Efficiency in the Data Centre Jack McArdle Managing Director Kirlaur Ltd
Introduction • Jack McArdle • Kirlaur Ltd – Independent Data Centre Consultancy – Design and Build Management – Efficiency Engineering – ROI Engineering – UPS Management – SMART Metering – Data Center Project Management
Jack McArdle ©2013
• Partnerships • Levant UPS Ltd – UPS Design and Maintenance
• Trendpoint Inc – European Distributor – SMART Metering
• Clients – – – –
Axcess Financial Ltd Gamma Telecom Ltd ScoLocate Scotland Online
Some Statistics • •
If all the Data Centres in the world were a country they would rank somewhere between Spain and Italy in power consumption (DCD Intelligence 2013) Approximately 38Gw of power used by Data Centers worldwide –
63% increase in the last 12 months (Data Centre Dynamics)
Jack McArdle ©2013
Efficiency What actually is Efficiency? Will it save money? Yes it will help reduce Operating Costs! Will it save the planet? It won’t do any harm! Will it save resources? It will help! Is it working smarter? Best practice always helps! Good discipline in the industry
It is all of these things! How do you quantify it? Jack McArdle Š2013
Metrics If you don’t know what the Data Center is doing you can’t make value decisions for change! There are many metrics available for Data Center reporting. The trick is to find the one that suits you, that you will continually manage and report on, and is not too onerous to carry out. • • • • • •
PUE/DCiE: Power Usage Effectiveness/Data Centre Infrastructure Efficiency pPUE : partial Usage Effectiveness WUE: Water Usage Effectiveness DCcE: Data Center Compute Efficiency ERE: Energy Re-Use Efficiency CUE: Carbon Usage Efficiency
Jack McArdle ©2013
PUE, DCiE and pPUE • Developed by The Green Grid and has received a lot of attention. • “The Green Grid notes that many published PUE or DCiE numbers are not measurements but are estimated by engineers for hypothetical conditions, such as for Data Centers under construction, or for IT loads other than the actual IT load” • Now a ‘marketing term’ • Typically addresses the facilities side of the equation. • Is a continual process, not a goal. • There is an assumption that ‘lower PUE’s are better’. Jack McArdle ©2013
Metrics PUE
DCiE
PUE is defined as the ratio DCiE is defined as the reciprocal of of Total Facility Energy to PUE x100 (expressed as a IT Equipment Energy percentage) PUE = Total Facility Energy IT Equipment Energy
DCiE = IT Equipment Energy Total Facility Energy x 100
800kW
500 800 X 100 = DCiE = 62.5%
500Kw
Jack McArdle Š2013
= PUE =1.6
Power Consumption with PUE = 1.6
5 kW 15 kW
1MVA
240 kW
Ventilation – Fresh Air
Lighting & small power
Cooling fans, pumps & compressors
IT 500 kW
35 kW
IT terminal load Distribution & conversion losses
3 kW Security, BMS 2 kW Communications
Total 800 kW
Jack McArdle ©2013
Three Tier Approach to PUE Level 1 (L1) Basic
Level 2 (L2) Intermediate
Level 3 (L3) Advanced
IT Equipment Energy
UPS Outputs
PDU Outputs
IT Equipment Input
Total Facility energy
Utility Inputs
Utility Inputs
Utility Inputs
Measurement interval
Monthly/Weekly
Daily/Hourly
Continuous <15 minutes
Jack McArdle Š2013
PUE Levels (Green Grid) Level 1 Basic
Level 2 Intermediate
The IT load is measured at the output of the UPS equipment and can be read from the UPS front panel, through a meter on the UPS output, or, in cases of multiple UPS modules, through a single meter on the common UPS output bus. The incoming energy is measured from the utility service entrance that feeds all of the electrical and mechanical equipment used to power, cool, and condition the data center
The IT load is measured at the output of the PDUs and can b typically be read from the PDU front panel or through a meter on the secondary of the PDU transformer. Individual branch circuit measurement is also acceptable for Level 2. Intermediate monitoring requires, at a minimum, the collection of power measurements once a day.
Level 3 Advanced The IT load is measured at each individual piece of IT equipment within the data center, either by metered rack PDUs (i.e., plug strips) that monitor at the strip or receptacle level or by the IT device itself. Note that non-IT loads must be excluded from these measurements. Advanced monitoring requires, at a minimum, the collection of power measurements once every 15 minutes or less; for energy measurements, that frequency is recommended. Level 3 measurements should not require human activity to gather and record data. Jack McArdle Š2013
Efficiency Planning Initial Steps Ghost Servers
–Switch them off
HVAC
–Set-Points!!
•1degC saves 3 – 4%
Air-Flow
–Clear and Free
Filters
–Keep them Clean
Monitor
–Temperatures –Humidity
Jack McArdle ©2013
Next Steps Metering What Where When Data Collecting Reporting Plan of Action Carry it Out Review improvements Quantify Savings Speculate
Speculate to Accumulate Install Metering Branch Metering in PDUâ&#x20AC;&#x2122;s Automatic Collection of data
Install Vari-Control Fans Consider Adiabatic Cooling PiR Controlled Lighting Containment Systems
Jack McArdle Š2013
Containment Systems Hot Aisle Containment •Works well in racks with <5kW density •Captures hot-air from the back of racks and returns to CRAC unit, or extract •Uses plenum as Cold Air intake •Requires blanking plate management
Cold Aisle Containment •Works well in racks with >5KW •Focuses cold air to front of rack. •Data Centre surrounds become hot •Requires blanking plate management
Jack McArdle ©2013
Containment Systems Do Pick the right system Perimeter Cooling Raised Floor Cold Aisle CRAC/In Rack Hot Aisle Use Blanking Plates Monitor Temperatures
Donâ&#x20AC;&#x2122;t Leave doors open Leave floor tiles up Mount kit the wrong way Remove blanking plates
Be Aware Fire Suppression Working in area Visitors
Achieving a Low PUE Cooling efficiency • Site selection, latitude and local climate (water-usage a limiting factor?) • Rigorous air-management in the room (limited by delta=T?) • High server inlet temperature (avoiding fan ramp-up, 27°C) • Minimum humidification and de-hum (if any?) • Free-cooling coils for when the external ambient is cool • If possible avoid compressor operation altogether Power efficiency • Avoid high levels of redundancy and low partial loads in general • Design redundancy to always run at >60% load • Adopt high-efficiency transformer-less UPS where efficiency is c96% at • 60% load • Adopt eco-mode UPS where efficiency is 99% for >95% of the year • Apply high efficiency lighting • Best practice gets us to a PUE of 1.2
Jack McArdle ©2013
Lower PUE is good, isn’t it? On Average a typical DC has a PUE of2.0 High range > 2.75 Low range < 1.5 Q: What happens to PUE if we raise the temperature?
A: Cooling load goes down R: PUE goes down
Q: What happens to PUE if we shut 10% of servers that are deemed ghost servers? A: IT load goes down R:: PUE goes up Q: What happens if we also throttle the cooling to meet the new lower IT loads? A: IT load goes down, Cooling load goes down, R: PUE could remain the same
PUE is useful but may not be the ‘end all’. Ultimately you want to minimize waste and save money
PUE Varies by Month, and Load PUE by Month and Load 12.00 11.00 10.00
100%
9.00
90%
8.00
80%
7.00
70%
6.00
60%
5.00
50%
40%
4.00
30%
3.00
20%
2.00
10%
1.00 Jan
Jack McArdle Š2013
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Can Data Centers be ‘Sustainable’, or Green? Not on their own! •Data Centers are the factories of the digital revolution •They convert power into digital services •Impossible to quantify efficiency as there is no ‘work done’ •Energy is treated as waste, and usually dumped into the environment
They won’t be green unless: •The load is a low-carbon solution •Energy consumption is minimised by best of breed hardware •PUE is reduced to the minimum •Power is sourced from 100% renewable sources •Waste heat is re-used extensively
Jack McArdle ©2013
Efficiency Planning
Monitor
Improve
• Investigate
Record
• Speculate
Monitor
Jack McArdle ©2013
Change
• Plan
Monitor
Record
Review
Change • Savings
Thank You Questions?