




Contract Costing is a form of specific order costing where costs are attributed to contracts.
Essential features of contract costing:
(a)A formal contract is made between customer and supplier.
(
b)Work is undertaken to customers’ special requirements.
(c)The work is for a relatively long duration.
(
d)The work is frequently constructional in nature.
(
e)The method of costing is similar to job costing.
(
f)The work is frequently based on site.
(g)It is not unusual for a site to have its own cashier and time-keeper.
Types of Contracts:
(1)Cost-Plus Contracts: Cost-plus contract is a contract where the value of the contract is determined by adding an agreed percentage of profit to the total cost. These types of contracts are entered into when it is not possible to estimate the contract cost with reasonable accuracy due to unstable condition of factors that affect the cost of material, employees, etc.
(2)Target-price contracts: In such cases, the contractor receives an agreed sum of profit over his pre-determined costs. In addition, a figure is agreed as the target figure and if actual costs are below this target, the contractor is eligible for bonus for the savings.
Cost of Work Certified or Value of Work Certified: A contract is a continuous process and to know the cost or value of the work completed as on a particular date; assessment of the completion of work is carried out by an expert (it may be any professional like surveyor, architect, engineer etc.). The expert, based on his assessment, certifies the work completion in terms of percentage of total work. The cost or value of certified portion is calculated and is known as Cost of work certified or Value of work certified respectively. Payment is made on the basis of work certified.
Cost of Work Uncertified: It represents the cost of the work which has been carried out by the contractor but has not been certified by the expert. It is always shown at cost price. There is no role of work uncertified in payment.
Work-in-Progress: It costing refers to the work which is not complete on the reporting date.
Value of the work-in-progress = the cost of work completed, both certified and uncertified + the cost of work not yet completed + amount of estimated/notional profit (reserve for contingencies). [amount received from the contractee is subtracted from the WIP in the Balance Sheet]
Retention Money: In a contract, a contractee generally keeps some amount payable to contractor with himself as security deposit. To ensure that the work carried out by the contractor is as per the plan and specifications, it is monitored periodically by the contractee. This security money upheld by the contractee is known as retention money.
Retention money = Value of work certified- Payment made to contractor.
Notional Profit: It represents the difference between the value of work certified and cost of work certified.
Estimated Profit: It is the excess of the contract price over the estimated total cost of the contract. [can be calculated and feasible to calculate only in case of contracts whose end is near].
Escalation Clause: In order to protect the contractor from the rise in the price, an escalation clause may be inserted in the contract. Escalation clause in a contract empowers a contractor to revise the price of the contract in case of increase in the prices of inputs due to some macro-economic or other agreed reasons. As per this clause, the contract price is increased proportionately if there is a rise in input costs like material, labour or overheads.
Degree of completion of the contract (%) = Work Certified × 100/Contract Price
If the contract is in its early stages: No profit should be credited to Profit and Loss Account.
As a general rule, no profit should be recognised unless a contract is at least 25% complete.
In this case the portion of notional profit to be transferred to Profit & Loss Account is based on the degree of completion of the contract.
1. If the degree of completion of work is above 25% but less than 50% of total work
1/3 × Notional Profit × Cash Received/Work Certified
2. If the degree of completion of work is more than or equal to 50% of the total work but less than 90%,
2/3 × Notional Profit × Cash Received/Work Certified
If the contract is almost complete (Degree of composition is 90% or more):
1. Estimated Profit × Work Certified/Contract Price
2. Estimated Profit × Work Certified/Contract Price × Cash Received/Work Certified
3. Estimated Profit × Total Cost to date/Estimated Total Cost
4. Estimated Profit × Total Cost to date/Estimated Total Cost × Cash Received/ Work Certified
When an incomplete contract reveals a loss:
The whole amount of the loss must be charged to the profit and loss account of the accounting year.
Q.1. Fill in the blanks:
WIP appears on the credit side of the contract account when the contract is ……………… at end of the accounting period. [Dec. 2013, 1 Mark]
Ans. Incomplete
Q.2. A JBC machine was used on a contract site for the period of 7 months and depreciation on it was charged to the contract ` 78,750. If the working life of the machine is 5(five) years and salvage value is ` 25,000, then the cost of JBC machine will be:
(A) ` 7,00,000
(B) ` 4,18,750
(C) ` 6,75,000
(D) ` 3,93,750 [Dec. 2014, June 2015, 1 Mark]
Ans. (A) ` 7,00,000
Working Note:
Depreciation for one year 78,750 × 12/7 = ` 1,35,000
Depreciation for 5 years 1,35,000 × 5 = ` 6,75,000
Cost of Machine = Total Depreciation plus salvage value ` 6,75,000 + 25,000 = ` 7,00,000
Q.3. Match the items in Column I with the most appropriate items in Column II. State the item No. only:
Ans. (B) Contract Costing
Q.4. A contract is expected to be 80% complete in its first year of construction, as certified. The Contractee pays 75% of the work certified as and when certified and makes final payment on the completion of the Contract. The following information is available for the first year:
As the Contract is 80% complete, 2/3rd of Notional Profit on Cash basis has been transferred to P/L A/C in the 1st year of the contract. Thus, amount transferred to P/L A/C = 2/3 × Notional Profit × % of cash received Or, ` 60,000 = 2/3 × Notional Profit × 75% Or, Notional Profit = 60,000 × (3/2) × (100/75) = ` 1,20,000
Q.5. Match the items in Column I with the most appropriate items in Column II. State the item no. only
Ans. (B) Notional Profit
2017, 1 Mark]
Q.6. In the context of Contract a/c, work completed and not yet certified will be shown
(A) at cost plus + 2/3rd of the notional profit under ‘Completed Work’.
(B) at cost plus notional profit less retention money under ‘Completed Work’.
(C) at cost under ‘Completed Work’.
(D) at cost under WIP a/c. [June 2017, Dec. 2021, 1 Mark]
Ans. (D) at cost under WIP a/c
Q.8. _______ is to provide for any future decrease in price etc., so that the benefit may be passed on to the contractee.
(A) Reserve Clause
(B) Escalation Clause
(C) Contract clause
(D) Retrospective Clause [Dec. 2017, 1 Mark]
Ans. (B) Escalation Clause
Q.9 Contract Costing is often termed as a variant of the Job Costing System. [True/False] [Dec. 2017, 1 Mark]
Ans. True
Q.10 In contract costing, the cost unit is ________________. [June 2019, 1 Mark]
Ans. Per Contract
Q.11. Cost plus contract is usually entered into those cases where:
(A) Cost of certified and uncertified work
(B) Cost can be easily estimated
(C) Cost of certified work
(D) None of the above [Dec. 2022, 1 Mark]
Ans. (D) None of the above
Q.1. Explain the treatment of profits on incomplete work in contract accounts. [June 2013, 5 Marks]
Ans.
Treatment of profits on incomplete work in contract accounts:
(i) In case of contracts which are less than 25% complete, on profits should be taken into consideration and consequently no credit should be taken to Profit and Loss Account.
(ii) In case of contracts which are more than 25% complete, but less than 50% complete, the following method should be used for computing the profit to be credited to the Profit and Loss Account:-1/3 x Notional Profit x Cash Received/ Work Certified.
Notional Profit is the difference between the value of work certified and cost of work certified. It is computed in the following manner. Notional Profit = Value of work certified – [cost of work to date – cost of work completed but not certified].
(iii) In case of contracts complete between 50% and 90% [more than 50% but less than 90%] the following method is used for computing the profit to be credited to the Profit and Loss Account:- 2/3 × Notional Profit × Cash Received/Work Certified.
(iv) In case of contracts completed 90% or more than that, it is considered to be almost complete. In such cases, the estimated total profit is first determined by deducting the total costs to date and additional expenditure necessary to complete the contract from the contract price.
The portion of profit so arrived is credited to the Profit and Loss Account by suing any of the following formula:—
Method I – Estimated Profit × Work Certified/Contract Price
Method II – Estimated Profit × Work Certified/Contract Price × Cash Received/ Work Certified or Estimated profit × Cash Received/Contract Price
Q.2. What are the advantages of cost plus contract? [June 2014, 5 Marks]
Ans. Advantages of Cost Plus contract:
The advantages of cost plus contract are discussed below: —
(a) It protects the contractor from the risk of fluctuation of price of factor of production.
(b) Reasonable profit of the contractor is ensured as such profit is added to the actual cost incurred by him to determine the price of the contract.
(
c) The contractor pay a fair price for the work as price is based on actual cost which can be verified by the contractee from the books and documents of the contractor.
(d) At the time of unstable conditions this type of contract is most advantageous both to the contractor and the contractee.
Q.3. Write short note on Retention money in contract costing [June 2014, 5 Marks]
Ans.
Usually the contractee stipulates in the contract deed that he would withhold a part of the contract price to be paid at a later stage after completion of the contract.
This is to make sure that the contractor has performed all work relating to contract on the most satisfactory manner and that no repair work arises within a prescribed time limit.
The amount so withheld by the contractee is known as retention money.
It safeguards the interest of the contractee against the contractor, who may at time perform sub-standard work and gain there from.
This is done on the value of contract completed and certified by the architect/ surveyor appointed by the contractee.
The retention money will be paid once the contract is completed to the customer’s satisfaction.
The main advantage of Retention Money is safe-guarding the contractee against the default risk of contract.
Q.4. Write Short Note on Cost Plus Contract
[Dec. 2014, 5 Marks; Dec. 2021, 3 Marks] Ans.
In this type of contracts the contractor is usually entitled to a stipulated amount of profit in addition to actual cost of the service.
The amount of profit to be added to the actual cost of contract may be in the form of fixed amount on a percentage on actual cost.
This type of contract is generally entered into for executing special type of work which is not usually undertaken by the contractor.
Examples of this type of contracts are construction work during war, production of newly designed ship, etc. This type of contract is advantageous both to the contractor and the contractee.
Contractor generally receives a reasonable profit. He is protected from any loss or unusual risk.
Contractee can ensure a fair price of the contract because the contractee is entitled to verify the books of contractor.
Q.1. Compute a conservative estimate of profit on a contract (which has been 90% complete) from the following particulars. Also calculate the proportion of profit to be taken to Profit & Loss Account under any three methods.
Ans. Computation of estimated Profit
ParticularsAmount (`)
Contract Price6,12,000
Cost till date(4,50,000)
Further estimated cost(25,000) Estimated profit1,37,000
Computation of PROFIT to be transferred to profit & Loss Account under different Methods:
(i) Estd. Profit × Work certified/contract price = 1,37,000 × 5,50,800/6,12,000 = ` 1,23,300.
(ii) Estd. Profit × [Work certified/contract price] × [cash received/work certified] = 1,37,000 × [5,50,800/6,12,000] × [4,40,640/5,50,800] = ` 98,640.
(iii) Estd. Profit × Cost of work to date/Estd. Total cost = 1,37,000 × 4,50,000/4,75,000 = ` 1,29,789.47
(iv) Estd. Profit × [cost of work to date/Estd. Total cost] × [cash received/work certified] = 1,37,000 ×
Q.2. BATRON LTD., a contractor commences the contract No. HB-108 on 1st July, 2013. The details about the contract for the year ending 31st March, 2014 were following:
Material costing ` 15,000 was sold for ` 11,000 and plant costing ` 80,000 returned to stores on 31st December, 2013.
A crane costing ` 2,000,000 has been on the contract site for 73 days. Its working life is estimated at 6 years and its scrap value at ` 110,000. Depreciation on plant is to be charged @15% per annum. Up to 31st March, 2014, 3/4 (Three-fourth) of the contract was completed but architect’s certificate has been issued covering 2/3 of the contract price and 15,00,000 had been received in cash on account.
Required:
(a) Prepare the Contract No. HB-108 Account for the year ended March 31, 2014.
(b) State as to how much Profit should be credited to Profit and Loss Account for the year ended March 31, 2014. [Dec. 2014, 10 Marks]
BATRON LTD.
Contract No. HB-108 Account for the year ended March 31, 2014
(vi) Since, work certified is 50% or above, Profit transferred to P/L A/c = Notional profit × 2/3 × (cash received/work certified) = ` 2,63,375 × 2/3 × (15,00,000/20,00,000) = ` 1,31,687
Q.3. A company undertook a contract for construction of a large building complex. The construction work commenced on 1st April 2016 and the following data are available for the year ended 31st March 2017:
The contractor owns a plant which originally cost ` 20 lakhs and has been continuously in use only in this contract throughout the year. The residual value of the plant after 5 years of life is expected to be ` 5 lakhs. Straight line method of depreciation is in use.
As on 31st March 2017, the direct wages due and payable amounted to ` 2,70,000 and the materials at site were estimated at ` 2,00,000.
(i) Prepare the contract account for the year ended 31st March 2017. Present figures in (` ’000)
(ii) Compute the amount of profit/loss to be taken to the profit and loss account of the year ending 31-3-2017. [June 2017, 7 Marks]
Ans.
Particulars ` ’000 Particulars ` ’000 To Material Issued7,500By Material returned to stores 250
To Direct Wages Paid and accrued 4,270By Material at site200
To Wage related costs500By Work-in-progress:
To Direct Expenses902Work Certified20,000
% of Work Certified: (20,000/35,000) × 100 = 57.14%
Profit to be taken to Profit & loss Account = 2/3rd Notional Profit × Cash received/ Work certified = 2/3 × 3,324 × 15,000/20,000 = ` 1,662
Q.4. A contractor has undertaken a construction work at a price of ` 5,00,000 and begun the execution of work on 1st January, 2016. The following are the particulars of the contract up to 31st December, 2016.
It was decided that the profit made on the contract in the year should be arrived at by deducting the cost of work certified from the total value of the architect’s certificate, that 1/3 of the profit so arrived at should be regarded as a provision against contingencies and that such provision should be increased by taking to the credit of Profit and Loss Account only such portion of the 2/3rd profit, as the cash received to the work certified. Prepare the Contract Account showing the profit on the Contract.
Contract Account for the year ended December 31, 2016
% of Work completed:(3,90,000/5,00,000) × 100 = 78% Profit
2/3rd Notional Profit × Cash
Work certified = 2/3 × 59,450 × 3,60,000/3,90,000 = ` 36,585.
Q.5. A contractor, who prepares his accounts on 31st March each year, commenced a Contract No. 220 on 1st July, 2016. The following information is revealed from his costing records on 31st March, 2017:
salary
81,300
A machine costing ` 2,60,000 remained in use on site for 146 days. Its working life is estimated at 7 years and final scrap value at ` 15,000. A supervisor is paid ` 8,000 per month and has devoted one half of his time on the contract. All other expenses amount to ` 1,36,500. Materials at site on 31st March, 2017 cost ` 35,400. The contract price is ` 20,00,000. On 31st March, 2017 two-third of the contract was completed, however, the architect gave certificate only for 50% of the contract price and ` 7,50,000 had so far been paid on account. Prepare Contract Account and state how much profit or loss should be included on 31st March, 2017 in financial accounts. [June 2018, 7 Marks]
Ans.
Contract Account for the year ended March 31, 2017
Particulars `
To Foreman’s Salary81,300By Work-in-progress:
(ii) Calculation of Cost of Work Uncertified:
(iii) Since more than 50% work is certified, Profit
Account
Q.6. OMEGA LTD. undertook a contract for ` 5,00,000 on 1st January, 2017. The company furnishes the following details for the year ended 31st December, 2017:
useful life is 5 years.
` 60,000 with a scrap value of ` 10,000
plant was used on the contract for 146 days. Required: Prepare Contract Account showing therein the cost of materials issued to site and the amount of profit or loss to be transferred to the Profit & Loss Account. [Dec. 2018, 7 Marks; July 2023, 7 Marks]
3. Calculation of Depreciation on Plant = (60,000-10,000)/5 × 146/365 = ` 4,000
4. % Work Certified = 3,00,000 × 100/5,00,000 = 60%
5. Since more than 50% work is certified, Profit Transferred to Profit and Loss Account = 2/3rd Notional Profit × Cash received/Work certified = 80,000 × 2/3 × 2,70,000/3,00,000 = ` 48,000
Q.7. NIRVANA LTD. undertook a contract for ` 50,00,000 on 1st April, 2018. On 31st March, 2019 when the accounts of the company were closed, the following details about the contract were gathered:
The above contract contained an escalation clause which read as follows:
“In the event of prices of materials and rates of wages increase by more than 5%, the contract price would be increased accordingly by 25% of the rise in the cost of materials and wages beyond 5% in each case.”
It was found that since the date of signing the agreement, the price of materials and wage rates increased by 25%. The value of work certified does not take into account the effect of the above clause.
Required: Prepare Contract Account of the company as on 31st March, 2019. [June 2019, 7 Marks; Dec. 2021, 6 Marks]
Ans.
Contract Account for the year ended March 31, 2019
Working Notes:
(i) Calculation of Escalation Amount:
Cost of Materials and Wages incurred = ` 10,00,000 + 4,50,000 + 50,000 –2,50,000= ` 12,50,000
Cost of Materials and Wages before increase in prices = (` 12,50,000 × 100)/125= ` 10,00,000
Therefore, increase in Contract Price = 25% × [`12,50,000 – {(10,00,000 × 105)/100}] = ` 50,000
(ii) % work certified = 20,50,000 × 100/50,50,000 = 40.59%
% work certified is less than 50%, hence Profit to be credited to P&L A/c = Notional Profit × {(1/3) × (cash received/work certified)}
= ` 8,00,000 × {(1/3) × (15,00,000/20,50,000)} = ` 1,95,122
Q.8. OMEGA LTD undertook a contract for the construction of a building at a contract price of ` 45,00,000. During the first year, the following amounts were spent against which a sum of ` 16,87,500 (representing 90% of the work certified) was received by the contractor:
During the second year, the contractor spent the following amounts:
In the second year, the contract was completed and a sum of ` 26,25,000 was received by the contractor.
You are required to prepare the Contract Account and the Contractee Account for both the years and determine the profits. [Dec. 2019, 8 Marks]
(
certified is less than 50%, hence Profit to be credited to P&L
= Notional Profit × {(1/3) × (cash received/work certified)}
(ii) Since contract is completed in 2nd year, entire profit is transferred to Profit & loss
Q.9. Monteck Ltd., a construction company with a paid-up share capital of 50 lakhs undertook a contract to construct LIG house. The contract work commenced on 1st April, 2021 and the contract price was 50 lakhs. Cash received on account of the contract on 31-3-2022 was 18 lakh (90% of the work certified). Work completed but not certified was estimated at ` 1,00,000. As on 31-3-2022 material at the site was estimated at 30,000 and machinery at the site costing 2,00,000 was returned to stores. Plant and machinery at the site is to be depreciated at 5%. Wages outstanding on 31-03-2022 was 5,000.
(
(ii) Value of Work in Progress A/c to be shown in Balance Sheet = Work Certified + Work Uncertified – Reserve = 20,00,000 + 1,00,000 – 1,70,100 = 19,29,900
Working Notes:
(i) % work certified = 20,00,000 × 100/50,00,000 = 40% % work certified is less than 50%, hence Profit to be credited to P&L A/c = Notional Profit × {(1/3) × (cash received/work certified)} = ` 2,43,000 × {(1/3) × 90% = ` 72,900
Q.10. M/s. Goyal Brothers accepted a contract for the construction of a building for ` 10,00,000. Construction work started on 1st July, 2022 and the firm usually closes its books of account for the year on 31st March of each year. The contractee agreed to pay 90% of work certified as certified by the architect. During the first year, the amount spent was as follows:
Further Information:
(i) Materials costing ` 6,000 was damaged during the year.
(ii) A Supervisor who devotes one-half of his time on the contract has an outstanding salary for 2 months. He is paid @ ` 4,000 per month.
(iii) A special machine was hired for the contract for 4 months @ ` 500 per month.
Required: Prepare Contract Account in the books of the firm. Also show the amount of profit that can be transferred reasonably to the profit and loss account. [July 2023, 7 Marks]
AUTHOR : TARUN AGARWAL
PUBLISHER : TAXMANN
DATE OF PUBLICATION : AUGUST 2023
EDITION : 2023 EDITION
ISBN NO : 9789357781954
NO. OF PAGES : 468
BINDING TYPE : PAPERBACK
This book is prepared exclusively for the Intermediate Level of Cost & Management Accountancy Examination requirement. It covers the past exam questions & answers as per the syllabus of ICMAI.
The Present Publication is the latest 2023 Edition for CMA Intermediate | Dec. 2023 Exam. This book is authored by CA Tarun Agarwal, with the following noteworthy features:
Strictly as per the Syllabus of ICMAI
Coverage of the book concludes:
[Past Exam Questions] till CMA-Intermediate July 2023 Exam
Part I – Objective Questions [MCQs, Blanks, True/False, Match and Short Sums]
Part II – Descriptive Question
Part III – Numerical Problems
[Introduction] to each Chapter covering:
Important Definitions
Concepts
Formulas
[Sample Questions] for Topics newly introduced in the syllabus
[ Marks Distribution ] is given Module-wise from June 2017 onwards
[ Previous Exam Trend Analysis ] is provided in this book
[ ICMAI Study-Material Comparison ] is also given module-wise ORDER