RGN | Tietto Minerals

Page 1

WWW.RESOURCEGLOBALNETWORK.COM


TIETTO M

Entering the final sta West Africa’s n


MINERALS

ages in the development of next major gold mine

MINING | TIETTO MINERALS


At the start of April 2021, gold exploration and development firm Tietto Minerals published a highly anticipated pre-feasibility study (PFS) for its flagship Abujar Gold Project in Côte d’Ivoire, to the delight of its legion investors who have been following Tietto’s progress since its listing on the ASX in January 2018. “I think the general market is always quite cautious when your PFS results come out, but our shareholders were extremely happy with the outcomes of the PFS, particularly with the robust economics,” Tietto’s managing director Caigen Wang tells RGN. The study revealed a 3.5 million tonnes per annum (Mtpa) open pit operation, producing 200,000 ounces of gold in the first year and an average 168,000 ounces over the first six years of the project, based on a maiden probable reserve of 15.7 Mt at 1.7 g/t gold for 860,000 ounces within the life of mine inventory of 1.1Moz in the base case scenario. The economics, which were perceived so favourably by Tietto’s investors, included a post-tax NPV (5%) of US$266 million and an IRR of 42%, based on an average gold price of $1,506 per ounce – significantly lower than the current spot of around $1,900 per ounce. The PFS resembled one of the most significant pieces of news flow released by the company since it first applied for an exploration licence at Abujar back in 2014. The milestone study also begins a ~two-year countdown to first commercial production at what will be West Africa’s next major gold mine.

MANAGING DIRECTOR CAIGEN WANG (RIGHT) AND ABUJAR ON-SITE MANAGEMEN

A key outcome of the PFS

Abujar will be mined via open

was its ability to demonstrate

pit – with 100% of the total

a simple, low-cost mining

ore reserve amenable to open

operation at all-in sustaining

pit mining in the base case

costs (AISC) of $839 per ounce.

scenario.

Crucially, for the first six years of the current 10-year mine life,


MINING | TIETTO MINERALS

NT TEAM

The open pit scenario is one

a simple carbon in-leaching

it’s easy to crush and grind

contributing factor to the low

(CIL) method at a course

the ore and average energy

AISC at Abujar; another is

grind particle size of 180µm to

requirements of fresh ore are

the high gold recovery levels

106µm.

lower than the vast majority

on the ore processing side.

of gold projects operating in

Laboratory results have shown

“Our gold is very easy to

recovery rates of 96-98% via

recover. The test results show

West Africa. That shows that


the processing side is not only simple, it’s also cheap,” Wang asserts.

World-class gold jurisdiction The low-cost nature of the project ultimately stems from its location in the Ivorian segment of the Birimian greenstone belt snaking across West Africa, where gold operations regularly fall into the lowest global AISC quartile.

T IE T TO MIN E RALS

AT A G L A N C E

STOCK TICKER: ASX:TIE MARKET CAPITALISATION: US$157 million (as of May 26, 2021) aj


MINING | TIETTO MINERALS

Côte d’Ivoire encompasses the largest section of the Birimian (covering 34% of the total mineralised belt) and produced 32.6 tonnes of gold from five mines in 2019, with the latest addition being Perseus Mining’s 3.8 million ounce (Moz) Yaouré Gold Mine in central Côte d’Ivoire, which was commissioned at the end of 2020 and is similarly sized to the Abujar project.

“Our expectation is that all resources currently in the inferred category, including the expanded case, will be drilled and upgraded to indicated category. Following the DFS, we’re expecting to have a reserve of around 1.4 Moz just like what was indicated in the expanded case, if not more” Caigen Wang, Tietto Minerals managing director and founder


Aside from the strong

friendly hydroelectricity,

based generators to provide

geological potential

which is not only cheap but a

energy.”

available to Tietto and fellow

stable source of power for the

exploration miners, the

nation’s industrial operations.

country offers favourable fiscal

Wang is also quick to point out that Côte d’Ivoire is a nation

terms and strong government

“Every existing modern

of bitumen roads, including in

support, alongside a network

mining operation in-country

the Abujar region. The project

of infrastructure that is

operates on grid power. In

is well served by bitumen

unrivalled in the region.

our location in central-West

roads which run through the

Côte d’Ivoire, electricity costs

middle of Tietto’s 1,114 km2

In terms of energy, a

for domestic use are 12 cents

exploration licence and along

significant chunk of Côte

US per unit. That’s actually

of the edge of its 120.36 km2

d’Ivoire’s grid power is

very cheap compared with

mining licence. The only

supplied by environmentally-

other mines operating in West

infrastructural development

Africa, where they often use

required is the upgrade of an

expensive and polluting diesel-

18 km site access road, which


MINING | TIETTO MINERALS

ECG Engineering – Proudly partnering Tietto Minerals

From our offices in Perth, Brisbane, Manila and Toronto, ECG services the electrical needs of Mining, Utilities and Material Handling clients across the globe. Our electrical engineering expertise covers feasibility and system audits, design, studies, project management, procurement, construction management and site support. We are proud to partner with Tietto Minerals as it develops the exciting Abujar Gold Project in Cote d’Ivoire.

ECG Engineering Pty Ltd A 2-10 Adams Drive, Welshpool, WA, 6106 T +61 (0) 8 6164 3400 E info@ecg-engineering.com.au Electrical & Controls Global W www.ecg-engineering.com.au

Engineering innovation & integrity in partnership

2801_ECG_Resource_Global_Network_Half_Page_Hor_Ad.indd 1

13/5/21 8:35 am

has already commenced and a

“The work in our PFS on the

optimisation of the production

90kV connector to Daloa.

processing plant side has been

profile at Abujar. The mill

done very much to definitive

is slightly larger than the

feasibility study (DFS) level

capacity used in the PFS,

and Mintrex has actually

which means Tietto won’t have

The PFS estimates that a

been working towards the

to do as much pre-production

$230 million capex will be

DFS from the beginning, so

mining.

required to build the mine

the contingency numbers are

– a conservative figure that

going to be reduced when we

“Now we will be able to

includes $35 million in pre-

reach the definitive stage very

maintain a bigger gold

production mining and

soon.”

production profile,” Wang says.

Lowering the capex

contingency which may not be

“The SAG mill is going to save

necessarily used in the Abujar

In addition, the recent

$3.5 million in capex alone

mine construction, according

procurement of a 4 Mtpa

compared to the PFS estimate.

to Tietto’s managing director.

SAG mill will further reduce

These [aforementioned] things

the capex bill through


are likely to deliver a sizeable reduction in the total capex requirement as well.”

Delivering the DFS The Abujar DFS is scheduled for Q3 of 2021 and will contain upgraded figures on the current 3.02 Moz resource which came out in October last year, based on more than 53,000 metres of mostly infill (and some extensional) drilling across the existing resource on the middle tenement at the project. The infill drilling has focused on adding confidence in the inferred resources that were identified in a scoping study for an expanded project at Abujar. The expansion plan has the potential to deliver increases in NPV, IRR and mine life, with gold production growing to 1.4 Moz of gold recovered over 12 years of operation in the expanded scenario.


MINING | TIETTO MINERALS

“Our expectation is that all resources currently in the inferred category, including the expanded case, will be drilled and upgraded to the indicated category, which means we have an opportunity to add this part of the resource to the reserve. Following the DFS, we’re expecting to have a reserve of around 1.4 Moz if not more,” says a confident Wang. After publication of the DFS, Tietto plans to complete a debt facility, mobilise contractors and begin major construction works in the final quarter of the year. While this timeline puts the company soaring towards first gold and commercial production in Q4 2022, the story doesn’t end there at Abujar. As Tietto always reminds its investors, the current Abujar resource comes from a very small portion of the overall 70 km mineralised strike length, with less than 10% of the project tenements explored


and multiple mineralised

“This puts us in a very

at Abujar: Building and

structures existing in parallel

strong position to continue

operating the gold mine, as

to the strike of the current

expanding our resource base

well as continuous drilling

resources.

while we focus on the mine

to expand the resource base.

development at the same time.

The transition from being

“Most of these targets are yet

With new resources to be

100% exploration-focused to

to be drill tested. That gives us

defined, there is clear upside

a gold producing company is

big potential to increase our

beyond the initial mine life of

evidenced by recent additions

resource base and with our

around 10 years.”

to the executive team, such as

own drilling capacity of six

COO Matt Wilcox in February

are able to drill around 11,000

Personnel for the transition

metres of diamond holes per

As alluded to by Wang,

Tietto’s new COO brings

month.

Tietto is now preparing

huge experience in building

itself to work on two fronts

modern gold mines, with

sets of diamond drill rigs; we

2021.


MINING | TIETTO MINERALS

the latest being the 2.6 Mtpa

mine construction manager,

Yao Nkanza and our geological

Sanbrado mine for West

commercial manager and

team, led by Yaya Ouattara

African Resources in Burkina

health and safety manager.

and Rock Seouvo. They

Faso, which was delivered

are so capable and reliable

under-budget and under-

“I believe that people are

people working at extreme

schedule. Gradually, more

the most critical asset of any

efficiencies. We are really

members of Wilcox’s team will

company. On that note, I would

proud of them and thank them

be joining Tietto, including

like to flag our appreciation

very much,” Wang concludes.

his earthmover manager,

of the in-country team, led by our country manager Fred


Published by Anderson Murray Media Ltd

To tell the resource market your story, contact: editorial@resourceglobalnetwork.com

WWW.RESOURCEGLOBALNETWORK.COM


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.