RGN | First Mining Gold

Page 1

WWW.RESOURCEGLOBALNETWORK.COM


MINING | First Mining Gold

MAYUR RESOURCES

First Min

Developing an industrial minerals and power generation platform in Papua New Guinea


ning Gold

Resource Global Network


MINING | First Mining Gold

First Mining Gold’s chairman Keith Neumeyer first began building an asset base for his company in the second half of the 2010s, at a time when the capital markets environment was brutal, particularly for junior resource developers. However, the mining investment industry veteran glimpsed an opportunity to pick up high potential projects in trusted jurisdictions when belief in the mining sector was low, and his team went about compiling a list of 10 projects to pursue. After a rigorous screening process, First Mining bought six of those plus a few more shortly after to total eight acquisitions in a 15-month period. Today, the Toronto, US and Frankfurt-listed company has a diversified portfolio of gold assets across North America with a sharp focus on two assets in Ontario, Canada: The Springpole and Goldlund gold projects.

Next, First Mining brought in new COO

The onset of 2019 brought changes to

Gold and Premier Gold Mines and the Magino

the management team at First Mining,

project by Argonaut Gold. These are all 10-

starting with the appointment of new CEO

30,000 tonnes per day operations which have

Dan Wilton in January. The experienced

been permitted in a two-year timeframe, so I

mining finance executive was joined by Mal

think this is one of the best jurisdictions to be

Karwowska in April, both of whom arrived

operating in.”

from mining-focused private equity firm Pacific Road Capital Management.

Ken Engquist to lead the technical and operational teams as the company looks to drive its two flagship projects forward. Following these managerial changes, Wilton believes that First Mining has the right team set up to execute its vision in Ontario. “I think we are blessed with these projects being where they are,” Wilton tells RGN on a recent business trip to London. “Four of our projects are in the same region of Northwest Ontario, towards the Manitoba border where there is an established resource economy.” Mining, forestry and to a lesser extent power generation are the big drivers of industry in this part of the world, and this means that local permit authorities and regulators have a strong understanding of the mining sector going back several decades. Local regulators are highly cooperative and supportive of mineral development projects according to Wilton, and this is evidenced by Ontario’s recent track record of approving permits for three large-scale open pit gold mines in the last three years. “There was the Côté project by IAMGOLD and Sumitomo, the Hard Rock project by Centerra


Resource Global Network


MINING | First Mining Gold


Resource Global Network

The Springpole Gold Project Located 110 km Northeast of the town of

that we could take recoveries from around the 80% level to the low 90s through flotation and fine grinding.�

Red Lake in Ontario, the Springpole project is one of the largest undeveloped open pit gold

The outcome of improving the recoveries rate

deposits in Canada, capable of producing

by a margin of 10% is a noteworthy drop in

over 400,000 ounces per year at the peak of

the costs per ounce of the project, with direct

its operation.

operating cash costs estimated at $575 per ounce of gold equivalent, and all-in sustaining

First Mining completed an updated

costs (AISC) valued at $611 per ounce of gold

preliminary economic assessment (PEA)

equivalent.

for the project in October this year, which indicated a 12-year mine life with a post-tax

Although initial capital costs went up to $809

net present value of US$841 million and an

million, the overall message that Wilton

internal rate of return of 22%.

took from the PEA is that Springpole is a big enough gold project to be meaningful for any

“The real goal of that study was to update

mining company in the world during the core

the economics and the production profile

part of its mine life.

to incorporate some metallurgical work we had done in 2018-19. The test work indicated

88


Are you generating enough value to attract investment? #AskAusencoHow

www.ausenco.com


Resource Global Network

Fracflow Consultants Inc. Environmental, Hydrogeological and Geotechnical Engineering Consultants

St. John’s, NL / Dartmouth, NS Tel: (709) 739-7270 / (902) 468-1317 Email: ffc_nf@nfld.net www.fracflow.com

Packer Test

Fracflow provides a full range of hydrogeological, geotechnical and environmental baseline services to support open pit and underground mine design and water management, especially in fractured bedrock. Collected physical hydrogeological, fracture geometry and aqueous geochemical data are integrated into 3D flow and transport models for prediction of water quality, pit inflows, dewatering design, ecological impacts and pit lake chemistry, on mine closure. 3D Numerical Modeling

Fracture Logging

Piper Plot

“We’re happy with the PEA, but there still is a

While detractors of the project might argue

lot of work to do. Last week we announced

that approval could be difficult to secure,

that we will be taking the project through to

owing to the deposit’s position under the

the pre-feasibility stage (PFS) and we need

shallow bay of a lake, First Mining has

to consider our plan for initial capital costs,

collated seven years of environmental

and we’ll look into our production profile and

baseline work that suggests otherwise.

tailings waste management. Overall, the PEA gave us a good sense of what we need to do

This wealth of information is currently being

in the PFS.”

incorporated into a terms of reference (ToR) document ahead of submission to the

Alongside the technical advancement of the

Ontario environmental ministry by the end

Springpole project, First Mining is progressing

of the year. The ToR will effectively form

along the permitting timeline, which is a

the table of contents for the subsequent

lengthy process to undertake in Ontario, but

environmental impact assessment (EIS)

one that is ultimately reliable once all the

document.

required documents are submitted to the authorities.

Throughout the next 12 months, First Mining will maintain close consultation with key indigenous groups regarding the content

90


MINING | First Mining Gold of the EIS, ahead of a formal submission of

important vote of confidence from what I

the document by the end of 2020. At around

think is one of the best engineering groups in

the same time, the company hopes to have

the world for a gold project of this size.”

completed the PFS for Springpole.

The Goldlund Project

“Then the project goes through the

First Mining’s secondary focus in Ontario

environmental assessment process which in

is the Goldlund gold project, located

Ontario typically takes between 18 months

approximately 60 km Northeast of the town

and two years. This timeline would keep us

of Dryden. The property has a strike length

on track for a construction decision in 2023

of over 50 km and has shown strong district

and financing around the same time,” Wilton

scale potential.

projects. The current resource estimate stands at Global engineering firm Ausenco will

809,200 ounces of gold at 1.96 g/t in the

complete the Springpole PFS, in an

Indicated resource category and 876,954

interesting deal that will see First Mining pay

ounces of gold at 1.49 g/t in the Inferred

the Australian company in shares for their

resource category, although there is

engineering work.

significant exploration potential and several targets identified across the property.

“It’s an interesting model for alignment with our technical partners, and I think it’s an

“We probably under-sell the fact that the


Resource Global Network


MINING | First Mining Gold Goldlund deposit as it sits right now is one of the highest- grade open pit projects in Canada. You’re talking about 800,000 ounces of Indicated resources at 2 g/t and approximately 870,000 ounces of Inferred resources at 1.5 g/t that falls into an open pit and we think there is a lot of room to grow that just in the Goldlund Main Zone.” In addition to the high-grade mineralisation present at Goldlund, the project is blessed with excellent infrastructural links. The property is located next to a provincial highway with existing power lines 20 km away. However, the real value driver at the Goldlund project is its district scale potential. This outlook has been evidenced by a string of exciting results from regional prospects, most notably at the Miller target over the last two years. Miller is located approximately 10 km Northeast and along strike of the current resource area and has been the primary focus of the company’s 2019 drill programme at Goldlund, with visible gold often observed. The prospect is not currently included in the resource estimate. “I think Miller is a real example of one of a number of similar type targets that we can test along the big strike of this property,” says Wilton. “Ultimately, we think Goldlund could become a large gold district feeding one central mill.”

“We probably under-sell the that the Goldlund deposit is of the highest grade open pi projects in Canada right now we think there is a lot of roo grow that just in the Main Z Dan Wilton, CEO and directo First Mining Gold


e fact s one it w and om to Zone� or

Resource Global Network


MINING | First Mining Gold

First Mining has maintained a strong

Having demonstrated the district scale

relationship with its drilling partner from

potential of the project via successful drill

the Springpole project and has retained

programmes at several deposits, First Mining

Winnipeg-based Rodren Drilling’s excellent

is returning to the Goldlund Main Zone for

services for the Goldlund campaigns.


Resource Global Network expansion and infill drilling, which will contribute towards a better understanding of the resource estimate there. “At some point soon, we will need to wrap some economics around this project and take it through a PEA, which shouldn’t be difficult or take long. We have an opportunity here to demonstrate the robust nature of the project, especially with the grade and strip ratio we think we can achieve in an open pit.”

A big year ahead First Mining is on the brink of a massive year in the development of its headline gold assets in Ontario, with the submission of the EIS and PFS for Springpole earmarked for 2020, while Goldlund is also set to receive more substantial economic assessment next year. Hitting these milestones will serve to significantly de-risk the projects and demonstrate to the market that quantifiable progress is being made, which should pave the way for greater recognition of this unique opportunity to invest in world-class gold assets in a trusted jurisdiction.

TSX:FF OTCQX:FFMGF FSE:FMG

a j


Published by Anderson Murray Media Ltd

To tell the resource market your story, contact: editorial@resourceglobalnetwork.com

WWW.RESOURCEGLOBALNETWORK.COM


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.