A DESIGN | BUILD PRE-SALE PROPOSAL 1 1 2 5 PA R K AV E N U E | A P T 1 0 E | N E W YO R K , N Y | 1 0 1 2 8
THE RENOVATED HOME THE DESIGN | RENOVATION AUTHORITY
TM
PRE-SALE PROPOSAL
112 5 PARK AVENUE APART MENT 10 E NEW YO R K , NY | 10 128
PRE-SALE PROPOSAL
PREPA RED EX CLU SI V ELY FO R:
MICHELE KLEIER
EXISTING FLOOR PLAN
CL.
CL.
CL.
CL.
BATH
BEDROOM
MASTER BEDROOM
BEDROOM
BEDROOM STAFF ROOM
LINEN
W/D
FAMILY ROOM / DINING ROOM
REF
CL.
KITCHEN GALLERY OVEN
LIVING ROOM
SERVICE ENTRY
CL.
WBFP ENTRY
PROPOSED
FLOOR PLAN
ENCLOSURE
MASTER BATH BENCH
ENCLOSURE
24" MIELE DW
RE
SU
O
CL
EN
BEDROOM
BUILT-IN MILLWORK / ENCLOSURE
BEDROOM
CL
STAFF ROOM
CL
18" MIELE DW 42" SUB ZERO REF
DINING ROOM
PANELED OPENING
W
D
MILLWORK PANTRY / STORAGE
GALLERY
PANELED OPENING
KITCHEN
CL
MILLWORK PANTRY / STORAGE
LIVING ROOM BUILT-IN MILLWORK
BUILT-IN, FULL HEIGHT MILLWORK
SERVICE ENTRY
MASTER BEDROOM
CL
ENTRY
WBFP BUILT-IN MILLWORK
BUILT-IN MILLWORK
ENCLOSURE
DRESSING ROOM
WIC
DESIGN | SPECIFICATION HIGHLIGHTS BESPOKE KITCHEN & BATHS KITCHEN 1” thick solid wood beaded inset framed cabinetry with walnut interiors hand painted on site. countertops fabricated with 2” thick Calacatta Marble specified by Superior Stone. full height matching backsplash in Calacatta Marble. premium appliances throughout the kitchen specified by Miele, Wolf, and Sub-Zero.
MASTER BATHROOM select Calacatta 4” x 12” herringbone marble tiles on all floors. select Calacatta 12” x 24” marble tiles specified by ABC worldwide stone on all walls. custom solid wood vanity and medicine cabinets with walnut interiors hand painted on site. fixtures specified in polished nickel finishes by Waterworks, Toto and Samuel Heath.
GUEST | CHILDRENS’ BATHROOMS select carrara and bardiglio basketweave mosaic marble specified by Artistic Tile on all floors. white ceramic 3” x 6” subway tile with matching trim to be installed to wainscot height. fixtures specified by polished nickel finishes by Newport Brass, Toto and California Faucets.
DESIGN | SPECIFICATION HIGHLIGHTS BESPOKE KITCHEN & BATHS FLOORING wood floors throughout to be fine sanded, stained and finished. all existing wood floors of the residence to be stained and refinished kitchen and all associated to receive new 5” Wide Plank Select Walnut specified by carlyle wood flooring
INTERIOR DOORS | HARDWARE all interior doors specified as custom 1¾” solid wood paneled doors, all custom jams and casings throughout. door hardware specified by Baldwin & Merit Metal
TRIMWORK AND MILLWORK new baseboards, casings & crown moldings throughout as specified custom millwork at all windows to incorporate radiators and/or HVAC units to provide additional storage as available all windows to receive new finish trim and window sills throughout to be consistent with specified baseboards, and door casings rough and full skim coat plastering, priming and painting to be completed to a ‘level five’ finish throughout the residence, including hand painting all millwork and cabinetry throughout the residence
KITCHEN
LEVEL OF FINISH
KITCHEN LEVEL OF FINISH
KITCHEN LEVEL OF FINISH
KITCHEN INSPIRATION
KITCHEN
INSPIRATION
KITCHEN LEVEL OF FINISH
KITCHEN LEVEL OF FINISH
KITCHEN LEVEL OF FINISH
DINING ROOM LEVEL OF FINISH
DINING ROOM INSPIRATION
DINING ROOM INSPIRATION
POWDER ROOM LEVEL OF FINISH
POWDER ROOM INSPIRATION
LIVING ROOM LEVEL OF FINISH
LIVING ROOM LEVEL OF FINISH
LIVING ROOM INSPIRATION
LIVING | DINING ROOM INSPIRATION
GALLERY LEVEL OF FINISH
GALLERY
LEVEL OF FINISH
LIVING ROOM LEVEL OF FINISH
LIVING ROOM LEVEL OF FINISH
LIVING ROOM LEVEL OF FINISH
LIBRARY
LEVEL OF FINISH
LIBRARY
LEVEL OF FINISH
MILLWORK LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
MASTER SUITE INSPIRATION
MASTER SUITE INSPIRATION
MASTER SUITE LEVEL OF FINISH
MASTER SUITE LEVEL OF FINISH
SECONDARY BATHROOM LEVEL OF FINISH
SECONDARY BATHROOM LEVEL OF FINISH
CHILDREN’S SUITE LEVEL OF FINISH
CHILDREN’S SUITE LEVEL OF FINISH
ARCHITECTURAL DETAILS SITE SAFETY daily on site supervision of all trades to assure work is being completed to NYC Building code and The Renovated Home workplace guidelines DEMOLITION | PROTECTION proposed renovation would require the entire removal of all interiors; including walls, partitions, closet interiors, bathrooms, millwork, and cabinetry, throughout the residence as noted to accommodate the new proposed plan and details CARTING | DEBRIS | SITE REMOVALS continuous debris pick-ups throughout the entire course of construction through completion full debris removal and carting during demolition and a full cleaning at completion of demolition in preparation of work to commence professional cleaning crew at completion of project including full exterior and interior window cleaning prior to client occupancy ROUGH | TRIM ELECTRICAL all work to be completed by our NYC licensed and insured master electrician. all rough electrical materials and installation included. all new rough and trim electrical throughout the residence. new service or full upgrade of existing panel throughout the residence if specified. permitting, inspections, and sign offs throughout LIGHTING PACKAGE this line item includes all finish recessed lighting throughout the residence as well as all undercabinet lighting, task lighting as designed throughout
ARCHITECTURAL DETAILS ROUGH | TRIM PLUMBING all work to be completed by our NYC licensed and insured master plumber includes all new branch, waste, and water to all locations throughout the residence all piped back to the local risers mandatory 24-hour retention tests included for all new showers all trim plumbing to completion throughout permitting, inspections, and sign-offs throughout SPRINKLERS as applicable MIRRORS | GLASS | GLAZING as designed throughout the residence including glazing for millwork, closet mirrors and shower enclosures as designed throughout WOOD FLOORING | SPECIALTY FLOORING as designed and specified throughout the residence HVAC this budgetary placeholder is for the installation of a full HVAC system including all acoustically lined ductwork, all new thru wall compressors (5 ton units) and all associated masonry work air handlers, zoned systems which all include the installation of NEST thermostats to control throughout. All associated electrical, plumbing and filing for this mechanical element is included within this line item. full dimensioned duct work drawings and all associated filing documentation is included within this package for the NYC DOB filing as well as all filing for the buildings alteration team to review
ARCHITECTURAL DETAILS APPLIANCES within this line item is a budgetary placeholder for kitchen appliances as specified in the design specifications. Sub-Zero, Wolf, and Miele are specified to identify the level of this budgetary placeholder WOOD DOORS | JAMBS | CASINGS delivery and tax on elements and all associated installation labor. included is the installation of all new doors (1 ¾” thickness), jambs, trims, hardware (passage sets throughout, privacy sets for all bathrooms, and three 4” hinges mortised on site for each door. door styles to be confirmed through design HARDWARE | DECORATIVE all hardware is specified for as custom polished nickel from Baldwin. all hardware styles to be selected by client ROUGH CARPENTRY this line item includes all rough and trim carpentry, partitions as needed, ceilings, drywall, trim, base and crown molding installations, and accessory installations at completion as proposed within the plans. millwork installations are calculated within the pricing of the individual millwork elements listed below CLOSET INTERIORS this line item includes a budgetary placeholder for all closet interiors provided by California Closets The Renovated Home has used California Closets exclusively since 1988 for all of its closet interiors. absent our own full wood custom closet interiors bespoke custom offerings are available but are not included within this budgetary proposal
ARCHITECTURAL DETAILS STONE | MARBLE | TILE MATERIAL templating, installation, sealing, and protection of all completed countertops fabrication Labor of all slab stone throughout. Stone: this is the fabrication of all stone throughout kitchen material for these Countertops: Budgeted in Calacatta Marble with a 2� Thick built-up edge in a honed finish. all natural stone to be sealed with two coats of Sealer templating, installation, sealing, and protection of full stone / tiled backsplash to completion preparation includes ALL of the necessary sand, cement, labor and materials to re-build the structure of the bathrooms to prepare for the installation of the finishes and materials Specified and Included for all waterproofing is the Laticrete 9235 waterproofing membrane installation includes the labor to install all provided tile and stone once the preparation is completed. installation of floor stone/tiles, wall stone/tiles, and custom stone included. sealing of all natural stone products at completion with two coats of Bulletproof Sealer. all high grade Latricrete bonding materials to be used. fabrication: all fabrication cost for the custom door saddle, and vanity top.
BUDGETARY GUIDANCE TRADESPEOPLE / CONTRACTORS
CATEGORY PERCENTAGE
TOTAL CATEGORY
Site Safety, Protection, Site Management
1.10%
$9,856.00
Demolition
4.55%
$40,768.00
Carting, Debris, & Site Removals throughout the project
2.85%
$25,536.00
Rough & Trim Electrical
7.45%
$66,752.00
Lighting Package
2.45%
$21,952.00
Fireproofing
0.60%
$5,376.00
Plumbing
8.35%
$74,816.00
Wood Flooring/ Soundproofing / Underlayment
4.04%
$36,198.40
Specialty Flooring
0.00%
$0.00
HVAC and all associated to this line item
4.55%
$40,768.00
BUDGETARY GUIDANCE
TRADESPEOPLE / CONTRACTORS
CATEGORY PERCENTAGE
TOTAL CATEGORY
Wood Doors, Jambs, Casings & Installation
2.55%
$22,848.00
Rough Carpentry & all associated trades
9.03%
$80,908.80
Building Materials
2.35%
$21,056.00
Architectural Millwork, Installation, Trim Installation
2.78%
$24,908.80
Closet Interiors
9.10%
$81,536.00
Custom Kitchen Millwork, Bathroom Millwork Throughout, & Installation
2.80%
$25,088.00
Painting, Coating, Finishing, Plaster, & Skim Coating
11.24%
$100,710.40
Stone, Marble, & Tile Installation / All Associated Masonry, Waterproofing
9.10%
$81,536.00
Project & Site Setup
0.45%
$4,032.00
Project Administration Reimbursable
0.10%
$896.00
BUDGETARY GUIDANCE VENDORS / CLIENT PAYS DIRECT
CATEGORY PERCENTAGE
TOTAL CATEGORY
Plumbing Fixtures, Fittings, Accessories
2.67%
$23,923.20
Mirrors, Glass, & Glazing
0.45%
$4,032.00
Appliances (Allowance)
3.67%
$32,883.20
Decorative Hardware, Locksets & Hinges
1.45%
$12,992.00
Stone, Marble, & Tile Material throughout project
6.32%
$56,627.20
Fireplaces
0.00%
$0.00
Audio & Video Systems, Motorized Shades, & Security Systems
Pending Client Input
Pending Client Input
BUDGETARY GUIDANCE
CATEGORY
CATEGORY PERCENTAGE
TOTAL CATEGORY
Total Tradespeople / Vendors Total Square Footage of Residence
3,200
Per Square Foot Value of Renovation
$280.00 100.00%
$896,000.00
TRH Architectural (which includes): Drafting, Design, Architecture, Permitting, Building Submissions
4.50%
$40,320.00
TRH Construction / General Conditions
20.00%
$179,200.00
TRH Insurance
1.25%
$11,200.00
Total The Renovated Home
25.75%
$230,720.00
Total Construction Costs
The Renovated Home
Total Project Cost
$1,126,720.00