As ratepayers, you will want to know that your money is being spent responsibly on things that matter to you. We have achieved some long anticipated goals over the last year and we share some of the highlights here:

• The Papawai Wastewater Pipeline upgrade was brought forward and successfully completed in the 2021/22 year.

• Tauwharenikau (Tauherenikau) pipe repairs were completed as a medium-term solution while a longer-term one is planned and budgeted for.

• An upgraded 8 million litre water storage capacity was added at the Waiohine reservoir to increase the resilience of the water supply to the Featherston and Greytown communities.

• The Featherston Wastewater Treatment Plant consent application has been made to Greater Wellington Regional Council.

• One of the four Martinborough water reservoirs has received much needed maintenance, with work completed on the reservoir’s interior linings and exterior walls.