PMP Inputs and Outputs

Page 1

PMP Inputs and Outputs Accepted Deliverables OUTPUTS 5.5 Validate Scope INPUTS 4.6 Close Project or Phase

Activity Attributes OUTPUTS 6.2 Define Activities INPUTS 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule

Activity cost Estimates OUTPUTS 7.2 Estimate Costs INPUTS 6.4 Estimate Activity Resources 7.3 Determine Budget 11.2 Identify Risks 12.1 Plan Procurement Management

Activity duration Estimates OUTPUTS 6.5 Estimate Activity Durations INPUTS 6.6 Develop Schedule 11.2 Identify Risks

Page 1 of 24


Activity List OUTPUTS 6.2 Define Activities INPUTS 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule

Activity Resource Requirements OUTPUTS 6.4 Estimate Activity Resources INPUTS 6.5 Estimate Activity Durations 6.6 Develop Schedule 9.1 Plan Human Resource Management 12.1 Plan Procurement Management

Agreements OUTPUTS 12.2 Conduct Procurements INPUTS 4.1 Develop Project Charter 7.3 Determine Budget 12.3 Control Procurements

Approved Change requests OUTPUTS 4.5 Perform Integrated Change Control INPUTS 4.3 Direct and Manage Project Work 8.3 Control Quality 12.3 Control Procurements

Page 2 of 24


Basis of Estimates OUTPUTS 7.2 Estimate Costs INPUTS 7.3 Determine Budget

Business case INPUTS 4.1 Develop Project Charter

Change log OUTPUTS 4.5 Perform Integrated Change Control INPUTS 13.3 Manage Stakeholder Engagement

Page 3 of 24


Change requests OUTPUTS 4.3 Direct and Manage Project Work 4.4 Monitor and Control Project Work 5.5 Validate Scope 5.6 Control Scope 6.7 Control Schedule 7.4 Control Costs 8.2 Perform Quality Assurance 8.3 Control Quality 9.4 Manage Project Team 10.3 Control Communications 11.6 Control Risks 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13.3 Manage Stakeholder Engagement 13.4 Control Stakeholders Engagement INPUTS 4.5 Perform Integrated Change Control

Closed procurements OUTPUTS 12.4 Close Procurements

Communications Management Plan OUTPUTS 10.1 Plan Communications Management INPUTS 10.2 Manage Communications 13.3 Manage Stakeholder Engagement

Cost Baseline OUTPUTS 7.3 Determine Budget Page 4 of 24


Cost forecasts OUTPUTS 7.4 Control Costs INPUTS 4.4 Monitor and Control Project Work

Cost Management Plan OUTPUTS 7.1 Plan Cost Management INPUTS 7.2 Estimate Costs 7.3 Determine Budget 11.2 Identify Risks 11.4 Perform Quantitative Risk Analysis

Deliverables OUTPUTS 4.3 Direct and Manage Project Work INPUTS 8.3 Control Quality

Page 5 of 24


Enterprise Environmental Factors INPUTS 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 5.1 Plan Scope Management 5.4 Create WBS 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 7.1 Plan Cost Management 7.2 Estimate Costs 8.1 Plan Quality Management 9.1 Plan Human Resource Management 9.2 Acquire Project Team 10.1 Plan Communications Management 10.2 Manage Communications 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 12.1 Plan Procurement Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Management

Page 6 of 24


Enterprise Environmental Factors Updates OUTPUTS 9.3 Develop Project Team

Updates

9.4 Manage Project Team

Updates

Final product, service, or result transition OUTPUTS 4.6 Close Project or Phase

Human Resource Management Plan OUTPUTS 9.1 Plan Human Resource Management INPUTS 7.2 Estimate Costs 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 11.2 Identify Risks

Issue log OUTPUTS 13.3 Manage Stakeholder Engagement INPUTS 9.4 Manage Project Team 10.3 Control Communications 13.4 Control Stakeholders Engagement

Make‐or‐Buy Decisions OUTPUTS 12.1 Plan Procurement Management INPUTS 12.2 Conduct Procurements

Page 7 of 24


Milestone List OUTPUTS 6.2 Define Activities INPUTS 6.3 Sequence Activities

Page 8 of 24


Organizational Process Assets INPUTS 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 4.6 Close Project or Phase 5.1 Plan Scope Management 5.3 Define Scope 5.4 Create WBS 5.6 Control Scope 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 6.7 Control Schedule 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8.1 Plan Quality Management 8.3 Control Quality 9.1 Plan Human Resource Management 9.2 Acquire Project Team 9.4 Manage Project Team 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Control Communications 11.1 Plan Risk Management Page 9 of 24


11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 12.1 Plan Procurement Management 12.2 Conduct Procurements 13.1 Identify Stakeholders 13.2 Plan Stakeholder Management 13.3 Manage Stakeholder Engagement

Organizational Process Assets Updates OUTPUTS 4.6 Close Project or Phase

Updates

5.6 Control Scope

Updates

6.7 Control Schedule

Updates

7.4 Control Costs

Updates

8.2 Perform Quality Assurance

Updates

8.3 Control Quality

Updates

9.4 Manage Project Team

Updates

10.2 Manage Communications

Updates

10.3 Control Communications

Updates

11.6 Control Risks

Updates

12.3 Control Procurements

Updates

12.4 Close Procurements

Updates

13.3 Manage Stakeholder Engagement

Updates

13.4 Control Stakeholders Engagement

Updates

Outputs from other Processes INPUTS 4.2 Develop Project Management Plan

Process improvement Plan OUTPUTS 8.1 Plan Quality Management INPUTS 8.2 Perform Quality Assurance Page 10 of 24


Procurement Documents OUTPUTS 12.1 Plan Procurement Management INPUTS 11.2 Identify Risks 12.2 Conduct Procurements 12.3 Control Procurements 12.4 Close Procurements 13.1 Identify Stakeholders

Procurement Management Plan OUTPUTS 12.1 Plan Procurement Management INPUTS 12.2 Conduct Procurements

Procurement Statement of work OUTPUTS 12.1 Plan Procurement Management INPUTS 12.2 Conduct Procurements

Project Calendars OUTPUTS 6.6 Develop Schedule INPUTS 6.7 Control Schedule

Page 11 of 24


Project Charter OUTPUTS 4.1 Develop Project Charter INPUTS 4.2 Develop Project Management Plan 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 6.1 Plan Schedule Management 7.1 Plan Cost Management 11.1 Plan Risk Management 13.1 Identify Stakeholders

Project communications OUTPUTS 10.2 Manage Communications INPUTS 10.3 Control Communications

Project Documents INPUTS 8.2 Perform Quality Assurance 8.3 Control Quality 11.2 Identify Risks 12.2 Conduct Procurements 13.4 Control Stakeholders Engagement

Page 12 of 24


Project Documents Updates OUTPUTS 4.3 Direct and Manage Project Work

Updates

4.4 Monitor and Control Project Work

Updates

4.5 Perform Integrated Change Control

Updates

5.3 Define Scope

Updates

5.4 Create WBS

Updates

5.5 Validate Scope

Updates

5.6 Control Scope

Updates

6.3 Sequence Activities

Updates

6.4 Estimate Activity Resources

Updates

6.5 Estimate Activity Durations

Updates

6.6 Develop Schedule

Updates

6.7 Control Schedule

Updates

7.2 Estimate Costs

Updates

7.3 Determine Budget

Updates

7.4 Control Costs

Updates

8.1 Plan Quality Management

Updates

8.2 Perform Quality Assurance

Updates

8.3 Control Quality

Updates

9.4 Manage Project Team

Updates

10.1 Plan Communications Management

Updates

10.2 Manage Communications

Updates

10.3 Control Communications

Updates

11.3 Perform Qualitative Risk Analysis

Updates

11.4 Perform Quantitative Risk Analysis

Updates

11.5 Plan Risk Response

Updates

11.6 Control Risks

Updates

12.1 Plan Procurement Management

Updates

12.2 Conduct Procurements

Updates

12.3 Control Procurements

Updates

13.2 Plan Stakeholder Management

Updates Page 13 of 24


13.3 Manage Stakeholder Engagement

Updates

13.4 Control Stakeholders Engagement

Updates

Project Funding Requirements OUTPUTS 7.3 Determine Budget INPUTS 7.4 Control Costs

Page 14 of 24


Project Management Plan OUTPUTS 4.2 Develop Project Management Plan INPUTS 4.3 Direct and Manage Project Work 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 4.6 Close Project or Phase 5.1 Plan Scope Management 5.5 Validate Scope 5.6 Control Scope 6.1 Plan Schedule Management 6.7 Control Schedule 7.1 Plan Cost Management 7.4 Control Costs 8.1 Plan Quality Management 8.3 Control Quality 9.1 Plan Human Resource Management 10.1 Plan Communications Management 10.3 Control Communications 11.1 Plan Risk Management 11.6 Control Risks 12.1 Plan Procurement Management 12.3 Control Procurements 12.4 Close Procurements 13.2 Plan Stakeholder Management 13.4 Control Stakeholders Engagement

Page 15 of 24


Project Management Plan Updates OUTPUTS 4.3 Direct and Manage Project Work

Updates

4.4 Monitor and Control Project Work

Updates

4.5 Perform Integrated Change Control

Updates

5.6 Control Scope

Updates

6.6 Develop Schedule

Updates

6.7 Control Schedule

Updates

7.4 Control Costs

Updates

8.2 Perform Quality Assurance

Updates

8.3 Control Quality

Updates

9.2 Acquire Project Team

Updates

9.4 Manage Project Team

Updates

10.2 Manage Communications

Updates

10.3 Control Communications

Updates

11.5 Plan Risk Response

Updates

11.6 Control Risks

Updates

12.2 Conduct Procurements

Updates

12.3 Control Procurements

Updates

13.3 Manage Stakeholder Engagement

Updates

13.4 Control Stakeholders Engagement

Updates

Project Schedule OUTPUTS 6.6 Develop Schedule INPUTS 6.7 Control Schedule 7.2 Estimate Costs 7.3 Determine Budget 12.1 Plan Procurement Management

Page 16 of 24


Project Schedule Network Diagrams OUTPUTS 6.3 Sequence Activities INPUTS 6.6 Develop Schedule

Project Scope Statement OUTPUTS 5.3 Define Scope INPUTS 5.4 Create WBS 6.3 Sequence Activities 6.5 Estimate Activity Durations 6.6 Develop Schedule

Project Staff assignments OUTPUTS 9.2 Acquire Project Team INPUTS 6.6 Develop Schedule 9.3 Develop Project Team 9.4 Manage Project Team

Project Statement Of Work INPUTS 4.1 Develop Project Charter

Quality Checklists OUTPUTS 8.1 Plan Quality Management INPUTS 8.3 Control Quality

Page 17 of 24


Quality Control Measurements OUTPUTS 8.3 Control Quality INPUTS 8.2 Perform Quality Assurance

Quality Management Plan OUTPUTS 8.1 Plan Quality Management INPUTS 8.2 Perform Quality Assurance 11.2 Identify Risks

Quality Metrics OUTPUTS 8.1 Plan Quality Management INPUTS 8.2 Perform Quality Assurance 8.3 Control Quality

Requirements Documentation OUTPUTS 5.2 Collect Requirements INPUTS 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 8.1 Plan Quality Management 12.1 Plan Procurement Management

Requirements Management Plan OUTPUTS 5.1 Plan Scope Management INPUTS 5.2 Collect Requirements Page 18 of 24


Requirements Traceability Matrix OUTPUTS 5.2 Collect Requirements INPUTS 5.5 Validate Scope 5.6 Control Scope

Resource breakdown structure OUTPUTS 6.4 Estimate Activity Resources INPUTS 6.5 Estimate Activity Durations 6.6 Develop Schedule

Resource Calendars OUTPUTS 9.2 Acquire Project Team 12.2 Conduct Procurements INPUTS 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 7.3 Determine Budget 9.3 Develop Project Team

Risk Management Plan OUTPUTS 11.1 Plan Risk Management INPUTS 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Response

Page 19 of 24


Risk Register OUTPUTS 11.2 Identify Risks INPUTS 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 7.2 Estimate Costs 7.3 Determine Budget 8.1 Plan Quality Management 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Response 11.6 Control Risks 12.1 Plan Procurement Management

Schedule Baseline OUTPUTS 6.6 Develop Schedule

Schedule Data OUTPUTS 6.6 Develop Schedule INPUTS 6.7 Control Schedule

Schedule forecasts OUTPUTS 6.7 Control Schedule INPUTS 4.4 Monitor and Control Project Work

Page 20 of 24


Schedule Management Plan OUTPUTS 6.1 Plan Schedule Management INPUTS 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 11.2 Identify Risks 11.4 Perform Quantitative Risk Analysis

Scope Baseline OUTPUTS 5.4 Create WBS INPUTS 6.2 Define Activities 7.2 Estimate Costs 7.3 Determine Budget 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis

Scope Management Plan OUTPUTS 5.1 Plan Scope Management INPUTS 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS

Selected sellers OUTPUTS 12.2 Conduct Procurements

Page 21 of 24


Seller proposals INPUTS 12.2 Conduct Procurements

Source selection criteria OUTPUTS 12.1 Plan Procurement Management INPUTS 12.2 Conduct Procurements

Stakeholder Management Plan OUTPUTS 13.2 Plan Stakeholder Management INPUTS 5.2 Collect Requirements 13.3 Manage Stakeholder Engagement

Stakeholder Register OUTPUTS 13.1 Identify Stakeholders INPUTS 5.2 Collect Requirements 8.1 Plan Quality Management 10.1 Plan Communications Management 11.1 Plan Risk Management 11.2 Identify Risks 12.1 Plan Procurement Management 13.2 Plan Stakeholder Management

Team Performance assessments OUTPUTS 9.3 Develop Project Team INPUTS 9.4 Manage Project Team

Page 22 of 24


Validated Changes OUTPUTS 8.3 Control Quality INPUTS 4.4 Monitor and Control Project Work

Verified Deliverables OUTPUTS 8.3 Control Quality INPUTS 5.5 Validate Scope

Work Performance Data OUTPUTS 4.3 Direct and Manage Project Work INPUTS 5.5 Validate Scope 5.6 Control Scope 6.7 Control Schedule 7.4 Control Costs 8.3 Control Quality 10.3 Control Communications 11.6 Control Risks 12.3 Control Procurements 13.4 Control Stakeholders Engagement

Page 23 of 24


Work Performance Information OUTPUTS 5.5 Validate Scope 5.6 Control Scope 6.7 Control Schedule 7.4 Control Costs 8.3 Control Quality 10.3 Control Communications 11.6 Control Risks 12.3 Control Procurements 13.4 Control Stakeholders Engagement INPUTS 4.4 Monitor and Control Project Work

Work Performance Reports OUTPUTS 4.4 Monitor and Control Project Work INPUTS 4.5 Perform Integrated Change Control 9.4 Manage Project Team 10.2 Manage Communications 11.6 Control Risks 12.3 Control Procurements

Page 24 of 24