MINUTES OF MEETING Project :

Contract No. :

RIYADH PP-12 COMBINED CYCLE PLANT PROJECT

31121039/00 Dated on May 10,2012

Venue :

Date(time) of Meeting :

SEC Takhassusi Office, Al Mourooj Building

10th Nov. 2012 @ 1.30 PM

Purpose of Meeting :

Substation Crown elevation

Participants : SEC

Dar

BECO/JV

Mr. Mohd. Jalaluddin

Abdul Latif

Su Hun Lee Sang Jun Lee Mohamed Taher

Mr. Pashah

Zeeshan Bahadar

Alstom-Cogelex Mohammad Nashit Arsalan Umer

Distribution : ï‚· SEC, BEMCO / GS, Alstom File :

Minutes issued by :

Date :

Alstom

10th Nov. 2012

Alstom

No.

PP 12 - 380kV Sub Station

Action

Due

1

Sec will send their comments over site grading drawing in this week.

SEC

For info

1 of 2

Remark


No.

PP 12 - 380kV Sub Station

Action

Due

2

SEC informed us to provide only one crown elevation in revise drawing. Two crown elevation is not accepted by SEC.

Dar

12Nov 2012

3

SEC accept to have grading at some area as per 0.5% to 0.75% Slope

Dar

12Nov2012