PLAYA VISTA
BY THE NUMBERS:
3,000 2,800 200 $2,247 5,946 $120 $137.7 130,000
construction workers are in Playa Vista on any given day.
housing units are under construction or about to be built.
newly built Playa Vista homes sold last year (some even before completion) at prices ranging from the $900,000s to about $2.5 million. per month rents a 1-bedroom, 675-square-foot apartment in Playa Vista, according to a recent listing.
homes, condos or apartments will house about 13,000 people when Playa Vista is completed.
million is the amount Google spent in December to purchase 12 acres of vacant land next to the former Spruce Goose hanger, which Google is expected to lease. The combined capacity of 1.2 million square feet of office space could house as many as 6,000 workers. million was the purchase price for 2 empty 6-story buildings built in 2009 east of the Spruce Goose hanger. Buyer Clarion Partners has put $8 million into remodeling the buildings in a successful bid to attract creative industry tenants.
square feet of space in The Collective at Playa Vista, a low-density creative office complex being built to the south and east of Playa Vista Central Park, was leased by Yahoo in January. The move is expected to bring in at least 400 workers to Playa Vista.
220,000
square feet of shops and restaurants, more than 33,000 square feet of office space and 420 apartments — a total of 612,000 square feet of development — are slated for the $260-million, 11-acre Runway at Playa Vista development.
50,000 1,350 47,000 36,000 8 8
cubic yards of concrete and roughly 20,000 tons of steel are being used by about 370 workers each day to build Runway at Playa Vista.
parking spaces in a 7-level parking structure will serve Runway shops and offices. square feet is the size of the new 9-screen Cinemark XD movie theater that on March 12 became the first Runway business to open. square feet is the size of the new Whole Foods Market expected to open as early as May at Runway.
restaurants have already signed Runway leases: Urban Plates (expected to open April/May), N’Ice Cream (April/May), Panini Café (May/June), 800 Degrees Pizza (May/June), Sol Cocina (summer), LYFE Kitchen (summer), Hopdoddy Burger Bar (August), Starbucks (TBD). other businesses have already announced Runway leases: CVS Pharmacy (March), Chase and Wells Fargo bank branches (May), Varnish Lab (May/June), YogaWorks (summer), Studio MDR (summer), ROC (summer), 18|8 Fine Men’s Salon (summer).