What is the difference between Piping and Pipeline? Pipeline - Long series of Pipes usually of large diameter often underground with few fittings & equipment's mostly Pumps & Valves mainly to control the flow, that are laid with an intention to transport any fluid whether liquid or gas over long distances.
The design of pipeline is governed by ASME B31.4 that is code for Liquid Transportation Systems for Hydrocarbons, Liquid Petroleum Gas, Anhydrous Ammonia, and Alcohol and ASME B31.8 that is a code for Gas Transmission and Distribution Piping Systems. The constructions drawing here are termed as alignment sheet. Pipeline design generally involves river crossing, highway crossing, rail line crossing etc. The pipeline is Series of straight pipe welded together over a long distance. The pipeline can run underground, aboveground and underwater such as a subsea pipeline. Pipelines are mostly large diameter that transport bulk liquid or gas from one place to other sometimes 1000s of miles in distance. In pipeline few equipment are used within the Pipeline system such as pumps, valves & instruments that support the function of the system to transport fluid safely over a long distance.
Piping - Large series & networks of Pipes within the well-defined boundaries of the plant/plot with all fittings & equipment's like Pump, Valves, Unions & other Miscellaneous items with an intention to transfer fluid from one facility to another within those boundaries as required.
Piping is designed in accordance with ASME B31.3 that is Process Piping code and for power plant piping ASME B31.1 that is code for Power Piping. The construction drawings here are termed as isometric drawings. Piping is a Complex network of pipe & fittings within the defined boundaries of the plant. Piping is mostly above ground with very few underground services. Piping can be from ½” to 80” as per the plant design requirements that transfer fluid from on equipment to another within the plant boundary. Variety of equipment such as a pump, valves, filter vessel, column, heat exchanger, instruments are used within the piping system that supports the function of the plant to produce finish product.
Onshore System SL. NO.
Onshore PIPELINE
1
Design Codes
2
ASME B31.4 : Pipeline Transportation Systems for Liquids and Slurries ASME B31.8 : Gas Transmission and Distribution Piping Systems
Ons
ASM
Scope Outside plant boundary Cross-country (i.e. villages, fields, river, canal, railway, highway, cities, deserts, forests, hills, Ghats etc.)
Wit (up
3
Type of pipe Line pipes as per following code:
4
API Spec 5L: Specification for Line pipes
Ass
Valves Valves are procured as per following code:
API 6D: Specification for Pipeline and Piping Valves
Valv
Full Bore (FB) Ball Valves are used for smooth passage of pigs.
5
API Std. 1104: Welding of Pipelines and Related Facilities
We
Type of welding: Automatic / Semi-Automatic/ Manual
ASM We Typ Ma
Weld joint inspection (NDT requirements) 100% by Automatic UT or RT (by using X-Ray)
7
BS API Full as p pigg
Welding Welding code:
6
AST BS API
5%
Analyses - Wall Thickness Analysis - Elastic Bend Radius Analysis - Stability Analysis for Water Bodies/ Marshy Areas - Horizontal directional drilling design analysis - Railroad/ Highway Crossing Analysis - Casing Pipe Analysis for Crossings - Seismic Analysis
- Pip Spe - Pip per Stati Dyn Win
8
Flan Seis
Installation Buried (mostly)
9
Abo
Special Installations
10
Across rivers Horizontal Directional Drilling (HDD) method Micro-tunneling method Across road/ rail/ highway Auger boring/ jacking boring method Shallow HDD Ghats/ Hills – Special equipment used
Spe Mo Finn Stu Jack Spo U/G
Exp Mo Cry Spr
Win Seis
Pain
Special Equipments
11
Sectionalizing Valves (Remote operated) Insulating Joints Scraper Launcher/ Receiver Stem Extended Valves (for buried valves) Flow Tee Long Radius bends (R=6D) Cold field bends (R = 30D or 40D) Survey
12
Topographical Survey (all along the pipeline route) Geotechnical investigation (all along the pipeline route) Soil resistivity survey (all along the pipeline route) Hydrological Survey for water bodies (for scour depth calculation) Cadastral Survey (for RoU acquisition) Corrosion Protection Coating
Three Layer Polyethylene (3LPE) coating
13
Three Layer Polypropylene (3LPP) coating Fusion bonded epoxy (FBE) coating Coal tar enamel (CTE) Coating
Cathodic Protection System
14
Impressed Current Cathodic Protection (ICCP) system Sacrificial Anode (limited locations)
Not
Hydrostatic testing Gauge Plate run of 95% of ID of highest thickness of pipes
No to c
Test Pressure Minimum:
1.25 times of Design Pressure (for liquid pipelines) 1.25 to 1.5 times of Design Pressure (for gas pipelines) Maximum:
Pressure equivalent to Hoop stress of 95% of SMYS of pipe material Hold period: 24 hours (generally)
Test Min
1.5 Ma
bas Hol
Selection of hydrostatic test section based on elevation difference of ground profile 15
Preservation Preservation of pipeline with corrosion inhibited water or by filling of inert gas (N2)
16
Communication System Telecom/ SCADA
17
Not
Pigging
Not
Intelligent Pigging 18
Not
Machines/ Equipments required for installation
Trencher Backhoe/ Excavator Side Boom Cold field bending machine Holiday Detection Machines Pneumatic/ Hydraulic Internal Clamps
Offshore System SL. NO.
Offshore PIPELINE
1
Design Codes
2
DNVGL-ST-F101 : Submarine pipeline systems API RP 1111 : Design, Construction, Operation and Maintenance of Offshore Hydrocarbon Pipelines (Limit state design)
ASM
Installation Subsea (in water on seabed or buried in seabed)
3
Dec
Survey (Subsea)
4
Offs
Geophysical survey/ Bathymetric Survey by using side scan sonar, sub-bottom profiler and echo-sounder Met-Ocean data collection Geo-technical data of the pipeline route
Not
Pipes Line pipes are utilized as per following specs:
Ass
5
API Spec 5L : Specification for Line pipes DNVGL-ST-F101 : Submarine Pipeline Systems
AST
Red pigg BS/
Dec
Valves
6
Full bore Valves for smooth passage of intelligent pigs are utilized as per spec: API 6D SS : Specification on Subsea Pipeline Valves Analyses
7
Wall thickness Analysis On-bottom Stability Span Analysis Global Buckling – Lateral and Upheaval Pipeline Expansion Analysis Riser Design (Span , Stress & Flexibility Analysis) Riser Clamp Design Pipeline Crossing Design and Analysis Installation Analyses such as :- Pipelay Analyses in OFFPIPE, Shore approach installation design & Analyses, Riser/ Expansion Spool installation analyses, Hoses lifting & installation analyses Environmental Loads (Met-ocean Parameters) Wave, current and external pressure and buoyancy
8
Win
Corrosion Protection Coating
9
Coatings such as:– Coal Tar Enamel Coating (CTE) Three layer polyethylene coating (3LPE) Three layer poly-propylene coating (3LPP) Double layer fusion bonded epoxy coating (DLFBE)
Pain
Cathodic Protection System Sacrificial Anodic Cathodic Protection (SACP) system
Not
10
Welding Welding is performed as per specification:
11
API Std. 1104 : Welding of Pipelines and Related Facilities Mostly automatic welding on pipelay barge.
We
Weld joint inspection (NDT requirements) 100% by Automatic UT
12
Mo
Special Equipments
13
Subsea Isolation Valve (SSIV) LR Bends Flow tee Pipeline End Manifold (PLEM) Single Point Mooring (SPM) system Submarine hoses Floating hoses Cables and umbilical installation Piggy-back pipelines
Not
Installation Equipment
14
Pipelay Barge Derrick Barge Diving support vessel Dynamic Positioning (DP) barge (for deep-water)
Pre
Alo
Installation Methods
15
ASM We Ma
S-lay Method (for shallow water installation) J-Lay Method (for deep water installation) Shore pull/ barge pull near Land Fall Point (LFP) Hydrostatic testing
16
Gauge Plate run of 95% of ID of highest thickness of pipeline. Test Pressure Minimum : 1.25 times x Design Pressure Hold period 24 hours
NDT requirements 100% weld joints by RT or AUT
17
No Test Ma Hol 2 ho
Var
Intelligent Pigging Compliant
Table source: - From Web Metallica is one of the oldest importers, and big steel seller and stockholder in India, its customers range from procurement managers to traders or resellers in almost every corner of India and overseas. Contact us now!
Not