Project Presentation Dated 10 Oct 17
Projects Focused • • • •
Three Projects Focused – synthetic pyrothroides Acephate Expansion Conizol
Others 1. Utility Expansion. 2. Environment Clearance. 3. Electrical additional Load approvals.
Target • Synthetic Pyrothroides – By March 17 • Acephate Expansion – By April 17 • Conizol - By May 17 • We will revise and squeeze the target after reviewing the progress.
Project Schedule • Synthetic Pyrothroides • F:\Working Desktop\1. Plant 4 - synthetic pyrothroides\Planning
Current status • • • • • •
Process Finalization Work Completed. Equipment Sizing Work Completed. Floor wise Equipment drawing Finalized. Structural Design Completed. Civil Work in progress. Equipment Inquiry Sent to suppliers for quotations.