Pipelines on Rails The Pipeline Alternative


Why Pipelines on Rails? Utilizing tank cars on existing railways or even building a new railway can often be quicker, cheaper and a more flexible way to move large volumes of petroleum and petro-products than building a new pipeline.

Why WorleyParsons Pipelines on Rails? WorleyParsons is the number one provider of engineering and project services to the global Hydrocarbons industry. We use our industry domain knowledge together with our diverse transport capability and understanding of complex rail requirements, to deliver integrated transport solutions incorporating rail, product handling and storage requirements, for our Hydrocarbons customers. WorleyParsons provides robust solutions for our clients by assessing engineering, economics, financing, operations and risk, and we incorporate these into our Pipelines on Rails project solutions that are efficient, both to deliver and operate.

2

WorleyParsons


The Challenge Is there an alternate, more viable option to a pipeline to transport your product? A thorough understanding of all viable options and comparative analysis of the relative feasibility, costs and in particular the operational continuity risks spanning the full asset lifecycle, is imperative to making the right investment decision.

Challenges throughout project life-cycle Cost/Benefit of rail vs pipeline Risk of supply disruption Planning a logistics network

Regulatory constraints Physical constraints of terminal

Securing local construction resources

Cost of ownership of tank cars Operation and maintenance of a tank car fleet Negotiating access tariffs

Our Response WorleyParsons analyzes logistics options, prepares bankable feasibility studies, and delivers integrated Pipelines on Rails systems comprising terminals, tank cars, operating plans, and associated infrastructure. All of this informs our approach to devising optimal solutions to our customer’s challenges.

Progressive risk mitigation

Options analysis (DELTΔ Tool) Logistics chain optimization modelling Route selection

Approvals management Flexible terminal designs supporting both rail and pipe

Execution planning Construction logistics Local contractor relationships Ownership/outsource analysis Railway costing models Chinese procurement Sustaining capital projects Project portfolio management

Pipelines on Rails The Pipeline Alternative

3


A phased approach Our phased approach to project development and delivery is a global discipline proven to progressively mitigate risk and provide delivery assurance.

WORLEYPARSONS’ EXPERIENCE COVERS ALL FIVE PHASES OF THE ASSET LIFECYCLE 1 IDENTIFY

2 EVALUATE

3 DEFINE

4 EXECUTE

5 OPERATE

Our Services

• Options/scoping studies

• Prefered Option selection

• FEED

• Business case

• Master Planning

• Procurement strategies

• Site Selection and permitting

• Risk assessment

• Pre-feasibility study

• Stakeholder engagement

• Simulation modelling • Execution strategy

• Detailed engineering

• Brownfield projects

• Bankable feasibility study

• Procurement

• Portfollio management

• HSE and IR strategies

• EPCM

• Project execution plan

• Project controls

• Cost estimate

• EIS/EA • Approvals management

• Water Solutions

• Mobilisation

• Asset management

• PMC • HVE/HVPD • Environmental Management

• Reliability and integrity • Business improvement

• Commissioning

• Operations and maintenance

• Completeions

• Support • Liability management • Restoration

Pipelines on Rails Service Offering Analyzing Markets Analyzing Markets and creating reliable railbased transport solutions across international borders, that enable multiple paths, using competing transport carriers, to multiple destinations.

4

WorleyParsons

Transport Options Robust Assessment of Transport Options including engineering, economics, financing, operations, risk analysis, and flexibility to serve multiple and changing markets.

Practical Experience Practical Experience of the WorleyParsons team in designing and delivering liquid bulk terminals, railway corridors, and tank car rolling stock.


TCO Crude Export Project CUSTOMER TENGIZCHEVROIL (CHEVRON)

LOCATION KAZAKHSTAN

Key Achievements • Developed feasibility studies and resource calculations for loading facilities, storage and transhipment terminals, rail facilities and trunk routes • Coordinated design activities on interlinked private and state managed railway systems, state and private terminals and sea ports in several countries • Optimized infrastructure and resource requirements for state railways making significant savings for the customer • Devised stage payment regime for contractors on the state railway (first of its kind in Kazakhstan) • Construction monitoring and payment verification

Pipelines on Rails The Pipeline Alternative

5


6

WorleyParsons


Pipelines on Rails The Pipeline Alternative

7


Global experience

1. T CO Crude Export Project

2. Diesel and Jet Fuel Trans-shipment Facilities

3. C ondensate Trans-shipment Facility

Detailed Design, Procurement, Commissioning/Start-up

EPCM, Detailed Engineering, Preliminary Design

Fast track delivery on congested brownfields terminal

Fast track project in harsh marine environment was completed without interruption to existing methanol export facilities

4. A PI West Pilbara Iron Ore Project

5. O akajee Port and Rail – Fuel Infrastructure

6. E thiopia-Djibouti Railway Assessment

Conceptual Design and Definitive Feasibility Study

Feasibility Study

• Fuel infrastructure and fuel procurement strategy to support 126ML pa 6 iron ore mines at 60 MTPA, 400km railway and port facility

• Fuel infrastructure and fuel procurement strategy to support 186ML pa 3 iron ore mines at 45 MTPA, 530km railway and port facility

• 6 x 96kL Rail tank cars

• 12 x 96kL Rail tank cars

• Developed fuel supply chain cost matrix

• Fuel rail train and road train loading and unloading gantries at port and mines

Tengizchevroil Kazakhstan

Feasibility Studies, Design Coordination, Construction Supervision Optimized infrastructure and resource requirements for state railways making significant savings for the customer

API Management Pty Ltd Pilbara, Western Australia

8

WorleyParsons

Kinder Morgan Bulk Terminals North Vancouver, Canada

Oakajee Port and Rail Pty Ltd Mid-West Region, Western Australia

EnCana Oil and Gas Partnership Kitimat, Canada

Citadel Capital Ethiopia

Feasibility Study, Operations Plan Developed detailed business case, operations plans, and market penetration strategy to support our customer in negotiations with the government owners, including a comprehensive plan to import petroleum products to three distribution terminals as Ethiopia has no pipeline infrastructure


1

8 6

3, 10 2 9 7

7. T onkolili Iron Ore Project - Fuel Infrastructure

African Minerals Limited Sierra Leone, West Africa

Definitive Engineering Study • Fuel infrastructure design to support magnetite mine at 25 MTPA, 125km railway and port facility • 18 x 96kL Rail tank cars • Fuel rail train and road train loading and unloading gantries at port and mines

8. F easibility Study for Liquid Sulphur Handling Facilities for Shah Gas Development Abu Dhabi Gas Industries Ltd Abu Dhabi, United Arab Emirates

Pre-FEED, Feasibility Study, Conceptual Engineering, Cost Estimating Delivery Rail alignment through challenging terrain of shifting sand dunes

4 5

9. L a Guajira Thermal Coal Project

CCX Colombia La Guajira, Colombia

Conceptual Design, Environmental Permits 180 Km railway

10. M TBE Trans-Shipment Terminal

Hancock/GVK WorleyParsons Ausenco JV Kitimat, Canada

Preliminary Engineering, Procurement, Detailed Design, Commissioning/Start-up Management • $12 million expansion • New methanol handling facilities • New 30,000 tonne storage tank

Pipelines on Rails The Pipeline Alternative

9


WorleyParsons delivers projects, provides expertise in engineering, procurement and construction and offers a wide range of consulting and advisory services. We cover the full lifecycle, from creating new assets to sustaining and enhancing operating assets, in the hydrocarbons, mineral, metals, chemicals and infrastructure sectors. Our resources and energy are focused on responding to and meeting the needs of our customers over the long term and thereby creating value for our shareholders.

Zero Harm is our corporate vision for health, safety and the environment (HSE). We are committed to our vision and apply it to all operations, at all times, in all locations, and at all levels of responsibility. We will actively work to align our expectations and behaviors to achieve Zero Harm in our dedication to continuous improvement. These expectations are reflected in our integrity management framework, OneWay™, and linked to our global systems and procedures.

EcoNomics™ provides our customers with the systems, technologies and expertise to optimize and balance financial, social, and environmental outcomes, improving sustainability performance while enhancing profit and long-term viability. WorleyParsons’ vision is to be a leader in sustainability by helping our customers capture new markets and business opportunities created by the new energy economy.

10

WorleyParsons


Our values

Performance • Industry leadership in health, safety and environmental performance • Delivering on our promises • People accountable and rewarded for performance • Innovation delivering value for our customers • Creating sustainable value for our shareholders

Relationships • Open and respectful • A trusted supplier, partner and customer • Collaborative approach to business • Willing to challenge and innovate • Seeking enduring customer relationships

Leadership • • • • •

Energy and excitement Integrity in all aspects of business Minimum bureaucracy Committed, empowered and technically capable people Delivering profitable sustainability

Agility • Smallest assignment to world-scale developments • Comprehensive geographic presence • Global expertise delivered locally • Responsive to customer preferences • Optimum customized solutions

Pipelines on Rails The Pipeline Alternative

11


For further information please contact: Larry Shughart Transport Consulting Practice Leader Tel: +1 352 284 1250 Email: larry.shughart@worleyparsons.com

Pipelines on Rails The Pipeline Alternative

www.worleyparsons.com

Warren Williams Global Director, Transport Tel: +61 3 8676 3101 Email: warren.williams@worleyparsons.com