9 of 9
TASK filter: All Activities Š Oracle Corporation
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8360
78
78 7-Day Workweek
0
Geotechnical investigation
10-Oct-13
26-Dec-13
10-Oct-13
26-Dec-13
0
A8450
4
4 7-Day Workweek
0
Alteration Project procedures
10-Oct-13
13-Oct-13
10-Oct-13
13-Oct-13
0
A8530
51
51 7-Day Workweek
0
Contract Modification
10-Oct-13
29-Nov-13
10-Oct-13
29-Nov-13
0
A8740
19
19 7-Day Workweek
0
Testing for indoor air quality
10-Oct-13
28-Oct-13
10-Oct-13
28-Oct-13
0
A8800
21
21 7-Day Workweek
0
Cutting and patching
10-Oct-13
30-Oct-13
10-Oct-13
30-Oct-13
0
A8730
7
7 7-Day Workweek
0
Leed & sustainable design requirements
10-Oct-13
16-Oct-13
22-Oct-13
28-Oct-13
12
A8460
38
38 7-Day Workweek
0
LEED submital Form
29-Oct-13
06-Dec-13
29-Oct-13
06-Dec-13
0
A8570
10
10 7-Day Workweek
0
Field engineering
27-Dec-13
05-Jan-14
27-Dec-13
05-Jan-14
0
A8610
21
21 7-Day Workweek
0
List of drawings
27-Dec-13
16-Jan-14
27-Dec-13
16-Jan-14
0
A8500
17
17 7-Day Workweek
0
Coordination drawings
27-Dec-13
13-Jan-14
04-Feb-14
21-Feb-14
39
A8300
8
8 7-Day Workweek
0
Prevailing wage documents
17-Jan-14
25-Jan-14
17-Jan-14
25-Jan-14
0
A8320
7
7 7-Day Workweek
0
Electrical Construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8330
6
6 7-Day Workweek
0
Plumbing construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8340
6
6 7-Day Workweek
0
Hvac construction bid
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8350
7
7 7-Day Workweek
0
General construction bid form
17-Jan-14
23-Jan-14
17-Jan-14
23-Jan-14
0
A8370
13
13 7-Day Workweek
0
Instruction to bidders
17-Jan-14
29-Jan-14
17-Jan-14
29-Jan-14
0
A8380
6
6 7-Day Workweek
0
Qualification questionnaire
17-Jan-14
22-Jan-14
17-Jan-14
22-Jan-14
0
A8390
25
25 7-Day Workweek
0
invitation to bid
17-Jan-14
10-Feb-14
17-Jan-14
10-Feb-14
0
A8640
5
5 7-Day Workweek
0
Sample Insurance certificates
17-Jan-14
21-Jan-14
17-Jan-14
21-Jan-14
0
A8310
11
11 7-Day Workweek
0
Bid security
10-Feb-14
21-Feb-14
10-Feb-14
21-Feb-14
0
A8410
39
39 7-Day Workweek
0
Product requirements
10-Feb-14
21-Mar-14
10-Feb-14
21-Mar-14
0
A8550
43
43 7-Day Workweek
0
Unit prices
10-Feb-14
26-Mar-14
10-Feb-14
26-Mar-14
0
A8620
4
4 7-Day Workweek
0
Safety and health management plan
10-Feb-14
14-Feb-14
10-Feb-14
14-Feb-14
0
A8630
1
1 7-Day Workweek
0
Standard General conditions
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8650
1
1 7-Day Workweek
0
Payment bond
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8660
1
1 7-Day Workweek
0
Performance bond
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8670
1
1 7-Day Workweek
0
AIA document a132
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
A8680
1
1 7-Day Workweek
0
Non collusion affidavit
10-Feb-14
11-Feb-14
10-Feb-14
11-Feb-14
0
1008 1008 7-Day Workweek
0
Payement procedures
11-Feb-14
15-Nov-16
11-Feb-14
15-Nov-16
0
A8520 A8750
330
330 7-Day Workweek
0
Demonstration & training
11-Feb-14
07-Jan-15
11-Feb-14
07-Jan-15
0
A8790
868
868 7-Day Workweek
0
Construction waste mangement
11-Feb-14
28-Jun-16
24-Aug-14
08-Jan-17
193
A8600
12
12 7-Day Workweek
0
Summary
21-Feb-14
05-Mar-14
21-Feb-14
05-Mar-14
0
A8430
14
14 7-Day Workweek
0
References
05-Mar-14
19-Mar-14
05-Mar-14
19-Mar-14
0
A8440
49
49 7-Day Workweek
0
Quality requirements
05-Mar-14
23-Apr-14
05-Mar-14
23-Apr-14
0
A8470
46
46 7-Day Workweek
0
Submittal form
05-Mar-14
21-Apr-14
05-Mar-14
21-Apr-14
0
A8540
12
12 7-Day Workweek
0
Alternates
05-Mar-14
18-Mar-14
05-Mar-14
18-Mar-14
0
A8560
26
26 7-Day Workweek
0
Quantity allowances
05-Mar-14
31-Mar-14
05-Mar-14
31-Mar-14
0
Page 1 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8580
46
46 7-Day Workweek
0
Work restrictions
05-Mar-14
20-Apr-14
05-Mar-14
20-Apr-14
0
A8590
6
6 7-Day Workweek
0
Summary of multiple contracts
05-Mar-14
11-Mar-14
05-Mar-14
11-Mar-14
0
A8690
5
5 7-Day Workweek
0
General Commissioning requirements
05-Mar-14
10-Mar-14
05-Mar-14
10-Mar-14
0
S336
744
744 7-Day Workweek
0
Install flagpoles
27-Mar-14
08-Apr-16
27-Mar-14
08-Apr-16
0
A7080
70
70 7-Day Workweek
0
Install all site utilties
27-Mar-14*
04-Jun-14
27-Mar-14
04-Jun-14
0
S96
15
15 7-Day Workweek
0
Install Rock Construction Entrance
27-Mar-14
10-Apr-14
13-May-14
27-May-14
47
1
1 7-Day Workweek
0
Start milestone
27-Mar-14*
27-Mar-14
27-Mar-14
27-Mar-14
0
A8970 S86
30
30 7-Day Workweek
0
Site Layout
28-Mar-14
26-Apr-14
28-Mar-14
26-Apr-14
0
S106
25
25 7-Day Workweek
0
Erosion controls
02-Apr-14*
26-Apr-14
02-Apr-14
26-Apr-14
0
1005 1005 7-Day Workweek
0
Execution
09-Apr-14
08-Jan-17
09-Apr-14
08-Jan-17
0
A8400 A8510
996
996 7-Day Workweek
0
Project Management & coordination
18-Apr-14
08-Jan-17
18-Apr-14
08-Jan-17
0
S116
70
70 7-Day Workweek
0
Site Clearing and Strip Topsoil
27-Apr-14*
05-Jul-14
27-Apr-14
05-Jul-14
0
S136
120
120 7-Day Workweek
0
Site grading
05-May-14*
01-Sep-14
05-May-14
01-Sep-14
0
S206
120
0 7-Day Workweek
100
Water system
05-May-14 A 17-Oct-14 A
26-Apr-14
26-Apr-14
S126
35
35 7-Day Workweek
0
Temporary Basin and Swales
07-May-14*
10-Jun-14
29-Jul-14
01-Sep-14
83
S186
245
245 7-Day Workweek
0
Install Storm Sewer
12-May-14 A 27-Dec-14
27-Apr-14
27-Dec-14
0
S156
20
20 7-Day Workweek
0
Install Paving binder access roads and staging areas
12-May-14*
31-May-14
28-May-14
16-Jun-14
16
A8480
966
966 7-Day Workweek
0
Construction Progress documentation
18-May-14
08-Jan-17
18-May-14
08-Jan-17
0
A8490
955
955 7-Day Workweek
0
Web based project management
28-May-14
08-Jan-17
28-May-14
08-Jan-17
0
10
10 7-Day Workweek
0
Site Preparation
04-Jun-14
14-Jun-14
04-Jun-14
14-Jun-14
0
A8420
946
946 7-Day Workweek
0
Temporary Facilities & controls
07-Jun-14
08-Jan-17
07-Jun-14
08-Jan-17
0
SF55
21
21 7-Day Workweek
0
Construct building pad
09-Jun-14*
29-Jun-14
17-Jun-14
07-Jul-14
8
T77
T37
10
10 7-Day Workweek
0
Mobilize Job Trailers
14-Jun-14*
24-Jun-14
14-Jun-14
24-Jun-14
0
T27
12
12 7-Day Workweek
0
Install Tempor ary Fence
24-Jun-14*
06-Jul-14
24-Jun-14
06-Jul-14
0
S226
40
40 7-Day Workweek
0
Site lighting
30-Jun-14*
08-Aug-14
24-Jul-14
01-Sep-14
24
S196
45
45 7-Day Workweek
0
Install Sanitary Sewer
30-Jun-14*
13-Aug-14
13-Sep-15
27-Oct-15
440
S146
50
50 7-Day Workweek
0
Install Sediment Basin
06-Jul-14*
24-Aug-14
06-Jul-14
24-Aug-14
0
S176
50
50 7-Day Workweek
0
Electrical ductbank
06-Jul-14*
24-Aug-14
06-Jul-14
24-Aug-14
0
T87
10
10 7-Day Workweek
0
Temporary electric to trailers
06-Jul-14*
16-Jul-14
06-Jul-14
16-Jul-14
0
T67
15
15 7-Day Workweek
0
Temporary utility poles
06-Jul-14*
21-Jul-14
10-Aug-14
24-Aug-14
34
SF25
7
7 7-Day Workweek
0
Layout for foundation
08-Jul-14*
14-Jul-14
08-Jul-14
14-Jul-14
0
SF45
20
20 7-Day Workweek
0
Tie Rebar
15-Jul-14*
03-Aug-14
15-Jul-14
03-Aug-14
0
S166
30
30 7-Day Workweek
0
Install additional staging areas
24-Jul-14*
22-Aug-14
24-Jul-14
22-Aug-14
0
SF35
45
45 7-Day Workweek
0
Footing excavation
04-Aug-14*
17-Sep-14
04-Aug-14
17-Sep-14
0
SF65
45
45 7-Day Workweek
0
Concrete foundation
04-Aug-14*
17-Sep-14
04-Aug-14
17-Sep-14
0
S216
100
100 7-Day Workweek
0
Concrete curbs
09-Aug-14*
16-Nov-14
02-Sep-14
10-Dec-14
24
T47
30
30 7-Day Workweek
0
Provide temporary electric and lighting to buildings
25-Aug-14*
23-Sep-14
25-Aug-14
23-Sep-14
0
Page 2 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
S396
35
35 7-Day Workweek
0
Install new topsoil
25-Aug-14 A 28-Sep-14
16-Dec-14
19-Jan-15
113
S386
140
140 7-Day Workweek
0
Site excavation
02-Sep-14*
19-Jan-15
02-Sep-14
19-Jan-15
0
A8770
850
850 7-Day Workweek
0
Operation and maintenance data
11-Sep-14
08-Jan-17
11-Sep-14
08-Jan-17
0
ST1224
10
10 7-Day Workweek
0
Plumbing underground sanitary/storm rough-in
18-Sep-14*
27-Sep-14
18-Sep-14
27-Sep-14
0
ST1244
15
15 7-Day Workweek
0
Deep underground rough-in
28-Sep-14*
12-Oct-14
28-Sep-14
12-Oct-14
0
ST984
10
10 7-Day Workweek
0
Plumbing underground sanitary/storm rough-in
28-Sep-14*
07-Oct-14
08-Oct-14
17-Oct-14
10
ST1004
15
15 7-Day Workweek
0
Deep underground rough-in
08-Oct-14*
22-Oct-14
18-Oct-14
01-Nov-14
10
ST744
10
10 7-Day Workweek
0
Plumbing underground sanitary/storm rough-in
08-Oct-14*
17-Oct-14
30-Jan-15
09-Feb-15
114
ST1234
20
20 7-Day Workweek
0
Waterproofing
13-Oct-14*
01-Nov-14
13-Oct-14
01-Nov-14
0
ST764
15
15 7-Day Workweek
0
Deep underground rough-in
18-Oct-14*
01-Nov-14
09-Feb-15
24-Feb-15
114
ST994
20
20 7-Day Workweek
0
Waterproofing
02-Nov-14*
21-Nov-14
02-Nov-14
21-Nov-14
0
ST1024
23
23 7-Day Workweek
0
Erect structural steel and deck
02-Nov-14
24-Nov-14
02-Nov-14
24-Nov-14
0
ST754
20
20 7-Day Workweek
0
Waterproofing
02-Nov-14*
21-Nov-14
24-Feb-15
16-Mar-15
114
S376
40
40 7-Day Workweek
0
Retaining wall
17-Nov-14*
26-Dec-14
11-Dec-14
19-Jan-15
24
ST784
23
23 7-Day Workweek
0
Erect structural steel and deck
22-Nov-14
14-Dec-14
22-Nov-14
14-Dec-14
0
ST544
23
23 7-Day Workweek
0
Erect structural steel and deck
22-Nov-14
14-Dec-14
16-Mar-15
08-Apr-15
114
ST1074
25
25 7-Day Workweek
0
Cold formed metal framing and sheathing
25-Nov-14
19-Dec-14
25-Nov-14
19-Dec-14
0
ST1254
12
12 7-Day Workweek
0
Stone under slab rough-in
25-Nov-14
06-Dec-14
25-Nov-14
06-Dec-14
0
ST1044
15
15 7-Day Workweek
0
Stone under slab
07-Dec-14
21-Dec-14
07-Dec-14
21-Dec-14
0
ST834
25
25 7-Day Workweek
0
Cold formed metal framing and sheathing
15-Dec-14
08-Jan-15
15-Dec-14
08-Jan-15
0
ST1014
12
12 7-Day Workweek
0
Stone under slab rough-in
15-Dec-14
26-Dec-14
16-Dec-14
27-Dec-14
1
ST594
25
25 7-Day Workweek
0
Cold formed metal framing and sheathing
15-Dec-14
08-Jan-15
08-Apr-15
03-May-15
114
ST1094
18
18 7-Day Workweek
0
Install air membrane
20-Dec-14
06-Jan-15
20-Dec-14
06-Jan-15
0
ST1034
32
32 7-Day Workweek
0
Pour concrete slab on deck
22-Dec-14
22-Jan-15
22-Dec-14
22-Jan-15
0
ST804
15
15 7-Day Workweek
0
Stone under slab
27-Dec-14
10-Jan-15
28-Dec-14
11-Jan-15
1
ST774
12
12 7-Day Workweek
0
Stone under slab rough-in
27-Dec-14
07-Jan-15
09-Apr-15
21-Apr-15
103
100
100 7-Day Workweek
0
Install Geo Exchange Field
28-Dec-14*
06-Apr-15
28-Dec-14
06-Apr-15
0
ST1084
20
20 7-Day Workweek
0
Spray urethane insulation
07-Jan-15
26-Jan-15
07-Jan-15
26-Jan-15
0
ST564
15
15 7-Day Workweek
0
Stone under slab
08-Jan-15
22-Jan-15
21-Apr-15
06-May-15
103
S406
ST854
18
18 7-Day Workweek
0
Install air membrane
09-Jan-15
26-Jan-15
09-Jan-15
26-Jan-15
0
ST614
18
18 7-Day Workweek
0
Install air membrane
09-Jan-15
26-Jan-15
03-May-15
21-May-15
114
ST794
32
32 7-Day Workweek
0
Pour concrete slab on deck
11-Jan-15
11-Feb-15
12-Jan-15
12-Feb-15
1
S246
40
40 7-Day Workweek
0
Place trees and shrubbery
20-Jan-15*
28-Feb-15
20-Jan-15
28-Feb-15
0
ST1064
15
15 7-Day Workweek
0
Pour concrete slab on grade
23-Jan-15
06-Feb-15
23-Jan-15
06-Feb-15
0
ST554
32
32 7-Day Workweek
0
Pour concrete slab on deck
23-Jan-15
23-Feb-15
06-May-15
07-Jun-15
103
ST844
20
20 7-Day Workweek
0
Spray urethane insulation
27-Jan-15
15-Feb-15
27-Jan-15
15-Feb-15
0
ST1104
10
10 7-Day Workweek
0
Wood blocking & sheathing on roof
27-Jan-15
05-Feb-15
27-Jan-15
05-Feb-15
0
Page 3 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8820
5
5 7-Day Workweek
0
Metal stairs
27-Jan-15*
31-Jan-15
27-Jan-15
31-Jan-15
0
ST1144
20
20 7-Day Workweek
0
Insulated metal wall panels
27-Jan-15
15-Feb-15
17-Mar-15
05-Apr-15
49
ST604
20
20 7-Day Workweek
0
Spray urethane insulation
27-Jan-15
15-Feb-15
21-May-15
10-Jun-15
114
A8830
4
4 7-Day Workweek
0
Install railings
01-Feb-15*
04-Feb-15
01-Feb-15
04-Feb-15
0
A8840
13
13 7-Day Workweek
0
Interior H.M frames
05-Feb-15*
17-Feb-15
05-Feb-15
17-Feb-15
0
ST1124
11
11 7-Day Workweek
0
Roof Drains
06-Feb-15
16-Feb-15
06-Feb-15
16-Feb-15
0
ST1114
7
7 7-Day Workweek
0
Roof curbs
06-Feb-15
12-Feb-15
05-Mar-15
11-Mar-15
27
ST1054
20
20 7-Day Workweek
0
CMU walls
07-Feb-15
26-Feb-15
07-Feb-15
26-Feb-15
0
ST824
15
15 7-Day Workweek
0
Pour concrete slab on grade
12-Feb-15
26-Feb-15
13-Feb-15
27-Feb-15
1
ST1134
5
5 7-Day Workweek
0
Roof top equipment
13-Feb-15
17-Feb-15
12-Mar-15
16-Mar-15
27
ST864
10
10 7-Day Workweek
0
Wood blocking & sheathing on roof
16-Feb-15
25-Feb-15
16-Feb-15
25-Feb-15
0
ST904
20
20 7-Day Workweek
0
Insulated metal wall panels
16-Feb-15
07-Mar-15
06-Apr-15
25-Apr-15
49
ST624
10
10 7-Day Workweek
0
Wood blocking & sheathing on roof
16-Feb-15
25-Feb-15
10-Jun-15
20-Jun-15
114
ST664
20
20 7-Day Workweek
0
Insulated metal wall panels
16-Feb-15
07-Mar-15
29-Jul-15
18-Aug-15
163
ST1154
15
15 7-Day Workweek
0
Metal soffit and fascia
17-Feb-15
03-Mar-15
17-Feb-15
03-Mar-15
0
A8850
9
9 7-Day Workweek
0
Drywall and spackliing
18-Feb-15*
26-Feb-15
18-Feb-15
26-Feb-15
0
ST584
15
15 7-Day Workweek
0
Pour concrete slab on grade
24-Feb-15
10-Mar-15
07-Jun-15
22-Jun-15
103
ST884
11
11 7-Day Workweek
0
Roof Drains
26-Feb-15
08-Mar-15
26-Feb-15
08-Mar-15
0
ST874
7
7 7-Day Workweek
0
Roof curbs
26-Feb-15
04-Mar-15
25-Mar-15
31-Mar-15
27
ST644
11
11 7-Day Workweek
0
Roof Drains
26-Feb-15
08-Mar-15
20-Jun-15
01-Jul-15
114
ST634
7
7 7-Day Workweek
0
Roof curbs
26-Feb-15
04-Mar-15
17-Jul-15
24-Jul-15
141
A8860
5
5 7-Day Workweek
0
Caulking
27-Feb-15*
03-Mar-15
27-Feb-15
03-Mar-15
0
ST1264
29
29 7-Day Workweek
0
Layout stone veneer
27-Feb-15
27-Mar-15
27-Feb-15
27-Mar-15
0
ST814
20
20 7-Day Workweek
0
CMU walls
27-Feb-15
18-Mar-15
28-Feb-15
19-Mar-15
1
ST1204
37
37 7-Day Workweek
0
Masonry veneer
27-Feb-15
04-Apr-15
28-Feb-15
05-Apr-15
1
ST1164
13
13 7-Day Workweek
0
Roof metal edges
04-Mar-15
16-Mar-15
04-Mar-15
16-Mar-15
0
A8870
7
7 7-Day Workweek
0
Ceramic and porcelain wall/floor tiles
04-Mar-15*
10-Mar-15
04-Mar-15
10-Mar-15
0
ST894
5
5 7-Day Workweek
0
Roof top equipment
05-Mar-15
09-Mar-15
01-Apr-15
05-Apr-15
27
ST654
5
5 7-Day Workweek
0
Roof top equipment
05-Mar-15
09-Mar-15
24-Jul-15
29-Jul-15
141
ST914
15
15 7-Day Workweek
0
Metal soffit and fascia
09-Mar-15
23-Mar-15
09-Mar-15
23-Mar-15
ST674
15
15 7-Day Workweek
0
Metal soffit and fascia
09-Mar-15
23-Mar-15
01-Jul-15
16-Jul-15
A8880
9
9 7-Day Workweek
0
Painting
11-Mar-15*
19-Mar-15
11-Mar-15
19-Mar-15
0
A8760
666
666 7-Day Workweek
0
Project record documents
14-Mar-15
08-Jan-17
14-Mar-15
08-Jan-17
0
ST1184
20
20 7-Day Workweek
0
Metal roof ladders
17-Mar-15
05-Apr-15
17-Mar-15
05-Apr-15
0
ST964
37
37 7-Day Workweek
0
Masonry veneer
19-Mar-15
24-Apr-15
20-Mar-15
25-Apr-15
1
ST574
20
20 7-Day Workweek
0
CMU walls
19-Mar-15
07-Apr-15
22-Jun-15
12-Jul-15
95
A8890
6
6 7-Day Workweek
0
Wall coverings
20-Mar-15*
26-Mar-15
20-Mar-15
26-Mar-15
0
Page 4 of 10
0 114
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
ST924
13
13 7-Day Workweek
0
Roof metal edges
24-Mar-15
05-Apr-15
24-Mar-15
05-Apr-15
0
ST684
13
13 7-Day Workweek
0
Roof metal edges
24-Mar-15
05-Apr-15
16-Jul-15
29-Jul-15
114
A8900
7
7 7-Day Workweek
0
Acoustical ceiling grid
26-Mar-15*
02-Apr-15
26-Mar-15
02-Apr-15
0
A8910
10
10 7-Day Workweek
0
PC AG san/rw
02-Apr-15*
12-Apr-15
02-Apr-15
12-Apr-15
0
ST1174
10
10 7-Day Workweek
0
Exterior Caulking
05-Apr-15
14-Apr-15
06-Apr-15
15-Apr-15
1
ST944
20
20 7-Day Workweek
0
Metal roof ladders
06-Apr-15
25-Apr-15
06-Apr-15
25-Apr-15
0
ST1194
10
10 7-Day Workweek
0
Aluminum windows & curtain walls
06-Apr-15
15-Apr-15
06-Apr-15
15-Apr-15
0
ST704
20
20 7-Day Workweek
0
Metal roof ladders
06-Apr-15
25-Apr-15
29-Jul-15
18-Aug-15
114
T57
40
40 7-Day Workweek
0
Provide temporary heat
07-Apr-15*
16-May-15
07-Apr-15
16-May-15
0
ST724
37
37 7-Day Workweek
0
Masonry veneer
08-Apr-15
14-May-15
12-Jul-15
18-Aug-15
95
A8920
10
10 7-Day Workweek
0
PC overhead pipe
12-Apr-15*
22-Apr-15
12-Apr-15
22-Apr-15
0
S296
30
30 7-Day Workweek
0
Exterior masonry seat walls and site walls
13-Apr-15*
12-May-15
20-Jun-15
19-Jul-15
68
ST1214
25
25 7-Day Workweek
0
Aluminum entrance doors/sliding doors
16-Apr-15
10-May-15
16-Apr-15
10-May-15
0
5
5 7-Day Workweek
0
PC insulation
22-Apr-15*
27-Apr-15
22-Apr-15
27-Apr-15
0
A8930 ST934
10
10 7-Day Workweek
0
Exterior Caulking
25-Apr-15
04-May-15
26-Apr-15
05-May-15
1
ST954
10
10 7-Day Workweek
0
Aluminum windows & curtain walls
26-Apr-15
05-May-15
26-Apr-15
05-May-15
0
ST714
10
10 7-Day Workweek
0
Aluminum windows & curtain walls
26-Apr-15
05-May-15
18-Aug-15
28-Aug-15
114
A7090
5
5 7-Day Workweek
0
Metal stairs
26-Apr-15*
30-Apr-15
17-Sep-15
22-Sep-15
144
A8940
10
10 7-Day Workweek
0
PC drop sprinkler head
27-Apr-15*
07-May-15
27-Apr-15
07-May-15
0
A7100
4
4 7-Day Workweek
0
Install railings
01-May-15*
04-May-15
26-Sep-15
30-Sep-15
148
A7110
13
13 7-Day Workweek
0
Interior H.M frames
05-May-15*
17-May-15
30-Sep-15
13-Oct-15
148
ST974
25
25 7-Day Workweek
0
Aluminum entrance doors/sliding doors
06-May-15
30-May-15
06-May-15
30-May-15
0
A8950
5
5 7-Day Workweek
0
PC casework fixtures
07-May-15*
12-May-15
07-May-15
12-May-15
0
A8960
5
5 7-Day Workweek
0
PC toilet fixtures
12-May-15*
17-May-15
12-May-15
17-May-15
0
ST694
10
10 7-Day Workweek
0
Exterior Caulking
15-May-15
24-May-15
18-Aug-15
28-Aug-15
95
A8980
5
5 7-Day Workweek
0
HC hangers
17-May-15*
22-May-15
17-May-15
22-May-15
0
A7120
9
9 7-Day Workweek
0
Drywall and spackliing
18-May-15*
26-May-15
13-Oct-15
22-Oct-15
148
A8990
7
7 7-Day Workweek
0
HC pipe install
22-May-15*
29-May-15
22-May-15
29-May-15
0
ST734
25
25 7-Day Workweek
0
Aluminum entrance doors/sliding doors
25-May-15
18-Jun-15
28-Aug-15
22-Sep-15
95
S356
20
20 7-Day Workweek
0
Retaining wall for landscaping
25-May-15*
13-Jun-15
04-Sep-15
23-Sep-15
102
S276
65
65 7-Day Workweek
0
sidewalks and ramp concrete pour
26-May-15*
29-Jul-15
20-Jul-15
22-Sep-15
55
A7130
5
5 7-Day Workweek
0
Caulking
27-May-15*
31-May-15
22-Oct-15
27-Oct-15
148
A9000
5
5 7-Day Workweek
0
HC duct install
29-May-15*
03-Jun-15
29-May-15
03-Jun-15
0
A7140
7
7 7-Day Workweek
0
Ceramic and porcelain wall/floor tiles
01-Jun-15*
07-Jun-15
27-Oct-15
03-Nov-15
148
A9010
11
11 7-Day Workweek
0
HC ATC rough-in
03-Jun-15*
14-Jun-15
03-Jun-15
14-Jun-15
0
A7150
9
9 7-Day Workweek
0
Painting
08-Jun-15*
16-Jun-15
03-Nov-15
12-Nov-15
148
A9020
15
15 7-Day Workweek
0
HC GRD install
14-Jun-15*
29-Jun-15
14-Jun-15
29-Jun-15
0
Page 5 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7160
6
6 7-Day Workweek
0
Wall coverings
17-Jun-15*
23-Jun-15
12-Nov-15
18-Nov-15
148
A7700
5
5 7-Day Workweek
0
Metal stairs
19-Jun-15*
23-Jun-15
22-Sep-15
27-Sep-15
95
A7170
7
7 7-Day Workweek
0
Acoustical ceiling grid
23-Jun-15*
30-Jun-15
18-Nov-15
25-Nov-15
148
A7710
4
4 7-Day Workweek
0
Install railings
24-Jun-15*
27-Jun-15
27-Sep-15
01-Oct-15
95
A7720
13
13 7-Day Workweek
0
Interior H.M frames
28-Jun-15*
10-Jul-15
01-Oct-15
14-Oct-15
95
A9030
12
12 7-Day Workweek
0
HC equipment and final connections
29-Jun-15*
11-Jul-15
29-Jun-15
11-Jul-15
0
A7180
10
10 7-Day Workweek
0
PC AG san/rw
30-Jun-15*
10-Jul-15
25-Nov-15
05-Dec-15
148
A7190
10
10 7-Day Workweek
0
PC overhead pipe
10-Jul-15*
20-Jul-15
06-Dec-15
15-Dec-15
148
A7730
9
9 7-Day Workweek
0
Drywall and spackliing
11-Jul-15*
19-Jul-15
14-Oct-15
23-Oct-15
95
A9040
10
10 7-Day Workweek
0
HC kitchen equipment and hookups
11-Jul-15*
21-Jul-15
11-Jul-15
21-Jul-15
0
A7740
5
5 7-Day Workweek
0
Caulking
20-Jul-15*
24-Jul-15
23-Oct-15
28-Oct-15
95
A9050
12
12 7-Day Workweek
0
EC rough-in walls
21-Jul-15*
02-Aug-15
21-Jul-15
02-Aug-15
0
A7750
7
7 7-Day Workweek
0
Ceramic and porcelain wall/floor tiles
25-Jul-15*
31-Jul-15
28-Oct-15
04-Nov-15
95
A7760
9
9 7-Day Workweek
0
Painting
01-Aug-15*
09-Aug-15
04-Nov-15
13-Nov-15
95
A9060
14
14 7-Day Workweek
0
EC overhead rough-in
02-Aug-15*
15-Aug-15
02-Aug-15
15-Aug-15
0
A7770
6
6 7-Day Workweek
0
Wall coverings
10-Aug-15*
16-Aug-15
13-Nov-15
19-Nov-15
95
A9070
14
14 7-Day Workweek
0
EC cable tray
15-Aug-15*
30-Aug-15
15-Aug-15
30-Aug-15
0
A7780
7
7 7-Day Workweek
0
Acoustical ceiling grid
16-Aug-15*
23-Aug-15
19-Nov-15
26-Nov-15
95
A7790
10
10 7-Day Workweek
0
PC AG san/rw
23-Aug-15*
02-Sep-15
26-Nov-15
06-Dec-15
95
S346
25
25 7-Day Workweek
0
Parking control equipment
24-Aug-15*
17-Sep-15
24-Sep-15
18-Oct-15
31
S326
35
35 7-Day Workweek
0
Fiberglass bus stations
25-Aug-15*
28-Sep-15
23-Sep-15
27-Oct-15
29
S366
20
20 7-Day Workweek
0
Timber guide railin gs
25-Aug-15*
13-Sep-15
29-Sep-15
18-Oct-15
35
A9080
9
9 7-Day Workweek
0
EC wiring
30-Aug-15*
07-Sep-15
30-Aug-15
07-Sep-15
0
A7800
10
10 7-Day Workweek
0
PC overhead pipe
02-Sep-15*
12-Sep-15
07-Dec-15
16-Dec-15
95
A9090
8
8 7-Day Workweek
0
EC light fixtures
07-Sep-15*
15-Sep-15
07-Sep-15
15-Sep-15
0
A7810
5
5 7-Day Workweek
0
PC insulation
12-Sep-15*
17-Sep-15
17-Dec-15
21-Dec-15
95
A9100
5
5 7-Day Workweek
0
EC wring devices
15-Sep-15*
20-Sep-15
15-Sep-15
20-Sep-15
0
A7820
10
10 7-Day Workweek
0
PC drop sprinkler head
17-Sep-15*
27-Sep-15
22-Dec-15
31-Dec-15
95
S286
46
46 7-Day Workweek
0
Unit Pavers
18-Sep-15*
02-Nov-15
19-Oct-15
03-Dec-15
31
A9110
6
6 7-Day Workweek
0
EC fire alarm and security
20-Sep-15*
26-Sep-15
20-Sep-15
26-Sep-15
0
A9120
10
10 7-Day Workweek
0
EC kitchen equipment and hookups
26-Sep-15*
06-Oct-15
26-Sep-15
06-Oct-15
0
A7830
5
5 7-Day Workweek
0
PC casework fixtures
27-Sep-15*
02-Oct-15
01-Jan-16
05-Jan-16
95
S236
50
50 7-Day Workweek
0
Final Landscaping
29-Sep-15*
17-Nov-15
28-Oct-15
16-Dec-15
29
A7840
5
5 7-Day Workweek
0
PC toilet fixtures
02-Oct-15*
07-Oct-15
06-Jan-16
10-Jan-16
95
A9130
5
5 7-Day Workweek
0
EC hook ups and connections
06-Oct-15*
11-Oct-15
06-Oct-15
11-Oct-15
0
A7850
6
6 7-Day Workweek
0
PC kitchen equipment hookups
07-Oct-15*
13-Oct-15
11-Jan-16
16-Jan-16
95
A9140
8
8 7-Day Workweek
0
Casework/millwork
11-Oct-15*
19-Oct-15
11-Oct-15
19-Oct-15
0
Page 6 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7860
5
5 7-Day Workweek
0
HC hangers
13-Oct-15*
18-Oct-15
17-Jan-16
21-Jan-16
95
A7870
7
7 7-Day Workweek
0
HC pipe install
18-Oct-15*
25-Oct-15
22-Jan-16
28-Jan-16
95
A9150
8
8 7-Day Workweek
0
Resilent tile base and floor
19-Oct-15*
27-Oct-15
19-Oct-15
27-Oct-15
0
A7880
5
5 7-Day Workweek
0
HC duct install
25-Oct-15*
30-Oct-15
29-Jan-16
02-Feb-16
95
A9160
8
8 7-Day Workweek
0
Seamless vinyl flooring
27-Oct-15*
04-Nov-15
27-Oct-15
04-Nov-15
0
A7890
11
11 7-Day Workweek
0
HC ATC rough-in
30-Oct-15*
10-Nov-15
03-Feb-16
13-Feb-16
95
S306
38
38 7-Day Workweek
0
Exterior site railings
03-Nov-15*
10-Dec-15
04-Dec-15
10-Jan-16
31
A9170
11
11 7-Day Workweek
0
Carpet tiles
04-Nov-15*
15-Nov-15
04-Nov-15
15-Nov-15
0
A7900
15
15 7-Day Workweek
0
HC GRD install
10-Nov-15*
25-Nov-15
14-Feb-16
28-Feb-16
95
A9180
7
7 7-Day Workweek
0
Install rubber stairs, treads and landings
15-Nov-15*
22-Nov-15
15-Nov-15
22-Nov-15
0
S316
25
25 7-Day Workweek
0
Position Site seating
18-Nov-15*
12-Dec-15
17-Dec-15
10-Jan-16
29
A9190
6
6 7-Day Workweek
0
Doors and Hardware
22-Nov-15*
28-Nov-15
22-Nov-15
28-Nov-15
0
A7910
12
12 7-Day Workweek
0
HC equipment and final connections
25-Nov-15*
07-Dec-15
28-Feb-16
11-Mar-16
95
A9200
8
8 7-Day Workweek
0
Interior glass partitions
28-Nov-15*
06-Dec-15
28-Nov-15
06-Dec-15
0
A9210
5
5 7-Day Workweek
0
Wood wall panels
06-Dec-15*
11-Dec-15
06-Dec-15
11-Dec-15
0
A7920
10
10 7-Day Workweek
0
HC kitchen equipment and hookups
07-Dec-15*
17-Dec-15
11-Mar-16
21-Mar-16
95
A9220
5
5 7-Day Workweek
0
Visual display surfaces
11-Dec-15*
16-Dec-15
11-Dec-15
16-Dec-15
0
S416
43
43 7-Day Workweek
0
Final placement of trees and shrubbery
13-Dec-15*
24-Jan-16
11-Jan-16
22-Feb-16
29
A9430
1
1 7-Day Workweek
0
Substantial milestone
16-Dec-15*
16-Dec-15
16-Dec-15
16-Dec-15
0
A9230
5
5 7-Day Workweek
0
Signage
16-Dec-15*
21-Dec-15
16-Dec-15
21-Dec-15
0
A7200
5
5 7-Day Workweek
0
PC insulation
17-Dec-15*
21-Dec-15
17-Dec-15
21-Dec-15
0
A7930
12
12 7-Day Workweek
0
EC rough-in walls
17-Dec-15*
29-Dec-15
21-Mar-16
02-Apr-16
95
A9240
3
3 7-Day Workweek
0
Wood ceiling
21-Dec-15*
24-Dec-15
21-Dec-15
24-Dec-15
0
A7210
10
10 7-Day Workweek
0
PC drop sprinkler head
22-Dec-15*
31-Dec-15
22-Dec-15
31-Dec-15
0
A9250
11
11 7-Day Workweek
0
Place Acoustical ceiling tiles
24-Dec-15*
04-Jan-16
24-Dec-15
04-Jan-16
0
A7940
14
14 7-Day Workweek
0
EC overhead rough-in
29-Dec-15*
11-Jan-16
02-Apr-16
15-Apr-16
95
A7220
5
5 7-Day Workweek
0
PC casework fixtures
01-Jan-16*
05-Jan-16
01-Jan-16
05-Jan-16
0
A9260
8
8 7-Day Workweek
0
Tiolet complartments
04-Jan-16*
11-Jan-16
04-Jan-16
11-Jan-16
0
A7230
5
5 7-Day Workweek
0
PC toilet fixtures
06-Jan-16*
10-Jan-16
06-Jan-16
10-Jan-16
0
A7240
6
6 7-Day Workweek
0
PC kitchen equipment hookups
11-Jan-16*
16-Jan-16
11-Jan-16
16-Jan-16
0
A9270
6
6 7-Day Workweek
0
Fire protection specialities
11-Jan-16*
17-Jan-16
11-Jan-16
17-Jan-16
0
A7950
14
14 7-Day Workweek
0
EC cable tray
11-Jan-16*
26-Jan-16
16-Apr-16
30-Apr-16
95
A7250
5
5 7-Day Workweek
0
HC hangers
17-Jan-16*
21-Jan-16
17-Jan-16
21-Jan-16
0
A9290
10
10 7-Day Workweek
0
Window shades
17-Jan-16*
27-Jan-16
17-Jan-16
27-Jan-16
0
A7260
7
7 7-Day Workweek
0
HC pipe install
22-Jan-16*
28-Jan-16
22-Jan-16
28-Jan-16
0
A7960
9
9 7-Day Workweek
0
EC wiring
26-Jan-16*
03-Feb-16
30-Apr-16
08-May-16
95
A9300
7
7 7-Day Workweek
0
Wire mesh partitions
27-Jan-16*
03-Feb-16
27-Jan-16
03-Feb-16
0
Page 7 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7270
5
5 7-Day Workweek
0
HC duct install
29-Jan-16*
02-Feb-16
29-Jan-16
02-Feb-16
0
A7280
11
11 7-Day Workweek
0
HC ATC rough-in
03-Feb-16*
13-Feb-16
03-Feb-16
13-Feb-16
0
A7970
8
8 7-Day Workweek
0
EC light fixtures
03-Feb-16*
11-Feb-16
08-May-16
16-May-16
95
A9310
13
13 7-Day Workweek
0
Install lockers
03-Feb-16*
16-Feb-16
03-Feb-16
16-Feb-16
0
S266
20
20 7-Day Workweek
0
Concrete bumper blocks
08-Feb-16*
27-Feb-16
23-Feb-16
13-Mar-16
15
A7980
5
5 7-Day Workweek
0
EC wring devices
11-Feb-16*
16-Feb-16
16-May-16
21-May-16
95
A7290
15
15 7-Day Workweek
0
HC GRD install
14-Feb-16*
28-Feb-16
14-Feb-16
28-Feb-16
0
A7990
6
6 7-Day Workweek
0
EC fire alarm and security
16-Feb-16*
22-Feb-16
21-May-16
28-May-16
95
A9320
9
9 7-Day Workweek
0
Install hood and walk-ins
16-Feb-16*
25-Feb-16
16-Feb-16
25-Feb-16
0
A8000
10
10 7-Day Workweek
0
EC kitchen equipment and hookups
22-Feb-16*
03-Mar-16
28-May-16
07-Jun-16
95
A9340
5
5 7-Day Workweek
0
Install and setup food service equipment
25-Feb-16*
01-Mar-16
25-Feb-16
01-Mar-16
0
A7300
12
12 7-Day Workweek
0
HC equipment and final connections
28-Feb-16*
11-Mar-16
28-Feb-16
11-Mar-16
0
A9350
5
5 7-Day Workweek
0
Glass wall folding partition
01-Mar-16*
06-Mar-16
01-Mar-16
06-Mar-16
0
A8010
5
5 7-Day Workweek
0
EC hook ups and connections
03-Mar-16*
08-Mar-16
07-Jun-16
12-Jun-16
95
A9360
12
12 7-Day Workweek
0
Loading dock equipment
06-Mar-16*
18-Mar-16
06-Mar-16
18-Mar-16
0
A8020
8
8 7-Day Workweek
0
Casework/millwork
08-Mar-16*
16-Mar-16
12-Jun-16
19-Jun-16
95
A7310
10
10 7-Day Workweek
0
HC kitchen equipment and hookups
11-Mar-16*
21-Mar-16
11-Mar-16
21-Mar-16
0
S256
26
26 7-Day Workweek
0
site linestripping and signage
14-Mar-16*
08-Apr-16
14-Mar-16
08-Apr-16
0
A8030
8
8 7-Day Workweek
0
Resilent tile base and floor
16-Mar-16*
24-Mar-16
19-Jun-16
27-Jun-16
95
A9370
5
5 7-Day Workweek
0
Paint gym ceiling
18-Mar-16*
23-Mar-16
18-Mar-16
23-Mar-16
0
A7320
12
12 7-Day Workweek
0
EC rough-in walls
21-Mar-16*
02-Apr-16
21-Mar-16
02-Apr-16
0
A9380
7
7 7-Day Workweek
0
Gym equipment
23-Mar-16*
30-Mar-16
23-Mar-16
30-Mar-16
0
A8040
8
8 7-Day Workweek
0
Seamless vinyl flooring
24-Mar-16*
01-Apr-16
27-Jun-16
05-Jul-16
95
A9390
9
9 7-Day Workweek
0
Gym dividers
30-Mar-16*
08-Apr-16
30-Mar-16
08-Apr-16
0
A8050
11
11 7-Day Workweek
0
Carpet tiles
01-Apr-16*
12-Apr-16
05-Jul-16
16-Jul-16
95
A7330
14
14 7-Day Workweek
0
EC overhead rough-in
02-Apr-16*
15-Apr-16
02-Apr-16
15-Apr-16
0
A9400
7
7 7-Day Workweek
0
Install hardwood flooring
08-Apr-16*
15-Apr-16
08-Apr-16
15-Apr-16
0
A8060
7
7 7-Day Workweek
0
Install rubber stairs, treads and landings
12-Apr-16*
19-Apr-16
16-Jul-16
23-Jul-16
95
A9410
6
6 7-Day Workweek
0
Install collapsable belachers
15-Apr-16*
22-Apr-16
15-Apr-16
22-Apr-16
0
A7340
14
14 7-Day Workweek
0
EC cable tray
16-Apr-16*
30-Apr-16
16-Apr-16
30-Apr-16
0
A8070
6
6 7-Day Workweek
0
Doors and Hardware
19-Apr-16*
25-Apr-16
23-Jul-16
29-Jul-16
95
A9420
8
8 7-Day Workweek
0
Hydraulic elevators
22-Apr-16*
30-Apr-16
22-Apr-16
30-Apr-16
0
A8080
8
8 7-Day Workweek
0
Interior glass partitions
25-Apr-16*
03-May-16
29-Jul-16
06-Aug-16
95
A9330
10
10 7-Day Workweek
0
Install kitchen tiles
30-Apr-16
10-May-16
30-Apr-16
10-May-16
0
A8720
9
9 7-Day Workweek
0
Checklist enrollment building
30-Apr-16
08-May-16
30-Dec-16
08-Jan-17
244
A7350
9
9 7-Day Workweek
0
EC wiring
30-Apr-16*
08-May-16
30-Apr-16
08-May-16
0
A8090
5
5 7-Day Workweek
0
Wood wall panels
03-May-16*
08-May-16
07-Aug-16
11-Aug-16
95
Page 8 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A8100
5
5 7-Day Workweek
0
Visual display surfaces
08-May-16*
13-May-16
12-Aug-16
16-Aug-16
95
A7360
8
8 7-Day Workweek
0
EC light fixtures
08-May-16*
16-May-16
08-May-16
16-May-16
0
A9280
9
9 7-Day Workweek
0
Motorized projection screens
10-May-16
19-May-16
10-May-16
19-May-16
0
A8110
5
5 7-Day Workweek
0
Signage
13-May-16*
18-May-16
17-Aug-16
21-Aug-16
95
A7370
5
5 7-Day Workweek
0
EC wring devices
16-May-16*
21-May-16
16-May-16
21-May-16
0
A8120
3
3 7-Day Workweek
0
Wood ceiling
18-May-16*
21-May-16
22-Aug-16
24-Aug-16
95
A8130
11
11 7-Day Workweek
0
Place Acoustical ceiling tiles
21-May-16*
01-Jun-16
25-Aug-16
04-Sep-16
95
A7380
6
6 7-Day Workweek
0
EC fire alarm and security
21-May-16*
28-May-16
21-May-16
28-May-16
0
A7390
10
10 7-Day Workweek
0
EC kitchen equipment and hookups
28-May-16*
07-Jun-16
28-May-16
07-Jun-16
0
A8140
8
8 7-Day Workweek
0
Tiolet complartments
01-Jun-16*
08-Jun-16
04-Sep-16
11-Sep-16
95
A7400
5
5 7-Day Workweek
0
EC hook ups and connections
07-Jun-16*
12-Jun-16
07-Jun-16
12-Jun-16
0
A8150
6
6 7-Day Workweek
0
Fire protection specialities
08-Jun-16*
14-Jun-16
12-Sep-16
17-Sep-16
95
A7410
8
8 7-Day Workweek
0
Casework/millwork
12-Jun-16*
19-Jun-16
12-Jun-16
19-Jun-16
0
A8170
10
10 7-Day Workweek
0
Window shades
14-Jun-16*
24-Jun-16
18-Sep-16
27-Sep-16
95
A7420
8
8 7-Day Workweek
0
Resilent tile base and floor
19-Jun-16*
27-Jun-16
19-Jun-16
27-Jun-16
0
A8180
7
7 7-Day Workweek
0
Wire mesh partitions
24-Jun-16*
01-Jul-16
28-Sep-16
04-Oct-16
95
A7430
8
8 7-Day Workweek
0
Seamless vinyl flooring
27-Jun-16*
05-Jul-16
27-Jun-16
05-Jul-16
0
A8190
13
13 7-Day Workweek
0
Install lockers
01-Jul-16*
14-Jul-16
05-Oct-16
17-Oct-16
95
A7440
11
11 7-Day Workweek
0
Carpet tiles
05-Jul-16*
16-Jul-16
05-Jul-16
16-Jul-16
0
A8200
9
9 7-Day Workweek
0
Observation deck
14-Jul-16*
23-Jul-16
18-Oct-16
26-Oct-16
95
A7450
7
7 7-Day Workweek
0
Install rubber stairs, treads and landings
16-Jul-16*
23-Jul-16
16-Jul-16
23-Jul-16
0
A7460
6
6 7-Day Workweek
0
Doors and Hardware
23-Jul-16*
29-Jul-16
23-Jul-16
29-Jul-16
0
A8210
5
5 7-Day Workweek
0
Install Medical reclined chair
23-Jul-16*
28-Jul-16
27-Oct-16
31-Oct-16
95
A8220
5
5 7-Day Workweek
0
Glass wall folding partition
28-Jul-16*
02-Aug-16
01-Nov-16
05-Nov-16
95
A7470
8
8 7-Day Workweek
0
Interior glass partitions
29-Jul-16*
06-Aug-16
29-Jul-16
06-Aug-16
0
A8230
12
12 7-Day Workweek
0
Place additional medical equipment
02-Aug-16*
14-Aug-16
06-Nov-16
17-Nov-16
95
A7480
5
5 7-Day Workweek
0
Wood wall panels
07-Aug-16*
11-Aug-16
07-Aug-16
11-Aug-16
0
A7490
5
5 7-Day Workweek
0
Visual display surfaces
12-Aug-16*
16-Aug-16
12-Aug-16
16-Aug-16
0
A8240
5
5 7-Day Workweek
0
Install lecture seating
14-Aug-16*
19-Aug-16
18-Nov-16
22-Nov-16
95
A7500
5
5 7-Day Workweek
0
Signage
17-Aug-16*
21-Aug-16
17-Aug-16
21-Aug-16
0
A8250
7
7 7-Day Workweek
0
Install Student Desks and chairs
19-Aug-16*
26-Aug-16
23-Nov-16
29-Nov-16
95
A7510
3
3 7-Day Workweek
0
Wood ceiling
22-Aug-16*
24-Aug-16
22-Aug-16
24-Aug-16
0
A7520
11
11 7-Day Workweek
0
Place Acoustical ceiling tiles
25-Aug-16*
04-Sep-16
25-Aug-16
04-Sep-16
0
A8260
9
9 7-Day Workweek
0
Lab Desks
26-Aug-16*
04-Sep-16
30-Nov-16
08-Dec-16
95
A7530
8
8 7-Day Workweek
0
Tiolet complartments
04-Sep-16*
11-Sep-16
04-Sep-16
11-Sep-16
0
A8270
7
7 7-Day Workweek
0
Install hardwood flooring
04-Sep-16*
11-Sep-16
09-Dec-16
15-Dec-16
95
A8280
6
6 7-Day Workweek
0
Teacher desks
11-Sep-16*
18-Sep-16
16-Dec-16
22-Dec-16
95
Page 9 of 10
Project Start 10-Oct-13 Project Finish 28-Oct-17 Data Date 10-Oct-13
MONROE CAMPUS... Report Date 14-Apr-14 20:56
SR-01 Classic Schedule Report - Sort by ES, TF
Activity ID
Orig Rem Calendar Dur Dur
% Department Activity Name
Early Start
Early Finish
Late Start
Late Finish
Total Float
A7540
6
6 7-Day Workweek
0
Fire protection specialities
12-Sep-16*
17-Sep-16
12-Sep-16
17-Sep-16
0
A7560
10
10 7-Day Workweek
0
Window shades
18-Sep-16*
27-Sep-16
18-Sep-16
27-Sep-16
0
A8290
8
8 7-Day Workweek
0
Hydraulic elevators
18-Sep-16*
26-Sep-16
22-Dec-16
30-Dec-16
95
A8700
9
9 7-Day Workweek
0
Checklist classroom roe
26-Sep-16
05-Oct-16
30-Dec-16
08-Jan-17
95
A7570
7
7 7-Day Workweek
0
Wire mesh partitions
28-Sep-16*
04-Oct-16
28-Sep-16
04-Oct-16
0
A7580
13
13 7-Day Workweek
0
Install lockers
05-Oct-16*
17-Oct-16
05-Oct-16
17-Oct-16
0
A7590
9
9 7-Day Workweek
0
Install hood and walk-ins
18-Oct-16*
26-Oct-16
18-Oct-16
26-Oct-16
0
A7610
5
5 7-Day Workweek
0
Install and setup food service equipment
27-Oct-16*
31-Oct-16
27-Oct-16
31-Oct-16
0
A7620
5
5 7-Day Workweek
0
Glass wall folding partition
01-Nov-16*
05-Nov-16
01-Nov-16
05-Nov-16
0
A7630
12
12 7-Day Workweek
0
Loading dock equipment
06-Nov-16*
17-Nov-16
06-Nov-16
17-Nov-16
0
A7640
5
5 7-Day Workweek
0
Paint gym ceiling
18-Nov-16*
22-Nov-16
18-Nov-16
22-Nov-16
0
A7650
7
7 7-Day Workweek
0
Gym equipment
23-Nov-16*
29-Nov-16
23-Nov-16
29-Nov-16
0
A7660
9
9 7-Day Workweek
0
Gym dividers
30-Nov-16*
08-Dec-16
30-Nov-16
08-Dec-16
0
A7670
7
7 7-Day Workweek
0
Install hardwood flooring
09-Dec-16*
15-Dec-16
09-Dec-16
15-Dec-16
0
A7680
6
6 7-Day Workweek
0
Install collapsable belachers
16-Dec-16*
22-Dec-16
16-Dec-16
22-Dec-16
0
A7690
8
8 7-Day Workweek
0
Hydraulic elevators
22-Dec-16*
30-Dec-16
22-Dec-16
30-Dec-16
0
A7600
10
10 7-Day Workweek
0
Install kitchen tiles
30-Dec-16*
09-Jan-17
30-Dec-16
09-Jan-17
0
A8710
9
9 7-Day Workweek
0
Checklist student life building
30-Dec-16
08-Jan-17
30-Dec-16
08-Jan-17
0
A8780
79
79 7-Day Workweek
0
Close out procedures
08-Jan-17
28-Mar-17
08-Jan-17
28-Mar-17
0
A8810
176
176 7-Day Workweek
0
Demobilize job trailers
08-Jan-17
03-Jul-17
04-May-17
26-Oct-17
116
A7550
9
9 7-Day Workweek
0
Motorized projection screens
09-Jan-17*
18-Jan-17
09-Jan-17
18-Jan-17
0
A9440
1
1 7-Day Workweek
0
Final Milestone
27-Oct-17*
28-Oct-17
27-Oct-17
28-Oct-17
0
Page 10 of 10