Westminster Mobility Action Plan

Page 1

SUMMER 2016

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

SPRING 2017


Page intentionally left blank


TABLE OF CONTENTS I. Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1 1.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1 1.2 Plan Vision and Goals. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2 1.3 Planning Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3 1.4 Recommendations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4 1.5 Next Steps. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5

IV. Recommendations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1 4.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-1 4.2 Overall Recommendations. . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1 4.3 Project Prioritization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-9 4.4 Cost Estimates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10 4.5 Funding Sources. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-11

II. Existing Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1 2.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1 2.2 Pedestrian Facilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-6 2.3 Shared Use Paths and Trails. . . . . . . . . . . . . . . . . . . . . . . . . 2-14 2.4 On-Street Bicycle Facilities. . . . . . . . . . . . . . . . . . . . . . . . . . 2-17 2.5 Transit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-19 2.6 Roadways and Traffic. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-23

IV. Demonstration Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1 5.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5-1 5.2 Demonstration Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-2

III. Needs Assessment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1 3.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-1 3.2 Multimodal Suitability Index . . . . . . . . . . . . . . . . . . . . . . . . . 3-2 3.3 Pedestrian and Bicycle Collisions . . . . . . . . . . . . . . . . . . . 3-11 3.4 Stakeholder and Public Outreach. . . . . . . . . . . . . . . . . . . 3-14 3.5 Needs Assessment Conclusion. . . . . . . . . . . . . . . . . . . . . 3-21

Appendix. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix A: Project Recommendation Tables . . . . . . . . . . . . . .A Appendix B: Past Plan Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . .B Appendix C: Online Survey Summary. . . . . . . . . . . . . . . . . . . . . . .C Appendix D: Demonstration Project Cost Estimates. . . . . . .D

PROJECT PARTIES The City of Westminster

Consultant Team

Gabriella Arismendi, Project Manager Christine Gray, Project Advisor Debra Baskett, Project Advisor

Alta Planning + Design Joe Gilpin, Principal in Charge Sam Piper, Project Manager Charles Creagh, Project Planner Chloe Ward, Project Engineer Erin David, GIS Specialist

Atkins Andrew Iltis, Senior Transportation Planner


Page intentionally left blank


CHAPTER 1: EXECUTIVE SUMMARY


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

This Mobility Action Plan is intended to guide decisions about when, where, why, and how to enable active living, improve safety, and stimulate economic development through strategic investments in walking and bicycling infrastructure and enhanced transit connections. 1.1 INTRODUCTION comprehensive assessment of strategies to improve the safety, convenience, and enjoyment of walking, bicycling, and taking transit in the city. The Plan builds directly upon other recent planning efforts, and was developed in collaboration with City Staff, local stakeholders, and the general public. The Plan is an Action Plan, intended to guide decisions and investments about when, where, why, and how to develop a transportation network that provides true mobility choice by prioritizing bicycle and pedestrian improvements in Westminster. The plan’s recommendations, once implemented, will help connect the community, provide realistic and safe travel options for residents, and take advantage of great community assets, such as the new Downtown Westminster, RTD B Line at Westminster Station, the U.S. 36 bus rapid transit, and the community’s numerous parks, trails, shopping destinations and more.

Westminster is a city on the move. The city’s central location between Denver and Boulder has driven its development and population growth, and thousands of residents, employees, and visitors walk, bicycle, take transit, carpool and drive in the community daily. In the past, transportation improvements in the city focused primarily on improving access for motor vehicles. Simultaneously, the City developed a robust trail network with a primarily recreational focus. In recent years, communities across the United States, including Westminster, have recognized the benefits of developing connected networks that facilitate active modes of transportation, such as walking and bicycling, and have begun to prioritize investments in these modes. A well-connected multimodal transportation network, where people have convenient access to transit, sidewalks, bikeway facilities, and multi-use trails, requires intentional planning. MAP Westminster, Westminster’s Mobility Action Plan, is the result of a

1-1 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

1.2 PLAN VISION AND GOALS A vision statement outlines what the city wants to be. It concentrates on the future and is a source of inspiration. The following vision statement, developed in coordination with the Project Steering Committee and the public, guides MAP Westminster:

MAP WESTMINSTER VISION: The City of Westminster delivers walking, bicycling, transit, driving and carpooling options that support active living for people of all ages and abilities, provide for safer and healthy transportation, and improve the economic and physical health of the City and its citizens. MAP Westminster Goals

Goals help guide the City towards fulfilling the Project Vision, and relate to existing and newly-launched efforts. The following goals, developed through the planning process, will serve to guide the implementation of MAP Westminster. Goal 1: Experience – Deliver a walking, bicycling, transit and driving environment that is attractive and low-stress for all modes of transportation. Goal 2: Safety - Improve walking and bicycling safety through the design and maintenance of roadway improvements. Goal 3: Connectivity - Develop a balanced transportation system that includes convenient mobility options that enable citizens of all ages and abilities to access community and regional destinations easily and comfortably. Goal 4: Health and Economics - Prioritize increasing multimodal trips, reducing the need to own or drive a personal vehicle to improve local air quality, economics, overall health and quality of life in Westminster. Goal 5: Programs – Create a culture that supports walking, bicycling, transit and ridesharing use by increasing the awareness and value of these modes through education, encouragement, enforcement, evaluation, and equity programs. The implementation of MAP Westminster will help the City continue to become a community that offers true mobility choice

Goal 6: Regional Collaboration - Prioritize the leveraging of funding for multimodal infrastructure, and combine multimodal improvements with other capital improvement projects to continually implement the plan’s recommendations to immediately enhance multimodal options in Westminster.

1-2 Chapter 1: Executive Summary


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

1.3 PLANNING PROCESS The process for developing the plan’s recommendations was divided into three phases: Existing Conditions Analysis, Needs Assessment, and Recommendations. The existing conditions analysis resulted in a thorough understanding of what it is like to walk, bicycle, access transit and drive in Westminster today. The Needs Assessment built on this foundation, and identified where there is demand for multimodal transportation, and assessed the supply of facilities that link these areas. Recommendations were developed following the conclusion of the needs analysis. Being a Mobility Action Plan, the recommendations focus on projects that fill critical gaps in the network to improve mobility for pedestrians, bicyclists and transit users. Specific emphasis was also placed on improving connections to the community’s assets, including Downtown Westminster, Westminster Station, the bus rapid transit (BRT) line along U.S. 36, and the city’s numerous parks, trails, shopping destinations and more.

1.4.1 Recommendations The development of the network recommendations was an iterative and collaborative process. The needs of all roadway users, including the safety and comfort of people walking, bicycling, accessing transit, and driving, must be balanced with roadway characteristics and corridor constraints. The Plan’s recommendations provide guidance that can be used to progress projects towards implementation. Some recommendations are conceptual, and additional coordination will be needed for implementation.

NETWORK RECOMMENDATIONS DEVELOPMENT

1

EXISTING CONDITIONS ANALYSIS

EXISTING FACILITIES

2

DESTINATIONS

BARRIERS

COMMUNITY IDENTIFIED NEEDS

FACILITY CONNECTIVITY GAPS

LEVEL OF TRAFFIC STRESS

CONNECT ACTIVITY CENTERS

ADDRESS BARRIERS

NEEDS ANALYSIS

MAPPING CRASH DATA

3

PREVIOUSLY PROPOSED FACILITIES

RECOMMENDATIONS DEVELOPMENT

REVISE PREVIOUSLY PROPOSED

In total, over 80 recommended projects are identified in this Plan. To support implementation, planning level cost estimates were prepared for these projects, and the projects were prioritized. The Plan concludes with a presentation of five demonstration projects that can be implemented in the short term to immediately improve mobility in key areas of Westminster. For these projects, conceptual diagrams of proposed improvements were prepared to advance them towards implementation.

1-3 Westminster’s Mobility Action Plan

CONNECT NETWORK GAPS


WESTMINSTER’S MOBILITY ACTION PLAN

ZUNI ST

LOWELL BD

MAPWESTMINSTER

WESTLAKE DR

ASPEN ST

136T

V TH A

134

Cree Dr y Big 128

MAP 1.1: DEMONSTRATION PROJECT LOCATIONS 10TH AV 10TH AV AL

MIDWAY BD

LN

MAIN ST

TRI

ST

US

L KOH

IND

124

L PY

ERA

FED

128

120TH AV

Cre ek

Tra il

36

PECOS ST

128

287

Dr y

121

IFF

96TH AV

DR

E NC

DE

EN

EP

IND

PY

FEDERAL BLVD

ST CL

LOWELL BD

Farm

WE

ek T rail

ER FLY

Cre

H ers’ ig h

104TH AV

SHERIDAN BLVD

Ch

rai l anal T

L ine C

anc h R h Bl v d

N IRO AT 36

S TA N D L E Y L A K E

ALKIRE ST

92ND AV

DOWNTOWN WESTMINSTER

Farmers’ High Line Canal Trail

DR

ay ew Bik

E AS

Creek Tra

DR

il

80TH AV

Litt

DEMONSTRATION PROJECT LOCATIONS US-36 Ramp Crossing Improvements Sheridan Station Access Improvement Public Access to City Services Improvements

le D

74TH AV

ry C

ree k

WESTMINSTER STATION

CARR ST

95

LOWELL BD

Chapter RALSTON RD 1: Executive Summary

TENNYSN ST

121

SHERIDAN BLVD

1-4

LAMAR ST

GARRISON ST

ING S T

72ND AV

E LIN

58TH AV

74TH AV

Tra il

B RTD

64TH AV

T

76

76TH AV

69TH AV

68TH AV

Church Ranch BRT66TH Station Access Improvements AV Promenade Sidepath Connector

BRADBURN BD

DR

PIERCE ST

R

R CA

WADSWORTH BD

SIMMS ST

KIPLING ST

80TH AV

72ND AV

88

84TH AV

36

84TH AV

CH

Little Dry

121

LA MA R

86TH P Y

88TH AV

SHERIDAN STATION US

GARRISON ST

88TH AV

PECOS ST

Standley Lake Regional Park

Farmers’ High Line Canal Trail

100TH AV

Dr y

Westminster City Park

FL

Big

Farmers’ High Line Canal Trail

CHURCH RANCH

104TH AV

ur c

OA K

ST

JOHNSON ST

SIMMS ST

W 108TH AV

ZUNI ST

Trail Walnut Creek

WADSWORTH BD

B ig

112TH AV

287

76


L PY

ERA

FED

128

WAGON PARK A RIDE

Big

Dr y

121

HURON ST

Cre ek Tra il

36

PECOS ST

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

120TH AV

128

287

in

IFF

36

88TH AV

88TH AV

121

R

R

ED

Trail

80TH AV

1 Mile

WADSWORTH BD

PIERCE ST

WESTMINSTER STATION

69TH AV

68TH AV

CARR ST

72ND AV

95

70TH AV

RTD

68TH AV

BL

INE

Existing Conditions

64TH AV

LOWELL BD

TENNYSN ST

G ST

SHERIDAN BLVD

121 RALSTON RD

LAMAR ST

62

GARRISON ST

0.5

74TH AV

Tra il

287

76

KIPLIN

0

ree k

BD

64TH AV

ry C

AV

OD

Representative Photo Simulation US 36 and Federal Boulevard, westbound off-ramp

58TH AV

le D

PROJECT LOCATION

TH

76

76TH AV

WO

Litt 74TH AV

BRADBURN BD

CA

EEN

SIMMS ST

RR

DR

GR

KIPLING ST

80TH AV

66TH AV

PECOS ST

y wa ike

LA MA RD

84TH AV

6B

84TH AV

1  Ramp crossing improvements for the US 36 and Church Ranch Boulevard West 72 Ramps and US 36 and Sheridan Boulevard North East Ramp are detailed in the 2017 Federal Highway Safety Program (HSIP) application. The design for the US 36 72ND AV and Church Ranch Boulevard West Ramps should be replicated on the East Ramp.

88TH AV

SHERIDAN STATION 3 US

GARRISON ST

ALKIRE ST

92ND AV

DOWNTOWN WESTMINSTER

AS

y Creek

96TH AV

CH

Little Dr

PY

R LYE

ST CL

HURON ST

L ine C

WE

104TH AV

LOWELL BD

Farm

ur c

H ers’ ig h

NF IRO AT

anc h R h Bl v d

rai l anal T FL

INDIANA ST

Westminster City Park

Farmers’ High Line Canal Trail

104TH AV

US 36 travels north/south through Westminster, and many of the city’s major destinations and transit hubs are located along Ch 100TH AV the corridor. This project aims to improve pedestrianBigcrossing Dr y Cre ek T rail Standley Lake Park conditions where the US 36 on- and Regional off-ramps intersect Church AV 96TH Ranch Boulevard/104th Avenue, Sheridan Boulevard, and DENCEDR EN EP IND Federal Boulevard. Improvements at the ramp crossings vary S TA N D L E Y L A K E by location, but in general, they are focused on increasing the Farmers’ High Line Canal Trail visibility of pedestrians, slowing vehicles as they exit and enter the ramps, and increasing the yield compliance of vehicles when 86TH PY pedestrians are attempting to cross the roadway.1

rail nal T e Ca

CHURCH RANCH

SHERIDAN BLVD

OA KS

T

JOHNSON ST

Project Overview

W 108TH AV

108TH AV

’ Hig L Far m ers h

ZUNI ST

Tra Walnut Creek

FEDERAL BLVD

il

SIMMS ST

US 36 Ramp Crossing Improvements

WADSWORTH BD

112TH AV

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Summer 2016

N

OVERVIEW MAP

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

1-5 Westminster’s Mobility Action Plan

Autho


104TH AV

IFF

DR

CE Flatiron Flyer Bus Rapid Sheridan Station provides access toENthe D N Transit (BRT) line as well as Elocal bus service, and is adjacent PE ND I to Downtown Westminster. Additionally, the US 36 Bikeway Station and then crosses 88th Avenue E connects Y L AtoKSheridan E at-grade and continues north. Improving access between Sheridan Station, the US 36 Bikeway and High Downtown Westminster at 88th Line Canal Trail Farmers’ Avenue will make bicycling and walking between these destinations more comfortable. The improvements at this location are detailed in the city’s 2017 CDOT Highway Safety Improvement Program application. Improvements are focused on increasing 121 the visibility of pedestrians, slowing vehicles as they exit and enter the ramps, and increasing the yield compliance 84TH AV of vehicles when pedestrians are attempting to cross the roadway. The project includes the construction of a raised crosswalk, as displayed in the Little Dr y Creek photo simulation below. Tra

36

92ND AV

DOWNTOWN WESTMINSTER

88TH AV

SHERIDAN STATION US

GARRISON ST

36 ay ew Bik

PROJECT LOCATION

il

R

PIERCE ST

ree k

74TH AV

Tra il

72ND AV

69TH AV

68TH AV

WESTMINS STATION

RALSTON RD

1-6 Chapter 1: Executive Summary

SHERIDAN BLVD

121

LAMAR ST

64TH AV

KIPLI NG S

STMINSTER

ry C

76TH AV

95

GARRISON ST

64TH AV

T

le D

74TH AV

CARR ST

66TH AV

58TH AV

Existing Conditions

Litt WADSWORTH BD

SIMMS ST

KIPLING ST

Representative Photo Simulation - RR D CA Access Improvements 88th Avenue at Sheridan Boulevard

LOWELL BD

DL

PY

LOWELL BD

ST CL

ER FLY

Project Overview

WE

BRADBURN BD

Farm

Dry Bus Rapid Transit Station Sheridan Cre ek T rail Access Improvements

H ers’ ig h

ON TIR FL A

Ch

100TH AV

Big

anc h R h Bl v d

TENNYSN ST

ur c

WESTMINSTER’S MOBILITY ACTION PLAN

rai l anal T

L ine C

MAPWESTMINSTER

104TH AV

SHERIDAN BLVD

OA K

ST

N ST

City Park

Farmers’ High Line Canal Trail


DR

Project OverviewCE

EN

D Yates Street EN provides an important connection between P E Station and the city’s public services, located within Sheridan IND the city hall campus. In addition, there is pedestrian crossing demand between the city hall campus and Westminster Center Park at Xavier Street and 92nd Avenue, but a marked crossing at this location does not exist. This project includes pedestrian Trailthree locations. Each will improve High Line Canalat Farmers’ access improvements connectivity to the city hall campus. The improvements include installing a Pedestrian Hybrid Beacon and marked crosswalk at 92nd Avenue and Xavier Street, installing a mid-block crosswalk at Yates Street and 91st Avenue, and making 88th Place and Yates Street a four-way stop-controlled intersection 121 with marked crosswalks. Additional details of these improvements are provided on the conceptual plan illustrations and 84TH AV photosimulations.

DOWNTOWN WESTMINSTER

92ND AV CITY HALL CAMPUS

88TH AV

SHERIDAN STATION

GARRISON ST

E

36

LOWELL BD

Public Access to City Services Improvements

SHERIDAN BLVD

ek T rail

WESTMINSTER’S MOBILITY ACTION PLAN

H ers’ ig h

YATES ST

MAPWESTMINSTER

Cre

L ine

Ch

100TH AV

Farm

ur c

anc h R h Bl v d

PROJECT LOCATION y Creek

DR

CA

ree k

74

Tra il

72

68TH AV

WE 95

1-7

Westminster’s Mobility Action Plan

RALSTON RD

HERIDAN BLVD

121

LAMAR ST

64TH AV

GARRISON ST

T

ry C

69TH AV

CARR ST

66TH AV

le D

74TH AV

PIERCE ST

WADSWORTH BD

Litt

76

LOWELL BD

RR

Existing Conditions

BRADBURN BD

KIPLING ST

Trail Representative Photo Simulation Yates Street and West 88th Place

TENNYSN ST

Little Dr


128

MAPWESTMINSTER

128

287

WESTMINSTER’S MOBILITY ACTION PLAN

36

Church Ranch Bus Rapid Transit Station Access Improvements

121

112TH AV

WADSWORTH BD

Westminster City Park

Standley Lake Regional Park

Dr y

Farm

ur c

Big

Cre

ek T rail

96TH AV

104TH AV

R LYE y N F ewa IRO Bik AT S 36 FL U

L ine C

OA K

ST

JOHNSON ST

SIMMS ST

The recently constructed Bus Rapid Transit Trail (BRT) stations in Walnut Creek Westminster provide new mobility options for people in the city. 108TH AV CHURCH W 108TH AV Currently, there is no sidewalk leading from 104th Avenue to RANCH Church Ranch BRT Station on the east side of US 36, and while a sidewalk does exist on the west side, it is circuitous and pedestrians have been observed walking along the grass to the station,104TH AV rai l as this route is more direct. This project would construct direct anal T n a c sidewalk connections to the station platforms on both sides of US h R h Bl v d H 36 from 104th Avenue north to the stations. Ch ers’ ig h

SHERIDAN BLVD

Project Overview

PROJECT LOCATION

ALKIRE ST

S TA N D L E Y L A K E

92ND AV

Representative Photo Simulation West Side Sidewalk

CITY HALL CAMPUS

DOWNTOWN WESTMINSTER

Farmers’ High Line Canal Trail

88TH AV

GARRISON ST

Existing Conditions

86TH PY

Little Dry

121 84TH AV

Creek Tr ail

Litt

72ND AV

0.5

1 Mile

69TH AV

95

RALSTON RD

Chapter 1: Executive Summary

LAMAR ST

TENNYSN ST

1-8

121

SHERIDAN BLVD

G ST KIPLIN

58TH AV

ree k

64TH AV

GARRISON ST

64TH AV

ry C

68TH AV

CARR ST

66TH AV

le D

74TH AV

BRADBURN BD

DR

PIERCE ST

2

R

R CA

WADSWORTH BD

SIMMS ST

KIPLING ST

80TH AV

Tra il


AL

MIDWAY BD

LN

MAIN ST

MAPWESTMINSTER

TRI

ST

US

L KOH

IND

WESTMINSTER’S MOBILITY ACTION PLAN

128 128

287

Promenade Sidepath Connector Project Overview

36

ur c

Farm

Cre

ek T rail

Westminster City Park

104TH AV

ail anal Tr

H ers’ ig h

96TH AV

PROJECT LOCATION

SHERIDAN BLVD

T

OA KS

Standley Lake Regional Park

Ch Dr y

CHURCH RANCH

L ine C

WADSWORTH BD

SIMMS ST

JOHNSON ST

Big

112TH AV

ER LY y N F ewa IRO Bik AT S 36 FL U

The Big Dry Creek Trail provides a comfortable bicycle and pedes121 trian facility for neighborhoods east of Westminster Boulevard, and the Promenade Drive Sidepath provides a link towards the Church Ranch BRT Station. Currently, there is no direct bicycle/ k Trail Creek Trail (south of pedestrian connection between the Big CreeDry Walnut 108th Avenue) and the sidepath on the north side of Promenade 108TH AV W 108TH AV Drive. This project would construct a new connection between these trails. The project includes removing and replacing existing gravel sections of trail with a concrete shared-use path, and 104TH AV constructing new sections of shared-use path. The project also anch B includes constructing a culvert to bridge over an existing ditch. hR lv d

S TA N D L E Y L A K E ALKIRE ST

92ND AV

Representative Photo Simulation Promenade Sidepath Connector

CITY HALL CAMPUS

DOWNTOWN WESTMINSTER Existing Conditions

Farmers’ High Line Canal Trail

GARRISON ST

88TH AV

86TH PY

Little Dry

121

84TH AV

Creek Tr ail

DR

Litt

72ND AV

0.5

1 Mile

69TH AV

1-9

Westminster’s Mobility Action Plan

TENNYSN ST

SHERIDAN BLVD

121

LAMAR ST

64TH AV

RALSTON RD

G ST KIPLIN

58TH AV

ree k

95

GARRISON ST

64TH AV

ry C

68TH AV

CARR ST

66TH AV

le D

74TH AV

PIERCE ST

WADSWORTH BD

SIMMS ST

KIPLING ST

RR

CA

BRADBURN BD

80TH AV

Trai l


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

1.5 NEXT STEP RECOMMENDATIONS Westminster is strategically improving its transportation network. Bicycle, pedestrian and transit connections are integral to future development in existing neighborhoods and business districts. In the future, private developers may be required to construct mobility infrastructure for their projects. This plan recommends the following policies and programs be put in place in order to advance mobility in the city. 1. Integrate MAP Westminster Prioritization Criteria and Project Recommendations into the CIP and budget development process. 2. Continue funding the MAP Westminster project list. Commensurately, plan for and budget operations and maintenance funding for non-motorized infrastructure. 3. Formalize the adoption, recommendation, and benchmarking of citywide mobility policies, including: • Complete Streets – Policies that enable the safe access for all users, including pedestrians, bicyclists, motorists and transit riders of all ages and abilities. • Vision Zero – Projects that aim to achieve a transportation system with no fatalities in the roadway system. 4. Include active transportation network language into City documents: • Comprehensive Plan • Design Guidelines • School zone and neighborhood design policies • Access Management Policy • Zoning Ordinances • Pedestrian overlay districts and form based code districts • Specific Area Plans • Create Standards and Specifications for mobility elements. Examples of mobility elements include: • Crosswalks • Speed tables • Bike lanes (all types) • Sidewalks • Bus stops • Residential Service Commitment applications

5. Support implementation of active transportation programs: • Bicycle wayfinding • Safety education initiatives • City active transportation web page 6. Enhance data collection efforts that support bicycle and pedestrian infrastructure and programs, including: • Bicycle and pedestrian count program • Bicycle and pedestrian crash data CIP Prioritization Criteria

Opportunities to integrate bicycle and pedestrian infrastructure into capital improvement projects should be identified early in the planning and design process. This will help to ensure that non-motorized improvements are built as part of capital projects. To facilitate this process, the following criteria shall be used by city staff to identify capital improvement projects that enhance mobility for people walking, bicycling, or taking transit: 1. Improves Safety: The project addresses identified safety problems for one or multiple modes of travel in Westminster’s transportation system, based on field work, stakeholder, and public input. 2. Improves Mobility Experience: The project results in a walking, bicycling, transit and/or driving environment that is attractive, and low-stress for one or more modes of transportation. 3. Improves Connectivity through Walking, Biking and/or Transit: The project provides a new walking, bicycling or transit connection, or improves upon an existing connection, to transit stations, job centers, activity centers, neighborhoods, schools, public parks, open spaces, trails, and other recreational destinations.

1-10 Chapter 1: Executive Summary


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Page intentionally left blank

1-11 Westminster’s Mobility Action Plan


CHAPTER 2: EXISTING CONDITIONS


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

2.1 INTRODUCTION

MAP 2.1 WESTMINSTER STUDY AREA

The City of Westminster has embarked on a path to improve transportation options for its residents. As the population grows and increased pressure is placed on the city’s transportation infrastructure, the city is seeking to shift trips to active modes of transportation, including walking, bicycling, transit and carpooling, and maximizing the efficiency of the roadway network for motor vehicles. A thorough assessment of current conditions for these modes is critical to developing recommendations to improve them. This chapter describes the existing roadway, pedestrian, bicycling, and transit conditions in Westminster.

ORCHARD TOWN CENTER

CHURCH RANCH

BUSINESS PARK

WESTMINSTER

2.1.1 Study Area

DOWNTOWN WESTMINSTER

SHERIDAN

STATION The City of Westminster, located northwest of Denver, is within Jefferson and Adams Counties and features a diversity of residential neighborhoods, a network of beautiful parks and open spaces, unique cultural and civic assets, WESTMINSTER STATION and thriving retail and commercial corridors. Westminster has grown considerably over the past fifty years, from a small community of less MAP Westminster focuses on the City of Westminster and the unincorporated areas within its The plan also focuses on creating strong multimodal connections to several developthan 2,000 people in the 1940s into a mid-size boundaries. ment and transit efforts converging in the city, to maximize the return on these investments. suburban city home to about 110,000 people today. As its population has grown, so has traffic congeswell as a commuter rail line through the city. The BRT line opened tion. To keep pace with this growth, the city has prioritized in 2016, and the first of three planned commuter rail stations roadway-widening projects to accommodate increasing opened in the summer of 2016. Construction of these facilidemand. Roadway projects have been funded through ties indicates that the city is committed to providing multimodal a combination of sources, including the City’s Capital options. Improvement Program, the Denver Regional Council of Land Use and Development Governments (DRCOG), and the Colorado Department of Westminster’s built environment has a significant impact on Transportation (CDOT). Westminster coupled its roadway walking, bicycling, and transit access. Over the course of its develimprovements with a commitment to environmental stewopment, Westminster, like most American suburbs, pursued ardship and today, boasts over 3,000 acres of preserved a regulatory practice of separating land uses by function. land and 74 miles of shared use paths. The proliferation of Commercial, industrial, and residential uses were concentrated in trails in the city largely resulted from the establishment of a geographically separate areas of the city. The placement of resisales tax approved in 1985, which provided funding for open dential neighborhoods, commercial and retail centers, and larger space preservation and trail development. Extensions of the employment centers in separate areas can increase the distance sales tax continue to be approved, signifying that residents between them. This affects mode choice and connectivity truly value access to the outdoors and trails. between residential neighborhoods and important community destinations, such as retail and commercial centers, parks, and In addition to valuing open space, citizens have also placed a schools. New efforts, such as the Downtown Westminster mixedhigh value on quality transit options. In 2004, a regional sales use development, are aimed at reversing this trend and converting tax increase was approved that provided funding to impleWestminster into “the next Urban Center on the Front Range.”1 ment a Bus Rapid Transit (BRT) system along US Highway 36 Other mixed-use development projects are identified in Map 2.1. (US 36), which would include two stations in Westminster, as

2-1

1 http://www.downtownwestminster.us/

Westminster’s Mobility Action Plan


Westminster, like many suburban communities, has developed in a manner that separates uses by function, including residential, commercial, and industrial. This separation of uses impacts mobility within the city, and Westminster has been proactive in recent years to improve multimodal transportation and create more mixed-use, transit oriented developments (Image: Westminster Blvd looking west).

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Roadway Network Development

included multiple connections to the arterial network, maintaining a high degree of accessibility. Subdivisions developed in the 1980s in Westminster were constructed around culde-sacs with single-point connections to the arterial grid. This type of development has several effects—some are intended, while others are unintentional results:3

The foundation of the city’s transportation network is its road system, which is comprised of local, collector, and arterial roadways. Regional access is provided by Interstate 25 (I-25) and US 36, as well as multiple state routes including: • Wadsworth Parkway (State Highway 121) • 120th Avenue (US 287/State Highway 128) • Sheridan Boulevard (State Highway 95 south of US 36) • Federal Boulevard (US 287)

• They limit vehicular traffic within the development but provide only few routes to access destinations outside of the neighborhood, which may not be the most convenient or direct route. • This poor connectivity also results in out-of-direction travel routes for pedestrians, thereby increasing travel distances and reducing the practicality and convenience of walking. • Since some neighborhood residents have only one arterial street option to reach other destinations in Westminster, vehicular traffic is concentrated on a limited number of arterial streets. • This, in turn, increases traffic on the arterial streets, and as volumes increase, it makes walking and biking along them less comfortable. • Over time, congestion worsens on the arterial streets, and additional lanes are added to mitigate congestion. • This, in turn, makes the arterial street network even less comfortable for walking and biking, further shifting what could be walk and bike trips to driving trips, and the cycle repeats itself.

As the population has increased in the city, congestion city-wide has increased in step, especially along the city’s arterials. The city’s policy has been to identify roadways that are operating over capacity (as indicated by a poor vehicle Level of Service at intersections) and then reduce congestion along these roadways by adding additional travel and turn lanes. Westminster’s major arterials are very wide now, with some intersections that are ten lanes across, such as Sheridan Boulevard and 104th Avenue. This policy has managed peak-hour congestion in the short term, but with build-out population expected to be 123,900, population and consequential traffic is estimated to grow 14 percent.2 Some roadways can be widened to accommodate this growth, but others cannot (such as 92nd Avenue), and additional measures are necessary to effectively manage traffic congestion, such as shifting drive alone trips to transit, carpooling, bicycling and walking. Traffic Congestion Perpetuates Itself

More recently, the city has been requiring multiple access points for new subdivisions, and continues to prioritize these types of improvements.

The city has developed within a regional super-grid of arterial roadways spaced at approximately 1-1/2 miles (north-south) and 1 mile (east-west) intervals. Commercial and employment development has been concentrated along these arterial roadways, while residential development has been concentrated between them. Earlier residential subdivisions

3  Designing Walkable Urban Thoroughfares: A Context Sensutuve Approach; Chapter 3

2  Westminster Comprehensive Roadway Plan Update

2-2 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

MOBILITY IN WESTMINSTER - A SNAPSHOT Chart 2.1

COMMUTE MODE SHARE IN WESTMINSTER

77.1% DRIVE ALONE

The number one goal for transportation included in the Westminster’s Comprehensive Plan is to “develop a balanced transportation system.” Currently, the transportation system in Westminster is skewed towards driving alone. By investing in active transportation infrastructure, and improving transit connections, Westminster’s transportation system can become more balanced. Although Journey to Work data does provide insight into mode choices, there are limitations to it, as described on page 1-4.

A sizable portion of Westminster’s residents carpool to work. Carpooling helps to reduce congestion by decreasing the number of single occupancy vehicle trips.

10.4% CARPOOL

4.7% TRANSIT OTHER

6.0%

0.4% BIKE 1.2% WALK

Chart 2.2 ACTIVE TRANSPORTATION,

TRANSIT & CARPOOL RATES

Westminster vs. other jurisdictions

Westminster

Comparing Westminster’s carpool, transit, and active transportation mode split to other communities helps to illustrate where Westminster is a leader and where the city lags behind. The data indicates that of the peer communities assessed, Westminster is second only to Denver in terms of total percentage of commuters either carpooling or taking transit. Comparing each mode individually, more people commute via carpooling in Westminster than in Arvada, Broomfield, and Denver, and more people commute via transit in Westminster than in Arvada, Broomfield or Thorton.

Arvada

Broomfield

Thornton

Denver (City and County)

Adams County

Jefferson County

Colorado Graphic Source: ACS 2014 5-year estimates

0

10%

2-3 Westminster’s Mobility Action Plan

20%


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

American Community Survey Journey to Work Data

The American Community Survey (ACS) Journey to Work data measures changes in mode share over time. However, the ACS only collects transportation information about the main mode of transportation for trips from home to work. It excludes trips made by those outside of the workforce, including children, retirees, unemployed residents, and stay-at-home parents. It also excludes trip purposes such as shopping, going to and from school, and recreational outings. Lastly, it only represents the primary mode of transportation to work and does not reflect

the mode choices of people who use more than one mode of transportation weekly, or who link multiple modes to complete a single trip. Though it does have limitations, it is useful for comparing general preferences for the primary commute to work mode. Recommended next steps include creating more granular data sets that provide better insight into mode choice, such as travel surveys administered by the city, Regional Transporation District (RTD) and DRCOG.

Westminster

Westminster CARPOOL COMMUTING

Arvada Broomfield

Broomfield

Thornton

Thornton

Denver (City and County)

Denver (City and County)

Adams County

Adams County

Jefferson County

Jefferson County

Colorado

Colorado

0

2%

4%

6%

PEDESTRIAN COMMUTING

Arvada

8% 10% 12%

0

Westminster

2%

4%

6%

Westminster TRANSIT COMMUTING

Arvada Broomfield

Broomfield

Thornton

Thornton

Denver (City and County)

Denver (City and County)

Adams County

Adams County

Jefferson County

Jefferson County

Colorado

Colorado

0

2%

4% 6%

BICYCLE COMMUTING

Arvada

0

8%

2%

4%

25%

30 - 39

40 - 59 > 60 6%

percentage of total

20 - 29

13.7%

10 - 19

22.6%

<9

25%

minutes

7.6%

Chart 2.3 MEAN TRAVEL TIME TO WORK (all modes) For some Westminster residents, journeys to work are relatively long (greater than 40 minutes), but others are much shorter. Shorter trips currently completed by vehicle represent trips that could potentially be shifted to walking and bicycling. Longer trips can potentially be shifted to transit or car pool trips, depending on origins and destinations.

50% of travel times are less than 24 minutes Graphic Source: ACS 2014 5-year estimates

2-4 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Review of Past Plans

As Westminster approaches its build-out limit, city leaders have focused on expanding the multimodal network to facilitate bicycle, pedestrian and transit circulation as a way to manage congestion, encourage wellness, and provide recreational opportunities in the city. Several past planning documents were reviewed, which together, focused on land use development, the transportation network, transit options, trails, and bicycle and pedestrian infrastructure. Overall, they demonstrate the city’s strong commitment to improving multimodal access to destinations and neighborhoods throughout Westminster. The plans reviewed include (summaries of the plans reviewed are included in Appendix B): • Westminster Bicycle Master Plan • Westminster Comprehensive Plan • Comprehensive Roadway Plan Update • Open Space Stewardship Plan • Trails Master Plan • Westminster Downtown Specific Plan • US 36 First and Last Mile Study • DRCOG Northwest Corridor Bicycle and Pedestrian Accessibility Study A timeline displaying the plans is displayed on pages 1-5 and 1-6.

TIMELINE OF PAST PLANS Comprehensive Roadway Plan Update (2008) The plan’s goal was to anticipate future transportation issues and develop a work program to address them. This program included adding capacity at key intersections, while also improving transit access and the bicycle and pedestrian networks.

Westminster Comprehensive Roadway Plan Update

March 2008 Westminster, Colorado

Westminster CO 2030 Bicycle Master Plan (2011) This bicycle master plan recommended implementation of 132 miles of new bikeway facilities over twenty years with an emphasis on new on-street facilities to connect to existing off-road trails, as well as wayfinding, bike parking, and programs.

TER S N I ESTMCLE BICY TER MAS N PLA

Building a Multimodal Future

Multimodal solutions and maximizing the efficiency of the existing roadway network is necessary to successfully manage future population and traffic growth in Westminster. Over the past decade, the city has invested significant resources to improve multimodal options for its residents, including better transit, park-n-rides and bicycle and pedestrian infrastructure. MAP Westminster coincides with four major projects that will have a significant impact on mobility in the city. These include: • Construction of Downtown Westminster, a new, mixed-use town center • Westminster’s first commuter-rail station, Westminster Station • Opening of a BRT along the US 36 corridor, which will include two BRT stations in Westminster. • Completion of the US 36 Bikeway, which parallels US 36 between Boulder and Westminster These projects will make Westminster an even more appealing place in which to live and work, simplifying regional travel and providing additional amenities for residents and visitors alike. To ensure a high rate of return on these investments, multimodal connections to them must be strong. If integrated properly, these new assets can reshape Westminster’s future, helping it to be less of an automobile-oriented city and more of a multimodal community. MAP Westminster will include recommendations to better link these projects via transit, walking, and bicycling to ensure they can fulfill their potential.

US 36 First and Final Mile Study (2013)

US 36 FIRST AND FINAL MILE STUDY

Fehr & Peers 621 17th Street, Suite 2301 Denver, CO 80210

The plan recommends multimodal improvements to access to two park-and-ride stations, Church Ranch and Downtown Westminster, ranging from new separated grade crossings to intersection improvements and better trail connections.

Westminster Comprehensive Plan (2014) The Comprehensive Plan was created to guide future growth in the community with a focus on redevelopment. Transportationrelated recommendations included consideration of all modes when implementing future roadway improvements and increased access to transit.

2-5 Westminster’s Mobility Action Plan

WESTMINSTER

Comprehensive Plan November 11, 2013

Amended June 23, 2014

WESTMINSTER


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

TIMELINE OF PAST PLANS Open Space Stewardship Plan (2014)

City of Westminster

2014 Open Space Stewardship Plan deCember 8, 2014

This plan addresses preservation and maintenance of existing open space and historic buildings and recommends improving connectivity through trail connections, neighborhood trail loops, and transportation corridor connections.

Trails Master Plan (2014) This plan addresses completion of the trail system, addressing existing connectivity issues, and expanding trails to development. Key recommendations include upgrading major trails, installing additional on-street bikeways, and creating neighborhood loops.

2 0 1 4 OPEN S PAC E STEWARD SH IP PLAN

Trails Master Plan Diagram - SupporƟng NarraƟve The conceptual approach to developing the City of Westminster’s Trails system began with idenƟfying major, linear corridors associated with drainage and irrigaƟon conveyance (i.e. Big Dry Creek, LiƩle Dry Creek and Farmers’ High Line Canal), purchasing and preserving land along those corridors, and construcƟng a Major Trails (regional) system. Through the subsequent development of residenƟal subdivisions and commercial development, Minor Trails were designed and constructed, oŌen ad hoc, linking neighborhoods and commercial development to Major Trails. The exisƟng combinaƟon of Major and Minor Trails serves as the framework for the Westminster Open Space and Trails system.

Exis�ng City of Westminster Off-Street Trail Summary Total (all trails): 118.5 miles Major/Minor/Connec�ng Trails: 105.63 miles Natural Trails: 12.87 miles

The City of Westminster has a robust sidewalk network. Farmers’ High Line Canal Trail

Goals for Trails Planning This Trails Master Plan, as part of the Open Space Stewardship Plan, seeks to progress the following three primary goals:

Big Dry Creek Trail

Walnut Creek Trail

Li�le Dry Creek Trail

2.2 PEDESTRIAN FACILITIES

Major Trail Corridors of the Westminster Trail System

1) Complete the Trails system as it was originally conceived by City staff. 2) Mi�gate unforeseen consequences of the exis�ng ad hoc developed “Major Trail Corridor/Minor Trail Links” framework for future trail expansion.

Sidewalks, marked crosswalks, and other pedestrian facilities are an integral component of the non-motorized transportation network in Westminster. These facilities support safe and comfortable travel for walkers, joggers, families pushing strollers, and persons with wheelchairs or other mobility assistive devices. Sidewalks are present along most roadways in Westminster, and range in width from 2 feet to wider than 8 feet. Some sidewalks are immediately adjacent to the roadway, while others are buffered from motor vehicle traffic by a planted strip. Where present, these planted strips are often wider along busier roadways, which help to provide additional separation from motor vehicles and an improved perception of safety and comfort for pedestrians.

3) An�cipate expansion of the existing trails framework in response to expansion and changing land uses and user groups.

Trail at Stra�ord Lakes into Big Dry Creek Open Space

1

Northwest Corridor Bicycle and Pedestrian Accessibility Study

Summary Report

Denver Regional Council of Governments Sustainable Communities Initiative December 2014

Northwest Corridor Bicycle and Pedestrian Accessibility Study (2014) The planning team conducted an audit of bicycling and walking conditions within a one-mile radius of new transit stations, two of which are in Westminster, along the US 36 corridor and recommended signage improvements and identified improvements in multimodal connections to the stations.

2.2.1 Linear Sidewalk Conditions Westminster Downtown Specific Plan (2015) This redevelopment plan for a new Town Center includes recommendations for improvements to the surrounding street network, access to transit, and improved bicycle and pedestrian connections.

Requirements in the city’s zoning code and subdivision regulations have helped to create a well-connected network of sidewalks within Westminster’s residential neighborhoods. The vast majority of residential neighborhoods have sidewalks on both sides of the road. One notable issue with the sidewalks within residential neighborhoods is that their widths vary substantially, with many of the sidewalks not meeting the minimum 5 feet required by the Americans with Disabilities Act. Many neighborhood sidewalks are not accessible to those with disabilities, as shown in Chart 2.4.

DOWNTOWN SPECIFIC PLAN CITY COUNCIL ADOPTED PLAN

WESTMINSTER , COLOR ADO NOVEMBER 24 , 2014 Updated September 28 , 2015

2-6 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Chart 2.4: Ratio of ADA Accessible Sidewalks

on the sidewalks. Along many of these roads, a planted buffer cannot be installed because the roadways have been widened to their maximum extent. Adding space to the pedestrian zone would require reducing the width of the traveled way, which would impact vehicular traffic patterns.

Although Westminster has several hundred miles of sidewalk, the majority of sidewalks in Westminster do not meet the minimum 5 foot required to be ADA accessible

> 5 feet

< 5 feet note: ratio is approximate

Some collectors and arterial roadways also have sidewalks on one or both sides of the roadway, such as on 112th Avenue and 104th Avenue. There are long gaps that exist along several arterial and collector roadways where sidewalks do not exist, such as on Federal Boulevard and Wadsworth Parkway. Pedestrian demand along roads that do not have sidewalks is shown by the presence of informal dirt paths that have been created by regular use. Along some with high traffic volumes and speeds, a planted

Sidewalks placed along high-volume, high-speed roads without buffers are uncomfortable to walk along (Image: 92nd Ave West of Raleigh St).

Improving the walking environment also involves enhancing the pedestrian experience. Currently, many sidewalks along arterial streets are between busy roads and long stretches of fence built for the adjacent subdivision, such as along Westminster Boulevard. Appealing pedestrian environments are characterized by visually interesting scenes, and walls of fencing along these streets make the pedestrian experience less inviting. The Denver region experiences hot, sunny weather, and the presence of street trees can provide welcome shade for pedestrians. Street trees also have a trafficcalming effect, indicating to motorists that they are driving through a pedestrian realm. Although some major roads in Westminster do have street trees (such as Sheridan Boulevard between 92nd Avenue to City Center Drive), many do not. A complete analysis of specific gaps in the pedestrian network is provided in the Gap Analysis Chapter of this report. Gaps in the sidewalk network along major roads are displayed on Map 2.2.

Informal paths have been created where there is demand for a sidewalk, but where no sidewalk exists (Image: W 108th Ave west of Westmoor Dr).

buffer between the roadway and sidewalk makes walking along the roadway more comfortable. Some arterial and collector roadways have planted buffers, but others do not. Major roads without buffers are stressful to walk along, as cars are travelling relatively fast (40 mph +) within 2 to 3 feet of pedestrians walking

Many streets in Westminster are flanked by long walls of fencing which detract from the pedestrian experience (Image: Westminster Blvd north of 92nd Ave).

2-7 Westminster’s Mobility Action Plan


FLAGG DR

SPAULDING ST

PUBLIC RD

84th Ave

17

Huron St

2

88th Ave

18

Independence Dr

3

96th Ave

19

Lowell Blvd

4

100th Ave

20

Oakwood St

5

108th Ave

21

Orchard St

6

112th Ave

22

Pecos St

7

120th Ave

23

Ranch Reserve Pkwy

8

121st Ave

24

Sheridan Blvd

9

122nd Ave

25

Simms St

10

124th Ave

26

Turnpike Dr

11

128th Ave

27

Wadsworth Blvd

12

144th Ave

28

Wadsworth Pkwy

13

Alkire Ave

29

Westminster Blvd

14

Bradburn Ave

30

Yates Dr

15

Federal Blvd

31

Zuni St

16

Harlan St

DR

LIC

120TH ST

PUB

EST

W TH

WY

PK

R

NO

DILLON RD

144TH AV

287

ZUNI ST

128TH AV

MAIN ST

N

124TH AV

ER

FED

128

120TH AV

128

PECOS ST

287

Y AL P

HURON ST

LL

AV

MIDWAY BD

ST

TRIA

TH

134

10TH AV

L KOH

US

WESTLAKE DR

ASPEN ST

136TH AV

10TH AV

IND

HURON ST

1

25 160TH AV

LOWELL BD

#

36 121

WAGON ROAD PARK AND RIDE

CHURCH RANCH STATION 104TH AV

FP Y

96TH AV

YATES ST

92ND AV

DOWNTOWN WESTMINSTER

25

SHERIDAN STATION

88TH AV

88TH AV

121

84TH AV

POMO

NA DR

A CH SE DR

0

0.5

1 Mile

ZUNI ST

WESTMINSTER STATION 64TH AV

287

76

BROADWAY

121 RALSTON RD

LOWELL BD

62ND AV

TENNYSN ST

G ST KIPLIN

58TH AV

68TH AV

95

GARRISON ST

Transit Station

68TH AV

LAMAR ST

Existing Sidewalk with Buffer

70TH AV

69TH AV

CARR ST

(likely greater than 5’ based on review of aerial imagery)

AV

36

72ND AV

SHERIDAN BLVD

Existing Sidewalk

74TH AV

PIERCE ST

WADSWORTH BD

(likely less than 5’ based on review of aerial imagery)

TH

76

D

Narrow Sidewalk

76TH AV

DB OO

72

W EEN

CA

Gap in Sidewalk Network

ZUNI ST

DR

GR

RR

80TH AV BRADBURN BD

80TH AV

EXISTING SIDEWALK CONDITIONS MAJOR ROADS

BROADWAY

DR

84TH AV

LA MA R

GARRISON ST

88TH AV

86TH PY

LIF

HURON ST

WADSWORTH BD

STC

HARLAN ST

ALKIRE ST

INDIANA ST

DR

DE

EN

EP

IND

E NC

WE

LOWELL BD

hu r

C

96TH AV

S TA N D L E Y L A K E

SHERIDAN BLVD

Ranch Bl vd ch

100TH AV

FEDERAL BLVD

104TH AV

PECOS ST

OA K

ST

JOHNSON ST

108TH AV

ZUNI ST

SIMMS ST

112TH AV

MAP 2.2: EXISTING SIDEWALK CONDITIONS (MAJOR ROADS)

EMMA ST

Major Roads with Sidewalk Gaps


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

The condition of sidewalks is important to the safety and mobility of all pedestrians. Sidewalks that are uneven, or which have deteriorated so that their surface is no longer smooth, pose hazards to pedestrians. These issues are exacerbated for mobility impaired users. In Westminster, where sidewalks exist, most are in good repair. Sidewalk conditions in South Westminster are generally in poorer condition than sidewalks in other sections of the city, especially along Federal Boulevard. Many of these sidewalks are only 2.5 feet wide, especially south of 88th Avenue. Recent efforts have been focused on improving sidewalk conditions in this area of the city, such as the reconstruction of Lowell Boulevard.

Poor Sidewalk Condition

Image: W 108th Ave near Wadsworth Pkwy

Sidewalks should also be clear of any obstructions that minimize the usable width of the sidewalk. Although the cross-section of most sidewalks in Westminster are clear of any obstructions, there are some instances where landscaping encroaches upon the sidewalk and where sidewalks have been built around utility poles.

Frequent Driveways

Another important consideration for ensuring adequate pedestrian facilities is minimizing the impact of driveways that provide access to adjacent land uses, known as access management. Vehicles entering and exiting driveways create added stress for pedestrians. A key strategy for minimizing the impact of driveways is to consolidate the number of driveways that service an adjacent development. Several of Westminster’s major roads service automobile-oriented land uses, such as strip malls and department stores, and, along these stretches of road, there are multiple instances where frequent driveways negatively impact the pedestrian experience.

Image: Federal Blvd south of W 74th Ave

Utility Obstructions within Sidewalk

Landscaping Encroachment

Image: Sheridan Blvd north of 98th Ave)

Image: 72nd Ave

2-9 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

2.2.2 Existing Intersection Conditions Crosswalks and Intersections

Crosswalk markings provide guidance for pedestrians who are crossing roadways by defining paths across intersections or other crossing points. While marked pedestrian crosswalks do not in and of themselves slow traffic or reduce pedestrian crashes, there are several reasons to install marked crosswalks, including: • To indicate a preferred pedestrian crossing location • To alert drivers to an often-used pedestrian crossing • To indicate school walking routes

Properly designed curb ramps are key pedestrian accessibility features. Most intersections in the city are equipped with curb ramps, a key element of an accessible pedestrian system. Many ramps in Westminster do meet current standards. The vast majority of the existing curb ramps are single ramps that direct people into the intersection rather than into the crosswalk. Issues associated with this design are described in the next section, Long Crossing Distances. Example of a typical sidewalk curb ramp in Westminster

The City of Westminster uses a “continental style” crosswalk in most applications. This type of crosswalk exhibits a high degree of visibility for approaching motorists, and is generally accepted as the preferred crosswalk treatment type. Most major intersections in Westminster include striped crosswalks at all legs of the intersection. The majority of signalized intersections in Westminster include push-button activated pedestrian signal heads, which alert pedestrians of the appropriate signal phase during which to cross the street. The majority of signalized intersections also include pedestrian signal heads at each crossing leg. While nearly all signalized intersections are equipped with these pedestrian feautres, pedestrian crossing distances can be very long.

Image: Yates St at 88th Ave

Most major intersections in Westminster include striped crosswalks and pedestrian push buttons and signal heads, but crossing distances tend to be very long (Image: Looking west across Sheridan Blvd from Westminster City Center Marketplace at the City Center development)

2-10 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Long Crossing Distances

Longer crossing distances increase exposure time for pedestrians. Although the relationship is not completely linear, in general, the longer a pedestrian is exposed, the greater the risk of being struck by a vehicle when crossing an intersection. This makes crossing long intersections uncomfortable, which can discourage people from walking altogether. Most major intersections in Westminster feature very long crossing distances caused by the presence of multiple travel lanes, some of which are greater than eight lanes across.

~143’ Sheridan Blvd

Two engineering practices in Westminster increase already long crossing distances. The first is that, at most major intersections, the curb radius is very large (about 40 feet). This design is intended to facilitate turning movements for large vehicles, such as trucks or buses. However, large turning radii also make crossing pedestrian distances longer when located at the corner, as seen in the figure below, and encourage higher vehicle turning speeds.

W 104th Ave

Many major intersections in Westminster have very long crossing distances, such as this nine lane crossing at 104th Ave and Sheridan Blvd. Navigating long crossings is stressful for pedestrians.

The second factor is that curb cuts at most major intersections in Westminster are diagonal in configuration, meaning they are consolidated at the corners of the intersection. This reduces the number of curb cuts for each corner, but places the crosswalk at the corner of the intersection where the crossing distance is the longest, as shown in the image at right. This placement also orients pedestrians diagonally into the intersection and not towards the adjacent crosswalks, an especially problematic issue for visuallyimpaired pedestrians. The large curb return radii at most intersections, consolidated curb cuts, and multiple through and turning lanes combined result in very long crossing distances for pedestrians. Most major roads in Westminster are posted 40 mph. These relatively high speeds coupled with long crossing distances can make crossing wide streets in Westminster challenging.

rb r Cu orte

Reduced crossing distance

Setting curb-cuts and crosswalks back from intersections would reduce crossing distances

Setting curb-cuts and crosswalks back from intersections reduces crossing distances, especially at intersections with large turning radii, like the intersection of 104th Ave and Sheridan Blvd shown above/below.

ius

Rad

Sh

R urb gC

us

adi

tin

Exis

Increasing the curb radius can shorten the crossing distance, and can also reduce vehicle turning speeds

2-11 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Channelized Right Turn “Slip Lanes”

Most signalized intersections in Westminster include right turn “slip lanes.” The purpose of a slip lane is two-fold. It allows right turning vehicles to make a right turn movement without needing to wait for the green phase, and separates through-moving vehicles and right turning vehicles in advance of the intersection. These two factors decrease vehicle delay at the intersection. Slip lanes divide long crossings into shorter segments, enabling pedestrians to make the crossing in phases. Another benefit of slip lanes is that there are typically no conflicts with motor vehicles when the walk signal is activated. While slip lanes do have advantages, vehicles travelling through the slip lane sometimes exhibit low yield compliance for pedestrians. Measures, such as signage, flashing beacons, and raised slip lanes, among other treatments, can can be implemented to improve yielding and the visible width of the slip lane. Pedestrian Refuge Islands

Most major intersections in Westminster have right turn slip lanes that channelize right-turning vehicles, which increases intersection efficiency from a vehicular standpoint but also can make crossing intersections more stressful for pedestrians (Image: Sheridan Blvd and 92nd Ave).

Crossing multi-lane roadways can be challenging for pedestrians. At unsignalized intersections and at mid-block crossings where there is pedestrian crossing demand, these issues are exacerbated. Pedestrians must gauge for themselves when there is an appropriate gap in traffic before crossing. On multi-lane roadways, true gaps in traffic, or times when the pedestrian can cross the roadway without having vehicles pass in front or behind them, may be infrequent. Pedestrians tend to cross the roadway when there are perceived “holes,” or when there are no oncoming vehicles in the lane the pedestrian is crossing, but there are vehicles passing their path, either in front or behind the pedestrian, as they cross the roadway. Pedestrian refuge islands help to overcome this issue, enabling pedestrians to cross when there are true gaps in traffic. Pedestrian refuge islands allow pedestrians to make the roadway crossing in two phases, reducing the number of traffic flows a pedestrian must predict. Refuge islands are especially beneficial when gaps in the opposing directions of traffic are inconsistent. Over 75 percent of pedestrian fatalities occur at non-intersection locations.1 “Providing raised medians or pedestrian refuge areas at pedestrian crossings at marked crosswalks has demonstrated a 46 percent reduction in pedestrian crashes. At unmarked crosswalk locations, pedestrian crashes have been reduced by 39 percent.”2 Pedestrian refuge islands are an effective tool to improve pedestrian crossing safety. 1  NHTSA, Traffic Safety Facts 2008 Pedestrians, NHTSA, Washington, DC, 2009. 2  Lindley, J., Guidance Memorandum on Consideration and Implementation of Proven Safety Countermeasures, FHWA, Washington, DC, July 2008.

Pedestrian refuge islands help to improve safety for crossing pedestrians, especially on multiland roadways (Image: Aspen, CO)

The City of Westminster has installed pedestrian refuge islands (such as on Countryside Drive), but there are instances where pedestrian crossing demand exists, but no refuge islands are provided.

2.2.3 Sidewalk Policies The Westminster Municipal Code and Standards and Specifications for the Design and Construction of Public Improvements identify specific requirements for sidewalk maintenance, sidewalk widths, sidewalk locations, guiding pedestrian traffic during construction, and requirements for installing a pedestrian push button.

2-12 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Westminster Municipal Code The City of Westminster Municipal Code provides guidance and requirements for bicycle and pedestrian facility maintenance and use.

Table 2.1: Minimum Sidewalk Widths by Street Type

Sidewalks (Section 8-1-10) The city requires clear and unobstructed sidewalk paths, which encourages safe and accessible pedestrian routes, even during inclement weather. This includes a requirement (Section 8-1-10 (A)) that states that it is the responsibility of the property owner “abutting or adjoining” a sidewalk to remove snow or ice within 24 hours of the last measurable snow fall. By providing codes and requirements that outline snow removal and maintenance for sidewalks, the city is taking steps to create dependable facilities for pedestrians. Sidewalk Use (Section 10-1-13) Section 10-1-13 of the City’s Municipal Code dedicates sidewalk use to pedestrian and non-motorized bicycles: (M) In Section 710, “Emerging from or entering alley, driveway, or building,” subsection (3) is modified to read as follows: (3) No person shall drive any vehicle other than a bicycle, electric assisted bicycle, or any other human-powered vehicle upon a sidewalk or sidewalk area, except upon a permanent or duly authorized temporary driveway and except as permitted in Sections 10-1-13 and 10-1-14, W.M.C. Standards and Specifications for the Design and Construction of Public Improvements Currently, the City of Westminster Standards and Specifications provides guidance and requirements for bicycle and pedestrian facilities. These include maintenance, design, and traffic control guidance that demonstrates a desire to have dependable, safe sidewalk facilities and connectivity.

Type of Road

Required Sidewalk Width

Section of Chapter 6

Local Street

5 foot minimum from curb

6.12.01(L)

Minor Collector

5 foot minimum, detached from curb

6.13.01(M)

Major Collector

5 foot minimum, detached from curb (typical detachment is 12 feet)

6.13.02(M)

Minor Arterial

8 foot minimum, detached from curb, or as required by the City Engineer

6.14.01(K)

Major Arterial (four lanes)

8 foot minimum, detached from curb, or as required by the City Engineer

6.14.02(K)

Major Arterial (six lanes)

8 foot minimum, detached from curb, or as required by the City Engineer

6.14.03(K)

• Curb ramps are to be built at all intersections, as well as certain mid-block crossings, and must include pedestrian warning strips that indicate to mobility impaired pedestrians that they are entering the traveled way (Section E) The city encourages maintaining dependable routes during construction (Section 6.60.02, Pedestrian Traffic): Specific counter-measures that need to be met during construction to ensure pedestrian movement are identified in Appendix A. Chapter 8, Traffic Control In Chapter 8, Traffic Control, of the City Standards, specifics regarding pedestrian push buttons are outlined in Section 8.35.01: (A) Pedestrian push-buttons shall be of the direct pushbutton contact type. Pedestrian push buttons also are shown in Standard Drawing T11. Standard drawings also are provided for School Flashing Beacon Assemblies on the side of road or overhead (T19, T20, T21).

Chapter 6: Roadway The city specifies minimum sidewalk widths in Chapter 6. Sidewalk widths are shown in Table 2.1. Chapter 6 of the Standards includes typical sections for roads that show sidewalk widths. Additionally, the following standards regarding sidewalks and ramps can be found in Section 6.20.00, Sidewalks, Curb and Gutters, Ramps, and Driveways: • Sidewalks or bicycle paths are to be built on both sides of roadways, and must have specific widths detailed in Table 2.1 (Section B) Most signalized intersections are equipped with pedestrian-actuated push buttons, and pedestrian signal heads that instruct pedestrians when it is appropriate to cross the intersection (Image: Church Ranch Blvd and 104th Ave).

2-13 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Image: Sheridan Blvd at W 104th Ave

2.3 SHARED USE PATHS AND TRAILS

WESTMINSTER EXISTING TRAILS

Shared use paths allow for two-way, off-street travel by bicyclists, pedestrians, skaters, wheelchair users, runners, persons with limited mobility, and other non-motorized users. The term “shared use path” and “trail” are often used interchangeably; however, the term “trail” can be more encompassing than “shared use path” and include natural surface trails and even sidewalks. Shared use paths are wider, hard-surface trails frequently found in parks, along rivers, and linear greenways, and typically have few conflicts with motor vehicles. They can also be located adjacent to the roadway as a “sidepath.” When located within a roadway right-of-way, sidepaths must be designed to enhance safety and minimize conflict with motor vehicles, particularly at unsignalized intersections and other motor vehicle crossings.

I-25 Trail

Big Dry Creek Trail

Walnut Creek Trail Farmers’ High Line Canal Trail US 36 Bikeway

Westminster’s Trail System

More than 74 miles of trails exist within the City of Westminster. The trail system is augmented by the presence of over fifty non-motorized underpasses that enable people to cross Westminster’s major arterials easily and comfortably. The trail system in Westminster largely follows a major trail and minor trail framework. The major “trunk-line” routes include the Farmers’ High Line Canal, Little Dry Creek, Big Dry Creek, US 36 Bikeway and I-25 Trail and the future Walnut Creek Trail. Other minor trails serve many of the city’s subdivisions, but connections between the major and minor trails are lacking.

Little Dry Creek Trail

Most of the older trails in Westminster follow an east/west orientation, while the newer US 36 Bikeway and I-25 Trail follow a north/south orientation. While northsouth trail connectivity remains a challenge, the city has actively taken advantage of opportunities to develop east-west corridors, and a major focus of the 2014 Trails Plan was improving north/south connections.

2-14 Existing Conditions


MAPWESTMINSTER

50+

WESTMINSTER’S MOBILITY ACTION PLAN

Most of the major trails follow an east/west orientation along historic drainage ditches, and therefore, are not ideal for reaching north/south destinations. This leaves many residential neighborhoods disconnected from the major trail network, increasing the need to travel long distances to reach them. Recently, new trails travelling north/south have been developed, including US 36 Commuter Bikeway and the I-25 Trail, which enhance mobility options for bicyclists and pedestrians travelling to destinations along these corridors. The 2014 Trails Master Plan recommends 1) upgrading all major trails to be at least 10 feet wide and be paved to facilitate multimodal travel, 2) creating more north/south and neighborhood trail connections, and 3) implementing a cohesive wayfinding system to improve navigation. The plan also recommends installing on-street bicycle facilities to enhance connectivity between neighborhoods, destinations, and the trail network. Trails Crossing Roadways

The number of trail underpasses the city has constructed

been proactive in addressing these potential barriers by constructing over 50 underpasses, which provide gradeseparated crossings that are safe and comfortable. In instances where an underpass has not been built or is not feasible, a range of treatments have been implemented by the city, including full signals at the mid-block, midblock crosswalks, raised crosswalks, and “trail crossing ahead” signage. The most appropriate type of crossings is dependent on the roadway context (e.g., street width, number of vehicle lanes, posted and observed speeds).

Many trails in Westminster cross major roadways, which are barriers to the trail’s overall connectivity. The city has

TRAIL CROSSING TREATMENTS Mid-Block Crosswalk with Signage

Raised Intersection

Image: Independence St south of W 94th Ave

Image: Independence St south of Independence Cir

Underpass

Full Mid-Block Signal

Image: Big Dry Creek underpass at US 36 and 103rd Ave

2-15

Westminster’s Mobility Action Plan

Image: Countryside Dr at Ketner Open Space


Material

30 mi

WESTMINSTER MAP Natural Surface

WESTMINSTER’S MOBILITY ACTION PLAN

12.8 mi

Westminster’s Major Trails Network

WESTMINSTER TRAILS - A SNAPSHOT

12.5 mi

US 36 Bikeway

11 mi

Westminster’s Major 9 miTrails Network

6 mi

Big Dry Creek 12.5 mi

Designation

Length (miles)

Length (miles)

Length (miles) Chart 2.5: Major Trail Lengths in Westminster

5 mi

Little Dry Creek

US 36 Walnut Creek / I-25 / Timberlake Bikeway Westminster’s Trails

Farmers’ High Line Canal 11 mi

Trails in Westminster follow a major/minor trail framework. The 2014 Trails plan recommended 9 mi paving all major trails in Westminster. 6 mi 5 mi

70 mi

Major Trails

Chart 2.6: Comparison of Major and Minor Trail Mileage in Westminster Little Dry Big Dry Farmers’ High US 36 Walnut Creek / I-25 / Creek Timberlake Creek Line Canal Bikeway

82 mi

Minor Trails

Westminster City Park Circle Trail

Westminster’s TrailsLength - Material Type (miles) Concrete 109.8 mi

Major trails primarily Trails follow an-east west orientation Westminster’s Material Type(with the exception of the US 36 Bikeway

Material Type

& I-25 Trails) making commuting via the trail network in a north/south orientation challenging.

Gravel

Material Type

Chart 2.7: Trail Surface Material Comparison of Westminster’s Trail System Concrete

30 mi 109.8 mi

Natural Surface Gravel Standley Lake North Open Space Park Trail

12.8 mi 30 mi

Natural Surface

Length (miles)

12.8 mi

tion

Designation

Length (miles)

The preferred surface type Westminster’s for a trail is dependent on the expected users. Joggers and pedestrians Trails may prefer a softer surface, as they tend to be easier on the knees, while recreational and commuter bicyclists may prefer paved trails (concrete or asphalt) since bicyclists can roll easily on these surfaces.

Major Trails

70 mi

Westminster’s Trails

Minor Trails

Major Trails

2-16

82 mi

Existing Conditions

70 mi


Lowell Boulevard was restriped in 2014, to include a more narrow center median, two vehicle travel lanes and bike lanes. The street now successfully operates as a complete street, with dedicated facilities for pedestrians, WESTMINSTER bicyclists and motor vehicles. WESTMINSTER’S MOBILITY ACTION PLAN

MAP

Density comparison graphics

2.5 ON-STREET BICYCLE FACILITIES The primary goal of the plan was to make Westminster a place where bicycling could become a viable transportation alternative, resulting in a healthier, more vibrant and sustainable city. The plan’s recommendations were envisioned to be implemented over a 20 year period, so that over time, bicycling would increasingly become a safer and more desirable mode of transportation and recreation. As of 2016, 17 miles of bicycle facilities had been installed in Westminster.

On-street bikeways are important components of a bicycle network. In 2011, the city published its first Bicycle Master Plan. At the time of publication, Westminster only had only 0.1 miles of on-street bicycle facilities. The lack of on-street facilities was limiting to Westminster’s multimodal transportation system, and the Bicycle Master Plan focused primarily on recommending new on-street facilities that would complement the existing trail system.

Chart 2.8: Rate of Bikeway Implementation, Current vs. 2011 Bicycle Master Plan Goal

MILES OF BIKEWAY IMPLEMENTED

140

132

Projected Implementation Rate based 2011 Bicycle Master Plan Goal 120

Projected Implementation Rate based on miles implemented to date

100

64

The # of bikeway miles the city will fall short in implementing by 2030 (if current rate continues) 68

80

The miles of bikeway that should exist today

60

40

At this rate, Westminster will have installed 68 miles of bikeway facilites by 2030

33 17

20

To date, about 17 miles bikeway facilities recommended in the 2011 Plan have been have been installed

2030

2029

2028

2027

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

0

YEAR Since the publication of the 2011 Bike Plan, 17 miles of bikeway facilities have been installed. Though this represents progress, the rate of bikeway implementation lags behind the rate identified in the Bike Plane needed to reach the goal of 132 miles of bikeways by 2030. 2-17 Westminster’s Mobility Action Plan


Adams County

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Jefferson County

In total, the plan recommended 132 miles of new bikeway POPULATION DENSITY & BICYCLING facilities, including bike lanes, bike routes, shared lanes, and new shared use paths and sidepaths. These faciliPopulation density is an important factor known to support bikeable cities. tiesColorado were to be implemented in three phases: short-term, Westminster is about as dense as Denver, but its bicycle mode share is much less. Although Denver differs demographically and culturally, it has prioritized mid-term and long-term. The plan also included recombicycling*, and this has supported its comparatively higher bicycle mode share. mendations to improve wayfinding in the community. If Westminster prioritized bicycling to the same degree, based on its population 0 10% A review of existing wayfinding conditions concluded density, it could expect the bicycle mode share to rise. Westminster’s bikeway wayfinding was relatively sparse and incomplete, with a lack of consistency among signage Chart 2.10: Comparative Population Densities (people per square mile): types and placement policies. The plan included several recommendations to standardize and improve bicycle COMPARATIVE POPULATION wayfinding throughout Westminster. In addition DENSITIES to WESTMINSTER (3,203) Westminster (people per sq mi) wayfinding, the plan also included recommendations westminster other to improve bicycle parking options in thevs city, whichjurisdictions is a critical component of all bicycle networks. To help shape PEDESTRIAN Denver a culture that supports bicycling in Westminster, the plan COMMUTING City Countya series of programming recommendations. also&identified These programs were grouped into categories, including education, encouragement, enforcement, and evaluation. Boulder Additional recommendations included in the bike plan are discussed in Appendix A.

Five years after the plan’s publication, Westminster has Adams County

implemented 17 miles of on-street bicycle facilities. Much progress still needs to be made to expand the on-street bicycle network if the 2011 Plan’s vision can be realized by 2030, as can be seen in the chart on page 2-17. Jefferson County

DENVER (4,044)

Increasing the miles of bicycle facilities will also help to increase the percentage of people commuting by bike.

Colorado

COMPARATIVE SHARE BICYCLING

Chart 2.9

10% COMMUTE

0

*Denver has 130 miles of on-street bike lanes

BOULDER (3,800)

Westminster Denver City & County Boulder

Adams County Jefferson County

0.4 % 2.4 %

BICYCLE COMMUTING

10.1 % 2-18 Existing Conditions

JEFFERSON COUNTY (699)


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

2.5 TRANSIT Transit is a key component of the Denver region’s mobility, servicing over 2.87 million people in the region and providing transportation for approximately 4.7 percent of Westminster residents for their commute to work trip. It is a key contributor to a regional transportation system that offers a range of transportation options, particularly when combined with walking and biking. Transit service in Westminster can be divided into four primary categories: • Fixed-route local bus service • BRT Service along US 36 • RTD’s commuter rail service • A Lift Dial-a-Ride Program

The subsections that follow describe how and where people in the city access and use transit service.

2.5.1 Local Bus Service Westminster has 14 local bus routes serving residents throughout the city. Eight of the routes run every day of the week, two routes run Monday through Saturday, and four routes serve commuters during the work-week. Depending on the route, riders can expect the buses to come every 15 to 60 minutes between 4:15am and 2:00am. Table 2.2 has a more detailed description of service offered by each individual route.

Table 2.2: Westminster Local Bus Routes (Sorted by Average Daily Ridership) Route

Description

Days of Operation

Span of Service (Weekdays)

Span of Service (Saturdays)

Peak Peak Span of Service Frequency Frequency (Sundays) (Weekdays) (Saturdays)

Peak Frequency (Sundays)

Avg. Line Ridership/ Day**

FF

Flatiron Flyer

Monday - Sunday

4:15a - 2:00a

5:00a - 3:04a

6:00a - 1:45a

10 mins

15 mins

30 mins

5062

15 mins

15 mins

30 mins

4199

31

Federal BLVD

Monday - Sunday

4:13a - 2:04a

4:16am 4:19am - 2:03am - 2:07am

12

Downing/N. Washington

Monday - Sunday

4:16a - 1:01a

4:26a - 12:56a

5:40a - 12:36a

14 mins

30 mins

60 mins

2624

76

Wadsworth BLVD

Monday - Sunday

4:26a - 2:00a

5:52a - 1:58a

5:56a - 2:02a

15 mins

30 mins

30 mins

2581

120X

Wagon Road/ Thornton Express

Monday - Saturday 4:35a - 11:46p

7:20a - 11:47p

10 mins

30 mins

51

Sheridan BLVD

Monday - Sunday

5:13a - 1:15a

30 mins

30 mins

122X

Wagon Road/Civic Monday - Friday Center Express

*5:35a - 6:50p

AB

Boulder/DIA

Monday - Sunday

3:10a - 1:59a

3:10a - 12:45a

3:10a - 12:48a

20 mins

60 mins

60 mins

884

92

92nd Avenue

Monday - Sunday

4:52a - 11:14p

7:15a - 11:12p

8:14a - 8:12p

30 mins

30 mins

60 mins

871

L

Longmont/Denver Monday - Saturday 4:45a - 11:28p

8:35a - 12:07p

30 mins

90 mins

90L

Sheridan Station to Monday - Friday Civic Center

4:43a - 1:11a

6:16a - 1:15a

1872 30 mins

5 mins

1779 1446

865

6:00a - 9:00a

822

100

Kipling Street

Monday - Saturday 4:45a - 11:10p

6:37a - 8:08p

8

North Broadway/ Huron

Monday - Sunday

6:03a - 8:03p

72

72nd Avenue

Monday - Saturday 5:28a - 9:10p

120

120th Avenue/ Brighton

Monday - Friday

4:45a - 10:25p

AA

Wagon Road/DIA

Monday - Sunday

3:05a - 11:58p

128

Broomfield/ Wagon Road

Monday - Friday

5:35a - 7:10p

112

West 112th Avenue

Monday - Sunday

6:00a - 11:00p 8:04a - 8:01p

80

80th Avenue

Monday - Friday

5:47a - 7:10p

60 mins

140

31L

North Federal Limited

Monday - Friday

*5:47a - 6:13p

15 mins

87

104

West 104th Avenue

Monday - Friday

5:50a - 7:43p

60 mins

81

80L

West 80th Limited Monday - Friday

*6:18a - 6:15p

30 mins

51

4:55a - 10:03p

8:04a - 8:02p

8:41a - 6:38p

30 mins

60 mins

30 mins

60 mins

60 mins

60 mins

812 60 mins

763

30 mins 3:37a - 11:50p

3:37a - 11:50p

30 mins

374 60 mins

60 mins

30 mins 8:04a - 8:02p

*31L - 5:47a - 7:26a & 4:23p - 6:13p; 122X 5:35a - 9:07a & 3:09p - 6:50p; 80L 6:18a - 7:35a & 5:02p - 6:15p **Based on the 2015 Weekday Total (source: RTD)

2-19 Westminster’s Mobility Action Plan

30 mins

767

369 282

60 mins

60 mins

195


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

WESTMINSTER BUS SHELTERS Providing attractive bus stops improves the appeal of using transit. Bus stops in Westminster have a range of treatments, from single poles with no benches to robust shelters with seating areas, bicycle parking, and real-time bus information. Stops along high volume routes should be standardized to offer shelters, benches and other amenities.

Pole Only

Pole and Bench

Wadsworth Parkway north of 108th Avenue

Wadsworth Parkway south of 108th Avenue

Bus stops marked by lone poles on the side of busy roads with no pedestrian infrastructure make taking transit less appealing

Benches at bus stops are an enhancement, but sidewalks should also be provided so those with disabilities can access the station

Shelter with Bench #2 Wadsworth Blvd south of 88th Avenue

Bus shelters provide a place of refuge for people waiting for the bus. US 36 Commuting solutions, in collaboration with the City, received a grant through DRCOG to build and operate a Bus-then-Bike shelter to be located on the westbound side of the Westminster Center Station. Access will be available through public, paid memberships.

In addition to the provision of BRT lanes, the Express Lane Project also included the construction of six new transit stations along US 36 to serve the system, known as FasTracks stations. These transit stations connect to dedicated bus off-ramps from US 36, which increase the efficiency of the bus service. These stations are Park-n-Ride facilities as well, enabling commuters to drive, park, and take transit to their final destination. The stations offer many modern amenities, including real-time bus information, ticket vending machines, and architecturally uniform canopies. All six stations provide transit service to an average of 14,428 passengers per weekday, an increase of 45 percent from previous bus service along the corridor (as of August 2015). The stations also service local routes, making them regional transportation hubs.

2.5.2 Bus Rapid Transit As part of the US 36 Express Lane Project, the “Flatiron Flyer” BRT line was implemented in coordination with other improvements aimed at managing congestion along US 36. The BRT system is now operational and travels upon dedicated high-occupancy vehicle lanes to minimize travel times. The first phase of the project was completed in 2010. The second phase was completed in 2016. Convenient and direct BRT service is now available along US 36 between Denver and Boulder.

Two stations are located in Westminster: Church Ranch Station and Sheridan Station. Church Ranch Station, located in the northwest corner of Westminster, provides 396 vehicle parking spaces, six bicycle racks, and six bicycle lockers, and services 760 riders per day. It provides service to two local BRT routes that run between Denver and Boulder on one local bus route. Near Downtown Westminster, a major residential and retail development that is under construction and described as the “next urban

2-20 Existing Conditions


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Church Ranch Station

Sheridan Station

center on the Front Range,” Sheridan Station serves a growing residential, commercial, and retail sector. The station provides service to five BRT lines that run between Denver and Boulder and eight local bus routes. The station currently provides 1,310 parking spaces, twenty-seven bicycle racks, and twenty-six bicycle lockers. It services 4,680 riders per day, making it one of the busiest Park-N-Ride stations in the entire RTD bus network.

The new transit-oriented development surrounding the Westminster Station includes a new parking garage funded by the city and RTD. The three-story structure supplies the area with over 600 parking spaces and has the capacity to expand to almost 1,200 spaces.

2.5.3 RTD Commuter Rail (B Line)

2.5.4 Park-N-Ride Facilities

Part of the RTD Commuter Rail (B Line) runs through Westminster. A 6.2-mile segment of B Line runs between Denver Union Station and Westminster Station at 70th Avenue and Irving Street. An additional 35 miles will be constructed north of Westminster in later phases to expand the Northwest Rail Line to Church Ranch, Flatiron, Louisville, Boulder Junction, and Downtown Longmont.

There are three Park-N-Ride facilities in Westminster. These include Sheridan Station, Church Ranch and Wagon Road. Sheridan Station and Church Ranch provide service to the US 36 BRT line. Multiple efforts have been focused on improving multimodal access to the Park-N-Rides. These improvements are identified in Appendix A. The details of each station are outline below:

There are a total of three Northwest B Line stations that are planned to be located within Westminster’s boundaries: • Westminster Station (70th Avenue & Irving Street): Complete • Downtown Westminster (88th Avenue & Harlan Street) • Church Ranch (US 36 north of The Shops at Walnut Creek) In support of transit-oriented development in the area, the Westminster Comprehensive Plan suggests streetscape improvements for bicyclists and pedestrians, and new, high-density, mixed-use developments to be built around Westminster Station. Specifically, the Comprehensive Plan’s goals for Westminster Station include: • Establish a vibrant, mixed-use district that will act as a neighborhood and community destination • Provide a multimodal circulation network that prioritizes access to transit and connectivity throughout the Westminster Station focus area

• Create a well-defined, engaging public realm

Church Ranch • Regional Bus Routes: FF1 and FF3 • Car Parking Spaces: 396 • Bike Racks: 9 Sheridan Station • Regional Bus Routes: FF1, FF3, FF4, FF5, FF6, L • SkyRide Routes: AB and ABA • Car Parking Spaces: 1310 • Bike Racks: 26 Wagon Road • Local Bus Routes: 8, 12, 120, and 128 • Express Bus Routes: 120x and 122x • SkyRide Routes: AA • Car Parking Spaces: 1540 • Bike Racks: 20

2-21 Westminster’s Mobility Action Plan


FLAGG DR

PUBLIC RD

SPAULDING ST

On Street Bike Lanes

25 160TH AV

Park-N-Ride Station

HURON ST

Trail DR

LIC

120TH ST

PUB

Existing RTD B Line/Station

EST

W TH

WY

PK

R

NO

Bus Route School

DILLON RD

144TH AV

287

ZUNI ST

B

MAIN ST

N

124TH AV

ER

FED

128

121

k Trail Cree

PECOS ST

Big Dry

36

Y AL P 120TH AV

128

287

H Farm e rs’ 108TH AV

88TH AV

84TH AV

68TH AV

ZUNI ST

36

70TH AV

68TH AV

95

B RTD

64TH AV

0.5

1 Mile

KIPLIN

0

LOWELL BD

TENNYSN ST

LAMAR ST

121 RALSTON RD

SHERIDAN BLVD

G ST

GARRISON ST

E LIN

58TH AV

FLYER

62ND AV

287

76

BROADWAY

PIERCE ST

WADSWORTH BD

WESTMINSTER STATION

69TH AV

CARR ST

BRADBURN BD

KIPLING ST

SIMMS ST

72ND AV

AV

D

Tra il

IRON

DB OO

ree k

TH

76

FLAT

W EEN

ry C

76TH AV

GR

72ND AV

le D

74TH AV

80TH AV

BROADWAY

DR

Litt

PECOS ST

D

OO

DR

RR

DR

CA

64TH AV

ZUNI ST

W

SE

k Trail

ay ew Bik

NA DR

K OA

POMO

36

ry Cree

66TH AV

88TH AV

121 84TH AV

80TH AV

72

FEDERAL BLVD

LOWELL BD

25

SHERIDAN STATION

A CH

Little D

DOWNTOWN WESTMINSTER

DR

GARRISON ST

88TH AV

92ND AV

ZUNI ST

ALKIRE ST

96TH AV

Farmers’ High Line Canal Trail

86TH PY

FP Y

US

INDIANA ST

S TA N D L E Y L A K E

LIF

HURON ST

EP

IND

STC

HARLAN ST

DR

CE

EN

Line C

WE

104TH AV

SHERIDAN BLVD

ek T rail D EN

Line Canal Trai igh l

YATES ST

gh

Farmers’ H i

Cre

LA MA R

96TH AV

C

WADSWORTH BD

Standley Lake Regional Park

Dr y

hu r

Ranch Bl vd ch

100TH AV

Westminster City Park

a n al Trail

ST OA K

CHURCH RANCH STATION

104TH AV

Big

WAGON ROAD PARK AND RIDE

W 108TH AV

JOHNSON ST

SIMMS ST

112TH AV

Trail ut Creek

Waln

128TH AV

HURON ST

LL

il k Tra

Cree

MIDWAY BD

ST

TRIA

LOWELL BD

ry ig D

L KOH

US

V TH A

134

10TH AV

10TH AV

IND

WESTLAKE DR

ASPEN ST

136TH AV

MAP 2.3: EXISTING BIKEWAY, TRAIL AND TRANSIT CONDITIONS

EMMA ST

EXISTING FACILITIES


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

2.6 ROADWAYS AND TRAFFIC The foundation of the city’s transportation network is its road system, which is comprised of local, collector and arterial roadways. Regional access is provided by Interstate 25 (I-25) and US US 36 as well as multiple state routes including: • Wadsworth Parkway (State Highway 121) • 120th Avenue (US 287/State Highway 128) • Sheridan Boulevard (State Highway 95 south of US 36) • Federal Boulevard (US 287) The 2008 Comprehensive Roadway Plan Update also provides an assessment of existing traffic conditions and identifies short-term improvements. Street widening, intersection upgrades, and multimodal integration are discussed in this plan.

The 2008 Roadway Plan Update recommends that new roadway projects include “Complete Streets” elements—facility enhancements for people walking, bicycling, and using transit. Where bicycle facilities are added, adequate separation is recommended to minimize the impacts of traffic on bicyclist comfort.

2.6.2 Intersection Upgrades The 2008 Roadway Plan Update also recommends intersection upgrades based on the Level of Service (LOS) analysis conducted. LOS is graded from “A” to “F,” where LOS A is free-flowing traffic, and LOS F is standstill congestion. Recommendations are provided for intersections that were experiencing a rating of LOS D or worse. The intersections specified in the plan are: • Federal Boulevard and 84th Avenue: Add a third northbound and southbound through lane, and southbound, eastbound, and northbound dual left-turn lanes • Federal Boulevard and 92nd Avenue: Add a third northbound and southbound through lane, and dual left-turn lanes for all directions (2016 project) • Federal Boulevard and 104th Avenue: Add a third northbound and southbound through lane, and dual left-turn lanes for all directions (2016 project) • Federal Boulevard and 120th Avenue: Add a northbound through and right-turn lane, a third through lane for eastbound and westbound, and dual left-turn lanes for eastbound and southbound • Simms Street and 100th Avenue: Realign the intersection • Sheridan Boulevard and 88th Avenue: Add a third northbound and southbound through lane • Wadsworth Parkway and 100th Avenue: Add a third northbound and southbound through lane, and southbound and eastbound dual left-turn lanes (Complete)

Although this approach can relieve congestion, wide roads act as barriers for those who are not travelling in personal vehicles, and Westminster’s 2014 Comprehensive Plan acknowledges that roadway improvements should consider impacts for all modes when changes are proposed. Many newer policies are promoted throughout the document, and together, they would help to alleviate congestion by creating a more connected and walkable Westminster.

2.6.1 Street Widening The 2008 Roadway Plan Update recommends widening nine sections of arterials. Recommended widening projects are shown in Table 2.3. Table 2.3: Streets recommended to be widened Street

Section

Widen To

Federal Boulevard

80th Avenue to 104th Avenue

Six lanes

Federal Parkway 120th Avenue to 128th Avenue

Four lanes

Sheridan Boulevard

72nd Avenue to 104th Avenue

Six lanes

Wadsworth Parkway

92nd Avenue to 108th Avenue

Six lanes

136th Avenue

Zuni Street to Huron Street

Four lanes

128th Avenue

Federal Boulevard/Zuni Street to Interstate 25

Four lanes

120th Avenue

Sheridan Boulevard to Pecos Street

Six lanes

Adding through lanes and turn bays addresses vehicular transportation concerns, but does not necessarily improve the city’s multimodal vision. Large intersections are particularly difficult to navigate as a pedestrian or a cyclist.

Widening roadways does not necessarily equate to improving pedestrian or bicycle facilities. The recommendations outlined for widening roadways in the Comprehensive Roadway Plan Update are based predominantly on increasing the motorized vehicle capacity of the roadway. However, with new projects, there is an opportunity to enhance connectivity for multiple travel modes.

Map 2.4 displays the Average Annual Daily Traffic Volumes (AADT) on Westminster’s arterial and collector roadways.

2-23 Westminster’s Mobility Action Plan


FLAGG DR

PUBLIC RD

SPAULDING ST

25 160TH AV

DR

LIC

580 - 4700

HURON ST

EXISTING TRAFFIC VOLUMES* 120TH ST

PUB

4701 - 9300

EST

W TH

WY

PK

R

NO

9301 - 16000

26001 - 38000

DILLON RD

2700

16001 - 26000 18000

144TH AV

16000

15000

*Average Annual Daily Traffic Volumes

6300 ZUNI ST

HURON ST

5200 ZUNI ST

FEDERAL BLVD

HURON ST

3300 76TH AV

TH

76

AV

72ND AV

BROADWAY

000

PECOS ST

4900

138

ZUNI ST

8900

15000

80TH AV

1500

1100

68TH AV

CARR ST

PECOS ST

24000 31000 WAGNER DR

36000 34000

4700

WADSWORTH BD

PIERCE ST

36

70TH AV

68TH AV

95 64TH AV

287

76

BROADWAY

LOWELL BD

TENNYSN ST

121 RALSTON RD

SHERIDAN BLVD

GARRISON ST

62ND AV

LAMAR ST

SIMMS ST

KIPLING ST

G ST KIPLIN

69TH AV

20000

84TH AV

BD

64TH AV

58TH AV

17000

88TH AV

OD WO

66TH AV

74TH AV

4100

7700

88TH AV

EEN

2800

72ND AV

6000

GR

CA

9000

R

ED AS

72

11000 2200

DR

BRADBURN BD

NA DR

80TH AV

RR

25

580 LA MA R

POMO

00 40 12

DR

121 84TH AV

3700

96TH AV

19000 92ND AV 6700

9300

48000

88TH AV

32000

2100

44000 43000 38000 30000

7400

7900

21000

57000

24000 27000 104TH AV 6300 LOWELL BD

38000

HARLAN ST

PY

38000

14000

14000

33000

SHERIDAN BLVD

00 280

WADSWORTH BD 8800

51000

3600

IFF

CH

GARRISON ST

17000

25000

YATES ST

7200 9000

36000 33000

hu r

OAK ST

14

00

7300 3300

TC L

0

ES

0

ALKIRE ST

0

00

490W 0

00

86TH PY

D

EN

EP

IND

S TA N D L E Y L A K E

38

00 ENCEDR

53

0

120TH AV

15000 112TH AV

89

0

00

5400

2200

Ranch Bl vd ch

C

42

3700 96TH AV

00

0

104TH AV

12000 100TH AV

37

00

00

81

48

39000

SIMMS ST

11000

5500

INDIANA ST

28000

14000

36

L PY

ERA

FED

44000

128

287

10000

11000

12000

LOWELL BD

00

100 128

121

124TH AV

ZUNI ST

N

12000 108TH AV

134

5400

MAIN ST

LL

2800

MIDWAY BD

ST

TRIA

136TH AV

V TH A

21000

L KOH

US

16000

128TH AV 12000

10TH AV

10TH AV

IND

WESTLAKE DR

ASPEN ST

287

MAP 2.4: TRAFFIC VOLUME AND ROADWAY WIDTH

EMMA ST


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

2.6.3 Most Congested Arterial Streets Increased availability of multimodal transportation options are needed to help manage congestion in Westminster. Table 2.4 shows the city’s most congested arterial streets. This plan intends to help manage congestion by helping the City to develop transportation options that serve people across the study area. Improved active transportation connections, especially when integrated with the transit network, can help accomplish this goal. Table 2.4: Westminster’s Most Congested Arterial Streets Street

Average Daily Traffic (ADT)

Lanes

% Over % Over General Threshold of Daily Traffic Congestion (1) Capacity (2)

Sheridan Boulevard - 88th Avenue to US 36

4

53,789

73.5%

49.4%

120th Avenue - Lowell Bvd. to Federal Blvd.(3)

4

47,662

53.7%

32.4%

Wadsworth Parkway - 92nd Ave. to I 00111 Ave.

4

43,775

41.1%

21.6%

120th Avenue - Federal Blvd. to Pecos St. (3)

38.9%

19.6%

4

43,063

120th Avenue - Huron St. to 1-25

6

62,183

35.2%

17.3%

Sheridan Boulevard - 88th Ave. to 80th Ave.

4

41,628

34.3%

15.6%

120th Avenue - Sheridan Blvd. to Lowell Blvd. (4)

4

41,213

32.9%

14.5%

Federal Boulevard - 84th Ave. to 80th Ave.

4

41,150

32.7%

14.3%

104th Avenue - US 36 to Westminster Blvd

4

40,006

29.1%

11.1%

Sheridan Boulevard - 80th Ave. to 76th Ave.

4

39,877

28.6%

10.8%

Federal Boulevard - 70th Ave. to BNSF Railroad

4

36,424

17.5%

1.2%

Sheridan Boulevard - 73rd Blvd. - 73rd Ave. to 76th Ave.

4

35,222

13.6%

0

Federal Boulevard - US 36 to 74th Ave.

6

51,280

11.5%

0

Sheridan Boulevard - 104th Ave. to 96th Ave.

4

32,671

5.3%

0

Federal Boulevard - I 04th Ave. to 92nd Ave.

4

31,489

1.6%

0

Church Ranch Boulevard - US 36 to 103rd Ave.

4

31,320

1.0%

0

1) The threshold for congestion is 31,000 ADT for a 3-4 lane road and 46,000 ADT for a 5-6 lane road. 2) The General Daily Traffic capacity is 36,000 ADT for a 3-4 lane road and 53,000 ADT for a 5-6 lane road. 3) To be widened to 6 lanes in 2016 4) 120th Avenue is 3 eastbound lanes in Westminster

2-25 Westminster’s Mobility Action Plan


CHAPTER 3: NEEDS ASSESSMENT


d

MAPWESTMINSTER

DILLON RD

144TH AV

WESTMINSTER’S MOBILITY ACTION PLAN

287 3.1 INTRODUCTION

The existing conditions chapter created a baseline for the conditions that people walking, bicycling and taking transit experience in Westminster. This chapter builds on this foundation, and identifies where there is demand for multimodal transportation and assesses the supply of facilities that link these areas. The assessment of the demand and supply for multimodal infrastructure was informed by 10TH AV 10TH AV several layers of information, ranging from data-driven IND MIDWAY BDdata collected models and a crash analysis, to qualitative US TRI AL LNthrough in-person workshops and online tools. These layers combined illustrate where the most significant needs for improvement exist, by indicating areas of the city 128 287 where there is demand for infrastructure but where insufficient or no facilities are provided. This chapter describes each of these layers in detail.

ZUNI ST

WESTLAKE DR

DATA DRIVEN MODELS

LOWELL BD

ASPEN ST

MULTIMODAL DEMAND 136TH AVANALYSIS V TH A

134

BICYCLE LEVEL OF TRAFFIC 128TH AV STRESS

L KOH

MAIN ST

L PY

ERA

FED

DATA ANALYSIS

36

HURON ST

120TH AV

121

WAGON ROAD PARK AND RIDE

PEDESTRIAN BICYCLE CRASH ANALYSIS

112TH AV

WADSWORTH BD

SHERIDAN STATION

88TH AV

NA DR

BRADBURN BD

76TH AV

AV

ONLINE INPUT MAP D

DB

74TH AV

36

PIERCE ST

ZUNI ST

72ND AV

70TH AV

69TH AV

CARR ST

68TH AV Both quantitative and qualitative sources of data and information were analyzed to assess the needs for multimodal transportation in Westminster. 95

68TH AV

WESTMINSTER STATION

ONLINE SURVEY

64TH AV

LOWELL BD

TENNYSN ST

SHERIDAN BLVD

121 RALSTON RD

LAMAR ST

GARRISON ST

3-1

G ST

TH

76

OO

WADSWORTH BD

CA

ONLINE TOOLS

W EEN

KIPLING ST

DR

80TH AV

GR

66TH AV

DR

R ED

D OO

W

AS CH

RR

MOBILE MEETINGS

84TH AV K OA

POMO

88TH AV

62ND AV

287

Westminster’s Mobility Action Plan

76

BROADWAY

84TH AV

25

DR

121

STAKEHOLDER GROUPS

92ND AV

DOWNTOWN WESTMINSTER

LA MA R

GARRISON ST

88TH AV

HURON ST

96TH AV

PECOS ST

LAKE

FP Y

ZUNI ST

D

EN

EP

IND

LIF

HARLAN ST

R

ED

C EN

STC

INTERNAL WORKING GROUP

BROADWAY

WE

FEDERAL BLVD

C

LOWELL BD

hu r

Ranch Bl vd ch

100TH AV

104TH AV

SHERIDAN BLVD

104TH AV

WORKSHOPS + MEETINGS

ZUNI ST

CHURCH RANCH STATION

WAGNER DR

OA K

ST

JOHNSON ST

W 108TH AV

YATES ST

108TH AV

SIDEWALK CONDITIONS + NEEDS MAP

PEDESTRIAN LEVEL OF SERVICE PECOS ST

ST

128

124TH AV


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

3.2 MULTIMODAL SUITABILITY INDEX The data-driven models described in this chapter use existing conditions data within Geographic Information System (GIS) to assess the demand and supply for multimodal transportation in Westminster. Three tools formed the basis for this analysis:

Westminster High School, along 72nd Avenue and between Sheridan Boulevard and Federal Boulevard, and Park Center and Westmoor Business Park.

• Multimodal Demand Analysis (demand) analyzes origins and destinations of resident trips (Map 3.1) • Level of Bicycle Traffic Stress (supply) analyzes what physical on-street infrastructure currently exists (Map 3.2) • Pedestrian Level of Service and Sidewalk Conditions Analysis (Maps 3.4 and 3.5)

This input is a combination of varied land use types and destinations. Overlays such as retail destinations and parks contribute to this category. “Play” hotspots are dispersed throughout the city, due to the many parks, trails and open spaces connecting to most neighborhoods. Particular areas of heat are located in the neighborhoods east of Standley Lake, South Westminster, and the neighborhoods to the east of US 36 between 120th and 104th Avenues.

Where people play

By analyzing both the demand and supply for multimodal transportation in Westminster, an array of potential improvement opportunities become apparent. This data-driven analysis was complemented by a robust public involvement process, described on pages 3-11 to 3-20.

Where people learn

This input represents where students K-12, at community college, or at university go to school. “Learn” hotspots are concentrated around the schools in Westminster, including the high schools in South Westminster, middle and elementary schools in the neighborhoods between Standley Lake and US 36, and the schools bounded by 120th Avenue and 112th Avenue on the north and south, and Main Street and Federal Boulevard on the east and west.

3.2.1 Multimodal Demand Analysis The Multimodal Demand Analysis model provides a general understanding of expected multimodal activity by analyzing spatial data representative of origins and destinations in the city.1 It results in a composite sketch of demand for walking, bicycling and transit use in Westminster, which is displayed on Map 3.1). In the model, multimodal demand is influenced by where people live, work, play, learn, and access transit.

Where people access transit

This input assesses areas with demand based upon the presence of transit stops (bus, commuter rail, and bus rapid transit) and park-n-rides and usage. It is modeled to reflect demand for Westminster Station, which opened in summer 2016. Transit hotspots are located around the major transit hubs in the city, including Church Ranch Station, Sheridan Station, Wagon Rd Park-N-Ride, and Westminster Station. Data for the transit input was provided by the RTD.

Where people live

This input includes 2010 census block-level density of home locations. These locations represent potential trip origin locations. More trips can be made in areas with higher population density if conditions are right. “Live” trip hot spots are dispersed throughout Westminster, driven by the fact that a large percentage of the city’s land use is residential. Concentrated areas include the neighborhoods east of Standley Lake, South Westminster, southeast of US 36, the neighborhoods between 92nd Avenue and 88th Avenue, west of US 36, and the multifamily Canyon Chase Housing Development.

3.2.2 Composite Demand The composite demand analysis for Westminster was developed by overlaying the factor outputs and applying standard weights to each factor. This analysis shows that the highest potential for multimodal travel demand exists in South Westminster, especially along 72nd Street, Downtown Westminster and the neighborhoods east of Standley Lake, and the neighborhoods bounded by 120th Avenue and 112th Avenue on the north and south, and Main Street and Federal Boulevard on the east and west. The composite demand results are displayed on Map 3.1, and the areas with more demand will be assessed in the recommendations chapter to determine if adequate multimodal facilitates service these areas.

Where people work

This input is based on 2010 total employment numbers by census block. Depending on the type of job, this category can represent both trip attractors (i.e., retail stores or cafes) and trip generators (i.e., office parks and office buildings) in terms of base employment population. Hot spots for the “work” analysis include the area around Downtown Westminster, the area around 1  The Multimodal Demand Analysis model was developed by Alta Planning + Design, Inc., with review and input from the scholastic community and practitioners across the US. This model has been used in numerous North American cities to assess the demand for walking and bicycling.

3-2

Needs Assessment


MAP 3.1: MULTIMODAL COMPOSITE DEMAND SCORE

EMMA ST FLAGG DR

PUBLIC RD

SPAULDING ST The demand model identifies expected multimodal activity by overlaying the locations where people live, work, play, access public transit, and go to school into a composite sketch of demand. Figure 3.1 summarizes this approach.

HURON ST

Example areas representing key ‘Hot Spots’ of Multimodal Demand have been highlighted on this map

25 160TH AV

DR

LIC

120TH ST

PUB

EST

W TH

WY

PK

R

NO

Composite Multimodal Demand LOWER DEMAND DILLON RD

144TH AV

287

Commercial development near Wagon Rd Park-N-Ride

Transit Station

Residential development 10TH AV 10TH AV adjacent to Front Range IND US TRIA Community College and LL N open space land

ZUNI ST

LOWELL BD

ASPEN ST

136TH AV WESTLAKE DR

V TH A

134

128TH AV

L KOH

ST

MAIN ST

MIDWAY BD 124TH AV

ER

FED

128

120TH AV

128

WAGON ROAD PARK AND RIDE

PECOS ST

287

Y AL P

HURON ST

HIGHER DEMAND

36 121

ZUNI ST

36 ZUNI ST

72ND AV PIERCE ST

70TH AV

69TH AV

68TH AV

68TH AV

CARR ST

WESTMINSTER STATION

LAMAR ST

95 64TH AV

62ND AV

TENNYSN ST

WADSWORTH BD

BRADBURN BD

KIPLING ST

GARRISON ST

BD

G ST

OD

WO

KIPLIN

AV

EEN

TH

76

GR

76TH AV

BROADWAY

DR

RALSTON RD

PECOS ST

D

58TH AV

80TH AV

74TH AV

South Westminster - Oldest development area in the city. Consists of small lot residential development along a grid system 121

64TH AV

HURON ST

HARLAN ST DR

GARRISON ST

84TH AV OO

66TH AV

88TH AV

W

LA MA R

NA DR

R

SIMMS ST

88TH AV

D SE

72ND AV

1 Mile

25

K OA

POMO

Downtown Westminster Future medium to high density DR RR mixed-use development CA

72

0.5

SHERIDAN STATION

121 84TH AV

92ND AV

DOWNTOWN WESTMINSTER

A CH

80TH AV

0

96TH AV

88TH AV

86TH PY

FP Y

SHERIDAN BLVD

ALKIRE ST

S TA N D L E Y L A K E

LIF

287

76

BROADWAY

WADSWORTH BD

E

IND

R

ED

NC

DE

N PE

STC

ZUNI ST

WE

FEDERAL BLVD

C

LOWELL BD

hu r

Ranch Bl vd ch

100TH AV

104TH AV

SHERIDAN BLVD

104TH AV

Standley Lake Neighborhoods - concentration of schools and higher density residential development 96TH AV

INDIANA ST

CHURCH RANCH STATION

LOWELL BD

OA K

ST

JOHNSON ST

W 108TH AV

WAGNER DR

108TH AV

YATES ST

SIMMS ST

112TH AV


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

(LTS (LTS2/3) 4)

Research into bicycling mode choice has indicated that all Westminster residents generally fall into four categories: Strong and Fearless riders, who will ride despite challenging traffic conditions (1-3%); Enthused and Confident riders, who will ride in most traffic conditions but prefer dedicated bicycle facilities (5-10%); Interested but Concerned Riders, who would ride but only if comfortable bicycle facilities are provided (50-60%); and those who will never ride a bicycle, for personal or physical reasons (30%). This research indicates that the majority of people in the United States (56-73%) would bicycle if dedicated bicycle facilities were provided. However, only a small percentage of Americans (1-3%) are willing to ride if no facilities are provided.

(LTS 3/2) 3/2) (LTS

Source: Roger Geller, City of Portland Bureau of Transportation. Four Types of Cyclists. http://www.portlandonline.com/transportation/ index.cfm?&a=237507. 2009; 2 D ill, J ., M cNeil, N . F our Types o f C yclists? Testing a Typology t o Better Understand Bicycling Behavior and Potential. 2012.

(LTS 1) (LTS 4)

3.2.3 Bicycle Conditions Level of Traffic Stress Analysis • LTS 3 is the level assigned to roads that would be acceptable to current “enthused and confident” bicyclists • LTS 4 is assigned to roadway segments that are only acceptable to “strong and fearless” bicyclists, who will tolerate riding on roadways with higher motorized traffic volumes and speeds

A bicycle network is likely to attract a large portion of the population if its fundamental attribute is low-stress connectivity. In other words, a network should provide direct routes between origins and destinations that do not include links that exceed one’s tolerance for traffic stress. Each user is different and will tolerate different levels of stress in their journey, so this analysis should be used as a general guide rather than an absolute truth.

Images displaying LTS scores 1 to 4 in Westminster are displayed on page 3-5.

The methods used for the Level of Traffic Stress Analysis were adapted from the 2012 Mineta Transportation Institute (MTI) Report 11-19: Low-Stress Bicycling and Network Connectivity. The approach outlined in the MTI report uses the following variables to classify roadways: • posted speed limit • the number (and width) of travel lanes • the presence of bicycle lanes • Average Annual Daily Traffic Volumes

In general, streets with separated bicycle facilities or streets with very low volume (<3000 vehicles per day) and speeds (<25 miles per hour) would qualify as a low-stress (LTS 1) bikeway, while roadways shared with motor vehicle traffic operating at high speeds and volumes would receive a higher-stress score. The results of the LTS analysis help to identify existing areas with a high level of service, as well as focus areas for improvement. The LTS analysis is specifically focused on the street environment. Adjacent shared-use paths (if present) offer a more comfortable facility type that is not reflected it the LTS score.

The Bicycle Level of Traffic Stress Model has become the industry standard for assessing comfort levels of bicycle networks and has been employed in many US cities, across urban, suburban, and rural contexts.

LTS provides an intuitive framework to describe the benefits of bicycle infrastructure and demonstrates that some roadways may require more intervention than others to provide a truly comfortable experience. For example, the only time a standard bike lane is considered all ages and abilities is a 6 -foot-wide facility on a roadway with posted speed of 30 mph or lower, and the best score achievable on a roadway with four or more travel lanes without installing a separated bike lane is LTS 3.

In figure 3-8, road segments are classified into one of four levels of traffic stress (LTS) based on these factors: • LTS 1 is assigned to roads that would be tolerable for all ages and abilities, including children and elderly adults, to ride • LTS 2 roads are those that could be comfortably ridden by the mainstream adult population 3-4

Needs Assessment


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Level of Traffic Stress Scores

LTS 1

LTS 2

Bicycle lanes with no on-street parking and moderate speeds/ volumes can be attractive for the mainstream population, as in this example on Lowell Blvd (30 MPH speed limit), north of 97th Ave.

Residential streets, such as Owens St, are low-volume and lowspeed (25 MPH speed limit) and are comfortable for a wide range of bicyclists, including children and older adults, even without dedicated facilities (source: Google Streetview)

LTS 4

LTS 3

Collector roadways tend to carry more traffic and have higher speeds, making riding along them more stressful and comfortable only for more capable bicyclists (Image: Lowell Blvd south of 88th Ave) Image: Google Streetview)

Sharing the traffic lane or riding in the shoulder on streets with high traffic volumes and speeds is not comfortable for the majority of bicyclists (Image: Wadsworth Pkwy south of 108th Ave, 55 MPH speed limit)

3-5 Westminster’s Mobility Action Plan


FLAGG DR

PUBLIC RD

SPAULDING ST

25

HURON ST

160TH AV

DR

LIC

120TH ST

PUB

EST

W TH

WY

PK

R

NO

BICYCLE LEVEL OF TRAFFIC STRESS 1: All Ages and Abilities DILLON RD

2: Average Adult 3: Intrepid Adult

144TH AV

287

4: Not Comfortable Transit Station ZUNI ST

LOWELL BD

AV

128TH AV

N

124TH AV

ER

FED

128

120TH AV

128

PECOS ST

287

Y AL P

HURON ST

LL

MAIN ST

TRIA

ST

US

This neighborhood10THisAVbounded by high10TH AV stress roadways, making travel out of MIDWAY BD the area on bicycle uncomfortable for less experienced bicyclists.

TH

134

L KOH

IND

WESTLAKE DR

ASPEN ST

136TH AV

36 121

WAGON ROAD PARK AND RIDE

CHURCH RANCH STATION

HURON ST TH

76

WAGNER DR

D

36 ZUNI ST

72ND AV PIERCE ST

AV

DB OO

74TH AV

76TH AV

BROADWAY

LA MA R

CA

70TH AV

69TH AV

68TH AV

68TH AV

WESTMINSTER STATION

CARR ST

WADSWORTH BD

95 64TH AV

287

76

BROADWAY

LOWELL BD

121 RALSTON RD

LAMAR ST

GARRISON ST

62ND AV

SHERIDAN BLVD

GARRISON ST

DR

80TH AV

W EEN

G ST

84TH AV

BRADBURN BD

RR

DR

88TH AV

GR

KIPLING ST

NA DR

DR

KIPLIN

88TH AV

D

1 Mile

25

OO KW OA

POMO

DR

SIMMS ST

121 84TH AV

SE

64TH AV

58TH AV

SHERIDAN STATION

A CH

66TH AV

0.5

92ND AV

PECOS ST

ALKIRE ST

INDIANA ST

88TH AV

While this neighborhood has low-stress access to Standley Lake to the west, 80TH AV 88th Ave and Wadsworth Parkway, which are high-stress roadways, act as barriers for people seeking to bicycle south and east. This condition exists 72ND AV in other areas of the city that are also bounded by arterial and collector roadways.

0

96TH AV

DOWNTOWN WESTMINSTER 86TH PY

72

FP Y

ZUNI ST

EP

IND

LIF

HARLAN ST

DR

CE

EN

D EN

WADSWORTH BD

96TH AV

STC

ZUNI ST

WE

FEDERAL BLVD

C

LOWELL BD

hu r

Ranch Bl vd ch

100TH AV

104TH AV

SHERIDAN BLVD

104TH AV

TENNYSN ST

OA K

ST

JOHNSON ST

108TH AV

YATES ST

SIMMS ST

112TH AV

MAP 3.2: BICYCLE LEVEL OF TRAFFIC STRESS

EMMA ST


FLAGG DR

PUBLIC RD

SPAULDING ST

25

While major roadways act as barriers along the roadways and at unsignalized crossings, signals provide a connection for bicyclists to move between low-stress DR LIC neighborhood roadways across major streets.PUBMap 3.3 displays LTS 1 and 2 roadways only. Where two LTS 1 and 2 roadways connect, a cluster is created. These connected clusters, shown as multiple streets that are the same color, can be traveled without using any link or crossing with a level of stress higher than LTS 2.

EST

W TH

HURON ST

120TH ST

160TH AV

WY

PK

R

DILLON RD

136TH AV

LOWELL BD

WESTLAKE DR

ASPEN ST

Some neighborhoods are bounded on all four sides by major roadways and are disconnected from destinations by these high-stress facilities.

TH

134

AV

128TH AV

10TH AV

L KOH

The largest clusters exist in neighborhoods that are not intersected by major roadways, including the 287 neighborhoods north and east of Standley Lake and the neighborhoods in South Westminster where a more traditional grid exists. The largest cluster is the neighborhood to the east of US 36. The cluster exists because of the bike lanes along and characteristics of Lowell Boulevard (including traffic volumes and speeds), which 10TH AV provides a low-stress north/southIN connection among DU STR IAL several neighborhoods. This demonstrates the connecLN tivity that on-street bikeways can provide. However, many other neighborhoods128remain isolated, disconnected from destinations by the presence of major roadways, which act as barriers to connectivity.

144TH AV

ZUNI ST

NO

MIDWAY BD

MAIN ST

ST

124TH AV

ER

FED

120TH AV

128

PECOS ST

287

Y AL P

HURON ST

MAP 3.3: BICYCLE LEVEL OF STRESS CLUSTERS

EMMA ST

36 121

SIMMS ST

112TH AV

WAGNER DR DR

BRADBURN BD

KIPLING ST

HURON ST 36 ZUNI ST

72ND AV PIERCE ST

WADSWORTH BD

D

DB OO

SIMMS ST

AV

70TH AV

69TH AV

68TH AV

68TH AV

CARR ST

66TH AV

95 64TH AV

287

76

BROADWAY

121 RALSTON RD

LOWELL BD

62ND AV

TENNYSN ST

GARRISON ST

KIPLIN

G ST

(each color represents an instance where multiple LTS 1 or 2 roadways connect)

SHERIDAN BLVD

64TH AV

LAMAR ST

Connectivity Clusters

58TH AV

TH

76

W EEN

74TH AV

76TH AV

GR

Concrete Trail

1 Mile

80TH AV

BROADWAY

NA DR

88TH AV

84TH AV

DR LA MA R

GARRISON ST

POMO

The existing bicycle lanes along Lowell Blvd provide connectivity DR RR a for several neighborhoods via CA low-stress bikeway facility.

72ND AV

0.5

88TH AV

SE

72

121 84TH AV

25

A CH

80TH AV

92ND AV

Downtown Westminster

PECOS ST

ALKIRE ST

INDIANA ST

96TH AV

88TH AV

86TH PY

0

FP Y

ZUNI ST

EP

IND

LIF

HARLAN ST

DR

CE

EN

D EN

WADSWORTH BD

96TH AV

STC

ZUNI ST

WE

FEDERAL BLVD

C

LOWELL BD

hu r

Ranch Bl vd ch

100TH AV

104TH AV

SHERIDAN BLVD

104TH AV

YATES ST

OA K

ST

JOHNSON ST

108TH AV


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

3.2.4 Pedestrian Conditions - Level of Service Analysis The Pedestrian Level of Service Analysis (PLOS) treats segments and intersections separately. A level of service was identified for each major roadway segment in the study area, and intersections were examined along roadways with a functional classification of “collector” or “arterial” as well. These higher-order roadways present the greatest obstacle to pedestrians, and more data was available for analysis along these corridors.

Dedicated facilities for pedestrians, such as sidewalks and shared use paths, are essential in creating safe travel conditions for pedestrians. This PLOS analysis is based primarily on safety and does not consider factors of the built environment known to make walking an attractive and preferred form of transportation. While built environment factors are not explicitly considered, lower posted speeds and more dedicated pedestrian space will typically correlate with places people want to walk based on the surrounding land uses and urban form (e.g., residential neighborhoods and commercial uses in urban areas with lower-speed traffic).

Analysis Methodology

The selected segment-based PLOS analysis is rooted in the concept that a doubling of travel speed results in a four-fold increase in stopping time and resulting crash severity. According to a review of pedestrian crash severity studies, speed has the following impact on pedestrian fatalities: A PEDESTRIAN HIT BY A VEHICLE TRAVELING A PEDESTRIAN BY AT A A PEDESTRIAN HIT HIT BY A VEHICLE TRAVELING VEHICLE TRAVELING AT AT

25 MPH MPH 35 25 MPH

10

20 10 10

30 30 20 40 20 40 30 40

00

0

SURVIVABILITY SURVIVABILITY

10%%

10

30

50%%

30%

50%

70%

30%%

60

50

70% % 90%

90%

70

89% 89% 68%

HAS AN

OF L

50

SURVIVABILITY

10%

HAS AN HAS A

50 50 6060

90

A PEDESTRIAN HIT BY A VEHICLE TRAVELING PEDESTRIAN HIT AAPEDESTRIAN HITBY BYA A AT VEHICLE TRAVELING VEHICLE TRAVELINGATAT

35 MPH 35 MPH 45 MPH

30 20 2030

20 10 10 10 0 0

0

CHANCE OF

40

40

40

50

50

10%

30%%

10

50% % 70% % 90%

30

50

70

10%

30%

50%

70%

90%

60

60

%

68% 68%

35%

HAS A

50

60

SURVIVABILITY SURVIVABILITY

SURVIVABILITY

%

CHANCE OF SURVIVAL SURVIVAL CHANCE OF SURVIVAL

30

HAS A HAS A

90

%

CHANCE OF CHANCE OF SURVIVAL

SURVIVAL CHANCE OF SURVIVAL

Tefft, B. C. Impact speed and a pedestrian's risk of severe injury or death. Accident Analysis & Prevention 50 (2013) 871-878.

The segment-based PLOS analysis measures pedestrian safety using four factors: posted speed limit, roadway width (number of travel lanes), pedestrian buffer (on-street parking or bicycle lanes), and the presence of sidewalks. Planting strips also provide A PEDESTRIAN HIT BY A an effective buffer and were included in this analysis. Table 2.1 VEHICLE TRAVELING AT A PEDESTRIAN HIT BY A VEHICLE TRAVELING AT 45 MPH outlines the scoring methodology of the PLOS analysis. The PLOS 45 MPH follows a five-point scale, with 1 representing the highest comfort 30 30 20 40 20 40 level. Generally, more pedestrian space on a lower speed roadway 50 10 50 10 segment correlates to a higher comfort level. Where sidewalks 0 0 60 60 are only provided on one side of the roadway, pedestrian comfort 10 30 50 70 90 degrades on multi-lane roadways since pedestrians are forced to HAS A CHANCE OF HAS A SURVIVAL CHANCE OFcross more than two lanes of traffic to reach that sidewalk. Bicycle SURVIVAL lanes or on-street parking act as buffers between pedestrians and motor vehicle traffic, increasing comfort. SURVIVABILITYSURVIVABILITY

10%

30%

50% % 70%

% 90

%

%

%

35% 35%

%

Tefft, B. C. Impact speed and a pedestrian's risk of severe injury or death. Accident Analysis & Prevention 50 (2013) 871-878. of severe injury or death. Accident Analysis & Prevention 50 (2013) 871-878.

Table 3.1: PLOS Scoring Table Speed Limit (mph) <= 25 mph***

Pedestrian Space along Roadway

30 - 35 mph

>= 40 mph

2 lanes

> 2 lanes

2 lanes

> 2 lanes

2 lanes

> 2 lanes

Complete sidewalk* on both sides next to a buffer**

1

1

1

1

2

3

Complete sidewalk *on both sides

1

1

2

3

3

4

Complete sidewalk* on one side next to a buffer**

2

2

2

3

3

4

Complete sidewalk on one side

2

3

3

4

4

5

No dedicated space next to a buffer*

2

3

3

4

4

5

No dedicated space

2

3

4

5

5

5

*A complete sidewalk is defined as a continuous segment without significant gaps that would impede travel by a person with a mobility impairment. This definition does not consider cracking or heaving that would impede travel or result in failure to meet acceptable travel conditions as defined by ADA regulations. Driveways may be counted as part of the continuous surface as long as there are no gaps in the paved surface. **Bicycle lanes and/or on-street parking. ***Scores also apply to 30 mph roadways with traffic calming.

3-8 Needs Assessment

Most Comfortable

Least Comfortable


MAPWESTMINSTER

MAP 3.4 PLOS ANALYSIS

WY

PK

MOST COMFORTABLE

EST

HW

RT

NO

HURON ST

WESTMINSTER’S MOBILITY ACTION PLAN

PEDESTRIAN LEVEL OF SERVICE

1 - Highest Comfort 287

ZUNI ST

136TH AV

5 - Lowest Comfort

AV

134TH

PLOS 1

128TH AV

124TH AV

HURON ST

PECOS ST

FEDERAL BLVD

104TH AV

96TH AV

HURON ST

LOWELL BD

WADSWORTH BD

R ED DE EN

PLOS 2

92ND AV

EP IND

88TH AV

88TH AV

86TH PY

(Image: Independence St)

84TH AV

PLOS Analysis Results

PLOS 3

BRADBURN BD

80TH AV

76TH AV

TH

76

AV

72ND AV

LOWELL BD

WADSWORTH BD

INDIANA ST

ALKIRE ST

NC

96TH AV

SHERIDAN BLVD

ST

108TH AV

OA K

SIMMS ST

112TH AV

100TH AV

(Image: Lowell Blvd)

120TH AV

287

287

The PLOS analysis assessed sidewalk conditions along the major roadways in Westminster. The planning team geocoded sidewalk WESTMINSTER data along major north/south and MAP east/west roadways in MAP OVERVIEW N WESTMINSTER’S MOBILITY ACTION PLAN Westminster. This data was used to perform the PLOS analysis. These roadways carry relatively heavy traffic volumes, and speeds along them tend to be high. These factors combined cause most of the sidewalks analyzed to score PLOS 3-5, even when a buffer is present. Sidewalks that do not have buffers separating the sidewalk from the roadway and segments where a sidewalk existed on only side of the roadway resulted in generally poorer scores. 0

0.5

1 Mile

Summer 2016

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

(Image: 112th Ave)

PLOS 4

Author: SP

Sidewalk Gaps and Needs Map (Image: Sheridan Blvd) LEAST COMFORTABLE

The PLOS model assesses how comfortable it is to walk along major roadways in Westminster. While some roadways are comfortable to walk along, equipped with 5-foot-wide minimum sidewalks that are Americans with Disabilities Act (ADA) accessible and include a buffer between the sidewalk and roadway, many do not. Long segments of major roadways lack sidewalks, and there are also many instances where an existing sidewalk is not wide enough to meet current ADA accessibility requirements. The sidewalk conditions, and areas where sidewalk improvements are needed in Westminster, are displayed on Map 3.5.

PLOS 5

(Image: Federal Blvd)

3-9 Westminster’s Mobility Action Plan


FLAGG DR

PUBLIC RD

SPAULDING ST

25

HURON ST

160TH AV

DR

LIC

120TH ST

PUB

EST

W TH

WY

PK

R

NO

SIDEWALK CONDITIONS & NEEDS Gap in Sidewalk Network Narrow Sidewalk

(likely less than 5’ based on review of aerial imagery)

DILLON RD

144TH AV

Existing Sidewalk

(likely greater than 5’ based on review of aerial imagery)

287

Existing Sidewalk with Buffer

MIDWAY BD

N

124TH AV

ER

HIGHER DEMAND

FED

128

120TH AV

128

287

Y AL P

PECOS ST

Transit Station

HURON ST

LL

MAIN ST

ST

TRIA

AV

128TH AV

L KOH

US

TH

134

10TH AV

10TH AV

IND

ZUNI ST

LOWER DEMAND

LOWELL BD

Composite Multimodal Demand

WESTLAKE DR

ASPEN ST

136TH AV

36 121

WAGON ROAD PARK AND RIDE

CHURCH RANCH STATION 104TH AV

LIF

YATES ST

25

88TH AV

WAGNER DR

SHERIDAN STATION

SE DR

0.5

1 Mile

36 ZUNI ST

72ND AV PIERCE ST

WADSWORTH BD

70TH AV

69TH AV

68TH AV

68TH AV

CARR ST

WESTMINSTER STATION 95 64TH AV

287

76

BROADWAY

LOWELL BD

TENNYSN ST

121 RALSTON RD

LAMAR ST

GARRISON ST

62ND AV

SHERIDAN BLVD

G ST KIPLIN

0

BRADBURN BD

KIPLING ST

SIMMS ST 58TH AV

AV

D

This project did not catalogue ADA66TH AV infrastructure. In building new 64TH AV infrastructure, the City will meet ADA infrastructure requirements.

TH

76

DB OO

72ND AV

74TH AV

76TH AV

W EEN

CA

GR

72

RR

DR

ZUNI ST

80TH AV

80TH AV

BROADWAY

NA DR

A CH

LA MA R

POMO

88TH AV

84TH AV

DR

121 84TH AV

96TH AV

92ND AV

DOWNTOWN WESTMINSTER

88TH AV GARRISON ST

FP Y

HURON ST

WADSWORTH BD

STC

HARLAN ST

ALKIRE ST

INDIANA ST

DR

DE

EN

EP

IND

E NC

WE

LOWELL BD

hu r

C

96TH AV

86TH PY

SHERIDAN BLVD

Ranch Bl vd ch

100TH AV

FEDERAL BLVD

104TH AV

PECOS ST

OA K

ST

JOHNSON ST

108TH AV

ZUNI ST

SIMMS ST

112TH AV

MAP 3.5: SIDEWALK CONDITIONS + NEEDS

EMMA ST


HARLAN ST

WADS

MAPWESTMINSTER

92ND AV YATES S T

WESTMINSTER’S MOBILITY ACTION PLAN

R

PIERCE ST

DR

BRADBURN BD

ZUNI ST

80TH AV

TOTAL COLLISIONS WITH MOTORISTS

TOTAL COLLISIONS WITH MOTORISTS 134 PEDESTRIANS

76T

72N 102 BICYCLISTS

69TH AV

68

68TH AV

64TH AV

SEVERITY OF COLLISIONS SEVERITY OF COLLISIONS

FATALITIES SERIOUS INJURIES

7

5.2%

287

LOWELL BD

In the five-plus years studied, thirty-one fatalities occurred that were related to transportation. Although 121 a majority of these were motor-vehicle fatalities, pedestrian and bicycling RALSTON RD rates per the total count modes have much higher fatality of fatalities reported, as shown in the Severity of Collision graphic. In Westminster, pedestrians are twenty-six times more likely to be killed in a crash and eight times more likely to be injured than people driving a motor vehicle. Bicyclists are ten times more likely to be killed during a crash on a bicycle and six times more likely to be injured than motor vehicle drivers. These exhibits show the importance of prioritizing safety for pedestrians and bicyclists across the transportation network.1

95

TENNYSN ST

LAMAR ST

CARR ST

During the period studied, a total of 12,187 total crashes were reported, 134 crashes involving pedestrians, 102 crashes involving bicycles, with the remainder involving only motor vehicles. Exhibit 1 shows the percentage of crashes in the City of Westminster reported for each mode of transportation.

SHERIDAN BLVD

WADSWORTH BD

D

Safety is the highest priority for the transportation system. This study provides an analysis of historical trends of crashes occurring within the City of Westminster, Colorado, between JanuaryDR2010 and April 2015. Raw crash data RR were provided CA by the City (collected initially from police reports) and summarized to identify trends in collision types and locations for pedestrian, bicycle, and vehicular travel modes. As part of a multimodal access plan for the City—a 74TH AV for transit, report focusing on making recommendations bicycling, and walking—this study focuses more specifically on those transportation modes, touching only briefly on vehicular crashes for comparison purposes. It also does not account for collisions or near-collisions that were not reported to law enforcement.

OO W

LA MA RD

NA DR

3.3 PEDESTRIAN AND BICYCLE COLLISIONS

GARRISON ST

84TH AV K OA

POMO

R ED AS

GARRISON ST

121 84TH AV

88TH AV

WAGNER DR

88TH AV

ZUNI ST

ND

PE

E IND

CH

AV

R

ED

C EN

2

76

2.0%

22

0.2%

85 63.4% 49 48.0% 942 7.9% TOTAL

1  The data was provided by the Westminster Police Department and only includes Westminster police-reported crashes.

3-11 Westminster’s Mobility Action Plan

% OF PED CRASHES

TOTAL

% OF BIKE CRASHES

TOTAL

% OF CAR CRASHES


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Where Collisions Occur

The majority of motorist collisions with both bicyclists and pedestrians occurred at intersections.

LOCATION OFCOLLISIONS COLLISIONS ALONG LOCATION OF ALONGROADWAYS ROADWAYS

Of the 134 pedestrian-related crashes reported, 54 percent occurred at an intersection or were related to an intersection location. Pedestrian-related crashes occurring at driveways, parking lots, and highway interchanges make up less than 10 percent of pedestrian crash locations. This trend is fairly consistent with national trends for crashes involving a pedestrian because intersections are where pedestrians most commonly interact with vehicles.

AT INTERSECTIONS

74%

54%

AT NON-INTERSECTIONS (MID-BLOCK)

Based on crash data, there is a high rate of crashes where pedestrians are attempting to cross the roadway midblock or not at an intersection. Close to 55 percent of the pedestrian crash reports at non-intersection locations noted that the pedestrian entered the roadway, indicating that the pedestrian was trying to cross the roadway.

12%

38%

AT DRIVEWAYS

The majority (74 percent) of bicycle-related crashes occurred at an intersection or were intersection-related. Of the remaining bicycle crashes, 12 percent occurred at non-intersections, and 17 percent occurred at driveways.

17%

6%

Frequency of Collisions

The frequency of motor vehicle collisions with pedestrians and bicyclists increased over the five years analyzed. Pedestrians had a slightly higher number of collisions than bicyclists in all years. Motor vehicle collisions with pedestrians peaked in 2013, and declined slightly in 2014. Between 2010 and 2014, pedestrian collisions increased

by 53 percent. Motor vehicle collisions with bicyclists peaked in 2013, and the frequency of collisions increased by 39 percent between 2010 and 2014. In 2014, the same number of bicycle collisions were recorded as 2013.

ANNUAL COLLISIONS WITH MOTORISTS

NUMBER OF COLLISIONS

40

32 30

20

27 19

21

18

0

2010

2011

25

25

2013

2014

17

15

10

29

2012 YEAR

3-12 Needs Assessment


MAP 3.6: MULTIMODAL COMPOSITE DEMAND SCORE

EMMA ST FLAGG DR

PUBLIC RD

SPAULDING ST Collision Analysis Summary Map 3.6 shows where the 134 pedestrian and 102 bicycle crashes in the city occurred. The highest WESTMINSTER occurrence of pedestrian crashes was at the intersection of 92nd Avenue and Federal Boulevard, WESTMINSTER’S MOBILITY ACTION PLAN with six reported crashes. Most pedestrian crashes occurred at locations on major arterial roads, DR LIC PUB specifically on 88th Avenue, 104th Avenue, Sheridan Boulevard, and Federal Boulevard. In terms WY PK EST WStreet—an of areas with concentrated multimodal activity, at 120th Avenue and Huron intersecH RT NO tion adjacent to the Wagon Road Park-n-Ride—two separate locations experienced four to five pedestrian crashes.

HURON ST

120TH ST

MAP

25 160TH AV

ZUNI ST

The frequency of bicycle crashes is notable along major arterials in the City of Westminster as well. DILLON RD appear to experience 144TH AV North-south arterials, such as Sheridan Boulevard and Federal Boulevard, more crashes than other roadways in the city, similar to east-west connectors, such as 92nd Avenue and 72nd Avenue. Wadsworth Boulevard and 92nd 287 Avenue experienced the highest number of crashes over the five-year study period, with four bicycle crashes.

LOWELL BD

ASPEN ST

136TH AV

WESTLAKE DR

Consistent with other crash studies, intersections exhibited the highest concentrations of reported crashes. For both pedestrian and bicycle crash reports, it is important to note that more than half of crashes recorded had no cause. Reported crashes that do not include a cause are an issue for the city because they do not allow action to be taken to mitigate crashes where patterns occur. Where 10TH AV 10TH AV a cause is reported, the city can better take action to prevent crashes through education, enforceIND MIDWAY BD US ment, and facility improvements. TRIA

V TH A

134

128TH AV

L KOH

MAIN ST

N

124TH AV ER

FED

128 128

120TH AV

PECOS ST

287

Y AL P

HURON ST

ST

LL

36

SIMMS ST

121

112TH AV

C

EN

96TH AV

92ND AV YATES ST

86TH PY

DR

84TH AV

D

ED

OO

AS

W DR

R

BRADBURN BD

ZUNI ST

PIERCE ST

WADSWORTH BD

70TH AV

68TH AV

68TH AV

95

Westminster’s Mobility Action Plan

LOWELL BD

121 RALSTON RD

LAMAR ST

62ND AV

3-13

TENNYSN ST

58TH AV

36

69TH AV

SHERIDAN BLVD

1 Miles

G ST

0.5

KIPLIN

0

72ND AV

64TH AV

GARRISON ST

64TH AV Crash Bicycle/Vehicle

AV

74TH AV

CARR ST

66TH AV

TH

76

D

Pedestrian/Vehicle Crash

76TH AV

DB OO

SIMMS ST

CA

CRASH MAP 72ND AV

80TH AV

W EEN

72

RR

DR

GR

KIPLING ST

80TH AV

ZUNI ST

LA MA R

NA DR

88TH AV

K OA

POMO

CH

GARRISON ST

121 84TH AV

88TH AV

WAGNER DR

88TH AV

25

PECOS ST

ALKIRE ST

INDIANA ST

FP Y

287

76

BROADWAY

EP

IND

S TA N D L E Y L A K E

LIF

HARLAN ST

DR

CE

STC

BROADWAY

WADSWORTH BD

96TH AV N DE

WE

HURON ST

100TH AV

ZUNI ST

hu r

Ranch Bl vd ch

104TH AV

FEDERAL BLVD

104TH AV

LOWELL BD

OA K

ST

SHERIDAN BLVD

108TH AV


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

3.4 STAKEHOLDER AND PUBLIC OUTREACH

Internal Working Group

The planning team led multiple meetings to gather opinions from the community. Residents, visitors, and project stakeholders were able to provide feedback through workshops and mobile meetings held throughout Westminster. Feedback collected through the stakeholder workshops is summarized on page 3-12, and the summary of the mobile meetings is included on pages 3-13 to 3-14.

The internal working group, comprised of city staff from various departments, met early in the planning process to identify barriers to mobility in the community

Stakeholder Workshops

Two stakeholder workshops were held in May 2016 with representatives from community organizations and businesses in Westminster to understand challenges to mobility and opportunities to overcome these challenges.

Mobile Meetings

Three mobile meetings were held in May. These meetings brought the project to the public and were held at a library, a grocery store, and a BRT station in an effort to get a wide range of input from a diverse group of residents and visitors in Westminster.

3.4.1 Workshops Three workshops were held to assess challenges to mobility in Westminster, and opportunities to overcome these challenges. The first meeting was held with representatives from various departments within the city, including Public Works, Community Development, Parks, Recreation and Libraries. The representatives identified issues from varying viewpoints, but, generally, consistent themes were articulated. After this meeting, two additional workshops were held with stakeholder groups, including community and business leaders. At each of these meetings, a presentation was given outlining the existing conditions analysis, and a workshop was conducted that asked attendees to identify challenges to mobility in Westminster. Having representatives from different backgrounds resulted in a robust set of comments that clearly highlighted areas of need in the community. The feedback collected during the internal working group meeting and stakeholder workshops is summarized on Map 3.7. 3-14 Westminster’s Mobility Action Plan


EMMA ST FLAGG DR

PUBLIC RD

EXISTING FACILITIES

25

STAKEHOLDER INPUT

HURON ST

Opportunity

Text

On Street Bike Lanes

160TH AV

R

D BLIC

Trail

PU IMPROVEMENTS NEEDED

120TH ST

EST

W TH

WY

PK

Park-N-Ride Station

Pedestrian (sidewalk & crossings) R NO

RTD B Line/Station

Bicycle (bike lanes, sharrows, side path)

No bike lane creates uncomfortable conditions

Access to Transit Roadway uncomfortable for cyclists, dedicated facility needed

Roadway

This map includes a synthesis of comments collected at both the internal working group meeting and stakeholder meetings. Many of the internal working group comments were related deficiencies in the sidewalk network. Refer to Map 3.5 for a graphic representation of these gaps.

DILLON RD

MAIN ST

LL

N

120TH AV

128

PECOS ST

Opportunity to create a north / south bikeway corridor Tra il

Lack of facility creates uncomfortable conditions

ek Cre Big

in

FEDERAL BLVD

ZUNI ST

Westminster Station

0.5

1 Mile

KIPLIN

0

LOWELL BD

TENNYSN ST

LAMAR ST

121 RALSTON RD

SHERIDAN BLVD

G ST

GARRISON ST

E

LIN

58TH AV

BROADWAY

B RTD

95 Establish formal connection between trail 64TH and Westminster Station AV

Improve connectivity70TH to AV station via Hooker St

68TH AV

62ND AV

287

76

BROADWAY

YATES ST

HURON ST PECOS ST

ZUNI ST

KIPLING ST

LOWELL BD

ZUNI ST

PIERCE ST

School safety crossing

Establish connection from Westminster Station to arts district

CARR ST

WADSWORTH BD

BD

36

72ND AV

69TH AV

68TH AV

AV

Consider shuttle bus from Westminster Station to school district

74TH AV

ek T rail

Establish connection from bike path to 72nd

TH

76

FLYER

OD WO

IRON

EEN

FLAT

76TH AV

GR

Install signsLthat ittle light-up Dr y during school hours Cre

Establish connection from Westminster Station to 80TH AV Downtown Westminster extending the US 36 Bikeway

DR

SIMMS ST

D

Pavers need repair 74TH AV

OO

Bike facility needed along Bradburn

88TH AV

Connections to schools in south Westminster need to be improved

W

64TH AV

y wa ike

CA

66TH AV

School Zone

DR

• Challenging bicycle and pedestrian conditions along corridor minimize mobility • More shelters for bus stops to support young families 72ND AV and people with disabilities • On-street bicycle facilities needed

Poor sidewalk condition with frequent driveways

K OA

R

ED

72

RR

88TH AV

Difficult intersection 84TH AV

Examine feasibility of car share and bike share at redeveloped Westminster Center

Trail

25

6B

NA DR

92ND AV

Sheridan Station

3 US

POMO

Crossing Sheridan Blvd at-grade challenging

BRADBURN BD

121

80TH AV

GENERAL COMMENTS

Downtown Westminster

88TH AV

Install adequate lighting along streets and at bus stops

Shopping destination area

96TH AV

HARLAN ST

High traffic speeds makes difficult pedestrian crossing to access northbound bus

AS

y Creek

PY

CH

Little Dr

Bus connections to Denver Airport desireable 84TH AV

IFF

WAGNER DR

Install pedestrian actuated signal at crossing

TC L

Motorist speeding makes pedestrians uncomfortable

Identify mobility plan for downtown

Farmers’ High Line Canal Trail

104TH AV

SHERIDAN BLVD

a l Trail

H Farm e r s’

Widen side path to 10’

Underpass WE opportunity S

rail nal T e Ca

Traffic calm roadway

DR

ALKIRE ST

INDIANA ST

Poor site distance

DR

CE

EP

IND

S TA N D L E Y L A K E

GARRISON ST

Paved trail connection opportunity

D EN

Bike Connection

igh Li n e C

an

hu rc

Bicycle and pedestrian gap

C

EN

86TH PY

Westminster City Park

Crossing Church Ranch Blvd is challenging, and the islands between slip lanes are too narrow for US 36 Bikeway users

LA MA R

96TH AV

C

100TH AV Dr y

WADSWORTH BD

Intersection lacks traffic control

Church Ranch Station

Farmers’ High Line Canal Trail

ancrossing c Dangerous h R h Blvd under railroad

ree k Tcrossing At-grade rail needed

’ Hig L Far m ers h

Sidewalk on south side of 104th is close to roadway, often traveled by young kids

W 108TH AV Station too far from parking, challenging to walk to station

Complete Trail Gap

OA K

ST

SIMMS ST

JOHNSON ST

Big

112TH AV

Improve connectivity from 112th Av to Church Ranch Station

Lack of bike facility makes corridor challenging

104TH AV

Challenging crossing for trail users

Wagon Road Park and Ride

Dr y

121

Lacking bike connectivity

Long crossing distance to school

124TH AV

L PY

FED

36

108TH AV

il

k Tra

Cree

128TH AV

ERA

Trail floods routinely in narrow / constrained portion 287

Wa

Dr y

Improve bike/ped access

Inadequate sidewalk width, constrained by fences

il lnut Creek Tra

ZUNI ST

LOWELL BD

Big

128

Alternate connection to Tech Park desireable

Convert sidewalk into two-way bike path

MIDWAY BD

ST

TRIA

Formally connect trail V TH A 134to Hospital campus

10TH AV

L KOH

US

WESTLAKE DR

ASPEN ST

136TH AV

IND

Standley Lake Regional Park

Desireable location for bus connections

Trail connection opportunity

287

10TH AV

Widen road to add shoulders

Future trailhead area

Difficult to cross

144TH AV

HURON ST

MAP 3.7: STAKEHOLDER FEEDBACK

SPAULDING ST


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

MAP 3.8 MOBILE MEETING LOCATIONS

3.4.2 Mobile Meetings Three mobile meetings were held over the course of the project. The difference between a mobile meeting and a conventional public meeting, is that with a mobile meeting, the project is moved to locations where Westminster residents already are rather than requiring that they take time to attend a specific project meeting. For these meetings, a booth was set up at three public locations throughout Westminster, including Community Pride Day (at the Irving Street Public Library), the South Westminster Safeway, and Sheridan Station. A large vinyl map of the city was provided at each location, and as people walked by the map, they were asked if they wanted to provide input on the project. Specifically, people were asked to place post-it notes on the maps representing desired improvements related to walking, bicycling, trails, transit and roadway enhancements. In total, over 180 comments were placed on the map. A summary of the feedback collected during these meetings is displayed on Map 3.9. Community Pride Day Mobile Meeting (May 14)

South Westminster Safeway Grocery Store Mobile Meeting (May 14)

Sheridan Station Park-n-Ride Bus Station Loading Area Mobile Meeting (May 19)

3-16 Westminster’s Mobility Action Plan

SHERIDAN STATION

WESTMINSTER PUBLIC LIBRARY SAFEWAY SOUTH WESTMINSTER


EMMA ST FLAGG DR

SPAULDING ST

PUBLIC RD

MAP 3.9: MOBILE MEETING INPUT

EXISTING FACILITIES On-Street Bike Lanes

25 160TH AV

Park-N-Ride Station

HURON ST

Trail DR

LIC

120TH ST

PUB

RTD B Line/Station (Existing/Proposed)

ST

E HW

RT

NO

WY

PK

Bus Route MOBILE MEETING INPUT DILLON RD

Pedestrian

144TH AV

287

Trail

ry ig D

B

L KOH

N

124TH AV

ER

FED

128

Big Dry

yC

H Farm e rs’ 108TH AV

92ND AV

DOWNTOWN WESTMINSTER

FLYER 36

PIERCE ST

72ND AV

WESTMINSTER STATION

69TH AV

CARR ST

68TH AV

70TH AV

68TH AV

95

B RTD

64TH AV

LIN

0.5

1 Mile

KIPLIN

0

LOWELL BD

TENNYSN ST

LAMAR ST

121 RALSTON RD

SHERIDAN BLVD

G ST

GARRISON ST

E

58TH AV

AV

62ND AV

287

76

BROADWAY

DR LA MA R 74TH AV

76

BROADWAY

ZUNI ST

IRON

D

WADSWORTH BD

TH

FLAT

DB OO

76TH AV

W EEN

BRADBURN BD

80TH AV

GR

DR

PECOS ST

DR

KIPLING ST

D

OO

Little Dry Cr eek Trail

CA

72ND AV

W

DR

RR

84TH AV

ay ew Bik

k Trail

64TH AV

88TH AV

K OA

NA DR

36

POMO

SE

SIMMS ST

88TH AV

A CH

ry Cree

66TH AV

25

121 84TH AV

80TH AV

72

SHERIDAN STATION

US

GARRISON ST

88TH AV

Little D

ZUNI ST

96TH AV

Farmers’ High Line Canal Trail

86TH PY

FEDERAL BLVD

FP Y

ZUNI ST

ALKIRE ST

S TA N D L E Y L A K E

LIF

HURON ST

EP

IND

STC

HARLAN ST

DR

CE

EN

D EN

WE

LOWELL BD

ek T rail

Line C

YATES ST

gh

Farmers’ H i

Cre

96TH AV

Line Canal Trai igh l

104TH AV

SHERIDAN BLVD

hu r

C

WADSWORTH BD

Standley Lake Regional Park

100TH AV

Westminster City Park

a n al Trail

ST OA K

CHURCH RANCH STATION Ranch Bl vd ch

Dr y

WAGON ROAD PARK AND RIDE

W 108TH AV

104TH AV

Big

INDIANA ST

112TH AV

rail t Creek T JOHNSON ST

SIMMS ST

Big

Dr

121

k Trail Cree

PECOS ST

kT rai l ree

36

Y AL P 120TH AV

128

287

Walnu

128TH AV

HURON ST

LL

MAIN ST

TRIA

il k Tra

Cree

MIDWAY BD

ST

US

V TH A

134

10TH AV

10TH AV

IND

LOWELL BD

ASPEN ST

Roadway

WESTLAKE DR

Transit

ZUNI ST

136TH AV

Bicycle


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

3.4.3 Online Engagement Tools Westminster residents were invited to comment on the existing bicycling infrastructure through two online means: a traditional question and answer survey and a map-based survey. The question and answer survey, available through the project webpage, collected user responses that were then tabulated by the team, while the online mapping tool allows residents to comment on specific locations. Analysis of the community responses are detailed in this section. Online Survey Results

The online question and answer survey, which was deployed in April 2016 and closed at the end of June 2016, was available in both English and Spanish and received 225 total responses. Respondents were asked sixteen questions about their transportation habits and demographic information. Residents identified their primary transportation mode for work and errands, their frequency of non-car transportation use and destinations, and their reasons for taking alternate modes of travel. The survey also provided an opportunity to share obstacles to travelling using alternate modes of transportation and priorities for future transportation investment.

Similar to census data, most respondents commute to work by driving alone, though transit, bicycling, and walking mode share were higher in the online survey than census commute to work data. Residents indicated that their primary reasons to walk or bicycle were for health benefits (88 percent of respondents) and time outdoors (75 percent). The survey also suggests that utility and recreational biking and walking far outpace active transportation commuting in Westminster, and highlights that there is likely a significant amount of walking and bicycling activity that is not being captured in commute to work census data. While 54 percent of respondents indicated that they do not currently use transit, those that did identified environmental impacts and multitasking as their primary reasons for using it. The top barriers to bicycling or walking identified were safety related, with traffic speed (56 percent), difficult crossings (53 percent), and inconvenient routes (44 percent) topping the list. Time was the primary barrier to transit usage (63 percent). Residents requested most investment in paved paths and trails (59 percent) and improved crossings (51 percent). The results of the survey are included in Appendix C.

The online input map was used to gather feedback about walking, biking and using transit in Westminster. Respondents were able to place points that represented barriers to mobility, and also draw lines corresponding to comfortable bicycling/walking routes, as well as routes that needed improvement. The online input map results are displayed on pages 3-19 to 3-20.

3-18 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

DRAFT 25

Online Input Map Results EST

HW

RT

NO

HURON ST

Map 3.10: Barriers to Bicycling: 61 Submissions

The online mapping software, Wikimapping, allows users to draw lines and drop points within an online map, and add comments to other people’s input. Subsequent visitors can add additional comments and agree or disagree with existing comments. The online input map used for Map Westminster included the following base layers: existing street, bikeway and transit infrastructure.

WY

PK

287

ZUNI ST

136TH AV

128TH AV

Residents were asked to identify barriers to bicycling, walking, or using transit and also draw lines corresponding to comfortable bicycling/walking routes, as well as routes that needed improvement. In total, 246 individuals participated with the map.

L PY

ERA

FED

128 128

HURON ST

287

36

SIMMS ST

121

108TH AV

ALKIRE ST

INDIANA ST

S TA N D L E Y L A K E

96TH AV

92ND AV

Downtown Westminster

88TH AV 86TH PY

HURON ST

Standley Lake Regional Park

96TH AV

LOWELL BD

WADSWORTH BD

100TH AV

25

88TH AV

121

80TH AV TH

76

76TH AV 72

WADSWORTH BD

72ND AV

36

DRAFT

25

25

WY

PK

121

0

0.5

1 Mile

ST

WE

TH

R NO

LOWELL BD

95

HURON ST

ST

WE

TH

R NO

WY

PK

287

DRAFT

76

Map 3.12: Barriers to Transit MAPWESTMINSTER OVERVIEW MAP

Map 3.11: Barriers to Walking 30 Submissions

N

WESTMINSTER’S MOBILITY ACTION PLAN

11 Submissions

287

Summer 2016

287

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

Author: SP

ZUNI ST

136TH AV

ZUNI ST

136TH AV

128TH AV

128TH AV

L PY

ERA

FED

128

36

92ND AV

88TH AV 86TH PY

121

96TH AV

Downtown Westminster

80TH AV

36

72ND AV

0.5

1 Mile

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Summer 2016

N

287 121

DRAFT

76

OVERVIEW MAP

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

AV

36

95

LOWELL BD

95

0

TH

76

76TH AV 72

0

3-19

0.5

LOWELL BD

WADSWORTH BD

72ND AV

AV WADSWORTH BD

TH

76

76TH AV

121

25

88TH AV

121

80TH AV

72

HURON ST

ALKIRE ST

25

88TH AV

S TA N D L E Y L A K E

LOWELL BD

WADSWORTH BD

HURON ST

Standley Lake Regional Park

FEDERAL BLVD

SHERIDAN BLVD

Westminster City Park

96TH AV INDIANA ST

LOWELL BD

WADSWORTH BD

ALKIRE ST

92ND AV

Downtown Westminster

108TH AV

100TH AV

96TH AV

88TH AV 86TH PY

FEDERAL BLVD

SHERIDAN BLVD

Westminster City Park

100TH AV

INDIANA ST

SIMMS ST

SIMMS ST

121

108TH AV

S TA N D L E Y L A K E

HURON ST

HURON ST

36

Standley Lake Regional Park

128

287

121

96TH AV

L PY

ERA

FED

128

128

287

AV

HURON ST

Conflict Areas Maps 3.10 to 3.12 display conflict areas identified by the online map respondents. Each map displays the feedback collected by point class, including Barriers to Bicycling (Map 3.10), Barriers to Walking (Map 3.11), and Barriers to Transit (Map 3.12). The points have been made transparent in these maps so that locations where multiple points were place are darker, helping to indicate areas of concentrated need. Map DRAFT 3.13 displays all of these points as a composite map.

FEDERAL BLVD

SHERIDAN BLVD

Westminster City Park

1 Mile

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Author: SP

Needs Assessment

Summer 2016

N

287

DRAFT

76

OVERVIEW MAP

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

Author: SP


PUBLIC RD

FLAGG DR The circles shown on this map represent the SPAULDING ST density of all point comments collected via the online input map. Areas that appear darker represent locations where a larger number of comments DR BLIC were placed,PUand are indicative of locations where WY PK ST there is a general consensus for improvements. WE H RT NO This composite map includes points representing barriers to bicycling, walking, and transit.

120TH ST

Conflict Area

25 160TH AV

HURON ST

High Priority Conflict Area

The lines shown on this map represent the density of all line comments collected via the DILLON RD online input 144TH AV map. Areas that appear darker are indicative of 287 there is a general consensus locations where for improvements. This composite map includes lines representing bicycling and walking routes that need improvement, which are both colored differently. These lines also represent desirable routes that will be analyzed in the recommendations chapter.

Walking Route Needs Major Improvements

L KOH

128TH AV

MIDWAY BD

No bike lane, shoulder, or sidewalk along this section of 112th Ave

N

128

Conflict areas on feeder roads to Route 36

No sidewalks and very difficult to bike

124TH AV

ER

FED

120TH AV

128

287

Y AL P

Conflict areas on feeder roads to Route 36

PECOS ST

LL

MAIN ST

TRIA

ST

US

High conflict area on 120th Avenue

V TH A

134

10TH AV

10TH AV

IND

LOWELL BD

ASPEN ST

136TH AV WESTLAKE DR

Walking Route Needs Improvements

High conflict area on 128th Avenue

HURON ST

Bike Route Needs Improvements

ZUNI ST

Bike Route Needs Major Improvements

36 121

108TH AV

Westminster City Park

WAGNER DR

ZUNI ST

HURON ST

PECOS ST

BD

36 ZUNI ST

72ND AV PIERCE ST

BROADWAY

AV

74TH AV

70TH AV

69TH AV

68TH AV

CARR ST

68TH AV

95 64TH AV

287

76

BROADWAY

121 RALSTON RD

LAMAR ST

GARRISON ST

62ND AV

LOWELL BD

GARRISON ST

DR

BRADBURN BD

TH

76

OD

WADSWORTH BD

76TH AV

WO

Difficult to bike along 92nd Ave to get to Wadsworth BLVD from the mall area

EEN

KIPLING ST

80TH AV

GR

G ST

DR

KIPLIN

High conflict area at Sheridan Station intersection

D

SIMMS ST

OO W

1 Mile

88TH AV

84TH AV

R

64TH AV

88TH AV

ED

66TH AV

58TH AV

High conflict area on 88th Avenue near Westminster Center

LA MA R

NA

No safe way to get down Wadsworth BLVD DR RR the Semper and to CA Jefferson Academy Elementray schools

72ND AV

25

AS CH

72

0.5

Downtown Westminster

K OA

POMO

High conflict areaDR at intersection of 92nd Avenue and Route 121

80TH AV

92ND AV

121 84TH AV

High conflict area near school on Harlan Street

96TH AV

88TH AV

86TH PY

0

FP Y

TENNYSN ST

ALKIRE ST

INDIANA ST

S TA N D L E Y L A K E

LIF

HARLAN ST

E

EP

IND

R

ED

NC

E ND

WADSWORTH BD

96TH AV

STC

ZUNI ST

WE

Standley Lake Regional Park

FEDERAL BLVD

C

LOWELL BD

hu r

Ranch Blv d ch

100TH AV

104TH AV

SHERIDAN BLVD

104TH AV

YATES ST

OA K

ST

JOHNSON ST

W 108TH AV

SHERIDAN BLVD

SIMMS ST

112TH AV

MAP 3.13: POINT FEATURE COMPOSITE MAP

EMMA ST

LEGEND


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

3.5 NEEDS ANALYSIS CONCLUSION Evaluating both data-driven models and community input, Westminster exhibits some areas that have adequate multimodal facilities. However, there are needs for multimodal infrastructure improvements along major roads, connectivity between neighborhoods, and better access to transit. The following bullets summarize the key findings from each layer of the Needs Analysis.

DATA DRIVEN MODELS MULTIMODAL DEMAND ANALYSIS

• Demand was found to be dispersed throughout the community and concentrated in Westminster’s more dense residential neighborhoods, commercial corridors, transit hubs, and near Downtown Westminster. • Ensuring strong multimodal connections are available to highdemand areas is paramount.

BICYCLE LEVEL OF TRAFFIC STRESS

• Most neighborhood streets scored Level of Traffic Stress of either 1 or 2, indicating that they are comfortable for a wide range of bicyclists, regardless of their age and ability, since they tend to be primarily low-speed and low-volume roads. • Arterials and collectors were found to be more stressful, scoring an LTS of 3 or 4, and act as barriers to connectivity for on-street bicyclists. • Improvements along these roadways need to be prioritized to reduce barriers to mobility. • Trails help to increase connectivity, but some low-stress clusters are not serviced by the paved trail system and remain isolated.

PEDESTRIAN LEVEL OF SERVICE

DATA ANALYSIS PEDESTRIAN BICYCLE CRASH ANALYSIS

SIDEWALK CONDITIONS + NEEDS MAP

• Of the roadways analyzed, those with buffers along lowervolume/-speed roads were found to be the most comfortable. Many arterials carry relatively heavy traffic volumes at moderately high speeds, causing most of the sidewalks analyzed to score PLOS 3-5. • Although many arterials and collectors are equipped with sidewalks that have buffers, many others have no sidewalks, or the existing sidewalks do not meet ADA standards—improvements need to be prioritized along these roadways. • In Westminster, pedestrians are twenty-six times more likely to be killed in a crash and eight times more likely to be injured than people driving a motor vehicle, indicating that walking/bicycling is more dangerous than driving and highlighting the need for better walking/bicycling infrastructure. • Over the crash study period from 2010 to 2014, pedestrians crashes increased by 53 percent, and bicycle collisions increased by 39 percent, emphasizing the need to more rapidly implement bike/pedestrian improvements to counteract this rise. • The majority of both pedestrian and bicycle collisions occurred at intersections (74 and 54 percent respectively) along the arterial roadway network, highlighting where improvements are needed most, especially for pedestrians.

3-21 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

WORKSHOPS + MEETINGS INTERNAL WORKING GROUP

STAKEHOLDER GROUPS

• Critical gaps in the sidewalk network along arterial and collector streets exist—efforts should be focused on closing these gaps. • Several intersections represent challenging crossings, especially along the arterial/collector network—efforts should focus on improving crossing conditions. • Trail network needs to provide better connectivity if it is to be used for transportation. • Develop connections from Downtown to the Westminster Station, and other points south. • Improve sidewalk conditions in South Westminster, and enhance connectivity to destinations in the area, especially to schools. • Complete gaps in the trail network to facilitate multimodal mobility. • Install on-street bike infrastructure along key corridors in Westminster. • Make crossing improvements across the city’s arterial and collector network.

MOBILE MEETINGS

• Segments of sidewalk need to be repaired and widened, and gaps in the sidewalk network need to be closed. • Better multimodal connections need to be made to destinations and neighborhoods within South Westminster and to Sheridan Station and Westminster Station. • Crossing the arterial network can be challenging for bicyclists and pedestrians. • Key north/south and east/west on-street bicycle facilities need to be installed.

ONLINE INPUT MAP

• Barriers to bicycling/difficult bicycling routes were the most frequent input. • Barriers along US 36 were prevalent in responses, especially near the park-n-ride facilities. • Desire for more on-street bicycle facilities was strong, especially along north/south corridors (Simms Street/Wadsworth Boulevard/ Lowell Boulevard and 112th/92nd and within South Westminster).

ONLINE SURVEY

• Residents indicated that their primary reasons to walk or bicycle were for health benefits (88 percent of respondents) and time outdoors (75 percent). • The top barriers to bicycling or walking identified were safety related, with traffic speed (56 percent), difficult crossings (53 percent), and inconvenient routes (44 percent) topping the list; time was the primary barrier to transit usage (63 percent). • Residents requested most investment in paved paths and trails (59 percent) and improved crossings (51 percent).

ONLINE TOOLS

3-22 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Page intentionally left blank

3-23 Westminster’s Mobility Action Plan


CHAPTER 4: RECOMMENDATIONS


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

4.1 INTRODUCTION

NETWORK RECOMMENDATIONS DEVELOPMENT

This chapter presents overall network recommendation for MAP Westminster, and concludes with a series of implementation next steps, including funding sources, project prioritization and cost estimates. The development of the network recommendations was an iterative and collaborative process. The multimodal network must establish seamless, connected routes that link people to their destinations. Recommended improvements must consider the existing environment, as well as the planned or expected future context. The needs of all roadway users, including the safety and comfort of people walking, bicycling, and accessing transit, must be balanced with roadway characteristics and corridor constraints. The outcome of this collective process represents a practical approach to improving the Westminster’s multimodal network over time. The majority of this plan’s recommendations provide guidance that can be used to progress projects towards implementation. Some recommendations are conceptual, and additional coordination will be needed for implementation. All recommendations are subject to change and refinement as site conditions and development patterns change, and as other adjacent or intersecting projects are implemented. Additionally, some projects may require feasibility studies to verify routing or applicability.

1

EXISTING CONDITIONS ANALYSIS

EXISTING FACILITIES

2

4.2 OVERALL RECOMMENDATIONS

BARRIERS

COMMUNITY IDENTIFIED NEEDS

FACILITY CONNECTIVITY GAPS

LEVEL OF TRAFFIC STRESS

CONNECT ACTIVITY CENTERS

ADDRESS BARRIERS

RECOMMENDATIONS DEVELOPMENT

REVISE PREVIOUSLY PROPOSED

Overall recommendations are classified into one of four categories: Trail Projects, Bicycle Projects, Pedestrian Projects, and Complete Street Projects. Within each category, several types of improvements are recommended. The specific improvements are presented in the project description tables, which are included in Appendix A. The following section summarizes the types of improvements proposed.

DESTINATIONS

NEEDS ANALYSIS

MAPPING CRASH DATA

3

PREVIOUSLY PROPOSED FACILITIES

Trail Recommendations

These projects are intended to improve the connectivity of the trail system, and upgrade existing trails to make them more compatible for utilitarian trips. Within this category, multiple improvements are recommended, including:

4-1 Westminster’s Mobility Action Plan

CONNECT NETWORK GAPS


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

• Shared Use Paths – Includes the construction of new shared use paths where they currently do not exist. All shared use path recommendations should be constructed in conformance with AASHTO guidelines. • Trail Surface Material Upgrades – Includes upgrading the trail surface material of gravel trails to concrete, which requires removal of the existing gravel trail, and installing a new, concrete surface. Concrete trails are more appropriate for bicyclists who are using the trail system for active transportation purposes. • Reconstruct Sidewalks into Sidepaths – Includes widening existing sidewalks to 10 feet minimum, which requires removal of the existing sidewalk, and installing a new, concrete shared use path • Spot Improvements – In addition to the linear trail improvements, several types of spot improvements are included in the project descriptions as well. The range of spot improvements are described on pages 4-3 to 4-5.

posted speed of 25 mph and target motor vehicle volumes of less than 1,500 vehicles per day (with a maximum 3,000 vehicles per day). Many streets in Westminster exhibit these characteristics already, and minor modifications, such as the addition of signage and pavement markings, could cost-effectively designate key corridors as neighborhood greenways. These improvements, combined with modifications at major intersections, make this type of facility intuitive and comfortable for a wide range of people to ride a bicycle or walk. Buffered Bike Lanes

Bicycle Recommendations

These projects are intended to improve access for bicyclists from neighborhoods to destinations throughout Westminster. They will also provide connections to existing trails, helping to expand the multimodal network. Some of the types of bikeway improvements recommended already exist in Westminster. These facilities include:

Many streets is Westminster, which already exhibit low volumes and speeds, could be designated neighborhood greenways through the application of shared lane marking and signage.

Buffered bike lanes are conventional bike lanes that are enhanced through the application of a diagonally striped buffer space. While not providing physical separation, this creates a wider buffer area between vehicles and bicyclists than a conventional six inch bike lane stripe. By providing the buffer, bicyclists ride further away from vehicles, and this facility type provides a higher level of comfort compared to conventional bike lanes as traffic volumes and speeds increase. Buffered bicycle lanes can be enhanced through the application of flexible posts to provide physical separation from motor vehicle traffic.

• Bike Lanes – This type of facility provides a dedicated space within the roadway for bicyclists to travel, and uses signage and striping to delineate the right-of-way assigned to bicyclists and motorists. Bike lanes encourage predictable movements by both bicyclists and motorists, and have been found to decrease stress levels for both groups. • Shared Roadways - Shared roadways use pavement markings and signage to communicate to motorists and bicyclists to operate within the same travel lane, either side by side or in a single file, depending on the roadway configuration. Typically, this facility is used to connect other bikeways (usually bike lanes), or designate preferred routes through high-demand corridors. While these facility types exist in Westminster, new bikeway facility types are recommended as part of this plan, including neighborhood greenways and buffered bicycle lanes. Neighborhood Greenways Neighborhood Greenways are local streets with low motorized traffic volumes and speeds that have been designated as bicycle routes. Neighborhood greenways should have a maximum

Buffered bike lanes provide more separation from motor vehicles than conventional bike lanes, and help to maintain comfort levels for bicyclists on higher speed and volume roadways.

4-2 Chapter 4: Recommendations


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Pedestrian Recommendations

Complete Street Projects

These projects are intended to improve pedestrian access in Westminster. Pedestrian improvements include constructing new sidewalks where they currently do not exist, constructing wider sidewalks, or improving crossing conditions at locations where crossing the roadway can be uncomfortable or challenging. The range of pedestrian improvements include: • Sidewalks – These projects would fill gaps in the sidewalk network, constructing 5 to 8 foot wide sidewalks in areas of Westminster where they currently do not exist. Along arterial and collector roadways, which carry higher traffic volumes, it is recommended that sidewalks be separated from the roadway by a grass buffer. • Spot Improvements - In addition to the linear sidewalk improvements, several types of spot improvements are included in this category of recommendations. The range of spot improvements are displayed on pages 4-3 to 4-5.

These projects are focused on improving bicycle, pedestrian, and transit connections along major corridors in the community. Projects within this category represent key corridors that should be studied further to analyze issues and develop block-by-block solutions to improving bicycle and pedestrian access. These corridors tend to carry high traffic volumes, and many of them corridors are constrained, meaning that the roadways have been widened to their maximum possible extent within the existing right-of-way. To improve conditions, travel lane narrowing or reallocation may be required to meet the needs of all users. The trade-offs associated with these changes will be identified when these projects are studied in more detail. Potential reconfiguration options and a high-level assessment of proposed improvements are provided for each project.

Spot Improvements

Within each of the four categories, spot improvements are also recommended for many of the projects. The spot improvements should be installed with the linear facilities as a single project. Generally, the spot improvements make crossing roadways more comfortable. The range of spot improvements included in the recommendations are described below. Crosswalks – Some crossing locations would benefit from the installation of a crosswalk where they were missing, or upgrading an existing crosswalk to have higher visibility.

Yield Lines – This treatment clearly indicates the point at which motorists should yield in advance of a crosswalk. On multi-lane approaches yield lines should be set back far enough so that both lanes can see crossing pedestrians.

4-3 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Median Refuge Island - A median refuge island reduces the exposure time experienced by a pedestrian in an intersection. While these islands may be used on both wide and narrow streets, they are generally applied at locations where speeds and volumes make crossings challenging, or where three or more lanes of traffic make pedestrians feel exposed or unsafe in the intersection. Median refuge islands have been proven to improve safety of pedestrians crossing mid-block.

Rectangular Rapid Flashing Beacons (RRFBs) – RRFBs use an irregular flash pattern similar to emergency flashers on police vehicles and can be installed on either two-lane or multi-lane roadways. RRFBs are used to alert drivers to yield where pedestrians and/or bicyclists have the right-of-way crossing a road. RRFBs drastically improve motor vehicle yielding compliance over no beacon and even considerably over older steady flashing yellow beacons. RRFBs can be either user or sensor activated.

Raised Crossings - Raised crossings, or speed tables, can be installed mid-block or in channelized right turn lanes. Their purpose is to slow motor vehicle speeds by vertically deflecting vehicles. Speed tables are distinct from speed humps, in that they are longer, and flat topped, with a height of 3-3.5 inches and length of 22 feet. If installed mid-block, raised crossing can be combined with curb extensions to narrow the roadway and decrease the crossing distance for pedestrians. Speed tables have been found to be an effective treatment to both increase yield compliance of crossing pedestrians and moderate vehicle speeds.

Pedestrian Hybrid Beacons – Pedestrian Hybrid Beacons provide a high level of comfort for crossing users through the use of a redsignal indication to stop conflicting motor vehicle traffic. Hybrid beacon installation faces only cross motor vehicle traffic, stays dark when inactive, and uses a unique ‘wig-wag’ signal phase to indicate activation. Vehicles have the option to proceed after stopping during the final flashing red phase, which can reduce motor vehicle delay when compared to a full signal installation. Hybrid beacons are used to improve non-motorized crossings of major streets in locations where side-street volumes do not support installation of a conventional traffic signal. Hybrid beacons can operate in areas of heavy traffic and multiple travel lanes where a RRFB would be less effective 4-4 Chapter 4: Recommendations


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Full Traffic Signals - Signalized crossings use a red-signal indication to stop conflicting motor vehicle traffic. A full traffic signal provides standard red-yellow-green traffic signal heads for all legs of the intersection.

Underpass - Bicycle/pedestrian underpasses provide critical links by providing grade-separated crossings of major barriers, such as railroads and major roadway corridors. There are no minimum roadway characteristics for considering grade separation. Depending on the type of facility or the desired user group, grade separation may be considered in many types of projects, though the cost to implement such facilities is significant.

MAP 3.1 RECOMMENDATION ZONES 4.2.1 Mapping Recommendations

ZONE 1

Recommendations for MAP Westminster are presented in three zones. The division of the city into three zones was done to simplify the presentation of information. Maps 4.2 to 4.4 display the recommendations by zone, and Appendix A includes tables of the recommendations divided by Zone and Project Category. Details for each project are provided in the table, including a project ID, description of the project, project extents, cost and prioritization score. Being a Mobility Action Plan, recommendations are focused on projects that should be implemented in the near term, providing multimodal connections between key activity generators in the city. Recommendations from past plans are included on these maps as well, to ensure that other proposed recommendations from these plans are implemented as opportunities arise, in addition to MAP Westminster projects.

ZONE 3

WESTMINSTER

ZONE 2 4-5 Westminster’s Mobility Action Plan


MAP 4.2: ZONE 1 RECOMMENDATIONS

INSET MAP

EXISTING CONDITIONS

MAPWESTMINSTER ZONE 1

Trail Underpass Trail Head

149th

145th

Lipan

Natural Surface Trail

146th

Ja 145th so n

Sidewalk (Major Road)

148th

The Orchard Town Center

144th Ave

Sidewalk Gap (Major Road)

WESTMINSTER

147th

Orchard

Osage

Pecos

Gravel Trail

Kalamath

148th

Concrete Trail

Huron St

Fox

On Street Bike Lanes

Delaware

T

WESTMINSTER’S MOBILITY ACTION PLAN

d

142n

Park-n-Ride Station

MCK AY LAKE

14

1s

School

t

Lexingto n

140th Le xin gt on

1.1

1.1

136th Ave

Pedestrian Projects

Bike Lanes

#

Bicycle Projects

Shared Lane Markings

#

Trail Projects

Signed Route

1.1

Amherst Park

th

129

Har

eek Trail Big Dry Cr

mo

128th Ave

ny

128th Ave

Bry an t

1.6

eC an

Navajo

Pecos St Osage

Clay

ck

Melody 116th

1.6

Wagon Road Park and Ride

jo va Na

111th

Bryant

Clay

Huron St

one Shosh

h 4t 11

Grove

Banno

sS t NP ico

Tejon

Zuni

Beach

Clay Clay

Federal Blvd

kT rai l ree Knox

113th

rail al T

rs’ High L i n Farme

Valley View 106th Park

4-6

Northpark

Meade

1s

t

101st

NORTHGLENN 104th Ave

287

Chapter 4: Recommendations rove 10

Huron St

10 7 Bruchez th

Bryant 5th

an

Irving

Juli

103rd

104th

108th

107th

10

Federal Blvd

Grove

105th

1.10 107th

Hooker

Perry Wolff

Zenobia

Benton

100th

id

104th Ave

102nd

112th Ave

Dale

ZONE 2

yR

Winsor Park

Eliot

103rd

ac

g Le

ge

105th

Farmers’ High Line Canal Trail

ZONE 1

36

yC Dr

10

1.3

121st

108th

King

th

7th

Stuar t

105

1.9

108th

Lowe ll

h

Vrain

Sheridan Blvd

Winona

Cree

6t

1.9

y Perr

10

110th

1.7

Creek

it

Yate s

110th

bb Ho

D ry

Cotto n

th

105th

d

111th

110th

Lowell

109

1.8

1.2

1.4

115th

Quivas

th

113

1.6

h 9t

Westminster City Park

r

10

Big

102n

Perry

Big

Wo V lff rai n

k Trail

h

ca tu

114th

h

Chase

9t

Lowell Stratfor

Sheridan Blvd

Chase

Eaton

Wolff Wi no na Vrain

Wo lff

Front Range Community College

1.4

1.2

121st

Club

De

h

6t

11

1.5

akes dL 11 3th

1.7 Vrain

Gray

s

lan

Ha r

all

Ames

Lamar

Kendall

Newland Otis

Ing

10

Countr y

nS tW

115th

111t

ste

r

3th

Gray

1.8

min

Westfield Village Park

5th

11

1.8

1.9 West

ZONE 3

110th

110th

1.4

th

118

NT ejo

vas

th

108th

11

1.3

1.7

110

118th

119th

a ol ce Os 116th

1.2

122nd

128

Qui

112th Ave

tre Park Cen

ot Wyand

n Fento

th

Harlan

113

115th

115th Jay

Depew

Marshall

Ryan Park

Benton

Gray

Gray

Main St

1

117th

1.1

120th Ave

118th

25

Willowbrook Park

y

Delaware

e NF

rail eek T ry Cr

119th

rn bu ad Br

th

kw al P der

120th Ave

Utica

116

5th 12

Lowell Blvd

1.4

1.5

h 15t

rm

124th

Big D

118th

125th

1.3

BROOMFIELD

Main

127th

Pecos

Big Dry Creek Park

Home Fa

1.2

1.5

Huron St

2n

d

rd

Delaware I-25 Trail

#

133

Pecos

Side Path

4th

13

Wyandot

Zuni St

Trail

Inclusive of pedestrian and bicycle improvements; dashed line denotes bicycle facility recommendation

h

Cheyenne Ridge Park

13

Shoshone

Complete Street Projects

#

13

5t

as Quiv

From Open Space Stewardship Plan and Bicycle Master Plan

an

PROPOSED FACILITIES

h 135t

Rarit

MAP WESTMINSTER RECOMMENDATIONS

135th

G

0

0.5

1 Mile


nt Bry a

Huron

Navajo

Pecos

Osage

Wyandot

Decatur

Clay

Irving Grove

Bryant

Federal Blvd

Hooker

Hooker

Grove

Grove

Judson Ken t

287

Hunter Ithac a Ha sti ng s

Lander

Canosa

Irving

Ho oke r 99 th

Mowry

Hazel

McCoy Osceola

Complete Street Projects Inclusive of pedestrian and bicycle improvements; dashed line denotes bicycle facility recommendation

92nd Ave

88th Ave

#

Pedestrian Projects

#

Bicycle Projects

#

Trail Projects

s te Ya

2.13

Clay

Bryant

Decatur

Clay

Federal Blvd

Zuni St

Grove

Signed Route

Clay

Gr 2.13 ee n

som

EXISTING CONDITIONS Trail Underpass

69th

Clay

Craft 71st Westminster Station

70th

Concrete Trail

Alcott

Bryant

Clay

Eliot

Eliot

ne

Gravel Trail

Zuni

Irving St Park

Trail Head On Street Bike Lanes

Skyli

Skyline Vista Park

Beach

Grove

James

Knox

T 36

74th Ave

73rd

71st

Elk

Raleigh

70th

Shared Lane Markings

80th Ave

75th

England Park

Wym an

Bike Lanes

2.9

77th

2.12

Bishop Sq Park 81st

Eliot

King Knox Julian Irving blos

King Knox

Orchard

Bradburn St

2.14

79th

App le

Julian

Newton

Osceola

th

76th Ave

75th 74th

79

Side Path

82nd

Cobblestone Park

Irving

ria

Meade

Raleigh

Ma

Trail

tt

Alcott

Grove

Cedar

Auburn

36 US

La Pl

81st

Al co

83rd

82nd

2.11

PROPOSED FACILITIES From Open Space Stewardship Plan and Bicycle Master Plan

86th

84th

2.2

King

ich Norw

on Mas

Lowell Blvd

Utica Rutgers

Qu igle y Pra tt

Bi

84th Ave

db Bra

2.12

78th

Stuart

Utica

90th

urn

2.4

Quitman

Raleigh

Stuart

Vrain

Stuart

Wolff

Wolff Winoa Vrain

Zenobia

Clay

Raleigh

n

Te nn ys on

Xavier

Set on

Wile y Quig ley Prat t Ap Ba ex rr ay kew

Xav ier

Shaw 85th

Newton Meade Wilson

City Center Yates

Wolcott

Wolff Wagner Sheridan Blvd

Zenobia

Benton

Federal Blvd

Knox

Lowell Stratfor

Lowell

Lowell Blvd

Meade

Yates 98 th

Osceola

Lowell

e as Ch

Perr y

Ea to n

Depew

Ingalls

Jay

King Julia n Julia n

Wolff r Xa vie

Benton Ames Sheridan Blvd

Depew

36 B US Harlan

Marshall

Newton

D ep ew

ay ikew

93rd

ar m

Pierce

Seto

Benton

Chase Way

Eaton

Gray

la n

a lls

Ha r

Ing

Jay

95th

Otis La

Pierce

Vrain

Depe

Sheridan Blvd

Kendall

Marshall 11 0t h

Big Dry Creek Trail

Quay

Quay

i th Zun 107

#

Canosa

70th

h 4t 10

70th

MAP WESTMINSTER RECOMMENDATIONS

Dale

70th

sler

80th

71st

71st

cor d

72nd Ave 71st

Eliot

72nd

le Da

Faversham Park

n

74th 73rd

Co n

2.3

77th

Wolf Run Park

Gree

2.5

88th

96th Ave

Kas

d

lan

d

Otis

rd d 73 72n 72nd Ave

75th

s

75th

e Am

76th Ave

oo kw

Xavier

78th

y th ra 77th 77 G

Stuart

2.11

89th

89th

Raleigh

2.10

80th Ave Wo lff

Tennyson

95

2.10

n

36

81st

2.8

L

THORNTON

87th

Oa

Downtown Westminster

gh

asalle

ZONE 2

rd 92nd

King

2.9

Hi

90th

WESTMINSTER

93

Julian

88th

Dixo

A R VA D A

h 94t

th

Valley 105 View Park 106th

h

95th

ton

r

r

ma

La

2.7

88th Ave

89th

2.7

88th Ave

87th

112th

98t

97th

2.1

Tennyson Utica Utica

ne Wag

2.6 Future Rail Station

90th

113th

h 2.4

96th

New

92nd 92nd Ave

Winona

2.8

See 2.8 Downtown Westminster Sheridan Inset BRT Station

h

0t

Squire Park

94th

y Perr igh Rale Stuart

93rd

k

Julian

2.7

88th Ave

92nd Ave

10

95th

2.6

ve it ro bb G

ns

Ho

ree

par

101st

y

dG

Carol Butts Park

92nd

91st

73rd

98th

2.3

93rd

2.5

74th

h

99th

96th 2.6

94th

92nd Ave

2.9

lan

Wolff

Ames 95th

100t

2.5 Kendall

th

2.4

Hy

1st

rth

d

r Per

lvd Gray

0th

100t h 99th

ff

rB

2.2

ar

Lam

90

98th

Westcliff Park

10

ol W

ste in

2.5

95th

94th

r

10

No

102n

Bruchez

105th

ian Jul

tm

th

97

Newland

95th

2.4

King

es W

99th

W ag ne

109th

107th

107th

104th

103rd

2.2

102nd

102nd 102nd 2.3 10 1st

106th

2.3

Perry

d

102n

Windsor Park

2.1

104th Ave

Wolff

2.1

nc

111th

108th

108th

ge

Rid

105th

103rd

and igh L il ers’ H Farm Canal Tra

2.1

96th

th

h

Farmers’ High Line Canal Trail2.2

Ave

acy Leg

105

6t

105th

36

Pie rce

10

7th

10

y Perr

Westminster City Park

104th

Westcl iff 98th is 97th Ot

Yate s

110th

h

ZONE 1

110th 109th

Cotton Creek

108th

h

Church Ranch BRT Station

Reed

th

111th

la

Ra

jo va Na

9t

108 107t

ZONE 2

h

h

ce o

th

113

111th

111t

INSET MAP Quivas

10

108th

109t

th

Wolff

ZONE 3

n Fento

112th

h

Alcott

109

Os

ca

109th

Stratford Park

112th Ave

rail ek T Cre Dr y Wo Vra g i B lff in U ti

Westminster Otis

WESTMINSTER’S MOBILITY ACTION PLAN 111 111th th 11 0th

akes dL 113 th

Front Range Community College

115t

h nc Ra

113th

n Fento

113th

Harlan

Sherwood Park

115th

Westfield Village Park

as Quiv

Gray

114th

D e pe w

115th Jay

MAPWESTMINSTER

t Circle Poin

MAP 4.3: ZONE 2 RECOMMENDAITONS

Main St Otis

th

Ingalls

116

Ryan Park

Natural Surface Trail Sidewalk Gap (Major Road)

n

ldo

She

Sidewalk (Major Road)

Fern

Park-n-Ride Station

68th Ave

RTD B Line/Station

4-7

School 287

BERKELEY

Westminster’s Mobility Action Plan 0

0.5

1 Mile


Trail Underpass

Inclusive of pedestrian and bicycle improvements; dashed line denotes bicycle facility recommendation

On Street Bike Lanes Concrete Trail

#

Pedestrian Projects

#

Bicycle Projects

#

Trail Projects

Gravel Trail Natural Surface Trail

PROPOSED FACILITIES

Sidewalk Gap (Major Road)

WESTMINSTER

From Open Space Stewardship Plan and Bicycle Master Plan

Sidewalk (Major Road)

Trail

Park-n-Ride Station

Side Path

RTD B Line/Station (Proposed)

Bike Lanes

School

Shared Lane Markings Signed Route

116th

115th 114th

36

BROOMFIELD

Otis

ZONE 3

Big Dry Cr eek Trail Quay Reed

Yukon

Vance

Quay

Farmers’ High Line Canal Trail

Yukon

90th

Nottingham Park

Yukon

88th Ave

Pierce

Allison

Ammons

Balsam

Carr

Lamar

Yukon on

Yu k hy r

Ze p d

Estes

Otis

Zephyr

Balsam Dover Cody

Everett

ley Dud

Estes

Flower Field

Garland

Garrison

Wadsworth Blvd

h 0t 11

sam Bal

Carr

Dover

Br en tw oo

Garland

Garrison

Hoyt

Hoyt Jellison

92nd

90

th

ce

Alkire St

ed th

97

94th

n Va

1 Mile

r

0.5

Trail

r ve Do

97th

3.6 92nd Ave

Yarrow

Chapter 4: Recommendations 0

y

ry Creek

87th

3.7

Dover Sq Park

Dover

Little D

88th

d Fiel

4-8

Farmers’ Hi gh Canal Trail Line

95th

93rd

3.2

86th Ave

A R VA D A

y

h

90t

92nd

d Co

92nd

d

93rd

3.4

94th

Westbrook Park

w Pk

l Fie

3.1

S TA N D L E Y L A K E

y

d Co

Westcl iff

Re

e

d en

h

97t

96th 95th

th or sw

ep

Ind

r eD nc

d Wa

h

96t

88th

r hy

d Brentwoo

Kipling

96th Ave

ham

St

B

98th

3.5 e Tell

97 on 3.4

llis

3.2

103rd

102nd

99th 99th Yarro w Big Dry Creek Trail

p Ze

Je

th 05 1Walnut Creek Trail

h Ran 102nd ch Blv d

Ammons

3.5 Trail k ree ry C ig D

th 98th

nce

98th

Chur c

3.4

nde

ek T rail

d

3.3

3.3

Up

Cre

epe

Standley Lake Regional Park

Dr y

10

Church Ranch BRT Station

Future Rail Station

Allison

Eagle View

100th Ind

Big

t

1s

nd

lla Ho

Barber

n 102

LOWER CHURCH LAKE

105th

er ov

Carr

Lewis Westmoor

Mo

Le e

101st

Dover D

or e

be wc om

3.3

104th

100th Ave

100th Ave

th

n

side Country Lewis

il

Robb

in Gr eenw ay Tr a

Ne

rd

103

unta

Kipling

Parfet

Quail

n so

Ro

bb

Pie r

Simms St

108th Tabo r

Union

y Mo

104

lso

Ne

3.1

t Circle Poin

Rock

s

104th

en Ow

104th

105th

121

106th

ison

3.2

3.2

Trail

Garr

e

ller

th

Iris

106

Creek

on

h

Walnu t

Johns

6t

Mi

un try sid

10

108th Ave

3.1

h 110t h 109t

ay ikew

107th

Oak

107th Ro ut t Co

110th

36 B

Walnut Creek Trail

111th

US

Westmoor Business Park

3.1

106th

113th

112th

Wadsworth Pkwy

Westmoor

Marshall

ZONE 3

Complete Street Projects

#

Trail Head

T

WESTMINSTER’S MOBILITY ACTION PLAN

ZONE 2 ZONE 1

MAPWESTMINSTER

3.5

91st

MAP 4.4: ZONE 3 RECOMMENDATIONS

MAP WESTMINSTER RECOMMENDATIONS

EXISTING CONDITIONS

Main St

INSET MAP


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

4.3 PROJECT PRIORITIZATION For MAP Westminster, projects were prioritized based upon scoring criteria. These criteria are described in Table 5.1, and were determined in coordination with the project steering committee. Project descriptions and scores are provided in Appendix A. Overall, as Westminster improves the transportation network, bicycle, pedestrian and transit connection facilities should be integral to the projects. Furthermore, when developers introduce new projects, they may be required to construct mobility infrastructure that is located on or adjacent to the streets that they are developing, as an alternative to other road capacity projects. This can be an added benefit to the city, as Westminster will not have to pay for the construction of these facilities. Additionally, when new projects are proposed internally, these criteria should be part of the internal assessment process. TABLE 5.1: PROJECT PRIORITIZATION CRITERIA Criteria

Description

Improves Safety and Mobility

Projects that addresses identified safety problems for one or multiple modes of travel in Westminster’s transportation system, based on field work and stakeholder/public input, resulting in a lower-stress walking, bicycling, and/or transit environment, qualified for this prioritization criterion.

Improves Connectivity

Projects that provide a new walking, bicycling or transit connection, or improves upon an existing connection, to transit stations, job centers, activity centers, neighborhoods, schools, public parks, open spaces, trails, and other recreational destinations qualified for this criterion.

Demonstrates Cost Effectiveness

Projects that require relatively little capital investment, and due to its lower cost, have fewer barriers to implementation qualified for this criterion.

Demonstrates Ease of Implementation

Projects that require minimal roadway reconfiguration, has an existing funding source/project that it can be implemented under, or coincides with an existing City project, qualified for this criterion.

4-9 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

4.4 COST ESTIMATES Planning level construction cost estimates for the overall project recommendations are included in Appendix A. Being a planning level assessment, project unknowns exist, and therefore a high and low cost estimate is provided. This broad range of potential costs is appropriate given the level of uncertainty in the design at this point in the planning process. Engineering costs, and any property acquisition costs (if applicable), are not included in the cost estimate. The following provides greater detail on some of the associated cost estimates. For the Demonstration Projects, more detailed cost estimates are provided, which do include estimated engineering costs. These costs are included in Chapter 5: Demonstration Projects. Sidewalks Cost to construct a foot of sidewalk was estimated to be $60 to $100 per linear foot for a 5 foot sidewalk, and $100 to $160 per linear foot for a 8 foot sidewalk, depending on complexity. Shared Use Paths Path construction can require a high level of preparation – purchasing property, engineering design, and coordination with many stakeholders. Costs for a new shared use path typically range from $120-$200 per linear foot, depending on complexity. Projects that require minimal grading and pavement will run at the lower end of the range, where projects that require culverts, bridges, retaining walls or other expensive improvements will fall toward the upper end of the estimate. Neighborhood Greenways The costs assume that the project consists of wayfinding signs every quarter-mile, and roadway markings about every 200 feet. The low cost estimate assumes $400 per installed sign and $30 per installed painted marking, and the per mile estimate is roughly $12,100. The high cost estimate assumes $400 per installed sign and $300 per thermoplastic marking, and the per mile cost is roughly $26,400. Thermoplastic markings are recommended, as paint markings will typically wear out completely in less than one year. Intersection improvements are estimated based on the level of complexity. In general, the more that concrete and signal work is required, the more expensive the improvement will be. Some neighborhood greenways include short sections of other facility types,

such as shared use paths or bicycle lanes, and these additional segments are included in the overall project cost estimate. All segments for individual projects should be implemented simultaneously. Bicycle Lanes Painting a bicycle lane on a road with sufficient width costs roughly $10,000 per linear mile ($5,000 in one direction) for paint striping and painted stencils, representing the low end of the cost estimate range. For such retrofit projects, some may require few or no other changes to the roadway configuration, however some may require lane configuration or orientation changes. This can be done by removing the existing road markings and applying new ones, or it also may be included as part of a routine resurfacing. The high range of the cost estimate includes thermoplastic tape striping and thermoplastic markings, and roughly costs $60,000 per linear mile ($30,000 in one direction). additional features such as buffers or separated bike lanes, increase the cost further. Rectangular Rapid Flash Beacons (RRFBs) These cost about $15,000 for a pair of solar powered beacons and pedestrian buttons. Median Refuges Median cost will vary depending on the overall design, Typically a median with pedestrian accommodations will range from $13,000 to $18,000. Hybrid Beacons Hybrid Beacons cost substantially more than a RRFB, however less than a full signal. Hybrid Beacons are estimated to cost about $80,000. Raised Crosswalks Raised crosswalks range in cost depending on the length and width of the crosswalk. Costs can range from $5,000 to $10,000 for a raised crosswalk. Underpasses Underpasses can range significantly in cost, depending on the number of lanes that the underpass is built beneath, and the individual complexities of the design. Costs can range from $400,000 for a two lane underpass to upwards of $1,000,000 on a four lane or more underpass.

4-10 Chapter 4: Recommendations


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

4.5 FUNDING SOURCES This section provides an overview of available federal, state, and local funding sources. Most funding sources are competitive and require the preparation of applications. For multi-agency projects, applications may be more successful if prepared jointly with other local and regional agencies. The majority of non-local public funds for bikeway and pedestrian projects are derived through a core group of federal and state programs. In addition to federal, state, and regional funding

sources, Westminster could dedicate local funds for active transportation improvements through a variety of measures, in addition to the $100,000 set-aside the city has already established. Westminster should also take advantage of private-public partnerships to fund projects identified in this Plan as well.

Table 4.1: Federal funding sources Funding Opportunity Surface Transportation Block Grant Program (STBGP)

Eligible Project Types

Qualifications

Bicycle and pedestrian improvements, among others

Varies

Lead Agency

Funding Source Detail

CDOT and MPO

With the passage of the 2016 Federal Transportation Bill, Fixing America’s Surface Transportation Act (FAST Act), the former Surface Transportation Program (STP) has become the Surface Transportation Block Grant Program (STBGP), which now includes Transportation Alternatives Program funding (described below). The Denver Regional Council of Governments (DRCOG) accepts concept reports for consideration of programming funds. This program has a state and an MPO component.

Transportation Alternatives Program (TAP)

Bicycle and pedestrian improvements only

Funds can be used for construction, planning and design of on and off-road bicycle and pedestrian facilities

CDOT and MPO

The FAST Act combines the former TAP (which included the former Recreational Trails and the Safe Routes to School programs) into the STBGP (above). Though program requirements will stay roughly the same, total funding has been slightly increased. Most projects have an 80/20 federal/local match split, and can include sidewalks, paths, trails (including Rails-to-trails), bicycle facilities, signals, traffic calming, lighting and safety infrastructure, and ADA improvements. Unless a state opts out, it must use a specified portion of its TA funds for recreational trails projects. Since the DRCOG Metro Area is larger than 200,000 people, funds are distributed based upon competitive applications by the MPO to municipalities.

Highway Safety Improvement Program (HSIP)

Infrastructure and program safety improvements

Public road with a correctable crash history, expected to reduce crashes, positive cost-benefit ratio, or, a systemic safety project

CDOT

Program purpose is to reduce fatalities and serious injuries on public roads through infrastructure and programs. Like SSIP, HSIP can fund low cost, systemic improvements if benefit-cost is met.

Transportation Infrastructure Finance and Innovation Act (TIFIA) Loans

Large projects

Varies

USDOT

While not a competitive grant funding source, these loans do provide financing options, including credit assistance in the form of direct loans, loan guarantees, and standby lines of credit for large, surface transportation projects of national or regional significance, as well as public-private partnerships.

Transportation Investments Generating Economic Recovery (TIGER)

Shovel ready, surface transportation projects

Positive estimated cost-benefit ratio meeting federal transportation goals, benefitting country as a whole

USDOT, State and Local Gov’ts

Approvals for the eighth round of TIGER, totalling $500 million, were signed into law in 2015 and applied for in 2016. Projects involving highways, bridges, bicycle and pedestrian facilities, transit, rail, and intermodal are eligible. Detailed application must be completed. Projects are highly competitive, and require a minimum 20 percent local match funding. Westminster applied for a TIGER grant to fund three underpasses along US 36 in 2016.

EPA, HUD, and USDOT

Joint project of the Environmental Protection Agency (EPA), the U.S. Department of Housing and Urban Development (HUD), and the U.S. Department of Transportation (USDOT). It is based on five Livability Principles, one of which explicitly addresses the need for pedestrian and bicycle infrastructure. It is not a formal agency with a regular annual grant program. Nevertheless, it is an important effort that has already led to some new grant opportunities

Partnership for Sustainable Communities

Bicycle and Pedestrian infrastructure

Project must fulfill Livability Principles

4-11 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Table 4.2: Federal Funding Sources (continued) Funding Opportunity

Eligible Project Types

Qualifications

Community Development Block Grants (CDBG)

Street improvements

Best if project benefits low or moderate-income populations

Community Transformation Grants

Bicycle and Pedestrian Infrastructure and Programs

Bicycle and pedestrian infrastructure

Federal Transit Administration (FTA) Funding

Additional Federal Funding

Varies

Lead Agency

Funding Source Detail

HUD and Local Gov’t

Funds can be used for reconstructing or rehabilitating housing and other property; building public facilities and improvements, such as streets, sidewalks, community and senior citizen centers and recreational facilities and paying for planning and administrative expenses. Trails and greenway projects that enhance accessibility are an ideal fit for this funding source. CDBG funds could also be used to write an ADA Transition Plans.

Projects and programs aimed at increasing physical activity to reduce risk of disease

CDC

Community Transformation Grants, administered through the Center for Disease Control (CDC), support community–level efforts to reduce chronic diseases such as heart disease, cancer, stroke, and diabetes. Active transportation infrastructure and programs that promote healthy lifestyles are a good fit for this program, particularly if the benefits of such improvements accrue to population groups experiencing the greatest burden of chronic disease.

Project must enhance or be related to public transportation facilities

FTA

Multiple FTA funding sources exist. Most FTA funding can be used to fund pedestrian and bicycle projects “that enhance or are related to public transportation facilities.”

Varies

The landscape of federal funding opportunities for pedestrian and bicycle programs and projects is always changing. A number of Federal agencies, including the Bureau of Land Management, the Department of Health and Human Services, the Department of Energy, and the Environmental Protection Agency have offered grant programs amenable to pedestrian and bicycle planning and implementation, and may do so again in the future. For up-to-date information about grant programs through all federal agencies, see: http://www.grants.gov/

Varies

Table 4.3: State/Regional Funding Sources Funding Opportunity

Eligible Project Types

Highway User Tax Fund (HUFT)

CDOT, County and Municipal transportation projects

State Highway Fund (SHF)

State General Fund

CDOT

CDOT

Department of Local Affairs (DOLA) Grants and Loans

Public facility and service needs

Statewide Transportation Improvement Program (STIP)

Transportation projects, including bicycle and pedestrian infrastructure

Qualifications

Varies

Varies

Varies

Varies

Varies

Lead Agency

Funding Source Detail

CDOT

Colorado’s Highway Users Tax Fund collects revenues from motor fuel excise taxes, annual vehicle license and registration fees, and passenger-mile taxes on vehicles. Revenues from the fund are disbursed to recipients, including Westminster, based on a formula prescribed by statute.

CDOT

The State Highway fund is a subset of the HUTF that is administered by CDOT for the maintenance of the state’s highway system. The fund also generates revenue through interest earnings on the fund balance. The SHF can also be used for matching available federal highway construction funding.

CDOT

The State General Assembly has provided mechanisms that can be used to allocate General Fund revenues for transportation projects, including direct transfers. Another mechanism, passed in 2009 by the General Assembly, creates a trigger of transfers from the General Fund to the HUTF when Colorado personal income grows 5 percent or more in a calendar year.

DOLA

The Local Government Financial Assistance section manages a number of grant and loan programs within the Department of Local Affairs specifically designed to address public facility and service needs. Through coordination and outreach with the department’s field offices, grant and loan resources are distributed on both a formula and discretionary basis depending upon applicable state statutory provisions, federal requirements and/or program guidelines.

MPO and CDOT

The Statewide Transportation Improvement Program (STIP) is CDOT’s shortterm capital improvement program, providing project funding and scheduling information for the department and Colorado’s metropolitan planning organizations. CDOT, as well as the Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) approve the STIP.

4-12 Chapter 4: Recommendations


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Table 4.3: State/Regional Funding Sources (Continued) Funding Opportunity

Metropolitan Planning Organization Transportation Improvement Program (TIP)

Colorado Safe Routes to School

GOCO Grants

Eligible Project Types

Transportation projects, including bicycle and pedestrian infrastructure

Infrastructure and noninfrastructure (program) projects

Qualifications

Varies

Projects that improve access for children to walk and bike to school

Bicycle and Pedestrian Planning and Infrastructure Improvements

Lead Agency

Funding Source Detail

MPO

MPOs are responsible for planning and prioritizing all federally funded transportation improvements within an urbanized area. DRCOG is the Metropolitan Planning Organization (MPO) for Westminster and surrounding urban areas. MPOs maintain a long-range transportation plan (LRTP) and develop a transportation improvement program (TIP) to develop a fiscally constrained program based on the long-range transportation plan. This Plan recommends that Westminster continues to work closely with MPO to ensure pedestrian, bikeways and transit improvement projects recommended in this Plan are listed in the TIP.

CDOT

Safe Routes to School (SRTS) was established in 2005 through Federal legislation to enable and encourage children, including those with disabilities, to walk and bicycle to school; to make walking and bicycling to school safe and more appealing; and to facilitate the planning, development and implementation of projects that will improve safety, and reduce traffic, fuel consumption, and air pollution in the vicinity of schools. CDOT manages the Colorado SRTS program. In 2015, the CDOT approved the continuation of the SRTS program by committing to fund the program with $2 million for infrastructure projects and $0.5 million for non-infrastructure projects. Grants are awarded through a statewide competitive process.

GOCO

GOCO invests a portion of Colorado Lottery proceeds to help preserve and enhance the state’s parks, trails, wildlife, rivers and open spaces. GOCO manages several grant programs that provide funds for bicycle and pedestrian planning and infrastructure projects. GOCO’s planning grant program offers competitive planning grants up to $75,000 to help entities develop strategic master plans for outdoor parks and recreation projects, trails, or sitespecific plans (applicants must provide at least 25% of the total project cost in matching funds). GOCO also manages Trail Grants that can be used to fund large and small trail projects and trail planning and maintenance. Lastly, GOCO manages The Connect Initiative, which funds projects focused on connecting existing trail gaps, constructing new, highly demanded trail systems, and providing better walkable and bikeable access for youth and families to existing outdoor recreation opportunities.

Lead Agency

Funding Source Detail

Table 4.4: Local Funding Sources Funding Opportunity

Eligible Project Types

Qualifications

General Fund

Maintenance, Capital Improvements List projects

Projects should incorporate active transportation accommodation

Local Gov’t

The General Fund is often used to pay for maintenance expenses and limited capital improvement projects. Projects identified for reconstruction or re-pavement as part of the Capital Improvements list should also incorporate recommendations for bicycle or pedestrian improvements in order to reduce additional costs.

Bond Financing

Varies

Varies

Varies

Bonds are a financing technique and not a funding source. Money is borrowed against a source of revenue or collateral (i.e. parcel tax revenue). Bonds do not increase total funding, but rather shift investment from future to present.

Local Gov’t

Special assessments are additional property taxes that are self- imposed on properties close to a new transportation facility or service. They can be used as a dedicated annual revenue stream for funding operations or bonded against under the right set of circumstances. The assessment is levied against parcels in an area that receives a special benefit that can be clearly identified and measured. Implementation of special tax districts can be challenging and before this mechanism can be considered an option, affected local landowners and businesses would need to buy into the premise that the tax is worth the value that the infrastructure or service improvement provides. Nationally, special tax districts are one of the most common forms of value capture for transportation projects.

Special Assessments or Taxing Districts

Varies

Varies

4-13 Westminster’s Mobility Action Plan


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Table 5.4: Local Funding Sources Funding Opportunity

Business Improvement Area of District

Development and Impact Fees

Sales Tax

Property Tax

Excise Tax

Tax Increment Financing

Eligible Project Types

Qualifications

Varies

Projects should benefit surrounding businesses’ customers

Varies

Varies

Lead Agency

Funding Source Detail

TBD

Trail, pedestrian, and bicycle improvements can often be included as part of larger efforts aimed at business improvement and retail district beautification. Business Improvement Areas collect levies on businesses in order to fund area wide improvements that benefit businesses and improve access for customers. A portion of this revenue could be used to fund bicycle and pedestrian improvements.

Local Gov’t

Development impact fees are one-time charges collected from developers for financing new infrastructure construction and operations, and can help fund bicycle and pedestrian improvements. Impact fees are assessed through an impact fee program.

Local Gov’t

Local governments can choose to exercise a local option sales tax, and use the tax revenues to provide funding for a wide variety of projects and activities. No sales tax is currently established in the Billings Area, but if there ever is, a small portion of the funds being directed towards transportation should be dedicated for active transportation projects. State approval required to enact local sales tax.

Local Gov’t

Property taxes generally support a significant portion of a local government’s activities. However, the revenues from property taxes can also be used to pay debt service on general obligation bonds issued to finance open space system acquisitions. Property taxes can provide a steady stream of financing while broadly distributing the tax burden. It should be noted that other public agencies compete vigorously for these funds, and taxpayers are generally concerned about high property tax rates.

Local Gov’t

Excise taxes are taxes on specific goods and services. These taxes require special legislation and the use of the funds generated through the tax are limited to specific uses. Examples include lodging, food, and beverage taxes that generate funds for promotion of tourism, and the gas tax that generates revenues for transportation-related activities.

Projects should specifically benefit the TIF area

Local Gov’t

Tax Increment Financing is a tool to use future gains in taxes to finance the current improvements that will create those gains. When a public project (e.g., shared use path) is constructed, surrounding property values generally increase and encourage surrounding development or redevelopment. The increased tax revenues are then dedicated to support the debt created by the original public improvement project.

Varies

Varies

Open space acquisitions

Varies

Varies

Varies- could specifically focus on tourism

Infrastructure projects

Street User Fees

Infrastructure projects

Varies

Many cities administer street user fees through residents’ monthly water or other utility bills. The revenue generated by the fee can be used for operations Local Gov’t and maintenance of the street system, and priorities would be established by (Public Works) the Public Works Department. This approach could be more equitable than property taxes, which just impact property owners.

In Lieu of Fees

Open space or trail projects

Varies

Local Gov’t

Developers often dedicate open space or trail projects in exchange for waiving fees associated with park and open space allocation requirements in respect to proposed development.

4-14 Chapter 4: Recommendations


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Page intentionally left blank

4-15 Westminster’s Mobility Action Plan


CHAPTER 5: DEMONSTRATION PROJECTS


Access to Transit Roadway MAPWESTMINSTER

DILLON RD

WESTMINSTER’S MOBILITY ACTION PLAN

144TH AV

5.1 DEMONSTRATION PROJECTS 287

128TH AV

124TH AV

MAP 5.1: DEMONSTRATION PROJECTS

Once the potential demonstration projects were selected, the public was given the opportunity to vote for the top three projects to be fast tracked 287 for implementation. A survey was developed that enabled the community to cast votes online, and a public meeting was held so that community members 36 person. The results of these could vote for projects in 121 voting exercises were tallied, and five projects were selected as the final demonstration projects for MAP Westminster.

L PY

ERA

FED

WAGON ROAD PARK AND RIDE

Dr y

Cre

ek

Tra il

PECOS ST

HURON ST

120TH AV

128

Big

112TH AV rail nal T e Ca

in

128

ZUNI ST

LOWELL BD

ASPEN ST

LN

B

MAIN ST

AL

T

TRI

LS KOH

US

Map 5.1 displays the name and location of the five demonstration projects, some of which include improvements at multiple locations. Project descriptions, conceptual graphics 136TH of AV the proposed improvements, and cost estimates are provided in this chapter for each V TH A 134 project. The proposed improvements are conceptual, and additional analysis, design, and engineering is necessary to advance the projects towards implementation. Due to this, all proposed concepts are subject Trail reek to modification. ry C ig D WESTLAKE DR

One of the primary objectives of MAP Westminster was to identify projects that could be implemented in the near term. Once the overall recommendations were finalized, 13 projects were selected by the project steering committee as potential demonstration projects. These projects were selected based upon community input collected throughout the planning process, and also represented lower-cost AV AV improvements that10TH could be feasibility10TH implemented within the next one to two to five years. IND MIDWAY BD

’ Hig L Far m ers h

il

nut Creek Tra

W 108TH AV

Westminster City Park Farmers’ High Line Canal Trail

DOWNTOWN WESTMINSTER

Farmers’ High Line Canal Trail

GARRISON ST

88TH AV

ZUNI ST

25

88TH AV

SHERIDAN STATION

88TH AV

PIERCE ST

PECOS ST ZUNI ST

BRADBURN BD

74TH AV 36

72ND AV

WESTMINSTER STATION

Westminster’s Mobility Action Plan

RTD

BL

INE

70TH AV 68TH AV

BROADWAY

WADSWORTH BD T

69TH AV

Tra il

BD

5-1

ree k

OD

ry C

WO

le D

AV

EEN

Litt

74TH AV

TH

76

76TH AV

GR

Promenade Sidepath Connector

80TH AV

ZUNI ST

LA MA R

DR

DR

D

CA

Church Ranch BRT Station Access Improvements

68TH AV

D OO

R

Public Access to City Services Improvements R RR

W

ay ew Bik

l

K OA

36

ED

AS CH

US-36 Ramp Crossing Improvements Creek Tr ai

84TH AV

Sheridan Station Access Improvement

KIPLING ST

CITY HALL CAMPUS

US

POMO

NA DR

66TH AV

92ND AV

121

DEMONSTRATION 84TH AV PROJECT LOCATIONS Little Dry

96TH AV

HURON ST

FP Y

HARLAN ST

EY LAKE

LIF

LOWELL BD

an

STC

YER N FL

EN

EP

WE

TIRO FLA

DR

CE

IND

igh Li n e C

FEDERAL BLVD

ek T rail

104TH AV

SHERIDAN BLVD

Cre

N DE

a l Trail

Farm e r s’

H

C

100TH AV Dr y

anc h R h Blvd

CHURCH RANCH STATION

WADSWORTH BD

Big

hu rc

104TH AV

YATES ST

OA K

ST

JOHNSON ST

108TH AV


L PY

ERA

FED

128

WAGON PARK AN RIDE

Big

Dr y

121

HURON ST

Cre ek Tra il

36

PECOS ST

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

120TH AV

128

287

in

IFF

36

88TH AV

88TH AV

121

R

R

ED

Trail

80TH AV

1 Mile

WADSWORTH BD

PIERCE ST

WESTMINSTER STATION

69TH AV

68TH AV

CARR ST

72ND AV

95

70TH AV

RTD

68TH AV

BL

INE

Existing Conditions

64TH AV

LOWELL BD

TENNYSN ST

G ST

SHERIDAN BLVD

121 RALSTON RD

LAMAR ST

62

GARRISON ST

0.5

74TH AV

Tra il

287

76

KIPLIN

0

ree k

BD

64TH AV

ry C

AV

OD

Representative Photo Simulation US 36 and Federal Boulevard, westbound off-ramp

58TH AV

le D

PROJECT LOCATION

TH

76

76TH AV

WO

Litt 74TH AV

BRADBURN BD

CA

EEN

SIMMS ST

RR

DR

GR

KIPLING ST

80TH AV

66TH AV

PECOS ST

y wa ike

LA MA RD

84TH AV

6B

84TH AV

1  Ramp crossing improvements for the US 36 and Church Ranch Blvd. West 72 Ramps and US 36 and Sheridan Blvd. North East Ramp are detailed in the 2017 Federal Highway Safety Program (HSIP) application. The design for the US 36 and 72ND AV Church Ranch Blvd West Ramps should be replicated on the East Ramp.

88TH AV

SHERIDAN STATION 3 US

GARRISON ST

ALKIRE ST

92ND AV

DOWNTOWN WESTMINSTER

AS

y Creek

96TH AV

CH

Little Dr

PY

R LYE

ST CL

HURON ST

L ine C

WE

104TH AV

LOWELL BD

Farm

ur c

H ers’ ig h

NF IRO AT

anc h R h Bl v d

rai l anal T FL

INDIANA ST

Westminster City Park

Farmers’ High Line Canal Trail

104TH AV

US 36 travels north/south through Westminster, and many of the City’s major destinations and transit hubs are located along Ch 100TH AV the corridor. This project aims to improve pedestrianBigcrossing Dr y Cre ek T rail Standley Lake Park conditions where the US 36 on- and Regional off-ramps intersect Church AV 96TH Ranch Boulevard/104th Avenue, Sheridan Boulevard, and Federal DENCEDR EN EP IND Boulevard. Improvements at the ramp crossings vary by location, S TA N D L E Y L A K E but in general, they are focused on increasing the visibility of Farmers’ High Line Canal Trail pedestrians, slowing vehicles as they exit and enter the ramps, and increasing the yield compliance of vehicles when pedestrians are 86TH PY attempting to cross the roadway.1

rail nal T e Ca

CHURCH RANCH

SHERIDAN BLVD

OA KS

T

JOHNSON ST

Project Overview

W 108TH AV

108TH AV

’ Hig L Far m ers h

ZUNI ST

Tra Walnut Creek

FEDERAL BLVD

il

SIMMS ST

US 36 Ramp Crossing Improvements

WADSWORTH BD

112TH AV

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Summer 2016

N

OVERVIEW MAP

Sources: City of Westminster, Colorado Dept of Local Affairs, RTD, ESRI

5-2 Chapter 5: Demonstration Projects

Autho


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

US 36 and Sheridan Boulevard, eastbound on-ramp - Conceptual Proposed Improvements

N BL VD .

Cost Estimate

RIDA

INSTALL RRFB

EXISTING ISLAND TO REMAIN

SH E

INSTALL RRFB

INSTALL GORE STRIPING TO VISUALLY NARROW RIGHT TURN LANE

Total Estimate

$34,000

ON AM P

E

200'

INSTALL ADVANCED WARNING SIGN

AN

100'

SL

Scale

-R

BU

US 36 and Sheridan Blvd: NW Ramp 50'

$8,000 $12,500 $5,500 $8,000

INSTALL YIELD LINES

INSTALL GROOVED RUMBLE STRIP

0

Striping Signing Lump sum items Contingencies

US 36 and Sheridan Boulevard, westbound on-ramp - Conceptual Proposed Improvements

Cost Estimate Striping Signing Lump sum items Contingencies

$10,500 $12,500 $6,500 $9,000

Total Estimate

$38,500

INSTALL ADVANCED WARNING SIGN

INSTALL GROOVED RUMBLE STRIP

P

INSTALL HIGH VISIBILITY CROSSWALK

AM

-R

ON

INSTALL GORE STRIPING TO VISUALLY NARROW RIGHT TURN LANE

BL VD ID

AN 50'

100'

SH ER

Scale 0

INSTALL RRFB

.

EXISTING ISLAND TO REMAIN

200'

5-3 Westminster’s Mobility Action Plan

W .8

8T

H

PL

.


MAP

WESTMINSTER WESTMINSTER’S MOBILITY ACTION PLANSW Ramp US 36 and Sheridan Blvd: US 36 and Sheridan Boulevard, westbound off-ramp - Conceptual Proposed Improvements

Cost Estimate

Total Estimate

$11,500 $36,500 $13,000 $18,500

P AM -R ON

Striping Signing Lump sum items Contingencies

INSTALL RRFB INSTALL HIGH VISIBILITY CROSSWALK

MEDIAN TO REMAIN INSTALL HIGH VISIBILITY CROSSWALK

$79,500

ER SH

*INSTALL YIELD MARKINGS IN ADVANCE OF ALL CROSSWALKS

ID

AN

BL VD

.

INSTALL GORE STRIPING TO VISUALLY NARROW RIGHT TURN LANE INSTALL RRFB

W. 88TH PL.

INSTALL RRFB

INSTALL ADVANCED WARNING SIGN

-RAM

OFF

Scale 50'

100'

200'

P

0

US 36 and Federal Boulevard, westbound off-ramp - Conceptual Proposed Improvements

Cost Estimate

REPLACE EXISTING

FEDERAL BLVD

INSTALL SIGN

Striping Signing Lump sum items Contingencies

$8,500 $1,000 $2,500 $3,500

Total Estimate

$15,500

INSTALL SIGN

MP

RA F-

OF

ADJUST EDGE LINE TO CREATE 12-FOOT TRAVEL LANE

Scale 0

5-4 Chapter 5: Demonstration Projects

50'

100'

200'


MAP

WESTMINSTER US 36 and Federal Blvd: EB Off- Ramp

WESTMINSTER’S MOBILITY ACTION PLAN

US 36 and Federal Boulevard, eastbound off-ramp - Conceptual Proposed

Cost Estimate

Scale 200'

Striping Signing Lump sum items Contingencies

$11,000 $600 $3,100 $4,500

Total Estimate

$19,200

MP

100'

FEDERAL BLVD

50'

RA

ADJUST EDGE LINE TO CREATE 12-FOOT TRAVEL LANE

OF F-

0

INSTALL SIGN

M

P

US 36 and Federal Blvd EB On Ramp O

N-

RA

INSTALL SIGN

US 36 and Federal Boulevard, eastbound on-ramp- Conceptual Proposed Improvements EXISTING ISLAND TO REMAIN

Cost Estimate Striping Signing Lump sum items Contingencies

$10,500 $12,500 $6,500 $8,500

Total Estimate

$38,000

EXISTING CROSSWALK TO REMAIN

ON RAMP

INSTALL RRFB INSTALL RRFB

INSTALL YIELD LINES

Scale 0

25'

50'

100'

FEDERAL BLVD.

INSTALL GORE STRIPING TO VISUALLY NARROW RIGHT TURN LANE

INSTALL ADVANCED WARNING SIGN

5-5 Westminster’s Mobility Action Plan


104TH AV

IFF

DR

CE Flatiron Flyer Bus Rapid Sheridan Station provides access toENthe D N E Transit (BRT) line as well as local EP bus service, and is adjacent to ND I Downtown Westminster. Additionally, the US 36 Bikeway connects E toYSheridan L A KStation E and then crosses 88th Avenue at-grade and continues north. Improving access between Sheridan Station, the US 36 Bikeway and Downtown Westminster at 88th Avenue Canal Trail Farmers’ High Line will make bicycling and walking between these destinations more comfortable. The improvements at this location are detailed in the city’s 2017 CDOT Highway Safety Improvement Program application. Improvements are focused on increasing the visibility 121 of pedestrians, slowing vehicles as they exit and enter the ramps, and increasing the yield compliance of vehicles 84TH AVwhen pedestrians are attempting to cross the roadway. The project includes the construction of a raised crosswalk, as displayed in the photo Little Dr y Creek simulation below. Trail

36

92ND AV

DOWNTOWN WESTMINSTER

88TH AV

SHERIDAN STATION US

GARRISON ST

36 ay ew Bik

PROJECT LOCATION

R

PIERCE ST 68TH AV

74TH AV

Tra il

72ND AV

WESTMINS STATION

RALSTON RD

5-6 Chapter 5: Demonstration Projects

SHERIDAN BLVD

121

LAMAR ST

64TH AV

KIPLI NG S

T

ree k

69TH AV

1  See 2017 Federal Highway Safety Program (HSIP) application for cost estimate detail

STMINSTER

ry C

76TH AV

95

GARRISON ST

64TH AV

Cost Estimate:1 $138,600

le D

74TH AV

CARR ST

66TH AV

58TH AV

Existing Conditions

Litt WADSWORTH BD

SIMMS ST

KIPLING ST

Representative Photo Simulation - RR D CA Access Improvements 88th Avenue at Sheridan Boulevard

LOWELL BD

DL

PY

LOWELL BD

ST CL

ER FLY

Project Overview

WE

BRADBURN BD

Farm

Dry Bus Rapid Transit Station Sheridan Cre ek T rail Access Improvements

H ers’ ig h

ON TIR FL A

Ch

100TH AV

Big

anc h R h Bl v d

TENNYSN ST

ur c

WESTMINSTER’S MOBILITY ACTION PLAN

rai l anal T

L ine C

MAPWESTMINSTER

104TH AV

SHERIDAN BLVD

OA K

ST

N ST

City Park

Farmers’ High Line Canal Trail


ree kT rai l

MAPWESTMINSTER

Big D

ry C

WESTMINSTER’S MOBILITY ACTION PLAN

112TH A

Public Access to City Services Improvements Project Overview

CHURCH RANCH

Yates Street provides an important connection between Sheridan Station and the city’s public services, located within the city hall campus. In addition, there is pedestrian crossing demand between the city hall campus and Westminster Center Park at Xavier Street and 92nd Avenue, but a marked crossing at this location does not exist. This project includes pedestrian access improvementsWestminster at three locations. Each will improve City connectivity to the cityPark hall campus. The improvements include installing a Pedestrian Hybrid Beacon and marked crosswalk at 92nd Avenue and Xavier Street, installing a mid-block crosswalk at Yates Street and 91st Avenue, and making 88th Place and Yates Street a four-way stop-controlled intersection with marked crosswalks. Additional details of these improvements are provided on the conceptual plan illustrations and photo simulations.

Far m

Farmers’ High Line Canal Trail

DOWNTOWN WESTMINSTER

ZUNI ST

LOWELL BD

36

92ND AV CITY HALL CAMPUS

88TH AV

SHERIDAN STATION

5-7 Westminster’s Mobility Action Plan

FEDERAL BLVD

PROJECT LOCATION

SHERIDAN BLVD

s’ Hig h

YATES ST

L ine C

rai l anal T

104TH AV


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

XAVIER ST 92nd Avenue and Xavier Street - Conceptual Proposed Improvements OPTIONAL: RECONSTRUCT LANDING. CONSTRUCT ADACURB RAMPS (WILL REQUIRE RECONSTRUCTION OF SIDEWALK PANEL)

2.3 92nd and Xavier

INSTALL STOP BAR

PROPOSED HAWK BEACON

INSTALL CROSSWALK EXISTING CURB LINE

W. 92ND AVE

Striping HAWK Signal Sidewalk Lump sum items Contingencies

$20,500 $80,000 $26,000 $56,000 $54,000

Total Estimate

$237,000

MEDIAN TO REMAIN

MEDIAN TO REMAIN

RAMPS WILL LIKELY REQUIRE UPGRADE TO MEET ADA

INSTALL CROSSWALK PROPOSED HAWK BEACON

OPTIONAL: RECONSTRUCT LANDING. CONSTRUCT ADACURB RAMPS (WILL REQUIRE RECONSTRUCTION OF SIDEWALK PANEL AND DRAINAGE WORK)

Existing Conditions

MEDIAN TO REMAIN

INSTALL CUSTOM THERMOPLASTIC CROSSWALK TO MARK GATEWAY TO CITY HALL CAMPUS (DESIGN IS EXAMPLE ONLY) INSTALL STOP BAR

Representative Photo Simulation 92nd Avenue and Xavier Street

5-8 Chapter 5: Demonstration Projects

Scale: 1" = 20' 0

10'

20'

40'

N


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

Yates Street and W 91st Avenue - Conceptual Proposed Improvements

Cost Estimate INSTALL ADVANCED WARNING SIGN

INSTALL CURB EXTENSIONS

MEDIAN TO REMAIN

EXISTING TO REMAIN INSTALL HIGH VISIBILITY CROSSWALK

INSTALL RRFB

EXISTING CURB LINES

Striping Signing Sidewalk Lump sum items Contingencies

$10,500 $24,500 $14,000 $13,500 $18,500

Total Estimate

$81,000

E. 9

1ST

YATES S

MODIFY MEDIAN

INSTALL RRFB

EXISTING CURB LINE

INSTALL ADVANCED WARNING SIGN

Scale 0

25'

50'

AVE

INSTALL PATTERNED CROSSWALK

T.

INSTALL DOUBLE SIDED RRFB

100'

© 2016 Google

Existing Conditions

Representative Photo Simulation Yates Street and W 91st Avenue

5-9 Westminster’s Mobility Action Plan


W. 88TH PL.

MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

YATES DR.

Yates Avenue and W 88th Place - Conceptual Proposed Improvements

INSTALL HIGH VISIBILITY CROSSWALKS, STOP SIGNS AND STOP BARS ALL DIRECTIONS

REVISE DEVELOPER PLAN TO INCLUDE CURB EXTENSIONS MEDIAN TO REMAIN

YATES ST.

MEDIAN TO REMAIN

Cost Estimate

EXISTING/PROPOSED CURB LINE

RECONSTRUCT CURB LANDINGS

Scale 0

50'

100'

200'

Striping Signing Sidewalk Lump sum items Contingencies

$17,000 $24,000 $85,000 $19,500 $42,000

Total Estimate

$187,500

Existing Conditions

Representative Photo Simulation Yates Street and W 88th Place

5-10 Chapter 5: Demonstration Projects


128

MAPWESTMINSTER

128

287

WESTMINSTER’S MOBILITY ACTION PLAN

36

Church Ranch Bus Rapid Transit Station Access Improvements

121

112TH AV

WADSWORTH BD

Westminster City Park

Dr y

Cre

ek T rail

96TH AV

PROJECT LOCATION

ALKIRE ST

S TA N D L E Y L A K E

92ND AV CITY HALL CAMPUS

DOWNTOWN WESTMINSTER

Farmers’ High Line Canal Trail

88TH AV GARRISON ST

East Side Sidewalk - Conceptual Proposed Improvements

Cost Estimate

121

EXISTING RETAINING WALL TO REMAIN 84TH AV BUS SHELTER TO REMAIN Little D

M

P

O

N

R AR

DR

Litt

le D

WADSWORTH BD

CONSTRUCT RETAINING WALL 74TH AV

72ND AV

ADD FILL

50'

RALSTON RD

.

KIPLIN

G ST

0

5-11

VE HA

Westminster’s Mobility Action 4TPlan

0

1 W.

ree k

95

64TH AV

Scale

GARRISON ST

EXISTING DRAINAGE 64TH AV CHANNEL INSTALL CULVERT UNDER SIDEWALK

58TH AV

REMOVE EXISTING TREES

CARR ST

66TH AV

ry C

69TH AV

8’ SIDEWALK TO BE 68TH AV CONSTRUCTED

EXISTING SIGNAL BEACON TO REMAIN

1 Mile

$531,500

C LUMINAIRE POLE EXISTING

MEDIAN TO REMAIN

0.5

Total Estimate

121

100'

SHERIDAN BLVD

A

LAMAR ST

2

R

ST AT I

Trail

$15,000 $87,000 $306,500 $123,000

PIERCE ST

N

KIPLING ST

S

O

SIMMS ST

80TH AV

ry Creek

BU

Sidewalk Lump sum items Retaining Wall Contingencies

TENNYSN ST

86TH PY

200'

BRADBURN BD

Standley Lake Regional Park

Farm

ur c

Big

104TH AV

R LYE y N F ewa IRO Bik AT S 36 FL U

L ine C

OA K

ST

JOHNSON ST

SIMMS ST

The recently constructed Bus Rapid Transit Trail (BRT) stations in Walnut Creek Westminster provide new mobility options for people in the city. 108TH AV CHURCH W 108TH AV Currently, there is no sidewalk leading from 104th Avenue to RANCH Church Ranch BRT Station on the east side of US 36, and while a sidewalk does exist on the west side, it is circuitous and pedestrians have been observed walking along the grass to the station, as this104TH AV rai l route is more direct. This project would construct direct sidewalk anal T n a c h R h Bl v d connections to the station platforms on both sides of US 36 from H 104th Avenue north to the stations. Ch ers’ ig h

SHERIDAN BLVD

Project Overview

Tra il


MAPWESTMINSTER

WESTMINSTER’S MOBILITY ACTION PLAN

West Side Sidewalk - Conceptual Proposed Improvements

Cost Estimate BUS ION STAT

EXISTING DRAINAGE TO REMAIN INSTALL LIGHTING

CONSTRUCT EXTENDED PLATFORM

EXISTING DRAINAGE OUTLET TO REMAIN

Sidewalk Lighting Retaining Wall Lump sum items Contingencies

$12,500 $2,500 $106,000 $33,000 $46,000

Total Estimate

$200,000

INSTALL SIDEWALK CONNECTION FROM EXISTING SIDEWALK TO STATION PLATFORM

RETAINING WALL TO BE CONSTRUCTED

OFF P RAM

INSTALL WAYFINDING SIGNAGE TO BUS STATION

.

E AV TH

Scale 0

50'

100'

04

1 W.

200'

Representative Photo Simulation West Side Sidewalk

Existing Conditions

5-12 Chapter 5: Demonstration Projects


AL

MIDWAY BD

LN

MAIN ST

MAPWESTMINSTER

TRI

ST

US

L KOH

IND

WESTMINSTER’S MOBILITY ACTION PLAN

128 128

287

Promenade Sidepath Connector Project Overview

36

ur c

Farm

Cre

ek T rail

Westminster City Park

104TH AV

ail anal Tr

H ers’ ig h

96TH AV

PROJECT LOCATION

SHERIDAN BLVD

T

OA KS

Standley Lake Regional Park

Ch Dr y

CHURCH RANCH

L ine C

WADSWORTH BD

SIMMS ST

JOHNSON ST

Big

112TH AV

ER LY y N F ewa IRO Bik AT S 36 FL U

The Big Dry Creek Trail provides a comfortable bicycle and 121 pedestrian facility for neighborhoods east of Westminster Blvd., and the Promenade Drive Sidepath provides a link towards the Church Ranch Station. Currently, there is no direct bicycle and k Trail Creek Trail (south of pedestrian connection between the Big CreeDry Walnut 108th Avenue) and the sidepath on the north side of Promenade 108TH AV W 108TH AV Drive. This project would construct a new connection between these trails. The project includes removing and replacing existing gravel sections of trail with a concrete shared-use path, and 104TH AV constructing new sections of shared-use path. The project also anch B includes constructing a culvert to bridge over an existing ditch. hR lv d

S TA N D L E Y L A K E ALKIRE ST

92ND AV

Representative Photo Simulation Promenade Sidepath Connector

CITY HALL CAMPUS

DOWNTOWN Existing Conditions WESTMINSTER

Farmers’ High Line Canal Trail

GARRISON ST

88TH AV

86TH PY

Little Dry

121

84TH AV

Creek Tr ail

DR

Litt

72ND AV

0.5

1 Mile

69TH AV

5-13

Westminster’s Mobility Action Plan

TENNYSN ST

SHERIDAN BLVD

121

LAMAR ST

64TH AV

RALSTON RD

G ST KIPLIN

58TH AV

ree k

95

GARRISON ST

64TH AV

ry C

68TH AV

CARR ST

66TH AV

le D

74TH AV

PIERCE ST

WADSWORTH BD

SIMMS ST

KIPLING ST

RR

CA

BRADBURN BD

80TH AV

Trai l


Promenade Sidepath Upgrade WESTMINSTER

MAP

WESTMINSTER’S MOBILITY ACTION PLAN

EATON ST.

Promenade Sidepath Connector - Conceptual Proposed Improvements

W. 108TH AVE.

W. 108TH CR.

EXISTING CONCRETE TRAIL INSTALL NEW CONCRETE TRAIL INSTALL BOX CULVERT

PR OM E

EXISTING CONCRETE TRAIL

DE NA TH OR .N DR

REMOVE AND REPLACE EXISTING GRAVEL TRAIL WITH CONCRETE TRAIL

Cost Estimate

Scale 0

50'

100'

200'

© 2016 Google

5-14 Chapter 5: Demonstration Projects

Sidewalk Lump sum items Contingencies

$71,500 $19,500 $27,500

Total Estimate

$118,500


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.