Project : Desert Elite Sports Complex Location: North Las Vegas Proposal Date: 5/1/2017
TOTAL BUDGET $ Spec. Sec. 1
2
Description General Conditions
1,166,487.00
Design Design Architect /Consultant / Coordinator Architectural Design and Contract Administration Misc. Reimbursable 3rd Party Structural & Mechancial QAA Owner's Representative
$ $ $ $ $
85,000.00 90,000.00 40,000.00 35,000.00 73,651.00
Permits Building Permits
$
75,000.00
Project Manager Assistant Project Manger Superintendent Field Engineer General Superintendent Site Labor Safety Officer Accounting/Admin. General Conditions- Other
$ $ $ $ $ $ $ $ $
114,400.00 132,480.00 118,720.00 160,000.00 43,520.00 8,960.00 51,136.00 138,620.00
$
1,481,448.85
Unit cost
Quantity
unit
$ $ $ $ $ $
106,408.75 39,250.00 46,250.00 39,250.00 65,000.00 13,000.00
$0.25 $0.50 $0.50 $0.50 $500.00 $50.00
425,635 78,500 92,500 78,500 130 260
SF SF SF SF EA CY
50,000.00 25,000.00 15,000.00 25,000.00 50,000.00 15,000.00
$50,000.00 $25,000.00 $15,000.00 $25,000.00 $50,000.00 $15,000.00 $0.00
1 1 1 1 1 1 0
LS LS LS LS LS LS LS
Division 2 - Site Earthwork Clear & Grub Building Pad Parking Lot Sub-grade Type 2 Building SOG Structural Excavation for Foundation Structural Excavation for Site Wall Site Utilities Nevada Energy (from transformer tp 5' of building) Southwest Gas Cox/ Century Link - (from street vault to within 5' of building) Water (from street to within 5' of building) Sanitary Sewer ( from street to within 5' of building Storm Drainage Grease Interceptor
$ $ $ $ $ $ excluded
Site Improvements Asphalt Pavement Parking Lot Asphalt Patching / Traffic Control Utility Street Tie ins Entrance Gate Stripping and Signage
$ $ $ $
639,938.25 15,000.00 15,000.00 54,851.85
$1.75 $15.00 $15,000.00 $0.15
365,679 1,000 1 365,679
SF SF EA SF
Landscape Landscape & Irrigation
$
231,000.00
$3.00
77,000
SF
$
36,500.00
$0.50
73,000
SF
$
802,800.00
Unit cost
Quantity
unit
$ $ $
62,500.00 50,000.00 78,000.00
$25.00 $5.00 $300.00
2,500 10,000 260
SF SF CY
$ $ $ $ $ $
105,000.00 324,000.00 132,500.00 15,000.00 10,800.00 25,000.00
$300.00 $4.50 $5.00 $15,000.00 $0.15 $25,000.00
350 72,000 26,500 1 72,000 1
CY SF SF LS SF LS
Division 4 - Masonry Masonry Walls Building CMU @12' Elevator Shaft Site Trash / MEP Enclosures Site Wall
$
297,120.00
Unit cost
Quantity
unit
$ $ $ $
119,520.00 16,000.00 5,600.00 156,000.00
$12.00 $10.00 $8.00 $8.00
9,960 1,600 700 19,500
SF SF SF SF
Division 5 - Metals / Steel Fabrication Metals Structural Steel / Metal Building @ Basketball Courts Structural Steel Balance of Building Skylights in metal Building @BB Courts Stairs
$
2,007,750.00
Unit cost
Quantity
unit
$ $ $ $
935,000.00 510,000.00 50,000.00 100,000.00
$22.00 $17.00 $1,000.00 $50,000.00
42,500 30,000 50 2
SF SF EA EA
$ $ $ $
22,750.00 320,000.00 10,000.00 60,000.00
$35.00 $400.00 $10,000.00 $60,000.00
650 800 1 1
SF LF LS Allow
Division 6 - Carpentry Rough Carpentry Misc. Safety Materials Finish Carpentry Millowork / Reception/ Office Space/ Classroom / Wellness
$
335,000.00
Unit cost
Quantity
unit
$
35,000.00
$35,000.00
1
LS
$
300,000.00
$20.00
15,000
LF
Division 7 - Thermal / Moisture Protection Roofing Roofing everywhere except BB court metal Building Fireproofing Fireproofing Structural Steel
$
810,000.00
Unit cost
Quantity
unit
$
630,000.00
$9.00
70,000
SF
$
180,000.00
$2.50
72,000
SF
Division 3 - Concrete Site Concrete Curb and Gutter Side Walk Footing for CMU site Wall Structural Concrete (Rebar Included) Spread Footings / Grade Beams Slab on Grade Slab on Metal Deck Level 2 Elevator Pit Vapor Barrier under SOG Misc. concrete Equipment Pads
4
5
Misc. Metals Decco Canopies Exterior Guardrail at 2nd level Misc. Metal for Elevator Misc. Metals Allowance 6
7
GC's as a % of Total 6.24%
$
Survey Survey and Building Control 3
18,687,968.11
Cost
8
Division 8 - Doors & Windows Door, Frame, & Hardware Interior HM Doors, Frames, Hardware Exterior HM Doors, Frames, Hardware Window Systems Lease Space 1 Lease Space 2 Lease Space 3 Lease Space 4 Lease Space 5 Lease Space 6 Lease Space 7 Vestibule @ Entrance Storefront @ Entrance Punch Windows Misc. Interior Glazing Locker Room Mirrors
9
Division 9 - Finishes Exterior Skin Exterior Skin
$
2,413,950.00
Unit cost
Quantity
unit
$ $
22,000.00 13,200.00
$2,200.00 $2,200.00
10 6
leaf leaf
$ $ $ $ $ $ $ $ $ $ $ $
65,000.00 97,500.00 97,500.00 227,500.00 325,000.00 455,000.00 650,000.00 105,000.00 191,250.00 50,000.00 100,000.00 15,000.00
$65.00 $65.00 $65.00 $65.00 $65.00 $65.00 $65.00 $70.00 $85.00 $50.00 $2.00 $15.00
1,000 1,500 1,500 3,500 5,000 7,000 10,000 1,500 2,250 1,000 50,000 1,000
SF SF SF SF SF SF SF SF SF SF SF SF
$
3,418,365.00
Unit cost
Quantity
unit
$
1,100,000.00
$20.00
55,000
SF
Interior Metal Stud Framing and Drywall Interior Walls Locker Room Interior Wall BB Court Above 12" CMU Interior Wall @ Concourse Area Temp Walls separting unfinished shell spaces Paint Walls Blackout Paint Ceiling Restrooms Buildout Demo Temp Wall Interior Walls Lease Space 1 Interior Walls Lease Space 2 Interior Walls Lease Space 3 Interior Walls Lease Space 4 Interior Walls Lease Space 5 Interior Walls Lease Space 6 Interior Walls Lease Space 7
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $
22,950.00 148,500.00 63,000.00 45,000.00 77,625.00 85,000.00 198,000.00 10,000.00 9,000.00 13,500.00 13,500.00 31,500.00 45,000.00 63,000.00 90,000.00
$9.00 $9.00 $9.00 $9.00 $2.50 $2.00 $165.00 $2.00 $9.00 $9.00 $9.00 $9.00 $9.00 $9.00 $9.00
2,550 16,500 7,000 5,000 31,050 42,500 1,200 5,000 1,000 1,500 1,500 3,500 5,000 7,000 10,000
SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF
ACT ACT Ceiling Locker Rooms ACT Ceiling
$ $
31,500.00 292,770.00
$4.50 $4.50
7,000 65,060
SF SF
$ $ $ $ $
758,940.00 49,400.00 50,400.00 100,100.00 59,680.00
$13.00 $10.00 $10.00 $7.00 $8.00
58,380 4,940 5,040 14,300 7,460
SF SF SF SF SF
Finishes Locker Room Wall Tile Flooring Locker Room Wall tile Carpet Between Courts Carpet in Concourse Area Acoustical Treatments Acoustical Treatments at BB Courts 10
$
60,000.00
$60,000.00
1
Allow
$
126,600.00
Unit cost
Quantity
unit
$ $
6,000.00 39,600.00
$150.00 $1,100.00
40 36
EA Stalls
Overhead Doors Overhead Doors
$
40,000.00
$10,000.00
4
EA
Signage Allowance for Code Signage Exterior Signage
$ $
6,000.00 35,000.00
$1,500.00 $35,000.00
4 1
Allow LS
Unit cost $0.00
Quantity 0
unit UN
Unit cost $250,000.00 $10,000.00 $8,500.00 $500.00 $133.00 $81.00 $2,812.00 $5,221.00 $3,413.00 $1,500.00 $134.00 $10.54
Quantity 1 24 20 80 24 5 6 6 6 400 6 28,200
unit Allow EA EA UN EA EA EA EA EA EA EA SF
Unit cost $0.00
Quantity 0
unit UN
Division 10 - Specialties Specialties Fire Extinguishers and Cabinets Bathroom Accessories & Locker Allowance
11
Division 11 - Equipment Name Scope Here
$ $
12
Division 12 - Furnishings Weight Room Equipment Ceiling Mounted Hoops Wall Pads w. Graphics Tip and Roll Bleachers 15' Player Benches 15' Divder Curtains Score Boards Shot Clocks Score Tables Lockers Basketball Court Portable Hoops
$ $ $ $ $ $ $ $ $ $ $ $ $
13
Division 13 - Special Construction No Scope
$ $
14
Division 14 - Conveying Systems Elevator Elevator Cab Finishes
$ $ $
45,000.00 35,000.00 10,000.00
Unit cost $35,000.00 $10,000.00
Quantity 2 1
unit STOPS LS
15
Division 15 - Mechanical Fire Suppression Sprinkler System
$
716,520.00
Unit cost
Quantity
unit
$
252,000.00
$3.50
72,000
SF
HVAC HVAC System
$
402,500.00
$7.00
57,500
SF
Plumbing Restroom Fixtures Plumbing Locker Room Water / Sanitary Sewer
$ $
22,500.00 39,520.00
$300.00 $8.00
75 4,940
EA SF
$
1,490,409.50
Unit cost
Quantity
unit
$ $ $ $
648,000.00 144,000.00 180,000.00 144,909.50
$9.00 $2.00 $2.50 $0.50
72,000 72,000 72,000 289,819
SF SF SF SF
Fire Alarm Fire alarm
$
216,000.00
$3.00
72,000
SF
Phone / Data / CATV Phone / Data AV/ Security/Building Access Allowance
$ $
45,000.00 112,500.00
$45,000.00 $2.50
1 45,000
ALLOW SF
16
Division 16 - Electrical Electrical / Lighting Switch Gear Distribution Lighting Site Electrical
1,670,305.00 250,000.00 240,000.00 170,000.00 40,000.00 3,192.00 405.00 16,872.00 31,326.00 20,478.00 600,000.00 804.00 297,228.00 -
Total General Conditions
$
1,166,487.00
Total Sub contract
$
15,615,268.35
Bond for subcontractors
$
Contingency Overtime Allowance
$
FEE Sub Total GL, PL and Umbrella Insurance
780,763.42
3% $
468,458.05
3% $
540,929.30
$ $
18,571,906.12 116,061.99
0.67%
Grand Total
Matrix Site Building Furnishings Design / Permits
-
5% $
Bid Check $ 16,781,755.35
(Should = $0
$ 18,687,968.11
Unit Acre Sf Sf Sf
5 70000 70000 70000
$1,187,995 $811,300 $2,079,000 $246,400
$237,599 $11.59 $29.70 $3.52
$ 16,781,755.35 $ -
Project : Desert Elite Sports Complex Location: North Las Vegas Proposal Date: 5/1/2017
General Conditions Management Staff PM Pre-construction Dates here Project Manager Asst. Project Manager
Duration (Weeks)
% of Time
13.0
50%
0.0 0.0
0%
Field Engineer
13.0
50%
Construction Dates here
Duration (Weeks)
% of Time
32.0
75%
Project Manager Asst. Project Manager
0.0
0%
Project Superintendent
32.0
100%
Field Engineer
32.0
175%
General Superintendent
32.0
100%
Accounting/ Admin
32.0
85%
Site Labor
32.0
50%
Safety Officer
32.0
10%
Closeout and Punch Dates here Project Manager
Duration (Weeks) 4.0
% of Time 50%
Project Superintendent
4.0
100%
Field Engineer
4.0
0%
Total Hours Rate Total Dollars
Supt.
Field Engineer
Director
Acct/ Admin
Site Labor
Safety Officer
Notes PRE CON 8/1/2017
10/31/2017
Days 91.0
Weeks 13.0
Mos 3.0
Construction 8/1/2017
3/13/2018
Days 224
Weeks 32.0
Mos 7.4
Closeout 3/13/2018
4/10/2018
Days 28
Weeks 4.0
Mos 0.9
260
0%
Superintendent
APM
0 0
960 0 1280 2240 1280 1088 640 128
80 160 0 1300
0
1440
2240
1280
1088
$88.00
$60.00
$92.00
$53.00
$125.00
$47.00
$114,400.00
$0.00
$132,480.00 $118,720.00 $160,000.00 $51,136.00
640
128
$68.00
$70.00
$43,520.00
$8,960.00
$629,216.00
Project : Desert Elite Sports Complex Location: North Las Vegas Proposal Date: 5/1/2017
General Conditions Management Staff PM Pre-construction Dates here Project Manager Asst. Project Manager
Duration (Weeks)
% of Time
13.0
50%
0.0 0.0
0%
Field Engineer
13.0
50%
Construction Dates here
Duration (Weeks)
% of Time
32.0
75%
Project Manager Asst. Project Manager
0.0
0%
Project Superintendent
32.0
100%
Field Engineer
32.0
175%
General Superintendent
32.0
100%
Accounting/ Admin
32.0
85%
Site Labor
32.0
50%
Safety Officer
32.0
10%
Closeout and Punch Dates here Project Manager
Duration (Weeks) 4.0
% of Time 50%
Project Superintendent
4.0
100%
Field Engineer
4.0
0%
Supt.
Field Engineer
Director
Acct/ Admin
Site Labor
Safety Officer
Notes
Equipment Field Office Trailer Set up / Take Down office trailer Cleaning of office trailer Temp Sewer - Office Sanitary Supplies / Office Storage Containers Mgmt Vehicles Pick up Truck Fuel Toilets Service of toilets Small Tools Outside Rental Equipt Copy Machine Fax machine Ice Water and cups Office Water / Ice Field Other General Clean upInstall Telephone System Telephone mo service Charges Cellular Phone Communication / Radio Equipment Electric set up Electric Service Moving Expense Out of Town / Subsistence Safety Training Program Job Signage Temp Signage Fire protection / Extinguishers Drug Testing Postage and Shipping Messenger / Courier Computer Support / Assistance /Hook up Employee Incentive / Bonus Total
Unit
1
0 0 0 0 0 0 3 0 32 0 0 26 0 8 0 0 0
MO LS WK WK WK MO MO MO WK MO WK WK MO MO MO WK WK
230 26 1 1 0 0 0
LS 0 LS 0 EA/mo 18 EA/mo 0 LS 0 LS 0 MO LS 0 MO 0 MO 0 LS 0 LS 6 EA 0 EA 32 WK 0 WK 0 LS
Mos 3.0
Construction 8/1/2017
3/13/2018
Days 224
Weeks 32.0
Mos 7.4
Closeout 3/13/2018
4/10/2018
Days 28
Weeks 4.0
Mos 0.9
0 1280 2240 1280 1088 640 128
80 160 0 1300
0
1440
2240
1280
1088
$88.00
$60.00
$92.00
$53.00
$125.00
$47.00
$114,400.00
$0.00
$132,480.00 $118,720.00 $160,000.00 $51,136.00
640
128
$68.00
$70.00
$43,520.00
$8,960.00
$629,216.00
General Conditions Detailed Breakdown- (Other)
LS LS LS LS LS EA WK LS LS EA LS EA/mo LS LS LS LS
Weeks 13.0
960
Total Dollars
0 1 1 1 0
Days 91.0
0
Rate
Qty
10/31/2017
0
Total Hours
Item Job Organization Plan Reproduction Cost- Bidding Process Plan Reproduction - Construction Process Photo Equipment and Reports Closeout Documents CAD as Built Prints Dumpsters Safety/Security Materials- Consumables First Aid Supplies and Equipment Field office Supplies Computers and software Printers / Sacners/Equipement Phone lines / Internet Lines Inspections/Testing Survey/Layout Final Clean up Pro Core Project Management
PRE CON 8/1/2017 260
0%
Superintendent
APM
$/Unit
450/EA 50/WK
900/MO 900/MO 80/WK
150/phone/mo
30/WK
$
Notes
$0.00 $2,000.00 $250.00 $500.00 $0.00 $103,500.00 $1,300.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $15,000.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,700.00 $0.00 $2,560.00 $0.00 $0.00 $2,600.00 $0.00 $4,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $450.00 $0.00 $960.00 $0.00 $0.00 $0.00 $138,620.00
By Sub
Included in Cost of Work
TOTAL $767,836.00
PROJECT
ESTIMATE
M M- DESCRIBE WORK TO BE DONE HERE
DESCRIPTION Worksheet Unit AV
MAT'L QUANTITY
0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 SUBTOTAL TOTAL $/UN Subtotal GC
0
UNIT
UN UN EA UN UN EA EA UN UN UN EA UN EA UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN
0 UNIT
UNIT
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$/UN
LS
SHEET TOTAL Sheet Total $/UN
ADJUSTED UNIT PRICE
$75.19
0 UNIT
MH MATERIAL
-
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
UNIT
0.00 0.35 0.00 0.00 0.75 1.00 0.00 0.00 0.00 0.35 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0 #DIV/0!
EQUIP M.H.'s
-
LABOR
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
-
UNIT
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SUB EQUIP
-
UNIT
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL SUB
-
DIRECT COST
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
-
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
0
$0 #DIV/0!
$0 #DIV/0!
$0 #DIV/0!
$0
0
$0
$0
$0
$0
$0
$0
0
$0
$0
$0
$0
$0
$/UN
#DIV/0!
ManHrs
0.0
#DIV/0!
#DIV/0! Hours/Wk
#DIV/0!
40.0 0.0 ManWeeks Duration= 4.0 CrewSize
#DIV/0!
0.0 Crew Days
#DIV/0!
$0 #DIV/0!
#DIV/0!
0.0 Crew Weeks
HIDDEN COLUMNS
TOTAL O&P
-
COST
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0 #DIV/0!
$0.00 #DIV/0!
$0
$0.00
UNIT
-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
UN EA UN UN EA EA UN UN UN EA UN EA UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN UN
UNIT PRICE
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
HRS/DAY
DAYS
CREW
HRS/WEEK
MANWEEKS
CREW
8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 40
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
4.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
4.0
CREW DAYS
0.0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! CREW WEEKS
0.0
TOTAL Conc GENERAL CONDITIONS DESCRIPTION Job Organization Supervision Field Layout Service Truck Driver Testing Services TESTING UNIT OTHER Testing (Specify) Testing TCI Assit Equipment Cranes Forklift Bobcat Operator Equipment ( FOR SPECIALTY TRADE ) Pick-Up Truck Service Truck Generator - Portable BLANK Equipment Repair Small Tools Transit & Level & Radios Survey Supplies Site Communication Load In & Out Outside Freight Fuel & Oil Pick-Up Service Truck Small Tools
MH UNIT
MHRS 0 QTY
RATE
MTL MTL
$0
LABOR LABOR
$0
EQUIP $0 EQUIP
(Labor) (Labor) (Labor)
MH MH MH
0 0 0
$50 $79 $79
-
$0 $0 $0
-
(Labor)
UNIT LS MH
0 0 0
$0 $79
-
$0
-
(Labor)
(Labor)
DYS DYS DYS MH DYS DYS DYS DYS DYS DYS MH DYS DYS DYS MH LS
0 0 0 0 0.0 0.0 0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0
DYS DYS DYS
0.0 $ 0.00 $ 0.0 $
$ $ $ $ $ $ $ $ $ $ $ $
SUB SUB
$0 0 $0 $0 -
#DIV/0!
$0 TOTAL $0 $0 $0
Overheads as % of
Responsibilty
$0
Supervision as % of Total Direct Manhours
5.0% 2.5% 1.0%
$0 $0 $0
253 124 55 $78 20 25 34 7 7 $1.10 13 3 6 $75 $0
$0
$0 $0 -
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 -
-
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
22 26 6
$0 $0 $0
-
-
-
$0 $0 $0
UNIT PER TEST MNHRS/TEST Work days/MO
5% 0%
CY PER TEST 21.75
Monthly Ra Monthly Ra Monthly Ra
$5,500 $2,700 $1,200
Equipment ( FOR SPECIAL Monthly Ra Monthly Ra Pick-Up Truck Monthly Ra Service Truck Generator - Portable Monthly Ra BLANK Monthly Ra Equipment Repair Monthly Ra
$425 $550 $750 $150 $0 $150
Transit & Level & RadiosMonthly Ra Survey Supplies Monthly Ra Site Communication Monthly Ra
$275 $75 $120
Fuel & Oil Pick-Up Service Truck Small Tools
$475 $575 $125
Cranes Forklift Bobcat
Monthly Ra Monthly Ra Monthly Ra
C1
CONC FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM FORM PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE PLACE
PROJECT C1
FORM WASTE 5% Supplier - VenVendor Name 5% 4000 PSI MTL MH UNIT DESCRIPTION QTY UNIT UNIT MTL PURCHASE CONCRETE +yield% 0.0 CY 125.00 $0 0.000 SPREAD FOOTING 0.0 SF 1.00 $0 0.110 STRIP FOOTINGS 0.0 SF 0.85 $0 0.095 BASE SLAB 0.0 SF 0.95 $0 0.100 blank 0.0 SF 0.00 $0 0.000 0.0 SF 1.00 $0 0.090 WALLS-< 5.0' high WALLS-< 5.0' high (SMALL QTY) SF 1.35 $0 0.115 WALLS- > 5' < 16' SF 1.10 $0 0.085 WALLS (Gang Form) SF 0.80 $0 0.055 BULKHEADS/ Wall Const. JT SF 1.50 $0 0.150 BOXOUT (WALL AND SLAB) SF 1.20 $0 0.150 (SF) SOG EDGE >12" SF 1.10 $0 0.100 (SF) SOG CONSTRUCTION JT > 12" SF 1.00 $0 0.115 SOG/TOPPING EDGE < 12" LF 0.75 $0 0.070 SOG/TOPPING CONSTRUCTION JT < 12" LF 0.75 $0 0.090 S. SLAB EDGE & CONST JT< 1'-0" LF 0.75 $0 0.090 PIERS SF 1.00 $0 0.120 COLUMNS SF 1.00 $0 0.120 HOUSEKEEPING PADS LF 1.00 $0 0.140 SPECIALS (HAUNCHES COBELS ETC) SF 1.75 $0 0.200 STOOP FOOTINGS/ SLAB EDGE--walls w/ sm qty wal SF 1.20 $0 0.125 blank 0.0 SF #REF! #REF! #REF! blank 0.0 SF #REF! #REF! #REF! blank 0.0 SF #REF! #REF! #REF! blank 0.0 SF #REF! #REF! #REF! blank 0.0 SF #REF! #REF! #REF! blank 0.0 SF #REF! #REF! #REF! STAIR RISERS LF 1.20 $0 0.125 SUPPORTED SLAB(SOFFIT) SF 0.90 $0 0.050 SUPPORTED SLAB EDGE > 1'-0" SF 1.00 $0 0.120 SUPPORTED SLAB (ADJ JTS & PURLINGS SF 2.00 $0 0.180 SUPPORTED SLAB SHORING LF 15.00 $0 0.500 BEAM BTTM w/Purlins SF 2.50 $0 0.200 BEAM SIDES SF 1.00 $0 0.125 BEAM SHORING LF 15.00 $0 0.750 WASTE @ x% of total SF (SUMC7:C31)*G 0.0 UNS 1.00 $0 #REF! FOOTINGS 0.0 CY #REF! #REF! 0.400 BASE SLAB CY #REF! #REF! 0.350 CY #REF! #REF! #REF! #REF! WALLS-< 5.0' high CY #REF! #REF! 0.650 WALLS- > 5' < 16' CY #REF! #REF! 0.700 SM QTY WALLS CY 0.00 $0 1.250 SUPPORTED SLAB CY #REF! #REF! 0.800 MISCELLANEOUS ITEMS CY #REF! #REF! 1.500 SLABS ON GRADE CY #REF! #REF! 0.800 HOUSEKEEPING PADS CY #REF! #REF! 2.000 STOOPS:FTGS/WALLS/SLABS CY 0.00 $0 1.250 blank CY 0.00 $0 #REF! blank CY 0.00 $0 0.000 blank CY #REF! #REF! 0.000 blank CY 0.00 $0 0.000 blank CY 0.00 $0 0.000
ESTIMATE Composite Labor Rate $56.00 1 M.H.'s 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 #REF! #REF! #REF! #REF! #REF! #REF! 0 0 0 0 0 0 0 0 #REF! 0 0 #REF! 0 0 0 0 0 0 0 0 #REF! 0 0 0 0
LABOR $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! #REF! #REF! #REF! #REF! #REF! $0 $0 $0 $0 $0 $0 $0 $0 #REF! $0 $0 #REF! $0 $0 $0 $0 $0 $0 $0 $0 #REF! $0 $0 $0 $0
EQUIP $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Pumping $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Concrete Pumping Unit Price-per CY this sheet #DIV/0! $0 TOTAL SUB DIRECT COST $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 $0 $0 #REF! $0 #REF! $0 #REF! $0 #REF! $0 $0 $0 #REF! $0 $0 $0 #REF! $0 $0 $0 $0
O&P
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL COST $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #REF! #REF! #REF! #REF! #REF! #REF! $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #REF! #REF! #REF! #REF! #REF! #REF! $0.00 #REF! #REF! #REF! #REF! $0.00 #REF! $0.00 #REF! $0.00 $0.00
ADJUSTED
HIDDEN
UNIT PRICE
COLUMNS
ADJUSTED UNIT UNIT PRICE UNIT PRICE 0 CY $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 $0.00 $0.00 0 SF 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 $0.00 $0.00 0 SF 0 LF $0.00 $0.00 $0.00 0 LF $0.00 0 LF $0.00 $0.00 $0.00 $0.00 0 SF 0 SF $0.00 $0.00 0 LF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 $0.00 $0.00 0 SF 0 SF $0.00 $0.00 $0.00 $0.00 0 SF 0 SF $0.00 $0.00 $0.00 $0.00 0 SF 0 SF $0.00 $0.00 0 LF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 SF $0.00 $0.00 0 LF $0.00 $0.00 $0.00 0 SF $0.00 0 SF $0.00 $0.00 $0.00 $0.00 0 LF 0 UNS $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00 $0.00 $0.00 0 CY 0 CY $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00 $0.00 $0.00 0 CY 0 CY $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00 $0.00 $0.00 0 CY 0 CY $0.00 $0.00 0 CY $0.00 $0.00 0 CY $0.00 $0.00
TOTAL BID $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
HRS/DAY
8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0
DAYS
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! 0.0 0.0 #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! 0.0 0.0 0.0 0.0
CREW
4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
CREW DAYS
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! 0.0 0.0 #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! 0.0 0.0 0.0 0.0
Pumping $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00 $12.00
FINISH FINISH FINISH FINISH FINISH FINISH FINISH FINISH FINISH FINISH FINISH SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM SF ITEM
EMBED EMBED EMBED EMBED EMBED EMBED EMBED MISC MISC MISC MISC MISC MISC MISC MISC MISC MISC MISC MISC MISC EXC EXC EXC EXC RESTL RESTL RESTL MISC
FOOTINGS BASE SLAB SLABS ON GRADE blank STRUCTURAL SLAB TOPPINGS blank blank STAIR TREAD & RISER MISCELLANEOUS ITEMS MISC SM AREA (ie TOPS OF WALLS) POINT & PATCH (SUMC7:C31) RUB EXPOSED CONC CURE (SUMC7:C31+C49:C56) SEALER / CHEM HARDENER F&I EXPANSION JOINT FINE GRADE (SUMC58:C61) VAPOR BARRIER blank blank blank blank PREP CONSTRUCTION JOINT INSTALL EMBED ANCHOR BOLTS INSTALL EMBED ANGLES INSTALL EMBED PLATES INSTALL PIPE SLEEVES blank blank blank SAWCUT CONTROL JTS CAULKING WATERSTOP DRILL AND EPOXY DWLS < #6 blank blank blank blank blank blank blank blank BOLLARDS Wdrilling/conc/place pipe HAND EXCAVATION EXCAVATION BACKFILL GRADE F&I REINFORCING STEEL F&I MESH 6x6 10/10 F&I MESH (other) REBAR SUPPORTS@ 1ea/25sf
0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF EA LF EA EA EA EA EA LF LF LF EA EA EA EA EA EA EA EA EA EA CY CY CY SY TN SF SF EA
0.00 0.00 0.00 #REF! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.08 0.02 0.10 0.65 0.00 0.03 #REF! #REF! 0.00 0.00 0.05 1.00 1.00 1.00 1.00 #REF! #REF! #REF! 0.35 0.25 1.75 2.50 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 25.00 #REF! #REF! #REF! #REF! 870.00 0.10 0.14 0.50
SUBTOTAL DIRECTS Directs $/UN Subtotal GC
0
0 CY
$/CY
LS
SHEET TOTAL Sheet Total $/UN
0 CY
$/CY
$0 $0 $0 #REF! $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! #REF! $0 $0 $0 $0 $0 $0 $0 #REF! #REF! #REF! $0 $0 $0 $0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0 #REF! #REF! #REF! #REF! $0 $0 $0 $0
0.003 0.010 0.010 #REF! 0.010 0.010 #REF! #REF! 0.060 0.050 0.035 0.001 0.025 0.001 0.001 0.012 0.003 0.001 #REF! #REF! 0.000 0.000 0.015 0.200 0.125 0.200 1.000 #REF! #REF! #REF! 0.020 0.015 0.025 0.120 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 1.500 1.500 #REF! #REF! #REF! #REF! #REF! #REF! 0.010
0 0 0 #REF! 0 0 #REF! #REF! 0 0 0 0 0 0 0 0 0 0 #REF! #REF! 0 0 0 0 0 0 0 #REF! #REF! #REF! 0 0 0 0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0 0 #REF! #REF! #REF! #REF! #REF! #REF! 0
#REF! #REF! #REF!
#REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0
$0 $0
$0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0 $0 $0 #REF! $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0 $0 #REF! $0 $0 $0 $0 #REF!
#REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
$0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0.00 $0.00 $0.00 #REF! $0.00 $0.00 #REF! #REF! $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#DIV/0!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
$0
$0 #DIV/0!
#REF!
#REF! #REF!
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF EA LF EA EA EA EA EA LF LF LF EA EA EA EA EA EA EA EA EA EA CY CY CY SY TN SF SF EA
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0
0.0 0.0 0.0 #REF! 0.0 0.0 #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! #REF! 0.0 0.0 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF!
4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
0.0 0.0 0.0 #REF! 0.0 0.0 #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! 0.0 0.0 0.0 0.0 0.0 0.0 0.0 #REF! #REF! #REF! 0.0 0.0 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF!
HRS/WEEK
MANWEEKS
CREW
CREW WEEKS
$0.00
40.0
#REF!
4.0
#REF!
CONCRETE MTL (6) FORMS (7-33)+C41 FORMS SUPPORTED DECK/BEAM (34 FORM FORMS SHORING (37,40) PLACE CONCRETE (42-57) FINISH FINISHES (59-68) SQUARE FOOT ITEMS (69-80) EMBED EMBEDDED ITEMS (81-87) MISCELLANEOUS ITEMS (88-100) EXC EXCAVATION (101-104) REINFORCING STEEL (105&108) MESH (106-107) MISC CONCRETE PUMPING (J106-J57) CONC FORM
QTY
0 0 0 0 0 0 0 0 0 0 0 0 0
UNIT CY SF SF LF CY SF SF LF LS CY TN SF CY
MTL UNIT $125.00 #REF! #DIV/0! #DIV/0! #REF! #REF! #REF! #REF! #REF! #REF! #DIV/0! #DIV/0! #DIV/0!
MTL #REF! $0 $ #REF! #REF! #REF! #REF! #REF! #REF! $ $ $
#REF! #REF!
ManHrs
1.5% 2.0% 5.0% 2.5% 1.0% 50 0.50
@ 20%
2% 8%
TOTAL Conc GENERAL CONDITIONS DESCRIPTION Job Organization Project Manager Overhead General Superintendent Overhead Supervision (Labor) Field Layout (Labor) Service Truck Driver (Labor) Testing Services Concrete OTHER Testing (Specify) Concrete Testing TCI (Labor) Equipment Cranes Forklift Bobcat 0 Operator (Labor) 0 Concrete Equipment SW 1 Pick-Up Truck SW 1 Service Truck SW 1 Generator - Portable SW 1 Concrete Troweling Machine SW 1 Equipment Repair SW 1 Small Tools SW 1 Transit & Level & Radios SW 1 Survey Supplies SW 1 Site Communication SW 1 Load In & Out (Labor) Outside Freight Fuel & Oil Pick-Up SW 1 Service Truck SW 1 Small Tools SW 1 Field Offices Office Trailer SW 0 Arch/Engr/Owner Trailer SW 0 Storage & Lunch Trailers SW 0 Office Supplies & Drwg Repro SW 0 Office Equip. Computer, fax, etc SW 0 Telephones SW 0 Electric SW 0 Heat #EA 0 Toilets # EA 0 Trailer Set-Up (Labor) Job Utilities & Expense Temp Elec - Sub Hook-Up Temp Light & Power SW 0 Temp Drinking Water/Ice SW 1 Temp Roads Temp Site Sign Temp Fences Temp Stairs & Ladders Temp Snow Plow Rmvl - Sub Job General Clean-Up (Labor) Clean-Up Supplies Dumpsters
MH UNIT
MHRS #REF! QTY
MH MH MH MH MH
#REF! #REF! #REF! #REF! #REF!
RATE
MH UNIT 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Hours/Wk
M.H.'s LABOR 0 $ #REF! #REF! 0 $0 0 $ #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 40.0 #REF! 4.0 CrewSize MTL LABOR #REF! #REF! MTL LABOR
$ $ $ $ $
$ $ $
EQUIP $0 #REF! #REF! #REF! #REF! #REF!
ManWeeks Duration=
$ $ $ $ $
$
TOTAL DIRECT COST $ #REF! $0 $0 $ #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! $ #REF! $ #REF! #REF! #REF! SUB
-
#REF! SUB #REF! SUB
EQUIP #REF! EQUIP
O&P
-
$0 $0 $0 $0 $0 $0 0 0 0 $0
Crew Days
#REF!
#REF! TOTAL
#REF!
TOTAL COST $0.00 #REF! $0.00 $0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
0 0 0 0 0 0 0 0 0 0 0 0 0
CY SF SF LF CY SF SF LF LS CY TN SF CY
UNIT PRICE $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
MH/ UNIT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL BID $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0
HRS/WEEK
MANWEEKS
CREW
CREW WEEKS
40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0
#REF! 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0
4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
#REF! 0.0 0.0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0
Crew Weeks #REF!
CHECK
UNIT
Overheads as % of
Responsibilty Supervision as % of Total Direct Manhours
0 0 0
CY LS MH
$
$65 $55 $50 $60 $60
-
4.50 $10 $60
-
DYS DYS DYS MH DYS DYS DYS DYS DYS DYS MH DYS DYS DYS MH LS
0 $ 234 0 $ 113 #REF! $ 83 #REF! $59 #REF! $ 22 $ 38 #REF! #REF! $ 55 #REF! $ 7 #REF! $ 25 #REF! $ 7 #REF! $ 1.10 #REF! $ 13 #REF! $ 7 #REF! $ 10 #REF! $56 1 #REF!
#REF!
DYS DYS DYS
#REF! #REF! #REF!
#REF! #REF! #REF!
MO MO MO MO MO MO MO MO MO MH
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
LS MO DYS SY LS LF EA EA MH LS EA
#REF! #REF!
$ $ $
0 0 0 0 0 0 0 0 0 0
31 37 8 $250 $350 $150 $75 $150 $135 $150 $150 $120 $56 $1,200 $300 $2 $5 $600 $3 $150 $150 $56 $50 $300
#REF! #REF! #REF! #REF! #REF!
-
-
-
#REF! #REF! $0 $0 $0 $0 $0 $0
#REF! #REF! #REF!
#REF!
#REF!
-
-
$0
-
-
#REF!
-
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
$0 $0
#REF! #REF!
-
#REF! #REF! #REF! #REF! #REF!
$0 $0 -
-
-
-
-
-
-
#REF! #REF! #REF!
$0
#REF! #REF! #REF! #REF! -
-
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
$0 -
-
$0 $0 -
-
#REF! $0 $0 $0
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF!
$0
$0 $0
#REF!
#REF!
Concrete Equipment Pick-Up Truck Service Truck Generator - Portable Concrete Troweling Machine Equipment Repair
SW SW SW SW SW SW
Transit & Level & Radios Survey Supplies Site Communication
SW SW SW
Fuel & Oil Pick-Up SW Service Truck SW Small Tools SW Field Offices Office Trailer SW Arch/Engr/Owner Trailer SW Storage & Lunch Trailers SW Office Supplies & Drwg Repro SW Office Equip. Computer, fax, etc SW Telephones SW Electric SW Heat #EA Toilets # EA
Monthly Rates Monthly Rates Monthly Rates
$5,100 $2,450 $1,800
Monthly Monthly Monthly Monthly Monthly
Rates Rates Rates Rates Rates
$475 $825 $1,200 $150 $550 $150
Monthly Monthly Monthly Monthly
Rates Rates Rates Rates
$275 $150 $210
Monthly Rates Monthly Rates Monthly Rates
$665 $805 $175
Monthly Monthly Monthly Monthly Monthly Monthly Monthly Monthly Monthly
$250 $350 $150 $75 $150 $135 $150 $150 $120
Rates Rates Rates Rates Rates Rates Rates Rates Rates
#REF! #REF! #REF!
Job Utilities & Expense
$0 $0 $0 $0 $0 $0 $0 $0 $0
21.75
Cranes Forklift Bobcat
#REF!
$0
CY PER TEST MNHRS/TEST Work days/MO
Temp Light & Power Temp Drinking Water/Ice
#REF!
SW SW
Monthly Rates DAILY Rates
$300 $2
Winter Protection 29% Heated Concrete CY 0 $ Winter Protect (Labor) MH 0 $56 Snow Removal (Labor) MH 0 $56 Heaters & Hose EA 0 $500 Propane GL 0 $1 50% Blankets (Slab area + form area x A194,%form 0 SF 0 $0.05 150% Ground thaw (Ftg area x A195, % Oversize) 0 LS 0 $950 Insurance SEE PROJECT GENERAL CONDITIONS Builder's Risk LS $0 Owner's Protect Liability LS $0 Umbrella LS OCP LS Additional G & L on Subs LS Special Taxes & Permits SEE PROJECT GENERAL CONDITIONS Building Permit LS 0 $0 Special Licenses/Fees LS 0 $0 SAC, WAC LS 0 $0 Park Development Fees LS 0 $0 Special Taxes (City, County or State) LS 0 $0 Office/Special Expense Supervisery (Bonus/Holiday) DYS 0 $ 230 Professional Engineer - forms LS 0 $0 BLANK LS 0 $0 Employee Parking LS 0 $0 Office Travel (Parking, Car Allow, Etc.) MO 0 $ 500 Quality Control Program LS 0 $ 2,500 H/ X No.of D Safety programs MH #REF! 0 640 Drug Testing ( 1MH/ X No.of DMHS) EA #REF! $ 75 640 Safety Orientation ( 1MH/ X No.of DMHS) (Labor) MH #REF! $ 46.95
$0 $0 $0 $0 $0
$0 $0 -
-
-
$0 $0 $0 $0 $0 $0 $0
$0
-
-
-
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0 $0 $0 $0 $0
-
-
-
$0 $0 $0 $0 $0
$0
-
-
-
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
#REF!
#REF! #REF!
-
#REF! #REF! #REF!
#REF!