Strategic Activity 1: People and Communities Ambition Create an enriched and vibrant social fabric through regular interaction with our people and communities Accountability Director Community Services
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 1A: Community Facilities - Provide safe, well-serviced facilities for people to live, grow and connect within Actions Relating to all 1A Function Elements:
Develop Building Asset Management Plan Collation and validation of building and recreational databases Negotiate Community facility Funding Projects with Resource Industry Proponents Review and Establish Service Level Agreements Review Management Committees in accordance with Council's Advisory Committee Policy Develop a public liability insurance policy for all Council owned facilities
Civic Centres
Community Halls
Sport & Rec Ground
1.2
RCSM
01-Jul-11
31-Aug-11
1.2
RCSM
01-Jul-11
31-Oct-11
1.2
DCS
01-Jul-11
30-Jun-12
1.2
RCSM
01-Sep-11
30-Jun-12
1.2
RCSM & CSMs
01-Jul-11
31-Dec-11
No of service levels reviewed % SLA's finalised
Number of Funded Community Facility Projects
1.2
RCSM
01-Jul-11
30-Sep-11
Review and establish Hire Agreements with volunteer committees
1.2
RCSM & CSMs
01-Jul-11
30-Jun-12
Identify and Collate Asbestos Register for Council owned facilities
1.2
RCSM & CSMs
01-Jul-11
31-Dec-11
Conduct a Disability Audit of Council owned facilities
1.2
RCSM & CSMs
01-Jul-11
31-Dec-11
CSMs
01-Sep-11
30-Jun-12
CSMs
01-Sep-11
30-Jun-12
01-Jul-11
30-Jun-12
Number Hiring's of Regional Civic Centres
01-Jul-11
30-Jun-12
Number Hiring's of Regional Showgrounds
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
01-Jul-11
31-Dec-11
Review existing service levels Develop Management and Marketing Plans Undertake maintenance and repairs to agreed service levels Undertake Annual Inspection of WHS, Fire Compliance and Access Undertake maintenance and repairs to agreed service levels Undertake maintenance and repairs to agreed service levels Develop of Master Plan for Centenary Oval, Miles Development
1.2 1.2 1.2 1.2 1.2
1.2 1.2
CSMs CSMs CSMs
CSMs CSM
% Management Contracts Finalised
Customer Service Centre
Council Housing
Coordinate the relocation from Drayton Street to Marble Street Customer Service Centre Investigate funding opportunities for Council Housing across the region Undertake maintenance and repairs to agreed service levels Ensure establishment of Council Housing Reserve for surplus revenue
1.2
CSM & SPE
1.2
CSMs
1.2
CSMs
1.2
DFICT & DCS
01-Sep-11
31-Dec-11
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
30-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA1 Page 1 of 7
Patronage of Regional Swimming Pools
Strategic Function Elements
Showgrounds
Swimming/Fitness Centre
Public Conveniences
Net Budget
Actions Develop a Master plan/Management Plan for Dalby Showgrounds Develop New Management Agreement for Dalby Aquatic Centre Review and develop new Management Agreement for Dalby PCYC Renewal of Management Agreement for Chinchilla Aquatic and Fitness Centre Investigate Regional Branding Swimming/Fitness Centres Undertake maintenance and repairs to agreed service levels
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
1.2
CSM
30-Jul-11
30-Jun-12
1.2
CSM
01-Sep-11
30-Jun-12
1.2
CSM
01-Jul-11
31-Dec-11
1.2
CSM
01-Nov-11
30-Jun-12
1.2
RCSM & SCM
01-Sep-11
31-Mar-12
1.2
CSMs
01-Jul-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 1B: Cultural Development - Encourage and develop participative and culturally connected communities Library
Stage One Relocation of Dalby Library - Develop Relocation Implementation Plan Stage Two Family Literacy Program for Sustainable and Learning Communities
1.8
LCSC
01-Sep-11
30-Jun-12
1.8
LCSC
01-Jul-11
30-Jun-12
Stage Two - Implement Self-Service Technologies
1.8
LCSC
01-Jul-11
30-Jun-12
Library Membership as percentage of population
Establish Service Level Agreements Develop Implementation and Inclusion Plan for Digitalisation Projects Target services and programs to align with key demand areas in learning, literacy, lifestyle and cultural support
1.8
LCSC
01-Jan-12
30-Jun-12
% Population active members of regional library network
1.8
LCSC
01-Oct-11
30-Jun-12
Number of literacy based resources added to the collection
1.8
LCSC
01-Jul-11
30-Jun-12
Number of literacy and learning based programs completed
1.8
LCSC
01-Jul-11
31-Dec-11
Number of self-service installations
1.7
RCSM
01-Oct-11
30-Jun-12
1.7
RCSM
01-Jul-11
31-Dec-11
1.7
RCSM
01-Jan-12
30-Jun-12
1.7
CSM
01-Jul-11
30-Jun-12
1.7
CSM
01-Jun-11
30-Jun-12
Review existing Library system to determine if it can support existing museum and gallery systems Cultural Programmes
Cultural Facilities
Develop Public Art Policy Finalise and implement a Regional Arts Collection Policy Investigate the need to develop a Regional Cultural Plan Managing development and implementation of Master Plan for new Cultural and Arts Precinct at 107 Drayton Street Investigate operational arrangements of new Cultural and Arts Precinct at 107 Drayton Street Review Visitor Information Centre and Art Gallery facility for Tara
Cultural Projects
1.7
CSM
01-Oct-11
30-Jun-12
Implement MAMM Branding
1.7
CSM
01-Jul-11
31-Dec-11
Revise Business Plan for Dogwood Crossing
1.7
CSM
01-Jul-11
31-Dec-11
Review Stage 3 Dogwood Crossing Expansion Formalise Management Agreements with Museums and Galleries Formalise Management Agreement for the proposed Bell Community Centre
1.7
01-Jun-11
30-Jun-12
1.3 & 1.7
CSM RCSM & CSMs
01-Oct-11
30-Jun-12
1.7
CSMD
01-Jun-11
30-Jun-12
1.7
CSM
01-Sep-11
30-Jun-12
Dogwood Crossing Visual Arts Project
Western Downs Regional Council Operational Plan - SA1 Page 2 of 7
Total library visits per capita
% Management agreements completed
Strategic Function Elements
Net Budget
Actions Investigate funding for Miles Dogwood Public Art Project Develop funding applications and facilitate implementation of Regional Public Art Project for Western Downs on Drayton Establish DOC and LGAQ Community Recovery Officers within Communities
Regional Art Development Fund
RADF 20 Year Celebrations Develop Disaster Recovery Activities in liaison with Local and District Disaster Coordination Centres
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
1.7
CSM
01-Jul-11
30-Jun-12
1.7
RCSM
01-Jul-11
30-Jun-12
1.1
CSM's
01-Aug-11
30-Jun-12
1.7
RCSM
01-Jul-11
31-Dec-11
1.2
CSM's
01-Sep-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
$ Funded for Regional Public Art Project for Western Downs on Drayton
Strategic Function 1C: Community Development - Improve community health and wellbeing through group and individual participation in social and recreational activities Youth Development
Sporting Programme
Review Wandoan Rural Youth Services for 2012 and beyond Develop Youth Shoot Strategy Report (Local and Regional Initiatives) Pilot Annual Forum for Community based Sport and Recreation Groups Develop Information and Communication Package
1.1
CSM
01-Jul-11
31-Oct-11
1.1
CSMs
01-Aug-11
31-Dec-11
01-Jan-12
30-Jun-12
01-Jan-12
30-Jun-12
RCSM
01-Oct-11
31-Mar-12
1.7 1.7
Community Fin Assist Program - Annual Donation
Develop a Community Grants Policy
1.1
Community Projects
Review Research Project for Rural Residential Sub-Divisions
Community Programmes
Community Events/Functions
RCSM & CSMs RCSM & CSMs
1.1
CSMT
01-Jul-11
30-Jun-12
Finalise Dalby Town Entry Elements Project Attract funding for Wandoan Visitor and Recreation Precinct Master Plan Develop a Community Services Section and Community Directory on WDRC Website
1.1
CSMD
01-Jul-11
30-Sep-11
1.1
CSMM
01-Jul-11
30-Jun-12
1.1
RCSM
01-Jul-11
31-Mar-12
Develop a Volunteers Policy
1.1
RCSM
01-Aug-11
31-Dec-11
Recruit Community Recovery Officers to develop and implement a Community Recovery Strategy
1.1
CROs
01-Jul-11
30-Jun-13
100 Year Celebrations for Tara Community
1.2
CSMT
01-Jul-11
30-Jun-12
50 Year Celebrations for Miles Civic Centre
1.2
CSMM
01-Jul-11
10-Sep-11
01-Jul-11
31-Dec-11
01-Jul-11
30-Jun-12
01-Jul-11
31-Dec-11
% Participation rate of Council Supported Youth Programs
Strategic Function 1D: Community Services - Provide a safe and well-serviced communities Aged Care
Conduct Audit of Aged Care Facility Expenses Source funding opportunities for future expansion of aged care facilities
1.2 1.2
CSMM & CSMT CSMM & CSMT
% Occupancy Rate Regional Aged Cared Services % Occupancy Rate Regional Housing Services
Social Housing
Home & Community Care (HACC)
Determine requirements under WDRC Housing Strategy
1.2
CSMs
Implement WDRC Housing Strategy
1.2
DCS
01-Jan-12
30-Jun-12
Review HACC Management Committee Structure to determine need for WDRC Regional HACC Advisory Committee
RCSM & CSMs
01-Jul-11
31-Dec-11
1.2
Western Downs Regional Council Operational Plan - SA1 Page 3 of 7
HACC client hours utilised
Strategic Function Elements
Net Budget
Actions Develop sub-contracts with HACC service providers
Corporate Plan Linkage
Responsible Officer
1.2
Timeframe Start
Finish
RCSM & CSMs
01-Jul-11
31-Dec-11
1.2
DCSM
01-Jul-11
09-Sep-11
1.2
DCSM
01-Jul-11
30-Jun-12
1.2
DCSM
01-Aug-11
31-Oct-11
1.2
DCSM
01-Jul-11
09-Sep-11
1.2
DCSM
01-Jul-11
09-Sep-11
1.2
DCSM
01-Aug-11
30-Jun-12
1.2
FPOW
01-Jul-11
30-Sep-11
1.2
DCSM
01-Jul-11
01-Aug-11
1.2
PM
01-Jul-10
31-May-12
1.2
CFSC
01-Jul-11
30-Jun-12
1.2
CFSC
01-Jul-11
30-Jun-12
1.2
CFSC
01-Jul-11
30-Jun-12
1.2
DFICT
01-Jul-11
30-Nov-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
People and Communities - Capital Projects
11110.0802.200.0002
11110.0802.200.0003
Dalby Pool - Diving tower re-installation - new steps need to be designed, built and installed that meet Heritage guidelines as well as the Building $50,000 Code Dalby Pool - upgrade & relocation of Chlorine Tank bund to comply with WPH&S regulations and to improve the level of safety to the public by not delivering chlorine via the Dalby Caravan Park $15,000 grounds Dalby Showgrounds - Asbestos removal to reduce the possibility of public injury/health concerns regarding the extremely poor condition of the old stable roofs and other site locations containing asbestos. Disposal must be conducted by licensed contractors and waste disposed of in registered waste facilities (Toowoomba closest site for required volume)
11110.0802.200.0011
11110.0802.200.0036
11110.0802.200.0050
11110.0802.200.0071
$100,000 Jandowae Pool - refurbishment of existing pumping and cleaning equipment in order to maintain the necessary health standards for water quality - resubmission of unapproved project from $160,000 2009/10 budget Jandowae Pool - purchase of thermal blanket to maintain water temperature and reduce water $23,000 evaporation Dalby Pool - 25m Indoor facility - expected grant of $4.6m from State funding for the development and construction of a 25m indoor heated swimming pool to be located adjacent to the existing Dalby $4,600,000 Pool Wandoan - Construction of a Skate Park for the Wandoan youth activities program - Council has applied for funding from Sport and Rec to the Value of $126000 - Carry over money only see project 11110.802.200.226 for 2011/12 allocation
11110.0802.200.0082
$60,256 Retaining Wall - Marble Street Arts Centre - Dalby
11110.0802.200.0171 11110.0802.200.0184 11110.0802.200.0208 11110.0802.200.0209 11110.0802.200.0210 11110.0802.200.0211 11110.0802.200.0212 11110.0802.200.0214
$30,000 $33,402 Bell - Community Centre Planning & Design Showground - Capital Works (Dalby) (was project $20,000 11110.802.200.0001 in 10/11 year) Showground Capital - Jandowae was project $20,000 11110.802.200.0195 in 10/11 Showground Capital - Bell (Project 11110.802.196 $20,000 in 10/11) Disposal of Wood Street - Dalby - Valuation $2,450 expense only Establishment of Corporate Office - Marble St $1,420,437 Carry Over - Main Contract $206,000 Establish Corporate Office - Air Conditioning
Western Downs Regional Council Operational Plan - SA1 Page 4 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
Net Budget
Actions
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
7.1
DCSM
01-Jul-11
31-Dec-11
1.2
TCSM
01-May-11
31-Jan-12
1.2
FPOW
01-Jul-11
30-Jun-12
1.2
FPOW
01-Jul-11
30-Jun-13
1.2
FPOW
01-Jul-11
30-Jun-13
1.2
CFSC
01-May-12
30-Jun-13
1.2
CCSM
01-Aug-11
30-Apr-12
1.2
DCSM
01-Jul-11
31-May-12
1.2
DCSM
01-Jul-11
30-Jun-12
1.2
DCSM
01-Jul-11
30-Jun-12
Establish Corporate Office - Fire Suppression System Removal & Fire detection system upgrade 11110.0802.200.0215
11110.0802.200.0216 11110.0802.200.0218 11110.0802.200.0219 11110.0802.200.0220 11110.0802.200.0221 11110.0802.200.0222 11110.0802.200.0223 11110.0802.200.0224 11110.0802.200.0225 14410.0802.200.0002
11110.0800.200.0015
11110.0800.200.0041
11110.0800.200.0041
11110.0800.200.0074
11110.0800.200.0082
11110.0802.200.0012
11110.0802.200.0030
11110.0802.200.0039
$16,800 Establish Corporate Office - Grounds Works (includes Car park Ergon substation) & Shade $164,500 structure Establish Corporate Office - Signage - internal & $75,000 exterior $19,000 Establish Corporate Office - Security System $25,000 Establish Corporate Office - Office Furniture Establish Corporate Office - Blinds & Reflective $43,000 film - level 4 & internal frosted film Establish Corporate Office - Project Consultants $33,000 Establish Corporate Office - Fire rating consultants $12,500 $45,000 Establish Corporate Office - AV System Establish Corporate Office - Acoustic Doors Level $35,000 1 & 4 Meeting Room Extensions to HACC centre 32 Bilton street Tara $194,444 Major refurbishment of the Tara Memorial Swimming Pool structure. Includes modification and fibre glassing of the pool "shell" creating a wet $250,000 deck area. Extension of Existing Gym @ Chinchilla Aquatic & Gym due to the increase of patronage by resource $130,000 workers. Extension of Existing Gym @ Chinchilla Aquatic & Gym due to the increase of patronage by resource $130,000 workers. Chinchilla Cultural Centre - Purchase of new equipment for use in conferences, replacement of air conditioning, reupholstering of 140 cinema chairs, installation of roof harness points to meet WHO standards for repairs on roof, repairs to timber floor in foyer and ballroom, replacement of damaged timber decking and completion of upstairs dressing rooms. $21,429 Provide exercise stations in Chinchilla Parks to encourage physical activity amongst locals and $55,000 visitors. Dalby Showgrounds - replacement of electrical services at the northern end of the site due to extremely poor condition of switchboxes, electrical wiring and power poles $60,000 Bell Community Centre - establishment of a Community Centre in the town of Bell resubmission of unapproved project from 2009/10 $1,300,000 budget Dalby - develop plans & relocation Dalby Library From Stuart Street to 107 Drayton Street $1,600,000
Western Downs Regional Council Operational Plan - SA1 Page 5 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
11110.0802.200.0054
11110.0802.200.0062
11110.0802.200.0074 11110.0802.200.0087
11110.0802.200.0091
Net Budget
Actions
Dalby Diplock Park - new solar lighting over Skate Park and relocation of existing toilet block closer to the Warrego Hwy for use by park users and $130,000 travelling public Kaimkillenbun Hall - refurbishment of electrical wiring within the hall as a result of identified failings of the existing wiring that may pose a serious safety risk to the hall users as well as posing a $10,000 potential fire risk Regional Showgrounds (7 of) - major project work to be shared across the regional showgrounds ($20,000 each) RECOMMEND: Project 11110.802.200.10 - $10K, Proj 11110.802.52 $140,000 $20K Wandoan - Wandoan Pool - Upgrade as per $38,000 RLCIP Application Wandoan Cultural Centre - Replace curtains with fire retardant curtains to meet fire safety standards, Curtains are torn and are getting to an $50,000 unusable state
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
1.2
DCSM
01-Jul-11
31-May-12
1.2
DCSM
01-Jul-11
30-Jun-12
1.2
DCSM
01-Jul-10
30-Jun-20
1.2
FPOW
01-Jul-11
31-Jul-11
1.2
FPOW
01-Jul-11
31-Dec-11
1.2
FPOW
01-Aug-11
31-May-12
1.2
FPOW
01-Jul-11
30-Jun-12
1.2
FPOW
01-Jul-11
30-Jun-12
1.2
FPOW
01-Oct-11
29-Feb-12
1.2
FPOW
01-Oct-11
31-Jan-12
1.2
DCSM
01-Jul-11
30-Jun-13
1.2
CDC
01-Jul-11
30-Jun-12
1.2
DCSM
01-Jul-11
30-Apr-12
1.2
FPOW
01-Jul-11
30-Jun-12
1.2
FPOW
01-Jul-11
30-Jun-12
Miles - Miles Swimming Pool - Refine Inside of Main and toddlers pools with fibreglass coating, upgrade pipe work under Main pool, painting of concourse, upgrade of Main pool pump, replacement of ballast tank ladder and ass valves and install new chemical dosing pump, electrical earth bonding of equipment around the pool Fibre Glass main and toddles pool $160,000, Upgrade pipe work under pool , Upgrade main pool pump , Painting of concourse Replacement of Ballast tank ladder , replacement of identified valves , Install new Chemical Dosing equipment, upgrade starting blocks, electrical earth bonding
11110.0802.200.0108
11110.0802.200.0122
11110.0802.200.0123 11110.0802.200.0147
11110.0802.200.0148 11110.0802.200.0170 11110.0802.200.0189 11110.0802.200.0198 11110.0802.200.0202 11110.0802.200.0203
$250,000 Miles - Community housing - Painting of the interior and external of 3 community houses - The 3 community houses were identified in the Annual $20,000 Report Miles - Miles Retirement Village - Painting of the interior of 3 retirement village units - Identified in $20,000 Annual Report Miles - Condamine Cemetery - Install new Fence $6,000 existing fence falling down Miles - Pioneer Park Condamine - New Play Equipment, Currently has no play equipment and the park is used by travellers for rest stops $45,000 Upgrade facilities precinct Jandowae - Squash $80,000 Court, Gym & Pool area. Purchase of a new pool vacuum cleaner for Tara Memorial Swimming Pool $10,000 PCYC, Nicholson Street Car park - GRAVEL $30,000 ONLY Miles Centenary Park - Football Oval Master plan $28,000 & Telemetry Works $30,000 Wandoan - Main Street Streetscape Plan
Western Downs Regional Council Operational Plan - SA1 Page 6 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements 11110.0802.200.0204 11110.0802.200.0205 11110.0802.200.0213
11110.0802.200.0217
Net Budget
Actions
$50,000 Lagoon Walkway - Extension Development of Dalby Town Entrances as per $120,000 master plans Establish Corporate Office - Marble Street - Main $100,000 Contract - Estimated Extras PCYC Redevelopment Refer to council report tabled 15/06/2011 Timetable pushed back due to floods and additional costs due to additional $545,000 variations outside of contract
11110.0802.200.0226
PCYC Redevelopment Refer to council report tabled 15/06/2011 Timetable pushed back due to floods and additional costs due to additional $345,000 variations outside of contract Wandoan - Construction of a Skate Park for the Wandoan youth activities program - Sport & Rec funding - See Project 11110.802.200.82 for carry $152,810 over
11217.0800.200.0001
Detailed design Multipurpose Sporting Centre $50,000 Chinchilla
11110.0802.200.0217
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
1.2
TCSM
01-Jul-11
30-Jun-15
1.2
WMD
01-Jul-11
30-Jun-14
7.1
DCS
01-Jul-11
31-Dec-11
1.2
DCSM
01-Jul-11
30-Jun-12
1.2
DCSM
01-Jul-11
30-Jun-12
1.2
FPOW
01-Jul-11
30-Sep-11
1.2
DCS
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA1 Page 7 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Activity 2: Growth and Opportunity Ambition Realise opportunities and build capacity for the sustainable growth of our prosperous region Accountability Chief Executive Officer and Director Community Services
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 2A: Major Projects - Maximise opportunities from major developments and ensure the highest level of regional governance and sustainability EIS Response
Respond to EIS/TOR/Amendments (2.1.7)
2.1
MDESM
01-Jul-11
30-Jun-12
All EIS Responses provided within set deadlines
Research
Develop Major Project Fact Sheets (2.1.2) Develop Fact Book via online database system (2.1.11) Prepare and publish Economic Profiles annual update reports (2.4.8)
2.1
SERO
01-Jul-11
30-Jun-12
100% Major Project fact sheets developed, loaded onto AWD website within 4 weeks
2.1
MDESM
2.4
EDC
01-Jul-11
30-Jun-12
01-Dec-11
28-Feb-12
Strategic Function 2B: Economic Development - Encourage and facilitate growth through development of business and industry Business Growth
Western Downs Business Excellence Awards
2.6
EDC
01-Jul-11
30-Jun-12
Improved average scores each District
Attend Surat Basin Conference
2.6
MDESM
01-Jul-11
30-Dec-11
10 key leads achieved business investment and skills attraction
Surat Basin Corporation
2.6
MDESM
01-Jul-11
30-Jun-12
Chambers of Commerce Operations
2.6
MDESM
01-Jul-11
30-Jun-12
KPI's set for Chamber funding met satisfactorily
Facilitate Two Business Investment Tours
2.1
MDESM
01-Jul-11
30-Jun-12
Number of businesses attending events from outside region
Implement Supply Chain Building Program
2.6
MDESM
01-Jul-11
30-Jun-12
10 businesses assisted with program
Establish Business Advisory Service (IP)
2.6
MDESM
01-Jul-11
30-Jun-12
25 Businesses Supported
Advance Western Downs Website
2.6
EDC
01-Jul-11
30-Jun-12
No. of visits increased by 20% from previous year
Business News Monitor Develop Action Agenda Plans and present to Council (Links to ED Plan)
2.6
EDC
01-Jul-11
30-Jun-12
Number of new subscribers quarterly
2.1
30-Jun-12
2.4
MDESM EDC
01-Jul-11
Exporters Strategy & Support Program
01-Jul-11
30-Jun-12
Number of businesses participating in program
Business Support Initiatives
2.6
EDC
01-Jul-11
30-Jun-12
Number of businesses participating in programs
Implement External Business Support Program
2.6
MDESM
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
MDESM Infrastructure & Transport
Develop Industrial & Commercial Land Strategy in liaison with Planning Directorate
2.4
MDESM MDESM
IT Education & Training
Skilled Persons Attraction Develop Multi Media Business Centre Plan for presentation to Council and seek funding Develop Digital Economy Plan and commence implementation (IT&ETTG)
2.8
MDESM
01-Jul-11
30-Jun-12
2.6
MDESM
01-Jan-12
30-Jun-12
2.6
MDESM
01-Jul-11
30-Jun-12
Establish Knowledge Industry Precinct Undertake Telecommunications Audit & Gap Analysis, develop Plan and commence implementation (IT&ETTG) Develop and implement Major Projects Employment & Skills Impact Report
2.3
MDESM
01-Nov-11
30-Jun-12
2.6
MDESM
01-Jul-11
30-Jun-12
2.8
JSDO
01-Jul-11
30-Jun-12
Moving Business Online
2.8
JSDO
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA2 Page 1 of 3
Number of persons participating
Number of business participating in Moving Business Online program
Strategic Function Elements
Net Budget
Actions Develop and implement Skills Attraction & Business Investment Plan
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
2.8
MDESM
01-Jul-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
MDESM Develop Housing Affordability Strategy and passed to Director Community Services for implementation
Social Infrastructure
2.3
MDESM
01-Jul-11
30-Jun-12
2.5
RCSM
01-Jul-11
31-Dec-11
2.5
RCSM
01-Jul-11
30-Jun-12
Launch the Regional Tourism Brand
2.5
01-Jul-11
31-Aug-11
Develop Regional and Local Marketing Collateral Review and Develop Tourism Section on WDRC Website
2.5
RCSM RCSM & CSMs
01-Jul-11
31-Dec-11
2.5
RCSM
01-Jul-11
31-Dec-11
Develop Local Stories (Interests and Experiences to be incorporated into promotions)
2.5
RCSM
01-Jul-11
30-Jun-12
Develop a Tourism Marketing Plan
2.5
RCSM
01-Jul-11
30-Sep-11
Develop Marketing Plan for Jimbour Amphitheatre
2.5
RCSM
01-Jul-11
31-Dec-11
Develop Communications Strategy to support requirements of all VICs in cohesive service-scape
2.5
RCSM
01-Jul-11
31-Dec-11
Review Electronic Touch Screens
2.5
RCSM
01-Jul-11
31-Dec-11
Review Book Easy System
2.5
RCSM
01-Jul-11
31-Dec-11
% Increase in Annual Merchandise sales
Review Merchandise across each VIC
2.5
RCSM
01-Jul-11
31-Dec-11
% increase of merchandise
Incorporate Regional Tourism Branding into VICs Develop a training program for staff and volunteers
2.5
RCSM
01-Jul-11
30-Jun-12
2.5
RCSM
01-Jul-11
30-Jun-12
Establish Service Level Agreements for VICs
2.5
RCSM
01-Jul-11
30-Jun-12
Strategic Function 2C: Tourism - Encourage the development of tourism and promotion of the Region Review economic value of regional events (Economic Value Models) Leverage events for promotion and lifestyle opportunities
Tourism Events
Marketing & Promotion
Visitor Information Centres
Media value of publicity gained through Tourism Promotion
Strategic Function 2D: Saleyards - Manage and operate a regionally competitive and financially sustainable modern saleyards complex in collaboration with key stakeholders. Develop Stage Two Concept Designs for Western Downs Saleyards Develop Marketing Plan and implement strategy for Western Downs Saleyards
Saleyards
2.7
DCS
01-Dec-11
31-Mar-12
2.7
DCS
01-Jul-11
30-Sep-11
Growth and Liveability - Capital Projects Dalby Saleyards - Pavement Replacement. Replace pavement to minimise risks of operational hazards in the pavement area, satisfy WHS requirements and improve aesthetics. 16115.0801.200.0003
$300,000
2.7
DCS
01-Dec-11
29-Feb-12
16110.0802.200.0001
Lot 4 on W64132 subdivision of land (Wandoan) $800,000 East St
2.7
DCS
01-Jul-11
30-Apr-12
Western Downs Regional Council Operational Plan - SA2 Page 2 of 3
% Service Level Agreements Completed
Strategic Function Elements
16110.0802.200.0002 16110.0802.200.0003 16110.0802.200.0007 16110.0802.200.0009 16110.0802.200.0012 16115.0801.200.0006 21110.0802.200.0001
Net Budget
Actions
Lot 5 on RP 125663 Subdivision of land and construction, Butter Factory Jandowae - 15 $400,000 Allotments Mauldauf St Chinchilla Stormwater Drainage work $750,000 $100,000 Purchase of Land at Meandarra from DERM Industrial Land Development - Carmichael Street $3,500,000 Chinchilla - 7 Allotments Purchase Land in Wandoan - from DERM - 13 + $1,500,000 extra allotments $700,000 OH&S Upgrades - Stage 1 $20,000
Miles VIC Upgrade - Purchase & Installation of air conditioning upgrade for VIC and Office
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
2.6
DCS
01-Jul-11
30-Jun-13
2.6
DES
01-Jul-11
30-Jun-12
1.2
DPE
01-Jul-11
31-Dec-11
2.6
DCS
01-Jul-11
30-Jun-12
1.2
DCS
01-Sep-11
30-Nov-11
2.7
DCS
01-Jul-11
31-Dec-11
2.5
DCS
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA2 Page 3 of 3
Key Performance Indicators - KPIs per Strategic Function
Strategic Activity 3: Planning for Liveability Ambition Build an effective planning solution that enhances the liveability and lifestyle of our regional communities whilst promoting sustainable development Accountability Director Planning and Environment
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 3A: Strategic Planning - Review development policy and planning instruments in response to regional planning requirements. Planning Scheme
Public Notification Stage of New Planning Scheme Prepare New Planning Scheme for Council Adoption Finalise Extinguishment of Native Title at Wandoan Finalise Extinguishment of Native Title at Meandarra
3.1, 3.2, 3.5 & 3.6 3.1, 3.2, 3.5 & 3.6 3.6 3.6
PM PM DPE DPE
01-Jul-11
30-Nov-11
01-Jul-11
29-Feb-12
01-Jul-11
30-Sep-11
01-Jul-11
30-Oct-11
01-Jul-11
30-Jun-12
% Development Applications processed within Statutory Timeframes
Number Development Applications processed within Statutory Timeframes
Strategic Function 3B: Planning Services - Effectively resource and manage planning, development assessment and compliance. Planning Assessment
Effectively manage development assessment planning
3.4 & 3.5
PM
Strategic Function 3C: Building Services - Effectively resource and manage building, plumbing and drainage assessment, and inspection services. Building Assessment
Effectively manage development assessment, building and plumbing/drainage Promote Council's Building Certification Service
3.4 & 3.5
BSC
01-Jul-11
30-Jun-12
3.4 & 3.5
BSC
01-Jul-11
30-Jun-12
Planning for Liveability - Capital Projects
Western Downs Regional Council Operational Plan - SA3 Page 1 of 1
% Increase Building Certification Service Client base
Strategic Activity 4: Our Environment Ambition Provide a healthy environment for our people today and the generations of tomorrow Accountability Director Planning and Environment
Strategic Function Elements
Net Budget
Actions
Corporate Responsible Plan Linkage Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 4A: Environmental Health - Improving environmental health for the benefit of our regional communities and environment.
Environmental Health
Finalise the Environmental Health Advancement Plan, to consider Environmental health needs within WDRC Develop Environmental Health Advancement Sub Plans, such as Water Quality Study on nonreticulated supplies and swimming pools, disaster management, public education programs etc
4.3.3
EHC
01-Jul-11
30-Sep-11 % Reduction of Animal Infringements
4.3.3
EHC
01-Jul-11
30-Nov-11 100% of Customer Requests responded to within Risk Based Response Timeframe
Finalise an Environmental Policy for Council
4.3.1
EHC
01-Jul-11
30-Sep-11
Develop Environmental Protection Sub Plans, such as Water Quality Study on urban waterways, Incident Response Plan etc
4.3.1
EHC
01-Jul-11
31-Mar-12 Below Mean Average of Mosquito Borne Disease Notifications 90% of Licensed Food Businesses inspected in financial year
Local Law Enforcement
Finalise an Animal Management Plan, considering service ambitions and standards and developing procedures and work practices Develop Animal Management Sub Plans, such as Promotion and Education in relation to new local laws etc Manage implementation of new Local Laws including staff training and developing fact sheets
4.3.1
EHC
01-Jul-11
30-Sep-11
4.3.1
EHC
01-Jul-11
31-Mar-12
50% of Licensed Flammable and Combustible Liquids Storage facilities inspected in financial year
50% of Registered Environmentally Relevant Activities audited in financial year 4.3.1
EHC
01-Aug-11
31-Dec-11
100% of Licensed Higher Risk Personal Appearance Services inspected in financial year
Strategic Function 4B: Rural Services and Natural Resource Management - Create a natural environment that is valued and sustainable by managing the region's natural character, heritage and values. Pest Management
Finalise Pest Management Plan including community consultation Implement Pest Management Plan including High Risk Pest Public Assistance Scheme Management of new Wash Down Bays including construction and operating procedures. Operate and maintain Wash Down Bays in accordance to operating procedures Operate barrier fences in accordance with NRM Barrier Fence Review, including consideration of changing obligations
4.1.2
RSNRMC
01-Jul-11
30-Sep-11
4.1.2
RSNRMC
01-Oct-11
30-Jun-12
4.1.2
RSNRMC
01-Jul-11
31-Dec-11
4.1.2
RSNRMC
01-Jan-12
30-Jun-12
4.1.2
RSNRMC
01-Jul-11
30-Jun-12
% Increase participation in wild dog baiting programs
All new Parthenium outbreaks on public land treated within 10 days of reporting All new Parthenium outbreaks on public lands reinspected monthly until no regrowth evident for two years
Natural Resource Management
Continue stock take of high priority NRM Assets under Council's control including riverine areas and roadside areas Develop Assessment Criteria for NRM Community Project Assistance
4.1.1
RSNRMC
01-Jul-11
30-Jun-12
4.1.1
RSNRMC
01-Jul-11
31-Dec-11
Western Downs Regional Council Operational Plan - SA4 Page 1 of 4
Strategic Function Elements
Net Budget
Actions Develop and Implement Management Plans for the protection and management of critical NRM Assets
Stock Routes
Continue management of stock routes in accordance with legislative requirements Finalise and implement Stock routes Management Plan
Corporate Responsible Plan Linkage Officer
Timeframe Start
Finish
4.1.1
RSNRMC
01-Jul-11
30-Jun-12
4.1.1
RSNRMC
01-Jul-11
30-Jun-12
4.1.1
RSNRMC
01-Jul-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 4C: Waste Management - Meet the current and growing needs of our region through a coordinated and considered approach to services and environmental infrastructure.
Waste Management Strategy
Undertake review of 2009 Waste Infrastructure Strategy to reflect new Waste and Recycling Act
4.3.2
WMC
01-Jul-11
30-Sep-11
Implement Waste Education Plan
4.3.2
WMC
01-Jul-11
30-Jun-12
Promotion of changes to Waste Management resulting from strategy and legislative changes
4.3.2
WMC
01-Oct-11
30-Jun-12
Increase Tonne/per capita domestic recyclable material from previous financial year
4.3.2
WMC
01-Jan-12
30-Jun-13
Decrease % contamination rate of domestic recycled material from previous financial year.
4.3.2
WMC
01-Jul-11
30-Jun-12
% Increase Green waste recycled in Dalby and Chinchilla
% Increase concrete recycled in Dalby and Chinchilla
Develop and implement development of Waste Reduction and Recycling Strategy as required by legislation
Waste Collection
Contract Management of new collection contract
Waste Landfills
Resolve legacy tenure and licensing issues with current landfills
4.3.2
WMC
01-Jul-11
30-Jun-12
Continuous improvement to on ground operations to meet compliance with DERM conditions including requirements of the new Waste and Recycling Act (Site Based Risk Assessment, Site Based Management Plans and Waste acceptance criteria etc)
4.3.2
WMC
01-Jul-11
30-Jun-12
4.3.2
WMC
01-Jul-11
30-Nov-11
WMC
01-Jul-11
30-Jun-12
WMC
01-Jul-11
30-Jun-12
WMC
01-Jul-11
30-Jun-12
WMC
01-Jul-11
31-Oct-11
WMC
01-Jul-11
31-Dec-11
WMC
01-Jul-11
30-Jun-12
4.3.2
WMC
01-Jul-11
31-Mar-12
4.3.2
WMC
01-Sep-11
30-Apr-12
Complete Waste Levy Readiness Project including security, illegal dumping, supervision, ICT, audit, surveying, stockpile management, cost recovery, levy collection and administration Maximise recovery opportunities to minimise exposure to Waste Levy including green waste, concrete and other recycling initiatives Develop post-closure and after-care management plans for landfills approaching end of life Commence rehabilitation of closed landfills
Transfer Stations
4.3.4
4.3.4 4.3.4
Conclude investigations of East Regional Landfill Preparation and submission of Development Application for East Regional Landfill
4.3.4
Continue investigations of West Regional Landfill
4.3.4
Develop Operating and Logistics Strategies for Waste Transfer Facilities Implement Operating and Logistics Strategies for Waste Transfer Facilities
4.3.4
Western Downs Regional Council Operational Plan - SA4 Page 2 of 4
Strategic Function Elements
Net Budget
Actions
Maximise recovery opportunities to minimise exposure to Waste Levy including green waste, concrete and other recycling initiatives
Corporate Responsible Plan Linkage Officer
Timeframe Start
Finish
WMC
01-Jul-11
30-Jun-12
4.1.2
EHM
01-Jan-12
31-Aug-12
4.3.3
EHM
01-Jul-11
30-Apr-12
4.1.2
EHM
01-Jul-10
30-Sep-11
4.1.2
EHM
01-Sep-11
29-Feb-12
4.3.4
Our Environment - Capital Projects
41110.0802.200.0002
41110.0802.200.0005 42211.0802.200.0007
42211.0802.200.0009
43311.0802.200.0001 43311.0802.200.0004
43311.0802.200.0007 43311.0802.200.0009
41110.0802.200.0003
41110.0802.200.0004 41125.0807.200.0002
42211.0802.200.0004
Relocation of Pound to Jandowae Road Depot & Include Provision for Cats - Dalby Increase on last years carry over due to depot $232,500 location (further down back) Renovation of public toilets - Russell Park Bunya Mts. Current toilets in poor repair, require extensive renovation (including replacement of $17,000 rotten timbers) $66,600 Washdown Bay - Wandoan Washdown Bay - Chinchilla RLCIP application successful. Requires directional boring of water/sewer under Warrego Hwy and Western $900,000 Rail Waste Transfer Facility - Dalby. Carry over project; EIP 80%, Council balance 20% + $3,857,143 contingency $293,000 Waste Transfer Facility - Kaimkillenbun Provision of 'front of house' transfer station for Miles. Current Miles landfill is operationally insufficient; Transfer station was proposed in Waste Strategy Review for the longer term, however, being brought forward due to $240,000 development in area Drummuster Enclosure - Dalby. To be constructed $6,500 at Dalby Transfer station Construction of new pound - Tara. Current pound undersized, in poor condition and unlikely to comply with animal welfare requirements. $76,923 Rejected from 2009/10 budget Construction of new pound - Chinchilla. Current pound is undersized, is in poor condition and is unlikely to comply with animal welfare $100,000 requirements $80,000 Landfill lids in lieu of soil purchase Washdown Bay - Miles. Seeking funding from APLNG (Origin) group. Location/design undecided $600,000 and discussing this with APLNG
4.3.1
EHM
01-May-11
30-Apr-12
4.3.1
EHM
01-Jul-11
29-Feb-12
4.3.1
EHM
01-Jul-11
30-Sep-12
4.3.4
EHM
01-Aug-11
30-Apr-12
4.3.1
EHM
01-Sep-11
30-Sep-12
4.3.1
EHM
01-Jul-11
30-Jun-12
4.3.4
EHM
01-Jul-11
30-Sep-11
4.1.2
EHM
01-Sep-11
30-Jun-12
4.3.4
EHM
01-Jul-11
31-Dec-12
Fencing Project for high priority landfills. some higher profile landfills being targeted by illegal dumping, project is to fence or complete fencing for those sites. Including Miles, Tara, Wandoan, Jandowae, Condamine. May be required with the introduction of state govt waste levy from 2011/12 43311.0802.200.0002
$203,333
Western Downs Regional Council Operational Plan - SA4 Page 3 of 4
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
Net Budget
Actions
Corporate Responsible Plan Linkage Officer
Timeframe Start
Finish
Post closure care for recently closed landfills (Jimbour, Brigalow) and those potentially closing (Macalister, 21 Mile). DERM licensing requirement 43311.0802.200.0008
43311.0802.200.0013
43311.0802.200.0014 43311.0802.200.0015
43311.0802.200.0016
$80,000 Development of East Landfill (development approval, commencement of detailed design, early works). Initial site investigations commenced Feb $250,000 2011 Waste Transfer Station - Chinchilla. Front of house facility, with weighbridge for DERM waste levy audit (weighbridge required under S 37 of Waste $833,333 Reduction and Recycling Act) $100,000 Improved on site facilities - Tara Landfill Provision of 'front of house' transfer station for Miles. Current Miles landfill is operationally insufficient; transfer station was proposed in Waste Strategy Review for the longer term however being brought forward due to $240,000 development in area
4.3.3
EHM
01-Jul-11
31-Jan-12
4.3.1
EHM
01-Jul-11
30-Jun-13
4.3.1
EHM
01-Jan-12
30-Jun-13
4.3.4
EHM
01-Oct-11
30-Jun-12
4.3.1
DPE
01-Jul-11
30-Sep-12
Western Downs Regional Council Operational Plan - SA4 Page 4 of 4
Key Performance Indicators - KPIs per Strategic Function
Strategic Activity 5: Utility Services Ambition Manage our water, sewerage and gas networks to achieve reliability, safety and cost effectiveness for our customers Accountability Director Engineering Services
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 5A: Water - Manage water treatment, networks, revenue and assets to achieve safe, reliable and cost effective water supplies. Bores
Maintain and operate Water Bore Assets as required
5.1
UTM
01-Jul-11
30-Jun-12 % Take-up of WaterWise Rebate scheme
Weir
Maintain and operate Surface Water Assets as required
5.1
UTM
01-Jul-11
30-Jun-12
Less than 10:1 Ratio of planned vs unplanned interruptions Response time < one hour for 95% of incidents for towns
Treatment
Investigate technical requirements for upgrade to existing water and sewerage infrastructure due to resource development in the region
SA5
Maintain and operate Water Treatment Assets to achieve required water quality standards
Response time < two hour for 95% of incidents for villages and hamlets UTM
01-Jul-11
30-Jun-12
5.1
UTM
01-Jul-11
30-Jun-12
Restoration services > 90% restored within four hours for towns
Operate fluoridation in Miles Complete planning for new water treatment plant at Tara
5.1
UTM
01-Jul-11
30-Jun-12
Restoration services > 90% restored within five hours for villages
5.1
UTM
01-Jul-11
01-Jan-12
Implement fluoridation in Chinchilla Work with the energy sector to implement infrastructure upgrades
5.1
UTM
01-Jul-11
31-Dec-11
5.1
GMU
01-Jul-11
30-Jun-12
Restoration services > 90% restored within twelve hours for hamlets Less than 5 reportable events under the Water Supply (Safety and Reliability) Act Less than 10 water quality complaints per 1,000 connections per year for towns Less than 20 water quality complaints per 1,000 connections per year for villages
Storage
Continue with reservoir inspection and cleaning program
5.1
UTM
01-Jul-11
30-Jun-12
Distribution
Maintain and operate Distribution Assets as required
5.1
UNM
01-Jul-11
30-Jun-12
Promote Western Downs Waterwise Program Continue working with sports and community groups on their Water Conservation Plans
5.4
GMU
01-Jul-11
30-Jun-12
5.4
GMU
01-Jul-11
30-Jun-12
Continue roll out of automatic read meters
5.1
UNM
01-Jul-11
30-Jun-12
Achieve full cost recovery plus appropriate margin on projects tendered and constructed within resource constraints
5.1
UNM
01-Jul-11
30-Jun-12
5.1
UTM
01-Jul-11
30-Jun-12
5.1
UTM
01-Jul-11
30-Jun-12
Conservation
Commercial Works
Raw Water
Operate existing untreated water supplies to appropriate customer service standards for villages and hamlets Operate existing Raw Water Supplies to community and sporting groups
Western Downs Regional Council Operational Plan - SA5 Page 1 of 7
Strategic Function Elements
Water Revenue
Net Budget
Actions Provide of technical advice and support to Council's Revenue Team and customers
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
5.1
GMU
01-Jul-11
31-Mar-12
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 5B: Recycled Water - Manage recycled water treatment, networks, revenue and assets to achieve safe, reliable and cost effective water supplies.
Treatment
Maintain and operate Treatment Assets as required under Recycled Water Supply Agreements
Storage
N/A
Distribution
Complete Recycled Water Management Plans for community users
5.3
GMU
01-Jul-11
30-Jun-12
Maintain and operate Distribution Assets as required under Recycled Water Supply Agreements
5.3
UNM
01-Jul-11
30-Jun-12
5.1
GMU
01-Jul-11
31-Mar-12
5.3
UTM
01-Jul-11
30-Jun-12 Comply with requirements of Recycled Water Agreements.
Commercial Works
N/A
Recycled Water Revenue
Provide of technical advice and support to Council's Revenue Team and customers
Strategic Function 5B: Wastewater - Manage wastewater treatment, collection and pumping, revenue and assets to achieve reliable and environmentally sensitive wastewater systems Treatment
Maintain and operate Wastewater Treatment Assets as required Continue planning for a new wastewater plant in Miles and Wandoan Work with the energy sector to implement infrastructure upgrades
5.5
UTM
01-Jul-11
30-Jun-12
5.5
UTM
01-Jul-11
30-Jun-12
5.5
GMU
01-Jul-11
30-Jun-12
Response time < one hour for 95% of incidents Restoration services > 90% restored within four hours % samples meet or exceed licensing requirements
Pumping Station
Maintain and operate Wastewater Pumping Assets as required
5.5
UNM
01-Jul-11
30-Jun-12
Mains
Undertake CCTV inspections in Miles, Chinchilla and Tara as per network program
5.5
UNM
01-Jul-11
31-May-12
Operate and maintain sewer network assets in accordance with customer service standards
5.5
UNM
01-Jul-11
30-Jun-12
Commercial Works
Achieve full cost recovery plus appropriate margin on projects tendered and constructed within resource constraints
5.5
UNM
01-Jul-11
30-Jun-12
Wastewater Revenue
Assist with the implementation of wastewater charging regime with the provision of technical advice and support
5.5
GMU
01-Jul-11
31-Mar-12
01-Jul-11
30-Jun-12
Strategic Function 5C: Gas - Manage Dalby gas network, revenue and assets to achieve a safe, cost effective gas distribution system. Gate Station
Operate and maintain Gate Station Assets as required
5.7
UNM
Work completed with 10% or greater margin achieved Measure cubic metres of gas loss Regulation Station
Operate and maintain Regulation Station Assets as required
5.7
UNM
01-Jul-11
Western Downs Regional Council Operational Plan - SA5 Page 2 of 7
30-Jun-12
Response time < one hour for 95% of incidents
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function % Turnover as Dividend to Council % Return on Investment
Operate and maintain Gas Distribution Assets as required Ongoing development and review of gas operating procedures
Mains
5.7
UNM
01-Jul-11
30-Jun-12
5.7
GMU
01-Jul-11
30-Jun-12
Retail
Promote the efficiencies and benefits of natural gas
5.7
GMU
01-Jul-11
30-Jun-12
Commercial Works
Achieve full cost recovery plus appropriate margin on projects tendered and constructed within resource constraints
5.7
UNM
01-Jul-11
30-Jun-12
Gas Revenue
Provide of technical advice and support to Council's Revenue Team and customers
5.7
GMU
01-Jul-11
31-Mar-12
5.1
UTM
01-Jan-11
30-Sep-11
5.1
UTM
01-Jul-10
31-Jul-11
5.4
UTM
01-Jul-10
30-Sep-11
5.1
UTM
01-Jul-11
31-Mar-12
5.1
UTM
01-Jul-11
31-Mar-12
5.1
UTM
01-Jul-10
31-Jul-11
Utility Services - Capital Projects
14135.0802.200.0001
14135.0802.200.0002
Filtration upgrade for Miles water supply. This project was not originally budgeted for in 2009/10. Council obtained RLCIP funding of $380,000 for the project which meant the timing of the project was brought forward. A small amount of expenditure is expected in 2009/10 with most in $126,667 2010/11 Construction of a 2ML RO plant for the Dalby water supply. $6.6 million total budget for evap ponds RO plant and Bores. About 4 million already spent. Project is behind schedule so we can expect about $2.37 million as carry over works $242,308 Fluoridation Water Supply - Miles This project was mandated by QLD Government legislation. The project has been carried over because of delays in Government approval. This project is subject to 100% funding by government.
14135.0802.200.0004
$18,808 Bell water plant upgrades. Chemical storages do not comply with safety requirements. It is intended to upgrade chlorine storage , and commence conversion to liquid chemicals. This will require the replacement of chemical pumps and tanks in some cases. Tanks would be bunged.
14135.0802.200.0006
$20,000 Warra water plant- Chemical dosing upgradeCurrent chemical tanks do not comply with safety legislation. Conversion to all liquid chemicals would be commenced and some dose pumps would be replaced. Tanks would be bunged.
14135.0802.200.0007
14135.0802.200.0010
$20,000 Miles water plant- Replace roof. Existing roof is asbestos and is in poor condition. This represents an WH&S risk but also has water quality implications for the plant as it is not currently bird $2,692 proof.
Western Downs Regional Council Operational Plan - SA5 Page 3 of 7
Strategic Function Elements
Net Budget
Actions
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
5.1
UTM
01-Jul-11
31-Dec-11
5.1
GMU
01-Jun-11
31-Dec-11
5.1
UTM
01-Jul-10
31-Jul-11
UTM
01-Jul-10
30-Sep-11
Tim Low
01-Jul-10
31-Jul-11
Dalby Water Treatment Plant- Alum sludge processing facility - DERM directive is that current arrangements are no longer acceptable 14135.0802.200.0011
14135.0802.200.0012
14140.0802.200.0002
14140.0802.200.0003 14141.0802.200.0002
14141.0802.200.0004 14150.0802.200.0007
$150,000 Miles-Construct storage shed at Miles water treatment plant. Existing shed to be used by PandG and fenced off. New shed to be built $55,385 beside treatment plant. 9 x 8 x 3 m . Miles water supply reservoir- Reservoir inspections showed that the old Miles reservoir was unsound in the roof. Roof is sheeted with asbestos which is in poor condition. Reservoir is unable to be entered and is not currently in use. Roof must be replaced. $5,385 Warra Off Stream Storage - Dam 50ML. Completion of the pump station component of this $17,692 project. $2,308 Fall Arrest System - Miles Water Tower Ladder Replacement or pressure/diesel Pump System Operation - Moonie revise pumps set and install diesel back up ladder can then be removed and system work with tower off line. $20,000 $13,143 Jandowae - Installation of remote read meters
5.1
5.1
UTM
01-Jul-11
31-Mar-12
5.1
UNM
01-Jan-11
31-Jul-11
5.1
UNM
01-Apr-11
30-Jun-12
5.1
UNM
01-Jul-11
31-Mar-12
5.1
UNM
01-Jul-11
31-Dec-11
5.1
UTM
01-Jul-10
30-Sep-11
5.1
UNM
01-Nov-10
31-Oct-11
5.1
UNM
01-Jul-10
31-Oct-11
5.1
UNM
01-Oct-10
30-Nov-11
5.1
UTM
01-Aug-10
31-Jul-11
Chinchilla - Installation of new remote read meters 14150.0802.200.0008
$418,560 Jandowae - Water mains replacements Jandowae areas to be assessed - a lot of old AC mains with break history and valves which are not working.
14152.0802.200.0001
14152.0802.200.0003 14152.0802.200.0006
14152.0802.200.0008 14152.0802.200.0009 14152.0802.200.0011 14153.0803.200.0004
14223.0802.200.0001 14223.0802.200.0002
$25,000 Tara - Replacement Main - Surat Development Road Materials have been purchased. work not $30,000 completed as terrain is very wet Miles - New Treatment Water Pumps & Standby $3,846 Generators - Water Treatment Plant Chinchilla water mains replacements To include 360 metres of mains along Wondai $14,444 Road Dalby water mains replacements - Coutts Moreton $17,143 Hawthorne Sts area Warra water - rising main replacement 2,000 $60,000 meters section $8,333 Replace Edward Street Water Pump Station Upgrade Pump Station 4 Black Street Dalby Design and reconstruction including new rising $1,000,000 mains as per Network Analysis $85,714 Upgrade Meandarra Pumping Station
5.1
UTM
01-Jul-11
30-Jun-13
5.6
UTM
01-May-11
31-Mar-12
Dalby, Tara Wandoan and Chinchilla - sewer manhole relining - required in various locations to reseal and prevent infiltration into the manholes 14232.0803.200.0010 14320.0803.200.0005
14322.0802.200.0001
$79,725 $12,000 Gas main extensions - Winton St East Regulator upgrade - separate district regulator from White Industries regulator to remove district $40,000 reg from private property
5.6
UNM
01-May-11
31-Dec-11
5.7
UNM
01-Jul-11
31-Dec-11
5.7
GMU
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA5 Page 4 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
53319.0802.200.0001 14121.0803.200.0002
14135.0802.200.0005
14135.0802.200.0008
Net Budget
Actions
Construction of new gas gate station - required for compliance of gas inspectorate audit - previous $119,808 project budgeted at $400,000 Condamine - Install Telemetry system for supply of $10,000 creek water - Refer to Cr. Smith Tara water plant augmentation- Investigate design and construct an RO plant for the Tara water supply. Estimated $750,000 expenditure over three years. Planning commence 10/11 with $552,000 construction 11/12 - 12/13
$20,000
Jandowae water plant- Upgrade chemical dosing facilities. Current chemical storage does not comply with OFandS legislation. Work towards the use of all liquid chemicals . Will require the replacement of tanks , provision of bunging and possibly dose pump changes.
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
5.7
GMU
01-Jul-10
30-Sep-11
5.1
UTM
01-Jul-11
30-Dec-11
5.1
UTM
01-Jun-11
31-Dec-12
5.1
UTM
01-Jul-11
31-Mar-12
5.4
UTM
01-Jul-11
31-Dec-11
5.1
UTM
01-Jul-11
30-Jun-13
5.1
UTM
01-Apr-12
30-Jun-13
Chinchilla water plant fluoridation -Fluoridation will be required by law by the end of 2012. Plan to include chlorine and activated carbon in upgrade. Project will be subject to stringent design approval processes by the government. Fluoride component will be fully funded by subsidy 14135.0802.200.0009
14135.0802.200.0016
14135.0802.200.0018
$350,000
$500,000
Dalby - Planning and construction of RO plant concentration stage - 2010/11 high rainfall and flooding used up 2 - 3 years of evap pond storage. Secondary RO stage needs to be brought forward to reduce waste stream and manage future risk of high rainfall events.
Wandoan - Construct new water treatment plant to meet proposed development needs - funded by $600,000 Xstrata initially Dalby Water Treatment Plant - Purchase neighbouring land - approx 4.5 Ha for buffer zone and construction of flood protection works
14135.0802.200.0019
$250,000
5.2
GMU
01-Jul-11
30-Jun-12
14140.0802.200.0001
Dalby water supply reservoir repairs- Work was done on the posts but leak is still huge - approx 300kl per day. Polyurea costing of both 9 and 4 Ml reservoirs is required, and new roofing to 4 Ml $501,429 reservoir Water reticulation extensions - unplanned projects to new developments which will be substantially funded by developer contributions through infrastructure agreements
5.1
UTM
01-May-11
31-Oct-11
14151.0802.200.0001
$200,000
5.1
UNM
01-Jul-11
31-Dec-12
5.1
UNM
01-Jul-11
31-Dec-11
5.1
UNM
01-Jul-11
30-Jun-12
14151.0802.200.0002
14151.0802.200.0006
$144,000
Miles water - reticulation extensions to new developments. Includes 400 metres of 200mm diameter along racecourse rd. Project timing dependent on receipt of contributions from developer infrastructure agreements
Miles - 100mm diameter main extension for 220 metres in Daisy St ( Wallen to Dawson) for loop $40,000 main interconnection
Western Downs Regional Council Operational Plan - SA5 Page 5 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
14151.0802.200.0007
Net Budget
Actions
Miles - 2 x 200mm diameter trunk mains replacements out of treatment plant for 25 metres each. These 2 mains cross private land and $180,000 buildings are on top of them Miles - Upgrade of 80mm diameter main to 150mm diameter in Industrial lane for 350 metres. Will improve flow and pressure to industrial area.
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
5.1
UNM
01-Jul-11
30-Jun-12
14151.0802.200.0008
$70,000
5.1
UNM
01-Jul-11
30-Jun-12
14151.0802.200.0009
Miles - 100mm diameter main extension from dead end in Lawton St to Race course Rd - 30 metres will improve flow and reduce dirty water complaints $20,000 from dead end. Wandoan - mains replacement/upgrade in Jerrard and Clark St area to improve hydrant pressures $33,000 210 metres of 150mm mains.
5.1
UNM
01-Jul-11
30-Jun-12
5.1
UNM
01-Jul-11
30-Jun-12
5.1
UNM
01-Dec-11
30-Jun-12
5.1
UNM
01-Jul-11
30-Jun-12
5.1
UNM
01-Jul-11
30-Nov-11
5.1
UNM
01-Jul-11
30-Jun-12
5.1
UNM
01-Jul-11
30-Nov-11
5.6
UTM
01-Jul-11
31-Mar-12
5.6
UTM
01-Jul-11
30-Jun-14
5.6
UTM
01-Jul-11
30-Jun-12
14151.0802.200.0010
Dalby - 150mm water main to service Healy St Developments - WDRC Depot and Arrow Energy 14151.0802.200.0011
14151.0802.200.0012
14152.0802.200.0018
14152.0802.200.0019
14152.0802.200.0020
14223.0802.200.0003
14223.0802.200.0004
14223.0802.200.0008
$90,000 Flinton - Reticulation alterations. Existing reticulation has been installed by locals in some areas, and in cases is straight line through private property and on top of the ground. There are meters in series to two properties. Requires approx 300 metres of 63 OD poly and some new $35,000 services. Warra - 150mm rising main replacement for 100 metres including under road bores of Warrego Hwy to provide secondary feed to tower. Old line $44,000 AC with bad break history. Dalby Water main replacement programme continue work in Coutt, Moreton Hawthorne Street $200,000 areas approx 1,500 metres Warra - 50m of 150mm main replacement including under bore of Warra Kogan Rd - existing $22,000 main with break history Jandowae sewer pumpstation upgrades- Existing pump parts are no longer available. Is expected to replace pumps and some pipework only. $50,000 Miles-Construct new sewerage treatment plantPlanning stage 11-12 and construction from 12-13$84,000 14 Chinchilla - reconstruct Pump Station B - Zeller Stto cater for development - funding from developer $500,000 infrastructure agreements Chinchilla - Reconstruct sewerage pumps station F - Gaske Lane - to cater fro development growth funded by developer infrastructure agreements
14223.0802.200.0009
$500,000
5.6
UTM
01-Jul-11
30-Jun-12
14223.0802.200.0010
Chinchilla - Reconstruct sewage pump station D to cater for development and remove existing bottleneck - partly funded by developer $100,000 infrastructure agreements Miles - Sewage Treatment Plant - Construct additional evaporation ponds - current capacity is not sufficient and overflow from site has occurred
5.6
UTM
01-Jul-11
30-Jun-12
14223.0802.200.0011
$100,000
5.6
UTM
01-Jul-11
30-Nov-11
Western Downs Regional Council Operational Plan - SA5 Page 6 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
Net Budget
Actions
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
5.6
UTM
01-Jul-11
30-Jun-13
Mile - Construct new sewage pump station in Hookswood Rd area to cater for developments funding from developer infrastructure agreements planning in 11-12 and construction in future years 14223.0802.200.0012 14223.0802.200.0013 14223.0802.200.0014
14223.0802.200.0015
$61,538 Wandoan - Construct new wastewater plant to $555,556 cater for growth - Xstrata funded $100,000 Wandoan - new sewage pump station no 4 Sewerage Pumps Stations - Design and tender documentation for upgrade and construction of new pump stations - needed to have projects ready to go to meet developer timelines $60,000
5.6
UTM
01-Jul-11
30-Jun-13
5.6
UTM
01-Jul-11
31-Mar-12
5.6
UTM
01-Jul-11
31-Dec-11
5.6
UTM
01-Jul-11
31-Mar-12
5.6
UNM
01-Jun-11
30-Jun-12
5.6
UNM
01-Jul-11
30-Jun-12
5.6
UNM
01-Jul-11
30-Jun-12
5.6
UNM
01-Jan-12
30-Jun-13
5.6
UNM
01-Jul-11
30-Jun-12
5.6
UNM
01-Dec-11
30-Jun-12
5.7
UNM
01-Jul-10
30-Sep-11
5.7
UNM
01-Jul-11
30-Jun-12
5.7
UNM
01-May-11
30-Aug-11
5.7
GMU
01-Jun-11
30-Jun-12
Dalby - Healy St sewage pump station to service developments - WDRC Depot and Arrow Energy 14223.0802.200.0016
$350,000 Dalby sewer main extension - to service new developments and mainly funded through developer infrastructure agreement contributions
14230.0803.200.0003
$46,154 Wandoan sewer extensions to service new developments - largely funded through developer infrastructure agreement contributions
14230.0803.200.0004
$50,000 Chinchilla - Construct new rising mains from SPS nos B and F to WWTP - to cater for developments funded by developer infrastructure agreements
14230.0803.200.0009
14230.0803.200.0010 14230.0803.200.0011
14230.0803.200.0012
14320.0803.200.0001 14320.0803.200.0003 14320.0803.200.0004 14322.0802.200.0002
$525,000 Miles - new rising main Stage 1 from new PS 3 in Hookswood Rd area to Treatment Plant - Design $38,462 only in 11-12 Sewerage regional - Manhole relining - ongoing $50,000 programme Dalby - New sewer rising main to Healy St Development pump station - WDRC Depot and Arrow Energy. Part Council funded for future $55,000 provisions Extensions to gas reticulation network to serve new customers and connect dead end areas $2,308 Extensions to gas network to new customers and $20,000 to link dead end mains Reroute high pressure gas main around CRT $45,000 development site Regulator upgrades - continuation of existing $46,154 programme.
Western Downs Regional Council Operational Plan - SA5 Page 7 of 7
Key Performance Indicators - KPIs per Strategic Function
Strategic Activity 6: Infrastructure Ambition Build and maintain civil infrastructure to create safe and liveable communities within our region Accountability Director Engineering Services
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 6A: Works - Plan, design, construct and maintain regional civil infrastructure to service the needs of the Dalby district. Footpaths
Maintain footpath network to agreed levels of service Liaise with Council to develop Community Levels of Service for Council's footpath network Implement Adopted Community Levels of Service for the Council's footpath network Implement a scheduled footpath inspection program Develop 10 Year Program for Footpath Extension and Replacement for each district
Roads
Bridges
Stormwater Drainage
Rural Drainage
Street lighting
6.2
GMW
01-Jul-11
30-Jun-12
6.2
GMW
01-Jul-11
30-Sep-11
6.2
GMW
01-Oct-11
30-Jun-12
6.2
WM
01-Jul-11
30-Jun-12
Achieve <10% margin M&R expenditure vs budget allocation per quarter
6.3
WM
01-Jul-11
30-Nov-11
% footpath network inspected and reports completed
6.2
GMW
01-Jul-11
30-Jun-12
Maintain road network to agreed levels of service Liaise with Council to develop Community Levels of Service for Council's road network Implement Adopted Community Levels of Service for the Council's road network
6.2
GMW
01-Jul-11
30-Sep-11
6.2
GMW
01-Oct-11
30-Jun-12
Implement a scheduled road inspection program
6.2
WM
01-Jul-11
30-Jun-12
Maintain bridge structures to agreed levels of service
6.2
WM
01-Jul-11
30-Jun-12
Implement a scheduled bridge inspection program
6.2
WM
01-Jul-11
30-Jun-12
6.2
WM
01-Jul-11
30-Jun-12
6.2
GMW
01-Jul-11
30-Jun-12
6.2
GMW
01-Jul-11
30-Jun-12
Maintain stormwater infrastructure to agreed service standards Develop stormwater network analysis for selected catchments in Dalby town area Implement Stormwater Master plan for selected catchments in Chinchilla
Liaise with DERM to determine if existing Wambo Shire River Trust remains statutory body or will become part of Council's normal function Determine if River Trust should take in wider area beyond former Wambo Shire
6.2
DES
01-Jul-11
31-Dec-11
6.2
DES
01-Jul-11
31-Dec-11
Maintain Street lighting infrastructure to acceptable Council standards
6.2
WM
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA6 Page 1 of 10
% of planned road infrastructure inspections completed Response time <14 days for 90% of customer requests
Strategic Function Elements
Public Offstreet Car parks
Net Budget
Actions Maintain off-street car park infrastructure to acceptable Council standards
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.2
WM
01-Jul-11
30-Jun-12
6.5
WM
01-Jul-11
30-Jun-12
6.5
DES
01-Jul-11
30-Jun-12
6.5
DES
01-Jul-11
30-Sep-11
6.5
DES
01-Jul-11
30-Jun-12
Strategic Function 6B: Aerodromes - Maintain and enhance aerodromes relevant to CASA and community requirements Aerodrome
Maintain Aerodrome infrastructure to agreed service standards Continue working with external stakeholders to source funding for the staged implementation of the Chinchilla Aerodrome master plan. Gain development approval for future development of the Chinchilla Aerodrome Liaise with resource companies in relation to the future of Miles and Wandoan Aerodromes
Strategic Function 6C: Asset Management - Develop a whole of organisation approach to implement best practice asset management
Asset Management
Develop Asset Management Plans for all asset classes including setting service levels Implement an Asset Management Policy and Asset Management Strategy Implement a strategy to resource the Asset Management function of Council
6.1
AM
01-Jul-11
31-Aug-11
6.1
CEO
01-Jul-11
30-Jun-12
6.1
CEO
01-Jul-11
30-Jun-12
Strategic Function 6D: Cemetery Operations - Maintain cemetery operations to a level acceptable to the community Cemetery
Develop Service Level Agreement with Community Services Implement Cemeteries Online Maintain and operate Cemeteries to agreed service standards
6.9
GMW
01-Jul-11
30-Jun-12
6.9
GMW
01-Jul-11
31-Dec-11
6.9
WM
01-Jul-11
30-Jun-12
Strategic Function 6E: Parks & Gardens - Maintain regional Parks and Gardens assets to service the needs of the Western Downs Communities Parks & Gardens
Maintain parks, gardens and open space assets to agreed levels of service Develop Levels of Service for Council's parks, gardens and open space assets Implement a scheduled parks and gardens assets inspection program
6.9
WM
01-Jul-11
30-Jun-12
6.9
GMW
01-Jul-11
30-Jun-12
6.9
WM
01-Jul-11
30-Jun-12
Strategic Function 6F: Council Depots - Provide and maintain functional depot facilities to support Council operations in each district Council Depots
Maintain and operate depots to meet Council's operational requirements Integration of Dalby district depot services to one facility
6.2
WM
01-Jul-11
30-Jun-12
6.2
DES
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA6 Page 2 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Timeframe
Responsible Officer
Start
Finish
DES
01-Jul-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 6G: Commercial Works - Actively pursue commercial works opportunities within our region
Commercial Works
Achieve full cost recovery plus appropriate margin on projects tendered and constructed within resource constraints
6.7
% margin achieved major works completed Main Roads - RMPC
Main Roads - BMI
Main Roads - Construction
Main Roads - Flood Damage
Carry out operations in accordance with Main Roads Contract Maintain quality assurance systems as per certification requirements Carry out operations in accordance with Main Roads Contract Maintain quality assurance systems as per certification requirements
6.7
WM
01-Jul-11
30-Jun-12
6.7
WM
01-Jul-11
30-Jun-12
6.7
WM
01-Jul-11
30-Jun-12
6.7
WM
01-Jul-11
30-Jun-12
6.7
WM
01-Jul-11
30-Jun-12
Achieve full cost recovery plus appropriate margin on projects tendered and constructed within resource constraints Carry out operations in accordance with Main Roads Contract Maintain quality assurance systems as per certification requirements
6.7
WM
01-Jul-11
30-Jun-12
6.7
WM
01-Jul-11
30-Jun-12
Carry out operations in accordance with Main Roads Contract
6.7
WM
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
Strategic Function 6H: Fleet - To manage an efficient fleet and plant to support Council operations Fleet
Maintain and utilise Council's fleet and plant assets to achieve efficient operation
6.6
FC
Accountable Tools (Floating Plant)
Operate within allocated budget for accountable tools
6.6
WM
Plant Utilisation Rate 01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
Strategic Function 6I: Workshop - Provide and maintain functional depot facilities to support Council operations in each district Workshop
Maintain and operate workshops to meet Council's operational requirements
6.2
FC
Strategic Function 6J: Quarry - To provide quality quarry products at competitive prices
Jimbour Quarry
Maintain and operate Jimbour Quarry to meet Council's operational and external client's needs
6.8
GMW % margin achieved on product sales
Integrate the mobile crushing operations to ensure compliance with Mines Department regulations
6.8
Mobile Crusher
Maintain and operate Council's Gravel Pits to meet Council's operational and external client's needs
6.8
Gravel Pits
GMW 01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
WM
Western Downs Regional Council Operational Plan - SA6 Page 3 of 10
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
Strategic Function 6K: Declared Disaster Recovery - Restore Council assets as per NDRRA Guidelines Flooding
Submit NDDRA flood management claims as required
Storm Damage
Respond to emergencies within acceptable timeframe
6.2
6.2
DES
DES
Infrastructure - Capital Projects 12422.0804.200.0009 12422.0804.200.0012 12422.0804.200.0022 12422.0804.200.0027 12422.0804.200.0028 12422.0804.200.0029 12422.0804.200.0046
12422.0804.200.0047 12422.0804.200.0049
12430.0807.200.0171
12430.0807.200.0172 13110.0802.200.0003 13110.0802.200.0007 13110.0802.200.0025 13110.0802.200.0026 13110.0802.200.0027
$9,500 Ramp - Move to Wambo Depot - Dalby $1,180,000 Construct New Workshop - Dalby Renovate Existing Building - Amalgamation Stores $45,000 Depot - Dalby Construct Hardstand - Upgrade Depot Plan - Dalby $557,955 $400,000 Utilities Building - Depot Upgrade - Dalby Design of New Industrial Subdivision - Reconfigure $1,000,000 Lot 11 on D9140 Healy - Dalby Disposal of Works Depot - Irvingdale Road - Dalby $2,500 - Valuation Expenses Only Carry over funds to finis smoko/crib room within existing shed Chinchilla $20,000 Ran out of time (floods, other priority work etc) Fitting out of offices and walkway, bitumen $12,000 spraying to car park 2349 Ute (carry over) new vehicle ordered however due to the Japan crisis vehicle will not be $37,023 delivered until late July early August 2216 Carry over New ute ordered, Due to the Japan crisis ute will not be delivered until late July $33,386 early august Inverai Road Rehabilitation 11.80 to 13.80 (RRG $320,000 TIDS) $100,000 Dalby Main Street Traffic Management Upgrade Culverts - Owen Street under Blaxland $37,000 Street & Hayden - Dalby $40,000 Bidstrups Road - Carry Over Second Seal $35,000 Springvale Road - Carry Over Reseal
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.2
WMD
01-Jul-11
30-Jun-12
6.2 6.2 6.2 6.2
DES DES DES DFICT
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
01-Jul-11
30-Nov-11
01-Jul-11
31-Dec-11
01-Jul-11
30-Jun-12
01-Jul-11
31-Oct-11
01-Jul-11
30-Sep-11
DES 6.2 6.2
WMD DES
6.6 DES 6.6 6.2
WMD
18-Jul-11
31-Dec-11
6.2
WMD
01-Aug-11
31-Dec-11
6.2
WMD
01-Sep-11
31-Dec-11
6.2
WMD
01-Oct-11
31-Dec-11
6.2
WMD
01-Oct-11
31-Dec-11
6.2
WMD
01-Oct-11
31-Dec-11
6.2
WMD
01-Jul-11
30-Jun-12
6.2
WMD
01-Jul-11
31-Mar-12
Branch Creek Rd - Carry Over Road Construction 13110.0802.200.0028 13110.0802.200.0029 13111.0802.200.0002
$45,000 $9,100,000 Kumbarrilla Lane Bitumen & Construction Reseal Program 2011/12 includes prior year $780,000 programme carryover Zellar Street intersection. Upgrade intersection with Gakse Ln to improve safety with new subdivisions. work on Intersection of Gaske Lane, Zellar St, and Chinchilla Tara Road.
13112.0802.200.0004
$650,000
6.2
WMCT
01-Jul-11
03-Jan-00
13112.0802.200.0009
6.2
WMCT
01-Dec-11
31-Dec-11
6.2
WMCT
01-Jun-11
30-Jun-12
13112.0802.200.0025
$70,000 Ko Ko Road. New road for access to a block V Bells Road - Bridge Replacement - Chinchilla $203,077 $416,000 Beelbee Road - Carry Forward
6.2
WMCT
01-Jan-11
30-Apr-12
13114.0802.200.0017
Racecourse road - Turnout Construction (Pre $180,000 development)
6.2
WMM
01-Oct-11
31-Dec-12
13112.0802.200.0011
Western Downs Regional Council Operational Plan - SA6 Page 4 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
13114.0802.200.0018 13116.0802.200.0001 13120.0802.200.0005 13120.0802.200.0012 13124.0802.200.0006
Net Budget
Actions
Dulacca South Road 95.0 to 10.0) - Asset upgrade $90,000 - Widen and seal Bell Tourist Route - Markham Hill Road - Fill in $124,000 Section Grosmont Road (22.59) - Bridge Deck $11,538 Replacement - Asset Replacement Nathan Road (0.0 to 4.0) - Asset upgrade - widen $75,000 and overlay & Seal $400,000 Chinchilla Reseal Program Carry forward
13128.0802.200.0002
$10,000
13128.0802.200.0003
$25,000
13147.0802.200.0008
$90,000
13160.0803.200.0001
$1,400,000
Reseal Entrance & Internal Roads - Aerodrome Dalby Resurface Aircraft Parking Apron - Aerodrome Dalby Murilla Street Streetscape Stage 2 Pine Street to Tully Street Patrick Street Bridge Replacement
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.2
WMM
01-Jul-11
30-Sep-11
6.2
WMD
01-Oct-11
29-Feb-12
6.2
WMM
01-Jul-10
30-Sep-11
6.2
WMM
01-Jul-11
30-Sep-12
6.2
WMCT
01-Jul-11
30-Jun-12
6.2
WMD
01-Oct-11
31-Mar-12
6.2
WMD
01-Oct-11
31-Mar-12
6.2
WMM
01-Jul-11
30-Jun-12
6.2
WMD
01-Jul-11
30-Jun-12
6.2
WMCT
01-Jul-11
30-Jun-12
6.6
FWC
01-Jul-11
30-Nov-11
6.6
FWC
01-Jul-11
31-Dec-11
6.6
FWC
01-Jul-11
31-Dec-11
Truck Stormwater - Gaske Lane to Charleys Creek 13311.0803.200.0002
$1,304,725 Depot Pressure Cleaner Electrics on old unit failing. Uneconomical to repair
12422.0804.200.0038
12422.0804.200.0039
12422.0804.200.0040
$7,500
$20,000
$50,000
Fitment of electric motors to 4 workshop roller doors Request through safety committee/advisors and workshop staff Heavy roller doors even with the chain drive & correct adjustment Repair concrete floor in workshop Original floor has a thin concrete overlay over the top of the structural concrete. This overlay is breaking away leaving large and dangerous holes in the floor causing accidents. Quote to repair $49,400 Planning & Design to upgrade Tara Depot wash down bay Wash down bay overflows when washing any item of plant/equipment. Solid material traps all water. No suitable pit/trap for solid material. Water cannot fall away from wash which then overflows into yard
12422.0804.200.0041
$10,000
6.6
FWC
01-Jul-11
30-Jun-12
12422.0804.200.0042
$45,000 Soil Lab Relocation - Dalby $42,000 Materials area - Dalby - Gravel pad & bins
6.2
DES
01-Jul-11
30-Jun-12
6.2
DES
01-Jul-11
30-Jun-12
$52,000 New Storage Sheds $52,000 New Staff Car park
6.2
DES
01-Jul-11
30-Jun-12
6.2
DES
01-Jul-11
30-Jun-12
6.2
FM
01-Jul-11
31-Aug-11
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
12422.0804.200.0043 12422.0804.200.0044 12422.0804.200.0045 12422.0804.200.0048
12430.0807.200.0001
$9,918 Purchase Fuel Bowser for Jandowae Depot 2407 Jimbour Quarry Pre Coater (homemade unit) Approx 22 years old. Home made unit which has become in efficient. Also numerous OH & S $170,000 issues
12430.0807.200.0135
2403 Smith Low Loader 22yrs. Council policy 20 yrs. Requires size upgrade to quad axle for legal $230,000 loading Ambi Trencher - replacement with a trencher arm for the backhoe. Approx 25yrs Ambi trencher $15,000 unusable do to OH & A issues
12430.0807.200.0136
$7,500 2386 - Slasher 28 yrs old Completely worn out
12430.0807.200.0134
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA6 Page 5 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
12430.0807.200.0137 12430.0807.200.0138 12430.0807.200.0139 12430.0807.200.0140 12430.0807.200.0141 12430.0807.200.0142 12430.0807.200.0143
12430.0807.200.0144
12430.0807.200.0145
12430.0807.200.0146 12430.0807.200.0147 12430.0807.200.0148 12430.0807.200.0149
12430.0807.200.0151 12430.0807.200.0152
12430.0807.200.0154
12430.0807.200.0155
Net Budget
$60,000
New Plant Ride on Footpath Scrubber for the regional town main streets Requested to address regular main street $40,000 complaints in most towns 1 x Ute (2573) Upgrade of Wandoan SES vehicle (trade SES ute 2753.2294 to SES, new to Works $40,000 $27,000 1 x Ute (2297) As per vehicle replacement policy 3 x Sedans (2590,2342,2770) As per vehicle $110,000 replacement policy 3 x utes (2344,2345,2343) As per vehicle $109,000 replacement policy 2 x 4WD 2927,2223 Sees ute upgrade. Sell SES utes 2927 & 2223 - 2351 & 2352 to SES new to $80,000 works 1 x Wagon 2870 As per vehicle replacement policy $36,923 9 x Sedans 1080 1083 1086 1134 1119 2231 2573 2575 2811 $270,000 As per vehicle replacement policy 8 x Sedans (1114 1112 1113 2790 2808 2805 2841 1115) $245,000 As per vehicle replacement policy $124,000
12430.0807.200.0157
$132,000
12430.0807.200.0158
$171,692
12430.0807.200.0160
$40,000
12430.0807.200.0163
New Plant - Secondhand Telehandler based from the Jimbour Quarry. Requiring to hire crane for the change out of screens and maintenance work on the crushing plant at the Jimbour Quarry. Can also be utilised at the mobile crushers and other regional sites
2166 - Case Skid Steer Loader. 13 yrs. Council $75,000 policy 10 yrs 2148 UD Water Truck 15yrs Council Policy 10yrs $240,000 2261 Walker Ride on Mower 5yrs As per Council $20,000 policy 2062 Caterpillar 962G Loader. 11 yrs Council $415,000 Policy 10yrs 2046 John Deere Mower 7yrs Council Policy 5yrs $15,000 2022 Isuzu Tip Truck 12 yrs Council Policy 10yrs $140,000 2007/2101 Mack Body Truck & TWE Dog Trailer. 10 yrs. As per Council Policy Change to a PM & $285,000 Side tipper
12430.0807.200.0156
12430.0807.200.0162
Actions
4 x Utes (1138 2501 2116 2518) as per vehicle replacement policy 3 x Wagons (1121 2856 2541) as per Council Policy 5 x 4WD (1093 2487 2515 2514 2521) As per Council Policy 1 x 4WD Ute Waste Operations Officer (requested by EHM)
2 x sedans (2234 2807) $65,000 as per vehicle replacement policy 2 x utes 2219 2218 $64,615 as per council replacement policy
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31-Jul-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31-Jul-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31-Jul-12
Western Downs Regional Council Operational Plan - SA6 Page 6 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
12430.0807.200.0164
12430.0807.200.0165 12430.0807.200.0166 12430.0807.200.0167
12430.0807.200.0168
12430.0807.200.0169 12430.0807.200.0173 12430.0807.200.0174
12430.0807.200.0175
Net Budget
Actions
1 x wagon 1142 $55,000 as per vehicle replacement policy 1 x new ute Local Laws Officer - Chinchilla as requested by $30,000 EHM 2 x sedans 2142 2591 $64,000 as per vehicle replacement policy 4 x utes 2122 2126 2134 2121 $128,000 as per vehicle replacement policy 1 x new ute Utilities Network Supervisor (requested by GMU) $35,000 1 x new ute Utilities Treatment Supervisor (requested by GMU) $35,000 2854 Miles SES Troop Carrier (30 yrs) 1143 to $55,000 SES new to works 2309 Volvo Body Truck - 10 years as per vehicle $280,000 replacement policy New Plant - 8 ton tip truck Existing works construction gang has no truck to carry signs posts equipment materials etc. Always running back to town to collect stock and equipment. Also to be used for maintenance work and use with the skid steer as well $110,000
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31-Jul-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
2276 case excavator 7yrs Council policy 10yrs. However this machine is requiring a large amount of major repair work 12430.0807.200.0176
12430.0807.200.0177 12430.0807.200.0179 12430.0807.200.0180 12430.0807.200.0181 12430.0807.200.0182
12430.0807.200.0183
$385,000
$80,000
Two aggregate roller spreaders to be fitted to truck 2901 2783 Given ability to reseal resheet and mitigate any sea bleeding straight away. Old existing cockerel units not be used due to safety issues (staff standing on the rear )
2363 Hino Dutro Tip Truck 8 yrs as per council $101,538 policy 2362 2372 Hino Body Truck TWE Dog Trailer 10 $280,000 yrs as per council policy 42 Zero Tum Mower replace with existing small $12,000 ride on mower 5 yrs as per council policy 2377 Iseki Front Deck Mower 6 yrs Council policy $33,000 5 yrs Two fuel trailers Currently using tanks on skids which require constraint craning onto the back of the trucks. Unable to lift these tanks with the earthmoving equipment on the jobsite as per the $42,000 craning code
12430.0807.200.0184
$25,000
12430.0807.200.0185
$15,000
12430.0807.200.0186
$75,000
12430.0807.200.0187
$440,000
New plant skid steer trailer currently requiring 2 trips to jobsite new skid steer attachments broom forks etc better utilisation of the skid steer loader 2433 cse skid steer loader 13yrs council policy 10yrs 1035 caterpillar 120H Grader 13yrs Council Policy 10yrs
Western Downs Regional Council Operational Plan - SA6 Page 7 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
12430.0807.200.0188
12430.0807.200.0189
12430.0807.200.0190
12430.0807.200.0191 12430.0807.200.0192 12430.0807.200.0193 12430.0807.200.0194
12430.0807.200.0195 12430.0807.200.0196 12430.0807.200.0197 12430.0807.200.0198 12430.0807.200.0199 13110.0802.200.0019 13110.0802.200.0020 13110.0802.200.0021 13110.0802.200.0022 13110.0802.200.0023 13110.0802.200.0024 13110.0802.200.0030 13111.0802.200.0001
13112.0802.200.0003
13112.0802.200.0017
Net Budget
Actions
2442 caterpillar D7R dozer 13yrs Council policy $870,000 10yrs 1030 vibromax vibrating roller 10 yrs council policy 15 yrs Machine very badly deteriorated and is falling apart Consideration given to major repair. Better value for money to trade. Also sell surplus roller 1(034 momag vibrating roller) $180,000 Cox ride on mower. New to works existing works (1070) to lake broadwater (as requested by the $27,000 lake broadwater association) 2465 Isuzu gang truck 8 yrs as per council policy Use for SES Dalby upgrade sell 2850 20 yrs 2465 to SES new to works $73,846 2397 hino crane truck 25 yrs Council policy 10 $150,000 years $120,000 2399 Hino tip truck 25 yrs Council policy 10yrs 2426/1025 Hino Body truck and Daybreak dog $245,000 trailer 15 yrs Council policy 10 yrs 2452 - Case duopactor tractor roller. 11 yrs Council policy 10 yrs The configuration of this unit no longer suitable to operational requirements $156,923 replace with multi tyred roller 2454 Komatsu WA470 Loader 11 yrs Council $460,000 policy 10 yrs Purchase New Utility for Miles Parks & Gardens $35,000 crew $60,000 Purchase two new sets Portable traffic lights Portable litter collection vehicle litter critter or $100,000 similar for use at transfer stations and landfills Branch Creek Road Reconstruction (RRG) $750,000 (Ch1.14 to 1.97) $80,000 Senior Citizens Onstreet Parking (TIDS) Dalby South State School On Street Carparking $140,000 (SafeST) Hunter Street Recycling Hard Stand Area (TIDS) $70,000 $450,000 Moreton Street (TIDS) Golf club to authur street) Dixon Street Dalby - Dust Suppression Seals as $60,000 per Council Policy $10,000,000 Flood Damage - Event Dec 10 to Jan 11 Reseal Program 2011/12 includes prior year $811,000 programme Banana Bridge Road. resheet and seal (5.0 to 9.0). Allow for higher traffic volumes, access to Kogan Creek Power Station. LRRS network $400,000 Vanrenen Road ch 4.1-10.5km. Upgrade to seal standard. Project funded by QGC through private works. Inc realignment to Weimbilla Cr crossing. Project requested by QGC to assist with there $1,227,273 operations in the area
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31-Jul-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
DES
01-Jul-11
31/06/2012
6.6
DES
01-Jun-11
30-Jun-12
6.6
DES
01-Jul-11
30-Jun-12
6.6
FWC
01-Oct-11
31-Oct-11
6.6
FWC
01-Oct-11
31-Oct-11
6.6
DES
01-Jul-11
30-Jun-12
6.2
WMD
01-Jan-12
30-Jun-12
6.2
WMD
01-Jan-12
30-Jun-12
6.2
WMD
01-Aug-11
31-Dec-11
6.2
WMD
01-Aug-11
30-Jun-12
6.2
WMD
01-Mar-12
30-Jun-12
6.2
WMD
01-Oct-11
31-Mar-12
6.2
WMD
01-Jul-11
30-Jun-12
6.2
WMD
01-Sep-11
31-Mar-12
6.2
WMCT
01-Sep-11
01-Jan-12
6.2
WMCT
01-May-11
31-Oct-12
Western Downs Regional Council Operational Plan - SA6 Page 8 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
13112.0802.200.0018 13112.0802.200.0026 13113.0802.200.0001 13114.0802.200.0011 13114.0802.200.0012 13114.0802.200.0013 13114.0802.200.0019 13115.0802.200.0001
13118.0802.200.0001
13118.0802.200.0002
13118.0802.200.0003
13118.0802.200.0004 13118.0802.200.0011 13119.0802.200.0001 13121.0802.200.0001 13123.0802.200.0001 13124.0802.200.0005 13125.0802.200.0001 13126.0802.200.0001 13127.0802.200.0001 13144.0802.200.0005
13145.0802.200.0005 13149.0802.200.0002 13210.0803.200.0010
13210.0803.200.0011 13211.0803.200.0006 13310.0803.200.0004
Net Budget
Actions
Noel Robinsons Road. Sealing of floodways and dust suppression, funded by QGC due to their $110,000 operations along that road $10,000,000 Flood Damage - Event Dec 10 to Jan 11 $454,000 Chinchilla District Reseals Power Station Rd (0.6 to 6.1) - Upgrade Bitumen $1,800,000 $464,000 Arubial Road (15.6 to 19.6) - Upgrade Bitumen Harphams Rd (14.3 to 16.54) - Upgrade Bitumen $206,000 $10,000,000 Flood Damage - Event Dec 10 to Jan 11 $241,000 Bitumen Reseals - Various Roads Miles Bennetts School Road. resheet and seal ch 10.02 13.63km (Alkira Lane to Upper Humbug Road) Extend seal into lifestyle area, and a bus route. $80,000 Goranba Lane. resheet and seal ch 7.54 14.76km, (Community Ln to Surat Dev Road) $175,000 Extend seal into lifestyle area, and bus route Kinkabilla Road. Resheet and seal ch 5.29 13.76km. Complete sealing of road, improve access and useability of road Lower maintenance issues with lack of good gravel for resheeting in area $880,000 Cambridge Crossing Road. Widen and overlay, ch 8 - 12km. Road require rehab, widening to improve safety $80,000 and useability Payne Street. Reconstruction of street for asset $170,000 management. $310,000 Tara District Reseals Bitumen Reseals - Various Roads - Asset $326,000 Replacement $676,000 Resheeting Program 2011/12 All Gravel Roads - Gravel Resheeting Program $780,000 Chinchilla $750,000 Gravel Roads - Resheeting Program $385,000 Gravel Resheeting - Various Roads Gravel Resheeting - Various Roads - Asset $303,500 Replacement New Footpath Jandowae (Main Street to Hospital) $60,000 Warrego Highway Brigalow. Replace the footpath in Brigalow due to existing one be hazardous $26,000 $50,000 Streetscape - Design & Planning - Wandoan Grays park - Replacement of playground $10,000 equipment Main Street Gardens - Block retaining wall - in front of Court House, roots of tree going into footpath $30,000 Lions Park Chinchilla. Replace / Install playground $20,000 equipment. Stage 1 of 3. Culvert Replacements - Curtis/Geisel Street $55,000 Intersection
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.2
WMCT
01-Oct-11
31-Dec-11
6.2
WMCT
01-Jul-11
30-Jun-12
6.2
WMCT
01-Sep-11
30-Apr-12
6.2 6.2
WMM WMM
01-Jul-11 01-Jan-12
30-May-12 31-Mar-12
6.2
WMM
01-Apr-12
31-May-12
6.2
WMM
01-Jul-11
30-Jun-12
6.2
WMM
01-Sep-11
31-Mar-12
6.2
WMCT
01-Sep-11
31-Dec-11
6.2
WMCT
01-Sep-11
31-Dec-11
6.2
WMCT
01-Feb-12
30-Jun-12
6.2
WMCT
01-Sep-11
31-Dec-11
6.2
WMCT
01-Mar-12
31-May-12
6.2
WMCT
01-Sep-11
31-May-12
6.2
WMM
01-Sep-11
31-Mar-12
6.2
WMD
01-Jul-11
30-Jun-12
6.2
WMCT
01-Jul-11
30-Jun-12
6.2
WMCT
01-Jul-11
30-Jun-12
6.2
WMM
01-Jul-11
30-Jun-12
6.2
WMM
01-Jul-11
30-Jun-12
6.5
WMD
01-Oct-11
31-Dec-11
6.5
WMCT
01-Aug-11
29-Feb-12
6.5
WMM
01-Nov-11
31-May-12
6.9
WMD
01-Jul-11
31-Mar-12
6.9
WMD
01-Oct-11
31-Dec-12
6.9
WMCT
01-Aug-11
31-Mar-12
6.2
WMD
01-Jul-11
30-Nov-11
Western Downs Regional Council Operational Plan - SA6 Page 9 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements 13310.0803.200.0005 13311.0803.200.0001
Net Budget
Actions
$49,000 Replace Culverts - Blaxland Road Charleys Creek - Gaske Lane stormwater system, $397,000 further funds for project
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
6.2
WMD
01-Jul-11
30-Nov-11
6.2
WMCT
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA6 Page 10 of 10
Key Performance Indicators - KPIs per Strategic Function
Strategic Activity 7: Empowering Our Team Ambition Provide Organisational support and leadership to build a strong and effective regional Council Accountability Director Organisational Services
Strategic Function Elements
Net Budget
Actions
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Key Performance Indicators - KPIs per Strategic Function
Finish
Strategic Function 7A: Strategic Management - To provide effective strategic planning and leadership to establish a clear focus, shared across our regional organisation Leadership
Strategic Management
Implement OTUS Adopted Recommendations
7.1
CEO
01-Aug-11
30-Jun-12
Conduct a Professional Development Program with Councillors and Executive Team
7.1
CEO
01-Jul-11
30-Jun-12
Implement statutory responsibilities of the 2012 LG Election
7.0
CEO
01-Dec-11
30-Apr-12
Completion and revision of the Executive Strategic 18 Point Plan
7.0
CEO
01-Jul-11
31-Aug-11
Conduct regular Strategic Executive Team and Management Team Meetings
7.0
CEO
01-Jul-11
30-Jun-12
Develop 2012 -2017 Corporate Plan
7.0
SCM
01-Jul-11
29-Feb-12
Facilitate Reporting on Planning and Accountability Documents as per legislative requirements
7.0
SCM
01-Jan-12
30-Jun-12
Facilitate Development of 2012/13 Operational Plan
7.0
SCM
01-Apr-12
30-Jun-12
Develop Divisional Plan Framework
7.0
SCM
01-Jan-12
30-Jun-12
Facilitate Development of new organisational performance and reporting systems
7.0
SCM
01-Jan-12
30-Jun-12
01-Jul-11
30-Jun-12
01-Jul-11
30-Jun-12
Strategic Function 7B: Governance - To implement best practice governance to achieve an effective and accountable organisation Corporate Governance
Facilitate Development of Risk Management Plan
7.7
Implement the Internal Audit Plan Adoption of Local Laws and Subordinate Local Laws
7.7 7.9
CSGM
01-Jul-11
01-Dec-11
Preparation of New Delegations Register
7.9
CSGM
01-Jul-11
31-Dec-11
OIC Audits Completed and legislative requirements met
Review and consolidate existing policies
7.9
CSGM
01-Jul-11
30-Jun-12
RTI Annual Return completed in accordance with legislative requirements
Implement Information Privacy Act 2009
7.0
CSGM
01-Jul-11
30-Jun-12
Number of Complaints made under Council's Complaints Management Policy
Implement Right to Information Act 2009
7.0
CSGM
01-Jul-11
30-Jun-12
Annual Report for 2010/11 adopted prior to 30 November 2011
Implement Council's Advisory Committee Policy Conduct a joint review of insurable assets with the asset management team
7.0
01-Jul-11
30-Jun-12
Number of complaints made under Information Privacy Act 2009
7.0
CSGM CSGM & AM & FPC
01-Jul-11
31-Oct-11
Appointment of Brokerage Services
7.0
CSGM
01-Jan-12
30-Jun-12
7.0
CSGM
01-Jul-11
31-Aug-11
7.0
CSGM
01-Sep-12
30-Nov-12
Implement required Identification Card System regionally in accordance with LG Act 2009 Compile Annual Report to meet new legislative requirements
IA
Western Downs Regional Council Operational Plan - SA7 Page 1 of 5
Regional Local Laws adopted by 1 December 2011 Deadline
Strategic Function Elements
Councillors Governance
Net Budget
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
Investigate Governance Compliance System
7.0
CSGM
01-Jul-11
30-Jun-12
Implement Complaints Management Policy Audit of Legal Documents and consolidation of regional Register. Develop and Facilitate Councillor Induction Program
7.0
CSGM
01-Jul-11
30-Jun-12
7.0
CSGM
01-Jul-11
30-Jun-12
7.0
CSGM
01-Jan-12
30-Jun-12
Develop Councillor Governance Framework
7.0
CSGM
01-Jul-11
30-Sep-11
Actions
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 7C: Strategic Marketing - Deliver marketing, communication and PR strategies that enhance Council's professional corporate image
Strategic Marketing
Maintain Council's Image Library with current photos of the region, our communities, local faces and our team. Continue to facilitate implementation of Council's Brand Architecture and integrity of Corporate Identity Expand merchandise range for use across Council for promotion and events
7.2
CSM
01-Jan-12
30-Jun-12
7.2
CSM
01-Jan-12
30-Jun-12
7.2
CSM
01-Oct-11
31-Mar-12
Annual $ value of media coverage achieved as reported by Media Monitors. % increase media releases and media alerts distributed from last annum Number Visitors to Website
Corporate Communications
Produce communication materials to inform the community of Council news, including daily media releases, monthly Council Updates, monthly Tara District Updates, bi-monthly Miles and Wandoan District Updates, Team Updates and Community Update Newsletters
7.3
CSM
01-Jan-12
30-Jun-12
Develop Strategic Council Communication Plan
7.3
CSM
01-Jan-12
30-Jun-12
7.3
CSM
01-Jan-12
30-Jun-12
7.3
CDM
01-Jul-11
31-Dec-11
7.3
CSM
01-Jan-12
30-Jun-12
7.3
CSM
01-Jul-11
31-Dec-11
Continue to enhance functionality and develop strategies to maximise the usage of COLIN Undertake Annual audit of WDRC Website to ensure compliance with relevant legislation Continue to enhance functionality and develop strategies to maximise the usage of WDRC Website include Self-Service functionality Develop Business Rules for effective use of Council's eNews and SMS subscription service Investigate data management system for SMS alert system
Community Engagement
7.3
CSM
01-Jul-11
31-Dec-11
Develop and implement a communication and community engagement strategy re Relocation to new Corporate Office
7.3
CSM
01-Jul-11
31-Dec-11
Investigate "WDRC Update" Television Campaign
7.3
CSM
01-Jan-12
30-Jun-12
Undertake professional broadcast production to establish stock footage for television advertising and promotion. Investigate the usage Social Media to expand Council's communication reach
7.3
CSM
01-Jan-12
30-Jun-12
7.3
CSM
01-Jan-12
30-Jun-12
Conduct Biennial Market Facts Community Customer Satisfaction Survey
7.3
CSM
01-Jul-11
31-Dec-11
Facilitate Council's Community Connect Forums
7.3
CSM
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA7 Page 2 of 5
Number of Visitors to COLIN
Strategic Function Elements
Net Budget
Actions Provide advice and support to Directorates to compile their Community Engagement and Communication Plans in accordance to Council's Policy, Guidelines and Toolkit
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
7.3
CSM
01-Jul-11
30-Jun-12
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 7D: Information Management - Effective and timely management of all forms of correspondence generated and received by Council in order to deliver excellent customer service Customer Service Management
Develop and implement a regional Customer Service Training Plan Develop KPIs and Reporting System for Customer Service Management Ongoing Implementation of Regional Customer Contact Centre and refinement of operating procedures
Information Management
7.5
CSGM
01-Jul-11
30-Jun-12
7.5
CSGM
01-Jul-11
31-Dec-11 Number Customer Requests received and processed (Once system established)
7.5
CSGM
01-Jul-11
30-Jun-12 % Customer Requests completed within agreed service level timeframes (Once system established) % telephone calls handled within customer service guidelines % Calls answered outside customer service guidelines
Develop and implement a regional Communication Campaign for Contact Centre Review After-Hours Call Service for Contact Centre
7.5
CSGM & SCM
01-Sep-11
31-Dec-11
7.5
CSGM
01-Jul-11
31-Dec-11
Number of Incoming and Outgoing Correspondence items per quarter processed
Develop Standard Operating Arrangements for new Phone System including Video Conferencing and scheduling roll-out of features
7.5
CSGM & ICTM
01-Jul-11
30-Jun-12
% Tasks per quarter completed within approved timeframes % Tasks per quarter not processed within approved timeframes
7.4
IMC
01-Jul-11
31-Mar-12
7.4
IMC
01-Jul-11
31-Mar-12
7.4
IMC
01-Jul-11
31-Mar-12
7.4
IMC
01-Jul-11
31-Dec-11
7.4
IMC
01-Jul-11
30-Jun-12
7.4
IMC
01-Jan-12
30-Jun-12
7.4
IMC
01-Jul-11
31-Dec-11
Link Subject Index to Retention Index in compliance with Qld State Archives requirements
7.4
IMC
01-Jan-12
31-Mar-12
Facilitate conversion of Training Room to new Archive Room in conjunction with Community Services
7.4
IMC
01-Jan-12
30-Jun-12
Comply with Public Records Act 2002 and relevant Information Standards regarding Record Management and the Retention and Disposal of Public Records Develop required Strategic and Operational Recordkeeping Implementation Plan Develop Security Matrix for document control within Dataworks Develop enhanced information management reporting tools for Executive Management Team Review Information Management Section including policies and SWPs Creation of Regional Property Files Review Retention and Disposal Schedule in compliance with new Qld State Archives requirements
Strategic Function 7E: Human Resource Management - Attract, retain and develop an effective team whilst promoting a positive and proactive culture HR Management
Implement adopted OTUS HR Recommendations Implement Equal Employment Opportunity Management Plan
7.1
HRSM
01-Sep-11
30-Jun-13
7.1
HRSM
01-Oct-11
31-Dec-11
Western Downs Regional Council Operational Plan - SA7 Page 3 of 5
Number of employees per 100 capita
Strategic Function Elements
Learning & Development
Recruitment
Net Budget
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
Review current aged care remuneration arrangements
7.1
HRSM
01-Jul-11
31-Dec-11
Review HR Management internal systems
7.1
HRSM
01-Jul-11
30-Jun-12
Continue to develop relevant HR Policies Internal Audit of remuneration scales and allowances
7.1
HRSM
01-Jul-11
30-Jun-12
Wages and Salaries as % of total Council Operating Expenses
7.1
HRSM
01-Jul-11
31-Mar-12
% employee performance appraisals completed on time (within 28 days)
Establish programs that contribute to Councils Commitment to be an Employer of Choice
7.1
HRSM
01-Sep-11
30-Jun-12
Establish HR Metrics Workforce Planning Project Review and enhance current Performance Appraisal Process Conduct Bi-annual Employee Opinion Survey and reporting results
7.1
HRSM
18-Aug-11
30-Jun-13
7.1
HRSM
01-Jan-12
30-Jul-12
7.1
HRSM
24-Oct-11
31-Mar-12
Negotiate and implement the 2012 WDRC EB
7.1
HRSM
01-Jul-11
31-Mar-12
Negotiate and implement the 2011 Aged Care EB
7.1
HRSM
01-Jul-11
31-Mar-12
Negotiate and implement the 2011 Nurses EB Conduct an organisational Training Needs Analysis Apply for relevant external learning and development funding Continue commitment to Trainee and Apprenticeship Program
7.1
HRSM
01-Jul-11
31-Dec-11
7.1
HRSM
01-Apr-12
30-Jun-14
7.1
HRSM
01-Jul-11
30-Jun-12
7.1
HRSM
01-Jul-11
30-Jun-12
Develop Organisational Leadership Program
7.1
HRSM
01-Jul-11
30-Jun-12
Implement recruitment and selection strategies to ensure attraction and retention of a highly skilled workforce
7.1
HRSM
01-Jul-11
30-Jun-12
Enhance Exit Interviews process to contribute to the continued improvement of Council operations
7.1
HRSM
01-Jul-11
30-Jun-12
Introduction of eRecruitment
7.1
HRSM
01-Sep-11
31-Dec-11
Introduction of new job evaluation system
7.1
HRSM
01-Jul-11
31-Dec-11
Actions
Key Performance Indicators - KPIs per Strategic Function
Average Staff Vacancy Rate % annual staff turnover % employees who completed skills development/training
Strategic Function 7F: Safety - Implement and maintain safe workplaces for our people through continual development of Council's WHS System to best practice standards
Workplace Health & Safety
Continually enhance Council's WHS System and assist Directorates to identify and minimise hazards Deliver regional WHS Training Program including hosting specific Training Days on high risk topics Coordinate the delivery of Bi-monthly WHS Toolbox Talks by Supervisors Promotion of Key WHS Performance Indicators to management and staff Conduct annual internal audit of WHS Management System Develop and implement Safe Operating Procedures/Risk Assessment Manual
7.6
SC
01-Jul-11
30-Jun-12
7.6
SC
01-Jul-11
30-Jun-12
7.6
SC
01-Jul-11
30-Jun-12
7.6
SC
01-Jul-11
30-Jun-12
7.6
SC
01-Oct-11
31-Dec-11
7.6
SC
01-Jul-11
30-Jun-12
Number of Lost Time Injuries (LTI) vs Scheme Average Total number, costs, frequency and duration of lost time injuries reducing. 100% Toolbox Talks Completed 100% WHS inspections completed 75% compliance on WHS Audit
Strategic Function 7G: Disaster Management - To establish and maintain disaster planning and response systems to reduce the likelihood and consequence of disasters on the community Disaster Management
Review Regional Disaster Management Plan
7.8
SC
01-Jul-11
Western Downs Regional Council Operational Plan - SA7 Page 4 of 5
31-Dec-11
Strategic Function Elements
Net Budget
Actions Conduct regional disaster management exercises and meetings Provide Disaster Management Training for staff Identify funding opportunities and action successful grants Maintain regular communication and support for local SES groups Develop Community Communication Strategy to increase awareness of Council's role in Disaster Management
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
7.8
SC & CSMs
01-Jul-11
30-Jun-12
7.8
SC
01-Jul-11
30-Jun-12
7.8
SC
01-Jul-11
30-Jun-12
7.8
CSMs
01-Jul-11
30-Jun-12
7.8
SC
01-Jul-11
30-Jun-12
7.4
IMC
01-Feb-12
30-Jun-12
Empowering Our Team - Capital Projects 78816.0802.200.0001
Compactus existing Archive room at admin * $85,000 culture centre - $60,000
Western Downs Regional Council Operational Plan - SA7 Page 5 of 5
Key Performance Indicators - KPIs per Strategic Function
Number LDMG and LECG meetings held
Strategic Activity 8: Business Systems and Technology Ambition Implement and manage effective business systems and accountable financial practices to serve the needs of Council and the community Accountability Director Finance and ICT
Strategic Function Elements
Net Budget
Timeframe
Responsible Officer
Start
Finish
8.1
FM
01-Oct-11
30-Nov-11
8.1
FM
01-Jul-11
15-Sep-11
8.1
FM
01-Jul-11
31-Oct-11
8.1
FM
01-Aug-11
30-Sep-11
Adopt 2012/13 Budget by 30 June 2012 Rewrite Chart of Accounts to align with Council's Corporate Plan
8.1
DFICT
01-Oct-11
30-Jun-12
Net Financial Liabilities Ratio
8.4
FM
01-Jul-11
30-Sep-11
Operating Surplus Ratio
Recategorisation of Work Orders
8.4
FM
01-Oct-11
30-Jun-12
Working Capital Ratio
Develop a Financial Risk Register Facilitate Independent Financial Sustainability Review
8.4
FPC
01-Jul-11
31-Jul-11
8.4
FM
01-Sep-11
31-Mar-12
Develop Financial Reporting Framework
8.4
FM
01-Oct-11
31-Mar-12
8.5
FPC
01-Jul-11
30-Sep-11
8.5
AM & FM
01-Jul-11
31-Dec-11
01-Jan-12
30-Jun-12
Actions
Corporate Plan Linkage
Key Performance Indicators - KPIs per Strategic Function
Strategic Function 8A: Financial Planning and Performance - To plan and monitor the Council's financial performance Financial Planning & Reporting
Review Long-Term Financial Forecast Prepare general purpose 2010-11 Financial Statements Facilitate Audit of Council's Financial Statements in preparation for Annual Reporting Prepare 2012/13 Budget Development and Review Plan
Asset Financial Management
Land Tenure Management
Develop a Whole of Life Costing Model to assist in decision making re asset acquisitions Coordinate the development of an integrated asset management system
Number High Risk Financial Audit Issues reported Interest Coverage Ratio
Asset Consumption Ratio
Coordinate revaluation of all asset classes Develop a Budget Model for Acquisition and Sale of Assets
8.5
FPC
8.5
FPC
01-Jul-11
31-Oct-11
Implement version 6.3 Civica Authority
8.5
FM
01-Jul-11
30-Sep-11
Identify Council and State Land with potential for future development in towns of Chinchilla, Miles, Tara, Jandowae and Wandoan. Develop Land Register (Record land leases, licences and agreements)
8.5
DFICT
01-Aug-11
30-Sep-11
8.5
FM
01-Aug-11
01-Mar-12
Asset Sustainability Ratio
Strategic Function 8B: Rating and Utilities Revenue - To implement the Council's Revenue Policy in relation to rates and utility charges General Rate Revenue
Rates and charged levied in accordance with Council's Revenue Policy and Statement Implement Debt Collection Policy Remit and claim funds in accordance Council's Revenue Policy
8.4
RC
01-Jul-11
30-Jun-12
8.4
RC
01-Jul-11
31-Dec-11
8.4
RC
01-Jul-11
30-Jun-12
Western Downs Regional Council Operational Plan - SA8 Page 1 of 4
Rates and charges arrears vs industry average
Strategic Function Elements
Net Budget
Actions Implement Integrity Check of Categorisation Rating Database Perform Data Cleansing of Revenue Database Complete QVAS Report within 10 working days of receipt Compliance with Gas Ombudsmen Reporting Requirements
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
8.4
RC
01-Jul-11
30-Jun-12
8.4
RC
01-Jul-11
30-Jun-12
8.4
RC
01-Jul-11
30-Jun-12
8.4
RC
01-Jul-11
30-Jun-12
8.4
RC
01-Jul-11
30-Jun-12
01-Jul-11
30-Nov-11
Levy Water Consumption and Gas Billing within 45 working days of end of read period Implement Utility Reporting for Notices to comply with legislative requirements Implementation of Regional Wastewater Charging Methodology
8.4
RC
8.4
RC
01-Jan-12
31-Mar-12
Implement version 6.5 Civica Authority
8.5
FM
01-May-12
30-Jun-12
Implement and review an On Cost/Overhead Methodology to ensure full cost is identified to effectively distribute financial costs across the organisation
8.4
FPC & FSC
01-Jul-11
31-Dec-11
Implement Inventory Control Stores Strategy
8.4
FSC
01-Jul-11
30-Sep-11
Implement Online Requisition System
8.4
FSC
01-Jul-11
30-Sep-11
Key Performance Indicators - KPIs per Strategic Function
Average Age of Debts
Strategic Function 8C: Financial Services - To provide financial service to support the Council's operations
Financial Services
Implement Purchase Card Costing System
8.4
FSC
01-Oct-11
29-Feb-12
Conduct Procurement Audit/Training
8.4
FSC
01-Oct-11
31-Dec-11
8.6 & 8.3
ICTM
01-Jul-11
31-Jan-12
Number High Risk Financial Audit Issues reported
Strategic Function 8D: Information Communication Technology - To provide technical support to Council's operations Technology Support
Develop a five year ICT Asset Management and Systems Strategy Finalise and test Disaster Recovery Plan Develop and Implement ICT Office Relocation Strategy
8.3
ICTM
01-Jul-11
31-Aug-11
100% ICT Helpdesk Requests logged with relevant supplier within timeframes of Standard Work Practice
8.3
31-Dec-11
ICT Helpdesk Requests responded to within 2 business hours
8.3
ICTM ICTM
01-Jul-11
Roll-out Microsoft Office 2007 upgrade
01-Jul-11
30-Sep-11
%Total Downtime resulting from ICT System Failures
Review module security within Civica Authority
8.3
31-Dec-11
8.3
ICTM ICTM
01-Jul-11
Review data back-up strategy
01-Jul-11
31-Dec-11
8.3
ICTM
01-Jul-11
30-Sep-11
8.3
ICTM
01-Jul-11
31-Dec-11
Review Electronic Information & Communication System and Mobile Phone Policies Develop Standard Work Practice for logging of IT Helpdesk requests
Business Systems and Technology - Capital Projects
8.4
ICTM
01-Jul-10
01-Jul-11
85517.0801.200.0004
Email Archiving Solution Compliance with record keeping standards and RTI Requirements. Reduction in space $3,846 requirements for exchange mail store $21,000 Civica Implementation - AIM
8.4
FM
01-Jul-11
01-Jun-12
85517.0801.200.0005
Civica Implementation - Online Requisition, Mobile $32,500 and Version 6
8.4
FM
01-Dec-10
01-Jan-12
85517.0801.200.0001
Western Downs Regional Council Operational Plan - SA8 Page 2 of 4
Average age of ICT Assets
Strategic Function Elements
85517.0801.200.0006 85517.0801.200.0007
85525.0801.200.0010
85525.0801.200.0012
85525.0801.200.0014
85525.0801.200.0016
85525.0801.200.0018
85525.0801.200.0027 85525.0801.200.0028 85525.0801.200.0050
85525.0801.200.0051
85525.0801.200.0011
Net Budget
Actions
Regional Fleet/Workshops Fleet Management Program F/M program to manage councils plant & fleet for repair/service history, scheduled servicing, replacement forecasts, utilisation, fuel cards, etc. Will integrate $50,000 with Civica $20,000 Purchase PowerPlanner Photocopier - Moonie RTC. Replacement of machine at the end of its' service $10,350 life Photocopier - Dogwood Crossing. Replacement of copier at the end of its' service life. Includes allowance for a swipe card reader $16,000 system Photocopier - Community Services. New photocopier for Community Services Section $16,000 on move into 30 Marble Street Cemeteries Online. Cemetery information provided to the public as a $23,000 function to Councils website CCTV - Dalby Upgrade existing infrastructure & relocate transmitters in order to achieve 99.99% network $126,500 availability Nexium Communications Optic Fibre Link to Brisbane - Setup Costs. Establishment of a single high speed internet link for the entire IPWAN network will enable Council to drop back our ADSL services to one high speed back-up link from the DR site at Chinchilla. Will enable SIP trunking for new VoIP phone system that will drive external call cost savings $20,700 Photocopier - Records Section (on Move to 30 $10,350 Marble Street) Photocopier - Jandowae CSC $10,350 Replace machine at the end of it's useful life Dataworks Access. Provide ability to provide webforms etc for $58,045 Customer Request System to Council Website Photocopier - Tara CSC. Replacement of main office copier at the end of its' $16,000 service life
Corporate Plan Linkage
Responsible Officer
Timeframe Start
Finish
8.4
DES
01-Jul-11
30-Jun-12
8.4
FM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Jul-11
30-Jun-12
8.4
ICTM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Jul-11
30-Jun-12
1.2
ICTM
01-Jul-11
31-Dec-11
8.3
ICTM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Jul-11
30-Sep-11
8.4
ICTM
01-Jul-11
29-Feb-12
8.4
ICTM
01-Jul-11
31-Dec-11
8.4
ICTM
01-Aug-11
31-Mar-12
8.4
ICTM
01-Jul-11
30-Jun-12
8.4
ICTM
01-Jul-11
30-Jun-12
Wireless LAN. Integrated, centrally managed business grade wireless LAN to provide stable, high speed wireless access for laptops and mobile devices. Dalby Corporate Office, Chinchilla CSC & Library, Miles CSC, Tara CSC, Wandoan CSC, Jandowae CSC, Dalby Rural Depot, Dalby Library, Tara Library, Dogwood Crossing, Bell Library, Meandarra Library, Moonie RTC 85525.0801.200.0039 85525.0801.200.0040
85525.0801.200.0041
$95,000 DRAINS (Stormwater Design). $17,250 Stormwater system design software ESX Servers - Upgrade. Upgrade ESX Servers at End of Life/Warranty $43,700
Western Downs Regional Council Operational Plan - SA8 Page 3 of 4
Key Performance Indicators - KPIs per Strategic Function
Strategic Function Elements
85525.0801.200.0042
85525.0801.200.0043
85525.0801.200.0044
85525.0801.200.0045
Net Budget
Actions
Radio Tower Replacement - Microwave Hill (Miles) Required to expand two-way radio network into Wandoan Area. Existing tower is well past a $51,750 serviceable condition Two-way Radio Tower Establishment. Establish a new two way radio tower to facilitate expansion of Councils two-way radio network into $51,750 the Wandoan area Trapeze Desktop (12 Licences). Electronic annotation, calibration, measuring and stamping of Development Applications without $25,000 printing Commvault. Backup software with better compatibility to NetApp storage. Much faster data throughput to $40,000 drastically reduce our backup window
Timeframe
Corporate Plan Linkage
Responsible Officer
Start
Finish
8.3
ICTM
01-Jul-11
30-Jun-12
8.3
ICTM
01-Jul-11
30-Jun-12
8.4
ICTM
01-Jul-11
30-Jun-12
8.4
ICTM
01-Jul-11
30-Jun-12
8.4
ICTM
01-Jul-11
30-Jun-12
85525.0801.200.0048
NetApp SATA Storage Upgrade. Upgrade SATA storage capacity on NetApp $45,310 FAS2020 in Dalby and Chinchilla Automatic Library Self Check Units. Libraries - Bell, Jandowae, Meandarra, Moonie, Tara, Wandoan. Automated self check out of $34,500 library material by patrons
1.8
ICTM
01-Aug-11
31-Mar-12
85525.0801.200.0052
Installation of CCTV security camera within the $80,000 CBD area of Tara
1.2
CDC
01-Jul-11
30-Jun-12
85525.0801.200.0046
Western Downs Regional Council Operational Plan - SA8 Page 4 of 4
Key Performance Indicators - KPIs per Strategic Function