1 minute read

BACK ON LINE

TRAM services between Calpe and Denia are back on track after going off the rails in 2016 due to safety concerns.

The final piece of the jigsaw was the reopening of the section linking Denia and Gata de Gorgos, following two months of test runs.

Denia mayor, Vicent Grimalt said: “It felt like a jug of cold water being poured over you when the line closed in 2016, but this is a service that supports the region and connects the towns of the Marina Baja.”

Line 9 TRAM d’Alacant trains between Calpe and Denia were suspended because bridges and viaducts were unable to take the weight of new rolling stock. Old bridges were restored and work also included the ‘straightening out’ of the line to allow new electro-diesel trains to use it - including the ability to travel faster.

Money

Section by section, the line reopened with the Gata de Gorgos to Teulada link restored last July.

Over €150 million of Valencian government and EU money has been spent on the project including the purchase of six new trains.

Hourly departures from Denia start at 5.50am with the last tram at 9.50pm going to the other Line 9 terminus in Benidorm.

This article is from: