Project Presentation Dated 05 Dec 17
Projects status Synthetic pyrothroide 1. Basic Engineering – Completed. 2. Detail Engineering – a) b) c) d)
Civil – Completed. Structure – Completed Equipments Specification – Completed Piping specifications – Working (To be completed by Dec 10th ) e) Instrumentation and Electrical – To be followed after completion of Piping detailing.
Project Status Continues… Synthetic pyrothroide….. 3. Execution : a. Civil Work : Completed. b. Equipment Procurement including utilities and MEE – Completed. c. Vendor Assessment and Material status follow-up visit – To be finished by 12th Dec 17. d. Equipments available for Erection – From 25th Dec 17. e. Installation of structure – Main Columns and beams t be completed by 15th Dec 17. f. All Structure work to be completed by Dec End.
Structure Installation
Project Status Continues… Acephate Expansion 1. Basic Engineering – Completed 2. Detail Engineering – a) Civil – Completed. b) Structure – Main Column and beam Completed. Other work Railing, Supporting Beams and roof to be completed by 15th Dec 17. c) Equipments Specification – Completed. d) Piping specifications – To be started after Synthetic pyrotroide work completed. e) Instrumentation and Electrical – To be started after Synthetic pyrotroide work completed.
Project Progress Pictures
Others 1. Utility Expansion. – Order Placed for i) Boiler ii) Chiller iii) Cooling Tower iv) Transformer – Waiting for Quotation and to be finalized in next week. 2. Civil Work for Cooling tower and chiller started. Boiler to be started after received civil drawings.
Cooling tower civil work in progress………
Project Cost SN
Description
Rs
1
Total Purchase order Values
167,011,401
2
Advance Given
3
Balance Amount
4
MEE not considered in earlier Project
18,900,000
5
GST Extra in above cost
40,517,075
50,054,517 116,956,884
Target Base line target Fixed as March 2018