Business Practices
Business Practices business issues Delegated Design
It is All about Communication
By the CASE Guidelines Committee
Project design and delivery systems have become more and more complex. The days when the Structural Engineer of Record (SEOR) designed all aspects of a project in a straightforward design-bid-build environment are becoming few and far between. Today, with the pressures on construction cost, design fees, and design and construction schedules, SEORs are looking to do more for less fee and in less time, while also delivering superior service. So, in addition to delegating the responsibility for the design for secondary structural elements (such as stairs, cladding, elevator rails, etc.), SEORs are also delegating the responsibility for the design of many primary structural elements (such as steel joists, metal deck, precast concrete slabs and beams, etc. in addition to traditional connection design) to a Specialty Structural Engineer (SSE). All of these elements introduce additional structural engineers into the process and, given concurrent changes in the design and delivery systems (design-build, designassist, integrated project delivery, etc.), it is not surprising that project participants have differing opinions as to what is the “design” and who has the ultimate responsibility for it. In such environments, the SEOR’s relationship with the SSE may be tested and strained and may become confrontational, particularly if the process is not managed well or if the motive of the SEOR for delegating is less than altruistic. Obviously, this is not the desired SEOR/ SSE relationship; the project will be better served with an atmosphere of trust, openness, understanding and cooperation. The owner, contractor, subcontractor and design team will all benefit from a non-controversial attitude with appreciation and acceptance of each other’s knowledge, expertise and experience.
Communication
There are three keys to this or any relationship, and they are not new. They are communication, communication and more communication that is clear, concise and non-compromising. The first step is the proper delegation of design responsibility and a well-defined scope of services within the SEOR’s initial engagement on the project. The Owner and the SEOR need to
agree to what will be designed by the SEOR and what aspects of the project will be designed by SSEs. It continues with concept development, the preparation of the specifications and construction documents, and is followed by pre-bid and pre-construction conferences. However, the process is not complete until the SSE’s submittals have been reviewed by the SEOR to confirm that the SSE’s interpretation of the design criteria is appropriate and acceptable, and the totality of the work is coordinated and complete.
Primary and Secondary Structural Elements
The issue that has most complicated the relationship between the SEOR and SSE has been the recent trend of including primary structural elements in the process. Design delegation of secondary structural items such as stairs, handrails, davits, and elevator support rails and beams, has been accepted for some time; their design is governed by time tested industry standards and practices. However, the delegation of the design for primary structural elements such as light gage trusses, wood trusses, structural precast concrete panels, post-tension concrete members, metal deck, and structural steel connection design has established the necessity for the SEOR to fully define the loading, design criteria and performance standards for each primary structural element to enable the SSE/subcontractor to properly develop their design/proposal. While the secondary systems are important to the functionality of the completed structure, the primary systems have unique needs associated with structural stability and coordination requirements of code compliance and public safety. Therein lies the rub. The SEOR’s delegation of the design of primary structural elements to an SSE requires project specific loading, design and acceptance criteria, and a comprehensive understanding of how the entire, sometimes unique, structural system is to perform while secondary elements may be acceptable as more standardized “off-theshelf” type items. As a possible rule of thumb, to develop a base line for what information is needed by the SSE, the SEOR needs to ask the question “what would I need if I had to design it myself?” More often than not, the SEOR probably does not spend as much time thinking about the “to be delegated” items, as he believes that the responsibility has passed on to the SSE and they are now someone else’s concern. This is definitely the wrong attitude to have, since the responsibility for the entire project still lies with the SEOR. If various SSEs design less than adequate systems based on poorly drafted or considered design and performance criteria, the result will be a poor project with many design and construction problems. In a worst case scenario, the SEOR will wish that he had just designed the delegated systems in-house. As an example of possible pitfalls, roof systems like steel joists, light gage trusses and wood trusses may require special loading as necessary for snow drift, mechanical units, solar panels, roof drain piping, seismic bracing, and sprinkler piping. The snow drift and roof drain piping loading are definable and should be shown on the contract documents. On the other hand, mechanical units loading and size may not be known until a mechanical subcontractor has been selected and requires the SSE to coordinate with the general contractor. Seismic bracing loads will be provided to the SSE by another SSE who was selected to design anchorage and bracing for piping and equipment. Sprinkler piping is even less defined than the mechanical units. Many times, the only information known about the sprinkler system is the location of the water line entering the building. Again, the layout and loading from the sprinkler is known after the sprinkler subcontractor is selected and the system is designed
by his SSE. Th e fundamental issue with these unknowns is whether the SSE is aware they exist so that he is not blindsided after or during his design eff ort. Th e owner will not be happy to be drawn into a war between the SEOR and the contractor and a small army of SSEs. As another example, the Steel Joist Institute (SJI) 2010 Code of Standard Practice for Steel Joists and Joist Girders states that the SEOR shall “calculate and provide the magnitude and location of ALL JOIST and JOIST GIRDER LOADS”. Th e term “ALL” implies a level of completeness that might not be achievable by the SEOR. Th ere will probably be some unknowns that the SEOR will need to make the SSE aware of, and there are loadings that will require his coordination with other trades. Th is SJI Code also identifi es fi ve (5) options that are to be used to specify joist design loads. Th e SEOR shall use one of the fi ve options to allow: • Th e estimator to price the joists; • Th e joist manufacturer to design the joists properly; or • Th e owner to obtain the most economical joists. Th ese issues of properly estimating the cost, properly developing the design and providing the economics for the Owner seem to be creditable goals for the relationship of the SEOR and the SSE.
Standards
But let’s go beyond the not so straightforward issue of developing specifi c design and performance criteria. How is the delegated design going to be achieved and what standards are going to be followed? Th ere are many important issues to consider: • Do you understand the industry code of standard practice for the element being delegated? Does it even exist? Is it insurable? • If you don’t like what is in the code of standard practice, you have the opportunity to change it via the contract documents. Do you know what needs to be changed? Does your understanding of the code enable you to be certain that a particular change does not impact other aspects of the code? • Is the SEOR responsible for specifying and also verifying the qualifi cations and experience of the SSE? • Is there a means to ensure that the
SSE has interpreted the SEOR’s requirements properly during the bidding stage? • Who is responsible for the coordination and/or compatibility of the primary structure (designed by the SEOR) with the delegated design portion (designed by SSE)? • How are the material quantities, details and loadings of the delegated design portion being accounted for in the fi nal design by the SEOR? • Who is responsible for the fi nal product? Again, communication plays a key role. • What is the impact of the elements designed by the SSE on the primary structural system? • Must SEOR review the results of the
SSE’s design to establish compliance with the governing codes and specifi cations?
Selecting the SSE
After the scope of work, including the project specifi c loading, design and acceptance criteria, is defi ned, the next step is the selection of the subcontractor. To ensure the contractor’s SSE is knowledgeable and experienced in the design of the designated elements, the SEOR should establish in the contract documents the minimum qualifi cations and experience of the SSE. One might say that the subcontractor that is retaining the SSE should be responsible for his selection, and ultimately the subcontractor will have to live with the designs prepared by his SSE. However, a poor selection, possibly the low bidder, may lead to not just the subcontractor having issues but the total design and construction team having to live with the poor results, extensive rework or modifi cations and the possibility of litigation. Th e possibility of litigation leads to the question – does the SSE have liability insurance and, if so, how much? Is it suffi cient based on the nature of the element and its importance in the strength and integrity of the overall structure? It is important to note that being a licensed Professional Engineer or licensed Structural Engineer does not mean that he or she has the knowledge and experience to perform the design services needed. It is imperative that the SEOR’s contract documents adequately defi ne the SSE’s qualifi cations and experience requirements.
Limits on Delegation
What about the material that has not been designed and is to be designed after the bids have been taken? If the bids or proposal to do the work establish qualifi cations to these unknown quantities, this can lead to controversy. Again, establishing the complete scope,
Triple Protection Against Corrosion
Increase Corrosion Resistance
Use in areas susceptible to corrosion and chloride
Prevent unsightly appearance to concrete
Increase the life expectancy of metals, steel and rebar
Repel Water
Reduce Chloride Permeability
Add Corrosion Inhibitor to Cement All® , Mortar Mix, Concrete Mix and DOT Repair Mix for triple protection against corrosion
800-929-3030 ctscement.com
defi nition and responsibility of the work to be performed by the SSE is the principal duty of the SEOR. While the construction documents, drawings and specifi cations are the primary tools, the pre-bid and pre-construction conferences can be useful in clarifi cation and confi rmation that the project requirements are understood. Th e 2010 AISC Code of Standard Practice (COSP, AISC 303-10) includes a codifi cation of an undefi ned and uncontrolled but widely employed industry practice that had existed since the 1960s. Section 3.1.2 defi nes the connection design or selection process, identifi es the loading and connection information that must be supplied by the SEOR and SSE, and addresses any project or design concept specifi c issues or restraints that are to be considered. Th e COSP has designated delegated steel connection design as Option (3). Th is option is to be noted “In the structural design drawings or specifi cations, the connection shall be designated to be designed by a licensed professional engineer working for the fabricator”. Th e COSP establishes the information needed by the SSE and emphasizes needs for conferences, pre-submittals and proper review and approval by the SEOR. Th e CASE Guidelines Committee has recently published a white paper on this facet of delegated design in A Review and Commentary of the American Institute of Steel Construction 2010 Code of Standard Practice for Steel Buildings and Bridges. Incorporated in this new document are examples of Pre- Bid and Pre-Construction Conferences agendas. Th e ability to delegate design elements may also be limited by local building codes, regulations, and professional licensure requirements. When developing standard language for inclusion in contracts, the SEOR should review these requirements before attempting to delegate design responsibilities. A local jurisdiction may have specifi c code language requiring the SEOR to design items which are not normally included in the SEOR’s basic services. On those occasions, the SEOR should address those secondary items, modify the contract documents accordingly and include the design of these elements in his basic services and not delegate the design of such elements.
Summary
In summary, it is important to view delegated design as a way to achieve the best possible project result for the owner given the project constraints on fee, schedule and quality. It is obviously a complicated process that requires considerable knowledge and skill in order to achieve success. Communication is the key, and it starts at the very beginning of the project. It requires that the SEOR continually thinks about what will be needed by the SSE, how best to specify the requirements of the design, how to defi ne the process and how the interaction of other designers is going to work, and who can and cannot be an SSE. It is much easier to discuss concerns and issues as the project is developing during the design phase or in the pre-bid/pre-construction meetings, than it is to correct the problems after the fact. You are part of a team, and part of the process, so be proactive within your discipline and promote eff orts to coordinate. Insist on two-way communication with an open mind to ensure the best understanding possible to those interpreting your design and intent.▪
Th e goal of Th e Council of American Structural Engineers (CASE) is to promote excellence in structural engineering business practices and risk management. Th e information presented in this article was developed by CASE members who volunteer their time and expertise to advance the structural engineering profession.
ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org



The only product recommended by FEMA and the US Army Corps of Engineers for fast repair of columns and piles following natural disasters.
UNDERWATER PILES • STEEL POLES • CONCRETE PILES • TIMBER PILES • UTILITY POLES • BRIDGE PILINGS • PILE EXTENSIONS
9 3-4 times stronger than steel with tensile strength more than 150,000 psi 9 Fastest repair & strengthening system with no traffic control 9 Increase axial capacity beyond original strength of column/pile 9 No weak seams along height offers uniform confining pressure (360°) 9 No costly divers for underwater repair 9 Underwater cured resin eliminates the need for coffer dams 9 Does not corrode 9 No metallic parts 9 Grout or resin can be pressurized to penetrate all cracks and crevices 9 Available in carbon or glass 9 Works equally well on concrete, steel and wood or timber piles and columns 9 One size fits all piles (no delays for ordering customized jackets)
CALL US TODAY FOR A FREE CONSULTATION!
TM
By QuakeWrap, Inc.
1-866-782-5397 www.PileMedic.com
BEFORE AFTER
American Wood Council
Phone: 202-463-2766 Web: www.awc.org Product: ANSI/AF&PA SDPWS-2008 Description: Special Design Provisions for Wind and Seismic standard with Commentary; covers materials, design, and construction of wood members, fasteners, and assemblies to resist wind and seismic forces.
CSC
Phone: 877-710-2053 Web: www.cscworld.com Product: Tedds Description: Automating your everyday structural designs, Tedds broad library includes anchor bolt design per ACI 318 Appendix D. The calculation includes comprehensive checks for tensile and shear failure of anchors and is available as part of a free trial at the website.
Product: Fastrak Description: Software for designing structural steel buildings using a single model, also provides an integrated design of anchor bolts.
All Resource Guides and Updates for the 2014
Editorial Calendars are now available on the website, www.STRUCTUREmag.org. Listings are provided as a courtesy. STRUCTURE® magazine is not responsible for errors. CTP
Phone: 219-878-1427 Web: www.ctpanchors.com Product: Concealed Masonry and Stone Panel Description: Non-corrosive restoration anchors used to re-anchor masonry facades to various building materials.
Decon® USA Inc.
Phone: 866-332-6687 Web: www.deconusa.com Product: JORDAHL Anchor Channels Description: Decon USA is the exclusive representative of JORDAHL in North America. Hot rolled Anchor Channels are embedded in concrete and used to securely transfer high loads. Their main application is for flexible connections of glazing panels to high-rise buildings. Anchor Channels with weldedon rebar or corner pieces are available.
Gripple Inc.
Phone: 630-406-0600 Web: www.gripple.com Product: Gripple Spider Description: A cast-in-place insert/hanger solution for concrete ceilings, the Spider is installed prior to the concrete pour. From the ground, a special Swivel Toggle cable hanger inserts into the Spider and locks in place to provide a secure hanging point for ductwork or other suspended services. Sold in a ready-to-use kit.
ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org Halfen USA
Phone: 800-423-9140 Web: www.halfenusa.com Product: Anchor Channels Description: Halfen Anchor Channels are typically hot dipped galvanized with welded I-anchors. They are foam filled to keep concrete out of the channel cavity while the concrete is poured and vibrated. A t-bolt is used for attachment. There is no welding or drilling required onsite. Hayward Baker
Phone: 800-456-6548 Web: www.haywardbaker.com Product: Anchors – Ground or Rock Description: Hayward Baker Inc., provides permanent, temporary, and removable ground and rock anchors for support of excavations, permanent resistance of hydrostatic uplift forces on bottom slabs, and resistance of windinduced uplift forces. Hayward Baker also provides the full range of geotechnical construction services.
Heckmann Building Products, Inc.
Phone: 800-621-4140 Web: www.heckmannanchors.com Product: Pos-I-Tie® ThermalClip™ Description: This new break-through in masonry construction adds thermal-break technology to all of the advantages of the Original Pos-I-Tie Veneer Anchoring System! The ThermalClip decreases thermal transfer and has over 100 times less conductivity than metals such as steel. The snap-on design provides for easy installation.
MADE ENTIRELY IN THE USA

Veneer Anchoring Solutions

Original Pos-I-Tie® Install the Original Pos-I-Tie® into the backup
THERMAL BREAK IS A SNAP
ThermalClipTM Insert Pos-I-Tie® ThermalClipTM onto the head of the Original
Pos-I-Tie®


Close both sides of the Pos-I-Tie® ThermalClipTM until they SNAP! Combine the time-tested features of the Original Pos-I-Tie® veneer anchoring system with the all new Pos-I-Tie® ThermalClipTM to create a thermal break in a SNAP!
Place Pintle Wire Tie into the eyes of the Pos-I-Tie® ThermalClipTM EASY • EFFECTIVE • INNOVATIVE
www.HeckmannAnchors.com
info@heckmannanchors.com • (800) 621-4140
Hilti, Inc.
Phone: 800-879-8000 Web: www.us.Hilti.com Product: Hilti Mechanical and Adhesive Anchors Description: Hilti Mechanical Anchors including HDA, Kwik Bolt-TZ and Kwik HUS-EZ. Hilti Adhesive Anchors including HY-150 MAX-SD and RE 500-SD.
Hohmann & Barnard
Phone: 631-234-0600 Web: www.h-b.com A MiTek - BERKSHIRE HATHAWAY COMPANY Product: Sharktooth Insert Description: An adjustable anchor for Precast, Relief Angles and Partition Top applications with working loads up to 8,000 lb/ft. Product: Thermal 2-Seal Wing Nut Tie Description: Features a Polymer Coated Steel Wing that is encapsulated in UL-94 Plastic to reduce thermal transfer through rigid insulation and wallboard.
ITW Commercial Construction, North America
Phone: 630-825-7900 Web: www.itwredhead.com Product: Epcon S7 Description: Epcon S7 is the new fast cure, all weather code approved Red Head adhesive! This hybrid adhesive has the ability to work fast with the strength and reliability of an epoxy. Formulated and code approved for use in water saturated, submerged and damp holes (ICC-ES ESR 2308). Powers Fasteners
Phone: 985-807-6666 Web: www.powers.com Product: Post-installed Concrete Anchors Description: IBC Listed/Compliant Anchors: Powers-Stud+ SD1/SD2 wedge anchors – PE1000+ / AC100+Gold adhesive anchors – Self Tapping Concrete Screws – Vertigo & Snake overhead anchors – Atomic Undercut anchors
RISA Technologies
Phone: 949-951-5815 Web: www.risa.com Product: RISABase Description: When accuracy counts, RISABase delivers. RISABase uses an automated finite element solution to provide exact bearing pressures, plate stresses, and anchor bolt pull out capacities, eliminating the guess work of hand methods. Define bi-axial loads and eccentric column locations. Choose from several connection types and specify custom bolt locations.
Simpson Strong-Tie
Phone: 925-560-9000 Web: www.strongtie.com Product: Mech. Anchors, Adhesives & Design Software Description: Innovative, code-listed anchors and fasteners, including Titen HD® screw anchor, StrongBolt® 2 wedge anchor and SET-XP® and AT-XP adhesives. New 3D Anchor Designer™ software has 42 pre-loaded anchor configurations. USP Structural Connectors
Phone: 952-898-8772 Web: www.uspconnectors.com Product: USP Structural Connectors Description: Since 1954, USP Structural Connectors (a division of Mitek) has become the world’s leading manufacturer of code approved, structural connectors and innovative software solutions. USP’s 4000+ products are engineered, manufactured and tested to withstand Mother Nature, and are backed by our professional engineering and technical support teams and international sales.
Williams Form Engineering Corp.
Phone: 616-866-0815 Web: www.williamsform.com Product: Anchor Systems Description: Williams Form has been providing threaded steel bars and accessories for rock anchors, soil anchors, high capacity concrete anchors, micro piles, tie rods, tie backs, strand anchors, hollow bar anchors, post tensioning systems, and concrete forming hardware systems in the construction industry for over 90 years.
ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org