NGAWANG TSETEN ARCH.TSETEN@GMAIL.COM 347.891.9639
SELECTED WORKS: CHARTER SCHOOL:
TRUXTON STREET
01
NEW LOTS AVENUE
04
APARTMENT BUILDING:
ARCHER AVENUE
06
WEST STREET
08
TECH HUB
10
SOLAR DECATHLON
RESIDENTIAL:
ACADEMIC: 12
TRUXTON STREET
39 TRUXTON ST, BROOKLYN, NY, 11233 TYPE: CHARTER SCHOOL GROSS AREA: 63,241.09 SF NEW BUILDING — DOB APPROVED COMPLETION DATE: ON GOING RENDER BY OTHERS 1
THIS PROJECT WAS UNIQUE DUE TO “E” DESIGNATION SET IN PLACE BY THE DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP). THE SITE HAD A EXTRAPOLATED MINIMUM OF 31 OITC RATING. MATERIALS SUCH AS KAWALL AND SOLERA WALL WERE CONSIDERED AND STUDIED; HOWEVER, THEY DID NOT MEET THE MINIMUM 31 OITC RATING. ULTIMATELY A HIGH PERFORMANCE GLAZING WAS SELECTED TO ACHIEVE APPROVALS.
1.8
2
3.6
3
4
4.6
6
1
A-502.01
A-301.01
Ow
5
SCUPPER 8' - 3"
DOWNSPOUT
5' - 0"
3' - 9"
6' - 4"
10' - 3"
5' - 0"
3' - 9"
6' - 4"
10' - 4"
5' - 0"
3' - 9"
6' - 4"
GYM ROOF PAVEMENT FINISH 169' - 6 3/4" TOP OF GYM ROOF STRUCTURE 168' - 6 3/4"
8' - 8"
8' - 6"
ELEVATOR ROOF 174' - 6 3/4"
EQ
EQ
W01A
5' - 2"
W02
W01B
W02
W01A
STAIR BULKHEAD 162' - 10"
2' - 0"
W02
19' - 6"
EQ
9' - 0"
EQ
ROOF FINISH 153' - 6 3/4"
Ke Iss
NU
1
3
A-301.01
A-505.01
1
THE SITE IS ON A CORNER LOT OF A NON-ORTHOGONAL STREET INTERSECTION WITH THREE STREET EXPOSURE OF VARYING LENGTHS. A DESIGN VOCABULARY FOR THE FACADE HAD TO BE PROPOSED SO THAT IT COULD BE SCALED TO FIT ALL THREE EXPOSURES; AND IN ADDITION, THE VOCABULARY HAD TO REINFORCE A LIGHT PRESENCE TO AVERT ATTENTION FROM THE HEAVY MASS. A PANEL SYSTEM WAS USED TO CREATE A PAUSE IN THE BRICK. THE BREAKS BETWEEN THE PANELS WERE SPACED TO BE AT THE HUMAN SCALE—RANGE OF FOUR TO SIX FEET; AND BY DOING THIS, WE MADE THE FACADE MORE FAMILIAR TO PEDESTRIANS.
1.8
2
3
3.6
4
4.6
5
5.5
6
6.2
7
7.3
7.5
7.9
8
6 A-502.01 SCUPPER
GYM ROOF PAVEMENT ELEVATORFINISH ROOF 169' 174' -- 6 6 3/4" 3/4" TOP OF GYM ROOF STRUCTURE 168' - 6 3/4"
10' HIGH CHAIN LINK FENCE—TYP
MP W01A
W02
W01B
5' - 5 5/8"2' - 9 1/8"
W09 73' - 9 5/8" 5' - 4"
3' - 0"
STAIR BULKHEAD 162' - 10"
6' - 10"
9' - 3 1/4"
W02
15' - 0"
15' - 0"
6' - 8 3/4"
6' - 0"
DOWNSPOUT
W01B
5' - 0"
19' - 0"
W02
W01B
4' - 11 3/8"
19' - 0"
W02
2' - 2 1/4"
15' - 9 3/4"
W01B
W02
W01B
15' - 0"
9' - 0"
W02
TOP OF ROOF STRUCTURE 152' - 6 3/4"
5' - 5 5/8"
W02
W01A
W02
W02
2' - 0"
2' - 0" 5' - 0"
3' - 8"
6' - 4"
2' - 0"
W10 W02
W02
W01B
W02
W01B
W01B
60' - 0"
6' - 4"
W01B
W01B
60' - 0" PROPOSED BASE HEIGHT
W01A
15' - 0"
W02
15' - 0"
W01A
63' - 4"
W02
9' - 0"
44' - 0"
W10 W01A
2' - 4"
6' - 0"
W02
9' - 0"
W02
9' - 0"
60' - 0"
4' - 4" 2' - 0" 5' - 0"
9' - 0"
3' - 0"
W01A
ME
W01B 75' - 0" MAX. PROPOSED BUILDING HEIGHT
19' - 8"
Ex
St
2' - 0" 4' - 0"
Ar
ROOF FINISH 153' - 6 3/4"
W10 W01B
6' - 0"
W02
Re
4TH FLOOR 138' - 6 3/4"
3RD FLOOR 123' - 6 3/4"
3' - 0"
4' - 0"
6' - 4"
9' - 0"
5' - 0"
W04 4' - 0"
W05
6' - 4"
EN01 72"
W04
W05
W04
15' - 0"
5' - 0"
10' HIGH CHAIN LINK FENCE—TYP
W05
2' - 8"
6' - 0"
W04
2ND FLOOR 108' - 6 3/4"
BASEPLANE 93' - 6 3/4"
2' - 8"
W05
8' - 0"
3' - 4"
3' - 0"
SF01
1ST FLOOR 93.57
Do Co fie C
ENTRANCE—TOP OF STRUCTURE 92' - 10 3/4"
(5) BICYCLE PARKING PROPOSED
FOUNDATION BRICK SHELF 92' - 6 7/8" FOUNDATION BRICK SHELF 92' - 6 7/8"
2
RESPONSIBILITIES: SD, DD, CD & CA
SOUTH ELEVATION 1/8" = 1'-0"
SOUTH ELEVATION — TRUXTON ST:
BASEPLANE CALCULATION FOR EASTERN PARKWAY: 93.42+93.57+93.54+93.68+93.80+94.29 = 562.3/6 = 93.72 BASEPLANE CALCULATION FOR TRUXTON STREET: 93.82+93.68+93.52+93.44+93.36 = 467.82/5 = 93.56
FOUNDATION BRICK SHELF 92' - 6 7/8"
02 10' HIGH CHAIN LINK FENCE
D
S.S. DOWEL W/ SEALANT THOUGH FLASHING CONT. PRESSURE TREATED WOOD BLOCKING 2" PC ALUMINUM COPING CONT. PRESSURE TREATED WOOD BLOCKING ELASTOMERIC SEALEANT BELOW DRIP EDGE(TYP.) WEEP HOLE (TYP.)
SEALED ANCHOR WEEP SCREED
INVERTED ROOF MEMBRANE ASSEMBLY
1/2" ANCHOR BOLT @ 1' O.C. MAX. (COUNTERSUNK) SEAL ALL PENTRATOPMS THRU VAPOR BARRIER WITH RUBBERIZED ASPHALT MASTIC(TYP.) STUCCO ASSEMBLY MATCH LINE 125' - 0" PROPERTY LINE 125.00'
CMU GROUTED 1
FLASHING WITH TERMINATION BAR MORTAR NET
1.8
STRUCTURAL STEEL ANGLE
2
3
25' - 7"
6' - 4"
1EX03 48"
A
4
UNOCCUPIED SPACE
6 FT TALL FENCE 3' - 8"
EN-112.01 A-311.01
5
2 A-201.01
6
124' - 10"
5' - 0"
W04
4.6
5 1
10' - 4"
6' - 4"
W05
3' - 8"
5' - 0"
W04
10' - 4"
6' - 4"
AD.
W05
3' - 8"
5' - 0"
W04
13' - 0"
5' - 0"
W05
4' - 0"
6' - 4"
W05
7
5' - 0" PROPERTY LINE 5.00'
TOP OF ROOF STRUCTURE 152' - 6 3/4"
CONTINUOUS AIR AND VAPOR BARRIER
10' - 0"
ROOF FINISH 153' - 6 3/4"
5' - 3"
7.3 1 / A-103.01
W04
A
A1 2 A-502.01
6' - 0"
0"
30' - 0 3/8"
30' - 0 3/8"
40
108 E
F 2
2' - 2"
G 1
G 2 F 2
MEN'S RM 210 SF
18' - 5 3/4" FD.
110
WOMEN'S RM 210 SF
49' - 4 1/4"
8' - 9 1/4"
2' - 5 1/8"
104A 36" 2' - 1"
4' - 4"
F 2
9' - 11 1/2"
C1 2
7' - 0"
109 E
OFFICE 1085 SF
'15
7' - 7"
W04
6' - 4"
C1 2
EN02 72"
10' - 9 1/2"
ADA COMPLIANT WALK OFF MAT
C9
ELEVATOR
6'
SECURITY 129 SF
5'
STAIR A
W04 6'
7' - 8"
5'
6'
1' - 6 1/8"
D
3'
W05
- 0"
7 7/8"
8'
02
10' - 2 3/8"
EN01 72"
'59
0"
5' - 0"
W04 4' - 0"
W05
6' - 4"
9' - 0"
5' - 0"
33' - 1 3/4"
C
4"
C1
8"
/4"
1 .0 03 A-2
4"
8"
0"
0"
EA
93.59
W04 4' - 0"
B9
/4"
EXISTING DROPPED CURB TO BE REMOVED
0"
73
AD.
W05 6' - 0"
73
1
SECURITY WINDOW (6'X3') 3' AFF
1' - 10 1/8"
3'
W05
R 6'
13' - 3 3/4"
102
101 VESTIBULE 143 SF
8' - 0"
C1 2
LOBBY 470 SF
B7
W04
24' - 2 1/2"
22' - 11 1/4"
28' - 10 5/8"
8"
28' - 4 1/2"
6' - 4"
EXISTING TREE TO REMAIN
103
2' - 0"
F 2
90
B.6
2 A-503.01
1' - 8 1/2"
12' - 7 7/8"
ADMIN 1817 SF
8"
35' - 10 5/8"
5' - 0"
104 E
W05
DN
B.8
F 2
F 2
3' - 8"
C6
STAIR C
" 1/8
STRUCTURAL COLUMN FIREPROOFED WITH SPRAY ON MATERIAL—TYP
25' - 8 3/4"
EXISTING TREE TO REMAIN
10
AD.
1SC 42"
W08
16
109A 36"
11' - 3 5/8"
6' - 4"
F 2
H 1
1SA 42"
C1
F 2
F 2
'21
110 36"
F 2
47' - 4 1/2"
7' - 0"
1' - 6"
111 36"
F 2
7' - 0"
G 2
18' - 5 3/4" FD.
111 1' - 6"
5' - 6"
57 SF
B4
F 2
01 A-551.00
F 2
F 2
BATHROOM
15' - 6 5/8"
FD.
10' - 4 1/2"
24' - 5 1/8"
5' - 6"
10' - 4 1/8"
G 1
25' - 6 3/4"
8' - 6 1/8"
JAN.
1EX01 60"
3' - 5 1/4"
F 2
9' - 4 7/8"
B 19' - 7"
F 2
4"
STORAGE
H 1
32' - 11 1/4"
4' - 8 1/8"
G 2
8' - 2 1/8"
108 36"
8"
54' - 3 3/4"
G 2
117 36"
11' - 7 7/8"
F 2
11' - 7 7/8"
2' - 2"
57 SF
112 36"
9' - 8"
G 2 8' - 4 3/4"
21' - 3 3/4"
F 2
116 36"
4' - 8 1/8"
2' - 0 3/8"
113 36"
8"
18' - 11 1/4"
32' - 11 1/4"
MECH
1' - 6 7/8"
C
7' - 9 1/8"
F 2
F 2
107 36"
BATHROOM
7' - 0 5/8"
3' - 8"
115 36"
7' - 1"
F 2
F 2
106 36"
" 7/8
25' - 11 1/4"
114 36"
W04
20' - 3 3/8"
F 2
F NURSING RM 2
F 2
F 2
5' - 4 3/8"
7' - 0"
1C04 CORRIDOR 788 SF
1
6' - 4"
DIAPER CHANGING STATION
12 A-551.00
F 2
W05
F 2
105 36"
7' - 0"
F 2
1SBA 42"
A6 A-202.01
3 A-310.01
7'
B9
A4
3' - 1"
1C04A 36"
MUSIC CLASSRM#4 1059 SF 42
27' - 3 3/8"
4"
7' - 0"
2' - 4 7/8" 4' - 8 3/4" 5' - 0"
105' - 0" PROPERTY LINE 105.00'
F 2
W05
95' - 0"
A-300.01
B.6
5' - 0"
1
5' - 0"
3
STRUCTURAL COLUMN FIREPROOFED WITH SPRAY ON MATERIAL—TYP
F 2
9' - 8"
B4
MOTHER GASTON BLVD.
CLASS RM #3 800 SF
26' - 8"
7'
METAL PANEL
107 E
0"
EXTRUDED HANGER
40
26' - 8"
6'
1SBB 42"
1'-5"
104B 36"
SHALLOW CANOPY DRAIN
CLASS RM #2 800 SF
6' - 10 7/8"
39' - 0 5/8"
R
A-205.01
5/8" EXP GYP EXTERIOR SHEATHING
106 E
26' - 8"
10' - 11 3/8"
B
3RD FLOOR 123' - 6 3/4"
40
30' - 0 3/8"
CLASS RM #1 797 SF
2' - 3 1/8" 3' - 0"
W05
STAIR B
A8
STEEL ANGLE - SEE STRUCTURAL DWGS. PAINT ANGLE TO MATCH BRICK WHERE EXPOSED
20' - 0"
25' - 10 3/8"
105 E
UP
1
25
OCCUPANCY IS NOT SIMULTANEOUS FOR TOILET FIXTURE COUNTS. 20' - 3"
6' - 0"
METAL SILL
F 2
F 2
F 2
F 2
A6
3" MINERA WOOL INSULATION R-8.5 MIN
PLAY AREA 1842 SF
E
A4
3" MINERA WOOL INSULATION R-8.5 MIN
ER ST
N
PA
R
KW
AY
EX
N TE
ON SI
C6
C9
D
17'-0" 6'-11"
6' - 4"
21'-3 5/8"
15'-8 3/4"
8'-2 3/4"
2 89' - 7 3/8"
6
02 A-501.01
A-204.01
6.2
7
7.3
90' - 9 1/2" PROPERTY LINE 90.79'
EXISTING TREE TO REMAIN
EXISTING TREE TO REMAIN
N
EXISTING TRAFFIC SIGN—TYPICAL
TRUXTON AVE
1ST FLOOR 93.57
ENTRANCE—TOP OF STRUCTURE 92' - 10 3/4"
WALL SECTION AT ENTRANCE:
TEMPERED GLASS DOOR FLASHING UNDER THE DOOR THRESHOLD SPLIT SLAB OR SANDWICH SLAB CANT STRIP CONTROL JOINT 2" RIGID INSUATION MIN. R-10
1
1.8
2
3
3.6
4.6
4 1
A-301.01
GROUND FLOOR PLAN: 1
1ST FLOOR—PART A 3/16" = 1'-0"
A1
3' - 6"
RAIN SCREEN PANEL
A2
6'
A2
R
ALUMINUM COVER
5
5.5
NEW LOTS AVE
556 NEW LOTS AVENUE, BROOKLYN, NY, 11207 TYPE: CHARTER SCHOOL GROSS AREA: 60,257 SF NEW BUILDING — DOB APPROVED COMPLETION DATE: ON GOING THE SITE IS LOCATED ON A CORNER ZONING LOT. THE BASE BUILDING HEIGHT IS SIXTY FEET AND THE MAX BUILDING HEIGHT IS HUNDRED-AND-TWO FEET AND EIGHT INCH. THE STARK DIFFERENCE, OF ROUGHLY, TWENTY-SEVEN FEET CREATED A STACKING EFFECT—GEOMETRY “A” AND “B” (SEE RIGHT) WERE COMPETING FOR DOMINANCE. THE STAKING VOLUMES DUE TO THE TWENTY FEET ZONING SETBACK AFTER THE BUILDING-BASE-HEIGHT DID NOT ALLOW THE TYPICAL FLOOR ELEMENTS,—BATHROOM AND CIRCULATION, TO BE APPLIED TO THE UPPER LEVELS. ON THOSE LEVEL, THE CIRCULATION AND ROOMS HAD TO BE REIMAGINED. THE BIGGEST PROGRAMMATIC VOLUME,—THE GYM, WORKED BETTER ON THE REDUCED FOOTPRINT. BY PLACING THE GYM ON THE TOP LEVEL, WE WERE ABLE TO MINIMIZE THE STRUCTURAL BEAMS SPANNING THE GYM. THE DESIGN STANDARD OF 60:30:10 RATIO WAS USED IN THE MATERIAL BOUNDARIES/AREAS. THIS ALLOWED THE BUILDING’S LARGE GEOMETRIC MASS THAT CONFLICT WITH ONE ANOTHER TO HARMONIZE INTO A SINGULAR UNIFIED DESIGN STATEMENT.
RESPONSIBILITIES: SD, DD & CD
RENDER BY OTHERS
04
CHARTER SC 1
1.7
2
2.3
2.7
3
108' - 4 3/4" PROPERTY LINE (108.4 FT)
3.4
3.8
556 NEW LOTS A BROOKLYN, NY 1
4
Owner:
1 A-202.00
1
ADJACENT BUILDING
SOLY D. BAW
ADJACENT BUILDING
A-301.00
CHEYENNE REALTY LLC 15 OCEAN AVE, 2ND FL BROOKLYN, NY 11225
17' - 4 5/8" PL. TO CURB
OFFICE
E
71.74 SF
1 F1 2
6' - 5 1/8"
115 36"
F1 2
9' - 0 5/8"
114 36"
F 2
F 2
F1 2
11' - 1 5/8"
5"
51' - 11 1/4"
24.78
1C01 CORRIDOR
31' - 1 7/8"
1ST VESTIBULE
7' - 0"
15' - 7 5/8"
106 IT SERVER RM 75.68 SF
3' - 2 1/2"
E
203.00 SF
104 MEN'S RM 109.06 SF
104 36"
101A NURSES STATION 9
3
8' - 2"
107 36"
101B 36" 6' - 9"
110
CLASS RM. K-4
E
623.17 SF
32
6' - 0"
19' - 5 1/2"
Architect:
40
E
885.19 SF
45
3' - 2 7/8"
108B 36" CL
CONFERENCE RM 264.24 SF
3 24.78
6' - 2 1/8"
22' - 0 1/4"
13' - 11 5/8"
27' - 10 1/2"
W33
7'-11"
17' - 6 1/8" PL. TO CURB
5'-0"
3'-4"
5'-0"
EB 2
24.78 3'-6"
4'-10"
9'-1"
W49
Structural Engineer:
STRUCTURAL TECHNOLOGIE 40-12 28TH STR LONG ISLAND
W33
W27 5'-0"
3'-5"
5'-0"
31' - 1 7/8"
W27 3'-3"
MEP Engineer:
A&D ENGINEE 2313 E 65T STR 2606 E 15TH ST NY 11235 - MAI Expediter:
7' - 6 1/8"
CORE CONSUL 254 36TH STRE BROOKLYN, NY
Interior Designer:
8 5/8"
EN05 36"
W27
IMC ARCHITEC 254 36TH STRE BROOKLYN, NY
5' - 11 1/2"
12' - 0"
5' - 0"
7' - 0"
E
5' - 7 1/4"
799.09 SF
109A PRE-K
100' - 0" PROPERTY LINE (100.0 FT)
W52
8' - 0"
5' - 0"
E
109B 36" CL
7' - 0"
108A PRE-K
102A 36"
103
REVIEW
1
5' - 0"
2
103 36"
W27
DOB RE
10.13.22
Revisions:
31' - 3 3/8"
156.78 SF
37' - 1 1/8"
E
11' - 2 3/8"
3' - 2 7/8"
102A STAFF LOUNGE
15' - 7 5/8"
ENERGY
09.07.22
7
A-201.00 14' - 0"
W33
ENERGY
08.29.22
6
W52
28' - 6 1/2"
W27
08.15.22
5
31' - 1 7/8"
109A 36"
7' - 2 3/8"
5' - 0"
102B 36"
4
EXISTING WALL 0.2' NO.
7' - 0"
101BBATHROOM E 51.96 SF 8' - 0"
102BBATHROOM E 53.96 SF
DOB RE
EXISTING PLANTER ON ADJACENT PROPERTY
35' - 9 7/8"
6' - 9"
35' - 2 3/4"
5' - 8 1/4"
EB 2
5' - 9 3/4"
5' - 0"
A-300.00
D
W49
F 2
108A 36"
W27
DOB RE
07.14.22
1" BUILDING SEPARATION FOR SEISMIC REQ. PER TPPN # 2/96: 1" PER 50" HEIGHT. PROPOSED PROPERTY WALL HEIGHT: 15 FT PROPOSED SEPARATION:5"
92' - 0"
107 WOMEN'S RM 102.37 SF
F 2
DOB SU
12.06.21
3
F 2
110 36"
2' - 0"
58' - 4 3/8"
5' - 0"
14' - 6"
92' - 0"
W33
854.76 SF
30
111 36"
11' - 6 5/8"
3' - 2 1/2"
9' - 5"
1
C
H1 2
101A 36"
MAIN OFFICE
582.42 SF
11.01.21
2
W52 106 36"
14' - 0"
24.78
E
E 7' - 6 5/8"
7' - 6 5/8"
10' - 0 1/4"
105 JAN. 69.47 SF
14' - 6 1/8"
100
CLASS RM. K-4
DESCRI
DATE
1
8' - 3 1/2"
10' - 1 3/8"
9' - 2 3/8"
105 36"
A-200.00
7" EXISTING TREE TO REMAIN
111
20' - 0"
W27
21' - 4 5/8"
100 36"
F 2 9' - 5 3/8"
5' - 0"
NEW LOTS AVENUE 70 FT NARROW
5' - 10"
100' - 0" PROPERTY LINE (100.0 FT)
3
5' - 11 5/8"
8"
8"
B
17' - 6 5/8"
NUMBER
8' - 5 7/8"
FIRE COMMAND STATION
W49
18' - 9 5/8"
EN01 72"
5' - 0"
EN03 72"
17' - 6 1/4"
17' - 6 1/8"
WALK-OFF MAT
18' - 2 1/8"
A.3
3096799 B006216
Key Plan: Issued: 1SB1 42"
25' - 2 3/8"
ADJACENT BUILDING
25' - 6"
EN02 72"
#: #:
1CSB STAIR B
12' - 9 1/8"
IT ROOM
F 2 116 36"
LOT: 1
NYC BIN NYC DOB
UP
114
7' - 0"
EN04 72"
F1 2
2 A-501.00
2' - 4 7/8"
25' - 4"
F1 2
F 2
115
B 3
3' - 0"
1SB2 36"
G 2
G 2
1SA1 42"
F1 2
B 3
C 2
50' - 7 1/2"
ADJACENT BUILDING
117 36"
10' - 2"
ELEVATOR
0"
DN
F 2
24.78
6'
4' - 10 1/2"
12' - 9 1/8"
101.67 SF
117
OFFICE
R
1CSA STAIR A
F 2
4' - 10 1/2"
126.33 SF
UP
118 36"
A.2
23' - 2 1/2"
2
SECURITY OFFICE
E
1 A-302.00
1SA2 36"
BLOCK:4305
100' - 3 3/4"
3' - 0"
EA 2
8' - 0"
9' - 4 7/8"
118
2' - 3"
6" EXISTING TREE TO REMAIN
12' - 9 1/8"
5' - 11 1/8"
A
7 A-553.00
(5) CYCLE PARKING SPACE PROPOSED 41' - 3 3/8"
12' - 9 1/8"
2 A-500.00
5'-0"
W33
W27 9'-4"
5'-0"
3'-4"
5'-0"
W27 4'-8"
5'-0"
6'-7"
99' - 4 3/4"
20' - 3 3/8"
A-203.00
Do Not Scale Plans Contractor to promptly notify Architect field conditions and existing conditions
PL. TO CURB
20' - 3 3/8"
PL. TO CURB
2
E
C COPYRIGHT 2018 IMC Architecture DPC
1ST FLOO 5" EXISTING TREE TO REMAIN 107' - 4 3/4" PROPERTY LINE (107.4 FT)
GROUND FLOOR PLAN: 1ST FLOOR 1
3/16" = 1'-0"
VAN SICLEN AVENUE 100FT WIDE
EXISTING BICYCLE RACK
PROPOSED TREE TO REMAIN
W
SEAL & SIGNATURE:
ARCHER AVENUE 48" PARAPET 48" PARAPET
10' - 0"
10' - 0"
10' - 0"
W2
10' - 0"
10' - 0"
W2
10' - 0"
10' - 0"
W2
10' - 0"
10' - 0"
W2
10' - 0"
10' - 0"
W2
10' - 0"
10' - 0"
W2
PROPOSED BUILDING 10' - 0" 221' - 0" 10' - 0" 10' - 0" HEIGHT 10' - 0"
10' - 0"
W2
10' - 0"
W2
10' - 0"
W2
10' - 0"
W2
10' - 0"
10' - 0"
W2
10' - 0"
W2
10' - 0"
W2
10' - 0" 10' - 0"
10' - 0"
10' - 0"
10' - 0"
W2
8' - 0" 10' - 0" 11' - 0"
10' - 0"
W2
10' - 0"
18' - 0"
10' - 0"18' - 0" 8' - 0" 11' - 0"
W2
10' - 0"
48" PARAPET 48" PARAPET
10' - 0"
BULKHEAD BULKHEAD 275.42 275.42
10' - 0"
ELEV. MAC ELEV.RM MAC RM 283.42 283.42
10' - 0"
EMR BULKHEAD EMR BULKHEAD 293.42 293.42
48" PARAPET 48" PARAPET
48" PARAPET 48" PARAPET
VESTIBULE VESTIBULE
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1 W1
W1
W2
W1
W1
W1
W1
W1
W1W1
W1
W2
W2
W1
W1
W1
W1
W1
W1W1
W1
W2
W2
W1
W1
W1
W1 W1
W1
9' - 9 1/2"
W1
9' - 6"
9' - 6"
W2
20TH FLOOR 20TH FLOOR 254.42 254.42
9' - 9 1/2"
ROOF ROOF 265.42 265.42
9' - 6"
9' - 6"
19TH FLOOR 19TH FLOOR 244.42 244.42
9' - 6"
9' - 6"
18TH FLOOR 18TH FLOOR 234.42 234.42
9' - 6"
9' - 6"
17TH FLOOR 17TH FLOOR 224.42 224.42
9' - 6"
147-27 ARCHER AVENUE, BROOKLYN, NY, 11207 TYPE: MIXED USE APARTMENT BUILDING GROSS AREA: 270,195 SF NEW BUILDING — DOB APPROVAL PENDING
9' - 6"
16TH FLOOR 16TH FLOOR 214.42 214.42
9' - 6"
9' - 6"
15TH FLOOR 15TH FLOOR 204.42 204.42
9' - 6"
9' - 6"
14TH FLOOR 14TH FLOOR 194.42 194.42
9' - 6"
9' - 6"
13TH FLOOR 13TH FLOOR 184.42 184.42
9TH FLOOR 9TH FLOOR 144.42 144.42
THE FACADE IS MADE UP OF BRICK. THE ZONING LOT HAS AN ENVIRONMENTAL RESTRICTION ESTABLISHED BY THE DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP). THE WINDOWS ARE REQUIRED TO MEET A MINIMUM BE OITC RATING OF THIRTY-FIVE.
9' - 6"
9' - 6" 9' - 6" 9' - 6" 9' - 6"
9' - 6"
8TH FLOOR 8TH FLOOR 134.42 134.42
9' - 6"
6TH FLOOR 6TH FLOOR 114.42 114.42
300
300
9' - 6"
9' - 6" 9' - 6"
YOGA ROOM YOGA ROOM
9' - 6"
4TH FLOOR 4TH FLOOR 94.42 94.42 9' - 6"
3RD FLOOR 3RDROOF FLOOR ROOF TERRACE ACCESSIBLE BY TERRACE ACCESSIBLE BY TENANTS. SEE FLOOR TENANTS. SEE FLOOR PLAN FOR BALANCE. PLAN FOR BALANCE.
CIRCULATION CIRCULATION
9' - 6"
5TH FLOOR 5TH FLOOR 104.42 104.42
9' - 6"
7TH FLOOR 7TH FLOOR 124.42 124.42
19' - 0"
PARKINGPARKING GARAGEGARAGE
19' - 0"
VESTIBULE VESTIBULE
19' - 4"
20' - 0"
20' - 0"
PARKINGPARKING GARAGEGARAGE
19' - 4"
3RD FLOOR 3RD FLOOR 84.42 84.42
20' - 0"
2ND FLOOR 2ND FLOOR 64.42 64.42
20' - 0"
THIS PROJECT WAS AN ENJOYABLE EXPERIENCE. AFTER YEARS OF WORKING ON THE APARTMENT TYPOLOGY—IT WAS A TESTING GROUND FOR ME AND MY TEAMMATE ON EXECUTING WHAT WE LEARNED. WE WERE ABLE TO DISTRIBUTE THE WORK AS NEEDED FOR THE PROJECT ARCHITECT. COMMUNICATION FLOWED SMOOTHLY AND WE WERE ABLE TO DELIVER ON VERY TIGHT DEADLINE.
9' - 6"
10TH FLOOR 10TH FLOOR 154.42 154.42
9' - 6"
11TH FLOOR 11TH FLOOR 164' - 5"164' - 5"
9' - 6"
221' - 0" PROPOSED BUILDING HEIGHT
THIS PROJECT IS TWENTY STORY MULTIFAMILY BUILDING WITH THREE-HUNDRED-FIFTY-NINE UNIT. ONE-HUNDRED-NINETEEN OF THE UNITS ARE FOR INCLUSIONARY HOUSING. THE MAX BUILDING HEIGHT IS TWO-HUNDRED-ONE FEET.
9' - 6"
12TH FLOOR 12TH FLOOR 174.42 174.42 BRICK FACADE—TYP. BRICK FACADE—TYP.
ELEVATOR ELEVATOR VESTIBULE VESTIBULE
COMMERCIAL COMMERCIAL
RES. LOBBY RES. LOBBY
VESTIBULE VESTIBULE
CELLAR FLOORFLOOR CELLAR 28.42 28.42 BASE PLANE BASECALCULATION: PLANE CALCULATION: (43.94' + 43.80' = 44.42' (43.94'++44.55' 43.80'++45.40') 44.55' /+445.40') / 4 = 44.42'
RESPONSIBILITIES: CD
1
SECTION PARALLEL TO ARCHER AVENUE:
SECTION A SECTION A 1 3/32" = 3/32" 1'-0" = 1'-0"
CIRCULATION CIRCULATION
ATS
ATS
15' - 0"
VESTIBULE VESTIBULE
15' - 0"
SERVICE CORRIDOR
PARKINGPARKING
SERVICE CORRIDOR
BASE PLANE BASE PLANE 44.42 44.42 16' - 0"
BASE PLANE BASE PLANE 44.42 44.42
16' - 0"
1ST FLOOR 1ST FLOOR 44.42 44.42
06
ING OSED BUILD 50' - 1 1/4" PROP 20' - 0"
H 2
1' DROP SOFFIT
H 2
1' DROP SOFFIT
515
13' - 10 1/2"
2' - 11 1/4"
6' - 5 7/8"
BEDROOM 9' - 1 7/8"
109 SF
LR / DA
1 BR
4' - 9 5/8"
2' - 8 1/2"
6' - 4 5/8"
190 SF
LR / DA
STUDIO
12' - 2 1/4"
155 SF
LR / DA
STUDIO
14' - 0"
156 SF
F 2
F 2
14' - 0"
LR / DA
LR / DA
159 SF
6' - 1"
W1
STUDIO
Revisions: Architect:
H 2
11' - 7 3/8"
W1
9' - 5"
513B
4' - 6"
5' - 10 3/8"
W1 4' - 6"
W1 5' - 4 1/2"
4' - 6"
W1
W2 5' - 4 1/2"
6' - 0"
5' - 5 1/2"
4' - 6"
W1 3' - 6"
4' - 6"
W1 5' - 2 3/4"
4' - 6"
W1 1' - 9 1/4"
4' - 6"
4' - 4 7/8"
W1
EA 2
4' - 6"
6' - 7 1/8"
164' - 7 3/8" PROPOSED BUILDING
5TH FLOOR — TYPICAL FLOOR PLAN:
1
FOURTH - TWENTY FIRST TYPICAL FLOOR PLAN 3/16" = 1'-0"
1 A-203.00
W2 6' - 0"
W1 4' - 9"
4' - 6"
W1 2' - 6"
4' - 6"
W1 3' - 0"
4' - 6"
2' - 6"
W1
EA 2
4' - 6"
5' - 9"
CL.
16' - 11"
CL.
E1 0
E1 0
WSP One Penn Pl 250 W 34th S New York, NY www.wsp.com
17' - 5 3/8"
513 LR / DA R2 405 SF LR / DA
W1
186 SF
Expediter:
JM ZONING 225 BROADW New York, NY www.jmzonin (212) 964 - 4
E1 0
512C
F 2
CL.
512F
512G
EA 2
W1
Interior Designer:
S/C
349 SF
E1 0
512E
512D
S/C
E1 0 BEDROOM
2 BR 13' - 11"
108 SF
E1 0 BEDROOM
10' - 0"
W2 6' - 0"
Structural Engineer:
MEP Engineer:
149 SF
10' - 0" 4' - 6 5/8"
W1 5' - 0 3/4"
EA 2
IMC ARCHIT 254 36TH ST BROOKLYN,
F 2
512B
11' - 10"
512 LR / DA R2 828 SF
W1
STUDIO 9' - 10 3/8"
5' - 4 7/8" 2' - 0"
2' - 7 1/2" 2' - 1" S/C
511 LR / DA R2 388 SF
S/C
OITC Rating 3
2' - 0"
E1 0
B3
F 2
1' DROP SOFFIT
11' - 4 1/2"
E1 0
7' - 10"
OITC Rating 3
2' - 0"
2' - 0 1/2" 6' - 1"
E1 0
H 2
7' - 10"
S/C
H 2
H 2
B3
4' - 0"
E1 0
13' - 10 1/2"
K2
S/C
510 LR / DA R2 380 SF
F 2
H 2
G 2
6' - 7 3/8"
173 SF
21' - 11 1/8"
ELEC/ TELE CL K2
513A CL.
H 2
512A
5' - 4 7/8"
511B
5' - 0"
DW
B5 6' - 1"
E1 0
H 2
DW
1' DROP SOFFIT 13' - 10 1/2"
5' - 0"
E1 0 8' - 0 3/4"
DW
H 2
E1 0
H 2
E1 0
H 2
DW
F 2
S/C
2' - 9"
3' - 8" 7' - 11"
G 2
159 SF
15' - 4 7/8"
509 LR / DA R2 602 SF
E1 0
13' - 8 5/8"
12' - 6"
5'-9" 5'-9"
4' - 10 7/8"
510B
K2
15' - 7 1/2"
512
511A
H 2
1' DROP SOFFIT 13' - 6 3/4"
13' - 7 1/4"
9' - 5 1/2"
1' DROP SOFFIT 13' - 10 1/2"
DW
B6
E1 0
G 2
K2
S/C
F 2
R3 '-8 "
5'-9"
24' - 3 1/2"
5' - 0"
509D
6' - 1"
E1 0
8' - 1 7/8"
2' - 0"
E1 0
509C E1 0
509E S/C
13' - 10 3/8"
1' DROP SOFFIT
4' - 6 3/4"
CL. 2' - 6"
K2
E1 0
H 2
E1 0
B4
OITC Legen
STUDIO
514 LR / DA R2 391 SF
11' - 0"
151 SF
E1 9' - 4 7/8" 0 6' - 6"
3' - 2 3/8" S/C
6' - 0"
71 SF 11' - 2"
7' - 11"
5' - 0"
TRASH RM
1' DROP SOFFIT 13' - 8 1/8"
DW
5' - 0"
WALK-IN CL.
E1 0
6' - 1"
E1 0
513
522
WALK-IN CL.
H 2
510A
7' - 10"
5' - 2 3/4"
11' - 0 3/8"
LR / DA
STUDIO
E1 0
6' - 1"
514B
WALK-IN CL.
G 2
11' - 0 3/8"
193 SF
E1 0
508 LR / DA R2 410 SF
509B
6' - 1"
H 2
5' - 0"
25' - 3"
E1 0
F 2
511
WALK-IN CL.
509A
E1 0
DW
1' DROP SOFFIT 514A
C1 3
C1 3
11' - 0 3/8"
LR / DA
STUDIO 17' - 6 1/2"
7'-0"
12' - 8 3/4"
12' - 8 1/8"
1' DROP SOFFIT 5' - 6 3/8"
F 2
STAIR A
510
E1 0
CL.
B4
K2
508B
509
11' - 0 1/2"
8' - 1 3/4"
507 LR / DA R2 457 SF
B7
H 2
DW
4' - 11 3/4"
4' - 11 3/4"
6' - 1"
H 2
8' - 1"
E1 0
H 2
E1 0 H 2
7' - 10"
5' - 0"
5' - 0"
12' - 2 1/4"
B7
6'-8"
5SA
G 2 508A
WALK-IN CL.
6' - 1"
E1 0
6' - 5 3/8"
S/C
190 SF
E1 0
507B
2' - 11 1/4"
5' - 4"
F 2
1' DROP SOFFIT 13' - 10 1/2"
13' - 10 3/4"
13' - 5 5/8"
1' DROP SOFFIT
E1 0
C1 3
501
508
K2
514
UP
DN
80' - 10 5/8" (DEAD END CORRIDOR)
11' - 10 7/8"
LR / DA
E1 0 2' - 11 1/4"
506 LR / DA R2 523 SF
1 BR
9' - 5"
DW
2' - 0" 5' - 6 1/8"
112 SF
9' - 3"
K2
6' - 1 1/4"
WALK-IN CL.
2
F 2
500
C1 3
5' - 0"
6' - 1 1/8"
H 2 8' - 1"
5' - 0"
BEDROOM
DW
7' - 11"
13' - 8 3/4"
12' - 8 1/8"
DW
1' DROP SOFFIT 13' - 8 3/4"
DW
1' DROP SOFFIT 13' - 8 3/4"
7' - 11"
7' - 11 3/4"
FD.
WALK-IN CL.
501A
G 2
11' - 0 3/8"
131 SF
506D E1 0
S/C
9' - 0"
5' - 0"
8' - 1" 2' - 0"
14' - 7"
BEDROOM
506C
E1 0
K2
507A
11' - 0 1/8"
162 SF
CL.
6' - 2 3/8" 11' - 10 7/8"
13' - 5 5/8"
S/C
E1 0
10' - 0"
2' - 9 3/4"
E1 0 506E
505H
S/C
H 2
DW
5' - 0"
F 2
506B
WALK-IN CL.
E1 0
H 2
11' - 0 1/2"
5' - 0"
CL.
7' - 11"
2' - 0" 5' - 2 1/2"
505G S/C
6' - 1"
G 2
G 2
H 2
H 2
F 2
13' - 10 1/2"
ELEVATORS 6'-8"
LR / DA
WALK-IN CL.
7' - 6 1/8"
C1 3
DOB
OITC Rating 3
4' - 6"
2' - 0"
E1 0
E1 0
5' - 0"
G 2
B4
E1 0
E1 0
C1 3
7' - 4 1/4"
6' - 1"
W1
12' - 6"
505F
H 2
G 2
502A
507
E1 0
CL.
K2
502
506
506A
B4
K2
WALK-IN CL.
503
1' DROP SOFFIT
2' - 0" 6' - 6" 6' - 6"
505D
CL.
12' - 8 1/8"
15' - 6 1/8"
9' - 9 5/8"
505E
E1 0 W/D
E1 0
S/C
501B
515 LR / DA R2 396 SF
4' - 6"
505C
504
E1 0
505
H 2
CL.
E1 0
503A WALK-IN CL. F 2 6' - 0 1/8" 5' - 0"
G 2
5' - 4 5/8"
F 2 18' - 11 5/8" F 2
B4
H 2
H 2
E1 0
DN 3' - 8"
DOB
4' - 0"
E1 0
G 2
E 0
B4
H 2
H 2
UP
E1 0
OER
4' - 6"
505A
K2
502B
6' - 1"
8' - 5"
C1 3
B4
11' - 4 1/2"
4' - 6"
B8 10' - 0"
504A
CL.
K2
2' - 0 1/2"
E1 0
S/C
6' - 1"
E1 0
8' - 2 3/4"
5'-2" 7' - 2 1/8"
H 2
E1 0
05.20.2022
4' - 6"
4' - 0"
S/C
S/C
503B
E1 0
7' - 8"
STUDIO
4' - 2 7/8"
7' - 10"
EA 2
W1
2' - 0"
H 2
505B
H 2 G 2
6' - 7 7/8"
H 2
E1 0
3' - 3 3/8" 1' - 5"
C1 3
STAIR B
E1 0
DOB
5
4' - 6"
B7
H 2
E1 0
504B
6' - 1"
7' - 3 5/8"
H 2
E1 0
CL.
H 2
6' - 10 5/8"
ELEVATOR
164 SF
5' - 2 3/4"
04.27.2022
3' - 6"
B8
E1 0
CL.
504C
STUDIO
6' - 1 7/8"
LR / DA
5SB
6' - 4 7/8"
G 2
504D
208 SF
6'-8"
515B
11' - 4 1/2"
14' - 0"
S/C
7' - 6 1/4"
E1 0
LR / DA
F 2
STUDIO
4' - 5 1/4"
F 2
S/C
153 SF
8' - 0"
F 2
25' - 4"
F 2
S/C
2' - 10 5/8" 4' - 8 5/8"
1 BR
LR / DA
F 2
501 LR / DA R2 409 SF
515A
6' - 0"
E1 0
F 2
12' - 10"
502 LR / DA R2 466 SF
E1 0
DW
4
4' - 6"
229 SF
16' - 3 7/8"
503 LR / DA R2 396 SF
K2 13' - 10 1/2"
6' - 0"
6' - 0 7/8"
F 2
6' - 4 7/8"
LR / DA
7' - 3 5/8"
DW
EA 2
5' - 0 1/8"
C1 3
C1 3
H 2
B3
E1 0
11' - 4 1/2"
2' - 0"
4' - 8"
EC 2
8' - 10 3/4"
8"
60' - 0"
W1
W1
R 3' -
55' - 4"
W1
27' - 10 1/8"
4' - 6"
1 A-511.00
4' - 6"
3' - 6"
W1
2' - 7 1/8"
W1
130' - 6 3/4" PROPOSED BUILDING
4' - 6"
158 SF
4' - 6"
W1
EA 2
2' - 10 7/8"
DOB
04.06.2022
2' - 6"
4' - 6"
6' - 0"
F 2
268 SF
8' - 2 7/8"
10' - 0"
BEDROOM
3' - 7 1/8"
12' - 0 1/4"
504 LR / DA R2 635 SF
2 BR
H 2
E1 0
147 SF
E1 0
1' DROP SOFFIT H 2
13' - 11"
BEDROOM
504E
K1
1
W1
4' - 6"
6' - 0"
15' - 6 1/2"
505 LR / DA R2 1156 SF LR / DA
9' - 6"
EA 2
E1 0
A-301.00
W1
W2
3' - 10 7/8"
LR / DA
STUDIO
14' - 0"
W1
EA 2
2' - 2"
1
4' - 6"
10' - 8 5/8"
W1
A-200.00
1' - 4"
H 2
5' - 2 3/4"
W1 13' - 10 3/4"
4' - 6"
4' - 6"
E1 0
B4
2' - 10 1/2" 4' - 8 5/8"
3' - 0"
EA 2
5' - 1 5/8"
H 2
WALK-IN CL.
6' - 4 7/8"
W1
6' - 0"
11' - 4 1/2"
516 LR / DA R2 409 SF
7' - 10"
E1 0
E1 0
DESC
02.07.2022 03.31.2022
3
S/C
516B
516A
521
6' - 0"
6' - 7 1/2"
516
E1 0
7' - 10"
4' - 6"
E1 0
DW
S/C
DATE
1 2
NUMBER
A-202.00
4' - 6"
K2
1' DROP SOFFIT
6' - 1"
4' - 7 1/8"
2' - 3 1/4"3' - 4 7/8"
4' - 6"
4' - 6"
DW
13' - 10 1/2"
6' - 0"
3' - 4 7/8"
113' - 0 3/4" PROPOSED BUILDING 3' - 11 1/2"
E1 0
7' - 0"
K2
H 2
255 SF
Key Plan: Issued:
1
4' - 8 5/8"
4' - 6"
LR / DA
W2
1' DROP SOFFIT H 2
521 LR / DA R2 407 SF
11' - 4 1/2"
1 BR
6' - 0"
CL.
16' - 0 3/4"
STUDIO
6' - 10 7/8"
DW
G 2
4' - 6"
CL.
14' - 0 1/2"
DW
342 SF
517 LR / DA R2 674 SF 13' - 10 1/2"
2' - 9 3/8"
9' - 5 7/8"
K2
4' - 6"
E1 0
517
1' DROP SOFFIT
3' - 0"
517C
E1 0
2' - 10 1/4"
55' - 3 1/8" (DEAD END CORRIDOR)
4' - 6"
F 2
1' DROP SOFFIT
W1
CL.
E1 0 517A
LR / DA
520 LR / DA R2 55 SF
K2
137 SF
14' - 4 1/4"
343 SF
STUDIO 16' - 0 3/4"
W1
BEDROOM
LOT: 1,
NYC BIN # : Q00676542-
6' - 1 1/8"
LR / DA
517E
E1 517D 0
E1 0
5' - 0"
F 2
E1 0
2' - 0"
517B
CL.
5' - 6 1/8"
66' - 1 1/4" PROPOSED BUILDING
4' - 6"
520
6' - 0"
B2 8' - 1"
E1 0
2' - 0"
W1
BLOCK:9995
DW
F 2
E1 0 CL.
H 2
G 2
F 2
6' - 6"
520A
W2
8' - 0 1/2"
9' - 6 5/8"
H 2
176 SF
KJL REALTY 512 7TH AVE NY NY, 1001
6' - 0"
LR / DA
1 BR
6' - 6"
8' - 1"
B2
EA 2
LR / DA 615 SF
1' DROP SOFFIT
518
K2
W1
EA 2
518
17' - 2 1/2"
147-27 ARCHER NY 11435
4' - 6"
519
ARCHER AV
Owner: E1 0
E1 0
H 2
E1 0
8' - 3 1/2"
E1 0
F 2
W1
11' - 5 5/8"
F 2
F 2
1' - 6 3/4"
EA 2
2' - 0"
518A
144 SF
E1 0CL.
518B
H 2
519A
4' - 9 1/8"
16' - 7 3/4"
E1 0
H 2
BEDROOM
7' - 7 3/4"
E1 0 CL.
CL.
6' - 1"
B-1
B1
F 2
K2
E1 0
2' - 0"
7' - 7 3/4"
H 2
H 2
2' - 6"
5' - 7 1/4"
E1 0
519B
14' - 9 1/2"
2' - 0"
6' - 3 5/8"
10' - 5 1/2"
CL.
4' - 0 1/8"
STUDIO
H 2
10' - 2 3/4"
187 SF
12' - 2"
9' - 6"
6' - 0"
LR / DA
G 2
DW
519 LR / DA R2 420 SF
W2
W2
9' - 4 1/8"
18' - 6 3/4"
6' - 1"
2' - 5 1/2"
1 A-201.00
5' - 0"
6' - 0"
EA 2
4' - 6" W1
5' - 0"
4' - 6" W1
5' - 1 1/8"
5' - 3 1/4"
1 A-300.00
W1 7' - 1 5/8"
4' - 6"
6' - 2 3/8"
W1
EA 2
4' - 6"
3' - 1 3/4"
Do Not Scale Plans Contractor to promptly notify Archite field conditions and existing conditio C COPYRIGHT 2018 IMC Architecture DPC
TYPICAL F (4TH SEAL & SIGNATURE:
WEST STREET
2049 WEST STREET, BROOKLYN, NY, 11223 TYPE: ONE FAMILY HOME GROSS AREA: 4,016.05 SF ALTERATION — DOB APPROVED LOCATED IN BROOKLYN, THE EXISTING HOUSE WAS ORIGINALLY A TWO FAMILY HOME WITH 1,766.39 SF. THE CLIENT REQUESTED A BULK INCREASE AND CONVERSION TO A ONE FAMILY USE. AN ADDITIONAL 2,249.66 SF WERE ADDED. THE FACADE MATERIAL WAS UPDATED TO MATCH THE ICONIC RED BRICK FOUND THROUGHOUT NEW YORK CITY. TO PROVIDE COST-SAVINGS AND AN EXPEDITED CONSTRUCTION TIME, THE BRICK WRAPS AROUND THE SIDE OF THE BUILDING BY ONLY AN APPROXIMATE OF FOURTEEN FEET. THE REMAINING EXTERIOR FACADE IS PROPOSED IN EIFS TO KEEP COST DOWN.
RENDER BY OTHERS:
RESPONSIBILITIES: SD, DD & CD
08
100' - 0" (PROPERTY LINE) 68'-7" (PROPOSED BUILDING) 11' - 5"
14' - 1 3/8"
1
13' - 3 3/4"
5'-2"
W02
NE 1
W02
2 A-013.00
NE 1
CUSTOM MILLWORK
30' - 0" (PROPERTY LINE)
16' - 11 3/8"
20' - 8 5/8" (PROPOSED BUILDING)
W9' - 0" x H5' - 0" SILL:2' - 6"
NE 1
DOWNSPOUT
1 A-302.00
1' - 11 3/8"
W04
W3' - 0" x H5' - 0" SILL:2' - 6"
1'-4" 14'-0"
7'-5 1/2"
EE 1
9'-0"
11'-3 1/2"
14'-9"
W02
W3' - 0" x H5' - 6" W3' - 0" x H5' - 6" W3' - 0" x H5' - 6" W3' - 0" x H5' - 6" SILL:5' - 6" SILL:5' - 6" SILL:5' - 6" SILL:5' - 6" 40' - 0 7/8"
W07
256 SF
25B 32"
0"
E1 0 25 34"
MASTER BEDROOM
1' - 0 1/8"
EE 1
5' - 0 7/8"
98 SF
25A 32"
3'-6 1/2"
2' - 10"
WALK-IN CL
3'-0"
E1 0
UP
W02
DOWNSPOUT
7'-11 1/2"
7 1/2" 5'-3 1/2"
103 SF
5'-0"
3'-3"
BATHROOM
4'-8 1/2"
14' - 1 3/8"
14'-0"
6'-2"
3'-4"
3'-6 1/2"
HALLWAY
8'-10"
3'-11 1/2"
3'-10"
23'-11 1/2"
1'-10"
NE 1
DOWNSPOUT
2'-0"
IB 0
10' - 2 1/4"
W3' - 0" x H3' - 0" SILL:3' - 0"
3'-11"
2'-0"
CL 5'-3 1/2"
NB 1
7'-5"
21 40" LINEN CL
22A 48" 5'-3 1/2"
3' - 6 1/2"
2' - 10"
3' - 11"
6'-6 1/2"
3' - 0 3/8"
4'-0"
NE 1
9'-5"
24 32"
W05C
W08
61 SF
23 32"
22 34"
3'-8"
11' - 0 7/8"
148 SF
23A 48"
5'-6"
BATHROOM
E1 0
2'-5"
6' - 8 1/4"
1'-0"
W03 W4' - 0" x H2' - 0" SILL:6' - 0"
7'-10"
9'-0"
W03 W4' - 0" x H2' - 0" SILL:6' - 0"
1'-1"
13'-0"
BEDROOM #2
NB 1 W4' - 4" x H5' - 0" SILL:2' - 6"
9'-0"
23B 48"
BEDROOM #1
16'-7"
W9' - 0" x H5' - 0" SILL:2' - 6"
9' - 0" 21' - 6 7/8"
2' - 8 3/4"
EE 1
11'-4 1/2"
1'-1"
2' - 4 1/4"
2'-11" 2'-0"
196 SF
3' - 1 7/8"
4' - 4"
A-304.00
W9' - 0" x H5' - 0" SILL:3' - 0"
11' - 5"
SECOND FLOOR PLAN:
W06A
DOWNSPOUT
11'-0"
W07
16' - 10 3/4"
1
A-303.00
NB 1
20'-0"
37' - 6 7/8"
14' - 4 3/4"
20' - 0"
74' - 7" (PROPOSED BUILDING)
100' - 0" (PROPERTY LINE) 68' - 7" (PROPOSED BUILDING) 14'13' - 4- 3/4" 11"
UNOCCUPIABLE AREA UNDER 5'-0" IN HEIGHT. NOT FLOOR AREA PER ZR12-10.
CHILDPROOF GUARDRAIL
15'-8 1/2"
2'-8 1/2"
LAUNDRY CHUTE
4'-9"
R17C 36"
DN
3'-9 1/2"
W01B
W01B
W01B
W3' - 0" x H4' - 0" W3' - 0" x H4' - 0" W3' - 0" x H4' - 0" W3' - 0" x H4' - 0" SILL:2' - 6" SILL:2' - 6" SILL:2' - 6" SILL:2' - 6" 40' - 0 7/8"
NE 1
DOWNSPOUT
11"
R16B 36"
R16A 36"
3'-8"
LEVEL
3'-8"
R15A 26"
E1 0
164 SF
E1 0
CL.
2'-0"
NAME
2'-11 1/2"
16'-5"
E1 0
LIGHT & AIR CALCULATIONS - 2ND FLOOR AREA
MINIMUM REQUIRED NATURAL LIGHT & AIR REQUIRED LIGHT REQUIRED AIR
PROPOSED 2ND FLOOR BEDROOM #1 196 SF 20 SF PROPOSED 2ND FLOOR MASTER BEDROOM 256 SF 26 SF 3/4" PROPOSED 2ND FLOOR BEDROOM #2 DOWNSPOUT 148 SF 14'15- 4SF
GUTTER
ATTIC FLOOR PLAN:
68' - 2 1/8" (PROPOSED BUILDING)
1
PROPOSED - ATTIC PLAN 1/4" = 1'-0"
Window Style Schedule Key Name
Light Area
Natural Air Area
5' - 10 1/8"
7' - 9 5/8"
8' - 1 1/8"
13' - 9 1/2"
7' - 8 1/2"
W05
30' - 0" (PROPERTY LINE)
STORAGE#1
5'-0"
13'-10"
18' - 2 3/8"
NE 1 E1 0
E1 0
10' - 11 1/4"
3'-1"
18 SF R14A 36 SF 36" 22 SF R14 34 SF 30" 45 SF 3' -45 4 1/8" SF R15 60 SF 30" 67 SF 10" 3'-5" 68 SF
5' - 9 7/8"
3'-1" 2'-0 1/2"
E1 54 SF 0
20' - 8 5/8" (PROPOSED BUILDING)
5'-4"
Natural Air Area
15 SF 2' - 0" 20 SF E1 0 43 SF 18 SF 36 SF 22 SF CL 23 SF 30 SF 23 SF 38 SF 45 SF 34 SF
2'-11 1/2"
R13 30"
15 SF R14B 36"20 SF
4' - 4 3/4"
11'-1 1/2"
8' - 0"
W01B
13' - 8 1/2"
61 SF
35' - 11 1/2"
3'-6 1/2"
PROPOSED NON-COMBUSTIBLE CONSTRUCTION TYPE IIB
BATHROOM
Light Area CL.
4' - 10 1/8"
W04 13' - 4 1/8" W05A BEDROOM W05A+W06 143 SF W05B W05B+W05B W05C W06 W06A 7'-9 1/2" W07 W07+W04 W07+W05C 3'-2"W07A 1'-0" 3'-2"
5' - 1 3/8"
UNOCCUPIED SPACE E1 0
E1 0
6' - 1"
2'-3 1/2"
EXISTING TYPVE VB CONSTRUCTION TO REMAIN.
E2 0
7' - 6"
5"
R12 30"
R11 30"
LEGEND:
145 SF
1' - 0"
3'-6 1/2"
98 SF
5' - 5 3/8"
DOWNSPOUT
Window Style Schedule
Key Name
1'-0"
13' - 6 5/8"
R12A 36"
CL.
E1 0
W7' - 6" x H4' - 6" SILL:2' - 6"
7'-6"
4'-1"
10'-11"
18' - 2 3/8"
A-302.00 UNOCCUPIABLE AREA UNDER 5'-0" IN HEIGHT. NOT FLOOR AREA PER ZR12-10.
STORAGE#2
W7' - 6" x H4' - 6" SILL:2' - 6"
BEDROOM
E1 0
4'-5"
DESCRIPTIONS:
2' - 0" 5'-11 1/2"
E1 0
RESERVED
2'2'- 11 - 6"7/8"
NE 1
1'-7"
R12B 36"
W06
W06
3'-0"
5'-0 1/2"
A-304.00
11' - 1 3/4"
2'-0"
E1 0
8'-11 1/2"
NE 1
11'-1"
GUTTER DOWNSPOUT
FLOOR PLAN NOTES: • SEE SCHEDULE ON RIGHT FOR THE LIGHT AND AIR CALCULATION.
1 A
5' - 7 1/4"
1
A-303.00
CL.
KEYS:
7' - 6"
W5' - 0" x H5' - 0" SILL:2' - 6"
1
20' - 0"
8' - 7 7/8"
11' - 1 3/4"
PROPOSED - 2ND FL 1/4" = 1'-0"
7' - 6"
4'-9"
1
8' - 3 3/4"
5' - 0"
14' - 1 3/8"
7' - 3 1/2"
11' - 5"
UNOCCUPIED AREA UNDER 5'-0" IN HEIGHT. NOT FLOOR AREA PER ZR12-10
10 SF 13 SF 7 SF
WINDOW TYPE
PROVIDED LIGHT AND AIR NATRUAL LIGHT NATRUAL AIR
W07+W05C W07+W04 W06A
67 SF 60 SF 45 SF
45 SF 38 SF 30 SF
TECH HUB
320 W FORDHAM RD, THE BRONX, NY, 10488 TYPE: COMMERCIAL LOT AREA: 162,200 SF DESIGN PROPOSAL
NORTHEAST BIRD’S EYE VIEW:
THIS PROPOSAL IS LOCATED IN THE BRONX. THE EXISTING SPACE WAS A VACANT ZONING LOT USED FOR STORAGE. THE LOT COULD BE AN ASSET TO THE COMMUNITY IF IT WERE A COMMERCIAL SPACE THAT WASN’T AN BARRIER BETWEEN THE RIVER AND THE BUILDINGS UPHILL. TO ACT AS A BRIDGE BY ACTING AS ECONOMIC CENTER FOR JOB CREATION AND TRANSIT HUB FOR A FERRY STATION. GIVING AN ALTERNATIVE ACCESS TO CONNECT WITH MANHATTAN AND NEW JERSEY. THE PROPOSED BUILDING IS MEANT TO TAKE ELEMENTS FROM THE SURROUNDING. AT THE SAME TIME, THE DESIGN IS MEANT TO CREATE A PERFORMATIVE ARCHITECTURE — A SENSORIAL AND EXPERIMENTAL EXPERIENCE.
NORTHWEST BIRD’S EYE VIEW: STRAINER WITH BALLAST SCREENING INSTALL CAULK WITH NEOPRENE GASKET BETWEEN DECK CLAMP AND COLLAR OF THE STRAINER. 6" MIN FLEX FLASHING TO OVERLAP UNDER THE ROOF MEMBRANE
THE ORIENTATION OF THE BUILDINGS ARE LAID OUT TO BE NONCONFORMING TO THE ORTHOGONAL ANGELS TYPICALLY FOUND IN THE “COMMISSIONERS’ PLAN OF 1811”. THIS DESIGN DIRECTION IS TAKEN FROM THE NEIGHBORHOOD’S NATURAL RIDGE LINE AND THE VALLEY’S WINDING CURVES. THIS ALLOWS A DISCONNECT FROM CONTROLLED STRUCTURE AND HIGHLIGHTS THE ORGANIC CURVES. THE DIAGONAL ANGLES, IN PLAN, ALSO DOUBLE IN ALLOWING UNOBSTRUCTED FLOW OF FLOOD WATERS. THE EXTERIOR WALLS(ANGLED) CREATE AS LITTLE FRICTIONS AS POSSIBLE THAN COMPARED TO A BUILDING THAT OBSTRUCTS THE FLOW OF THE SURGE WATER.
42" CHILD PROOF GUARDRAIL
Y-CHANNEL CLIP HSS TUBE ANCROED INTO TE CONCRETE SLAB CONCRETE PAVERS ON LEVELING PEDESTALS
GEOTEXTILE FILTER FABRIC 6" CONTINUOUS RIGID XPS INSULATION , R-30 MIN.
SEAMLESS INVERTED ROOF MEMBRANE ASSEMBLY TO ACT AS BOTH THE WATERPROOF AND VAPOR BARRIER
~2% SLOPED CONC. TOPING SLAB
ROOF MEMBRANE TO WRAP AROUND CANTILEVER SLAB 1/8" ALUMINUM PLATE SOFFIT
Z-CHANNEL - TYP 2 1/2" RIGID INSULATION, (R-12)
RESPONSIBILITIES: DD
ROOFDETAIL DETAIL OF SIXTH FLOOR TERRACE AND OFFICE SUIT: SECTION 1 3/4" = 1'-0"
DRAINAGE MAT
10
RIVER
RIVER
FERRY
E
AD PROMEN
E
ROOF TERRACE OVER FIFTH FLOOR ROOF TERRACE OVER ROOF TERRACE THIRD FLOOR OVER FIFTH FLOOR
SOLAR PANELS
ROOF TERRACE OVER THIRD FLOOR ROOF TERRACE OVER SECOND FLOOR
SOLAR PANELS
ROOF TERRACE OVER SECOND FLOOR
LAWN
RRACE ROOF TE FLOOR SECOND
ROOF TERRACE OVER THIRD FLOOR ROO ROO OVE F TERROVE F TERR A R A R FLO THIRD FLOCE THIRD CE OR OR
FERRY
AD PROMEN
ROOF TERRACE OVER THIRD FLOOR
COURTYARD
COURTYARD
R OO OV E F T E R R FLO R THIR ACE D OR
OVER
OV RRACE ROOF TE FLOOR SECOND ROOF TERRACE OVER FIFTH FLOOR
ROOF TERRACE OVER FIFTH FLOOR ROOF TERRACE OVER FOURTH FLOOR
ER
OFFICE SUIT
OFFICE SUIT
ROOF TERRACE OVER FOURTH FLOOR
R OO OV E F T E R R FLO R THIR ACE D OR
LAWN
PARKING BELOW
opy 1 SIXTH FLOOR PLAN:
PARKING BELOW
opy 1
RIVER
RIVER
PROMEN
FERRY
ADE
CAFETERIA
ADE DOUBLE HEIGHT WORKSHOP
PROMEN
FERRY
DOUBLE HEIGHT STORAGE WORKSHOP
WARMING KITCHEN WARMING KITCHEN
COURTYARD
WORKSHOP WORKSHOP LAWN
LAWN
DOUBLE HEIGHT WORKSHOP DOUBLE HEIGHT WORKSHOP
WORKSHOP
STORAGE
CAFETERIA
COURTYARD
WORKSHOP WORKSHOP WORKSHOP
SECURITY STORAGE
STORAGE
SECURITY LOBBY
LOBBY
N
PARKING BELOW
PARKING BELOW 2
FIRST FLOOR PLAN:
6TH FLOOR Copy 1 1" = 60'-0"
DURA HOME
RENDER BY OTHERS
SOLAR DECATHLON COMPETITION 2015 FABRICATED IN BROOKLYN NAVY YARD, NY GROSS AREA: 897 SF COMPLETED & LOCATED IN BERTHOUD, COLORADO PROFESSOR ALEXANDER APTEKAR & PAUL C. KING THIS PROJECT WAS SUBMITTED TO THE U.S DEPARTMENT OF ENERGY FOR THE 2015 COMPETITION YEAR. NEW YORK CITY COLLEGE OF TECHNOLOGY(NYCCT) ALONG WITH SIXTEEN COLLEGES AND UNIVERSITIES BUILT THEIR OWN SUSTAINABLE OFF-THE-GRID HOUSE. I SUPPORTED THE NYCCT TEAM IN THE FABRICATION OF THE HOUSE. THE WHOLE HOUSE WAS INSULATED IN ROCKWOOL AND THE WATERPROOFING WAS ACHIEVED WITH DORKEN DELTA FLASHING SYSTEM. HEAVY TIMBER WAS USED FOR COLUMNS, LVL BEAMS FOR GIRDERS AND WOODEN I-BEAMS FOR BEAMS. ONCE THE BUILDING WAS COMPLETED, IT WAS DISASSEMBLED AT THE STRUCTURAL SEAM AS SHOWN IN THE DIAGRAM ON THE RIGHT PAGE. THAN THE SECTION WERE SHIPPED TO IRVINE, CALIFORNIA. AFTER THE SHOWCASE IN CALIFORNIA, THE HOUSE WAS EVENTUALLY MOVED TO COLORADO FOR ITS PERMANENT INSTALLATION.
RESPONSIBILITIES: CONSTRUCTION
RAMP AND EXTERIOR CLADDING CONSTRUCTION PHASE:
PHOTO OF TEAM:
INTERIOR CONSTRUCTION PHASE:
t also to design a structure that would be easily constructed in emergency situations. Three, transportation: The shortest route from Brooklyn New York to Irvine California is a total of 2812.3 miles. Finding a suitable transportation company that will be able to transport the modules safely poses its own challenges. Along with these challenges the team will also need to design the house to be taken apart and to fit each section on each truck, while being able to maneuver alsowhile to design a structure that would easily constructed emergency shortest route fromthat Brooklyn York to Irvine California a total of 2812.3 of miles. a suitable transportation be able to transport modules safely posesthe its team own challenges. Along these and challenges thefeasib team le will also need towould designbe theable house tothe be taken apart andDURA to fit each section eachbeing truck, while beingNew able York to maneuver the research that us come up withbe solutions to pr in oblems. dbut easily; still helped maintaining its structural integrity onthese its trip from Brooklynsituations. New YorkThree, to Irvitransportation: ne California. The There are many factors need toNew be considered in the planningisand development the Finding DURA project. One the materialscompany involves that usingwill various calculations andthe comparative analyzing needs to select thewith strongest the most materials that to fit ascetics of the home. Alsoon while able to meet and California state building codes. nd the research come up solutions to pr from oblems. cted easily; whilethat still helped maintaining its structural integrity onthese its trip New Yorkintoemergency Irvi ne California. There are transportation: many factors that to beroute considered in the planning and development of the is DURA Onemiles. the materials various calculations and will comparative needssafely to select theitsstrongest and the Along most feasib le materials that would be will ablealso to fitneed the to ascetics thehouse DURA home. while meet New York and while California codes. dern and comfortable home,usbut also to with design a structure that would beBrooklyn easily constructed situations. Three, Theneed shortest from Brooklyn New York to Irvine California a totalproject. of 2812.3 Finding ainvolves suitableusing transportation company that be able toanalyzing transportthe theteam modules poses own challenges. with these challenges the team designofthe to be takenAlso apart andbeing to fit able eachto section on each truck, beingstate able building to maneuver modern and comfortable home, also to design a structure that up would easily constructed emergency situations. Three, transportation: The shortest route from Brooklyn New York to Irvine California is a total of 2812.3 miles. Finding a suitable transportation company that will be able to transport the modules safely poses its own challenges. Along with these challenges the team will also need to design the house to be taken apart and to fit each section on each truck, while being able to maneuver o deal with these obstacles and but the research that helped us come withbe solutions to these pr in oblems. ns to deal with these obstacles and the research that helped us come up with solutions to these pr oblems.
12
Structural M odul Transport & Connecti ons ons Structural M es odul es Transport & Connecti [DU RA Decathl on 2015] [DUSol RAarSol ar Decathl on 2015]
FRONT PORCH
FRONT PORCH
UP
MECHANICAL ROOM GREEN WALL
MECHANICAL ROOM
BEDROOM/OFFICE BEDROOM
By Brian Roger M ason and M argarita Salas, By BriProfessor an Roger M ason and M argarita Salas, A lexander A ptekar
BEDROOM/OFFICE
DW
Professor A lexander A ptekar N ew York C ity C ollege of Technology, Architectural D epartm ent N ew York C ity C ollege of Technology, Architectural D epartm ent
afe and stable house that would be able to be constructed and deconstructed easily; while still maintaining its structural integrity on its trip from Brooklyn New York to Irvi ne California. There are many factors that need to be considered in the planning and development of the DURA project. One the materials involves using various calculations and comparative analyzing the team needs to select the strongest and the most feasib le materials that would be able to fit the ascetics of the DURA home. Also while being able to meet New York and California state building codes.
a safe and stable house would beandable to be constructed and deconstructed easily; while maintaining its York structural on itsaretrip from Brooklyn York neNew California. There many factors that be considered the planning and development of the DURA project. One materials using various and comparative analyzing totruck, select the strongest and the most feasib le materials that would be able to fit the ascetics of the DURA home. Also while being able atructing safe house that would be able be constructed deconstructed easily; while still maintaining its structural integrity on that itsstill trip from New Irvi neintegrity California. There many factors that toNew beroute considered in Irvi the planning and development of are the is DURA One the need materials using variousincalculations and will comparative needs to select theitsstrongest and the the Along most feasib le involves materials that would be will ablealso tocalculations fitneed the to ascetics thehouse DURA home. while able to meetneeds New York and while California state codes. tly hitand the stable east coast area; the DURA teamtothat wanted to not only design a modern and comfortable home, but also to design a structure would beBrooklyn easily constructed intoemergency situations. Three, transportation: Theneed shortest fromto Brooklyn York to Irvine California a totalproject. of 2812.3 miles. Findingtoainvolves suitable transportation company that be able toanalyzing transportthe theteam modules safely poses own challenges. with these challenges the team designof the to be takenAlso apart andbeing to fitthe eachteam section on each being able building to maneuver onstructing a safe and stable house thatthe be able and deconstructed while maintaining its structural integrity onThree, its trip frombeBrooklyn New toemergency Irvi ne areistransportation: many factors that need to beroute considered incompany the planning and of the safely DURA Onemiles. theAlong materials various andhouse comparative analyzing needs to select and the Along most feasib le materials that would be will ablealso to fitneed the to ascetics thehouse DURA home. while cently hitrecently the east coast area; wanted to notthe only design ato modern and home, but also to design a structure thatstill would be easilybut constructed emergency situations. transportation: The shortest routeYork frominBrooklyn NewCalifornia. York to IrvineThere California a total of 2812.3 miles. Finding a suitable transportation that willYork be abledevelopment transportCalifornia the modules posesproject. its challenges. with these challengesusing the team will alsocalculations need to design that the tobe beable taken to apart and to fit the each section on each truck, whilethe being able tochallenges. maneuver somthat hitposter thethe east coast area; DURA team wanted tocomfortable not obstacles only design modern and comfortable home, also toinoblems. design a structure that would easily constructed situations. Three, The shortest from Brooklyn New toto Irvine is a total ofown 2812.3 Finding ainvolves suitable transportation company will transport theteam modules safely poses itsstrongest own with these challenges the team designofthe to be takenAlso apart andbeing to fit ae state to state. Our willDURA give anteam overview onwould how team plans tobe dealconstructed with these and thearesearch thateasily; helped us come up with solutions to these pr srms fromthat state to state. Ourhit poster will givecoast an overview how the teamteam plans to deal withtothese and the a that helped us come up withhome, solutionsbut to these oblems. recently the east area;aon the DURA wanted notobstacles only design modern and comfortable alsoprwhile to design a structure that would easily constructed emergency shortest route fromthat Brooklyn York to Irvine California a total of 2812.3 of miles. a suitable transportation be able to transport modules safely posesthe its team own challenges. Along these and challenges thefeasib team le will also need towould designbe theable house tothe be taken apart andDU to f hat varies from state to of state. Our poster will give an overview on the team plans toconstructed deal with these and the research that us come up withbe solutions to pr in oblems. ere assigned to the task constructing safe and stable house thathow would be able toresearch be and obstacles deconstructed easily; still helped maintaining its structural integrity onthese its trip from Brooklynsituations. New YorkThree, to Irvitransportation: ne California. The There are many factors need toNew be considered in the planningisand development the Finding DURA project. One the materialscompany involves that usingwill various calculations andthe comparative analyzing needs to select thewith strongest the most materials that to fit ascetics of the s)were thatassigned varies state tostorms state. Our on how the be team plans deal these obstacles and the research come up solutions to pr from oblems. to the task of constructing a will safe and stable house thatthe would able towanted betoconstructed and deconstructed easily; whilethat still helped maintaining its structural integrity onthese its trip New Yorkintoemergency Irvi ne California. There are transportation: many factors that to beroute considered in the planning and development of the is DURA Onemiles. the materials various calculations and will comparative needssafely to select theitsstrongest and the Along most feasib le materials that would be will ablealso to fitneed the to ascetics thehou D nspired by thefrom two major that poster recently hitgive the an eastoverview coast area; DURA team to with not only design a modern and comfortable home,usbut also to with design a structure that would beBrooklyn easily constructed situations. Three, Theneed shortest from Brooklyn New York to Irvine California a totalproject. of 2812.3 Finding ainvolves suitableusing transportation company that be able toanalyzing transportthe theteam modules poses own challenges. with these challenges the team designofthe n: Inspiredand by the twoobstacles) major storms that recently hit the east coast area; the wanted notthe only design a modern and comfortable home, also to design a structure that up would easily constructed emergency situations. Three, transportation: The shortest route from Brooklyn New York to Irvine California is a total of 2812.3 miles. Finding a suitable transportation company that will be able to transport the modules safely poses its own challenges. Along with these challenges the team will also need to design the ollbooths other that varies from state to state. Our poster willDURA give anteam overview onto how team plans to deal with these obstacles and but the research that helped us come withbe solutions to these pr in oblems. s, tollbooths and other obstacles) that varies from state to state. Our poster will give an overview on how the team plans to deal with these obstacles and the research that helped us come up with solutions to these pr oblems.
KITCHEN
INDOOR/OUTDOOR
Structural M odules Transport & Connections Structural M odul es Transport & Connecti ons ons [DU RA Sol ar Decathl onM 2015] Structural odul es Transport & Connecti
USE SOLAR PANELS URE
9' - 9"
INDOOR/OUTDOOR
[DU RA Decathl on 2015] [DUSol RAarSol ar Decathl on 2015]
BEDROOM
By Brian Roger M ason and M argarita Salas,Construction and Deconstruction
bstract
onday andcompetition. Deconstructi The Solar Decathlon is anConstructi intense nine To on task ofconstructing a safe and stable Professor A lexander A ptekar The Decathlon an intense nine day competition. To have the house upSolar and running in aistimely fashion will ssi a safe and stable tedgned easilto y,the w hitask le stiof llmconstructi aintainingngits N ew York C ity C ollege of Technology, Architectural help D epartm ent haveof the house andcomes running in a timely fashion will relieve some the stressupthat in competition. deconstructed easimly, w hi le stillthat m aintaining its end Cal ifornia.There are any factors help relieve some thewe stress thatneed comes For the team to accomplish this of task, would to in competition. wDUYork to Irvi neOCal forni There RA proj ect. neithe m a. ateri als,are usimngany factors that For theas team to accomplish this task,within we would need to construct the house quickly as possible; ideally lopmtoent RA project. nemthe m aterials,using eds selof ectthe theDU strongest andOthe ost Professor A lexander A ptekar UP construct the house quickly as possible; ideally within the first day. This requirement alsoascoincides with the door ng the sel ect the e DU RAteam hom needs e,w hilto e al so bei ngstrongest able to and the m ost Professor A day. lexander A ptekar N ew York C ity C ollege of Technology, Architectural D epartm the first This requirement also withent the door teams overall concept of the house being able to coincides be RESILIENT eructi asceti cs ofdeconstructi the DU RA hom e,Iwnspi hilered also onFIRST and on: bybeing able to FLOOR PLAN: N ew York C ity Cconstructed ollege very ofquickly Technology, Architectural D epartm ent teams overall concept of the house being able to be in emergency situations. Module des. Twteam o constructi deconstructi DU RA wSTRUCTURE antedon toand not onl y design aon:Inspired by Abstract on and Deconstructi on in emergency situations. Module constructed verythe quickly houses areConstructi quickly becoming preferred way of building coast area, DU RAslywteam w gned anted to notof onl y design re that w oulthe d be easi constructed intask The Solar Decathlon is an intense nine day competition. To tural /Transportati on team ere assi to the constructi ng aasafe and stable houses are quickly becoming houses in the construction field because thatpreferred reason. way of building C have the house up and running in a timely fashion willof the siwgn ad be structure that w oul d be y constructed inllm aintaining its oute Brookl yn New York toeasi Irvilne at oulfrom abl e to be constructed and deconstructed easily,w hile sti helprecent relieve some of the stress that comes in competition. houses in the construction tegri onon itscom trip from Brookl yn New to iforni a.There are m any factors that The super storms that hit the eastfield coastbecause area of that reason. :portati Thetyshortest route from ynIrvi New York to Irvine pany that wBrookl illYork be abl ene toCal C For the team to accomplish this task, we would need to onsidered in the planning and developm entofthe DU RA project.O ne the m aterials,using The recent as super can storms that hit the within east coast showed how someone’s home be taken away a area sui tabl eandtransportati on com pany lbe able to ith these chal lenges the team w ilthat lneeds alsowtoilsel construct the house as quickly lwcul ations com parati ve anal yzing the team ectthe strongestand the m ost B possible; ideally within Professor A lexander A ptekar how someone’s taken day. to replace those houses quickly one of away within a the Being first day.able Thisshowed requirement also coincides withhome the doorcanisbe lateri lti enges. Al ong w i th these chal l enges the team w i l l al so onalon each bei ng abl toDU RA hom e,w hile also being able to s that w oultruck, d be ablewtohi fil te the asceti cs ofethe N ew York C ity C ollegethe ofmain Technology, Architectural Dthose epartm ent Toquickly is one of A teams overall concept of the house being able be rk iforni a state bui ldi ng codes. Tw oto constructi on and red by day. for Being able to replace houses reasons the increase in to module homes. toand fitCal each secti on each truck, wstate. hileAbstract bei ngdeconstructi able to on:Inspi tri cti ons that vari eson from state illustrating modules constructed very quickly in emergency situations. Module orstorm s thatrecently hitthe eastcoastarea,the DU RA team w anted to notFloor onlyplan design a Constructi on and Deconstruction the mainthe reasons forway the increase inamodule To remedy this problem structural team created bolt homes. other travel restri cti ons that vari es from state to state. lndwcom ithfortabl thesee hom obstacl es and the research Abstract houses are quickly becoming the preferred of building e,butalso to design a structure thatw ould be easily constructed in Floor plan illustrating modules onday andcompetition. Deconstru The Solar Decathlon intense nine /Transportati onobstacl team s wesere gned to tasktoof constructi ng a safe and stable remedy this problem the structural team created a bolt is anConstructi connection that will be able toreason. allow a small crew houses in the system construction field because of that mythese ans toThree, deal w ith these andassi theB research sipl tuati ons. on: The shortest route from Brookl yn the New York Irvi ne oStructural probl emtransportati s. recenteach superconnection storms thatquickly hitsystem the east coast area The Decathlon an intense nine day the house upSolar and running in aistimely fashion will The /Transportati on team w ere gned to a safe and stable ith s athat total of mStructural ilabl es.Fi ng a sui ondeconstructed com spany thatassi w illbe able l to that will be able tohave allow a small crew toThe attach module and safely. As shown on the w 2812. oul d3to be endi to be constructed and easi y,the w hitask le stiof llmconstructi aintainingngits ise soluti ons these probl emtabl s.e transportati showed how someone’s home can be taken away within a e m odules safely poses its ow n challenges.Along w ith these challenges the team w illalso have the house andcomes running in a timely helpAsrelieve of the stressupthat in competitio toreplace attach each module quickly and safely. shownsome on the house that w oul d be abl e to be constructed and deconstructed easi l y, w hi l e sti l l m ai ntai ni ng i ts diagrams below, by placing the connections at certain ral i ntegri ty on i ts tri p from Brookl yn New York to I rvi ne Cal i forni a. There are m any factors that day. Being able to those houses quickly is one of sign the house to be taken apartand to fiteach section on each truck,w hile being able to help relieve some thewe stress thatneed comes For theatteam to accomplish this of task, would to below, by placing the connections certain structural integri ty on its tri p from Brookl yn New York to Irvi neOCal forni There the main reasonsdiagrams for the increase module homes. To areas it allows the house toinmaintain its structural stability, orough be consi deredtolilnbooths, the pl anni ngtravel and devel ent of RAtoproj ect. neithe m a. ateri als,are usimngany factors that overpasses, and other restri ctiopm ons that vari esthe fromDU state state. Abstract Floor plan illustrating modules Constructi on andthe Deconstructi onquickly remedy this problem thebe team ato bolt For theas team to accomplish task,within we w construct house as possible;this ideally w illcal givecul anneed overvi ew on the team plans deal wanni ithng these obstacl esneeds andopm theto research areas itstructural allows the created house maintain its structural stability, toand behow consi dered intothe pl ng and devel ent DU RA project. Othe nemthe m aterials,using while being able to constructed quickly. us ations com parati ve anal yzi the team selof ectthe the strongest and ost The Solar Decathlon is an intense nine day competition. To D The Structural /Transportati on team s w ere assi gned to the task of constructi ng a safe and stabl e connection system that will be able to allow a small crew thathelped us com e up w ith solutions to these problem s. the quickly as possible the first day.inThis requirement alsoascoincides with the do whilequickly beingand able toAsbeshown constructed quickly. vari cal ons and com parati ved be anal ngDU the needs sel ect the and the ible m ateri alsous that w cul oulati d be abl e tohouse fitthe asceti csabl ofeyzi the RAteam homand e,deconstructed w hilto e al so bei ng tollm ai have the house up and running aconstruct timely fashion willhouse to attach each module safely. on the that w oul to be constructed easi ly,strongest wabl hileesti ntaini ng im ts ost A first day. This requirement also help relieve some of the stress thatthe comes in competition. teams overall concept of the house being able to coincid be diagrams below, by placing the connections at certain structural integri ty on its tri p fromasceti Brookl yn New YorkDU to IRA rvinehom Cal iforni a. There are mbei anyng factors that feasi bl e m ateri al s that w oul d be abl e to fi t the cs of the e, w hi l e al so abl e to York and Cal i forni a state bui l di ng codes. Tw o constructi on and deconstructi on: I nspi red by Mew ateri al use. Selecting the right materials that For the team to constructed accomplish this task, wequickly would need to areas it allows the house to maintain its structural stability, need to consibui dered inng thecodes. planningTw opm entofon DU RAdeconstructi project.O ne the on: als,usi ng by teams overall concept of the house being very in emergency situations. Modu moneet New York and a be state ldi odevel constructi Inspi red ouilding m ajorstorm s that recentl yCal higiven tiforni the east coast area, the DU RAandteam w anted the toand not onl y design am ateri any house. Selecting the right materials construct the house as quickly as possible; ideally within acting the house at any time while being able to be constructed quickly. vari ous cal culations andthat com parative analyzing the team needs to selectthe strongestand the m ost constructed very quickly in emergency situ houses are quickly becoming the preferred way of build the tw o m aj or storm s that recentl y hi t the east coast area, the DU RA team w anted to not onl y desi gn a ern and com fortabl e hom e, but al so to desi gn a structure that w oul d be easi l y constructed i n the first day. This requirement also coincides with the door feasibl aterigiven als thatwtime ould be able to fitthe ascetics ofthe DU RA hom e,w hile also being able to that would bebe. acting on Mthe house ate many ucture would To select the right ateri al teams overall concept of the being able to be are quickly becoming houses in house the houses construction field because of the thatpreferred reason. m eet New York andshortest Cal iforni adesi state bui ng codes. Twthat o constructi on and deconstructi on:Inspirediby mteam odern andwould com fortabl ehouse. hom e, but al so to gn aldistructure w oul d be y constructed n rgency tuati ons.make Three, transportati on: The route from Brookl yn New York toeasi Irvilne design is si athe major component tothe building Selecting the right materials that he finished structure be.any To select the right o help correct constructed very quickly in emergency situations. Module the tw o acting m ajorstorm s that recentl y higiven tthe east coastarea,the DU RA team w anted to notonly design a houses in the construction The recent super storms that hit the eastfield coastbecause area o to withstand that would beng on the at The any emmany ergency si ons. Three, on: shortest route yn New York to Irvine orni aapplied is a(people, total 2812. 3tuati mteam iles. Fi ndi atransportati sui tabl ehouse transportati ontime com panyfrom thatwBrookl illbe abl e to houses are quickly becoming the preferred way of building oeetermining be toofforces/loads help the make the loads furniture, heavy m structure odern andcorrect com fortabl e hom e,but so to design a structure thatw ould be easi Dly constructed in how safe and stable the finished would be. To select thealright The recent super storms that hit the within east c showed how someone’s home can be taken away Cal i forni a i s a total of 2812. 3 m i l es. Fi ndi ng a sui tabl e transportati on com pany that w i l l be abl e to houses in the construction field because of that reason. ort the m odul es safel y poses i ts ow n chal l enges. Al ong w i th these chal l enges the team w i l l al so em ergency tuati ons.make Three, transportati loads), Liveconditions loadshave (people, furniture, heavy ead some of the need many different calculations tothat be applied toto help si the team the correct on:The shortestroute from Brooklyn New York to Irvine The recent superday. storms that hit the east coasthow areathose showed someone’s canisbe take Being able to replace houseshome quickly one of Framing ofeach the Cal a ito s a(people, ofn 2812. 3 ml ion les. Findi ngong amodules sui tabl eastransportati on pany thatwteam illbe abl ADAPTABLE transport the odul es safel yiforni poses itotal tstneed ow chal enges. Al w ith these lcom enges the w ielltoalso to desi gn the house tomof be taken apart and fi each secti on truck, wa whole hile chal bei ng abl e to Variables such as gravity loads (dead loads), Live loads furniture, heavy uake, etc.) are some the conditions that to with these calculations the team showed how someone’s home can be taken away within a transport the mofodul esconditions safely poses itsneed ow n chal lenges. Alongofwthe ith modules these chal enges the team w illalso STRUCTURE ADAPTABLE day. for Being to replace thosehomes. housesTo qu Framing aslw a whole the main reasons theisable increase in module , etc.), lateral loads (wind, earthquake, etc.) are some the that to need to desi gn the house to be taken apart and to fi t each secti on on each truck, hi l e bei ng abl e to ver through overpasses, tol l booths, and other travel restri cti ons that vari es from state to state. day. Being able to replace those houses quickly one of Framing of the modules as a whole ADAPTABLE s. for Toclasses. helpmaking us We with these calculations the Floor plan illustrating modules erial a need basic to desi gnteam the house to bethe taken apartand to fiteach section on each truck,w hile being able to ed when theconstructed selections. To help us with these calculations team the main reasons increase remedy this problem the structural team createdinamodu bolt STRUCTURE STRUCTURE the main reasons for the increase in module homes. To for the aneuver through overpasses, tol lbooths, and other restri cties ons that es from tostate. state. oster wand ilmlwith gi ve an ew on how the team plans toconstructed deal wlbooths, ithatravel these obstacl and research m constructed aneuver through overpasses, tol and other travel restri ctithe onsvari that vari es fromstate state to Floor plan illustrating modules ngth We aWe basic Floor plan illustrating modules to what wematerial learned in classes. our strength and material classes. basic sck along theovervi equations needed for remedy this problem the structural team created a problem bolt remedy this structural team c O ur poster w i l l gi ve an overvi ew on how the team pl ans to deal w i th these obstacl es and the research connection system that will be ablethe to allow a small crew O ur poster w i l l gi ve an overvi ew on how the team pl ans to deal w i th these obstacl es and the research that hel ped us com e up w i th sol uti ons to these probl em s. t thatto incorporates manywith different along with the equations needed for erent variables along thevariables equations needed for ven us by thethe design team we connection system that will be able to allow a small crew that helped us com e up w ith solutions to these problem s. connection system that will be able to on allot an informed decision. Using the dimensions given to us us by the design team weuti to attach each module quickly and safely. As shown that hel ped com e up w i th sol ons to these probl em s. to attach each module quickly and safely. As shown on the dimensions given to us by the design team we s would best and andwould react best and extremes and fferent loadreact combinations to seeextremes what materials to attach eachthe module quickly at and safely. A below, by placing connections certain diagrams below,diagrams by placing the connections at certain conditions. Below awould sample spreadsheet the basic step-by-step what materials react bestshowing and extremes and wing the basicisstep-by-step areas it allows the houseittoallows maintain its structural stability, diagrams below, by placing the connection areas the house to maintain its structural stabil seadsheet that guided showing us on choosing the right material for the DURA home. the basic step-by-step for the DURA home. while being able to be constructed quickly. areas it allows the house to maintain its st while being able to be constructed quickly. right material for the DURA home. M aterial while being able to be constructed quickly Connection of roof system Structural M design is aal major component to building any house. Selecting the right materials that ateri
By Brian Roger M ason and M argarita Salas, By Brian Roger M ason and M argarita Salas, Structural M odules Transport & Connections [DU RA Solar Decathlon 2015]
The Structural/Transportation teams were assigned to the task of constructing a safe and stable house that would be able to be constructed and deconstructed easily; while still maintaining its structural integrity on its trip from Brooklyn New York to Irvi ne California. There are many factors that need to be considered in the planning and development of the DURA project. One the materials involves using various calculations and comparative analyzing the team needs to select the strongest and the most feasib le materials that would be able to fit the ascetics of the DURA home. Also while being able to meet New York and California state building codes. The Structural/Transportation teamsInspired were assigned to the taskstorms of constructing a safe house thatthe would be able be constructed and deconstructed while still maintaining its structural on that its trip frombeBrooklyn New Yorkintoemergency Irvi ne California. There are transportation: many factors that to beroute considered in the planning and development of the is DURA Onemiles. the materials various calculations and will comparative needssafely to select theitsstrongest and the Along most feasib le materials that would be will ablealso to fitneed the to ascetics thehouse DURA home. while meet New York and while California codes. Two construction and deconstruction: by the two major that recently hitand the stable east coast area; DURA teamtowanted to not only design a modern easily; and comfortable home, but also to designintegrity a structure would easily constructed situations. Three, Theneed shortest from Brooklyn New York to Irvine California a totalproject. of 2812.3 Finding ainvolves suitableusing transportation company that be able toanalyzing transportthe theteam modules poses own challenges. with these challenges the team designofthe to be takenAlso apart andbeing to fit able eachto section on each truck, beingstate able building to maneuver Two construction and deconstruction: Inspiredand by the twoobstacles) major storms that recently hit the east coast area; the wanted notthe only design a modern and comfortable home, also to design a structure that up would easily constructed emergency situations. Three, transportation: The shortest route from Brooklyn New York to Irvine California is a total of 2812.3 miles. Finding a suitable transportation company that will be able to transport the modules safely poses its own challenges. Along with these challenges the team will also need to design the house to be taken apart and to fit each section on each truck, while being able to maneuver through travel restrictions (overpasses, tollbooths other that varies from state to state. Our poster willDURA give anteam overview onto how team plans to deal with these obstacles and but the research that helped us come withbe solutions to these pr in oblems. through travel restrictions (overpasses, tollbooths and other obstacles) that varies from state to state. Our poster will give an overview on how the team plans to deal with these obstacles and the research that helped us come up with solutions to these pr oblems.
HOUSE MODULES STRUCTURE MODULES
MODULES
By Brian Roger M ason and M argarita Salas,
will be able to withstand many would be acting on the house at any given time M forces/loads ateri al that the ural design is a major component to building any house. Selecting right materials that is vital in UNITS: determining how safe and stable the finished structure would be. To select the right STRUCTURE OF MODULAR Structural is a major component tocalculations building any house. Selecting the e able to withstanddesign many forces/loads thatdifferent would be actinghave ontothe house any timematerials materials many be applied toat help thegiven teamright make the correct that decisions. Variables such as gravity (dead loads furniture, will be able withstand many forces/loads that loads would beloads), acting on the(people, house at anyheavy given time in determining howtosafe and stable the finished structure would be. ToLive select the right equipment, lateral loads earthquake, etc.) arewould ofbe. the To conditions to is vital in determining safe and stable the finished structure selectthat theneed right ials many different calculationshow have to etc.), be applied to (wind, help the team make some the correct
ASSEMBLED ASSEMBLED
ASSEMBL
Connection of roof system
Connection of roof system