Banbridge Public Realm –Current Works

Phase1–TrafficRestrictions

Works

PLANNED WORKS –SCARVA ST
atHouston’sCorner+Downshire Bridge Commencing24th June–2nd July

Areashighlightedinyellow showavailableparking

Phase1-CarParking

WorksatHouston’sCorner+Downshire Bridge

Commencing24th June–2nd July

PLANNED WORKS –SCARVA ST

Phase2–TrafficRestrictions

WorksatDownshireBridge+Opticians 2nd July–5th July PLANNED WORKS –SCARVA ST

Areashighlightedinyellow showavailableparking

2nd July–5th July PLANNED WORKS –SCARVA ST
Phase2–CarParking WorksatDownshireBridge+Opticians

Phase3–TrafficRestrictions

Worksalong
8th July–26th July PLANNED WORKS –SCARVA ST
ScarvaSt(includesParking Bays)

Phase3–CarParking

WorksalongScarvaSt(includesParking Bays)

Areashighlightedinyellow showavailableparking

8th July–26th July PLANNED WORKS –SCARVA ST
Followtheprojectupdates ConanL@fox-contracts.com +44786570328 Fox-contracts.com ANY QUESTIONS?