Taxmann's Guide to Commercial Contract Management

Page 1

ABOUT THE BOOK

The Author realised the need of a guide to Commercial Contract Management in the current scenario where Government of India is making all attempts to enhance manufacturing sector to augment its GDP apart from self reliance (VOCAL for LOCAL) including infrastructure design & development and manufacturing in Indian Defence Production Sector and to take India towards ‘Aatmnirbhar Bharat’ even in defence. It struck that the core input for the development of this sector is contract management as the new industries need to be armed up with the various concepts including pitfalls in pre and post contract nalisation and operationalisation. The Book is providing crude input for delay and failure of the programme. Defence programmes have long gestation period and, hence, even bankers and insurance companies can take some input from the book while evaluating the proposals for sanctioning of borrowings/coverage of insurance. The Book will be of much help to the Students of Business Schools, Law Schools & Management Consultancy Firms. It can be helpful to private sector industries which want to penetrate in the eld of defence production. For getting appropriate insight into the Contract Management, the Of cials of Defence PSUs as well as private sector of cials can go through this Book and learn lot of complications and their solutions. I understand that there are multiple books on Contract Law but there is hardly any Book covering the Contract Law related issues and their solutions and even Contract Management techniques and its applications to generate success story for the Manufacturing Organisations and, particularly, Defence PSUs and private sector large integrated Defence Organisations. My personal perception is that it can be used even as a reference material to withstand the pressures of Audit.

KEY FEATURES

It enhances the skill sets of the key professionals involved in the field. There are relevant examples/case laws on the subject for enhancing knowledge base. I-17

Differentiate between specific clauses and general clauses of the contract and variance, if any.

This book deals with the deficiency in the generic mind set of public sector organization that smiling with a vendor is a corrupt practice and also the cases for the procurement management where vendor & customer are partners.

The book also suggest methodology where deviation from the laid down procedure is not to be treated as a corrupt procedure always as safety and security of the nation is of prime importance.

The book has cited examples where lack of transparency between vendor and customer results into delayed in project implementation.

The issues and obstacles in implementing “Atmanirbhar” in defence sector.

Covers man management and technology management.

The book even covers the requirement of self-reliance in Defence Design & Development, Equipment Manufacturing & Maintenance.

The book deals with hands-on experience of defence contract management-problem areas & tested solutions.

Depicts result of few questionnaires on status of contract management in defence.

Intricacies involved in contract management & reasonable solution as far as practicable.

This book seems to be helpful for lawyers & other professionals in drafting & vetting of contracts.

BOOK I-18
ABOUT THE

In the days of Covid-19 Pandemic, I didn’t know whether I will survive or not and in such circumstances it would be better to put my experience in writing so that it will be of some help to the future generation as this sector is going to grow in geometrical progression whether it is public sector or private sector.

Since the current Government is giving a lot of thrust for the development of defence industries and other manufacturing industries, I thought input available in this book will provide a basic guideline to the new entrant in industry while additionally adding learning and teaching in the management and law schools.

The book also covers some primary & secondary data collected in a research work on related eld & a result oriented, knowledge – team approach to execute goals and strategies. It may not be out of context to say, the focus on executing a few critical goals in contract management with excellence, will provide success or failure of the organisation entering the defence eld in particular as also in critical manufacturing where a lot of technology is involved. The most actionable & impactful insights from what I have learnt in the eld which covers both technical & commercial aspects of contract management of a manufacturing organisation apart from negotiating defence contract, nancial analysis, regulatory & legal management, is appropriately incorporated into the book. I hope the book may provide breakthrough results. It is unfortunate to observe that internal team of organisations don’t bother to conduct impact evaluation study for failures identi cation to improve their organisation performance. I am also astonished to see that the organisation is engaging external consultants to study & suggest solution to their problems instead of involving their own working & retired people who after retirement normally thinking good for their ex-organisation & knows problems & likely solutions. The book shares the author’s experience of conducting internal impact evaluation study for production failures by conducting two studies – uneven production in an manufacturing industry and cost of production v. cost of non-production.

PREFACE I-19

I don’t know how much but hope that it will provide reasonable working knowledge on the subject & I perceive that it will generate the spirit of analysing and improving the organisational performance through better contract management. If this book helps you in the journey of Contract Management then I will be very pleased that it has served the individual organisation and ultimately our motherland.

PREFACE I-20
CONTENTS PAGE Foreword I-5-I-13 About the Author I-15 About the Book I-17 Preface I-19 Acknowledgement I-21 List of Cases I-31 List of Abbreviation I-37 Disclaimer I-45 PART I INTRODUCTION & AEROSPACE/ DEFENCE INDUSTRY PERSPECTIVE 1 AEROSPACE & CONTRACT MANAGEMENT 1.1 Introduction 3 1.1.1 Concept of Contract Management 6 1.1.2 Types of Contracts 9 1.1.3 The role of modern contract manager 12 1.1.4 Smart Tools & Strategic Techniques 14 1.1.5 Emerging Opportunities 19 1.2 Concept of defence PSU contract 21 I-23
CONTENTS I-24 PAGE 1.3 Defence PSUs & Private Sector – Larsen and Toubro (L&T), Tata Defence Product Design, Development and Manufacturing, Kalyani Group, Hinduja Group - Ashok Leyland Defence & Alfa Design Technologies Pvt. Ltd. Bangalore 24 1.4 Pitfall of Manufacturing Organisation 35 2 GLOBAL AEROSPACE & DEFENCE COMPANIES – PERSPECTIVE 2.1 Introduction 38 2.2 Post Covid Situation 38 2.3 Defence expenditure scenario 39 2.4 Strategic Partnerships 41 2.5 Providing the right market Dynamics 42 3 TECHNOLOGY INNOVATIONS AND DEFENCE INDUSTRY IN AEROSPACE 3.1 Background 47 3.2 Big data 50 3.2.1 Big Data and analytics 50 3.2.2 Simulation 51 3.3 Future of Manufacturing in Aerospace and Defence 53 3.3.1 Additive Manufacturing (AM) 53 3.3.2 Computerised maintenance system 54 3.3.3 Repair technology 54 3.3.4 Skill Set – No Substitute to Trained Manpower 54 4 MAINTENANCE, REPAIR AND OVERHAUL (MRO) –AN EFFECTIVE SUPPORT SYSTEM FOR AEROSPACE 4.1 Civil Aircraft Maintenance Repair & Overhaul (MRO) and Development of Aero Engines 55 4.2 MRO Industry: Description and Structure 55
I-25 CONTENTS PAGE 4.2.1 ‘O’ Level: O level maintenance covers unit and eld repairs at the 1st and 2nd level 57 4.2.2 ‘I’ Level Maintenance 57 4.2.3 ‘D’ Level Maintenance 57 4.3 Existing Infrastructure 59 4.4 Estimated Investment for MRO Industry 63 4.5 Challenges Faced by MRO Industry 65 4.6 Establishment of an Aero-Engine HUB in India for Manned and Unmanned Aircraft 67 5 AEROSPACE MANUFACTURING – A RITE OF PASSAGE OVER 5 DECADES 5.1 Introduction 82 5.2 Manufacturing of Aircraft (HAL) – Technical Issues & Solutions 83 5.3 A Word of Guidance from Aerospace Luminaries 91 PART II DEFENCE CONTRACTS AND CURRENT SCENARIO 6 CONTRACT MANAGEMENT IN DEFENCE PSU’s 6.1 Issue in defence contracts in India 95 6.2 Administration of defence contracts 97 6.3 Defence expenditure of India 114 6.4 Contribution of DPSU’s to the defence requirements of the country 122 6.5 “Lease nancing” in defence contract 129 6.5.1 Finance Lease 132 6.5.2 Operating Lease 133 6.5.3 Pros and cons of Leasing 134 6.5.4 Leasing by the Armed Forces 135
CONTENTS I-26 PAGE 6.6 Offsets 136 6.6.1 De nition 136 6.6.2 Offset Feature, policy & Objective 137 6.6.3 Offsets – Avenues 139 6.6.4 India’s journey in Offsets - The full circle 144 6.6.5 Best Practises followed by other countries 152 6.7 United nations convention on contracts for the International Sale of Goods 156 6.7.1 Introduction 156 6.7.2 Practical CISG Issues for Purchasers 156 6.7.3 Practical Issues in Implementation of CISG 157 6.7.4 Passing of Risk in International Contracts of Sale of Goods between the United Nations Convention on Contracts for Sale of Goods 1980 (CISG) and the English Sale of Goods Act, 1979 (SGA) 158 7 RELATED ISSUES IN DEFENCE CONTRACT MANAGEMENT 7.1 Sanctions by foreign Government 161 7.1.1 Introduction 161 7.1.2 Implementation of Sanctions in the Indian Context 161 7.1.3 Consideration of Sanctions under Indian Foreign Policy 162 7.1.4 Sanctions on India 162 7.2 Obsolescence Management 163 7.2.1 Introduction 163 7.2.2 Obsolescence Mitigation Measures 164 7.2.3 Obsolescence Forecasting 165 7.3 International contracts and related issues 165 7.3.1 Introduction 165 7.3.2 The Legal Dimension of International Trade 165 7.3.3 Cultural dimension in International Contracts 166 7.3.4 Contractual Disputes 167 7.3.5 Major issues in Negotiating Cross Border Contracts 167
I-27 CONTENTS PAGE 7.4 Price Escalation 169 7.4.1 Introduction 169 7.4.2 Consideration of Price Variation 170 7.4.3 Consideration of Price Overheads & Pro ts 170 7.4.4 Mechanism for Computation of Price Variation 170 7.5 Integrity Pact 171 7.5.1 Introduction 171 7.5.2 The Mechanism 171 7.5.3 What are the essential ingredients of IP? 171 7.5.4 Terms of contract 172 7.5.5 Penalties 172 7.5.6 IP’s Advantages 172 7.5.7 IP’s challenges in its Implementation in general, not limited to DAP - 2020 173 7.5.8 Observations 173 7.5.9 Integrity Pact with Government Departments 174 7.6 Technology Transfer 174 7.6.1 Introduction 174 7.6.2 Technology In ow Routes 175 7.6.3 Issues and Challenges associated with Technology Transfer 177 7.7 Commercial, legal and nancial issues 178
GOVERNMENT CONTRACTS IN LARGE-SCALE INDUSTRIES/MSME 8 CONTRACT MANAGEMENT AND PRACTICE 8.1 Impact assessment for variation between contractual payment terms and release of actual payments by services 185 8.2 Suggested contractual terms and conditions (as devised by author while a member in related committee) 187 8.3 Practical life examples/case studies/contract management and practice – An appreciation 188
PART III
CONTENTS I-28 PAGE 9 LEGAL PERSPECTIVE 9.1 Introduction 206 9.1.1 Inter-Dependence of Indian Contract Act, 1872 (ICA) & Sale of Goods Act, 1930 (SGA) 208 9.1.2 Does Indian law recognize transactions carried out electronically? 210 9.2 Basics/Essential of Contracts 210 9.2.1 Intention to create legal relations 211 9.2.2 The nature of the obligation 211 9.2.3 Nature and Contractual Obligation 211 9.2.4 Classi cation or Types of Contracts 212 9.2.5 Does a contract have to be in writing? 213 9.2.6 The Parties 214 9.2.7 Privity of Contract 214 9.2.8 Recitals 215 9.3 Main Commercial terms in Contracts 215 9.3.1 Elements of a Contract 215 9.3.2 Reality of Consent 219 9.4 Key differences between speci c contract provisions 222 9.4.1 Limitation of Liability (Section 73 of ICA refers to) 222 9.4.2 Liquidated Damages (Section 74 of ICA refers to) 222 9.4.3 Agents and Distributors 222 9.4.4 Intellectual Property Rights Protection 222 9.4.5 IPR 223 9.4.6 Patenting Strategy 225 9.4.7 Con dential Information and Trade Secrets 226 9.5 Dealing with Government Contracts (Central/State) 226 9.5.1 Government Contracts 226 9.5.2 Position in India 226 9.5.3 ‘Contracts’ and ‘Government Contracts’ 226 9.5.4 Formation of Government Contracts 227 9.5.5 Judicial Review in Contractual Matters 233
I-29 CONTENTS PAGE 9.6 Grey areas of Indian Contract Act, 1872 (ICA) provisions 243 9.7 Enforceability of non-compete clause in India 247 9.8 Arbitration/dispute resolution issues 247 9.8.1 Non-arbitrability – Meaning, explanation & discussion 247 9.8.2 Relief under Arbitration and Conciliation Act, 1996 vis-a-vis the Jurisdiction of Specialised Tribunals 264 9.8.3 Non-Arbitrability : Meaning, Concept & Application 267 9.8.4 International Commercial Arbitration 274 9.9 Non-disclosure agreement – Applicability of laws of different countries 280 9.9.1 Introduction 280 9.9.2 What is a ‘Trade Secret’? 284 9.9.3 Trade Secrets in Different ASEAN Member Countries 288 10 LESSONS FOR FUTURE 10.1 Public/Private Collaboration 290 10.2 MSME 290 10.3 Atmanirbhar Bharat 291 10.4 Contracts for new products/equipments even for future technologies 291 11 FINDINGS OF AUTHOR’S RESEARCH WORK ON THE RELATED AREA 11.1 Synopsis 295 11.2 Main Findings 296 11.3 Contract Management and Practice - A review 302 Source of Data 340

CONTRACT MANAGEMENT AND PRACTICE

8.1 IMPACT ASSESSMENT FOR VARIATION BETWEEN CONTRACTUAL PAYMENT TERMS AND RELEASE OF ACTUAL PAYMENTS BY SERVICES

In Defence over 80-85% turnover is from Monopsony customer and hence the understanding of assessment of contractual payment terms carries a major weight factor in price determination. We all know that ` 100 given today will not have the same value after 6 months it is because of the cost of borrowings or loss of multiple affect for the dues. Presently the Defence PSUs bills are not cleared within the time frame as I have personally seen a few years back and as per the discussion with the colleagues also there is always delay in release of payments by the defence customers for which it is not that the defence customer are responsible but the systems and the mechanism of payment is such that the query and the replies always go up and down and even sometime involving amendment in contract as a result of which there is a natural delay. About a few years back when the Defence PSUs were 100% owned and controlled by Govt. of India through Ministry of Defence then there was a natural system of realising advance payment against a particular programmes so that while the contracts are getting negotiated and finalised let the Defence PSU to concurrently to procure material and start processing and manufacturing. With disinvestment of the Defence PSU now there is a natural blockage of this principles as the Govt. of India is not owing them 100% even though they are government company as per the provisions of Companies Act, 1956/Companies Act, 2013. Hence, the paying authorities and the Govt. officials both are conscious in realising advance payments or in a crude language parking of funds. Whoever enters in this field if they are private sector or a Joint sector their payment terms are to be crystal and clear linking to the achievement of milestones with certification of activity by the specified official of Services so that at a later date they should not have the difficulty in getting the payments on time. In these days of crucial overdraft rate, vis-a-vis capacity to bear the costs of financing; it is a must that these sectors should get the payment well in time as per their internal cash flow so that the financing cost should

185

8 CHAPTER

be near zero. If we keep a payment term of sum 10% advance and 70% on delivery and balance 20% of the certification, every organisation will have to incur the financing costs as the defence supplies involves particularly in the case of various platforms of aircraft, helicopters/heavy vehicles along gestation period. Since these private sectors or joint sectors will have their own strategy like Defence PSUs in the negotiation, lot of weight factor is to be given for release of early payments for those programmes where the gustation period is very high. Generally, in the PSU what I have observed that, we are more costs conscious for the material costs part and hence our quotation is always bit higher side in comparison to private sector because in the DPSU we do not consider the gain which we get on receiving advance payment. The time has come when the DPSU will have to work on costing system in a different manner perhaps like Baniya Community in the form of PART A. The costing system which we generally consider involves costs of material, cost of labour, cost of outsourcing, costs of Non-Recurring Expenditure (NRE), a portion of costs of fixed over rate, variable over rate. What we have to follow perhaps from the market system that what price we are likely to get from the customer based on international marketing perception and then to work in reverse direction considering various elements of costs which be fixed as a target and relief be provided for whatever extra cash we carry for the programme at different points of time. To be very frank even the CAG/Investigating Agencies also to see the costs dynamics and markets dynamics and adverse comments be avoided if the official of DPSU have worked with a positive set of mind and integrity. Financial decision/business decision at a later stage on a review will always be questionable because future is uncertain at present level. My personal perception is that given a free hand to the business manager of DPSU, the govt. or the Defence services will have not to look beyond DPSU considering its overall requirements. As per my perception if defence services feel uncomfortable with a particular defence PSU, it can always recommend to the government to have its representatives in the Board of Directors of concerned DPSU. Disinvestment of DPSU may not be healthy if we want to achieve “Atmanirbhar Bharat”. Even whichever DPSU has been disinvested, let through buy back arrangements even the concerned DPSU needs to made a fully owned and controlled government company. The DPSU are only committing a mistake which I feel is that they are not recruiting nowadays IIT Engineers/Engineering from reputed institutions but follow a process of advertisement through open selection. Let me respect IIT Engineers some top 5% brains which India is generating is not being utilized by India and they go out of the country and make Defence Equipment/ Missile Programme outside country & as a result, it rather works against us may not be directly but indirectly. I strongly feel that at least in the recruitment of engineers, the DPSU’s are to be given freedom both in the area of skill set of production and design to recruit eminent personality and pay the salaries compatible with private sectors

Para 8.1 CONTRACT MANAGEMENT AND PRACTICE 186

187 SUGGESTED CONTRACTUAL TERMS AND CONDITIONS

Para 8.2

and the government should hold the hands of those peoples at a later stage if there is a technical flow or programme fails. I have seen in Aerospace manufacturing DPSU how new products were developed in 70s and 80s why we have failed in 2000’s. Hence, the costs of engineering/reengineering for the programme also to get appropriate allocation and as a separate item of costs so that the country gets all future generation fighter equipments/ armaments well in time.

8.2 SUGGESTED CONTRACTUAL TERMS AND CONDITIONS (AS DEVISED BY AUTHOR WHILE A MEMBER IN RELATED COMMITTEE)

Clause 1 Scope of Supply-Technical Description/Requirement/Quality requirement, etc.

Clause 2 Price & Payment terms

Clause 3 Price variation formula

Clause 4 Packing conditions

Clause 5 Inspection and Technical document requirements

Clause 6 Acceptance of goods

Clause 7 Training & Technical Assistance

Clause 8 Warranty

Clause 9 Optional clause (if any) - Repeat Order/ Additional requirements

Clause 10 Product support

Clause 11 Taxes & Duties

Clause 12 Integrity Pact & Bribes

Clause 13 Liquidated Damages (LD)

Clause 14 Earnest Money Deposit (EMD)

Clause 15 Security Deposit (SD)

Clause 16 Performance Bank Guarantee (PBG)

Clause 17 Spares management

Clause 18 Obsolescence

Clause 19 Withholding tax

Clause 20 Product Liability

Clause 21 Risk Purchase

Clause 22 Termination clause

Clause 23 Insolvency

Clause 24 Appropriation

Clause 25 Applicable law/ Jurisdiction

Clause 26 Arbitration

Clause 27 Indemnity against Patent rights

Clause 28 Sub-contracting/Sub-let

Clause 29 Work & Payment during arbitration

Clause 30 Fall clause

Clause 31 Export license

Clause 32 Immunity to the Government of India

Clause 33 Classi ed/Con dentiality

Clause 34 Agents/Agency Commission

Clause 35 Intellectual Property Rights

Clause 36 Force Majeure

Clause 37 Amendment & Waiver

Clause 38 Exit criteria

Clause 39 Cartel Formation

8.3 PRACTICAL LIFE EXAMPLES/CASE STUDIES/CONTRACT MANAGEMENT AND PRACTICE – AN APPRECIATION

1. What I have seen in the Defence Aerospace that Project Management which includes material management is one of the most prime concern for any programme. Let me tell you that whenever defence programmes come whether for manufacturing fighter aircraft or transportation aircraft or trainer aircraft or for its radar, the most important element are two things – one is flow of technical documents, knowhow and second is the skill set of the organisation. Technological flow of documents depends upon the contract management to a large extent as the Contract provides for the flow of technological documents for the programme from the licensor or developer. Generally, what is happening that most of the foreign countries will not provide you the most updated equipment but will provide you an established product. In that case the documents flow is not so much bottleneck but if the programme is a developing programme and still the fighter aircraft is to get proven, the documentation part itself is not firmed up and as a result the various manufacturing NRE & Equipments may not be well established. Our MoD/Defence Customer has a very stringent quality control department which is called DGAQA which thoroughly checks up all the processes and documentation to avoid any missing gap. Hence, when the defense PSU goes for manufacturing under license then it has to face a large problem of smooth flow of documents which in turn affects ordering for technical kits/tools/equipments. As a result, most of the programme of License manufacturing, no doubt, gets into delay mode. The flaw is in the detailed contract signed by the Defence PSU with the allotted organization of foreign country so we should be aware of about the practical problems being faced by Defence PSU. This will be more critical for the private sector

Para 8.3 CONTRACT MANAGEMENT AND PRACTICE 188

having no experience in this field and they may not get so much co-operation from various foreign Indian Embassy as the Indian Defence PSU are getting. So, before any private sector jump into the fray of manufacturing of defense equipment be it of Army, Navy and Air force, they should first understand the critical bottlenecks in getting the technology and absorbing the technology. What is next thing important is the skill set of the organization, rightly the defense PSU by being in this field for years together have developed a high skill set in this field and some of the Defence PSU have a backup design set up to assist it whenever and wherever the technological gap is there. The Private Sector with highly paid executive will have to first search for the skill set of the technologists in this field, who has worked for defence aerospace or so and was involved in design Liasoning and will have to work with the Defence PSU in joint sector to learn the trade tricks. I have seen even the design programme about to go to its finality, get into some trouble at the fag end of the programme. Our MoD and services will expect a high level of technological and some unachievable targets as their base which hopefully not only Defence PSU have failed even our privates sector may also fail.

2. As the programme is not successful and the Defence PSU have drawn advances from the MoD/ Defence services, it harpens upon the PSU to refund back the amount which in no way is possible as generally the defence PSU sometime to augment the programme they go on placing orders for the full-fledged programme concurrently as they have established the successful vendors whose products have met the airworthiness criteria/ quality assurance criteria. So when the programme gets closed, it becomes very difficult for the PSU to recover the money from the Government without any mistake on its part. In any Design & Development programme all the 3 parties are involved i.e. the defense PSU, Concerned Defence Services and the MoD and still at fag end programme fails. While Defense PSU have learnt from their mistakes, what for the private sector there will be initial greenery but they will learn about all these things only after 5 to 10 years of the programme and not before that.

3. Getting money for the job done is also not easy from defence services paying authorities as they critically check their bill with reference to the contract/supply order and always will find some missing gaps in bits and pieces and if the payment is other than through Letter of Credit it becomes very difficult to get the bill cleared from those paying authorities. Paying Authorities have to see multiple things apart from their in house management i.e. their budget availability in specific head and then the supply order and the contract stipulating the terms of the payments along with the milestone completed and so on and so forth and naturally in the process there is a delay.

4. CAG in the post audit period will raise multiple issues both against the defence PSU and the defence services apart on paying authorities and all

189 PRACTICAL LIFE EXAMPLES Para 8.3

these agencies will have to then give a coordinated reply to meet the observation of CAG. Since, the defence supplies are always complicated as the Defence PSU will have to purchase certain banned items from certain foreign countries for which they have to take coordination from multiple agencies before proceeding ahead. So, all these also leads to delay in the programme.

5. Design & Developments in defence programmes are highly capital intensive and success is not 100% so investment in design and development is very risky. However, Defense PSU’s are generally investing 20% of their profit after tax for design and development; their design department is also involved in meeting the risk of obsolescence management and obsolescence management is quite critical in aerospace field. Every product has a life including the airframe has a life so when our country is not so rich we have to upgrade the same aircraft to the current level by way of upgradation of avionics, communications, radar and other mechanical & hydro mechanical systems to the current standards so that it can substitute the new generation fighter aircraft or transport aircraft. I have seen that this obsolescence management becomes nerve system even for existing programmes forget for the upgrades. All these critical elements are to be appropriately covered in the contracts with the licensor or the design provider of the platform. Generally, in the olden days we used to cover this requirement by way of an appropriate clause in the contract that one time buy option will be provided before closure of the product line or a substituted item with a substituted source with proper documentations will be provided by the licensor or design provider. All these are checked by DGAQA before its incorporation in the platform.

6. While, we all are aware whether it is under national arena or under international arena that the term of the contact itself becomes the law as the Contract Act, 1872 itself is based on the proposition that if the contract is built on fundamental principal of contract, it is enforceable in India and even in other jurisdictions so drafting the contract and incorporating appropriately all the conditions are a must for making any programme successful.

7. In Defense Programme what I have seen that the working capital requirement is very high, the reason being that MOD is the monopsony customer and getting payment from them is not an easy, smooth and so realization is always delayed and backlog of payments will continue with MoD paying authorities whereas the A class items that the organizations will have to purchase they have to place orders quite in advance so that production cycle is not disturbed. Production Cycle for manufacturing fighter aircraft from raw material phase is approx. 5 years. These A class items other than from Russian vendors are mostly through letter of credit. Letter of credit or sight draft under both the systems, the payments are to be released to the banks, once the documents are dispatched as per the terms of the letter of credit or sight draft. So, payments are to be made to these creditors well in advance,

Para 8.3 CONTRACT MANAGEMENT AND PRACTICE 190

realization is always delayed; hence, working capital cycle management is not smooth. Hence, the private sector will also face the same difficulty as it has become the established pattern. DGAQA checks up the production process intermittently so that quality product is available to the services but the process delays due to these checking is also involved. If Indian private sectors want to do the job of only assembly of aircraft and then test flying and delivery then ok ; they can do that but in a fighter aircraft manufacturing in a vertically integrated plant i.e. manufacturing from components, spares, line replaceable units and then structural assembly, final assembly, etc. are involved for a full aircraft manufacturing Standard Man Hours (SMH) will be approximately more than 10 lakhs SMH and for assembly of the Aircraft and test flying, the SMH content will be hardly approx. 30,000 SMH. Make in India programme or Aatmanirbhar Programme hopefully will not allow only final assembly and test flying, if the manufacturer has to do the job of repair and overhaul of the aircraft for learning technology and becoming self-reliant; the country must have the capacity to build aircraft from manufacturing of components to all the stages of production of spares, line replaceable units, sub-assembly etc. Hence, all these requires a proper contract with the licensor or with the concerned foreign agency.

8. In the contract, I have found that in spite of number of years of experience, certain clauses are not drafted properly from the practical life situation rather it is more based on legal terminology which leads to multiple types of problems at a later stage. Some such examples which I have realized personally are as follows:

a. Payment terms – We are not linking payment terms with the cash outflow adding delay in clearance & payment release from services. We are also not considering impact of advance payment. Getting payment early will need to consider saving in working capital burden of financing cost.

The respective organizations can develop own mathematical model for pricing with payment term as the same may vary from organization to organization.

b. Sometimes the Defence PSUs are not giving proper weightage to the remarks/ conditions provided in their commercial offers by the foreign vendors against the quotation/ tender asked by DPSU and subsequently when orders are finalized with that vendor then they are forcing the defense PSU to change certain NRE payment based on milestone payment and delayed payment charges which was not part of evaluation at the time of CFA approval. Although, such issues are mostly happening in proprietary vendors i.e. the Vendors whose items are approved on the aircraft platform and such demand by the foreign vendor sometimes acts as a precondition to accept the pur-

191 PRACTICAL LIFE EXAMPLES Para 8.3

chase orders. DPSU naturally has to meet the target of supply to the MoD and at the stipulated time they have no option but to accept it.

c. Amendment of Contract to avoid delay in completion of the defence projects. Such situations are also emerging when the development programme is delayed and non-recurring costs (DRE) is claimed by the vendor not as per the standard terms but there is a delay in the programme of development and once that particular milestone has been achieved, they are asking for change in payment terms. It is also observed that sometimes even accepted commercial terms and conditions with reference to inco-terms, packing data, conditions of items, etc., the foreign vendors are asking for changing the terms at a later stage which is in variance with the original contractual terms and conditions. Similarly, the proprietary vendors or even original equipment manufacturer (OEM) are asking for changes in defect investigation, technical assistance, liquidated damages, spares and products support, fall clauses, escalation formula, delivery schedule, option clause, etc., whenever there is a delay in co-production and co-development and DPSU is not in a position to disrupt the programme by cancelling the order. Let me tell you very frankly from the practical angle that once a particular engine is fitted in a fighter aircraft, it is not possible to change the engine at a later stage of some other manufacturer because of so many technical requirements like Weight factor, thrust of the engine, oil flow, etc., so many issues are involved, so once you fit a particular engine you have to live with it for the aircraft life. This problem will be equally faced by the even top-notch private sector as it is not a car manufacturing or a truck manufacturing but it is a flying machine which has multiple technical aspects and all those have to be taken care of during technical stage. Hence, in order to bring in win-win situations whether it is private sector or public sector one has to be very careful in selection of vendor particularly initially on the basis of single acceptable offer keeping in mind the past experience of dealing with that vendor by the DPSU or the Govt. and this will avoid subsequent pressure of the vendor, what it is suggested that scrutiny of background and performance of the vendor thoroughly before final selection is a pre-condition for even the private sector big organization. This also necessitates to build vendor directory both for ongoing programme and for developing programme with technical options for replacement at a later stage due to unavoidable situation and accordingly it is suggested to invite competitive tendering and selection of reliable vendors and that vendor may not be L1 with H1 criteria but should have past precedence of being a reliable vendor, the designers have to face multiple problems during large developments programme but seeing the past experience

Para 8.3 CONTRACT MANAGEMENT AND PRACTICE 192

it is suggested that as far as practicable specification for the product should be generic and not tailor made specification to get a particular manufacturer selected.

d. Design and Development programme requires sometimes consultancy for a very specialist test or for developing certain features like stall and spin test for developing a trainer aircraft. Providing consultancy of such specific test, hardly a few organizations in world is available and such organisation terms and conditions will be stringent during the course of the progress of the consultancy assignment they ask for amendment to contract to accommodate their demand. Sometimes they will ask for revisit of scope of work, updating the description of one of the milestone so that their payment is not hold up because of non-achievement of their milestone, extension of time schedule, redefining of payment milestone. All these suggest for in case of such programme to go into the background of the organization, past dealings, drafting of right RFQ/Contract to avoid change in parameters after finalization of contract. Such activity may also requires taking defense customer into confidence in consonance with the anticipated physical progress of the projects and avoid contract which is expenditure driven and release of payment milestone is not resulting into parking of funds with the concerned organization.

e. I have also seen in a particular programme of national interest how a particular joint venture of the DPSU behaved with the DPSU. Payment terms as per the contract in development phase was 10% of the order value to be paid on finalization of system requirement. The same would be paid on receipt of technical specification and interface control document signed by the DPSU, who has assigned the job to the joint venture and the joint venture did not agree for performance bank guarantee during development phase and agreed to do the same only on series production phase. Similarly, they wanted to change the intellectual property right solely available with the DPSU which is paying the money for the development programme to IPR residing with both Joint Venture company & DPSU. ToT clause was accepted by the JV before the placement of the order and after placement of the order, the JV company wanted to change that ToT with DPSU. Now DPSU is in trouble because if they cancel the order of JV they will not be in a position to get the programme completed in time as that equipment is mandatory equipment for the particular programme so they have to accommodate their own JV by accepting those conditions. It is suggested that when you are dealing with JV, where other partners are also involved, don’t trust the JV fully but see the competence of the organizations whether it is your own JV or a market organization and then decide.

193 PRACTICAL LIFE EXAMPLES Para 8.3

GUIDE TO COMMERCIAL CONTRACT MANAGEMENT

AUTHOR : ASHOK KUMAR MISHRA

PUBLISHER : TAXMANN

DATE OF PUBLICATION : OCTOBER 2023

EDITION : 2023 Edition

ISBN NO : 9789356227552

NO. OF PAGES : 388

BINDING TYPE : PAPERBACK

DESCRIPTION

Rs. 895

This book comprehensively offers practical guidance, best practices and strategies to effectively handle contract administration, risk mitigation and dispute resolution.

The book provides a comprehensive overview of contract management in manufacturing organizations, discussing technical and commercial dimensions. It addresses the intricacies of negotiating defence contracts, financial analysis, and regulatory and legal management and elucidates various contract commercial terms. Specific provisions such as limitation on liability, liquidated damages, force majeure, and patenting strategies are given particular attention. Furthermore, the book offers insights into alternate dispute resolution mechanisms and showcases research in the related area aimed at helping manufacturing organizations avoid pitfalls. It also underscores the interdependence of Commercial Acts within these organizations and delves into various legal facets of contracts.

This book will be helpful for lawyers & other professionals in drafting & vetting contracts.

The Present Publication is the Latest 2023 Edition, authored by Dr. (CA) Ashok Kumar Mishra, with the following noteworthy features:

• [Enhances Professional Skill Sets] in the field

• [Features Relevant Examples and Case Laws] for a richer understanding

• [Difference Between Specific and General Contract Clauses] are clarified in the text

• [Addresses Misconceptions about Vendor Interactions] in public sector organizations

• [Discusses the Need for Understanding Between Vendors and Customers] to avoid project delays

• [Discusses the Challenges of Implementing 'Aatmanirbhar'] in the defence sector.

• [Comprehensive Coverage of Man Management and Technology Management]

• [Highlights the Importance of Self-Reliance] in Defence Design, Development, Equipment Manufacturing, and Maintenance

• [Provides Hands-On Experience Insights] on defence contract management, detailing problem areas and their tested solutions

• [Presents Results From Surveys] on the current state of contract management in defence

• [Explores the Complexities of Contract Management] and offers feasible solutions

ORDER NOW

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.