TesmecMag-2012-02-SE-1000 kV China-EN-Rev.02a

Page 1

Tesmec esmecMag

02#2012 February 27th

JOURNAL OF MARKETING INFORMATION

Mr. Paolo Celeri Business Development Director, describes the project of the first full operaƟve 1000 kV Line in China. The line starts from Shanxi Changye in North China, passes through Henan Nanyang, and reaches to Hubei Jingmen with the overall distance of 640 km.

CHINA 1000KV LINE PROJECT “8 PULL 8 Stringing OperaƟon” Tesmec stringing equipment were used in the project of the first Ultra-high voltage power line (1000 kV AC Power Transmission and TransformaƟon) in China. Below the storyboard.

Tesmec technical department got the idea of using mul ple machines (called pullertensioner) electronically connected each other in order to increase the max pulling force up to 540 kN.

THE CHALLENGING PROBLEM (2006) The new 1000 kV experimental power line brought a lot of new technical ques ons on the table, one of them is how to string 8 bundled conductors at the same me in efficient and safe way.

THE SOLUTION (2007 - 01) The final solu on was the result of several technical mee ng where different aspects of the job to be carried out were deeply analyzed. The final preference was given to the Tesmec 90 kN (45 kN+45 kN) PullerTensioner model AFB506. Four machines connected working as puller guaranteed the simultaneous stringing of 8 bundled conductors with 8 independent pulling ropes at the max total force of 360 kN. Six machines connected working as puller guaranteed the simultaneous stringing of 6 bundled conductors of bigger sec on with 6 independent pulling ropes at the max total force of 540 kN.

THE IDEA (2006 - 12) The tradi onal stringing method of one big puller with one pulling rope stringing 8 independent conductors by a running board was a possibility but with one important limita on: the max pulling force cannot be higher than 280 kN. This limita on not allows overcoming some cri cal sec on of the line, in par cular the River Crossing Sec on.

͢


Tesmec esmecMag 02#2012 1

THE SIMULATION (2007 - 06) In any good engineering process is very important to validate an idea, for this purpose a simula on of the real job site was carried out by using older Puller-Tensioner to string independently 4 bundled conductors with 4 pulling ropes. The simula on was successful and demonstrated that the ideas was good and simple and can be applied in appropriate way.

2

Several teams work together with Tesmec technical department on this challenging issue including Diesel Engines and Hydraulic components manufacturers, Electronic Hardware and So ware houses, Instruments manufactures and so on. THE MANUFACTURING (2008 - 06) The manufacturing process went smoothly in considera on of the huge technical prepara on, even if some component were completely new and designed on purpose.

3

THE DESIGNING (2007 - 05-09) The final solu on was the result of several technical mee ng where dierent aspects of the The designing process needed to face several diďŹƒcul es and solve a huge number of problems. First of all a completely new electronic hardware and so ware needed to be designed in order to allow the mul ple machines work in speed synchroniza on. The possible choice of components was consequently limited to the ones that can allow such sophis cated electronic controls.

Photo 1 Drawing of the idea of using mul ple machines (pullertensioner) electronically connected each other

Photo 2 The simula on process

Photo 3 The manufacturing process


Tesmec esmecMag 02#2012 THE HOME TESTING AND CALIBRATION (2008 - 04-06) Tesmec facili es allow performing complete calibra on and performance tests. In par cular these machines required a long hardware set-up and so ware debugging process in order to reach the designing criteria and parameters. All the teams par cipate to this project collaborate intensively to reach what we consider today the most advanced stringing machine worldwide.

THE SITE START-UP (2008 - 06-07) One upon the me all the machines and rela ve accessories arrived on job sites, different Tesmec technical teams retested all the machines and accessories equipment, in order to re-confirm that all the items were in good order and ready to operate.

6

4

THE TRANSPORTATION (2008 - 06-07) The me available to develop such sophis cated machines appeared not enough since the beginning of designing issue and despite the huge effort all Tesmec staff to respect the lead me given in the purchasing contracts, some delay was accumulated. Therefore Tesmec in order to reduce the final delivery me to the job sites decided, for the first me in its history, to deliver the machine by air. A total number of 12 machines, for a total weight of over 57.000 kg, were send by planes from Italy to china with a very huge effort by Tesmec logis c department.

THE STRINGING OPERATION (2008 - 06-07) Finally at work! Three different job sites prepared and two of them are s ll now running. THE JINGMEN HAN RIVER CROSSING JOB SITE PERFORMED BY THE HUNAN TRANSMISSION AND TRANSFORMATION CORPORATION Han River big crossing is one of the two big crossing for 1000kV Line project of China, while the other is the Yellow river one. The line is a three phases one, composed by 6 conductors for each phase, plus 2 earth wire (1 OPGW). Conductor type: AACSR Sec on: 630 mm2 Ø: 33 mm Earth wire (including OPGW in one of the two lines): 19 mm Pulling Rope: Ø 13 mm for OPGW and 20 mm for conductors

5

7

Photo 4 The home tes ng and calibra on

Photo 6 The site start-up

Photo 5 The transporta on

Photo 7 The Jingmen Han river crossing job site


Tesmec esmecMag 02#2012 THE TANGHE JOB SITE - PERFORMED BY THE HUNAN TRANSMISSION AND TRANSFORMATION CORPORATION The line is a three phases one, composed by 8 conductors for each phase, plus 2 earth wire (1 OPGW). Conductor type: AACSR Sec on: 500 mm2 Diameter: 30 mm Earth wire (including OPGW in one of the two lines): 19 mm Pulling Rope: Diameter 13 mm for OPGW and 18 mm for conductors

8

THE SUCCESSFUL JOB (2008 - 07) The performance and the simplicity of use of these synchronized machines enchanted all the people present at the Job site from Project Leaders to the machine operators. More and more days passing the Stringing teams of the two construc on companies are taking confidence with the use and the process of this innova ve technology and systems becoming more and more eďŹƒcient. It is now a common conclusion that this system is valid and become a new standard for the future UHV power line with high number of conductors per bundle.

10

THE XIANFANG JOB SITE - PERFORMED BY THE BEIJINNG TRANSMISSION AND TRANSFORMATION CORPORATION The line is a three phases one, composed by 8 conductors for each phase, plus 2 earth wire (1 OPGW). Conductor type: AACSR Sec on: 500sqmm Diameter: 30 mm Earth wire (including OPGW in one of the two lines): 19 mm Pulling Rope: Diameter 13 mm for OPGW and 18 mm for conductors

9

Photo 8 The Tanghe job site Photo 9 The Xianfang Job Site Photo 10 The Successful Job

TESMEC S.p.A - Headquarters via Zanica, 17/O - 24050 Grassobbio (BG) - Italy Tel. +39.035.423 2911 - Fax +39.035.4522444 Management and Administra on Fax +39.035.4522445 Stringing Equipment Division - Fax +39.035.335664 Trencher Division www.tesmec.com - info@tesmec.it


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.